Operator

operator
#1

Appreciation for holding. I’m the conference operator, and I’d like to welcome everyone to Endeavour Silver Corp.’s conference call on the financial results for the first quarter of 2024. <<operator_script>>. At this point, I’ll hand the conference over to Galina Meleger, Vice President of Investor Relations. You may proceed.

Galina Meleger

executive
#2

Thanks, operator, and hello everyone. Before we begin, I’d ask you to review the cautionary language in our MD&A concerning forward-looking statements, along with the risk factors related to those statements. Both our MD&A and financial statements can be found on our website at www.edrsilver.com. Joining us for today’s call are Dan Dickson, Endeavour Silver’s CEO, Elizabeth Senez, our Chief Financial Officer, and Don Gray, Endeavour’s COO. After Dan’s remarks, we’ll open the line for questions. I’ll now turn it over to Dan.

Dan Dickson

executive
#3

Thanks, Galina, and hello everyone. We got off to a strong start in 2024. Gold has climbed to fresh record highs and silver is beginning to trail along, which has warmed up market sentiment. Higher prices are boosting our cash flow, and so far in 2024 our share price has beaten our peer groups. Operationally, our mines are meeting their targets. Beyond that, we achieved outstanding progress building Terronera, our next cornerstone mine, which locks in a promising future for the company. It's thrilling to consider that a year from now, Terronera will be adding production to our profile. Consolidated Q1 silver equivalent output came to 2.3 million silver equivalent ounces, meaning 1.5 million ounces of silver plus 10,000 ounces of gold. That leaves us well positioned to meet 2024's production guidance of 8.1 million to 8.8 million silver equivalent ounces. Both operating mines, Guanacevi and Bolanitos, continue to perform steadily and, for want of a better word, on script. Gold grades at both operations ran slightly ahead of plan, offset by silver grades running slightly below plan. Silver equivalents are unchanged, and we anticipate a similar grade profile through 2024. Turning to our financials, we posted revenue of $64 million, up 15% year-over-year, driven by higher volumes sold and a higher realized gold price than in Q1 2023.

Dan Dickson

executive
#4

Cost of sales came in at $52 million, which is also a 32% increase over Q1 2023, driven by a mix of more ounces sold, elevated direct costs, and depreciation. Direct costs have leveled off and are tracking nicely against our 2024 plan costs. Mine operating earnings reached $12 million, and after expiration, G&A and income tax expense, we reported a net loss of $1.2 million, or $0.01 per share. Looking at the site level, Guanacevi generated mine free cash flow pretax of $6.5 million, while Bolanitos added $4.5 million. Our Bolanitos operation has benefited considerably from the stronger gold price. The full impact of the 2023 cost escalations and the appreciation of the Mexican peso weighed on direct operating costs relative to Q1 2023. Consequently, our direct operating costs per time were substantially higher than last year. That said, when measured against the 2024 budget, our direct operating costs tracked well with budget. For clarity to our listeners, we define our direct operating costs as mining, processing and indirect costs. Royalties, special mining duty and purchased ore are part of our direct cost metrics and are all affected by higher metal prices. Once again, these costs, including our direct cost per ton, have all come in above budget because of the higher metal prices.

Dan Dickson

executive
#5

That's about $50 per ton added to our direct cost per ton. On a net basis, the higher byproduct gold credit did work in our favor, and as a result, both our cash costs and all-in sustaining costs came in under guidance. As of March 31, we held $35 million in cash and working capital of approximately $56 million. In Q1, our ATM facility generated gross proceeds of $39 million. As a reminder, it's important to note that under our agreement for drawdown on the senior secured debt, we were required to self-fund development up to $150 million before we could access the $120 million credit facility. After the quarter ended, we met that condition, which then allowed us to draw the first installment of the $60 million out of the $120 million committed. In connection with that draw, we also finalized the terms of the last hedge contract to reduce financial risks on the project. First, taking advantage of the strong gold price environment, we entered forward sale contracts covering 68,000 ounces of gold at $2,325 per ounce. That equals 55% of the planned gold byproduct production over Terronera's initial three years of operations. Second, we locked in the cost of the pesos through forward purchases of $45 million of U.S.

Dan Dickson

executive
#6

That equals the amount in Mexican pesos, and it takes care of the rest of the construction phase at a locked-in rate of 16.56 per U.S. dollar. All in all, we're happy with how the debt package is structured, since our finance team put in a great deal of work to obtain favorable terms while protecting the upside for our shareholders. We expect to finish the remaining $60 million draw in Q3, which lines up with the Terronera build being completed in Q4. Let me bring you up to speed quickly on how construction at Terronera is going. By the close of Q1, we hit an important milestone by getting past the halfway mark on construction, reaching 53% completion, and we saw progress both on surface construction and in underground mine development. As I noted earlier, we put $38 million toward development, which brings total spending to $158 million. Our project commitment is now $225 million, which works out to 83% of the $271 million capital budget. With work at the site moving ahead quickly, we've focused our efforts on installing structural steel, which is 80% done, and on major equipment installation for our upper mill platform. Because our quarterly reporting is quite thorough, I'll share a few recent highlights of progress. During the last year, we've stressed how important it is to speed up mine development rates to four meters per day for critical heading, a target we are steadily reaching so we can meet our production timeline.

Dan Dickson

executive
#7

During this quarter by itself, we finished more than 1,000 meters of underground mine development, which lifted our cumulative figure past 3,200 meters and keeps us positioned for first ore access in Q2. Most construction work has moved ahead nicely up at the upper plant site. At present, surface construction is 56% complete. Where procurement is concerned, our buying of bulk materials matches the construction timeline, so we can put many components in place as soon as they reach site, taking advantage of the project's lean footprint. Our COO has refined a just in time delivery framework that has demonstrated strong effectiveness while we hold firmly to ongoing safety measures. Because of your expanding site workforce, now numbering 550 employees and contractors, this quarter delivered further important milestones. These take in the successful setting of both the SAG and ball mills, placement of the regrind mill and flotation cells, and the start of installation for the crusher belt conveyors and apron feeders. Also, in Q1 we began excavation of the TSF embankment key trench in the lower platform area, and those are 60% and 45% complete respectively. Concrete work on the lower platform is expected to begin in Q2.

Dan Dickson

executive
#8

And finally, regarding community relations, we set up a new minor trainer program aimed at people in the local community, offering both training and employment. Should you wish to see photographs and video of the construction as it advanced, I'd suggest stopping by our website. There you'll find our current photo gallery displaying the newest developments, along with video shot in mid-March. Prior to starting Q&A, I want to emphasize that we understand our success over the long term extends past hitting financial metrics. Next week, we'll release our 2023 sustainability report, which addresses the steps we continue taking to mine responsibly and to help build a more inclusive, sustainable future for our business and our stakeholders. 2023 was the second year of putting our three-year sustainability strategy into practice, and we'll report on the progress achieved so far. I'd suggest you take the time to look at our new report once it's posted online. In addition, we're happy to announce the nomination of a new board member, Angela Johnson, at our 2024 Annual Meeting of Shareholders, which takes place on May 28. Her technical background and ESG experience fit exceptionally well with our current board members and assist us in meeting succession planning goals so that core board competencies and expertise remain in place.

Dan Dickson

executive
#9

That concludes my prepared remarks for today. Along with the rest of our management team, we're glad to answer any questions. Operator, please open the lines.

Operator

operator
#10

Our first question is from Lucas Pipes at B. Riley Securities. Go ahead, please.

Lucas Pipes

analyst
#11

Thanks a lot, operator, and good afternoon to all of you. Dan, I'd like to ask a bit about the Latin American exchange rate and how you'd anticipate it affecting both your expectations for operating costs and any effect on the capital cost side? Thanks so much.

Dan Dickson

executive
#12

Yeah, Lucas, good question. In the assumptions and guidance we used for 2024 through Q1, we did apply a 17:1 ratio, and in practice we're very near 17:1. What we expect is a Mexican peso rate of roughly 17:1. So operationally, we're staying with our guidance, which comes down to $14 to $15 cash costs, while all in sustaining costs we expect at 22 to 23. Clearly, in Q1 we're under that guidance, and I believe that reflects the gold price. Looking at our costs, direct operating costs per tonne are consistent with our plan. On the construction side, we signed $45 million of FX contracts. So we've essentially locked that in at 16.6. That means the impact for Terronera going forward would be muted as a result, but of course, as I said, I think the peso is going to it appears to be stabilizing here at 17:1. My expectation is that it stays there for the year.

Lucas Pipes

analyst
#13

Thanks, Dan. Nice work at Guanacevi. You mentioned silver grades came in a bit under plan, so my question is: when do you expect them to be more on plan, or perhaps above it? And with the plan in place, you went past the 1,200 tonnes per day mark — I'm curious whether there's more to do there. Thanks a lot.

Dan Dickson

executive
#14

Yeah, in terms of grade, we actually came in above plan for gold this quarter at Guanacevi, and we were a little below plan on silver grades. That's just typical fluctuation in the ore body, and we'd expect something comparable over the coming three quarters too. So we're a bit above 400 grams of silver and roughly 1.2, or just shy of 1.2 grams of gold. I'd say those grades are quite favorable, and that's what we're expecting for the year. When it comes to running 1200 tonnes per day through the Guanacevi plant, or going past our 1200 tonnes per day capacity, it's our hope that this continues. Obviously, we issued guidance based on an estimate of 1200 tonnes per day, but we did a great deal of work in the plant during 2023 refurbishing things, and obviously we have the capability to push beyond that 1200 tonnes per day, and now it all depends on the mine keeping pace. We don't want to get too far ahead of ourselves. At the same time, as I mentioned in my comments, Guanacevi has been very steady, and the expectation is that we'll easily hit that 1200 tonnes going forward.

Lucas Pipes

analyst
#15

Thanks a lot. Perhaps a quick question, and with the support of considerably stronger precious metal prices, how do you view M&A in the sector — either as a buyer yourselves or more widely across the ecosystem? Thank you very much.

Dan Dickson

executive
#16

Yes. I mean, from where we sit, the priority is to deliver on Terronera and bring it into production. I think if we can execute on Terronera by the end of this year, get commissioning done in Q4 and reach commercial production for 2025, that will be reflected in our share price. Now, you never say never — there are always opportunities out in the market place, and from our standpoint we want to see something accretive — but I don't believe the full value of Terronera is built into our share price yet, and again, I think that has to be executed this year for it to show up there, and more broadly, yes, we are seeing higher prices. Obviously, last year we saw margins get constrained simply because of higher costs, and I think that has percolated its way through the industry. I think cash is important. Obviously, there hasn't been a lot of capital available in our industry, and there need to be investments from an exploration standpoint and a development standpoint, which will create more opportunity for prices to increase, especially from a silver standpoint. I can't speak for the entire industry. I know as Endeavor, we want to be here 10 years from now.

Dan Dickson

executive
#17

We keep searching for development and exploration projects, but at this moment our cash and our workforce are focused on Terronera. We have only a limited amount of time and energy to devote to particular projects, and we are quite fond of our Pitarrilla project, which is coming along behind Terronera. So for us, I think we want to get through 2024 and then examine that landscape, and more broadly speaking, I think people will always be curious, and we always aim to build a bigger, better company.

Operator

operator
#18

Heiko Ihle from H.C. Wainwright has the next question. Go ahead, please.

Heiko Ihle

analyst
#19

Hi Dan and everyone, appreciate you fielding my questions — and I’m guessing you’re able to hear me fine?

Dan Dickson

executive
#20

Heiko, we’re able to hear you clearly.

Heiko Ihle

analyst
#21

Thanks, Don. Looking at the gold-to-silver ratio for the quarter, clearly, gold output rose quite sharply. In fact, gold performed so strongly that it had a fairly sizable effect on cash costs because of gold byproduct credits. Right now, we're midway through Q2 and gold is still at 23.30. Just conceptually, could you give us some guidance on whether you expect this to hold for the rest of the year, what the effect on cash costs would be, and whether you think this will fully offset the impact of the stronger Mexican peso?

Dan Dickson

executive
#22

Yeah, first off, the stronger Mexican peso is already factored into the guidance we gave, at 17:1 from the outset. So naturally, if the peso keeps appreciating, a higher gold price would offset that. Again, I believe the Mexican peso has settled down at this point. So ideally it holds around where it is now, since it makes up a meaningful share of our costs on the labor side — roughly 30% of our operating costs, which clearly are linked to the Mexican peso. On gold, as I mentioned earlier in my remarks, our gold grades came in slightly better than planned, and that's simply routine variation within the ore body. Where I believe there's upside is Bolanitos. Clearly, Bolanitos generates proportionally more gold output than Guanacevi does, and that lets us potentially move into certain other zones at Bolanitos that we couldn't access when the gold price was lower. So naturally, more gold output translates into a larger gold credit. Heiko, what we on the management team focus on is our direct operating costs per tonne. That covers the items we can manage — mining costs, processing costs, and the indirect costs, meaning our on-site G&A. Our target is to hit plan on that, and if we find ourselves in a stronger gold price environment, then of course that byproduct credit brings down our all-in sustaining costs and our cash costs, but we're — as I said, we try to control what's within our control, and that's the inputs feeding into our operating costs.

Heiko Ihle

analyst
#23

Okay, that's fair. And then a question on a longer horizon: your direct operating costs rose roughly 10% in the quarter. In the release, you attributed this to continuing ventilation and water management difficulties that hurt productivity. Clearly, none of that carries over to Terronera at all. And I was just looking at a few of the photos on your website, and it seems like this project is really taking shape, but then the release also notes that you're facing continuing inflationary pressures and costs that I'd imagine might eventually show up at Terronera somewhat. I mean, with commissioning at this point, Q4 isn't that far away. Should the analyst community begin factoring in some inflationary costs on that side, or should the current figures remain a solid baseline for where we ought to be?

Dan Dickson

executive
#24

Sure, Heiko, that’s a really solid question. We haven’t given operational guidance for Terronera since April 2023, when we made the construction decision. At that point, we released an optimized plan that featured a cost of $81 per tonne. That figure had decreased from the $87 per tonne in the feasibility study, thanks to economies of scale as throughput rose from 1,700 tonnes per day to 2,000 tonnes per day. That estimate was essentially prepared in December 2022 and January 2023. Since the beginning of 2023, across the industry and particularly in Mexico, the Mexican peso has appreciated by 15%. You’ve also seen inflationary pressure, especially on steel, reagents, and power costs, all within Mexico. So it’s quite reasonable to expect that operating costs at Terronera have escalated from $81, perhaps into the $95 to $100 range. We haven’t gone back and rebuilt those operational estimates. As we move toward production, hopefully later this year—commissioning is targeted for Q4—management will update those costs, and we’ll provide guidance to the market as we head into 2025. But again, if you simply consider what has occurred industry-wide and in Mexico, it’s fair to say those operating costs are higher than what we presented when we first issued that optimized plan.

Heiko Ihle

analyst
#25

Fair enough — that's a great answer, and a great quarter. Clearly, the stock is responding pretty well, and I'll get back in the queue.

Operator

operator
#26

Our following question is from Craig Hutchison at TD Securities. Your line is open.

Craig Hutchison

analyst
#27

Hey, everyone. Could you speak to how the remaining spend at Terronera is paced? I believe you mentioned 53% in March, with commissioning perhaps six to nine months out. My guess is that the spending you reported previously, roughly 2% to 3% each month, is going to pick up. But if you could just kind of explain how that spending will ramp up from now until commissioning?

Dan Dickson

executive
#28

Sure, Craig, that's a fair question. The reality is that we're hitting peak construction at the well during this month and next month, running through August. The main pieces are the upper platform — as I mentioned, steel work there is 80% done. So at this point we're moving into piping and electrical, and that's been progressing quite nicely with our contractor. Mine development is still on the critical path toward production. We reach ore in Q2, so during this quarter we anticipate ore beginning to come out of the mine. We've now cut across the vein, and from that perspective everything looks very good. So there's some added spend from that angle, and then the other key critical-path item is our tailings facility. For the tailings facility — what we refer to as the lower platform — that's where the dry stack tailings facility will sit, along with our concentrator and, eventually, our LNG plant. Our LNG plant is still running behind schedule. Concrete work is expected to get underway this quarter, and then vertical construction follows after that, obviously. What we expect is that the LNG plant — which accounts for 10% of production at 100% — will not be finished until 2025. That means we'll be running on diesel gensets when commissioning begins in Q4, but in the end, from that 2% to 3%, it's going to ramp up considerably, and as I said, I believe we've noted $225 million committed.

Dan Dickson

executive
#29

Much of that will get pushed through during this quarter and then into early Q3. So there's plenty happening, but procurement is really behind us now. At this point it's simply a matter of execution, and as we execute the embankment for the tailings facility — which has been going relatively well — we'll remain on track for commissioning in Q4.

Craig Hutchison

analyst
#30

All right, thanks. Maybe just to follow up on that point — my understanding is that LNG will be commissioned once more in 2025. What throughput are you able to operate the plant at using only diesel?

Dan Dickson

executive
#31

Right, the output from our diesel gensets will match that of our LNG plant, which comes in at just under 13 megawatts. So the plan is for everything to be up and running on those diesel gensets. What those diesel gensets will do is raise our operating costs relative to the LNG plant.

Craig Hutchison

analyst
#32

All right, thank you. So once you reach commissioning, roughly what kind of timeline applies before commercial production is achieved? In other words, how do you folks define commercial production, and how long do you expect that it will take to get there?

Dan Dickson

executive
#33

Right, I can't give you the exact definition — qualifying for commercial production, or getting into it, depends on a whole range of factors. Our initial estimate was 3 to 4 months. I think we believe we can accomplish that much faster than 3 to 4 months, but as we get closer and figure out where our bottlenecks sit, and if we're able to pre-commission part of the upper platform ahead of Q4, that would be ideal — though we'll provide guidance to the marketplace on that as we get near Q4.

Craig Hutchison

analyst
#34

All right, thanks. One final question regarding that second drawdown — could you remind me what milestone has to be met in order to access the extra funds?

Dan Dickson

executive
#35

Yes. At this point, what we'd say is that in April we secured $60 million, and as part of that there was a cash requirement held in your account — what we ultimately refer to as an overrun facility of $24 million. We need to build that up to $28 million, and then independent engineers will be making a visit on behalf of the lenders in late May, just to sort of provide an update and confirm that what's in our reports matches what's actually happening on-site — that's one of the conditions — plus a number of other smaller conditions that have to be completed as we move into that.

Operator

operator
#36

Our following question is from Robert Carlson at Janney Montgomery Scott. Kindly proceed.

Robert Carlson

analyst
#37

Excellent. Nice work on the quarter and the fast progress you've achieved up to now. One question, though: does your team make use of hedges?

Dan Dickson

executive
#38

Yes, Robert. So a gold hedge is mandatory under the terms of our lending facility, and that's what we put in place. We've therefore set up 68,000 ounces of gold, with delivery occurring across 2025 and 2026 and a small portion extending into 2027, and the price we locked in was $2,325 per ounce of gold. Beyond that, we don't hedge silver at all. Part of our mandate is ensuring that shareholders who invest in Endeavor Silver get the upside we anticipate from a silver price standpoint. On an inter-quarter basis, we'll put on very short-term arrangements, meaning under 90 days, though that's really just about capturing spikes in the silver price when they occur.

Robert Carlson

analyst
#39

So since you won't be joining until next year, there aren't any plans to set up a silver hedging program?

Dan Dickson

executive
#40

No, we don't have any plans for a silver hedging program. What we're witnessing in the silver market today, I believe, is a climate that will prove quite beneficial for silver prices. From the industrial side, demand has risen considerably thanks to solar panels, global electrification, and obviously the effort to cut carbon, but the monetary narrative around silver has trailed behind for roughly the past two to three years, and gold has clearly surged, ultimately reaching fresh all-time highs. Silver remains far below its $50 all-time high. Right now, obviously, we're at just above $28. So I think silver has plenty of runway ahead over the coming year or couple of years, and we want to preserve that upward price movement in silver for our shareholders.

Operator

operator
#41

Our following question is from Jake Sekelsky with Alliance Global Partners. You have the floor.

Jake Sekelsky

analyst
#42

Hi Dan, and thanks to the whole team for fielding my questions. To pick up a little on what was just asked, I want to return to the boost we saw this quarter from better gold byproduct credits, and even more so at today's prices. Is there a gold price level at which you would consider hedging some extra gold output beyond what the Terronera facility requires?

Dan Dickson

executive
#43

That's a reasonable question, honestly. My view is that precious metals still have considerable room to run, though that isn't something we'd seriously consider pursuing during this year. Naturally, given how much capital is flowing into Terronera, we need to safeguard the company's downside — and we believe the 68,000 ounces of gold already hedged for when Terronera reaches operations accomplish that. Across our other operations, Bolanitos and Guanacevi, we've turned out roughly 30,000 to 35,000 ounces of gold. We feel good about gold continuing to trend higher. Sure, there's always risk of a pullback, but our guidance forecast assumes $1840, including on a cash flow basis. Then again, perhaps once we reach Q3 we might sell a portion of gold forward, though we wouldn't go past the 90 days.

Jake Sekelsky

analyst
#44

Sure, understood. And regarding Terronera, could you briefly discuss the staffing situation there as we move toward commissioning later this year?

Dan Dickson

executive
#45

Sure. From a staffing perspective, all mine development is handled in-house by us. Our mining team, which is going to move from development over into operations, will remain steady and be completely ready on the labor side for the plant from an operational readiness angle. That process is already underway. We've brought people on for plant operations, and clearly on the indirect side we're fairly well staffed there too. So there really shouldn't be any major shift or big hiring push from now through Q4. There are individuals we still need to bring in, but operational readiness plans have already been in the works, which lets us execute well in Q4. Again, on the labor cost side, everything we've carried out this year operationally was done at 17:1 Mexico peso to U.S. dollar. Once we move into operations at Terronera, that's a comparable FX rate to what we'd apply for Bolanitos and Guanacevi — 30% of our cost ties to labor, and that's comparable for Terronera. Again, if we look back at the 2022 optimized plan, that would have been done at a 21:1 ratio. So today it sits at 17:1. That means you'd see higher labor costs operationally, purely because of the FX move.

Dan Dickson

executive
#46

Once more, as we move into 2025, we’ll share that extra level of detail with the market.

Jake Sekelsky

analyst
#47

Understood. All right, that's everything from my side. Appreciate it once more.

Operator

operator
#48

That wraps up our Q&A portion. Dan Dickson, I'll hand things back to you for any closing comments.

Dan Dickson

executive
#49

Thank you, operator, and I appreciate all of you joining us today for the release of our Q1 2024 earnings. Once again, I believe we've performed very well when it comes to simply carrying out our plan operationally. Executing on Terronera this year is our responsibility. We have the ability to deliver on Terronera across the coming two quarters. Commissioning ought to get underway for Q4 2024, and it will be great to watch that production profile join the Endeavor production profile for 2025. Thank you all, and have a good day.

Operator

operator
#50

Thanks, operator.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Endeavour Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Endeavour Silver Corp. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Endeavour Silver Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.