Elia Group SA/NV (ELI) Earnings Call Transcript & Summary
July 28, 2021
Earnings Call Speaker Segments
Marleen Vanhecke
executiveGood afternoon and thank you for joining us for this live-streamed event. Today, we will be giving you an overview of the Elia Group's Half Year Results, and for this, we are joined by Elia Group's CFO, Catherine Vandenborre; and the group's CEO, Chris Peeters. Welcome to you both. The agenda for today is as follows: first, we will give you an overview of the highlights. We will talk with Chris Peeters about the Fit for 55 legislative package from the European Commission. We will also discuss some of our newest publications, for example, we recently published a paper about a new market design. Catherine Vandenborre will then take us through the financials. And finally, we will present the group's outlook for the coming 6 months. Before we start, I would like to point out the disclaimer for today's presentation. As mentioned on screen now, you must read the disclaimer before we can continue, and I suppose you have all done it by now. So let's immediately kick off with the presentation. Although we will be focusing on the past 6 months, it's difficult to ignore very recent events in Belgium. In mid-July, Wallonia, in particular, was hit hard by floods. In addition to the human suffering, an immense amount of material damage occurred, and Elia was also affected. Let's have a look at some images from our substation in Pepinster, taken on Wednesday, 14th of July. The substation is next to the River Vesdre and was flooded. Shortly after these images were taken, our teams [ had to -- becoming ] too dangerous. Chris, these are shocking images, how did Elia handle this crisis?
Chris Peeters
executiveWell, Elia was warned before that we would have heavy rainfall in the region but we were not warned for the fact that it could have been those floods that we have seen. We had our teams onsite that immediately started to work to save the sites that could have been impacted. So we had 7 substations that were under threat and they did everything to keep it online. As an example, for instance, the substation in Spa, thanks to the support of the fire brigade, we could with heavy [ pumps ], clear that site and make sure that it was not impacted. But finally, we had 2 sites that were really heavily impacted. The ones that you have seen in Pepinster and another one in Rochefort, those ones we had for safety reasons switched off, of course to avoid further damages and also for safety reasons. And we did that in coordination with RESA, the distribution grid operator to minimize the impact on the region and to re-dispatch as much as possible the electricity supply. To just give the impact of that, the overall capacity of those 2 substations altogether is 100 megawatt. In the end, we only had to switch off 6 megawatt in one, and 7 megawatt in the other one, and all the rest could be refitted by other means. We also started right away with the emergency procedure, which means that our crisis center in Brussels is then immediately manned and that they monitor the situation, do all the calculations in a similar situation in Lambert to make sure that we are prepared for any event that could still happen later on the day. Luckily it didn't happen and as of the next day, we saw that the water levels were going down again. But I would like to take the opportunity as well now to thank our teams because many people came out of holidays to support us, to make this happen, and as well, many of them now have shown their solidarity to the people in the region and they are now volunteered to support it. Elia as well has already given a grant of EUR 10,000 to the Red Cross to make sure that we can support the recovery of the situation.
Marleen Vanhecke
executiveYes. As Chris just mentioned, the substation in Pepinster was most impacted by the floods. Here, you can see a picture of the station taken from a distance during the floods and the next picture shows us what the station looked like when it was safe for our teams to return to the site. You can imagine the workload required to get us all up and running. Chris, how are the reparation works progressing?
Chris Peeters
executiveWell, our people started right away with [indiscernible] worked in close collaboration to make sure that we could bring both stations back online. The substation in Rochefort was back online in less than 24 hours, which is an amazing impact that we could have there. And so as well that we could re-feed as well the people that support all the activity that's happening now in recovery. On the other hand, Pepinster, as you have seen on the pictures is much more damaged over there. It probably will take until the end of the month of August before can be back online. Meanwhile, we work together with the people in distribution to ensure that we have minimum impact on the supply of energy.
Marleen Vanhecke
executiveYes. We have mainly discussed the operational impact of the flooding but what about the financial impact, Catherine?
Catherine Vandenborre
executiveYes. And the operating situation was indeed very complicated and thousands of people were very hardly affected, but nevertheless, the serious damage to all electrical installation happened to 2 substations for which repair work has been started. And we believe that the impact on net profits will remain limited because of damages we suffered, and which are honestly minor compared to others, are covered by our insurance policies and the regulatory framework.
Marleen Vanhecke
executiveOkay. That's all the news we have about the floods in Belgium. Thank you, Catherine and Chris. We still continue to discuss other events, which are very much still current. 2 weeks ago, the European Commission adopted the Fit for 55 package, its largest-ever legislative package, related to the pursuit of climate goals. The package aims to reach the goal of cutting CO2 emissions by 55% by 2030 and put the continent on track to hit net-zero by 2050. Chris, what is the impact of this new legislative package on Elia Group?
Chris Peeters
executiveWell, Marleen, as you can imagine, it's an opportunity for Elia Group, and we welcome this package very much because it creates a clear framework going forward. European Commission wants to move from 32% of renewables towards 40% of renewables towards the overall energy supply, and this is an important increase. And we, as Elia Group are fully committed to ensure that we deliver the infrastructure to make sure that this integration can happen. On top of that, it will mean as well, an acceleration of the electrification of certain sectors like mobility and heat, and there as well, there is an opportunity for us to accelerate in terms of digitalization. Not only the European Commission has made their targets in Fit 55, also Germany has made an acceleration. They now want to be net-zero by 2045 and that means as well that there, we will see an increase in acceleration in the long run in our investment program, likely more offshore zones that will be developed to ensure that they can deliver on that target. And finally, Elia Group wants to continue to contribute to the debate or de-carbonizing society. And therefore, we issued a paper Fit for 55, which you can find on our website and which gives indications about all the things that you have to take into account if you want to deliver on a society, which is going for net-zero.
Marleen Vanhecke
executiveAs Chris just said, Elia Group is fully committed on delivering transmission infrastructure. In the press release that we published this morning, we stated that the company is well on track in its CapEx program. Catherine, without going too much into details yet, how has this impacted the first half year?
Catherine Vandenborre
executiveYes. So ETB and 50Hertz have invested so far, EUR 386.5 million to build the necessary infrastructure, to integrate low-carbon generation, and flexibility resources, and to regulate. Chris will work you through the key CapEx projects a little bit later. In addition, with a reliability level of 99.999%, we provide society with a robust power grid that is so important for social-economic prosperity. And these make us one of the most reliable grids in Europe. In terms of financial result, the adjusted net profit of Elia Group share increased by 0.6% to EUR 124.9 million compared to the first half of 2020. This increase was driven by the realization of our investment plan and the strong performance of Nemo Link. It was offset by the lower result of 50Hertz due to higher operational cost and I will give more details about all this later, Marleen.
Marleen Vanhecke
executiveOkay. Thank you, Catherine, for these first figures. Before we dig deeper into the financial results, we would like to take a moment to discuss 2 of our most recent reports. In mid-June, the Elia Group published its paper on a Consumer-Centric Market Design. The advent of electric cars and heat pumps will lead to consumers interacting differently with the grid. Towards a Consumer-Centric and Sustainable Electricity System describes what needs to be done so that consumer can better gear their consumption to the needs of the power grid. Let us have a closer look at what this newest official paper is all about. [Presentation]
Marleen Vanhecke
executiveApart from industrial companies, consumers are not directly linked to the high-voltage grids of Elia Group. So Chris, why are we interested in consumer services?
Chris Peeters
executiveWell, Marleen, the paradigm shift that we see happening in the sector is making the case for consumer-centric surfaces more and more obvious and more and more attractive. So what you see in terms of paradigm shift is the following: we come from a system where suppliers and large industrials are delivering the flexibility of the system. So we have a change in demand, which is actually happening when it happens because there are little signals to change at this point of time. And we see thermal plants and large industrial players that provide flexibility for the system. Now if you see what's happening in the energy transition, you see that we're moving to a system where there is more electrification at the consumer side, also in the lower voltage levels, and meanwhile, we are replacing those thermal plants with more and more intermittent renewables. And therefore, of course, those consumers with that half flexibility can adjust their behavior towards the availability of that system. This is not something which is new to Elia. We launched already a paper on this 2.5 years ago where we, at that moment of time, introduced the 3 building blocks of consumer-centric system. The first one was around a real-time communication layer for which we then launched the Internet of Energy and together with 65 other companies, experimented in the way how we could, with that communication, ensure that flexibility was better managed. This paper now is about 2 other dimensions, which are about upgrading the market design. So allowing consumers to directly interact with the wholesale market and exchange blocks of energy and get those price signals to optimize their position. And so we will develop a number of tools so that people can use those tools to make that happen for themself. What we will do from now is together with the sector, but also the sectors that are electrifying will organize until the end of the year, a number of workshops to go into the details on how the system will work. And on top of that, we will also have a hackathon in the mid of October, where together with everybody who is interested, we will develop a number of use-cases that will allow that we showcase how such a good consumer-centric system will work in the future.
Marleen Vanhecke
executiveAll nice examples of co-creation. Besides our report on consumer centricity, the end of June, Elia also published its adequacy and flexibility study for Belgium. As provided by the Belgium Electricity Act, Elia is required to calculate every 2 years, Belgium's adequacy and flexibility needs for the coming decade. To maintain security of supplies, special attention has been paid to the impact of the nuclear exit and the changes brought about by the European Green Deal. The study contains 3 key messages. And Chris, could you give a quicker explanation on the 3 key messages that we see now on screen?
Chris Peeters
executiveYes, Marleen. It was a long-awaited report this time. It's the fourth report in the row that we have on this topic but obviously, we are now at the -- very close to the decommissioning of the nuclear capacity as is foreseen by the Belgian law on that. And so everybody was of course, interested in what our report would say about that impact. You see here on the page, what is going to happen between now and '25 and you see that we will decommission 6 gigawatts of nuclear capacity. And all report confirms that you need to have replacement capacity in the order of 3.6 gigawatts, which is in line with what we have stated in the previous reports. Similar to those previous reports as well, we have analyzed that those capacities that are needed will not come by themselves. So that you will need a supporting mechanism to make that happen. That was already in the previous reports, therefore, the former government already started with the process with European Commission to ensure that a capacity remuneration mechanism could be put in place. And we expect an answer from Europe in the coming weeks about this mechanism. And if this one will be positive, there will be an auction in the mid of October to provide for that replacement capacity. New in this report is the fact that we not only look at a nuclear exit in Belgium, we also look beyond that. You have seen before that Europe is looking at the net-zero society, Belgium will as well have to look at the net-zero society going forward. And one of the obvious things, of course, is that Belgium will be short in renewable energy as we are a dense country in terms of energy demand. We have industries that have a high demand in electricity as well and we have a limited potential in terms of renewable energy. And therefore, we will have to make alliances with other countries. A good example of that is the hybrid interconnector that we plan to do with Denmark on which we have made an announcement earlier this year already.
Marleen Vanhecke
executiveOkay. Thank you, Chris, for explaining our recent studies. Let's now focus on the half year results, and we'll start with the CapEx delivery. What milestones, Chris, have been achieved?
Chris Peeters
executiveWell, in terms of total investments, so far, we have delivered on EUR 387 million for the first half of the year of which EUR 165 million were in Belgium and EUR 222 million were in Germany. Important investments that we have done is in the offshore region Ostwind 2 in Germany, where we laid the first sections of the offshore cable and also where we laid successfully the onshore cable. We have delivered and commissioned a phase shifter in the south of Belgium at the French border, which will be important to ensure the security of supply going forward. And we have, both in Germany and in Belgium, done important reinforcements works of the backbone. In Belgium, that means that we have replaced certain lines by lines with more capacity so that we can transport more capacity over the grid. We have done similar projects in Germany, but on top of that, in Germany as well, we have reinforced the grid around Berlin, that we have a safer supply in Berlin. And then finally as well, we have contracted the converter stations for SuedOstLink, which is the largest investment Elia ever has done. We already had contracted in the cable works -- 540 kilometers of cable works that we have jointly with TenneT to deliver on that. But this is of course an important signal that we are on track with this project and that we will deliver it on time on budget as planned in the plans that we have made public.
Marleen Vanhecke
executiveYes, and the 2 converter stations were awarded to Siemens. Thank you, Chris, for this update. Earlier in this presentation, we witnessed how climate change could affect all of us on our Capital Markets Day in April. Elia Group provided you with a deep dive on our targets with regard to sustainability. And we introduced the ACT NOW programme. Catherine, could you provide an update on the realization of these targets?
Catherine Vandenborre
executiveSo first and as mentioned by Chris, our business strategy embraces sustainability and supports many dimensions of the Green Deal. And as an international TSO, we believe we are in a unique position to integrate renewables into the system and as such contribute to the decarbonization of the power sector. With the execution of the investment plan and the adequate market design in system operations, we can have the most impact in terms of climate actions. On our second dimension, we have increased the number of herbicide-free substations from 8 to 31 for Elia, and 50Hertz is on track to be fully banning herbicides by 2022. In our third dimension, Health and Safety, we made progress on the implementation of the safety program for works undertaken by our contractors. Some of them were from safety audits allowing to identify which behaviors need to be improved and what actions still need to be taken to fully anchor our safety in the processes and operations, thus minimizing risk situations. Also, we published a Diversity, Equity & Inclusion Charter outline the management team's commitment to further embedding diversity, equity, and inclusion across the organization. And in this connection, a group-wide diversity and inclusion awareness campaign was launched that involved interactive discussion sessions that focus on how diversity can be fostered and celebrated in our day-to-day activities. ETB's management has also committed some long-term KPIs related to diversity and inclusion. And finally, we're also back on the road since COVID measures have been eased, we are resuming in-person dialogues to engage in discussion about the evolution of the grids.
Marleen Vanhecke
executiveThank you, Catherine, for this update on our sustainability. Our activities span several countries and different regulations. Today, Elia Group is active under 3 different regulatory frameworks. Nemo Link is fixed until 2044 for both Belgium and Germany. A new period will start in 2024 in about 3 years from now. Chris, have you had any discussions with the respective regulators on the framework so far?
Chris Peeters
executiveWell, yes, Marleen. So what you as well could have witnessed a few weeks ago in the German press BNetzA, the German regulator made a first proposal for the RoE for the next regulatory period. And that was proposed at 4.59% pre-tax and 3.74% post-tax RoE for that period. BNetzA made very clear that this was a minimum value and it was based on the calculation method that they used in the past. There will, of course, be still quite some discussion that will happen. We are, as Elia and 50Hertz, we are preparing an argumentation together with some other grid operators that we will have to submit by the 25th of August. Then there will be a public hearing about this proposal. And then we expect that we will have a final view on that by October. At the Belgium side, we are preparing now for the discussions with the Belgian regulator CREG that will start as of early 2022. And we will of course report as soon as we have more news on that.
Marleen Vanhecke
executiveThank you for the update on the frameworks. Catherine already provided us with a few key figures. I assume, Catherine, you have many more to show us, so let's start by looking at the group figures.
Catherine Vandenborre
executiveThank you, Marleen. So first, Elia Group's revenues amounts to EUR 1.3 billion. This represent an 11.5% increase compared with the same values last year. This increase was driven by higher revenues in Belgium, which were up by EUR 63.7 million and higher revenues in Germany, which were up by EUR 89.7 million. It was partly offset by lower revenues for Elia Grid International, which were down by EUR 2.3 million driven by the impact of the COVID-19 on the international consulting business. The higher revenue in Belgium was due to a higher regulated profit and increase in costs that are all passed through into revenues under the cost precision we have. We'll go into more detail on the key drivers when presenting the Belgian segment. In Germany, revenue was increased due to the higher energy revenue which are also passed through and a higher investment remuneration due to the asset growth. The EBIT decreased by 7% compared with last year amounting to EUR 265.3 million. This is the result of a slightly lower EBIT in Belgium, which decreased by EUR 3.1 million and a lower EBIT in Germany, which was EUR 26.1 million lower. This was partially offset by a higher contribution from associates of EUR 9.7 million. In Belgium, the lower EBIT in 2021 was driven by lower financial costs, which are passed through. The lower costs were due to the refinancing of a shareholder loan in 2020 and better financial conditions and one-off costs for the unwinding of an interest rate swap. In Germany, the lower EBIT was the result of increasing staff and IT costs and also a peak in the maintenance cycle. The associates contributed for approximately 6% of group's EBIT reflecting the strong operational and financial performance of Nemo Link over the first half of the year. Elia Group's adjusted net profit was down by 1.6% reaching EUR 150.5 million. Germany contributed for approximately 50% to result with lower adjusted net profit due to higher operation cost, and this was partially compensated by the very strong performance of Nemo Link contributing for 10% to the result and a higher result in Belgium with a relative contribution slightly above 40%. Let us now turn to the net debt of Elia Group. At the end of June, we carried a net debt of around EUR 5.8 billion, which represented a decrease of 22% compared with the end of 2020. This decrease is entirely attributable to Germany. At the end of last year, we saw a big drop in the EEG cash balance. This was due to a very high renewable electricity increase combined with low electricity prices and lower consumption volumes. In order to finance this EEG deficit, Eurogrid contracted in 2020 several facilities for a total amount of EUR 700 million. Today, we have received 2 federal contributions, which amounts to hopefully EUR 1.6 billion to settle the EEG deficits and allowed us to pay back all the temporary revolving credit facilities drawn at the end of last year. As we mentioned earlier, the group invested EUR 386.5 million in infrastructure. This investment we mainly finance by cash flow from all operating activities. Furthermore, Eurogrid took advantage of favorable market conditions to issue a EUR 500 million Eurobonds securing part of the liquidity for the 50Hertz upcoming investment program. Following this issuance, the average cost of debts of Elia Group reduced by 27 basis points to 1.62%. This is largely to the benefit of society as the cost of debts are mainly passed through. Elia Group only has fixed-rate debts outstanding. Elia Group's rating remains unchanged at BBB+ with a stable outlook by S&P.
Marleen Vanhecke
executiveYes. These were the results for Elia Group. Let's zoom in now on Belgium. We are now in the second year of the current regulatory period in Belgium. Catherine, is it fair to say that Belgium is performing as expected?
Catherine Vandenborre
executiveIndeed, Marleen. Belgium is performing in line with our guidance, and let me take you through our key figures. Our revenues in Belgium increased by 13.5% totaling EUR 534.8 million. The revenues were impacted by a higher aggregated net profit, also higher depreciations linked to the growing asset base and higher costs from ancillary services. The latter were driven by the energy mix reflecting a high nuclear baseload and higher wind capacity during the first half of 2021. This was offset by lower financial cost and all those items we passed through into revenue. The adjusted net profit came in at EUR 62.1 million up by 1%. Now what are the key drivers of these increase. First, we have a higher fair remuneration up by EUR 2.9 million to EUR 52.2 million. And this was driven by both an increase in the regulatory asset base and consequently higher equity. Second, the contribution from incentives increased slightly reaching EUR 10.4 million. This increase was primarily driven by the incentives linked to the interconnection capacity and to the availability of the grid and was partly offset by a lower performance on data quality and balancing. Finally, the results was positively impacted by lower damages to electrical installations at the end of June compared with prior period. Now those positive elements were offset by lower capitalized borrowing costs due to a lower average cost of debt and the commissioning of major project in the second half of 2020.
Marleen Vanhecke
executiveOkay. Thank you, Catherine. You mentioned earlier in this presentation that the execution of our investment program is well on track in Belgium. Could you provide us with some insights into the financial position of ETB?
Catherine Vandenborre
executiveI think ETB continues to have a solid capital structure. It has an equity portion slightly above 40% of the regulated asset base. Equity rose slightly mainly because of the half year profits and the evaluation of post-employment benefit obligations linked to an increase in the discount rate. The company's liquidity position remains robust and the sustainable RCF and commercial paper are both fully undrawn. ETB also obtained its own public credit rating from S&P. It's rated BBB+ with a stable outlook. And finally, ETB has a well-balanced debt maturity profile. It has a weighted debt duration of 6.9 years and no upcoming near-term material maturities, and the average cost of debt is 1.91%.
Marleen Vanhecke
executiveWe go from Belgium to Germany. Germany has always been an important contributor to Elia Group's results, how was the performance of 50Hertz Transmission over the past 6 months, Catherine?
Catherine Vandenborre
executiveI will start with the top line where we see that revenues increased by 12.6% to reach almost EUR 784.9 million. This was driven by higher energy revenues, which we passed through and a higher investment remuneration from asset growth. The adjusted net profit came in at EUR 79.9 million, down by 15.4% compared with the previous year. And the key drivers of these results are the following: First, higher operation cost, which increased by EUR 19.3 million as 2021 marks a peak in the maintenance cycle. The OpEx cost also increased due to our expanding business and digitalization efforts to manage increasing complexity in system operations. Second, the ongoing investment program led to increased asset remuneration, which is up by EUR 3.6 million. At the same time, depreciation cost increased by EUR 2.1 million. And additionally, the result benefited from higher regulatory settlements, up EUR 1.1 million and this following a review by the regulator of the 2018 regulatory accounts, while prior year result also included a partial release of the easement provision for EUR 1.5 million. Finally, on the plus side, the financial result improved by EUR 3.6 million and is driven by lower interest expenses as a high interest rate bond was refinanced at more favorable conditions in Q2 of last year. From a balance sheet perspective, the equity remains solid. The slight decrease is driven by the payment of dividends being not fully compensated by the half year results. The liquidity position of 50Hertz remains very strong at EUR 2.7 billion with all revolving and overhead facilities fully undrawn. In the EUR 1.8 billion cash position, an amount of EUR 948 million of EEG cash is included and has to be given back to the consumers. In addition, in 2021, Eurogrid took advantage of favorable market conditions to issue a EUR 500 million senior bonds with a 12-year tenure and fixed coupon of 0.74%. Thereby, it secured part of the liquidity for financing its investment program and further reduce its average cost of debt to 1.34%. The maturity profile is well balanced with a weighted debt duration of 6.9 years. There has been no change to the rating of Eurogrid, which remains BBB+ with a stable outlook.
Marleen Vanhecke
executiveOkay. Let us now zoom in on our third segment, the non-regulated segment. Nemo Link we already said that there was a very strong start in 2021, could you give us some more details, Catherine?
Catherine Vandenborre
executiveIndeed. Our third segment performed well. Its adjusted net profit came in at EUR 8.4 million and the key drivers were the following. First, we had a higher contribution from Nemo Link, which was up by EUR 9.6 million. This reflects a strong operational and financial performance during the first semester with renewable availability of 99.89%. Nemo Link continues to be one of the highest performing assets of its kind in the world. In addition, the market price-spread increased compared with the same period last year from EUR 5 by megawatt hours to EUR 13.5 by megawatt hours in the same period. This followed on from the strong nuclear availability in continental Europe and increased gas and cabin prices in the U.K. This led Nemo Link to contribute EUR 15.6 million to the group's result. Secondary segments results benefits from lower regulatory settlement following the 2020 Saldi review by the CREG while also the operating loss of re.alto reduced by EUR 0.8 million reflecting tight cost control measures and the generation of first fee income. Finally, holding costs increased by EUR 1.5 million due to the higher operating cost driven by business development activities.
Marleen Vanhecke
executiveOkay. And finally, we still need to cover the outlook for 2021. What can we expect from Elia Group over the last -- in the coming 6 months, Catherine?
Catherine Vandenborre
executiveYes. We expect to end the year with an adjusted return on equity in the upper end of the targeted 5.5% to 6.5% range for 2021. If we look at the 3 segment, for Belgium, we remain confident about achieving return on equity of between 5% to 6% while investing around EUR 390 million in our grid. The slight upward revision in CapEx is mainly driven by the quick progress we made on our investment programme and the acceleration of certain projects that were originally planned for 2022. In Germany, we remain confident about achieving return on equity of between 8% to 10%. 50Hertz transmission intends to invest hopefully EUR 860 million in its grid. The realization of the investment program in Belgium and in Germany are of course always subject to external risks. And finally, on the back of a strong performance of Nemo Link for the first half of the year, we expect a positive contribution for the third segment to the group's results. And nevertheless, I would like to stress that the final contribution of these segments will depend highly on the performance of Nemo Link in the second half of the year, which remains subject to the volatility in the market spread of the electricity commodity price. And I would like to note that the guidance obviously, doesn't take into account any potential M&A transactions.
Marleen Vanhecke
executiveOkay. Thank you, Catherine. In conclusion, it's clear that during the first half of the year, our investment plans were executed in line with our original intentions and that we remain confident about achieving the predicted return on equity. Let us look a little bit further beyond the end of the year. Chris, you have said in the previous presentations that the sector is in full swing and that it offers many opportunities. How do you see the future?
Chris Peeters
executiveWell, we continue to be very optimistic about that. Our business is about supporting the energy transition, and we have only seen acceleration in the last couple of years and we expect to have a continued acceleration into that segment. The reason for that is of course that the extreme weather events that we've seen across the globe make very clear that we have to do something about the climate change that is happening as we speak. And that means that we will see more renewables coming in faster, that we see also that electrification in sectors like mobility and heat will go faster. And that means, of course, for us, more investments, more digitalization and more focus on ensuring that flexibility can be made available towards the market. This is fully in line with the strategy that we have seen in the past. We expect even a faster acceleration in terms of the offshore developments, and this is fully in line with what we're preparing for. Therefore, we can only look at the future with optimism in terms of the business side. Of course, we are as concerned as everybody else with that climate change. So we have to continue to work on that and to deliver in line with all that.
Marleen Vanhecke
executiveOkay. Thank you, Chris, and thank you also, Catherine, for today's update. Ladies and gentlemen, we have been provided with a comprehensive update on Elia Group's latest figures, and I suggest we now move on to the Q&A. Operator, it's your turn now. Did you receive any questions?
Operator
operator[Operator Instructions] And there was a question coming in from Olivier Vandewoude.
Olivier Vandewoude
analystI have a question first one related to the investments in Belgium. As I understood it correctly, you increased your investment outlook from EUR 365 million to EUR 390 million for 2021, does that mean because the projects are progressing faster than expected, so we can bring basically the investments from 2022 forward to this year? And then also a little sub-question as regarding the floods in Belgium, you mentioned that you do not expect them to have any direct impact on net profit but given that you have some investment programs in the affected regions, could it be that it will result in delay in the execution of the investment program? Or yes, given that you increase your outlook, don't we expect any delay on those projects there?
Catherine Vandenborre
executiveThank you, Olivier. So on the first question, I can only confirm that you understood it perfectly. So we increased slightly the guidance on the CapEx to EUR 390 million for 2021. And the reasons for this increase is exactly what you described, namely, that we are progressing well. We are anticipating on some investment of 2022. There is also a minor acquisition of some assets which was foreseen and for which the price might be slightly higher than initially projected, but most of the reason behind the increase is a progression in the investment and anticipation in 2022. On the second aspect, I mentioned that we expect very limited impact on the -- of the flooding on our net result. To be complete, we can still have an impact because you know that with insurance, you have also -- you always -- excess, you need to take into account. We have also reinsurance program through our Elia Re company where we have some loss. So it's not that we will not have any impact, but those impact is expected to be very limited and remote on the P&L. Do we expect some delay in the execution of the investment? No. First, because we had not that much investments in -- going on in the region that were affected. Of course, we had to redirect a little bit workload on cleaning the debris and afterwards, I am sure that the infrastructure could be put in a situation to work correctly again. But this was done in the vast majority in the last 15 years. For the rest, we will have more investments to do in one of our substation, the one of Pepinster, but that will be mainly related to 2022. We had anyhow planned some works in the substations into 2022. So I hope to have been complete in my answer with your question.
Olivier Vandewoude
analystYes, very clear. Thank you. Then second question relates to 50Hertz in Germany. So the higher OpEx and then the investments in digitalization and personnel costs had an impact of roughly EUR 20 million. On the net profits, do you expect that amount to be equal in the second half of the year? Or are we already on the top and you say, okay, the second half of the year, it will be a little bit less or -- can you just say anything on that?
Catherine Vandenborre
executiveSo the liability impact in the OpEx of 50Hertz, if you look back and situation of previous years, and the point is that often we have somewhat more expenses in the second half of the year than in the first half of the year. So if you look at the impacts on the total year related to the maintenance, it's not completely balanced between the first semester and the second semester. That being said, I don't know how you precisely identified the EUR 20 million that you were referring to, and I propose on this one that we have a discussion afterwards.
Operator
operatorAnd the next question is coming from a Juan Rodriguez, Kepler.
Juan Rodriguez
analystMy question around CapEx has been already answered, but then I take the opportunity to double-check on the guidance revision on return on equity. If we take the middle of the upper range of the 6% to 6.5%, it would take -- that out of the middle of the range, let's say, 6.25%. And then, it's correct that the guidance upgrade that you're providing is around EUR 10 million, EUR 15 million of net income level. That will represent something around the EUR 240 million, EUR 245 million adjusted net income. If I'm correct, that was -- I want to double-check with you if this is correct.
Catherine Vandenborre
executiveYes, so in terms of guidance, like we are saying, based on the information we have today, we expect to end in the higher ends of the guidance. If you want to translate this guidance in impact on the result, you have also to make some assumptions on the equity. I would like to check with you which type of net profits you refer to? I suppose it's the one relating to the owners of the company, and if that's the case, it should be according to our estimation of the equity a little bit higher than the EUR 240 million that you mentioned.
Juan Rodriguez
analystYes, on the shareholders of the company, so, okay. Perfect. And then as a follow-up on that one, can we say that mainly the react -- that for revision on your guidance is mainly driven by the positive performance of the other segment, after the EUR 9 million loss that you have in 2020, now that you said that you expected them to finish in the positive territory?
Chris Peeters
executiveThat's correct.
Catherine Vandenborre
executiveIt's indeed. So the revision of the guidance is linked with the good performance of Nemo Link during the first half of the year. And of course, we expect this performance to continue somewhat, not necessarily and exactly in the same sense, but somewhat in the second half of the year, and that's the reason why we were seeing that the guidance will be subject to possible evolution on Nemo Link. But that's exactly the reason Germany and Belgium are performing according to us, in line with the year-end guidance and Nemo Link is performing better.
Operator
operatorAnd the next question is coming from Akhil Bhattar from Citi.
Akhil Bhattar
analystMy name is Akhil Bhattar from Citi Research. I have 3 questions, if I may. First one is, what is your view of the initial German proposal of allowed returns? And what is the potential impact on the returns, or let's say, net income, if it comes in line with the initial draft? Second question is, if the returns are in line with the proposal, how do you think it changes the capital requirement in the medium term? And lastly, we are seeing inflationary pressure across all peers in this industry. So how do you think this impacts Elia's big CapEx plan for the next 2, 3 years?
Catherine Vandenborre
executiveSir, could you repeat your second question? Because it was some background noise and I didn't catch the second question.
Akhil Bhattar
analystSo for the second one, if the returns are in line with the proposal, how do you think it changes the capital requirement? I mean do you think CapEx needs to be changed for the medium-term target?
Catherine Vandenborre
executiveI will give the first answer and afterwards, Chris, if you want to complete. So in terms of load return, before estimating any possible impact on the bottom line, I would rather advise to wait for the complete picture on the regulatory framework. You know that there are different components on this regulatory framework, so the fair remuneration is certainly one of the components, but next to that, you have the situation related to the incentive regulation that will be needed to that find -- that we will have to take into account. And of course, we have also the evolution of the unplugged walls of possible cost-plus model. So it's very hard for the time being to predict any impact in terms of bottom line, because we don't have the full picture yet. We have a number of indications, but I would really advise to wait first on the publication of the final decision regarding the return on equity and then to the publication of the other elements. And of course, as soon as we have this information, we will give these information and make it public. Second element in terms of capital, we see it's the other way around. To put it more clearly, we knew everyone knows within society that there is a huge need for delivering on the energy transition, and that TSOs are key players in facilitating this energy transition. So we had to see increasing needs for investments in our infrastructure, and we had belief that the proper environments, including regulatory environment should be given in order to facilitate the speeding up of the investments in the network. That's for the second aspect. And I think with that, I covered your third question, but don't hesitate to come back if it's not the case.
Operator
operator[Operator Instructions] There are no further questions. Please continue.
Marleen Vanhecke
executiveThank you. If there are no further questions, I suggest we bring this presentation to close. Thank you, Chris. Thank you, Catherine for your contributions. A recording of the presentation along with the slides used throughout will be made available online later today. Thanks for being with us and stay safe.
For developers and AI pipelines
Programmatic access to Elia Group SA/NV earnings transcripts and 32,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.