Evolution Mining Limited (EVN) Earnings Call Transcript & Summary
April 15, 2026
What were the key takeaways from Evolution Mining Limited's April 15, 2026 earnings call?
Evolution Mining Limited reported its March 2026 quarterly results, marking a significant milestone by transitioning to a net cash position, driven by $406 million in group cash flow. The company produced 170,000 ounces of gold and 11,000 tonnes of copper, with an all-in sustaining cost (AISC) of $2,220 per ounce. Management reaffirmed FY '26 production guidance and lowered AISC guidance by 6% to $1,640-$1,760 per ounce. The stock could be positively impacted by the company's strong cash flow generation and reduced debt, alongside ongoing exploration success.
What topics did Evolution Mining Limited cover?
- Net Cash Position: Evolution Mining achieved a net cash position with over $40 million, aided by $406 million in cash flow and a cash balance of $1.37 billion. This marks a rapid de-leveraging from over 30% gearing in two years.
- Production and Costs: Gold production was 170,000 ounces and copper 11,000 tonnes at an AISC of $2,220 per ounce. Management expects to meet FY '26 production guidance with a reduced AISC of $1,640-$1,760 per ounce.
- Exploration Success: Encouraging exploration results at Mungari and Cowal suggest potential for extending mine life and increasing resources. Management highlighted new high-grade discoveries at Genesis and Oban.
- Operational Challenges: Weather events impacted Ernest Henry's production, causing it to be cash flow negative for the quarter. However, operations have returned to normal.
- Future Growth Projects: Projects like E22 coarse particle flotation and Bert deposit development are progressing well, indicating future production growth and mine life extension.
What were Evolution Mining Limited's April 15, 2026 results?
- Net Cash Position: $40 million (Achieved from over 30% gearing in two years)
- Gold Production: 170,000 ounces (In line with expectations)
- Copper Production: 11,000 tonnes (Expected to be at the low end of guidance)
- All-in Sustaining Cost (AISC): $2,220 per ounce (Higher due to lower copper credits)
- Cash Flow: $406 million (Strong cash generation)
Evolution Mining's transition to a net cash position and strong cash flow generation are positive indicators for the stock. The company's ability to manage costs and maintain production guidance despite operational challenges is commendable. Investors should watch for further exploration results and any changes in cost structures due to inflationary pressures as potential catalysts or risks.
Earnings Call Speaker Segments
Operator
operatorAt this point I'd like to turn the conference call over to Mr. Lawrie Conway, our Managing Director and Chief Executive Officer. He has the floor.
Lawrie Conway
executiveThanks, Ashley, and good morning, everyone. On the call with me today are Matt O'Neill, our Chief Operating Officer; Glen Masterman, our VP Discovery; Fran Summerhayes, our CFO; and Peter Roiko-Connor?, our GM Investor Relations?. We published our March quarterly report and an exploration update today, and those documents will serve as the reference points for this call. A major milestone and the standout item for the quarter was moving into a net cash position, helped by yet another strong quarter. Having generated $406 million in group cash flow at just under $2,500 per ounce, we now hold a net cash position of more than $40 million. Our cash balance stood at $1.37 billion at quarter end, and no debt repayments fall due until FY29. This swift deleveraging — going from over 30% gearing to net cash in just over 2 years — shows Evolution's high-margin portfolio delivering consistently, making sure the benefits of the strong metal price environment get banked. For context, we have eliminated roughly $1.7 billion of net debt? at average achieved gold and copper prices that sat $2,100 per ounce and $3,200 per ton below current spot prices, all while continuing to invest in high-grade projects and paying dividends to our shareholders.
Lawrie Conway
executiveWe remain on schedule to produce roughly $3.6 billion in operating mine cash flow during FY26, and the June quarter is designed to push our net cash position even higher. Page 1 of the quarterly report contains charts that graphically capture quite well how much cash we can generate and the momentum we are building, even as we put money into high-return projects that either increase output or lengthen mine life. This result reflects credit on all at Evolution who keep safely delivering the plan with appropriate discipline on cost and capital. During the March quarter, output came to 170,000 ounces of gold plus 11,000 tons of copper, at an all-in sustaining cost of $2,220 per ounce for continuing operations. That higher all-in sustaining cost in the quarter stemmed from reduced production and, above all, smaller copper byproduct credits at Ernest Henry. We completed the quarter safely, with our TRIF still low at 5.9. The March quarter had been anticipated to be one of lower production because of the weather event's impact at Ernest Henry in December and the semiannual maintenance work at Cowal that was planned. Ernest Henry has returned to normal operations at this point. As a consequence of the weather impact at Ernest Henry, we anticipate landing around the low end of group copper guidance.
Lawrie Conway
executiveWe're still on schedule to hit FY26 group production within our all-in sustaining cost guidance range of $1,640 to $1,760 per ounce. That AISC guidance sits 6% lower — or better — than what we originally guided. Group cash flow came in at $769 million, with operating and net mine cash flows of $486 million respectively. Worth noting these results were delivered even though Ernest Henry was cash flow negative during the quarter. Mine cash flows should rise substantially in the June quarter, and we're on track for that. Every one of our projects is proceeding according to plan and within budget. The E22 project, coarse particle flotation, and the expansion study projects — all recently approved — have made solid progress over the first 6 weeks, and at Ernest Henry, preparations are underway to begin development of the Bert deposit. A few remarks from me on the global fuel supply picture as it stands today. So far, we've seen no material operational impacts — and that applies not only to fuel but to our consumables overall. Matt and Fran are managing our supply chain logistics actively, and suitable response action plans are in place. The team's bigger focus is on making sure supply of all goods and services continues without interruption. On fuel specifically, our supplies are under contract with major oil distribution companies, and those companies keep meeting their obligations.
Lawrie Conway
executiveFuel accounts for 2% of our total costs, and although prices are elevated right now, it isn't materially affecting our cost base. Glen and I are really excited about what today's exploration results offer when it comes to adding low-cost ounces to the portfolio. They demonstrate that at Mungari and Cowal, both already long-life operations, there is considerably more gold waiting to be discovered. Among the key highlights are the highly encouraging results from the underground areas of Genesis and Arctic at Mungari, which back our goal of extending the high-grade underground mine life at current production rates. At Cowal, meanwhile, we received significant high-grade results at the Oban underground target. At the same time, significant new results from multiple locations throughout the planned E41 open pit will give us helpful insight into the deposit's full scale before development. Regional exploration around Ernest Henry is going to be accelerated over the next 6 months, now that we've consolidated the large tenement holdings surrounding the mine. We've also begun work on the two most recent projects in British Columbia. With that, I'll hand things over to Matt, who will take us through the operational performance.
Matt O'Neill
executiveThanks, Lawrie. As Lawrie said earlier, operational performance in the March quarter came in according to our plan, following the rain event at Ernest Henry in December and the scheduled plant maintenance at Cowal. Safety performance is still in a very healthy spot, with continued strong results in this area thanks to tireless work happening right across our business. I want to take this chance to thank all our employees warmly for contributing to that every day. On production, we remain on track to achieve full-year guidance for gold and to finish at the lower end of guidance for copper. The biggest operational milestone during the March quarter was the return to normal operations at Ernest Henry, and for me, the standout aspect of this team's work was that it was done with no significant injuries or incidents. Across the March quarter, the Cloncurry region kept seeing rainfall above average, which slowed our recovery activities and led to further impacts on full-year production at Ernest Henry, now estimated at between 9 to 11,000 ounces of gold and 6 to 8,000 tons of copper.
Matt O'Neill
executiveAt Cowal, wet weather also affected the completion of mining stage H in the E42 pit. On a positive note, the processing plant ran without interruption, with extra feed coming from surface stockpiles during those weather events. We also finished the regular plant maintenance program at Cowal on schedule. As we head into the June quarter, we will be mining the last ore from stage H, and as previously advised, we will then move to the stage I cutback and be processing stockpile ore in FY27. That will see Cowal producing roughly 10% lower ounces next year. However, importantly, we will not see a material change in cash flows from the processing of the already mined ore. Northparkes, Red Lake, and Mt Rawdon all performed in line with expectations, with the quarter's highlights at these operations being the approval by the board of the growth projects at Northparkes; the cash flow generated at both Red Lake, which was a record $104 million for the quarter and nearly $225 million year to date, and at Mt Rawdon, which was $13 million in the quarter and over $30 million year to date from processing very low-grade stockpile material. Mt Rawdon is planned to complete processing at the end of this financial year.
Matt O'Neill
executiveOver the quarter, Mungari set a whole series of new records, and the mill, now fully commissioned, ran at nameplate capacity for the entire period. Standouts among those records include quarterly net mine cash flow of $175 million and gold production of 51,000 ounces. So far this year, Mungari has brought in more than $320 million in net cash flow, which confirms the choice to put money into expanding the plant and establishing the Castle Hill mining hub. As we look ahead, we're in good shape for a solid final quarter: Ernest Henry is coming back to normal operations, Mungari keeps performing strongly, and Cowal has finished its annual maintenance program and is mining again in stage H. I'll hand things over now to Glen, who will walk through the exploration announcements we made this morning.
Glen Masterman
executiveThank you, Matt, and good morning to all of you. I'd like to direct everyone's focus to the exploration announcement we put out this morning as well, which provides a quick update on the strong momentum we've experienced during the past 6 months. Beginning with Mungari, I want to briefly go back over a few of the remarks I offered when we last reported our drilling results. The team's recent accomplishments have fundamentally reshaped how we view the historical geological thinking surrounding Kundana, which had mostly dismissed the possibility of meaningful new discoveries, especially outside the familiar high-grade tram track positions. By pushing back against that longstanding geological dogma, we have cut high-grade veins in fresh structural settings beyond where the traditional models had been focused. This matters because it has effectively shattered the old paradigm and unlocked entirely new search spaces across Kundana. Practically speaking, that hands us a considerably larger opportunity to keep expanding high-grade underground resources and reserves. The strongest illustration of this is at Genesis, where drilling has focused on extensions of a known system that we discovered, which appears in Figure 1 of the update. Infill drilling spanning a 300 m gap running north toward the Barkers Mine, an area that previously had no drilling at all, recently delivered narrow intervals but with very high grades, among them numerous short intervals grading above 10 ounces to the ton, producing intercepts better than 90 gram-meters, and confirming that mineralization runs continuously through this zone.
Glen Masterman
executiveEverything I'm about to describe sits beyond the mineral resource footprint, and — this matters — close to infrastructure that already exists underground. That carries genuine consequences for how long the mine can operate. Over at the Arctic deposit nearby, drilling from surface below the open pit has turned up high-grade results as well. Those results extend earlier reported work and keep showing there's room to grow the underground resources, especially at depth, where past drilling was scarce. Follow-up drilling now underway is meant to define how large these mineralized systems are, how continuous they are, and what shape they take, with the explicit aim of turning them into a long-term underground reserve — locking in high-grade output across a longer mine life and able to hold at or above the 200,000 ounces per annum annualized rate we achieve today. Moving on to Cowal, where step-out drilling featured in Figure 2 of the release has proven just as encouraging. We recently got results from surface drilling at E41, which, as a reminder, sits a few hundred meters south of E42 and will be mined as part of the open pit continuation project. This morning's released results delivered broad, consistent intercepts outside the planned E41 pit's outline. What stands out is that drilling across the mineralized veins rather than along them, as a lot of the historic drilling did, is unlocking zones that people had regarded as well tested before.
Glen Masterman
executiveThat points to obvious room for expanding the E41 footprint, especially northward in the direction of E42 and the underground mine. I'd also note that the E41 pit geometry shown in Figure 2 was optimized using a highly conservative gold price assumption of $1,760 per ounce. At Oban underground, the results keep adding to our confidence. The drilling is aimed at major mine-scale structures as well as a favorable geological contact that, elsewhere at Cowal, is known to host high-grade mineralization. Importantly, recognizing this key contact — illustrated in Figure 3 on page 4 — has opened up a completely new search space to the north and south between the E42 pit and the Glenfiddich Fault, an area that has barely been drilled at all. We've gotten multiple high-grade intercepts that back the potential for Oban to develop into a new independent mining front over time, and a geological position where I'm confident that further work will lead to delineation of future resources and consideration in the mine plan in the years ahead. That's going to be a major focus going forward. Beyond the operations, we're also continuing to build out our longer-term pipeline. In North Queensland around Ernest Henry, we've grown our land holding and identified several drill-ready copper-gold projects, with an aggressive drilling program planned across the June and September quarters.
Glen Masterman
executiveUp in Canada, at Cue, Thomas Fred, and Clesbacco in British Columbia, permitting work and community engagement are both moving forward, and drilling is set to take place throughout the summer field season. At the same time, at the October Gold project joint venture in Ontario, drilling is currently running, and we expect assay results later in the June quarter. Taken together, these results show our discovery strategy in action: we keep unlocking value in the short to medium term at our operating assets, while also building a strong pipeline of drill-ready and more advanced exploration plays that could deliver new greenfields production opportunities in the medium to long term. With that, I'll hand the call back to Ashley to open the line for questions.
Operator
operatorThanks. Should you want to pose a question, hit star one on your phone and hold until your name is called. To withdraw that request, hit star two. In case you're using a speakerphone, kindly lift the handset before asking. Our first question this session is from Hugo Nicolaci at Goldman Sachs. Go right ahead.
Hugo Nicolaci
analystGood morning, Lawrie, Matt, Glen, and Fran. I hope everyone is doing well. My first question concerns Mungari. During the quarter, you exceeded nameplate capacity. I just wanted to understand how much of that reflects softer ore being processed, or whether you are already identifying chances to begin raising that nameplate a bit?
Lawrie Conway
executiveThanks, Hugo. I'll pass it over to Matt. I put the same question to him: why aren't we proceeding at the higher rates, but it is ore.
Matt O'Neill
executiveYeah, it is. Those figures make it pretty clear. What's driving that rise is partly the transitional ore, or the easy-to-process material, coming from Castle Hill. Having said that, this is clearly something we'll be going after, though right now it's operating at nameplate capacity with the design feed we're putting through it.
Hugo Nicolaci
analystThanks, that's useful. Moving to my second question, which may have two parts, about exploration. Clearly, you released some exciting drilling results today. First, when should those begin showing up in resource updates? Will that happen in this year's update? And second, at Cowal, the upside on resource and asset life appears to be solidifying at both the open pit and the underground there. I believe I raised this last time, but when do we start looking at mill expansion studies at Cowal?
Lawrie Conway
executiveGlen is going to cover the first two sections. As for that final part regarding the plant expansion, I think we'll examine it once we have more details, though whatever we do will hinge on getting into E46 and E41 and how that shapes our plans at the facility. We're likely at least 12 to 18 months away from having to deal with that.
Glen Masterman
executiveHugo, the results we released this morning for Mungari and Cowal are not going to make it into the next MROR update. They simply arrived a bit too late for us to rate them, but we have already delivered a resource and reserve at Genesis. That's a growing, ongoing concern — that's probably the best way to put it. What excites us is that we can see the opportunity taking shape along that trend between the Pope John pit, a hanging wall structure sitting outboard of it, and it appears it will link into Barkers, and we believe we will fill that gap between Genesis and Barkers. What we intend to do, especially over the next 12 months, is drill that very aggressively so we can capture it in the 2026 MROR statement. That's the plan there. Turning to Cowal, particularly what we're doing at Oban, there is a lot of space there, and if you look at the location on Figure 3, one thing we really like at Oban is that the contact I described earlier appears to be very similar, if not a repeat — we haven't confirmed that — of the contact which controls all of the underground mineralization in the underground mine at the moment.
Glen Masterman
executiveThis is another case where that image shows all of the drilling, and there is almost nothing along it. There is a lot of ground left to explore there, but we have the target at Oban, and we will keep on essentially broadening the story as we know it along strike, to the north and to the south, and aim to get additional drilling into that area over the next 12 to 18 months.
Hugo Nicolaci
analystGreat, thank you. One final question — I realize Northparkes and Cowal are 100 to 200 kilometers from you, but has the earthquake overnight caused any safety effects or disruption to the mine?
Lawrie Conway
executiveNo, nothing at all on that front from either Northparkes or Cowal.
Hugo Nicolaci
analystPerfect, thank you everyone. I'll relay that.
Operator
operatorThe following question is from Kate McCutcheon at Bank of America. You may proceed.
Kate McCutcheon
analystHello, and good morning, Lawrie. Thanks for the reminder about Cowal in '27. For this year, we remain on track with the guidance. I'd like your help thinking through the fourth-quarter step-up needed to reach that roughly 190 oz level you achieved a couple of quarters ago. My assumption is that it's Cowal together with stage H grade, with Ernest Henry returning to normal — could you walk us through that?
Lawrie Conway
executiveI’ll have Matt add to that. I doubt he has much more to say, but the two main drivers are the two key? assets.
Matt O'Neill
executiveIn my view, the two major items everyone is quite familiar with are, first, completing the planned maintenance at Cowal and, second, Ernest Henry returning to operation—those are the two main ones. Beyond that, Mungari keeps running at a fairly solid rate. Northparkes is performing as it has been. You'll notice a slight decline at Northparkes as the legacy stockpiles from E31 near their end. Apart from that, it's normal operations, with the boost coming from the two items you mentioned.
Kate McCutcheon
analystUnderstood. Then there's Cowal — I like that underground opportunity. We're seeing return hits of 1 to 2 grams below E41, and that underground system keeps extending. Obviously, the real prize is pulling out additional high-grade underground tons, and Glen touched on this a bit earlier, but I suppose my question is: what would you need in order to feel confident enough to commit to another exploration decline there, or how should we think about the timing or the stage gates for a bigger underground operation?
Glen Masterman
executiveKate, I figured that question was coming. Honestly, if we look back at the 2018 discovery of the underground mine—especially the Dalwhinnie lode, which was really the game changer—it took roughly 3 years from the initial drill hole results to kicking off production underground. That's the kind of timeline we'd have in mind, so 3 years at a minimum. A lot of drilling is going to be needed here. We also need to bring in new positions to get a better angle of attack on the contact. That's work we'll have to do, and I'll be leaning on Matt very heavily to help push that forward so we can get the rigs positioned to do it. I'd view that as a 3-year opportunity. Then, thinking about the results at E41, historical drilling has mostly been oriented east-west, and as we've learned at the Cowal underground, that orientation has been suboptimal. We've now pivoted the rigs to hit those veins at a much better angle. Historically in the underground, what we've seen is that when we've done that, grades do improve in some areas.
Glen Masterman
executiveOur expectation is that once we begin filling that in at a significantly improved angle, E41 will display comparable behavior. After that, as I noted, the pit shell we have on display is a rather conservative one, so we do anticipate that as resource drilling, or resource space drilling, goes into E41, we'll be able to enhance how that pit optimizes.
Kate McCutcheon
analystUnderstood. If I may squeeze in one final quick question. Regarding operating cash flow expected for this year, you've said there's no plan as of now to hold onto a cash reserve or pursue transactions at record valuations. Would it be reasonable to expect that the board will review the capital management policy at the FY, or how should we think about capital returns?
Lawrie Conway
executiveKate, we said before that as we reach the close of the financial year, once our life of mine plans are in place, Fran and the team will assemble a refreshed capital management plan, examining our approach to dividend policies and capital returns. That will be released alongside the full-year financial results.
Kate McCutcheon
analystThat’s great. I appreciate it.
Operator
operatorThe following question is from Levi Spry at UBS. Go right ahead.
Levi Spry
analystHello, everyone, and thank you for joining. Perhaps one more question directed at Fran. Turning to expenses, the market is clearly concentrating on this area across every sector. Diesel represents merely a tiny share of your overall cost structure, and you are likely comparatively much better positioned than certain competitors. What about the remaining portions of that pie chart? What observations do you have there? How should we consider developments heading into FY27?
Lawrie Conway
executiveLevi, on the cost side, labor accounts for almost 50% of our cost structure. Six months ago, when inflation was trending around 3.5% to 3.8% and moving lower, I would have given a different answer — and that has clearly shifted now. Going into FY27, you should probably expect labor cost movement somewhere in the 4% to 5% range. Turning to our other costs, power is fairly well locked in, with pricing fixed at Cowal and Northparkes. Ernest Henry and Mungari are also fixed through FY27 in terms of pricing, though there is some slight escalation there. On consumables, it will hinge on how long the current situation lasts regarding temporary pricing we would be asked to cover for additional logistics costs and similar items. Since that represents roughly 50% of our cost base, you will probably see a few percent increase in that bucket too. Overall, I think it is still being well managed, but it does depend on what happens globally over the next 3 to 6 months.
Levi Spry
analystUnderstood. Appreciate it, Lawrie.
Operator
operatorDaniel Morgan from Barrenjoey has the next question. Go right ahead.
Dan Morgan
analystHello, Lawrie and the team. My question concerns Mungari, specifically on costs. For this question, could we set diesel aside briefly—regarding what we're seeing in a live session? Focusing on costs, was this a typical quarter for Mungari, meaning $2,150 AISC? In earlier quarters on the cost side, we clearly had some capitalisation of various spend and, clearly, the project had not fully ramped up. I'm just wondering whether you consider this a representative quarter. Thanks.
Lawrie Conway
executiveDan, we're nearly there. We mentioned roughly a 16% cut in all-in sustaining costs once the mill was up and running, and after that, depending on the ore mix, you'd likely land somewhere between $2,250 and $2,350, with $2,400 at the upper end, which would match what we had projected. It was a strong quarter, driven really, I'd say, by the campaign at the EKJV, high-grade material, which therefore helped us on both the mining and processing cost sides there. In Q4 you'd see a slightly higher figure, but at that point you're approaching a reflection of how Mungari will operate.
Dan Morgan
analystThanks. Just on Cowal — it's pretty clear you're leaving stage H and that high-grade ore behind next quarter and heading toward stage I, where you'll be pushing back. I'm just wondering how much time will pass before you actually get material access to stage I ore. Is that FY27 — obviously there's a lot of hard work through there — but do we begin to see improved grades in '28? Thank you.
Lawrie Conway
executiveWe expect to return to stage I ore during the first half of FY28, and at that point we'll also be accessing good material from E46. There really won't be anything meaningful in '27, with just a small amount coming through in the first half and the second half of '28, when you'll see it begin to ramp up in stage I. That's roughly 18 months.
Dan Morgan
analystThanks. For the final question, I'll focus on Red Lake, where things have been more stable and delivery has improved. One remark you made, I believe, was that this positions us well for a solid finish to the year. Could you elaborate on the most current operational picture through the rest of this year and anything past that? Thank you.
Matt O'Neill
executiveYeah, Matt here, Dan. Basically, as we head into the final quarter, we're moving into a couple of higher-grade zones, which should drive a modest uplift in grade. On the development side, if you look through it, things have been really quite steady. Same story there — you see a slight dip in throughput with some ore during the quarter, with a few interruptions from power and from the winter side of things, but apart from that, that's really where it's trending. Pretty steady, and pretty well positioned on both grade and volume going into the next quarter.
Dan Morgan
analystCan that last—or is it the benefits that can last?
Lawrie Conway
executiveDan, honestly, where we stand at Red Lake remains exactly the same. Our aim is producing 30,000 to 40,000 ounces each quarter, consistently, while generating positive cash flow. Matt has been collaborating effectively with John and the team on ensuring contingency exists within the system, since you're aware of the challenges those mining operations present at Red Lake, right? They need to guarantee that whenever certain things fail to pan out, alternative zones are available to move to.
Dan Morgan
analystSorry about that — I think your audio dropped for a second there, but thanks so much for sharing your perspectives.
Operator
operatorThanks. Our following question is from Jon Sharp at J.P. Morgan. You have the floor.
Jonathan Sharp
analystGood morning, Lawrie, and everyone on the team. I'll start with a question about Ernest Henry. You mentioned that you're back to normal operations. Could you clarify precisely what being back to normal means, and are there any improvements still to come during this quarter? Perhaps more significantly, has anything been altered regarding dewatering or water management so that this doesn't occur again, or at least so the impacts are reduced? I'm simply trying to work out whether it will continue to be an operational constraint going forward. Thanks.
Lawrie Conway
executiveLet me take the first question. Essentially, normal operations are back to where they were before the event — we're running out of the cave again just as we did previously. That's basically what we've accomplished. Our truck loops and the crushers and everything else are up and running there once more. A few minor works remain. We're still dewatering the lower section of the mine. That isn't an operational area; it's where our development work takes place. Dewatering activities are still going on through that section, but at the moment they don't affect day-to-day operations. Looking ahead, we've completed the investigations and we're working through that process as we speak. There will be some lessons taken from it, but I think it's important to remember that event was roughly three times what we'd seen previously in '23. While it's easy to sit here and call it a one-off event, it is something we need to learn from. The key for us will be stopping the water from getting there in the first place, and then being able to manage it once it does. We are learning from it, and we will take steps to make sure we minimize the chance that it happens again.
Jonathan Sharp
analystRight, got it. So for my second question, Lawrie: this morning you repeated that you're running under the initial all-in sustaining cost guidance. Three quarters are done now and Ernest Henry is back to normal — do you have enough visibility to say whether this year's all-in sustaining cost will probably come in below the midpoint of the updated range?
Lawrie Conway
executiveI won't put Matt or Fran in a tough position by naming where. Our view is that we're going to land in that range. A number of factors will decide it. You've got the gold price, copper tons, copper price. One thing I will say, and it's what was mentioned on the call, the cost and capital discipline in the business, we're running very well in terms of our sustaining capital and our operating costs against budget. We'll be in the range. That's the political answer that you needed to give Matt some room.
Jonathan Sharp
analystI appreciate that.
Lawrie Conway
executiveAppreciate it.
Operator
operatorMatthew Frydman from MST Financial has the next question. Please proceed.
Matthew Frydman
analystSure, thank you. Good morning, Lawrie and everyone. First, may I build on what Levi asked about diesel—clearly it's fairly small by itself at 2% on the pie chart. Just to be clear, how does that flow through when it comes to the different sorts of increases and decreases across some of your mining contracts and other contracts you may have in place throughout the business that are somewhat sensitive to diesel? Are there any further exposures beyond that 2% on a standalone basis that we ought to be considering? Then specifically, I suppose, with your CapEx plan, the major projects in your pipeline, presumably much of that involves waste movement or underground development. Should we also be thinking about, I guess, diesel or explosives or other cost sensitivities in that area? Is it reasonable to assume that this low single digit figure is a representative sensitivity for those parts of CapEx as well? Thanks.
Lawrie Conway
executiveMatt, if you take a look, for any of those contracts where diesel is required — whether it's haulage or mining contractors — you'll notice that the diesel expense gets passed through. That said, as we've mentioned before, it remains embedded within our overall business costs. It doesn't represent the largest component. Labor still accounts for half, and then power sits at roughly 9%, 10%, and so on. We aren't observing any material effect, though those increases and decreases do flow through. Then when it comes to capital, yes, the largest mine development we have underway across the coming couple of years is at Cowal with E46, stage I, and similar items in terms of mining cost. Material movement won't be meaningfully greater, nor is there anything of consequence for us regarding our costs there. We simply need to keep watching it over the next few months to see where everything settles, Matt.
Matthew Frydman
analystGot it, thanks Lawrie. And then maybe just as a second point, quickly — it's not especially material, but obviously noting that at Ernest Henry during the quarter, you highlighted $26 million of non-operating costs tied to recovery from the December quarter, and presumably, with the ongoing impacts in the March quarter in terms of weather, there will be some continuing non-operating recovery costs, I guess, in future quarters. Can you give us some sort of indication of what we should expect there — whether that's going to be a bigger quantum in the June quarter or onwards? I expect there are some sort of tail costs there. Thanks.
Lawrie Conway
executiveMatt, look, much like what we saw in March '23, you begin with a big chunk of recovery costs — getting equipment out and bringing all the infrastructure back to normal — and after that it tapers off. Through the June quarter, I'd say you'll see a bit more. As Matt mentioned, we still have water at the bottom of the mine that has to be removed and so on. We still have some equipment as well. It will trend out. I don't believe you're going to see multiple quarters at $25, $26 million, but I think the majority of it has been captured in this first quarter.
Matthew Frydman
analystGot it — thank you, Lawrie.
Operator
operatorAdam Baker from Macquarie has the next question — go right ahead.
Adam Baker
analystHi Lawrie and the team. Congratulations on getting to that net cash position. I realize a fresh capital management plan is going to come alongside the financial results, but I'm eager to hear your early thoughts about capital management from here. Do you see the existing dividend policy as still fit for purpose, or might there be a change to that current policy, or could we perhaps see a buyback put in place, as some of your peers have done? Thank you.
Lawrie Conway
executiveAdam, I appreciate you noting the net cash position. Honestly, it's genuinely satisfying to watch the company reach this stage given what we've managed to accomplish across the past 2 years. It leaves us with a favorable dilemma. Over the last 2 quarters, I'd say it's accurate that Fran and I have gotten more input from shareholders than ever regarding the use of that cash—whether that means raising dividends, reinvesting, issuing specials, or doing buybacks. All of those options will be factored in as we approach the June year-end, and we'll talk them through with the board. As I mentioned, that's a nice challenge to be facing. It arrived sooner than we likely anticipated. The interim dividend we paid out, which represented a substantial increase tied to the cash we produced, and the fact that we pulled forward a portion of the second-half cash—I believe that fairly signals what shareholders ought to expect moving forward.
Adam Baker
analystThat's a good sign, thanks. Just one clarification regarding Cowal. You said ounces would be 10% lower for FY27. I'm just wondering whether that 10% reduction is measured against the midpoint of the current guidance or against the bottom end of it? I'm simply trying to pin this down, since it could land anywhere from 275 to 286,000 ounces. Thank you.
Lawrie Conway
executiveLet me try to help you with that, Adam. My suggestion would be to calculate your estimate for the June quarter, then subtract 10% from the full year, and that should give you a fairly solid estimate of what next year would look like. As Matt explained, the shutdown is complete, and you'll see production rise in the fourth quarter. Run that through, and it will give you the figure for next year. Matt and Joe won't be pleased about it; it means their guidance for next year is essentially being set.
Adam Baker
analystMuch appreciated. Cheers.
Operator
operatorBaden Moore from CLSA has the next question in the queue. You may proceed.
Baden Moore
analystGood morning, everyone. I appreciate your remarks regarding the fuel supply situation you're facing. I wanted to ask whether you might expand a bit on how long your contracted position runs. What kinds of timeframes do you currently have in place, and then perhaps whether any discussions have taken place with the government, or with your suppliers, about how you could be given priority for fuel should rationing of any degree occur in the country? Then I suppose the third layer would be this: how do you think about resilience and planning in case supply is disrupted? How do you plan around something like that? What safeguards do you have?
Lawrie Conway
executiveLet me take the second question first, on the government side. Our stance has consistently been that we are accountable for running our operations and for ensuring supply continuity, and that is exactly what Matt, Fran, and the site teams are working through. We are not placing our reliance on government support in that regard. If a decision were made about rationing, we would deal with whatever impact that has on our operations at the time it happens. One point worth making is that our open pits consume the most diesel, and at both Mungari and Cowal we hold stockpile material that we could run through the plant. That would involve slowing some mine development in order to preserve diesel use. Turning to other consumables and similar items, that is the work Matt and Fran have in place regarding the response actions we need to take as issues with consumables arise. The good news is that through March we experienced no interruptions to anything concerning consumables supply into the business, and the outlook for the June quarter looks very similar.
Lawrie Conway
executiveSo first off, those contracts span multiple years. Our ties with the oil companies distributing for us are really strong. As I mentioned earlier on this call, we see them honoring what they committed to. We aren't attempting anything beyond what the contract covers, and that keeps the relationship in great shape so our supply is guaranteed.
Baden Moore
analystThanks. Just a quick follow-up. Could you speak to how many months of inventory you'd be holding? And then, with those stockpiles you brought up, how long would they last before any kind of effect would hit your cash flow?
Lawrie Conway
executiveSo regarding volumes at the site, as we mentioned, we have sufficient volumes there and steady deliveries against our orders, so we don't view that as a problem. It's not really meaningful to quote the percentages, since they'll shift today and be different once more next week depending on whether we're consuming or receiving deliveries, but our coverage is adequate. If you examine it, Cowal is the largest one. We have more than 47 million tons of stockpiled ore. We operate at 8.8 million tons per annum, and I believe that gives you a sufficient picture of the impact on our biggest operating asset if we were unable to have fuel on
Baden Moore
analystExcellent response. Thanks very much.
Operator
operatorBelinda Humphries from IQ Industry Queensland has the next question in the queue. The line is yours.
Belinda Humphries
analystThanks a lot for the update today. I just wanted to ask about the exploration work around Ernest Henry. Could you give us a little more detail on what's planned for the June and September quarters — meters drilled, budget, that kind of thing?
Lawrie Conway
executiveI’ll pass it to Glen. My guess is he won’t go through the meters; I think he’ll focus more on the point that the programs matter more to us.
Glen Masterman
executiveThanks, Lawrie. The main goal of these programs—not only the recent tenements but really the whole package we've been assembling over the past several years—is to find new production opportunities that can help fill the mill at Ernest Henry, where we have latent capacity. We're not chasing huge deposits, though if we found one we'd certainly take it; what we're after is probably more modest-style deposits that can essentially help us hit that goal. The drilling programs will get underway in the next month or two. We've basically been waiting—there's been a lot of weather up there. We need to hold off until everything is completely dry. It's very difficult to get any access, especially with equipment, until it is dry. As soon as it is, we'll be drilling. This morning in our update we gave some examples of the kinds of targets we're looking at, which gives you a bit of a sense—10 k's from Ernest Henry, previous drilling identifying anomalies. The consolidation of tenements up there is the really exciting thing that's happening, because bringing those together means we can explore the full opportunity rather than piecemeal it on tenement to tenement.
Glen Masterman
executiveThat truly has been a big, big help in terms of how we'll rank the drilling program ahead of the dry season. My advice would simply be to keep watching. We'd expect to say more about what we're finding once the December quarter wraps up and we have results in hand from that drilling program.
Operator
operatorThank you. As a reminder, should you want to pose a question, hit star one on your phone and hold until your name is called. We’ll take a brief pause so any last questions can be registered. Thank you. We have no more questions at this point. I’ll return the call to Mr. Conway now for his closing remarks.
Lawrie Conway
executiveThanks, Ashley. It feels good to have turned in another really strong quarter, and we remain on course to hit our group guidance and to make the most of today's elevated metal prices. Now that we've reached net cash and have no debt repayments until FY29, we are definitely creating room to move. Looking ahead, our 2025 MROR report will come out within the next month, and we also have an investor briefing plus visits to Cowal and Northparkes lined up. I appreciate everyone joining the call today.
Operator
operatorThat brings today's conference to a close. We appreciate everyone joining us. You're welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.