Endeavour Silver Corp. (EDR) Earnings Call Transcript & Summary
March 10, 2022
Earnings Call Speaker Segments
Operator
operatorAppreciation for holding on. I'm the conference operator speaking. We welcome you to the Endeavour Silver Corp. conference call covering financial results for year-end 2021. <<operator_script>> Just a note that this call is being recorded. At this point I'll hand things over to Trish Moran, Interim Head of Investor Relations. The floor is yours.
Patricia Moran
executiveThank you, and hello to everyone. Before we begin, I'd like to ask you to review our MD&A, which contains cautionary language about forward-looking statements as well as the risk factors tied to those statements. Both our MD&A and our financial statements can be found on our website, edrsilver.com. Joining us on today's call are Dan Dickson, the CEO of Endeavour Silver, along with Christine West, our Chief Financial Officer; Don Gray, Endeavour's COO; Dale Mah, VP of Corporate Development; and Luis Castro, our VP of Exploration. Once Dan finishes his formal remarks, we'll open the line for your questions. Dan, over to you.
Dan Dickson
executiveThanks, Trish, and hello everyone. Endeavour Silver had a solid 2021 on both the financial and operational fronts. Guanacevi and Bolanitos both turned in strong results, and that performance helped offset the hit from halting operations at El Compas partway through the year. On a consolidated basis in 2021, we turned out 8.3 million ounces of silver equivalent — up 27% from the year before. That landed us above the upper end of our guidance, which we had raised in October. Two factors mainly drove last year's strong showing: first, gains in the volume of ore processed, ore throughput, and recoveries; and second, and more significantly, a better average realized silver grade. Revenue climbed 20%, the best in 5 years, lifted by both volume and price growth. Most importantly, that higher revenue fed through into greater profit and cash flow, with earnings per share of $0.08 and over $32 million in operating cash flow before changes in working capital. Our cost per ounce metrics came in higher than the previous year and above guidance. All-in sustaining costs and cash costs exceeded guidance by 1% and 3%, respectively. Inflation across the industry has been a challenge and remains one. In 2021, it touched everything from labor to power to consumables throughout our operations.
Dan Dickson
executiveOn top of that, Guanacevi faced increased costs tied to buying third-party ore and to operating development. We also had higher royalties, and a special mining tax got triggered because of Guanacevi's substantial output, plus the elevated silver prices and profitability. That financial performance gave us a solid balance sheet as the year closed. Cash stood at $103 million, and we carried no long-term debt other than routine leases. Working capital came to $121 million in total, which includes unsold bullion inventory carried at a cost above $15 million; that bullion was worth roughly $31 million in market value as of December 31. Given where prices sit now, we began drawing that balance down during 2022. This sturdy balance sheet positions us nicely to build out Terronera. As we entered 2021, Terronera was classified as an advanced exploration project. Then last fall, after a feasibility study was finished and its economic viability confirmed, it was reclassified as a development project. That study pointed to numerous improvements for the project, among them greater output and throughput. Once it is complete, we anticipate Terronera will roughly double what we produce and halve our cost profile. Reserves also rose by 33% under the updated study, and we see strong potential for additional growth. The drill campaigns now underway are delivering very encouraging results, and we aim to release the newest exploration results within the next few weeks.
Dan Dickson
executiveObviously, Terronera is a game-changer. Although we're still waiting for the official green light on construction, the project continues to advance. During 2021, $12 million went toward land purchases, initial development, and mobile and processing equipment. A further $9.5 million is budgeted for the first quarter of 2022 to cover site clearing, final detailed engineering, early earthworks, a temporary cap, and procurement of other long lead items. Once a debt financing package is complete and certain amended permits are in hand, we'll go to the Board seeking approval for construction. I should also point out that although financing has slipped a little, we continue to aim for completion of commissioning in the first half of 2024. With an eye on the future, we began last year to rationalize our portfolio and addressed a couple of assets that no longer fit or were too small for us. Early in the year, the Guadalupe y Calvo project was optioned to Ridgestone Mining, and El Cubo was sold to Guanajuato Silver. In August, we suspended operations at our small El Compas operation. We also closed a couple of smaller acquisitions to strengthen our flagship assets. First, we added 2 more properties adjacent to the existing historical mine work in the Guanacevi.
Dan Dickson
executiveAnd second, at Parral, we bought out a 1% NSR royalty — we now hold 100% of it, free of any royalty encumbrance. We also acquired the Bruner Project, situated in Nevada's well-known Walker Lane district. Our attention remains squarely on the bigger growth projects set to speed up our goal of becoming a premier senior silver producer — specifically Terronera, Parral, and now Pitarrilla. In mid-January, we announced we had signed the definitive agreement to acquire the Pitarrilla project from SSR Mining. Pitarrilla sits in Durango State, a place with a long mining history that's recognized as a mining-friendly jurisdiction in Mexico, with several operations running there, including our Guanacevi mine. It ranks among the world's largest undeveloped silver deposits, with a historic M&I resource of 525 million ounces of silver and grain close to 100 grams per tonne, plus amounts of lead and zinc. SSR has done significant comprehensive work to advance the project, and many key permits are in place. As a potential Tier 1 asset, Pitarrilla is an exciting project for us. Once the transaction closes in Q2, work will begin immediately to redefine the historical resource into a current resource, assess the number of targets, and move the project forward to an updated economic study.
Dan Dickson
executiveWe discussed the prior year and the exciting future ahead. Let's finish by covering what 2022 holds, beginning with our guidance for 2022. Our production forecast aligns with the average of the past 3 years, and controlling costs will be a major priority as we work to counter the effect of increasing costs. Guanacevi and Bolanitos are mature assets. We intend to spend over $34 million in sustaining capital to enhance performance and maximize output in the years ahead. Just as important among our priorities is further growing our mineral reserves and resources. Proven silver and gold reserves grew by almost 30% last year. And we have $13 million allocated within our exploration portfolio to extend our long successful record through the drill bit. 2022 will be an exciting year for the 3 cornerstones of our growth pipeline, Terronera, Parral and Pitarrilla, and each offers a significant characteristic and opportunity to add to our future growth profile. As mentioned, Terronera should progress from the funding and approval phase into construction over the coming months. At Parral, we anticipate launching a PEA in the second half of 2022.
Dan Dickson
executiveAlso, as we said before, we expect the Pitarrilla acquisition to wrap up during the second quarter, and once that happens, the work gets underway. By the end of this year, our aim is to identify current resource. All in all, this will be yet another busy year. With that said, operator, I'd like to begin taking questions.
Operator
operator<<operator_script>> Our first question is from Joseph Reagor at ROTH Capital Partners.
Joseph Reagor
analystThere's a broad question that keeps coming up on many of these calls: how are you all gauging the effect of supply chain inflation? And are you taking any proactive steps to keep that from hitting you? Then, as a follow-on to that: what rate of inflation are you all baking in for costs across the board this year versus last?
Dan Dickson
executiveAbsolutely, and thanks for asking, Joseph. For 2022, our budgets took a two-pronged approach: we assumed inflation of 6% to 9%, depending on whether the driver was labor or a direct cost input. Power costs had risen substantially late last year, and all of that was factored into the budgeted information. So the range varies with the components that go into the product. As I mentioned, labor came in at 6% to 8%, while power costs climbed nearly 28%. And in the end, we saw that reflected in our 2021 costs too. So part of it has already been addressed, and addressed within our budgets. Naturally, though, actual results will likely differ considerably from what we estimated in those budgets, and we'll watch how it unfolds. Looking at the bigger picture, our expectation is that inflation will persist, and we field plenty of questions about inflation as it relates to our capital expenditures and, ultimately, Terronera. I believe we've managed Terronera well, given that we've secured some long lead items, most notably our mobile fleet. A portion is already on site, and more is arriving in March.
Dan Dickson
executiveAnd we placed those orders around the middle of the year and began taking steps so that we could secure some of those pricing levels. Even so, there is no way for us to secure every one of them. So as far as the plant is concerned, the steel is going to be available. We have built contingencies into our feasibility study as we work through it. We will bring the market up to date on where we believe prices will land. I believe we have done quite well in our efforts to keep this advancing and to keep costs aligned with what we expect, which is in line with the feasibility study. So we will give it our best effort. Naturally, inflation is widespread across the entire industry, not only for us. And my view is that it will persist through 2022.
Joseph Reagor
analystAlright, this sort of follows up on that, and it's specifically about Terronera. If a lot of people think some of the supply chain inflation is temporary, would you consider pushing back the start of construction? Do you think about it as maybe it's in the best interest of the project's long-term value to kick the can until inflation pulls back a touch?
Dan Dickson
executiveSure, that’s something you’d weigh, obviously. In our case, though, Terronera is so essential and such a game-changer for us that we won’t hold it back. We’re working to move it ahead as fast as we can. And when you get down to it, the fact that it will double our output and reduce our cost structure by half is going to transform what this company looks like overall. As it stands in our feasibility study, Terronera has a 12-year mine life, but in the end, we anticipate it will operate for 20, 25 years. I realize people try to time markets or try to time inflation. Ultimately, if inflation rose 10% in 2022 and is still slightly up in 2020, we won’t be seeing deflation in 2023 or 2024. So we’ll continue driving it forward, and it’s vital to our company.
Joseph Reagor
analystAlright, and one last item, if I may. At your mines, what share of the total cost structure comes from fuel — diesel?
Dan Dickson
executiveCorrect. Since this is an underground vein operation, that figure sits below 7%. To put it another way, in any particular year it moves around within a 6% to 9% band, purely based on fuel price levels. So Joseph, when you're running an open pit, diesel represents an enormous expense for us. The cost that ranks second behind labor is in fact electricity, supplied through the CFE in Mexico. So where diesel is concerned, as I mentioned, the range is 6% to 9%, which isn't a large share next to open pits.
Operator
operatorOur following question is from Lucas Pipes at B. Riley Securities.
Matthew Key
analystMatt Key here, actually, posing a question on Lucas's behalf. It concerns the long-term grade expectations at Guanacevi. Clearly, the implied grade guidance for fiscal year 2022 is really strong. Still, I was wondering how we ought to think about grades over the longer term. Could we possibly return to the sort of levels seen in 2018 and 2019 in the near term? Or is that behind us at this point?
Dan Dickson
executiveAt this point, that's behind us. So we issued guidance only for the upcoming year, which is 2022 right now. And the grades in 2022 will be comparable to those we had in 2021. Beyond that, it's really a matter of looking at our reserves and resources, which are in our AIF, and the grades should carry on that way in 2023 and 2024. But as of now, we're not there yet. We've had a significant discovery with El Curso. It keeps growing, and that's where some of the most significant grades are coming from. So as prices can also rise, which is our expectation this year and next year, you could see that grade decline because your cutoffs change in the mine as well. But right now, what we see for 2022 is similar grades to what we achieved this past year.
Matthew Key
analystUnderstood — that’s very useful. And I’ll ask just one more. Could you help lay out which exploration projects you regard as the most promising over the long term once we’re past Terronera in the next 2 years? And perhaps also give a possible timeline for how you expect that next major growth project on the horizon to take shape.
Dan Dickson
executiveYeah. I mean, you're basically asking me to rank my own projects against each other. But as things stand, we have two strong growth pipeline assets sitting behind Terronera. There's Parral, a smaller one where exploration keeps delivering success for us. At the end of 2019, we had 40 million ounces defined, plus lead and zinc. And we've told the market that we need to grow that to 60 million, 65 million ounces, a level we believe would give us enough scale for an operation that matters to Endeavour and is big enough to be cost-effective and economically viable. During 2020, COVID kept us from drilling it. We began drilling in 2021, and the results have been very good — we released them earlier this year. Parral will see continued drilling in 2022. Then, midway through the year, we hope to have a resource base sufficient to support a preliminary economic assessment on it. Again, a certain scale is required for it to work, but we believe we can get there. The other asset, Pitarrilla, is obviously potentially a Tier 1 asset. I mean, it ranks among the world's largest undeveloped silver bodies, and we're excited — extremely excited — about it.
Dan Dickson
executiveClearly, we held a conference call just a short while back when we bought it from SSR Mining. That deal will be finalized during Q2, and after that we'll develop out the existing resource there. Regarding the sequencing between Pitarrilla and Parral, future prices will play a role. Ultimately, for Terronera we're anticipating a 2-year construction period. And ideally, one of those projects follows immediately after that 2-year build. At Pitarrilla, we intend to redefine the resource. So at present, it's viewed as a historic resource completed by silver standard. We're going to turn it into a current resource by carrying out the work in-house and publishing a technical report, ideally before this year is over. Then we'll conduct an economic study on Pitarrilla for 2023. So with Pitarrilla and Parral, ultimately you're looking at sometime in 2024 or 2025 when construction begins. But I believe it's among the leading growth profiles in the sector that you can find in our space.
Operator
operatorOur following question is from Mark Reichman at NOBLE Capital Markets.
Mark Reichman
analystTo start, my question concerns the Terronera funding. As far as I understand, you intended to arrange a debt facility of $80 million to $100 million. I wanted to ask if that remains the plan and how the talks are progressing. Also, do you expect to have it finalized by the close of the second quarter, considering the 24-month construction period?
Dan Dickson
executiveCorrect. That's precisely the case. The target range we have in mind for debt is $80 million to $100 million. On our balance sheet, we hold $100 million in cash along with $120 million in working capital. Things moved somewhat slower during Q4 and Q1, since the Omicron virus affected the banks' technical due diligence. Still, we've gotten past all of that. Progress tends to come in a bit under expectations. Even so, we're hoping the banks will give us a commitment before this quarter ends.
Mark Reichman
analystThen for my second question — you've got a lot on your plate right now, with a solid project pipeline. Even so, would you still be open to smaller producing acquisitions? And given the higher prices, what does the M&A landscape look like out there at the moment?
Dan Dickson
executiveYes. I mean, we do have a corporate development group. Dale is here on the call with our management team today, and we are always on the lookout, whether it's a growth asset or a greenfield exploration asset, for two reasons. First, we believe our asset base can always be improved. And second, if there's an asset available at the right price, we would absolutely be open to adding it to our portfolio, particularly if it generates cash flow. The landscape is constantly shifting. In the world we live in today, I think it changes more quickly than it ever has. And there are a couple of deals we've seen over the past year. There's a scarcity in the silver market. Ultimately, we're trying to remain a primary silver producer, to keep our revenue mix above that 51% threshold, which not many of our peers have managed to do. So we're interested in primary silver assets, and finding them is difficult, and finding ones that are profitable is difficult, and finding ones that are cost effective and what we pay for them is also difficult. But nonetheless, we are always looking. And if something makes sense, we'll pull the trigger on it.
Mark Reichman
analystAlright. I think you already sort of mentioned this earlier regarding the Parral project — that you've got the indicated and inferred resources sitting at $435 million. You're aiming to reach somewhere between $60 million and $65 million. As things stand right now, with no further drilling, what do you figure you could ultimately end up with? I mean, do you feel at this stage that you're fairly close to the target? And so the updated report you'll be releasing — is there pretty high confidence that you'll hit that threshold?
Dan Dickson
executiveRight, the $60 million to $65 million range plus completing a PEA — that's what we intend to do, and we've got the PEA budgeted for the end of the year. Of course, drilling still has to keep going, and it has been delivering positive results, though that's what we'd expect. And I think when you look at the drill results from 2021, they compare more favorably with what we put out on Parral between 2016 and 2018. So as I said, I anticipate that continuing, and provided it does, we ought to reach that target.
Operator
operator<<operator_script>> Our following question is from John Tumazos of John Tumazos Very Independent Research.
John Tumazos
analystI noticed that the tonnes you processed over the year, both mined and milled, went up 17%. And the cost per tonne went up 17% as well. Normally, higher volume helps bring down how fast unit costs rise. Was there anything unusual happening with the mine — something idled, some downtime, or special maintenance?
Dan Dickson
executiveNo, John — you've got that right for us. Processed tonnes came in slightly higher, but in the end, both our cost per tonne and our operating cost per tonne rose too. As I mentioned earlier on this call, that's driven by inflation. It showed up just about everywhere, with power costs standing out most. Between August and December, on a monthly basis, our power costs climbed roughly 30%. We also saw labor costs rise last year, along with pressure on professional labor — geologists and engineers. In the end, this is something widespread across the industry at the moment: cost pressures are visible, and we're doing our utmost to hold cost per tonne as steady as we can. I think we got a very positive result from the fact that grades coming out of Guanacevi are considerably higher. Royalty costs also went up last year, reflecting the improved profitability. In the end, we paid a 16% royalty at our El Curso mine, which we leased from Frisco a couple of years back. So as I say, naturally we'd like to keep costs as low as we can. We're managing it wherever possible, but inflation and global supply constraints are having an impact.
John Tumazos
analystLet me ask one more thing, if I may. When you acquired the Bruner Project for $10 million in cash, I was really excited for you. The company before you had permitted that project and claimed it was partially built. Whether they put $25 million into it or $50 million into it, I don't know. And at first, what you disclosed was quite brief. I simply figured you weren't saying much because the deal was so favorable to you. Now that you've held it for 6 months, could you go into more detail? And could it be turning out 40,000 ounces within a couple of years?
Dan Dickson
executiveWe’re fond of the Bruner Project. We acted opportunistically. We’re very happy with the price we paid. For anyone who isn’t familiar, it has a historic resource of 300,000 ounces of gold and 13 million ounces of silver. It did have a historic PEA on it with a NAV value of roughly 80 million, and that kind of envisioned a 35,000 to 40,000 tonne or 35,000 to 40,000 gold ounce operation. Nothing is partly built on it. It’s a greenfield exploration project. So there’s no infrastructure of substance. I’m not sure exactly what the predecessors said in the past, but I can assure you it is a greenfield exploration project. We’re advancing it this year. We’ll convert that current — or the historical resource into a current resource. There are many targets at Bruner that excite us, and we’re excited about it. As I said, a very opportunistic deal for us. The predecessor ran into some debt trouble, and we were lucky enough to acquire it for only $10 million. A lot of work remains to be done there. We’d like to acquire some more land and exploration potential around it.
Dan Dickson
executiveEven so, by the close of this year we'll have additional findings from that.
John Tumazos
analystSo in your lineup, would this come in fourth behind Pitarrilla, Parral, and Terronera? Or does El Cubo sit ahead of it? Or, roughly speaking, where does it fall in your ranking of projects?
Dan Dickson
executiveRight now, it likely sits behind Parral and Pitarrilla, simply given how far those two have progressed. But at the end of the day, the work still has to get done. So we'll let the drill bit show us where it stands by the close of 2022.
Operator
operatorThat wraps up the question-and-answer portion. Dan Dickson, I'll hand the conference back to you for any closing remarks.
Dan Dickson
executiveOkay, thank you, operator, and I appreciate all of you joining us for our 2021 earnings call. In my view, 2022 should shape up as a solid year. Clearly, prices are running high right now. My hope is that conditions in Europe become somewhat more settled, since at the end of the day, we'd like to see a resolution there over the next few months. In the meantime, we'll keep doing what we've been doing — once again, working to move our development project with Terronera forward, and ideally we'll reach a construction decision on that before long. Then, ultimately, we'll keep advancing Parral and Pitarrilla, where we believe we hold one of the sector's leading growth profiles. So thank you to all who attended, and I'm certain we'll speak again soon over the next few months.
Operator
operatorThat brings us to the end of today's conference call. Your lines can now be disconnected. We appreciate your participation, and we hope the rest of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Endeavour Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Endeavour Silver Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Endeavour Silver Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.