Operator
operatorWe appreciate everyone holding on. I’m the conference operator, and I’d like to welcome you to the Endeavour Silver call covering year-end 2024. <<operator_script>> This call is being recorded. <<operator_script>> At this point I’ll hand things over to Allison Pettit, our Director of Investor Relations. Please continue.
Allison Pettit
executiveThanks, operator, and good morning to all of you. Ahead of beginning, I'd like you to review our MD&A, which contains cautionary language about forward-looking statements along with the risk factors tied to those statements. Both our MD&A and our financial statements can be found on our website at edrsilver.com. Joining us on today's call are Dan Dickson, Chief Executive Officer of Endeavour Silver; Elizabeth Senez, our Chief Financial Officer; and Don Gray, Endeavour's Chief Operating Officer. Once Dan finishes his formal remarks, we'll open the line for questions. Dan, over to you.
Dan Dickson
executiveThanks, Allison, and hello everyone. As we kick off this year's earnings call, I want to take a moment to recognize the shifting conditions that defined mining in 2024. The gold price climbed 27%, finishing the year at $2,624 per ounce — the biggest yearly gain since 2010. Gold reached a record $2,786 per ounce in October and went above $2,900 earlier this year amid global tensions, worries about an economic slowdown and concerns regarding U.S. trade policies. Silver frequently follows gold's moves, and we anticipate that link will hold. Industrial demand and constrained supply have powered silver's advance. The worldwide push toward electrification, renewable energy and electric vehicles is fueling demand for silver in solar panels, batteries and key technologies. Meanwhile, supply shortfalls have appeared as new production strains to match mine depletion. Growing industrial demand and supply shifts keep exerting upward pressure on silver prices. We also anticipate that demand for silver as a safe haven asset will play a bigger role in the silver market down the road. Endeavour Silver is well positioned to gain from these favorable market dynamics. Now let's go into production in more detail. During 2024, Endeavour Silver generated 7.6 million ounces of silver equivalent, landing at the top end of the revised guidance range of 7.3 million to 7.6 million ounces.
Dan Dickson
executiveOur guidance was reduced during Q3 2024 as a result of a trunnion failure at the Guanacevi mine, and that affected throughput from August through December. The team put in tremendous effort to fix the problem, and by December, Guanacevi was back running at its normal rate of 1,200 tonnes per day. I want to express my heartfelt thanks to our operations team for acting quickly and effectively to get past this difficulty. Although Guanacevi faced its own issues, Bolañitos stayed consistent, with gold output rising on the back of better gold grades, which was partly offset by reduced silver production stemming from somewhat lower silver grades. For 2024, the company posted total revenue of $218 million, a 6% increase over 2023, alongside cost of sales of $176 million, mine operating earnings of $42 million and mine operating cash flow of $72 million. Endeavour recorded adjusted net earnings of $8 million, or adjusted earnings per share of $0.03, after excluding loss on derivative contracts, mark-to-market deferred share units, gain on disposal and unrealized foreign exchange and investment losses. Cost of sales rose roughly 4% versus the prior year. There are several factors behind this, among them reduced economies of scale from lower throughput, fixed costs incurred during the trunnion failure at Guanacevi and inflationary pressures early in 2024.
Dan Dickson
executiveWe did get a boost from the Mexican peso weakening during the latter half of the year. For the full year, direct operating cost per tonne rose 8%, largely because throughput at Guanacevi was lower. Consolidated cash cost per ounce, net of byproduct credits, fell 4% to $12.99 in 2024, mainly on stronger byproduct gold sales. All-in sustaining costs climbed 4% to $23.88 per ounce versus the prior year, again reflecting reduced silver ounce production, partly offset by the lower cash costs. At December 31, 2024, our cash position stood at $106 million, with working capital of $79 million. Both cash and working capital grew in Q4 after a $73 million bought deal financing intended to advance the Pitarrilla project and bolster general working capital. As a reminder, Pitarrilla is the company's next major growth project and is situated in Durango, Mexico. Globally, it ranks among the largest undeveloped silver deposits, holding nearly 600 million ounces of silver. A $26 million budget has been allocated by the company to advance exploration, evaluation efforts and underground development. That covers drilling and technical studies meant to support an economic assessment by Q1 2026. Although progress at Pitarrilla continues, bringing Terronera online in Q2 2025 remains the company's primary focus.
Dan Dickson
executiveBy December 31, 2024, construction overall at Terronera had hit 89%, and $302 million of the allocated budget had been spent. The company said earlier this year that the total estimated project cost comes to $332 million. In the fourth quarter, underground mine development totaled 1.7 kilometers, bringing project development to 7.2 kilometers overall. Approval also came through for the underground explosive magazine storage permit, which boosts development efficiencies. Construction of most of the upper platform was finished, with final punch list items still to be handled before handover to the commissioning operations team. The lower platform area remains the main focus, and it stood at 42% complete at the close of the fourth quarter. The tailings storage facility's main embankment hit 1,185 meters of elevation, the tailings filter swing plates were installed, and concrete was poured on the first floor. Structural steel installation moved up to the second floor, with preparations to install the filter press again as of the end of the fourth quarter. The event pond liner was installed and finished in January of this year, and the upper surface water diversion canal was almost 90% complete. As we get ready for the wet commissioning phase at Terronera and prepare to bring Endeavour's next operating mine online, key critical path items include the tailing filter presses, which remain on track for completion in mid-April.
Dan Dickson
executiveFor Endeavour, 2024 was a pivotal year, and 2025 was set to be a transformative milestone for the company. We sincerely thank our shareholders and stakeholders for their steadfast support as we begin this new era of growth and operational efficiency. As we move forward, we remain committed to delivering sustained value, achieving operational excellence, and fostering a sustainable future for all our partners. For a more fulsome construction update at Terronera, I encourage you to visit our website, where you'll find our quarterly photo gallery showcasing the latest developments, progress and information. With that, I'm happy to open this up to questions. Operator, please proceed to our Q&A session.
Operator
operator<<operator_script>> Our initial question is from Nick Giles at B. Riley Securities.
Nick Giles
analystCongratulations on everything you've accomplished. For my first question, I'd like to go in reverse a bit and begin with Pitarrilla. Could you remind us what CapEx looks like for 2025? And then how might we see that increase in 2026?
Dan Dickson
executiveYes. Great question, Nick. Thanks for the kind words. At Pitarrilla, as you probably know, our 2025 budget there is $26.6 million. In the end, the bulk of that budget breaks down as $10 million set aside for drilling, with $16 million going toward various budget or capital items such as mobile equipment, mine development, and additional evaluation and studies for an economic assessment we expect to deliver in Q1 of next year. Ultimately, our focus is on 2025. So no capital expenditure is planned for 2026 until we see that feasibility study finished. But as I mentioned, it is what we expect to be our next growth asset, and we fully expect a positive result from the economic assessment, though we can't really say much until we get there.
Nick Giles
analystThat's fair, and thanks for that, Dan. Maybe just turning to Terronera for a moment. Sorry if I missed this, but should we still be expecting commercial production in Q3? And beyond that, from a cost standpoint, are there any other puts and takes you'd flag for the rest of 2025?
Dan Dickson
executiveYes. Our budget remains at $332 million. Since the news release on January 8, which laid out a timeline pointing to early Q2, things have been going extremely well. We're on track for that, and we expect to go to wet commission at the end of April. So all of it is tracking well. Ramp-up should happen in Q2, and commercial production ultimately comes in Q3.
Operator
operatorWayne Lam from TD Securities has the next question.
Wayne Lam
analystI was hoping you could spend a moment on the cost pressures showing up in Mexico. I'd also like to know your overall exposure to the peso and how much of those pressures the recent softness in the local currency might offset.
Dan Dickson
executiveYeah, that's a really good question. Clearly, there's a great deal of worry globally at the moment, particularly in North America, with what appears to be a tariff war that has been getting underway. And we've fielded quite a few questions about the cost pressures this will create for our operations in Mexico, and then ultimately what that means from a currency perspective, and probably the expectation that you'll see further devaluation in the Canadian dollar and the Mexican peso. Looking at the Mexican peso, roughly 33% of our costs are tied to labor. And that has generally been the situation at Guanacevi and Bolañitos over the last 15 years, and we expect a similar ratio at Terronera. Of the remaining cost, the 67%, historically it's been roughly 50-50 between U.S. dollars and pesos, and that fluctuates back and forth. So approximately 50% to 60% of our costs are tied to the Mexican peso. And if we see additional devaluation of the peso, obviously that benefits Endeavour from a cost standpoint. On the supply chain side, we still don't know whether reciprocal tariffs would be put in place and what impact that has on cost. We don't believe it will have a significant impact because after labor, power costs, which obviously are incurred in country, are our second.
Dan Dickson
executiveCyanide is actually our third-largest expense, and we also bring that in from Mexico. So once more, everything is dynamic and circumstances will shift. But in the end, we have observed a general easing of cost pressures, mainly thanks to the Mexican peso's devaluation during the final 6 months of 2024. And should that trend persist, I believe it works in our favor on a cost per tonne basis.
Wayne Lam
analystAll right, great. And then perhaps regarding Terronera, what's the status of the e-house build-out? And on the tailings side, are the filter presses still the key constraint? And after that wraps up in mid-April, do you move straight into commissioning?
Dan Dickson
executiveYes. The e-houses have been installed. I don’t believe there’s anything further worth adding there. As you likely know, Wayne, there’s an LNG vaporization plant that we’re going to construct, and that ultimately will be in service in Q3. But once more, we’re running on diesel gensets during startup, up until that LNG vaporization plant is finished. You’re right, and the filter presses are indeed the bottleneck. That item sits on the critical path. Our concentrate filters are nearing completion here in March. And in the end, as for the filter presses, the structure and steel structures are already in place. So it truly comes down to electrical work and piping, and then finally energizing both filter presses and beginning to run ore from the crusher all the way through to that tailings dam. So just to remind everyone, as of December 31, our upper platform was more or less finished, and we were carrying out a great deal of dry commissioning and precommissioning, and it was the lower platform that in the end caused the delay and pushed us effectively into Q2 2025. Again, from January through today, March 10, progress has gone exactly according to plan. And the filter presses, which were the critical path at that time, remain the critical path at present, and they appear to be installing relatively smoothly.
Dan Dickson
executiveSo with any luck, come April, we’ll be able to get everything running and begin placing ore — as I mentioned — onto the tailings dam.
Wayne Lam
analystAlright, that's great. Perhaps just one final question from me regarding Guanacevi. Could you give us some sense of how the royalty structure differs between the ore from the mine and the El Curso concessions? And then, what share of the mill feed is that anticipated to represent this year?
Dan Dickson
executiveYeah. That's a really good question. For anyone who doesn't know what Wayne is asking about, El Curso is ultimately leased land that we signed for in October 2019 with Minera Frisco, a company owned by Carlos Slim. We pay a sliding scale royalty there. When silver was below $15, we paid a 4% NSR, and it scaled all the way up to over $25, which is obviously where we sit now, we pay a 16% NSR. So it's a very significant royalty. It's north of $55 per tonne, north of $5 per ounce of silver. And about 80% of our production is coming from El Curso. We still have our Malache area that we do source some ore from, and then we obviously have that purchased ore. So it's a significant part of our cost structure. And like I say, El Curso is over 80% of our actual production, Wayne.
Operator
operatorHeiko Ihle from H.C. Wainwright has the next question.
Heiko Ihle
analystGreat to hear about all the headway at Terronera. I'll start with my follow-up since it pairs nicely with the question that just came up. At Terronera, you're clearly at 89.4% as of December 31. Is there any item that still hasn't physically arrived on site? You brought up the filter press a bit earlier, though that's presumably a component built specifically for you. I mean, is anything held up in customs, anything that ended up in the wrong village? You noted electrical and piping are still required, but I'd guess that's probably mostly off-the-shelf items sitting in large boxes, just waiting, correct?
Dan Dickson
executiveYeah. No, that's a completely reasonable thing to ask. And on January 8, we issued the news release about our timing. And if you remember, there was a steel beam that wasn't at the site — we figured that out in December — and it arrived in early January. We went through the exercise of asking what else might be missing. Right now, we believe everything is either on site or sitting in our laydown yard, and honestly, that's what we thought back in December. So we've done that, ran a second check on it. And like you said, the piping and electrical work is fairly standard off-the-shelf material and it's moving along. So everything we needed to get done for that filter press is there. And once again, we're aiming for April to have it turned on so wet commissioning can begin.
Heiko Ihle
analystUnderstood. I reviewed your release this morning, and cash cost appeared in a lot of different places. I used control F4, and it showed up 21 times in that document. Clearly, costs looked pretty strong considering the gold credits. Your number was based on $2,647 gold, while we sit at $2,900 at the moment. That said, perhaps you could take us through cash costs as Terronera starts up in the very near future, both by quarter and for the rest of the year, as you see pricing on that side affecting your company's cash costs. What I'm getting at is this: take me through how we ought to model the ramp-up without putting you in a position where you have to state it outright.
Dan Dickson
executiveOkay, so I’ll address the first part — or really the second part — of your question, and it applies across the whole company. Back in January we issued guidance covering all-in sustaining costs and cash costs. Our assumptions included a gold price of $2,200. Clearly, if you use where we are right now, or even $2,800, that $600 gap multiplied by our 30,000 ounces of gold comes to roughly $18 million of credit. And at 7 million ounces produced, that works out to almost — or $2.5 to $3 lower than the guidance we stated. Now, we prefer to stay conservative with our guidance, and perhaps $2,200 was too conservative. But again, we began putting all of that together back in October and November of last year. So I believe Guanacevi and Bolañitos can do better than that. And the other piece of this, Heiko, is the Mexican pesos. Once more, we assumed 18:1. We’ve been above 20:1, and it looks like the peso will keep weakening from there. So for the existing operations — we’ve been there 19 years and 18 years, respectively — I think we have a really solid grasp of that. In our guidance we were fairly conservative. So that should let us likely perform better than that.
Dan Dickson
executiveThat's simply arithmetic, and it's fairly clear-cut. When it comes to how Terronera will ramp up, we're aiming to stay conservative there. And as we move into that ramp-up, we had planned to share additional specifics regarding, first, the production totals for 2025, since that really hinges on when commercial production is actually achieved — July or August. And from there, that determines the cash cost, our cost per tonne, and the pace at which we can ramp up. So we're deferring that, and the expectation is that we'll release it to the marketplace by the end of Q2. So I appreciate your question about where we'll stand at this moment, and I'll continue to reference the feasibility study, which indicated that essentially all the gold covers the silver at Terronera. Our cost per tonne will clearly be somewhat higher during the first year while we work through things. But once we reach our 10-year mine life, we anticipate costs aligning such that it will rank among the lowest operating mines in our space — the lowest cost operating mines in our space.
Operator
operatorOur following question is from Craig Stanley at Raymond James.
Craig Stanley
analystPitarrilla, you're putting together an economic study. What shape is it going to take — something like a PEA or a PFS? And are the findings going to be released to the market?
Dan Dickson
executiveYes, Craig, thanks for that question. Our aim is to move toward a feasibility study. We simply haven't encountered that yet. When SSR held the asset, there was a substantial amount of information from those days. As you're likely aware, the feasibility study they released concerned an open pit operation in 2012. Our perspective is from underground. And in 2009, they issued a pre-feasibility study. We're working through that evaluation alongside some of the technical studies currently underway. Then later in the year, we'll be in a position to truly determine whether we hold sufficient information to proceed directly to a feasibility study, but that is roughly what we expect at this point.
Operator
operatorThat brings the Q&A portion to an end. Dan Dickson, I'd like to hand things back to you for any closing remarks. Please go ahead.
Dan Dickson
executiveAppreciate it, operator, and I want to thank every investor who joined the call today. For Endeavour, 2024 turned out to be a really strong year. And when all is said and done, I believe we're positioned quite nicely heading into 2025 — to bring Terronera into production and, in the end, to capitalize on what we expect is ahead of us with the silver price. So, enjoy the rest of your day.
Operator
operatorThat concludes the conference call for today. Your lines can now be disconnected. We appreciate you joining us, and we hope you have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Endeavour Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Endeavour Silver Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Endeavour Silver Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.