First Quantum Minerals Ltd. (FM) Earnings Call Transcript & Summary

October 29, 2026

Toronto Stock Exchange CA Materials Metals and Mining earnings 51 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, everyone, and welcome to the conference call covering First Quantum Minerals' third quarter 2026 results. Please be aware that today's call is being recorded. Every line has been muted so that background noise doesn't interfere. Following the speakers' remarks, we'll hold a question-and-answer session. To ask a question at that point, just press * and then the number 1 on your telephone keypad. Should you wish to withdraw your question, press * 1 once more. I'd now like to hand the call over to Bonita To, Director, Investor Relations and Capital Markets. Please go ahead.

Bonita To

executive
#2

Hello, and thanks, operator. I appreciate all of you being here today as we go over the results for our third quarter. We'll be making forward-looking statements during this call. So I'd ask you to please review the cautionary notes that come with this presentation, along with our MD&A and the related news release. Just a reminder that the presentation can be found on our website, and that every dollar figure referenced is in US dollars unless we say otherwise. Joining us on today's call are Tristan Pascall, our Chief Executive Officer; Ryan MacWilliam, our Chief Financial Officer; and Rudi Badenhorst, our Chief Operating Officer. With that said, I'll hand the call over to Tristan.

Tristan Pascall

executive
#3

Thank you, Bonita. Good morning to everyone, and thanks for being with us today as we discuss our third quarter results. The three months since our previous call have been eventful, and I'm glad to have the chance to give you an update. During the third quarter, with the hedge book now behind us, we gained the full benefit of stronger copper prices. That produced a substantial enhancement in our financial performance and showed what our business can earn at its underlying level, which Ryan will address in greater detail later on today's call. We also achieved increased production during the quarter, and Rudi will walk us through that in more detail later. Let me begin with the earthquake that struck Panama on October 9. Above all, every First Quantum employee in the country was reported safe. Our thoughts continue to be with the families and communities who were affected, especially in the Penonomé area, where reports indicated some of the most significant impacts. The earthquake fell well within the mine's design parameters, with no material effects on site infrastructure or environmental protection systems, and the tailings and water management facilities are also stable and secure. I want to acknowledge the Cobre Panamá team for responding strongly and immediately to the incident, and for their commitment to helping local communities through the provision and delivery of essential supplies as part of the broader relief efforts in the country.

Tristan Pascall

executive
#4

In Q3, we achieved solid progress on the stockpile processing initiative, which forms part of the mine's continuing environmental stewardship. All three processing trains have now been successfully recommissioned — another key milestone in the program — and attention has moved to enhancing reliability and stability. Turning to other Panama developments, the Interministerial Commission issued its recommendation on September 30 concerning the future of Cobre Panamá. The report recognizes that keeping the site going indefinitely without a long-term framework is not a sustainable path, and it recommends the government enter negotiations with First Quantum to create a new framework capable of resolving the outstanding arbitration proceedings and enabling a restart that supports an orderly, self-financed, long-term closure process, while abiding by the Supreme Court of Justice's ruling and putting environmental, social, and economic outcomes for Panama first. The report drew attention to the independent environmental audit's findings, which showed a high level of compliance alongside a limited number of improvement areas that we have already begun to address. It further acknowledges the considerable economic consequences the shutdown has had for Panama — spanning employment and local business activity through to exports and government revenues — and noted that the economic activity the mine once generated is not easily replaceable by other sectors.

Tristan Pascall

executive
#5

What matters greatly here, the Commission points out, is the serious effect on communities surrounding the mine, and it advises giving those communities priority status as beneficiaries under any forthcoming framework, with more local involvement in the economy and concrete investment addressing community needs. Some context is also worth giving regarding what the Commission said about closure. As the report acknowledges, shutting down a site the size of Cobre Panamá is a complicated engineering and environmental task, one that involves continuing management of tailings and water, rehabilitation, stabilization, and monitoring over the long term so that a high-quality result is achieved for environmental rehabilitation, biodiversity, and local communities. Closure is not portrayed in the report as one single event; instead it is a long-term process requiring proper planning, funding, and independent verification. So instead of immediate closure, which would put a heavy burden on the State of Panama, the Commission recommends a progressive closure spanning several decades, paid for by the mine's own economic activity. The Commission further recommends that the mine's territorial footprint not expand and that it be progressively reduced through closure and rehabilitation across the life of the operation. According to the ministers, the ultimate territorial footprint must be smaller than what was agreed under Law 406. As a reminder, the Commission's report explicitly says it is setting out general principles, while mechanisms and other specifics are to be worked out through negotiations.

Tristan Pascall

executive
#6

To us, this report represents a constructive move ahead toward creating a foundation for formal talks to start. We continue to be prepared to work constructively alongside the Government of Panama, aiming at a fair and lasting resolution for everyone involved, while honoring Panama's sovereignty, its ownership of reserves and resources, democratic institutions, and legal processes. Thank you — I'll now hand things over to Rudi for our operational results.

Rudi Badenhorst

executive
#7

Thanks, Tristan. Quarter three delivered yet another period of production growth, helped along by S3 at Kansanshi continuing to perform strongly and by ongoing processing of stockpiled ore at Cobre Panamá. We produced roughly 109,000 tonnes of copper in the third quarter, which represents a rise in total copper output versus the second quarter. Copper sales came to 110,000 tonnes, about 1,000 tonnes more than we produced, helped by Cobre Panamá volumes carried over from quarter two. At Kansanshi, quarterly copper production reached approximately 46,000 tonnes, an increase of 2,000 tonnes over the prior quarter thanks to better throughput. S3 kept running above design capacity because of greater operating time along with strong utilization and milling rates. At Kansanshi we also managed leaching actively, prioritizing material that consumes less acid during periods when acid consumption rates ran high. That yielded 70,000 tonnes of surplus sulfuric acid sales in the third quarter, letting us capture added value from the strong pricing environment, which Ryan will cover. Our 2026 copper production guidance has been narrowed to a range of 175 to 185,000 tonnes, and gold production guidance has been reduced to a range of 95 to 105,000 ounces, with both reflecting performance to date. Although S3 is expected to keep operating above design capacity, stripping at South East Dome is taking longer than originally planned, and that will mean lower grades persisting into the following year.

Rudi Badenhorst

executive
#8

In addition, we expect the acid sales program to carry on through 2027, and that will have an effect on copper output as well. At Sentinel, we produced roughly 49,000 tonnes of copper, which is down around 1,000 tonnes versus the prior quarter, as lower grades outweighed the gains we saw in throughput. Those weaker grades were a function of the areas we mined in the quarter, since access to higher-grade zones was pushed back because mining volumes were lower following the midlife overhaul of rope shovel 1. We anticipate grades and throughput picking up in the fourth quarter of 2026 as mining advances with Stage 2, with shovel 1 coming back, a new larger hydraulic face shovel being deployed in October, and the relocated in-pit crusher 4, which had been out of service for all of quarter three, being brought in. For 2026, our production guidance at Sentinel has been revised to 190 to 200,000 tonnes of copper to reflect how we have performed so far. We are still managing bolt fatigue maintenance effectively and continue to plan a major upgrade in 2027 related to flange bolt fatigue and ball mill 2, which will involve swapping out a section of the discharge end for a new original equipment manufacturer design that delivers a permanent engineered solution.

Rudi Badenhorst

executive
#9

As Tristan mentioned, we've made solid strides with the processing program at Cobre Panamá, and it's now moving from recommissioning into stable operations. Copper output for the quarter came in above 13,000 tonnes, while gold production exceeded 6,000 ounces. On top of that, we restarted concentrate shipments during the third quarter. In August, 33,000 wet metric tonnes of copper concentrate was loaded and shipped, which shows the site's processing and export capabilities have been restored. A second vessel carrying roughly 39,000 wet metric tonnes was loaded and shipped in September. Processing of stockpiled ore is going smoothly. At the start of the program, we had 38 million tonnes of stockpiled ore, and those stockpiles are sufficient to support processing until mid-2027. We're still on track for our 2026 guidance, with copper production from the stockpiles expected to reach 30 to 40,000 tonnes and gold production expected at 10 to 15,000 ounces. Enterprise produced just under 10,000 tonnes of nickel, which is a 13% decrease from the prior quarter owing to lower grades, after stronger grades during the first half of the year. Ore grades are expected to be lower in the fourth quarter, consistent with the mine plan. Mining volumes, though, are expected to rise in the fourth quarter as additional contractor equipment arrives, and 2026 production guidance has been raised to between 40 and 45,000 tonnes of contained nickel, reflecting strong performance so far.

Rudi Badenhorst

executive
#10

With the ore footprint now expanded, our operational focus shifts to getting ready for the rainy season. That work covers installing the in-pit dewatering stage tank and completing final development of the main pit sump, with completion expected ahead of the upcoming wet season. In the same way, since the ROM ore pad is approaching its capacity, feed of ore to the nickel concentrator is in good shape for the wet season. Then finally, turning to Guelb Moghrein, copper output came in at 1,000 tonnes and gold output at 16,000 ounces, including production from tailings that were reprocessed through the CIL plant as well as ore stockpiles processed by the flotation circuit. Guidance for copper production in 2026 sits at roughly 7,000 tonnes of copper. Gold production guidance, though, has been raised to 45 to 50,000 ounces after the successful shift to a gold-focused operation. Thank you — with that, I'll hand the call to Ryan for the financial review.

Ryan MacWilliam

executive
#11

Thanks, Rudi. Copper on the LME stayed robust during Q3, hitting all-time peaks of $6.74 a pound. September brought more market turbulence tied to ambiguity over US tariffs. Even so, the underlying fundamentals stayed supportive, as constrained supply was made worse by weather-related disruptions and strikes in Chile. We delivered a strong financial quarter. Revenue rose 37% to $2.1 billion, powered by stronger copper prices and greater sales volumes. That revenue figure included two concentrate shipments from stockpile processing at Cobre Panamá. In Zambia, output from our integrated smelter guarantees a secure acid supply for our SX-EW operations and leaves extra acid available for sale. Zambian acid prices climbed from $180 per tonne in Q1 to $460 per tonne in Q3. Given the favorable acid pricing, we sold 70,000 tonnes of acid during the quarter, bringing in $33 million of revenue and delivering a 14 cents byproduct credit against our copper C1 costs. EBITDA more than doubled from the prior quarter, reaching $844 million. That reflected higher revenues and the advantage of full exposure to copper prices, since we now have no hedges remaining. Now on to costs. Apart from Cobre Panamá's stockpile processing, copper C1 costs came in at $2.40 per pound, which was 8 cents lower than the previous quarter.

Ryan MacWilliam

executive
#12

Lower fuel and maintenance expenses plus higher acid sales drove this. That more than compensated for the effect of Guelb Moghrein's shift to a gold operation, where the accounting treatment means gold output no longer qualifies as a byproduct credit. With Cobre Panamá included, copper C1 costs came in at $2.59 per pound, a 5 cent rise versus the prior quarter. That figure reflects a 13 cents per pound effect from a full quarter of stockpile processing at Cobre Panamá. As anticipated, diesel prices stayed elevated through the quarter, averaging $1.40 per liter, a modest decline from the Q2 average of $1.59 per liter. Given a two- to three-month lag on fuel deliveries, higher fuel prices will keep feeding into the cost base through the remainder of the year. Moving to guidance. Copper C1 guidance now stands at $2.50 to $2.65 per pound, incorporating the 25 cent sensitivity previously provided for elevated fuel prices and a stronger Zambian kwacha. Those inflationary pressures should keep affecting our cost base into the new year. All-in sustaining cost guidance rose to $4.10 to $4.25 per pound, mainly reflecting higher royalties tied to stronger copper prices and the effect of lower production volumes.

Ryan MacWilliam

executive
#13

For enterprise nickel, we're lowering cost guidance to $3 to $3.25 per pound, thanks to how well that mine has been running. And on total capital expenditure, guidance is now narrowed to $1.15 to $1.25 billion, which reflects our latest timing assumptions on capex. We had earlier put the cost of stockpile processing at Cobre Panamá at $250 million. Our newest estimate is $200 million, and $80 million of that has already been spent. Turning to the balance sheet, net debt came down by $98 million to $5.3 billion, as strong EBITDA generation was enough to cover our planned capex, tax, and interest outflows. Net leverage improved to 2.6 times — our lowest since Q3 2023, before production was suspended at Cobre Panamá. We stay focused on deleveraging, and we expect strong copper prices and continued free cash flow generation to strengthen the balance sheet further. All in all, another solid quarter, with strong operational performance and higher copper prices supporting robust margins. I'll now hand the call back to Tristan.

Tristan Pascall

executive
#14

Thank you, Ryan. Having been at London Metal Exchange Week two weeks ago, I heard one point repeated again and again: new copper is becoming scarcer around the globe. Even with the macroeconomic and geopolitical turbulence we see near term, over the medium and long term the world is going to require additional copper to satisfy rising demand. Still, delivering substantial new output won't be easy, since the project pipeline holds only a small number of large, high-quality greenfield copper developments after decades of insufficient investment. That tight supply picture highlights both the optionality and the worth of First Quantum's greenfield pipeline, along with the decades of experience our team brings to executing growth. On a measured and indicated resource basis, two of the biggest undeveloped greenfield copper projects anywhere in the world sit in our portfolio: Taca Taca and La Granja. At Taca Taca, we keep engaging constructively with the provincial authorities, and approval of the mine ESIA is anticipated this year after public consultation, which has been set for November. Approvals for water use concessions should come next, and we are getting our RIGI application ready to file shortly. At La Granja, the engineering study is far along, together with environmental baseline efforts, community engagement, and resettlement planning. We keep pushing engineering definition and permitting forward while retaining flexibility regarding the eventual development approach.

Tristan Pascall

executive
#15

We expect a technical report on reserves to be filed in 2027. Both projects will be handled by the same core team that built Sentinel, Cobre Panamá, and, most recently, the S3 expansion at Kansanshi. Over the last 20 years, that core team has completed $13 billion in capital projects, including two of the world's largest greenfield copper projects by initial throughput capacity. We have gained valuable technical and financial lessons that will guide not only how we design and build these projects, but also how we fund them in a disciplined manner. This experience puts us in a strong position over the long term to deliver the next generation of large-scale projects at the right time. In the meantime, we have made meaningful progress on our priorities so far this year, and our near-term focus remains firmly on executing them: firstly, a fair and durable resolution for Cobre Panamá; secondly, safe, reliable, lean, and productive performance at our operations; thirdly, continued proactive management of our balance sheet to ensure flexibility to invest in the future; and fourthly, derisking our growth pipeline with the discipline needed to deliver long-term value. The improvement we saw in our third quarter results demonstrates the underlying potential of First Quantum's business.

Tristan Pascall

executive
#16

There's still more for us to do, but my confidence in this business and in how we carry out the priorities we've set hasn't wavered — those priorities will steadily open up optionality and additional value. So with that, operator, I'll gladly open the line for questions.

Operator

operator
#17

Thanks. We're moving into the Q&A portion now. Before that, a quick reminder: to pose a question, hit * and then 1 on your phone's keypad. Should you wish to pull your question, just press * 1 once more. We'd appreciate it if you kept to a single question plus one follow-up, so that everyone gets a chance to ask something. Up first is Orest Wowkodaw from Scotiabank. Go ahead, please.

Orest Wowkodaw

analyst
#18

Hi, good morning. I have a question regarding Kansanshi. In your disclosure, you mention delays with stripping at the South East Dome, which I assume has affected the grade profile for this year, and your release refers to a knock-on effect extending into '27. I was wondering whether you could provide more detail on that. How far behind is it? Is it three months or six months late? Could you give us some sense of what the grade impact will be on the sulfide circuit for '27?

Tristan Pascall

executive
#19

Hi, Orest. Thanks for asking. That's correct. We're not quite where we'd like to be, and that's why we're calling it out up front. As for this year, we don't anticipate much of an effect, and our guidance reflects that. What we're indicating is that we expect that to be difficult going into next year. We'll revisit that, and there's considerable attention on how that can be accomplished, and we'll return to it when we give our guidance in January, February.

Orest Wowkodaw

analyst
#20

Could you give us some indication — is it lagging by three months, by six months? We have no sense of that here.

Tristan Pascall

executive
#21

Appreciate that, Orest. We'll take that on and get back to you. There won't be much of an impact this year, and we'll address it when we give guidance next year.

Orest Wowkodaw

analyst
#22

Appreciate it.

Operator

operator
#23

We now take a question from Richard Garchitorena, who is on the line from Barclays. You have the floor.

Richard Garchitorena

analyst
#24

Thanks a lot, and nice work on the strong quarter. I want to ask about acting on the Interministerial Commission's recommendation. Could you take us through the upcoming milestones on the government side? Clearly, a decision is needed from the president. What commercial, legal, and environmental matters remain to be settled? And if approval does come, what is your present timeline for ramping up after receiving the go-aheads?

Tristan Pascall

executive
#25

Appreciate the question. The first point I'd make is that those recommendations were fully consistent with taking the situation at the mine forward and addressing it over the long term, and that calls for reactivation. We'd welcome the chance to engage on that in a formal manner. As I see it, the focus in Panama right now is on relief work surrounding the earthquake. For our team certainly, but more widely across the country, that is really what matters most, and we believe it will take a number of weeks to make sure that everyone affected by the earthquake is in a good position. At the appropriate moment, I think the mine issue will return to the government's attention, and on that front the next step is clear to us: an announcement that follows the recommendations, which went to the president, to negotiate. Our expectation is that it will be, "Okay, well, thank you for the recommendations, and the instruction is to proceed as per the recommendations." We would look forward to engaging formally at that point around negotiation. As for what that will require, yes, there are certainly three key elements: the legal structure — and I think it has been made clear that we expect a different pathway under the constitution — and we will certainly be constructive on that.

Tristan Pascall

executive
#26

What matters on that front is being transparent about what the outcome will be and how it will look, and that people have a solid grasp of it. Second, on the environmental front, as a follow-up to the environmental audit and the Supreme Court's statement that an ESIA update was required, that this has been dealt with, and that consultation is taking place around that process so there is transparency. Then third, regarding the commercial terms. On that point — and you raised that question — it is simply too early to say. We will welcome discussion on that, but we recognize a balance is needed between, clearly, people in Panama saying more tangible benefits are required locally, and the benefits for the mine coming through, yet equally, this represents the largest investment in Panama's history, and that needs to be recognized in preserving the country's reputation as a destination for investment. That covers it broadly, and once more, we look forward to the announcement at the appropriate time that there will be formal conversation, formal negotiation, and we, certainly on our side at First Quantum, will engage constructively to find the best result for all stakeholders.

Richard Garchitorena

analyst
#27

Appreciate the additional detail. Now, turning to copper costs — clearly, they rose from $2.40 to $2.50 and then to $2.65. Could you help us bridge the components, specifically how much of that increase stemmed from the stronger kwacha, the higher fuel costs, and the growing volumes at Cobre Panamá? If possible, a breakdown of those elements would be helpful. Thank you.

Tristan Pascall

executive
#28

Thanks. Ryan, would you mind handling that question?

Ryan MacWilliam

executive
#29

Absolutely. So this quarter, Cobre Panamá coming online had roughly a 13-cent effect. We'd point out that Cobre Panamá was already baked into the guidance we gave previously — we factored it in during Q1. The 25 cents we've added to guidance comes entirely from cost impacts. As you mentioned, that's diesel and the kwacha. About 20% of our cost base sits in kwacha, and over the past year we've clearly seen it strengthen considerably, moving from just under 30 to just under 20. Then on diesel, similarly, costs have risen sharply. In Q1 we were buying at around 80 cents, and by Q3 we've been purchasing at as much as $1.60, so because of that, we've built in that 25 cents. The impact splits roughly 50/50 between kwacha and diesel.

Operator

operator
#30

Alain Gabriel from Morgan Stanley is up next with a question. The floor is yours.

Alain Gabriel

analyst
#31

Yes, thanks for taking my question. Good morning and good afternoon, everyone. My first question goes back to Cobre Panamá. How realistic is it that the discussions will address the three buckets you laid out, Tristan, within the next seven or eight months that you've laid out until you fully exhaust the stockpiles? Practically speaking, how will you run the operations if the timelines slip by a few months? That's my first question.

Tristan Pascall

executive
#32

Thanks, Alain. Yes, those 3 areas are the main focus, and we've done considerable prep work on each element and have a solid grasp of the way forward there. We do need to engage with government and get a clear picture of where their priorities lie. I think as the recommendations come through, we're starting to see a clear picture. Getting through that will take time. As you say, yes, we feel good about the concrete milestones that have been achieved, and we keep acting in good faith on both sides. The arbitration was set aside, and certainly First Quantum has been committed to keeping the asset in good standing with respect to its environmental condition. We were investing about $13 to $15 million a month, and now that we're in the processing phase of the stockpiles, we're able to cover that cost, which was important, but ensure that we keep rehabilitating the site. On the government side, we've seen clear milestones around the enactment of the Preservation and Safe Management Plan, the export of concentrate, the restart of the power plant, and then the start and completion of the environmental audit, and now the ministerial recommendations and with the stockpiles in process.

Tristan Pascall

executive
#33

Yeah, we do have a schedule for that. We believe it's the proper step to make sure folks get a solid training program before them. We keep evaluating whether it makes sense to add the second train so that people have a solid grasp of the mine, employees and people are prepared, the community is prepared. We'll have to work through that negotiation process. For our part, we will definitely be constructive in pursuing a resolution as quickly as we can.

Alain Gabriel

analyst
#34

Thanks. That makes sense. My second question also concerns Taca Taca. You're still progressing the ESIA and the water permits, and you plan to file the application under RIGI, as you said. Could you remind us of the timelines, and how rigid are the balance sheet metrics or guardrails you've established that would let you sanction the project? When you weigh minority stake sales against partnerships, Vicuña-style, or just outright debt financing, what are your preferences for catalyzing the project?

Tristan Pascall

executive
#35

Okay, Alain — I'll take the first part, and then I'll turn to Ryan for the second part of the question about financing. On the milestones, those are quite clear. We have four main ones. First is the ESIA, with a public consultation scheduled for November, and at this point we keep seeing that move forward in the proper sequence, and we'd anticipate it being resolved shortly, within several months inside this year. Second is the RIGI application. We've been preparing it to ensure it's a high-quality submission. We're mindful of the deadline of 8th of July next year, so we'll be filing that shortly. Third is the financing, which you mentioned, and Ryan can address that further. Fourth is when we reach a decision. As you note, we'll be economically disciplined about it. We've stated publicly that we'd like our net EBITDA ratio to move down toward 1, and at this stage it keeps declining, and, given the strong third quarter, it sits in a very good position right now. We'll stay focused on that, and it matters for ensuring the balance sheet is well positioned alongside the financing pathway we've been developing.

Tristan Pascall

executive
#36

Ryan, you have the floor.

Ryan MacWilliam

executive
#37

As Tristan mentioned, it's good to see the balance sheet moving forward, with net debt to EBITDA at 2.6 times in Q3. To be clear, there's still a distance to cover. We'll stay disciplined and aim for roughly 1 times net debt to EBITDA ahead of project sanction. At the same time, we'll pursue financing alternatives. We've said that strategically we're open to partnerships across our asset base as we collaborate more with others, and that includes exploring such options at Taca Taca. If we take that path, it would be a minority stake, allowing us to bring our project execution capabilities to the asset. There are also various other alternatives open to us that we'll examine. The asset has very strong byproduct credits; streaming is one route. Project finance is certainly another route we're pursuing. We noted we announced the consultation agreement with IFC earlier this year, which backs project financing. It's really about giving ourselves a range of options and then evaluating which one is most attractive from a cost-of-capital standpoint and also a strategic standpoint. That's part of the work ahead of us in the coming period before a project sanction.

Operator

operator
#38

Deutsche Bank's Cody Hayden has our next question. The floor is yours.

Cody Hayden

analyst
#39

Yes, good afternoon, and thanks for taking my question. Just to return to Kansanshi very quickly, right now you're processing material that consumes less acid so as to maximize acid sales. I was wondering whether you could give us a little color on that strategy and the potential or acid production volumes in Q4, and then how this strategy could potentially impact copper production into 2027. Thank you.

Tristan Pascall

executive
#40

Absolutely. Ryan, would you mind handling that question coming from Cody?

Ryan MacWilliam

executive
#41

Cody, as you pointed out, the Middle East situation has created a really strong acid market, with prices averaging more than $400 in Q3. Because of that, we processed a bit less of the low-margin copper — roughly 1,000 increment, meaning 1,000 tonnes of copper production we gave up, and that let us generate 70,000 tonnes of acid, which we sold, and that brought in $33 million, or a 15 cents byproduct credit on our C1 costs. We expect to keep selling acid into Q4 and next year. In our Q4 guidance, we've taken a somewhat more conservative assumption. We assume sales of about 45,000 tonnes through the balance. Certainly, at any acid price above $200, we'll keep looking to sell excess acid. If those prices persist into next year, that will mean slightly lower copper production. As we noted in Q3, we've seen it have an impact of about 1,000 tonnes per quarter. How much of that we ultimately realize or push forward will really depend on how the acid market evolves over the next 12 months.

Cody Hayden

analyst
#42

All right, thanks.

Operator

operator
#43

Ian Rossouw from Barclays has our next question. The line is yours — please proceed.

Ian Rossouw

analyst
#44

Thanks. One more thing on Cobre Panamá. Earlier you talked about what we should expect regarding the timing of a full restart decision and the ramp-up to, I believe you said 80% over the following six to nine months — now that all the trains are commissioned, I wonder if you could give us an update on that. Over the longer term, I think you said it would always depend on whether you're able to reach the full employee complement, so I just wanted an update on how that's progressing.

Tristan Pascall

executive
#45

Yes, hi Ian. That's still accurate. What we're seeing — and I think you noticed it in the cost reduction we're referring to regarding the rehabilitation, going from $250 million down to $200 million — is that the asset is in solid shape. It was well maintained throughout the shutdown period, and most of the effort was really in man-hours spent on painting, welding, and reconditioning. We keep working our way through the back end of the plant, especially the columns and the concentrate areas. On the front end, yes, the three trains position. During the quarter, we mostly finished the SAG mill segment change-out on train 3. All of that work does show up in performance terms. From this point, we do believe we're still holding to that ramp-up timeline, the levels you mentioned, roughly 80%, 80% in six to nine months. Really, that comes down to the mining side of things. We have no drill and blast. We're running about seven trucks in a circuit, even though we've brought 18 trucks of the total into service at this stage. We need to go through all the trucks and then get all the operators and train them all up for a full mining operation, and we think that's where the time will be in reaching that six to nine months.

Tristan Pascall

executive
#46

After that, reaching full nameplate capacity at Cobre Panamá will require a great deal, just as it always has — optimizing the operation, having the screening plant up and running, and all the other pieces along the path toward 100 million tonnes per year.

Ian Rossouw

analyst
#47

Thanks. And perhaps just to follow up on that point, I believe earlier you mentioned a range of 350 to 500, sort of, counting the 250, which you've since cut to 200, for a complete restart. Does that figure still apply, and how ought we to think about that outlay? Is part of it weighted toward the front as you scale up the movement of material?

Tristan Pascall

executive
#48

Absolutely. Ryan, would you like to weigh in on that?

Ryan MacWilliam

executive
#49

Ian, just to pick up on that. We had said 250 for restarting the stockpile, and then a further 250 once we receive the formal go-ahead to return to operations. As you point out, we anticipate coming in under the first 250, at roughly $200 million. Our view hasn't changed that upon the full green light, we'll spend an additional 250, divided among building working capital, some capex, and then the commissioning costs as we go back into full operations.

Operator

operator
#50

The next person in the queue for questions is Matt Murphy of BMO Capital Markets. Go right ahead.

Matthew Murphy

analyst
#51

Hello. Could I ask a different question about Sentinel's production guidance? Regarding how long the ball mill is expected to be out of service next year, what analysis have you completed? Has that already been factored into the guidance?

Tristan Pascall

executive
#52

Thanks, Matt. Rudi, could you handle that one?

Rudi Badenhorst

executive
#53

Sure thing, Tristan. Hey, Matt, hope all is well with you. Yes, the replacement of the can on ball mill 2 at train 2 is planned for roughly the middle portion of next year. That's included in our plan, and the budget for it already sits within guidance. One thing worth noting: even though replacing that section at the back end of ball mill 2 is expected to take 30 to 40 days, it won't mean train 2 at Sentinel is fully stopped. The SAG mill will keep operating along with the whole train 1 milling circuit. Throughput will dip only slightly because that ball mill won't be available. It doesn't really have an effect on our overall production guidance for next year. We're quite far along in preparing for it. We're only waiting on the last few items to arrive at site, and then we'll get started.

Matthew Murphy

analyst
#54

Understood. Thanks, Rudi. Then one more thing about the Zambian kwacha and what it means for costs. I suppose we've watched it soften somewhat since the peaks we saw early in Q3. I'm not sure what your crystal ball shows for the Zambian kwacha going into next year. Would you look to hedge that, or do you hold any views on whether it might turn into a tailwind next year?

Tristan Pascall

executive
#55

Sure, Matt. Ryan, how about you field that one with your crystal balls?

Ryan MacWilliam

executive
#56

I'd say forecasting global exchange rates is usually a pretty murky business, Matt — I wouldn't want to call where the Zambian kwacha is headed. What we're seeing is that in the more risk-off environment globally over the last quarter, emerging market currencies took a hit, and the Zambian kwacha definitely wasn't immune to that. That gives us a modest tailwind on costs during the quarter. It's too soon to tell. When we do our planning, we assume a rate of roughly 18 to $20 kwacha to the dollar, and we don't expect any step change there over the next year. We'll certainly keep watching it. Hedging isn't something we do. I'd say the kwacha market, first, isn't very liquid for hedging purposes. Second, we're always quite wary about hedging exchange rates generally, because you can get squeezed if you haven't hedged the top line. At this point we're glad to be unhedged on both our revenue lines and our cost inputs, and we expect that to remain the case into the new year.

Tristan Pascall

executive
#57

I'd simply like to mention, Matt, that the election result is now clear to us, and in my view the market is acknowledging the continuity that exists. As far as what we're picking up regarding the expected naming of ministers and similar matters, there's a solid degree of continuity. Zambia keeps showing up as an attractive place for investment, and that also highlights the kwacha's strength along with the factors Ryan has raised. On the whole, we regard this as strongly favorable for the country. The performance we've witnessed should carry forward, and we are definitely embracing that as we look toward the period ahead.

Operator

operator
#58

We move now to Myles Allsop of UBS, who has our next question. The floor is yours. Myles Allsop, you're unmuted now.

Myles Allsop

analyst
#59

Oh, apologies for that—I had myself on mute. Returning to the interministerial report, which finding in it surprised you the most? The share price clearly reacted quite sharply. Then, could you maybe shed light on how long you had initially thought Panama would be running? Was that 25 years, or a longer period? Also regarding the footprint—of the existing footprint, what portion has been relocated as opposed to left as is, should that turn into a problem that limits output down the road? That covers the first question.

Tristan Pascall

executive
#60

Thanks, Myles. What the recommendations really showed was that the groundwork had been laid for a long-term closure, and that meant bringing the mine back into operation. The key piece there is negotiating a resolution to the arbitration, and also making sure that the communities near the mine — and the recommendations pointed out very plainly that those living around it were the hardest hit — are assured of continued robust environmental stewardship. Every one of those elements has to be in place. As for what caught people off guard that day, sure, there was plenty going on, but it serves as a reminder to actually read the document instead of reacting to headlines or to headlines posted up front. We definitely saw a lot of machine trading kick in as it set off stop-losses and so forth — on pretty thin volume, there was a sizable move. Again, the recommendations had clear components that were pretty simple. From our standpoint, obviously we keep pursuing the path toward resolving this matter constructively, and we're still working at it. Then, sorry, Myles, the second part of the first part of your question — what was that again? Oh, that

Myles Allsop

analyst
#61

What was the original intended operating life for Cobre Panamá, roughly, and how much ground has the mine disturbed up to now if you're limited by being unable to use the entire lease?

Tristan Pascall

executive
#62

Absolutely. Look, that's something we'll have to make clearer during the negotiations. We've taken note of that remark in the recommendations, and it's one of the things we'll need to grasp and talk through with the government.

Myles Allsop

analyst
#63

What was the initial intended lifespan for Cobre Panamá? Was it 25 years, or does the reserve resource, as I assume, extend considerably further?

Tristan Pascall

executive
#64

The original ESIA covered the three main pits, and with the reserves and resources surrounding them, it came in at roughly 32 years. Then, when higher throughput rates were applied, it dropped back somewhat. That gives you the order of magnitude from the earlier basis of approval. As for what lies ahead, there's obviously prospective ground around that area, but those zones weren't part of the original ESIA approval.

Operator

operator
#65

Anita Soni from CIBC has our next question. The line is yours.

Anita Soni

analyst
#66

Hello, and thank you for taking my question. Just to continue on that point, I want to confirm: the commission has advised that it's only what was part of the initial ESIA approval, correct? You're not able to go beyond that — so the mine life is 25 years at present, with no extensions? No,

Tristan Pascall

executive
#67

No, Anita. Hi, and thanks for asking. No, no timeline was included in that recommendation. What it provided was simply a worked example, and I think any discussion of timing here is speculation about what might be involved. It did acknowledge that getting things resolved and reactivated would require time, and we'll have to enter into a negotiation to figure out how that process works.

Anita Soni

analyst
#68

Beyond what the ESIA covers, does room still exist for additional phases?

Tristan Pascall

executive
#69

The ministers were quite explicit that the final footprint has to be smaller than what was agreed under Law 406, and as we get into conversation and negotiation, we'll need to see what that turns out to be.

Anita Soni

analyst
#70

All right. So my real question was simply this: have you had any engagement with Franco-Nevada as of now, and where do they stand in light of what the commission recommended? My assumption would have been that they were likely seeking a bit more upside from the investment they originally made in Cobre Panamá. I'm just curious whether any discussions have taken place with them since those recommendations came out?

Tristan Pascall

executive
#71

Thanks, Anita. Franco-Nevada plays a significant role here in getting this issue resolved. Together with our partners KORES, they are involved in the capital markets investment into Panama, and that is essentially how the global capital markets overall have contributed the funds for the investment in Cobre Panamá. Every one of us has an important part to play in resolving this matter constructively as we move ahead.

Operator

operator
#72

The next person to ask a question is Chris LaFemina from Jefferies. You have the floor.

Christopher LaFemina

analyst
#73

Hello there, and thanks. I have one more item regarding Panama. The notion of running that mine so it finances its own long-term closure — I suppose that holds true for every mine worldwide, but I'm curious whether there's something particular we ought to draw from it. Does it mean you would need to hold restricted cash inside the country in order to cover the closure? Clearly, this remains a matter you will keep negotiating with the government, yet what might it imply regarding how you guarantee funding while Panama commits no capital at any point? Restricted cash, or investments in Panama, or is it simply unknown at this stage?

Tristan Pascall

executive
#74

Thanks, Chris. The main point, I think, is that we’re looking at what the liability would be if there were a walkaway today, and how the State of Panama would handle that. Ryan, could you add any further detail on that?

Ryan MacWilliam

executive
#75

Chris, obviously there are all sorts of mechanisms that could get us there — guarantees, closure funds, or cash reserves. What’s been laid out as the principle is that closure must be funded responsibly, and that the money set aside for it has to be protected. As for which mechanism the government will ultimately choose to deliver that, we’ll need to wait for the specifics once we’re in those negotiations, and we’ll go into them constructively, since we share the government’s goal of seeing responsible provisions for closure put in place in due course.

Christopher LaFemina

analyst
#76

That's clear, thank you. And second, also regarding Cobre, Tristan, you brought up the earthquake earlier, which clearly is a priority for the government at this point. I'm just wondering what kind of delays to negotiations that might mean. Keep in mind, it was last year that social security reform was the government's priority, and they were going to turn to the mine afterward. Now we're in the process of, hopefully, getting the mine back online quite soon, and then the earthquake unfortunately hits. I think you may have said weeks rather than months when it comes to delays on that, but how should we be thinking about it? Thank you.

Tristan Pascall

executive
#77

Thanks, Chris. So yes, the effect was considerable. Fortunately, there was no major loss of life in Panama, but 19 of our employees are receiving support after their families lost their homes, so it has definitely made a mark, especially in Penonomé, which appears to be among the hardest-hit areas, and making sure those people get relief is rightly the government's priority at this moment. A great deal of work is going into that, and it matters. Beyond that, we expect the mine issue to return. I'd say the November holiday period in Panama, around the independence public holidays, is likely a key factor in that timeline, and we'll simply have to see which side of it things land on.

Operator

operator
#78

Thanks. That brings our Q&A portion to an end. At this point I'll hand things back to Tristan Pascall for some closing comments.

Tristan Pascall

executive
#79

Appreciate it, operator, and thanks to all of you for taking the time to be with us today. I hope the remainder of your day treats you well. Thanks.

Operator

operator
#80

That wraps up today’s conference call, everyone. Thanks for joining us. You’re free to disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete First Quantum Minerals Ltd. transcript — plus 133,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to First Quantum Minerals Ltd. earnings transcripts and 133,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in First Quantum Minerals Ltd. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.