Torben Kleinfeldt

executive
#1

Thanks a lot for that kind introduction, and I'd also like to extend my own warm welcome to Friedrich Vorwerk Group SE's Q3 earnings call. My name is Torben Kleinfeldt, and I serve as the group's CEO. I've spent close to 25 years working at Friedrich Vorwerk, and I bring 30 years of industry experience to the board. If this is your first time on the call, here's a quick overview of Friedrich Vorwerk. We concentrate entirely on delivering energy infrastructure projects, we've been active in the market for more than 60 years, and we have deep experience in our core markets—natural gas, electricity, and clean hydrogen—along with the other activities we bundle under our adjacent opportunities. Right now we have 16 sites in operation. This marks the first time we've had operations not only in Germany but also a permanent presence in the U.S., specifically Houston, Texas — I'll cover that in more detail later in the presentation. Yes. The big TSOs that handle electricity, natural gas, and hydrogen transmission across their grids are, naturally, still our primary customers. That said, our client roster extends to energy producers like E.ON and cable makers such as Prysmian and NKT, among others. So it's quite a broad range of customers we've been serving for many decades now. Because of the energy transition happening in Europe, our market has gotten a real boost in recent years, and we can still report a very comfortable and very large order backlog of more than EUR 1 billion at the close of Q3 2026. The backlog is a bit lower, of course, but we're still very proud and feel very good about the quality of what we have right here; so for anyone watching for the first time, what does Friedrich Vorwerk actually do? The next slide is fairly old by now, I think, but in the end it shows best what Friedrich Vorwerk is all about. This sketch shows our three main markets: natural gas transition at the top, electricity transition in the middle, and at the bottom of the slide, hydrogen transition — mainly for pipeline construction, so natural gas and hydrogen. We have the capability to engineer and also deliver large-scale pipeline projects across multiple diameters. Our company group can also put up storage facilities and, of course, highly specialized facilities such as compressor stations or gas pressure regulating stations, which are ultimately needed to run and operate these energy grids. In essence, the nature of what we do is quite comparable when it comes to natural gas as well as the hydrogen market—though naturally, for hydrogen, the transported commodity isn't something you can pull out of the ground; it must be manufactured by people. Since the early 2010s, Friedrich Vorwerk has been involved in what are known as power-to-gas facilities, meaning electrolyzers. Actually, in 2012 we became the first firm in Germany to construct a power-to-gas plant, and that was for E.ON. Today we're able to offer electrolyzers across a wide variety of capacity ranges—these are more or less container-based units that can be set up in plug-and-play fashion; we can also handle large-scale electrolyzers with capacities exceeding 100 MW. Beyond those three main markets, we're involved in some fairly interesting niches. Take drinking water infrastructure, for example, and district heating too — that's a key element in Germany when it comes to decarbonizing heating for the big cities. We also continue to have a robust unit focused on biomethane and the infrastructure around it. Along with biomethane, naturally, comes CO2 treatment and the development of CO2 transport. Perhaps to start, here's the most recent update on our markets and on recent government decisions, particularly in Germany. The first round for establishing new gas-fired power plants in Germany just closed — these plants are meant to back up renewable electricity generation during periods without wind or solar output. In the first round up to now, awards have gone to 11 new gas-fired power plants, with a particular concentration in the federal states of Brandenburg, Nordrhein-Westfalen, Sachsen, Bavaria, and Baden-Württemberg. These 11 gas-fired projects come to a total capacity slightly above 5 GW. Currently, the plan calls for finishing all 11 projects by late 2031. Naturally, given that Germany has committed to carbon neutrality after 2045, these plants will all need to operate on green hydrogen after 2045. However, the intention is for them to remain in use not just from 2031 to 2045, but in the years beyond that as well. Naturally, that opens substantial opportunities for our group as well, because on the plant construction side we can provide the fuel gas systems needed to supply these power stations, and it also generates fresh demand for building new high-pressure pipeline networks that will feed them. And there is more ahead. During Q2 2027, an additional approximately 4 GW is expected to go out for tender, followed by another 2 GW. Ultimately, that adds up to 11 GW of capacity and likely somewhere between 15 and 18 new gas-fired power plants. This is positive for us, I'd say, since in the end the gas-fired option beat battery storage facilities across all the projects—those facilities failed to satisfy the tender's requirements. On the European level, as we've pointed out previously, the EU has established several so-called cross-border energy infrastructure projects. They continue to maintain a list, the PCI/PMI list, which is available online, and they recently added 235 projects to it. Those projects naturally include large electricity interconnectors, but also numerous hydrogen pipelines as well as electrolyzer projects. Several of the projects featured on the PCI/PMI list are ones Friedrich Vorwerk is already involved in. Take HyPerLink, H2ercules, and other highly interesting efforts such as AquaDuctus and HyPipe Bavaria that are coming up over the next years. Then there is perhaps some less encouraging news from BNetzA, the body responsible for establishing the hydrogen core grid here in Germany. BNetzA, meaning the Bundesnetzagentur, is right now reviewing a delay affecting a couple of projects, something we had already anticipated when the decision was taken to set up the hydrogen core grid. The original plan called for the hydrogen core grid to be ready by 2032, and that has probably now moved to 2037, so five years later. Naturally, during this period the scope of the hydrogen core grid will also be reviewed by Bundesnetzagentur. So in some cases that could mean a slight brake on expansion of the hydrogen grid. With that, I will hand things over to Tim for the financial performance.

Tim Hameister

executive
#2

Right, thanks, Torben, and good afternoon everyone. Welcome to Friedrich Vorwerk's earnings call covering the Q3 figures. I'm Tim Hameister, CFO of Vorwerk, and I'm very pleased to take you through our once again exceptionally strong quarterly results, along with the updated outlook. Following a rather slow start to the year on the revenue side in the first quarter, owing to the weather conditions we already discussed, the summer quarters, Q2 and Q3, turned out all the better; in both of those quarters we gained from favorable weather and extremely high resource utilization, which meant third-quarter revenue hit another record high of EUR 228 million. That was achieved even though the revenue share from our major EnBW project kept steadily declining. As in prior years, a key driver behind this continued growth is the rise in our workforce, up 8% since the beginning of the year, while the average workforce has grown by 13% versus the same period last year. On the revenue breakdown, the electricity segment was the strongest once again, making up 51% of total revenue, with natural gas next at 30% and adjacent opportunities at 16%. The hydrogen segment's share will rise significantly beginning next year, once the projects already secured this year move into the construction phase. Given the continuing uncertainty around overhead lines versus underground cables, let me take this opportunity to stress once more that significant portions of the electricity segments we are looking at come from plant construction projects, specifically substations and cable transition facilities, as well as offshore connection systems, none of which are affected by the current draft bill. Overall, there have also been no further debates on this topic so far since the summer break, neither in the Bundestag nor in the Bundesrat. In addition, since the start of the year we have been reporting a new KPI, known as production output, which besides revenue includes the proportionate revenue from our JVs, or Arbeitsgemeinschaften. Because the contract structure has increasingly shifted toward these JVs over the last two years, given the growing scale and complexity of the projects, we believe this key figure offers a more transparent view of our business performance. In the first nine months of the year, production output improved by 40% to EUR 791 million, which represents significantly stronger growth than revenue. Looking at the breakdown by segment, it becomes clear that a very large number of these JVs has been formed, especially in the natural gas and clean hydrogen segments. Profitability, however, showed particularly strong growth in Q3. EBITDA increased by 58% to EUR 80.9 million, corresponding to a margin of 35.4%, which again represents a quarterly record for Vorwerk in both absolute and relative terms. The EBIT margin rose by almost 13 percentage points to a new record high of 31.9%, corresponding to EUR 70.8 million in EBIT alone in the third quarter. What really drove this excellent result is that we've been able to bring the materials cost ratio down considerably while turnover has climbed sharply; put differently, delivering our services took fewer materials and fewer subcontractors. Materials costs went up just 2% versus the prior year, which lifted the materials cost ratio from 44.5% to 40% during the reporting period. Growing our own value chain stays central to our growth strategy, done both organically and via acquisitions; on top of buying meterQ in August this year, a maker of process gas chromatographs, we closed one more small deal with RAPA in September, reinforcing our standing in inner city construction projects; at the same time, we are busy on further topics and projects that will let us raise the level of value we create. Back to Q3 profitability: another major driver of the better profitability is the growing share of profits we book from joint ventures, up from EUR 6 million in Q3 2025 to EUR 16 million in Q3 2026. As a result, we posted EBITDA of EUR 173.4 million across the first nine months, at a margin of 30.7%, along with EBIT of almost EUR 150 million, which brings us to the updated guidance. Because of that excellent performance, above all in the third quarter, we raised our guidance for the 2026 fiscal year once more last month. So we now anticipate EBITDA between EUR 220 million and EUR 230 million, having previously guided to EUR 180 million-EUR 200 million, and revenues now between EUR 760 million and EUR 790 million; this outlook already reflects weather-related uncertainties in the fourth quarter, especially December, and ought to be reasonably achievable. The order intake picture is mixed. Although the conventional order intake number edged up, total project volume won in the first nine months came in roughly 30% under last year's level. That means we have locked in plenty of small and medium-sized projects, yet booked very few large-scale ones, which normally come through these JV structures. The main cause is the timing volatility of tender procedures in our industry. Still, plenty of interesting projects remain in the pipeline right now, and some should be awarded before Christmas. In spite of the high turnover, and the very high production output, the order book stays at a high level. With total project volume above EUR 1.2 billion as of September, we remain in a very strong position heading into 2027. I have no doubt that none of our employees will be bored in the years ahead. Let me now hand it back to Torben for some updates on the ongoing projects and our new subsidiaries.

Torben Kleinfeldt

executive
#3

Yes, Tim, many thanks. I'd like to begin with the big pipeline construction project we're doing for Gasunie Deutschland, which is completely underway. The ETL 182, a large-diameter pipeline, is about 50% complete; we'll pause for the winter break in mid-December shortly, but progress has pleased us greatly, and we're particularly proud of the welding work on ETL 182. That welding is likewise performed by our subsidiary 5C-Tech, with extremely high weld quality and very solid progress to date. As for the smaller line that links ETL 182 with the Stade facilities, it must be completed before Christmas so it can take up new regasified LNG from the Stade LNG terminal. Even though this year's schedule was extremely demanding, and we faced some early delays related to permitting, we managed to catch up, and we've just completed the pressure test; right now we're drying the pipeline, so handover to the customer should happen perhaps a couple of weeks ahead of plan. We're very pleased with both pipeline projects, and yes, there's notably more work ahead, particularly from Gasunie. With other clients too, we're currently bidding on some highly interesting projects that begin in mid-2027, with the main execution phase following in 2028. The next project is also quite remarkable: a water pipeline of very large diameter, run by RWE. Known as the Bündelungsleitung, this pipeline will carry water from the River Rhine to fill the old lignite mines, which originally came about through coal extraction from the ground. It will then operate for over 60 years, moving a great deal of water from the Rhine into those former coal mines. Friedrich Vorwerk is currently involved in lot two of this project, where we must lay nearly 4 km of very large diameter steel pipeline, 88 inch, or 2.2 meters in diameter. Here as well, welding expertise and technology come from our 5C-Tech subsidiary. At present this too is on schedule and of very high quality, and the client has acknowledged the high standard of our work here. Perhaps I'll turn now to our most recent M&A acquisition. As you're aware, Friedrich Vorwerk is also active in cities, chiefly Hamburg, Bremen, and Halle, Leipzig. Naturally, since we find plenty of asphalt roads in these cities and the main district heating pipelines and the large cable system are engineered and laid beneath the paved roads, it's always required to cut open those roads for the civil works and subsequently the pipe laying. Typically, we deploy asphalt mills to open up these roads. With RAPA Baudienst — a small Hamburg-based company — we now have our own machinery as well as personnel in-house, so we can handle the first step of executing our projects ourselves, namely asphalt milling in the major cities. Second, the M&A target — it isn't really an M&A target. I'd describe it as an extension of what 5C-Tech does: it's our move to go beyond Europe and set up a joint venture in the U.S., and that's what we did over the summer. The JV sits in Houston, Texas. Out of that Houston, Texas location, we'll serve markets across America and Canada, and in Middle and South America too. The first project we've already secured in America is a 48-inch pipeline, due to begin operation in January. Right now we're readying all the equipment we need and working through the procedures to obtain the permit for welding in the U.S.; we've developed special welding technologies that the U.S. requires for a very high welding pace. We aren't aiming, as we do here in Europe, at a pace of up to 30 welds. In the U.S. we're aiming more at a pace in welding terms of 120 welds a shift and beyond. That technology is available right now, and it will soon be tested and then brought to the U.S. market. So that's a very nice development for 5C-Tech as well. The last slide covers expansion of our workforce. We had made a plan to slow the growth of our workforce a little this year, but because of the large projects and also smaller work coming in, we've still added 8% to our employees since the start of the year, and I think that's a figure we'll also see at year's end. The actual plan was to run growth of about 5%-6%, but okay, now we have another 8% on board, and I think that will also help with the upcoming projects over the next two years. So we're actually done with our presentation, and we're ready to take your questions.

Tim Hameister

executive
#4

Like I mentioned, the sector we operate in doesn’t follow a linear path when it comes to order processes; delays do pop up from time to time in certain tender procedures. Conditions in the market remain highly favorable across every segment. In fact, the natural gas segment has been expanding lately. As I noted earlier, we anticipate additional, and possibly bigger, awards, perhaps even prior to Christmas. That leaves us fairly confident about seeing order intake numbers rise over the coming months. When it comes to capital allocation, our priorities haven’t shifted since recent quarters. Investing in organic growth remains our top priority, particularly in new drilling rigs, welding equipment, cranes, and so on. Some excess cash will remain, so we’re also pursuing further M&A acquisitions; we would be glad to complete a bigger M&A deal too, provided we identify the right target at a sensible price level. Lastly, we will certainly share the company’s success with shareholders—through, for instance, a higher dividend payout, as we already did in 2026 with the extra special dividend, or perhaps eventually a share buyback program, for which we already hold the required approvals from our annual general meeting. Well, I believe we can reach double-digit millions in revenue from the U.S. business alone as early as 2028; so that’s a very rapid development there. We’re also exploring new international markets, not just for welding technology but also, for instance, for our drilling technology.

Torben Kleinfeldt

executive
#5

So ultimately, we’re already involved in plenty of plant construction projects where we bring our E&I technology along as well—meaning programming for the plants and building out the control panels for those plants. That’s a space we’re already working in. A nearby opportunity—and probably where the most potential sits over the coming years—is district heating, since every city has to put together a plan for how it will decarbonize its residential areas and its businesses; that will be our main focus in the years ahead. But I also expect that over the midterm, CO2 capturing for certain industries—the cement industry, for instance—and then also establishing a CO2 infrastructure will be a very interesting area for our company.

Lasse Stüben

analyst
#6

Hello there, good afternoon. I have two questions, if I may. Regarding the Q4 outlook, the guidance suggests a fairly significant decline in EBITDA, both where margin is concerned and in absolute dollars. I'm curious whether there's some kind of special mix impact coming from the JV contributions, or whether you're simply erring a little on the cautious side given that weather in the quarter is typically worse? My second question concerns how we should think about that JV contribution going into next year. Should we assume roughly a comparable share or mix of projects falling under that structure next year? Or what's your thinking there? Thank you.

Tim Hameister

executive
#7

Well, yes, regarding Q4 and the guidance implied for 2026, we have factored in, as I mentioned, the effects or uncertainties tied to weather. Beyond weather, we also built in certain uncertainties concerning how the upcoming contract amendment negotiations will turn out. Of course, also with Q4, JV profits won't be as high as they were in Q3. I mean, in Q3 we saw an exceptionally strong quarter with a 35% EBITDA margin, and that simply can't be taken as the new baseline for the remaining or upcoming quarters. Under the current guidance, we sit more or less at the same EBITDA level as Q2, with these weather-related factors already accounted for. So I think it's quite a good guidance.

Torben Kleinfeldt

executive
#8

Yeah, just remember that the fourth quarter ends up being two weeks shorter than every other quarter because of Christmas.

Tim Hameister

executive
#9

Yes, regarding the 2027 mix, it's fair to expect roughly the same split between JV projects and our own projects that we're seeing in 2026.

Lasse Stüben

analyst
#10

All right, great. Perhaps just one more question. Have you begun to release any loss provisions tied to the A-Nord project, or does that still lie ahead? Could you share anything about a possible bonus for A-Nord in the coming year?

Tim Hameister

executive
#11

Well, that bonus gets determined only once the project has fully ended, so we still expect that to occur in the summer of 2027. The maximum potential impact from it, as I would currently assume, could fall in the low double-digit million EUR range for Vorwerk. We haven't yet adjusted the provisions on the balance sheet for A-Nord, so that will either be handled in Q4 in consultation with the auditors or possibly even next year.

Lasse Stüben

analyst
#12

All right, thanks.

Tim Hameister

executive
#13

So, like I mentioned, the hit from the bigger JV share came to roughly EUR 10 million in net profit during Q3 alone, which accounts for a sizable chunk of the profitability gain. Because of how the JVs are accounted for, we'd suggest focusing on absolute EBITDA growth rather than the EBITDA margin, since those JV effects tend to inflate the margin somewhat.

Torben Kleinfeldt

executive
#14

Yes, particularly when it comes to the core grid and hydrogen. Those projects are essentially locked into the grid development plan. And that's really what we expected from the outset once the plan had been put together — that completing the core grid by 2032 was extremely ambitious, considering how long permitting takes for building this kind of energy infrastructure. I believe the plan to now revise the entire core grid setup and land on 2037 was broadly necessary, and we had already factored it into our midterm planning. On the core grid side, I don't think we've seen any projects dropped from the grid development plan. When it comes to electrolyzers — hydrogen production — yes, we saw a handful of projects that didn't reach the final investment decision stage, but right now we're still tendering for quite a few electrolyzer projects. My view is that there will be some time delay, but we'll see a few additional projects carried out next year.

Tim Hameister

executive
#15

We remain pretty pleased with the pricing levels as well in tender procedures that are currently ongoing right now.

Torben Kleinfeldt

executive
#16

Right now, we're looking at several very large tenders for building transformer stations, and those could be quite interesting and would give us a really solid base load for the next years as well, even the upcoming ones; but also, at the moment, still in natural gas, there are some quite attractive projects coming up here in Germany, in the middle of Europe, and in Northern Europe too. So these projects look very interesting to us. Naturally, activities around 5C-Tech, particularly in the U.S. and in Southern America, could be quite interesting. Naturally, every welding service carries very low risk and comes with really attractive margins.

Torben Kleinfeldt

executive
#17

We're also considering targets in other countries, yes, and we've actually done that for years already. Right now, though, I believe that with 5C-Tech's technology, we'll begin providing welding services from there, and after that we'll watch how our operations in the U.S. evolve, since plenty of large-scale pipeline projects are underway as well as LNG liquefaction projects at present. That could make it a really compelling market, not just for welding services but for plant construction too, and for supplying specific equipment items that are needed, for instance, when liquefying LNG.

Torben Kleinfeldt

executive
#18

As we discussed earlier, we’ve observed general construction firms moving into the market to execute electricity lines. Because volume in this market has been so high over the last month, we haven’t seen any effect on pricing here. In the pipeline market—so natural gas and also hydrogen—we haven’t seen any additional competition. I’d say the usual pipeline construction companies, so this market is as it is, and we haven’t seen any changes to this market at all.

Torben Kleinfeldt

executive
#19

Thanks so much for tuning in today. We're feeling a lot of anticipation about this year, and we're extremely, extremely pleased with the strong results we delivered this year across every project. I believe everyone on our team performed really, really well. I'd say we're 100% satisfied with it. I hope you feel the same way. Please stick around with us, and we'll look forward to hearing from you next year. Bye-bye.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Friedrich Vorwerk Group SE transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Friedrich Vorwerk Group SE earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Friedrich Vorwerk Group SE or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.