Endeavour Silver Corp. (EDR) Earnings Call Transcript & Summary
March 11, 2024
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line. I'm the conference operator, and I'd like to welcome you to Endeavour Silver Corp.'s conference call on the financial results for full year 2023. <<operator_script>> Please note that this call is being recorded. <<operator_script>> At this point I'll hand the conference over to Galina Meleger, Vice President of Investor Relations. You may proceed.
Galina Meleger
executiveThanks, operator, and hello to all of you. Before we begin, I'd like you to review the MD&A, where you'll find cautionary language about forward-looking statements and the risk factors tied to them. Both our MD&A and our financial statements can be found on our website, www.edrsilver.com. Joining us today are Dan Dickson, the CEO of Endeavour Silver, along with Elizabeth Senez, our Chief Financial Officer, and Don Gray, Endeavour's COO. After Dan speaks, we'll open the line for your questions. Dan, over to you.
Dan Dickson
executiveThanks, Galina, and hello everyone. As we kick off this year's earnings call, I believe it's worth recognizing the shifting conditions that defined mining in 2023. Wild swings in the market produced share prices that were both unstable and weaker. Those developments hurt valuations of companies throughout the precious metals space and generated a major gap versus the prices of the underlying commodities. Against that wider market picture, we dealt with rising operating expenses, which made running our operations more complicated. This pattern showed up at every Mexican mining company, where expenses pressed from several directions. To give you a sense of scale, here are a few key figures. During the past 3 years, Mexico's consumer price index climbed by over 21%, and the effect was magnified in our sector because critical inputs including steel, reagents and other consumables were hit by supply restrictions. On top of that, between Q4 2021 and Q4 of 2023, the Mexican peso gained almost 20% versus the U.S. dollar, which rippled through to our local purchasing and labor expenses. Looking back over the year, I can say our operations team showed tireless commitment while working through these difficulties. Today, my aim isn't merely to revisit those difficulties, but to highlight the strategic steps we've taken to secure growth and success for our company.
Dan Dickson
executiveLooking at the full year on a consolidated basis, we turned out 8.7 million silver ounces equivalent metal, and that came in within guidance following 2 straight years in which we beat our production guidance. Output landed close to the bottom of the guided range, and we had a shortfall in Q3 that stemmed mostly from the mine resequencing changes we put in place to boost ventilation and, in the end, keep workers safer. That temporary interruption to operations meant less mine output and lower ore grades. I'm happy to report that Guanacevi did considerably better in the fourth quarter, since the planned improvements were carried out very well and very quickly. Guanacevi's production came back to historical levels, and on top of that our recovery strategy beat expectations, with silver grades, gold grades and plant throughput all coming in above what we had estimated. The plant refurbishments that wrapped up at the start of Q4 gave us more operational flexibility, letting us surpass the historical throughput of 1,200 tonnes per day. Those upgrades and enhancements drove costs higher in the second half, but cost metrics got much better in Q4. Guanacevi had its difficulties in Q3, yet Bolanitos stayed steady, with higher silver production offsetting lower gold production in the fourth quarter. Financially, for the year we posted revenue of $206 million, cost of sales of $169 million, operating earnings of $37 million and mine operating cash flow of $40 million.
Dan Dickson
executiveFollowing exploration plus G&A and other investment costs, net income came in at $6 million, or $0.03 per share. Over the full year, Guanacevi generated $14.3 million in mining free cash flow, while Bolanitos generated $2.5 million. Cost of sales rose 6% versus the prior year. There were several drivers behind that, but the Mexican peso's strength and inflation affecting consumables were the two biggest. Those two factors, together with ore grades that fell short of plan and the grades mined as a result of resequencing the mine in Q3, fed into elevated cost metrics for the year, with cash costs of $13.49 per ounce and all-in sustaining costs of $22.93 per ounce. Both figures exceeded our original guidance. That said, the fourth quarter gave us some footing, since costs fell considerably from Q3. In Q4, cash costs were $12.54 per ounce and all-in sustaining costs were $21.48 per ounce. Remediation work carried into early Q4, and the positive momentum from these initiatives should continue. As we look toward 2024, holding costs in check and finding efficiencies stay in focus. Although inflationary pressures and a strong local currency persist, we are moving aggressively on business improvement initiatives to offset these headwinds.
Dan Dickson
executiveAt year-end, our cash stood at $35 million, with working capital of $43 million. Cash was down in Q4 because money is being directed toward development work at Terronera, and long-term prepaids rose substantially as we put deposits down with contractors and for equipment. Working capital has declined while we keep investing in the Terronera project. Through that investment, we've grown our noncurrent assets, which include $22 million of construction deposits tied to the Terronera build and $23 million in value-added tax. That IVA receivable has been filed for processing, and the company is engaging with the authorities to secure timely collection. Even so, we take the conservative approach of classifying these as noncurrent assets until collection begins. Under the terms of the $120 million senior secured debt facility, we are required to fund development mainly from cash on hand before we draw on the facility. Because of that, we are well positioned to meet the project's financing needs and expect to complete our first draw in March. In Q4, we brought in gross proceeds of $39 million through the ATM, and an additional $24 million was raised after year-end so that sufficient funding is in place for developing Terronera. Adding it all together, we have sufficient capital, and we're confident that the steps we've taken will carry Terronera through to the finish line while also backing the high-value organic growth initiatives in place at Pitarrilla.
Dan Dickson
executiveJust to remind everyone, Pitarrilla is the project that comes next for us in the pipeline — it sits in Durango state, Mexico, and ranks among the biggest undeveloped silver deposits anywhere in the world, with close to 600 million ounces of silver defined. Let me give a brief update on how construction is going at Terronera. Back in January 2024, we finished a risk analysis covering what was left to spend on that project and issued a revised initial capital cost figure along with an execution plan. Much like the trends we've seen at our operating mines in Mexico, we ran into comparable headwinds at Terronera over the construction year. A stronger Mexican peso, persistent inflation, and tight equipment and bulk materials markets together drove an 18% increase in our updated initial capital estimate, which came to $271 million versus $230 million before. Even with those capital pressures, project development keeps moving forward and remains consistent with earlier guidance, with commissioning scheduled for Q4 of 2024. By year-end we had hit 46% completion on overall project progress against the original guidance. That said, because of the reweighting under the revised initial CapEx, management puts adjusted completion at 43% as of December 31. We had invested $122 million in direct development, and project commitments came to $171 million, equal to 63% of the updated capital budget.
Dan Dickson
executiveIn Q4, we focused on wrapping up key items, including earthworks for the Upper Mill Platform, equipment procurement, and progress on plant concrete, and we made substantial headway in building our process plant. If you'd like to see photos showing how construction is advancing, I'd encourage you to check out the Terronera page on our website. Let me share a few recent Terronera progress highlights that show how strongly we're committed to responsible, sustainable development and to collaborating with our key local stakeholders. Beginning with safety, our Te Cuido culture has provided a solid foundation for a strong safety record at the project. We ended the year with zero lost time accidents across 172 days of work at site, amounting to roughly 600,000 man hours. In particular, we tightened safety protocols considerably, especially through the rainy season and notably in Q4, when we received word that Hurricane Lidia was about to reach the coastline. Even though we faced a Category 4 storm, our site came through it admirably, with only minor damage to exterior fixtures and a few fallen trees. The strength of our drainage system was essential to preserving the integrity of the site and the roads. As a precaution, we halted on-site activities to keep our personnel safe.
Dan Dickson
executiveFortunately, power and normal operations came back quickly, within a few days. Our on-site team also assisted local relief efforts, helping nearby communities get back on their feet. Throughout the year, we have stressed how much efficiency matters in developing our mine. To tackle that, we deliberately brought in top-tier talent and made a successful move to our in-house mining team following start-up with mine contractors. That change was part of the plan from the beginning and has produced meaningful development efficiencies, with notable gains in Q4, when we hit our daily advance rate targets thanks to better blasting techniques, water control, and improved ground conditions. By the time the year ended, cumulative underground development had surpassed 2,200 meters, a substantial 70% increase in meters versus Q3. This positive momentum in advance rates points to a promising path ahead. During the quarter, the Portal 4 incline broke through to surface, and preparations are now underway to finish the portal structure in Q1 2024. Most construction activities at the plant site have moved along well. At present, surface construction is nearly 50% complete, and the advanced stage of concrete work sets the stage for the start of vertical construction, which began in January. At year-end, concrete work was nearly finished in both the grinding and flotation areas and was being readied for the general contractor to begin structural steel and mechanical installations.
Dan Dickson
executiveIn Q4, we also began building the access road that links the lower platform with the Tailings Storage Facility area and the Upper Mill Platform. At Terronera, our workforce keeps expanding — we now have more than 520 employees and contractors onsite. Regarding procurement, every major piece of equipment had been ordered by the end of the year, and the team's focus now is on buying bulk materials such as structural steel, piping and electrical cable. Finally, on community relations, the municipality remains fully supportive, and we keep engaging and educating them as work at site moves forward. Okay. I've covered a great deal about 2023. Now let's look at what this year holds for Endeavour. We're entering 2024 from a solid position financially and operationally, with several strategic initiatives in progress that will fuel our future growth. Our production outlook has gold and silver consistent with 2023, and managing costs remains a key focus as we work to offset rising cost impacts. Guanacevi and Bolanitos are mature assets, and we plan to invest over $30 million in sustaining capital to optimize their performance and maximize output. Just as important on this year's agenda is moving our growth profile forward.
Dan Dickson
executiveWe've allocated $9 million across our exploration portfolio so we can keep up the strong, long-running record we've built of growing through the drill bit. At Pitarrilla, for example, we're hoping to put more than $5 million toward a number of initiatives. The plan for this year involves running a 6,000-meter drill campaign aimed at the high-grade zones and feeder structures within the existing resource. Data we gather will be used to inform our next steps, with the goal of evaluating this project as an underground silver mine. In the end, Terronera and Pitarrilla together underpin our long-term vision of becoming a 20-million-ounce senior silver producer and give us a value proposition that stands out as the best in the silver space. With a constructive macro backdrop for gold and silver now in place, we think our growth strategy is well timed and well suited to delivering outperformance for our stockholders over the years ahead. I'd also note that during the past few years, we've purposely reinvested in the business for long-term growth. Now, with under a year remaining until Terronera comes on stream, we can look forward to seeing the benefits of those investments accrue to our shareholders. 2024 is all about execution at Terronera, which is clearly transformational.
Dan Dickson
executiveOnce that work is finished, we anticipate Terronera will come close to doubling what we produce, bring our cost structure down meaningfully, and deliver considerable free cash flow to shareholders. For Endeavour and the people who have a stake in us, the year ahead should be an exciting one. Although the next few months will be more capital-intensive as we build up toward production, we are looking forward to the robust free cash flow that 2025 is expected to generate. Ahead of taking questions, I want to officially welcome Elizabeth Senez, who was recently named our CFO, to the executive leadership team. Libby came aboard in January, and as a Finance Executive whose focus is predominantly Latin America, we are delighted to have her with us. She adds more than 20 years of value in accounting, corporate finance and corporate treasury to the position. On behalf of everyone at Endeavour Silver, I would also like to thank Christine West, our previous CFO, for the many contributions she made to the company across the past 16 years. Over her career with Endeavour, she showed incredible dedication both to her work and to our company's success. Christine, we wish you the very best in retirement. Along with the rest of our management team, we would be glad to take your questions.
Dan Dickson
executiveOperator, please go ahead and open the lines for questions.
Operator
operator<<operator_script>> Our first question is from Jake Sekelsky at Alliance Global Partners.
Jacob Sekelsky
analystTo begin, regarding the <<inaudible>> guidance for the year, could you address — or perhaps put a number on — how the recent gold price movement might benefit us from a gold credit standpoint?
Dan Dickson
executiveYes. Well, for the year, just so everyone listening is clear, we'll produce roughly 5 million ounces of silver along with about 35,000 ounces of gold. Obviously, a $100 impact from an increase in the gold price makes a significant difference from a byproduct standpoint. I believe we did our budgeting at $1,840 for gold for the year. And obviously, today we're sitting at just shy of $2,200. That impact will, first of all, significantly drive things down on a per ounce basis, on a byproduct basis. Specifically, when it goes right into our cash costs and where our guidance was, it's beneficial, but I think it's still early days, and we'll stick by our guidance of using $1,840.
Jacob Sekelsky
analystAlright, that's useful. Then, regarding Terronera specifically, could you briefly address how much CapEx is still exposed to wider inflationary pressure? And what else has been <<inaudible>> secured at this point?
Dan Dickson
executiveYeah, Jake, I'd say at this stage the inflationary pressure has likely eased, simply because by now we've completed the bulk of our key procurement, including on bulk items. When we reestimated Terronera's price, with initial CapEx rising from $230 million to $270 million, we set our Mexican FX rate at 17.3% in the budget. So provided the Mexican FX rate remains at that level, I believe we'll be fine. From here it's really about productivity at site and ensuring we execute. As I said, there will always be minor headwinds, be it inflation or further peso appreciation, but the impact, and what remains to be built over roughly the next 9 months, is small as long as we produce.
Operator
operatorHeiko Ihle from H.C. Wainwright has the next question.
Heiko Ihle
analyst<<inaudible>>.
Dan Dickson
executiveHeiko, I hope we can hear you clearly — right now you sound a bit digitized.
Heiko Ihle
analyst<<inaudible>>.
Dan Dickson
executiveSorry, Heiko — on our side we weren’t able to make out what you were saying; it all came through digitized.
Operator
operatorOur following question is from Lucas Pipes at B. Riley Securities.
Lucas Pipes
analystI'll do my best not to come across like R2-D2, but before anything else, let me add my congratulations to Elizabeth, and then to Christine — I hope you enjoy your retirement. Dan, perhaps my first question concerns the cost side. What more can be done? What other things are you examining in order to mitigate costs as we move ahead? I'd appreciate hearing your thinking.
Dan Dickson
executiveYes. At Guanacevi, we still see room to improve productivity. During Q3, ventilation problems meant it was extremely hot for our employees working underground. And as we went deeper into the El Curso area, conditions became hotter. In Q3 and Q4, we installed a new ventilation system and ultimately raised how much water we were pumping out. We saw a lot of benefit from that in Q4, but some benefit is still to come in Q1, and that comes down to productivity. So when the mine became overly hot, we had to give our employees more breaks and place them in cooling chambers to effectively ensure they were working in a safe manner. And I think at this point, with the ventilation and the underground temperature where it is, they can work fully. And so there are productivity gains that could be achieved at Guanacevi. And then it's working across both Bolanitos and Guanacevi and making sure we're procuring and reaching out to a number of different vendors and trying to get some bulk work done on that. And there are always abilities to kind of look at what we're doing from a purchasing standpoint, what we're doing from a productivity standpoint.
Dan Dickson
executiveEnsuring that, at the end of the day, mine development is a major priority for us in this year — that we're achieving the advance rate we expect and applying some incentives to guarantee we're doing that as a group. So there are plenty of small things we can do. Of course, Guanacevi and Bolanitos are mature assets, and there's this kind of diminishing returns over the years. But I think given what we've witnessed in Mexico regarding all those cost pressures that we have to examine, anything that's available to us to try to bring down our costs on a per ton basis.
Lucas Pipes
analystNow moving on to Terronera. How large is the workforce at present? And what's the split, roughly, between your own employees and contractor labor? I believe you've flagged that as a key factor behind the productivity and efficiency gains you expect ahead. Then on the ball mill — has it been moved to the plant yet, or do you expect that in Q1?
Dan Dickson
executiveYeah, absolutely. To address your first question: as of December 31, we had 520 people in total, counting employees and contractors, and roughly 120 of those 520 were direct employees. Over the course of this year, we expect on-site headcount to peak at about 700. Then, on the ball mill question — good one. I discussed quite a bit about Q4 and what was going on at site. Both our SAG mill and our ball mill are in fact already at site, and they've been set in place. So Q1 has been exciting in that sense, though we'll give a full construction-side update on Q1 more broadly in April.
Operator
operatorOur following question is from Stephen Soock at Stifel.
Stephen Soock
analystDan and team, congratulations on a solid quarter. My question focuses more on Terronera and the underground rates. I believe this was somewhat of a critical path item, and it's great to hear they've risen so notably over the last quarter. Could you maybe just comment on whether those are tracking to your original plan? Or is there some catch-up to do there? Or are you seeing additional efficiencies that you hadn't counted on at this point in the transition, and just a bit more color around how that's progressing?
Dan Dickson
executiveYeah. Stephen, that's a really good question. Ultimately, what we're aiming for is roughly 4 meters of advance per critical heading each day. We managed to hit that in Q4, and Q1 has shown the same. There's always some room for improvement when we redesign the mine plan. We're constantly reworking that plan—you could almost call it dynamic, given ground conditions, water flow, and various other factors we deal with. Our team on site is highly experienced, and over the past 6 months they've been outstanding, I'd say. So we're achieving the advance rate we planned, which keeps us on track for commissioning in Q4 of this year.
Operator
operatorOur following question is from Craig Hutchison at TD Securities.
Craig Hutchison
analystDan, this may echo Stephen's question, but it concerns critical items. You mentioned Tailings Storage Facilities being on the critical path. Is there any update on where that stands? You said an update would come in Q1, but can you share any figures on where the overall project sits here in mid-March — 43% at year-end. Are you somewhere in the 50s now? Anything along those lines would help.
Dan Dickson
executiveYes, that's right. And to build a bit on what Stephen asked: at the moment, the critical path we see is mine development along with the Tailings Storage Facility — and initially, the TSF, when the build was scoped, wasn't really anticipated to sit on the critical path. But given the timing of when we began work on that lower platform and where the tailings dam sits, it's right in line with mine development. I'm glad to report that during Q1, work on the TSF got underway in full, and we expect that work to wrap up midyear. So there's still a bit of time around it. Again, productivity on the TSF got off to a somewhat slow start, but it has picked up. And hopefully, we can get there. So it's no longer a critical path item — mine development remains the one.
Craig Hutchison
analystAnd on the broader picture, is there anything new you can share regarding that roughly 43% figure we're targeting by year-end?
Dan Dickson
executiveYes. As I mentioned, we initially had 46% in mind, and we revised that to reflect the updated initial CapEx. And as of December 31, we felt we were at roughly 43%. Typically, we're gaining 2% to 3% in efficiencies each month, and that's broadly the plan. So at the start of March — not mid-March of the year — we're probably around 50%. I know Don Gray, our COO, is on the line. Don, is there any other color you'd like to add to that?
Donald Gray
executiveYeah, thanks, Dan. So Craig, we're at slightly below 50% right now. We'll get clearer visibility on that by the end of March. But work at the site is progressing very well. There's a lot happening on the mechanical side and the upper platform. As Dan mentioned, the mills have been set, and we're also beginning to place pumps and flotation cells and similar equipment. And the excavation down in the lower platform area is going well.
Craig Hutchison
analystAlright. Great. Perhaps one final question from me. So — you’re planning to draw on the debt facility during this quarter. Is that still on schedule? Will it be the entire amount? Or will it be somewhat in increments of the full amount?
Elizabeth Senez
executiveI’ll answer that. It’s Libby Senez. We intend to make the first draw this month, though not for the entire amount.
Operator
operator<<operator_script>> Our following question is from Heiko Ihle at H.C. Wainwright.
Heiko Ihle
analystIs this coming through clearly for everyone?
Dan Dickson
executiveHeiko, you sound absolutely phenomenal.
Heiko Ihle
analystI'm actually at home right now. I'm not sure what happened a moment ago. So I hung up and called back in, so I apologize ahead of time if this question has already been asked. Dan, during your prepared remarks earlier in this call, you referred to commissioning in early Q4. If we read into that, we're likely looking at October or perhaps early November, which puts it 7 months out. Has that timeline shifted at all? I just went through the February 12 press release, and it merely says Q4 as well. And I mean, our model probably had more like mid Q4, and this is clearly considerably better. And if this timeline has changed, what exactly helped move it forward, please.
Dan Dickson
executiveOur public position has consistently been commissioning in Q4, and at no point have we specified a month within that quarter—October, November, or December. That, I think, gives us a small cushion. Originally, in our feasibility study, we had envisioned a commissioning period of roughly 3 to 6 months. In the model we're using at present, it may run somewhat under 6 months, nearer to 3. Yet from April 2023 through today, the expectation we've stated publicly has remained unchanged: commissioning in Q4 of 2024.
Heiko Ihle
analystUnderstood. All right, then, taking that a step further, and I'm just speaking off the cuff here, Terronera's cost curve clearly comes with a certain amount of ramp-up built in. Within your internal model, has anything about that ramp-up curve shifted relative to where you perhaps stood 1 or 2 years back, before construction was truly in full swing?
Dan Dickson
executivePerhaps I haven't quite grasped what you're asking. So when it comes to the initial CapEx ramp-up rising from $230 million to $270 million, is your question about how that affects our model?
Heiko Ihle
analystNo, no — that only happens once it's genuinely in production later this year. With — I'm assuming that as efficiencies get added at the site within 2, 3, 4 quarters, as the whole thing ramps up. Anything you're seeing, anything that shifted internally over the last couple of months, and what are you seeing on the cost side for the ramp-up? Like...
Dan Dickson
executiveYeah, honestly...
Heiko Ihle
analystWhat that works out to on a per-ounce basis.
Dan Dickson
executiveYes. We haven't made any public statement, and internally speaking, regarding operating costs — obviously, with the operations we currently run, we've experienced rising pressure on operating costs tied to the Mexican peso and the rate of inflation. In our feasibility study, which was made public, we disclosed an $87 cost per tonne for the operation. That figure, again, was based on 1,750 tonnes per day. At the time we announced the construction decision for Terronera, we discussed the 2,000 tonne per day scenario, and that lowered our cost per ton to $80. Now obviously, given the pressures felt throughout the space, that $80 per tonne probably won't stay at $80 per ton — higher steel prices and reagents are going to push it upward. We haven't remodeled any of that. As we get closer to operations and move into commercial production, we'll likely provide the market an update on those at that point. But simply knowing the operations and where those pressures have shown up, I don't believe it will be significant or alter the outcome of what we're doing at Terronera.
Operator
operatorThat wraps up the question-and-answer portion. Dan Dickson, I'll hand the conference back to you for any closing comments.
Dan Dickson
executiveAlright, thank you, operator, and I appreciate everyone joining us for the 2023 earnings call this year. Here's hoping 2024 proves to be a fantastic year. Over the past 2 weeks, gold prices have really surged, and my hope is that this carries through to silver prices. We remain near a 9:1 ratio, as I understand it. In the end, we expect that some of the strength in gold will flow through into silver. Our focus this year is to deliver on Terronera. I believe 2024 will be a truly great one, and hopefully well past that as well. Thanks, and enjoy the rest of your day.
Operator
operatorThat wraps up the conference call for today. Your lines can be disconnected now. We appreciate you joining us, and we hope the rest of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Endeavour Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Endeavour Silver Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Endeavour Silver Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.