Endeavour Silver Corp. (EDR) Earnings Call Transcript & Summary
November 5, 2024
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line. I'm the conference operator speaking. You're joining us for Endeavour Silver Corp's conference call on the results of the third quarter of 2024. Please note that everyone attending is in listen-only mode, and this call is being recorded. Following the presentation, there will be a chance for you to pose questions. <<operator_script>>. At this point I'd like to hand things over to Allison Pettit, our Director of Investor Relations. The floor is yours.
Allison Pettit
executiveThanks, operator, and good morning to all of you. Ahead of beginning, I'd ask everyone to review the precautionary language in our MD&A concerning forward-looking statements, along with the risk factors tied to those statements. Both our MD&A and our financial statements can be found on our website, edrsilver.com. Joining us on today's call are Dan Dickson, who serves as CEO of Endeavour Silver; Elizabeth Senez, our CFO; and Don Gray, Endeavour's COO. Once Dan has finished his formal remarks, we'll open up the line for questions. Dan, the floor is yours.
Dan Dickson
executiveThanks, Alison, and hello everyone. The third quarter has been a busy one here at Endeavour Silver. With gold hitting fresh record highs and silver beginning to decline, higher prices ought to keep benefiting the company's cash flow and financial position. Operationally, Q3 delivered an unexpected challenge: the company ran at reduced capacity because of a trending failure of the primary ball mill at the Guana City mine. Temporary modifications wrapped up in August, which let processing carry on at about 50% of capacity. The estimated timeline to return to full capacity is still 15 weeks, and the mine should be fully operating next month. I want to thank our operations team for their dedicated work in mitigating the issue. Q3 silver equivalent production came to 1.6 million ounces, or 875,000 ounces of silver and 9,300 ounces of gold, tracking well toward the updated 2024 production guidance of 7.3 million to 7.6 million silver equivalent ounces. Silver equivalent grades have matched expectations, with gold grades a little higher and silver grades a little lower. We expect this to be similar going forward, and we expect the fourth quarter production profile to resemble Q3.
Dan Dickson
executiveDuring Q3, we made a lot of headway at Terronera. By September 30th, surface construction had hit 77%, and we've spent over $258 million so far. We can see the finish line now — Terronera is still on schedule for commissioning close to year-end, and we're thrilled that this transformative project will join our production profile in 2025. Turning to the financials, revenue came in at $53 million, an 8% increase year-over-year, helped by higher precious metal prices than in Q3 2023. Cost of sales was $41 million, down 12% from Q3 2023, mainly because we sold fewer silver ounces this quarter and because of cost management steps taken at Guanacevi after the trunnion failure, which also include ending third-party contract mining activities. Direct operating costs per ton and per ounce were higher, reflecting the reduced operating capacity at Guanacevi. Given that reduced capacity, management pulled cost guidance for 2024 back in August. For the three months ended September 30, 2024, the company posted a net loss of $17 million, versus a $2.3 million loss in Q3 2023. If you exclude certain non-cash and unusual items, along with items tied to volatility that aren't related to the company's operations, adjusted income was $1.6 million, compared with an adjusted loss of $8.3 million in Q3 2023.
Dan Dickson
executiveBy September 30, cash stood at $55 million and working capital came to $29 million. In the quarter, the company finished drawdowns totaling $25 million under the Senior Secure Debt Facility for Terronera, and after the quarter ended, it completed a final drawdown of $35 million. As I noted earlier, Terronera's overall progress hit 77%, with over $258 million of the project budget spent so far. Commitments on the project came to $270 million — 99% of the $271 million capital budget — and commissioning remains on track for near the end of Q4 2024. In the third quarter, 1,050 meters of underground mine development were finished, bringing the cumulative total to 5,550 meters, and the team kept advancing portals 1, 2, and 4. Long-wall stokes are being developed, along with an initial production plan for Q4. The underground explosive magazines were also finished, and the explosive use permit application has been submitted for approval, with approval expected in the New Year. On the upper platform, construction of the surface mill and infrastructure is 90% complete and continues moving toward operations. The Coarse ore stockpile reclaimed tunnel hit 100% completion, with pre-commissioning testing starting in Q3, and the primary jaw crusher was commissioned with ROC in August — a major project milestone.
Dan Dickson
executiveWork on the key trench for the tailing storage facility embankment is fully finished — 100% — while the secondary key sits at 40% completion. We've put up the structural steel columns and beams for the concentration filter building and the equipment mechanical structures, and that work stays on the critical path toward commissioning in Q4. As of September 30th, procurement stood at 99% complete, and the project team keeps driving toward pending arrivals. Finally, on community relations, backing from the local community remains a major commitment. During Q3, the company threw its support behind a range of local initiatives and investments — among them the inauguration of an early childhood development center, scholarships for university students in Santiago, municipal road maintenance, business entrepreneurship workshops for local residents, environmental education programs for primary schools, community tree donations, and summer community workshops for children and youth. For a full construction update at Terronera, I'd encourage you to check out our website, where you'll find the quarterly photo gallery showing the latest developments, progress, and information. With that, I'm glad to take questions. Operator, please go ahead and open our Q&A session.
Operator
operatorAbsolutely. At this point we'll move into the question-and-answer portion of the call. <<operator_script>> The first caller is Heiko Ihle of H.C. Wainwright. You have the floor.
Heiko Ihle
analystHi Dan, and hello to everyone on your team. I’m trusting that you’re able to hear me clearly?
Dan Dickson
executiveHeiko, we can hear you very clearly. Good to hear from you.
Heiko Ihle
analystThanks. Earlier today I went back over your October 21st press release about Terronera once more. I have a handful of follow-ups stemming from that release. You touched on a few of these already during this call. You said that you are bringing on and training staff. What number of people are on the payroll right now? And could you perhaps lay out a trajectory for staffing levels, with the timeline from today through to full employment at the site?
Dan Dickson
executiveWhen the site is fully operational, it will employ a little more than 500 people — that I can confirm. Right now, we have considerably more than 750 people on site. As a matter of fact, a second ship is on its way to assist us in getting through to the end of this year with respect to our tailings filter press. Regarding how far along the ramp-up stands at present versus where we will be once full operations are reached, I believe we have roughly 250 Endeavour Silver employees. And I think there are in fact 800 contract workers at the site working hard to get us to the finish line here.
Heiko Ihle
analystThose are impressive figures. To add to all of that—and again, you had some talking points and got ahead of part of this in your prepared remarks—are you seeing the community embrace all of this? I mean, there's still a fair amount of local job creation coming out of all of this. What are you seeing? Could you perhaps share some examples? And obviously, you're doing the scholarships and you're doing all sorts of things. Is it working? Are they embracing it?
Dan Dickson
executiveSure, I’ll say a little about that, and maybe hand it over to Don, since he’s on site more often than I am. But basically, we’ve had a community relations team at the site since 2013, which is when we actually bought the property. And I have to give credit to our explorations group — they did a fantastic job of building in things that would let the community gain from our mine, and of weaving those in alongside an understanding of what we’re doing at Terronera. I’d say across the past 4 or 5 years, our engagement with the community has been strong. Santiago de los Pinos, I think, will gain a great deal, and I think they’re very much involved. We’ve hired local people there and, in the end, created a lot of direct and indirect jobs for the community. As for the programs we run, it’s much like what we’ve always done at Guanacevi and Bolanitos. I mean, we see ourselves as neighbors, and being a good neighbor means you have to be part of the community and lend a hand wherever we can. Obviously, I mentioned a few in my remarks — tree donations, community support for different days, such as Day of the Dead. We’re always involved in that, and we’re always seeking ways to make ourselves part of the community.
Dan Dickson
executiveAs you know, a social license to operate is really the bedrock at Endeavour, and I expect that will remain true going forward. Don, I’m not sure whether you’d like to add anything, or mention other community programs we run that you view as highly beneficial.
Don Gray
executiveAs I believe I noted, our mill operators go through a training program that runs in phases. A lot of folks around the area lack experience, so we bring them in early for training. At the outset of the program, we had some open positions there. Then once word spread that the training was solid and the company meant business, every slot got filled. I'd call that a genuine tribute to our people, who built strong programs and engage with the community.
Heiko Ihle
analystThanks. Now a totally separate follow-up on another topic. Could you share some detail on how we ought to model G&A for the rest of the year, and perhaps for 2025 as well, presuming the share price holds at its current level, in light of the revaluation of the DSU liabilities — the cash-settled ones you ran into this quarter, please?
Dan Dickson
executiveRight, absolutely. I won't dive too deep into 2025, but at the end of the day, when you look at Endeavour's track record, our cash G&A has consistently run in that $8 million to $10 million range. On top of that, you'd layer in the DSUs and the mark-to-market on DSUs or stock-based comps. I can't see any reason our G&A would increase meaningfully in 2025 versus 2024, and my belief is that we're staying right in line with that $8 million to $10 million of cash G&A.
Heiko Ihle
analystThat's great. I'll follow up with you. Thanks a lot.
Dan Dickson
executiveHeiko, I appreciate you raising those questions.
Operator
operatorOur following question comes from Lucas Pipes at B. Riley Securities. The line is yours.
Nick Giles
analystThanks a lot, Operator. Nick Giles here, asking on Lucas's behalf. Dan and the team, congratulations on everything achieved at Terronera up to now. This may be one for both Dan and Don. I'd just really like a bit more detail on the ramp process, how we should think about timing, and in the end, what you'd view as the biggest possible bottlenecks along the way? Many thanks.
Dan Dickson
executiveThanks, Nick. I can lend a hand a bit here on Don's behalf. In the end, we're anticipating something like a 3-month ramp-up. We're hoping it moves a little faster, and I'll let Don speak to that. He has his expectations about where the bottlenecks might be, but I'm certain plenty of them are running through his mind.
Don Gray
executiveSure, that's typical. There are the usual startup items, and since a good portion of the upper platform is already finished, quite a few things can be pre-checked ahead of time. Our attention will be mainly on the concentrate and tailing filters in particular. We want to get a single circuit running really well first. After that, we can finish a great deal of the commissioning. So that's where we'll concentrate, and we believe we've brought in the right people and have the vendor support. We therefore expect it to proceed according to plan.
Nick Giles
analystDon, good to hear that, and thanks for the detail. With gold and silver where they are right now, do you have any fresh take on cash costs, or on sustaining costs?
Don Gray
executiveI believe, Nick, that what you want is the 2025 figure compared with <<inaudible>>?
Nick Giles
analystYou've got that right.
Don Gray
executiveRight. So our plan is that once commissioning and ramp-up are underway, we'll issue 2025 guidance early next year. Ultimately, we updated the feasibility study that came out in 2021. Great — before the build started, we're ultimately making our investment decision. And at that time our cost per ton was $81, and we fully understand there have been a lot of inflationary pressures over the last two years. And we've seen that at our existing operations Guanacevi and Bolanitos. As we work through all our budgeting and make sure our cost driver is right, it'll take a little bit of time, and we want to make sure we understand all the numbers and then the timelines for coming out with that. You can bear with us. We expect it to come out, like I said, in January, February of next year.
Nick Giles
analystThat's fair, and I appreciate it. If I could fit in one more, perhaps a question for Elizabeth. It would be great to hear your view on the target liquidity and cash on the balance sheet, right as Terronera hits full run rates.
Elizabeth Senez
executiveBy the close of September, as you observed, our cash stood at $55 million, and then clearly through October we've kept advancing construction at Terronera. What we're noticing, though, is that many of the prepayments we made to our vendors are now being drawn down against our work. Spending at Terronera has been decelerating, so we fully expect a steady cash picture as we head into 2025 and begin that ramp-up, with cash flows arriving at Terronera early in 2025.
Nick Giles
analystThat's really great, and it helps a lot. Dan, Elizabeth, and Don, to all three of you and everyone else on the team, keep up the good luck. Many thanks.
Dan Dickson
executiveAppreciate that, Nick. Those are solid questions.
Operator
operatorNicholas Clarke from TD Cowen has the next question. You're up.
Nicholas Clarke
analystHello, Dan and the team. Appreciate you fielding my questions. This is Nick Clarke speaking on behalf of Craig Hutchison. I have just one question, and if I could return to Terronera for a bit more clarity: given that roughly 99% of that $271 million budget is committed at present, would it be reasonable to view the remaining 23% on a fiscal completion basis as being covered by those commitments, or might there be a small gap there? Thank you.
Dan Dickson
executiveSure, glad to take that one. Elizabeth and Don are in Mexico at this moment. In the end, the $270 million committed and the $258 million spent take in prepays and advances that Elizabeth mentioned in response to Nick Giles' question. Ultimately, with what remains — and this is a very fluid question, since we have plenty happening on the LNG vaporization plant — we have stayed in the market. It will be ready in 2025, or open by the close of the first quarter, though commercial production could actually begin ahead of completion. We have the embankment at our tailings dam. Initially it was estimated at $40 million within that $271 million. We believe we can start up with a lower embankment. Naturally, we are striving to reach our percentage completion figure, or the actual expectation, and then mine development. Given that commissioning timeline, it is hard to pin down, but we do know we are in the ballpark. We are not issuing a commitment on precisely what our spend will be, but at present we are on a good track.
Nicholas Clarke
analystUnderstood, thanks. Just to be clear, 77% of $271 million works out to roughly $209 million — but that isn't meant to imply that you're $50 million short of where you'd been hoping to land?
Dan Dickson
executiveThat’s right.
Nicholas Clarke
analystThanks a lot — appreciate it, everyone.
Operator
operatorOur following question comes from Jake Sekelsky at Alliance Global Partners. You have the floor.
Jake Sekelsky
analystHi Dan and everyone, appreciate you answering my question.
Dan Dickson
executiveJake, I'm glad to answer whatever you'd like to ask.
Jake Sekelsky
analystCould you give us a little more detail on Guanacevi getting back to a steady state — perhaps on the timing, and any snags you anticipate as operations return to more normal levels?
Dan Dickson
executiveSure, I’ll be glad to hand that over to Don.
Don Gray
executiveAs Dan noted during his opening remarks, I believe our operating team performed quite well on the milling circuit and kept it running. In addition, they have done just as strong a job with the repair work, staying in close touch with the foundry, since we did need to have certain items assembled. That effort is proceeding as we had planned. I think we are in good shape. The contractor is already arranged for the moment the parts and components arrive. We do not anticipate any problems there.
Jake Sekelsky
analystAlright, that’s useful. Then, generally speaking, given where precious metals prices stand, I’m just wondering: does that lead you to take another look at any of the near-term or medium-term mine plans, or at how you’re approaching milling at Guanacevi?
Dan Dickson
executiveSure, that’s a fair question. We review this on an annual basis. We’re right in that window now, working through budgets for the mine plans and getting them finalized for the coming year. I’d say even at Terronera, it’s a moving picture depending on where prices sit. Clearly, our resource models show indicated ounces and inferred ounces. As Endeavour, with the underground mining we do, we’ve frequently incorporated inferred ounces and indicated ounces into the mine plans. At times, potential ounces aren’t even part of our resource. When prices are higher, that gives us the ability to go into certain areas that we might have abandoned previously. Again, we’re completing a resource update for 2024, year-end 2024, and we’ll put that out, likely in our MD&A or our information, but our AIF ultimately for year-end.
Jake Sekelsky
analystAll right, I appreciate it. That's everything from my side. Thanks once more.
Dan Dickson
executiveAppreciate those questions, Jake.
Operator
operatorOur following question comes from Stephen Soock at Stifel. You have the floor.
Stephen Soock
analystHey, Dan and the team. Congratulations on a solid quarter even with a few operational hurdles. Credit to everyone. I just wanted to ask about the underground at Terronera. Has any test mining happened, or is there an update on how the ore body and ground conditions are looking versus what was expected now that you're well into it? And maybe as a follow-on, how comfortable are you with the level of underground development in place now that we're just ahead of production starting?
Dan Dickson
executiveThat's a great question, Stephen. Don, would you like to take that one? All right.
Don Gray
executiveWe’ve built out a section for a test stope. We’re actually near the point of starting some blasting in that stope and pulling the ore out. The nice part is that this section will be a long-hole stope. Originally, in the feasibility study, that section was cut and fill. We’ve observed ground conditions in the veins that are better than what we expected from the feasibility study. So we’ve been reviewing that, doing a lot of rock mechanics work, and we believe there’s some upside there. On the development side, since we’re finding more areas that we’ll add to the mine plan as long-hole stoping, that relieves some of the pressure from so much development needed to get the cut-and-fill stopes ready. We’ll be in good shape.
Stephen Soock
analystThat's encouraging, and hopefully it keeps going. I realize that if you can reduce that life-of-mine development by using more long holes, it would have really favorable effects on your ASIC number. That's excellent. Perhaps shifting to a somewhat different topic, could you provide a brief update on the situation at Pitarilla and maybe just what to anticipate there through 2025 at a high level?
Don Gray
executiveThat's actually a really good question, Stephen. As part of what we originally guided for the year, we're going to invest roughly $5 million at Pitarilla to push forward an underground ramp that we had heading toward what we call our Manto Zone. And then we believe there are some feeder structures in that area. We've been drilling there for nearly three months now, and we should have news on Pitarilla out within the next few weeks to move that ahead. At the end of the day, we genuinely believe in what we have at Pitarilla. We think that what we bought from SSR Mining two years ago is a special asset. For anyone who isn't familiar with Pitarilla, we have 600 million ounces of Silver-defined Plus Zinc and Lead. Basically, we've been viewing Pitarilla as an underground operation, or the potential for one. As I said, we should have some news on that in the next couple of weeks. Great timing for that question, Stephen.
Stephen Soock
analystGreat. I’ll keep listening. That’s all for you folks. I appreciate the detail.
Don Gray
executiveI appreciate you sending those in.
Operator
operatorThat brings the Q&A portion to an end. At this point I'd like to hand things back to Dan Dixon, who may have some closing comments.
Dan Dickson
executiveMuch appreciated, Operator. And thank you to everybody joining us for the Q3 financial call. As I mentioned at the start of today's call, the quarter proved somewhat challenging where the trending was concerned. In my view, our operating team did a phenomenal job of mitigating that to the greatest extent possible. Terronera remains on track, and we're excited about what Q4 in 2025 has in store for the company. Thank you all for attending.
Operator
operatorThat concludes the conference call for today. Your lines can now be disconnected. We appreciate your participation, and we hope you have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Endeavour Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Endeavour Silver Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Endeavour Silver Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.