Endeavour Silver Corp. (EDR) Earnings Call Transcript & Summary
May 13, 2025
Earnings Call Speaker Segments
Operator
operatorWe are standing by. The conference operator here. Welcome to the Endeavour Silver First Quarter 2025 Financial Results Conference Call. Please note that everyone is in listen-only mode and this call is being recorded. Following the presentation, you will have a chance to ask questions. To enter the question queue, press star followed by one on your telephone keypad. If you require help at any point during this call, you can signal an operator by pressing star then zero. At this time, I would like to hand the conference over to Allison Pettit, Director of Investor Relations. Please proceed.
Allison Pettit
executiveThank you, Operator, and good morning to all of you. Before we begin, I'd like to ask everyone to review the precautionary language in our MD&A concerning forward-looking statements, along with the risk factors related to those statements. You can find our MD&A and financial statements on our website, edrsilver.com. Joining us on today's call are Dan Dickson, CEO of Endeavour Silver, Elizabeth Senez, our CFO, and Don Gray, Endeavour's COO. After Dan delivers his formal remarks, we'll open up the call for your questions. Dan, over to you.
Dan Dickson
executiveThanks, Allison, and hello everyone. For Endeavour Silver, Q1 was a robust beginning to the year, with strong production numbers and ongoing advancement on important developments. With Guanaceví and Bolañitos delivering as planned and Terronera now generating concentrates as it nears the last phase of construction, we are closing in fast on a major milestone. This transformational asset, once added, will soon become a significant contributor to our production profile and represents a notable move forward in our growth strategy. During Q1, Endeavour turned out 1.2 million ounces of silver along with 8,300 ounces of gold, for a total of 1.9 million silver-equivalent ounces. Revenue came in at $64 million, consistent with the prior year, as we benefited from stronger precious metal prices. Direct operating costs per ton rose 6% versus Q1 2024, driven by throughput that was 6% lower, while total direct operating costs stayed roughly unchanged. The company recorded a net loss of $32.9 million for the period, mainly because of the unrealized non-cash effect of gold hedging and forward swap contracts entered into in March 2024. Those contracts, tied to the share of forecasted gold production from the Terronera project, were put in place as part of the senior debt facility that financed its construction.
Dan Dickson
executiveDuring the quarter, gold climbed from $2,600 to $3,100, and that loss stems from a mark-to-market accounting adjustment rather than any cash going out the door. Once you strip out mark-to-market adjustments, the company posted a modest adjusted loss of $200,000, versus income of $300,000 in Q1 2024. Cash costs came in at $15.89 per ounce of silver, while all-in sustaining costs were $2,448 net of gold credits — both a touch under annual guidance, mainly because of the higher bipartite gold credits. At March 31st, 2025, the company held $65 million in cash, with working capital of $15 million. Cash and working capital both declined from December 31, 2024, since the company kept putting money into development activities at Terronera. Terronera is now in the final stages of construction and began producing its first batch of concentrates at the end of Q1, and per our latest news release on May 6, commissioning is currently underway. Terronera is a game-changing opportunity for Endeavour Silver and is set to redefine the trajectory of our company. As we get closer to commercial production, we remain excited about the transformational impact this asset will have on our business. With a projected mine life spanning well over a decade, Terronera will be a long-term cornerstone asset in our portfolio, underpinning our growth strategy and reinforcing our position as a leading mid-tier silver producer.
Dan Dickson
executiveAs the commissioning phase moves forward, focus will be placed on raising fees and run times and ramping up to full throughput. Operational guidance will be provided by the company as ramp-up advances. On April 1st, we announced the acquisition of the Kolpa mine in Peru, and on May 1st, we closed that transaction. We're excited about the addition of Kolpa to Endeavour's operating and growth pipeline as it significantly enhances our current production profile with significant exploration upside and existing infrastructure for a long mine life. Kolpa represents a compelling opportunity where we can leverage our proven technical expertise and development capabilities. The project aligns with our existing operations and supports our strategy of building a scalable silver-dominant asset base. The company is working towards validating and updating the historical resource estimate prepared by the previous owners. In the meantime, using Kolpa's 2024 annual production of 5 million silver-equivalent ounces as a guide and with Terronera expected to come online in the near term, we are well positioned for a significant step change in production. When combined with our two producing assets, Guanaceví and Bolañitos, Endeavour is on track to achieve annualized production of approaching 20 million silver-equivalent ounces. With that, I'm happy to open up to questions.
Dan Dickson
executiveOperator, let's move on to the Q&A portion of the call.
Operator
operatorThe Q&A portion is starting now. If you'd like to ask a question, press star followed by one on your phone's keypad. A tone will confirm your request when it registers. Should you be on a speakerphone, lift the handset first, then press your keys. And if you want to pull your question, press star followed by two. Our opening question is from Nick Giles at B. Riley Securities. Go right ahead.
Nick Giles
analystThank you, Operator, and good afternoon, everyone. Dan and team, congratulations on all the progress this quarter. It's really good to see. My first question is just on Terronera. I think you said you'll provide guidance as the ramp-up advances. My question is, what do you ultimately need to see in the ramp to have the confidence to come out with something more formal, specifically on the cost side?
Dan Dickson
executiveYeah. I mean, the biggest factor is really going to be production and throughput — we need to confirm we're achieving steady throughput through the mill and right through to the filter press. That gives us confidence in the ramp-up timeline. In the end, our planned ramp-up is quite short, roughly 90 days, and that could be plus or minus those 90 days. Given that uncertainty, we don't want to issue production guidance until we have a higher probability of knowing how many months we'll be operating at Terronera. It doesn't make much sense to tell the market six months if we're only going to run for five months, or if we're at six months, we're going to be at seven months. That's the first and foremost item, the production guidance. After that comes cost and the cost impact. Obviously, in the first three to six months of commercial production, we'll be processing lower-grade ore than what would be deemed in our long-term mine plan, just to make sure we're getting through all the bugs. We just want to go through that once we understand grades and ultimately the timeline that we'll be offering for 2025, and then provide guidance around costs with that.
Dan Dickson
executiveNaturally, when it comes to 2026, we’ll be providing operational guidance along with costs at the other mines.
Nick Giles
analystDan, I understand all of that, and I appreciate the remarks. As a quick follow-up, though: wet commissioning appears to have gone smoothly so far, but what would you say are the closest-term priorities simply to make sure the ramp remains on track, particularly at the plant?
Dan Dickson
executiveYeah, I’ll pass that over to Don. Before I hand it off to him, though, I’d say with wet commissioning it’s difficult to predict how well it will go, since that process starts and stops. In the end, some days it feels like progress is being made, and on other days you take a pause. I think that is simply how commissioning works. There are punch list items you have to complete, but when it comes to the specifics of what is needed, I’ll leave that to Don.
Don Gray
executiveYeah. Nick, thanks for asking. To keep things on track, the team at that site is really concentrating on taking it system by system — you begin at the top of the plant and move down toward the bottom. That is exactly what we have been doing up to now. We have had the mills running, operating the mills and inspecting each system, confirming that bearings and clearances and similar items are working properly. We have only just begun introducing water, and soon the tailing into the tailing filter section, and that will truly get everything moving. It is simply a matter of progressing down through the system.
Nick Giles
analystThanks, Don. That's really useful. Folks, one more question if I may. Nick, just to refresh my memory, what does capital intensity ultimately come to at Kolpa? For the throughput expansion going from 1,800 tons per day up to the 2,500 level, what is the capital intensity?
Don Gray
executiveYeah. Right now, just based on early estimates, the work that the predecessors had previously done would run anywhere from $12 million to $16 million in order to go from 2,000 to 2,500 tons per day of capacity.
Nick Giles
analystUnderstood. All right. That's very clear. Everyone, once more, congratulations on what you've accomplished, and keep it going.
Dan Dickson
executiveAppreciate the questions, Nick.
Operator
operatorWayne Lam from TD Securities has the next question. You have the floor.
Wayne Lam
analystYeah. Thanks, guys. Sorry, perhaps just a single follow-up about that earlier ramp-up window. Could you clarify that 90-day ramp-up? Does that 90 days begin when you started wet commissioning, or could you just spell out which specific timeline period you mean?
Dan Dickson
executiveYeah. That would start May 1st. We released it on May 6th just to keep things simple — May 1st.
Wayne Lam
analystOkay, great. Now, regarding what it will cost to finish the 332 at Terronera, it appears you have roughly $7 million left in the guided spend. Does that figure cover everything through commissioning and the ramp-up phase, or I’m wondering whether we ought to factor in a modest increase in the funding requirement as you continue ramping up?
Libby Senez
executiveHi, Wayne. It's Libby Senez here. Regarding your question about how much is left to finish and the build cost — yes, you've got that right. Compared with the total we guided to, we're roughly $10 million short, and we don't expect much more spending to be added to that build cost. When we're in the operating phase, or while ramping up, every one of those costs counts as an operating cost and gets folded into the cost of the inventory rather than being treated as part of the project's build cost.
Wayne Lam
analystOkay, great, thanks. Perhaps just one final question about the balance sheet. How comfortable are you folks regarding the cash balance and the working capital needs required to fund Terronera through ramp-up? I'm just curious how you're thinking about the flexibility here on the balance sheet and whether there's potential to refinance quickly once commercial production has been declared?
Dan Dickson
executiveSure. There are a few in there. I mean, whenever you're ramping up and going through commissioning, there's plenty of uncertainty. Obviously, having a cash balance of $65 million at March 31st feels healthy. At the end of the day, working capital sits at about $15 million. We're in that stage of the project that's high stress, high anxiety, and pushing to get there so we don't run too low on cash. That's something we'll be watching very closely over the next two or three months to see how ramp-up is going and where cash balances are. As for when we reach commercial production and what we do with the project loan facility, and again, that's the overnight rate plus 4.25% right now as well as the 3.75%. We're always looking to lower our cost of capital. Obviously, it completely changes the project because it's now de-risked and in operations. As a management team, our job is to find the best cost of capital and, along with that, to make sure we have sufficient liquidity to get through what we need to get through. Obviously, Guanaceví and Bolañitos right now are generating cash flow for us.
Dan Dickson
executiveAs I mentioned, we've reached the most demanding phase of construction, and we're nearing the finish. Clearly, the faster we can begin commercial production, the better it will be for Terronera and, in the end, for the company.
Wayne Lam
analystAll right, that’s great. I appreciate you answering my questions, and I hope the ramp-up over the coming month goes really well for you.
Dan Dickson
executiveThanks, Wayne. I appreciate you asking those.
Operator
operatorOnce more, should you have a question, press star followed by one. Our following question is from Heiko Ihle at H.C. Wainwright. You may proceed.
Heiko Ihle
analystHello Dan and everyone. Appreciate you taking my questions. To follow up on the remarks you prepared earlier and the initial question raised during the Q&A portion before this, is there still a significant amount of cash flowing into Terronera during Q2? If that's the case, could you provide your best estimate of how much is being shipped there in Q2 and what those funds are being used for?
Dan Dickson
executiveYes. We’re continuing to spend in April. We were putting money in down there so that everything could be finished and so that we could move into commissioning. Libby mentioned a bit of that as well. What’s different in accounting terms is that, in the end, revenues get recognized on the income statement, and cost of sales get recognized on the income statement. Clearly, as we go from zero tons, hopefully up to 2,000 tons, we’ll record a loss here in Q2 while we’re commissioning. We no longer capitalize that, and there is cash going out. Unfortunately, April data isn’t ready and complete, so I don’t want to say precisely how much cash we sent down in April. We did keep funding in April. Now that the whole plant is essentially finished, with the tailings press in there, it’s mainly instrumentation and working through commissioning. There are still costs being incurred for that. Clearly, costs will also be incurred as we finish up various small items, but the major spending has been done. Hopefully, it has slowed down, and now it’s mainly about commissioning as we move into operations.
Heiko Ihle
analystThat's a solid response. Of course, since I drafted these questions before entering the queue, I'll need to tweak things a bit. Turning to something entirely different—Kolpa—and just out of sheer curiosity, it's clearly a massive operation spanning 25,000 hectares of claims. In the press release about the deal, there was a small detail noting that work has covered just 10% of the claims so far. Could you take us through a few of the higher-priority targets lined up for this year and even past that, now that the transaction has officially closed?
Dan Dickson
executiveYes. I mean, at Kolpa we once more have a sizable budget, and it came from what their predecessors had been working on. Between October and December, those predecessors uncovered a new vein they named Puerto Rosa. That discovery wasn't part of our historical resource estimate. Our exploration team has only just arrived on the ground, and we're trying to assist the Kolpa team with the exploration plans they've put together. In my view, they've done a phenomenal job with mining at the Kolpa asset. They've also done a phenomenal job growing it. Where we believe we can be of help to them is on exploration — the work we're able to carry out there. One main structure accounts for roughly half of Kolpa's production. We see opportunities for further structures of that kind, and maybe Puerto Rosa is one of them. Effectively we have a $12 million exploration program covering the next 24 months, or 24 months starting from when we acquired it. There are also tension veins that branch off the main structure, which the predecessors again discovered recently, and we've been working on those. At the moment, over the near term, we'll keep concentrating on some of these veins that they were working on before, and our exploration team is going to step back, examine some brownfields opportunities, and search for surface markers using geochem work, trenching work and geophysics, so we can try to identify some of the more significant structures.
Dan Dickson
executiveThere are numerous veins, and plenty of historical workings. It's quite comparable to the volume at Bolañitos that we moved to 20 years ago, where we can apply exploration methods and know-how and ideally find additional resources. I'd note that a historical resource of roughly 118 million ounces exists. We're working to validate it and, eventually, to expand from that point. We do have time. A mine plan is already in place on their side. Before we comment too much, we simply want to dig further into the data and verify a great deal of the historical work they've completed. To meet our own standards, we'd feel more at ease discussing it, Heiko.
Heiko Ihle
analystMuch appreciated for that. I'll hop back into the queue, and thanks once more for the response and for a solid quarter.
Dan Dickson
executiveThanks, Heiko.
Operator
operatorThat wraps up the Q&A portion. Dan Dickson, I'll hand things back to you for any closing comments.
Dan Dickson
executiveThanks, Operator, and I appreciate everyone joining us for our Q1 session. As most of you probably are aware, Q2 will be a very significant quarter for us. Clearly, we're highly focused on getting Terronera ramped up and into commercial production as quickly as we can, and we look forward to our Q2 earnings call in July or August. Thank you.
Operator
operatorThat concludes the conference call for today. Your lines can now be disconnected. We appreciate your participation, and we hope you have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Endeavour Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Endeavour Silver Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Endeavour Silver Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.