Good morning, everyone, and thanks for joining the G Mining Ventures conference call on our first quarter 2026 results. Everyone on the line is in listen-only mode for now. After the prepared remarks, we'll open up the lines for your questions. Just a note that this call is being recorded today. At this point I'll hand things over to Jean-François Lemonde, our Vice President of Investor Relations.

Jean-François Lemonde

executive
#2

Thanks, operator, and I appreciate everyone joining us for G Mining's conference call on first quarter 2026 financial results. Along with me on the line are Louis-Pierre Gignac, our Chief Executive Officer and Director, and Julie Lafleur, Chief Financial Officer and Vice President of Finance. Just a reminder that following management's remarks, we'll open things up for a Q&A session. During this call we'll be making forward-looking statements, so please see the cautionary notes and risk disclosure in our MD&A as well as on slide 2 of this webcast presentation. Also, please keep in mind that unless otherwise noted, every dollar figure mentioned on this conference call is in US dollars. With that, I'll hand things over to Louis-Pierre for an overview.

Louis-Pierre Gignac

executive
#3

Good morning, and thank you, JF, and thanks to all of you for being with us today. First, I'd like to acknowledge how dedicated our teams are at every one of our sites — their commitment to safety, to operational excellence, and to responsible mining keeps driving our success. Q1 2026 was a solid quarter for G Mining, with strong operational performance and elevated gold prices underpinning robust financial results. Production of 31,846 ounces came in line with our plan, and 33,776 ounces were sold. We expect progressive improvements as we move through the year, since stripping activity continues to open up access to higher-grade ore through the remainder of the year. We continue to deliver strong margins, with an all-in sustaining cost of $1,588 per ounce, compared to an average realized gold price of $4,143 per ounce. TZ generated $56 million of free cash flow, which works out to $1,764 per ounce of gold produced. We ended the quarter with $287 million cash and $248 million in net cash. We are reiterating our 2026 production and cost guidance, with production expected to be weighted approximately 38% and 62% between the first and second halves of the year, respectively. Through the year, we'll stay focused on our margins and on maximizing free cash flow for every ounce that we produce.

Louis-Pierre Gignac

executive
#4

Beyond that, the planned purchase of G2 Goldfields would allow for the consolidation of a whole mining district, bringing Oko West and Oko-Aremu together as one integrated Tier 1 asset. As a combined operation, the project could yield over 500,000 ounces of gold each year across the mine's life. This deal delivers a step change in both scale and output, with visibility toward exceeding 700,000 ounces annually by 2029 — and that is before Gurupi is factored in — speeding G Mining's move toward mid-tier producer status. Q4 production came in lower, as anticipated, because of reduced process grades as we push the pit forward and carry out more stripping to gain access to Phase 2 ore. That work underpins the stronger output profile we expect during the second half of the year. The plant kept performing well. Throughput matched the plan, and recovery held steady given the lower-grade ore we processed. At TZ, mining stayed robust in the first quarter, with 5.5 million tonnes mined, 1 million tonnes of which was ore, for a strip ratio of 4.4. That compares with 2.45 in Q4 of 2025 and 1.45 in Q1 of 2025. The higher strip ratio was expected and mirrors the planned waste stripping meant to ready the mine for the higher-grade ore profile anticipated in the second half of the year.

Louis-Pierre Gignac

executive
#5

We anticipate the second quarter will track similarly to the first, with our operational focus remaining on mining productivity and keeping sufficient drill and blast inventory on hand. As Q2 concludes, we'll move out of the rainy season and into the dry season, which should help our mining activities. Total cash costs came in at $1,034 per ounce, while all-in sustaining costs were $1,588 per ounce sold. This quarter's costs rose because of lower gold sales, higher gold-linked royalties, and a stronger Brazilian real. Importantly, we expect full-year costs to stay inside our guided all-in sustaining cost range of $1,230 to $1,440 per ounce. Safety performance at TZ stayed strong, with no lost-time injuries this quarter. With that, I'll now hand things over to Julie to walk you through the financial results, cash flow, and balance sheet.

Julie Lafleur

executive
#6

Thanks, Louis-Pierre, and good morning to all of you. Q1's financial results show robust operating margins, tight cost discipline, and TZ's ability to generate cash. We brought in $140 million in revenue, selling 33,776 ounces at an average realized gold price of $4,143 per ounce. A $10.7 million non-cash adjustment tied to the gold streaming agreement — prompted by higher mining reserves — lowered revenue for the quarter. Net income came to $80.4 million, equal to 35 cents per basic share and 34 cents per diluted share. Adjusted net income stood at $62 million, or 27 cents per share. EBITDA reached $114.1 million, while adjusted EBITDA was $97.7 million. Free cash flow for the quarter totaled $56.2 million, or 24 cents per share. Given that production was lower this quarter, these financial results were strong. TZ kept generating cash as we move Oko West forward and funded exploration throughout the portfolio. Operating activities provided $69.7 million in cash during the quarter, and free cash flow came to $56.2 million after sustaining capital and other adjustments. Investing activities used $119.5 million in cash this quarter, mainly reflecting construction spending at Oko West. Financing activities provided $208 million in cash, chiefly reflecting the La Mancha top-up investment, net of debt repayment.

Julie Lafleur

executive
#7

Our cash and cash equivalents rose to $287 million at March 31st, 2026, up from $135 million at year-end. We also went from net debt of $6.9 million at year-end to net cash of $248 million at quarter-end. With the undrawn $350 million revolving credit facility included, available liquidity came to approximately $638 million. That liquidity gives us flexibility as Oko West moves through peak construction spend, while letting us keep funding exploration and maintain balance sheet strength. Capital expenditure came to $108 million in the first quarter. At TZ, sustaining capital was $13.5 million, including capitalized waste stripping. At Oko West, we invested $88 million during the quarter. Cumulative spend reached approximately $292 million, or about 30% of the approved initial capital budget. Total commitments reached approximately $525 million, or 54% of the approved budget. This is a meaningful de-risking point, because more than half of the initial capital budget has moved into committed scope. Oko West capital guidance remains unchanged, with $514 million to $568 million expected in 2026 and $217 million to $240 million expected in 2027. Exploration spending was $6 million in the quarter across TZ, Oko West, and Gurupi. Activities are expected to increase through the remainder of the year as we advance our 2026 exploration program.

Julie Lafleur

executive
#8

Capital allocation is still centered on funding Oko West, putting money into exploration where potential looks strong, and keeping financial flexibility intact. Q1 production came in at roughly 18% of the midpoint of annual guidance, which aligns with the anticipated output profile weighted about 38% toward the first half and 62% toward the second half, reflecting the planned grade progression at TZ. Our 2026 production guidance is unchanged at 160,000 to 190,000 ounces of gold. For 2026, total cash cost guidance stays at $736 to $865 per ounce sold, and AISC guidance stays at $1,230 to $1,444 per ounce sold. As Louis-Pierre discussed, Q1 costs exceeded the annual guidance range owing to lower production volumes, higher gold-linked royalties, and the stronger Brazilian real. As output rises in the second half of the year, we anticipate unit costs will improve. For 2027, production guidance is 200,000 to 235,000 ounces of gold. Total cash costs are expected to fall to $633 to $743 per ounce sold, and AISC is expected to fall to $977 to $1,146 per ounce sold. The 2027 profile reflects a full year of higher-grade Phase 2 contribution, lower sustaining capital versus 2026, and continued operating maturity at TZ. With that, I will hand it back to Louis-Pierre to discuss Oko West and Gurupi.

Louis-Pierre Gignac

executive
#9

Thanks, Julie. I'll turn now to our growth project, Oko West. During the quarter, Oko West kept moving forward on schedule and within budget. At the close of Q1, overall project progress stood at 19.7% on an earned value basis, and both engineering and procurement had each reached roughly 80%. We've spent around $292 million and committed around $525 million, which equals 54% of the approved initial capital budget. That rising share of committed capital mirrors the project's continued advancement and the awarding of major procurement packages, locking in long-lead equipment, while pricing stays in line with expectations. On site, Oko West is still making solid progress even with the heavy rainfall season. Earthworks are well along, and concrete works are advancing steadily across the process plant and other key infrastructure areas. With foundations moving ahead, steel erection activity can now begin in earnest, starting with the truck shop and the assembly of tanks in the process plant areas. Project logistics also made headway during the quarter. With the access road bridge finished and the barge landing infrastructure commissioned, we're better able to receive and transport major equipment and materials to site. Power infrastructure development is coming along well, and delivery of the first power generators is expected throughout Q2, roughly two months ahead of schedule.

Louis-Pierre Gignac

executive
#10

The power plant is still on schedule to be up and running by July 2027. Over at the tailings storage facility, clearing work is now 36% complete, and foundation prep for the main tailings dam keeps moving forward. We plan to start placing fill material in Q2. Our workforce kept expanding over the quarter. We now have 1,379 people on site, Guyanese nationals make up 82% of that workforce, and cumulative hours worked have passed 1.6 million on the project to date. The current Oko West project is still on schedule, with first gold targeted for the second half of 2027 and commercial production expected in January 2028. The process plant remains on the project's critical path. Thanks to recent progress, the project is positioned to move into mechanical installation in the grinding area, with grinding mills expected to arrive in July 2026 and commissioning targeted for August 2027. Every one of these milestones supports the path to first gold. Our focus is on continuing to turn the schedule into completed fieldwork while staying disciplined on safety, cost, and quality. I'll wrap up with our priorities for the rest of 2026 and into 2027. At TZ, the priority is delivering the planned second-half production profile and bringing unit costs down.

Louis-Pierre Gignac

executive
#11

Our key focus areas include Phase 2 access, mining productivity, drill and blast inventory, plant throughput, recovery, and sustaining capital execution. At Oko West, what matters most is mill deliveries, power infrastructure, ongoing camp expansion, process plant construction, TSF work, and logistics readiness. At Gurupi, the main deliverables consist of the updated mineral resource estimate, the preliminary economic assessment, and filing the EIA before year-end. For G2, our priorities are closing the transaction, keeping the Oko West schedule on track, and moving forward the technical work needed to validate the combined district plan. We are heading into the next phase with a stronger balance sheet, a producing mine that generates cash flow, and Oko West progressing well through construction. The assets, liquidity, and team we need to carry out this next phase of growth are in place. Operator, we are ready for questions.

Operator

operator
#12

Thank you. We're moving into the question-and-answer portion now. If you'd like to pose a question, simply hit *1 on your phone's keypad. Should you wish to pull your question, hit *1 once more. We'd appreciate it if you kept to a single question plus one follow-up, and we'll take a brief pause to put the queue together. Our first question is from Fahad Tariq at Jefferies. Your line is open.

Fahad Tariq

analyst
#13

Hello, and thank you for taking my question. Could you perhaps discuss how sensitive things are to the elevated energy prices? My understanding is that it's roughly $10 an ounce for each 10% shift in the oil price, but please remind us what the budget was at the start of the year, what was assumed, and how that is trending now. Thank you.

Louis-Pierre Gignac

executive
#14

Absolutely. For 2026, we had assumed diesel would run around $1 per liter, and that accounts for roughly 10% of our cash costs. In Q1, the real figure came in at $1.13, which works out to about 12% of cash costs for that quarter. As you noted, a 10% rise translates to roughly $11 per ounce, so your $10 is quite consistent with that sensitivity.

Fahad Tariq

analyst
#15

And perhaps to build on that point — since you're roughly at the peak construction stage at Oko West, are any of those cost pressures starting to show up as a result of the higher energy prices?

Louis-Pierre Gignac

executive
#16

Logistics expenses are affected slightly, yet on the whole the impact is really quite minimal when it comes to every one of the major equipment packages we have bought. Those were awarded some time back, and we aren't seeing that carry through into the large expenditures we carry.

Fahad Tariq

analyst
#17

So perhaps just one additional question for Julie regarding accounting. Regarding that non-cash revenue adjustment tied to the Franco stream, would it be reasonable to expect that whenever reserves continue to grow, that negative adjustment will show up, since my understanding is that it reflects the upfront consideration as well as the deferred revenue?

Julie Lafleur

executive
#18

Exactly, that's spot on. Should those reserves — which is really welcome news — keep growing as time goes on, then yes, we'd like to see that catch-up adjustment appear. Still, we must keep in mind that this stream is going to run down down the road, and it will revert to revenue. Really, it amounts to a timing difference above all else, and it's non-cash. As you put it, this is purely an accounting matter.

Fahad Tariq

analyst
#19

Yeah, understood. That’s great. Thanks a lot.

Julie Lafleur

executive
#20

Glad to have you all here.

Operator

operator
#21

Ralph Profiti from Stifel has the next question. Your line is open now. Oh,

Ralph Profiti

analyst
#22

Thanks, operator. Good morning, and thanks for taking my questions. Louis-Pierre, there have been some stories about wage and union increases around some other mining operations in and around the area in Guyana. Just wondering on sort of labor productivity, labor engagement, labor inflation, just what's been your experience in the past few, say, weeks and months, and sort of looking forward into next year?

Louis-Pierre Gignac

executive
#23

At Oko West right now, I'd say there's no union in place. During a construction phase, that's usually how it works. We do anticipate a union potentially being established once we move into the operations phase. At present, no collective bargaining agreement exists. What I'd note is that recruitment keeps moving forward, consistent with the workforce plan we've laid out for the project. Essentially, we can bring people on under the wage scales we've established for this project. So far, nothing significant has caught us off guard. Generally, we try to hire from the local area whenever possible, and if we can't locate the skilled people we need, we broaden the search somewhat, beginning with CARICOM nations like Suriname, and after that we look at other expat roles, in places such as Canada and beyond. To date, on the labor side, things are tracking within our project budget.

Ralph Profiti

analyst
#24

That's really encouraging, thanks. Following up on that — as you get close to the last part of detailed engineering, you cited the 80% mark, and I'm curious whether any float items are still outstanding, particularly as you potentially expect G2 Goldfields to join from a corporate, mining, and engineering standpoint. How are you feeling about that Q3 '26 target for finalizing detailed engineering?

Louis-Pierre Gignac

executive
#25

What we're always aiming to do is carry out what I'll refer to as Phase 1, meaning the Oko West project in its current form. That detailed engineering will be completed so we can finalize construction of what we're undertaking. Once the G2 transaction closes, we intend to basically restart the feasibility stage in order to define the expansion we want to carry out. At that point it will form part of a separate budget, along with a capital budget, for executing that expansion. We really view it as a Phase 2, and then we'll be reporting further details on it once that technical study is finished.

Ralph Profiti

analyst
#26

Perfect. Yeah, I’m all set on my end. Thanks a lot.

Louis-Pierre Gignac

executive
#27

Appreciate it.

Operator

operator
#28

Anita Soni from CIBC Capital Markets has the next question. Your line is open.

Anita Soni

analyst
#29

Morning, LP and team. I wanted to ask about TZ specifically — what are your stockpile levels right now, and what grade is that stockpile?

Louis-Pierre Gignac

executive
#30

That figure isn't right in front of me, though it represents nearly 2 years of processing capacity. Our stockpiles are substantial. My recollection is roughly 7 million tonnes. At any moment, material is always on hand to feed the plant, and yes. Since we began mining—and for the coming couple of years—part of our mining strategy is essentially to stockpile lower-grade material while processing the higher grade. As you can imagine, in this Q1, as we advance waste stripping, we did draw somewhat from stockpile, but even then ore remained accessible to us throughout the quarter. Then

Anita Soni

analyst
#31

Regarding the mill's throughput, does it have extra capacity to handle somewhat more volume?

Louis-Pierre Gignac

executive
#32

With the sustaining capex program we have in place, we continue to believe we'll be expanding our capacity for pumping flotation tailings. Right now, we view that as a bottleneck in the process plant. After we complete that project — which will land more toward the end of Q2, Q3 — we expect to be able to move more tonnage through the plant. That's solely because we see some continued upside from the program we're putting into action this year.

Anita Soni

analyst
#33

Second, I'd like to ask about costs. How do you expect those to develop overall? Mainly, of course, the processing plant — as it achieves greater throughput, those unclear costs you're absorbing should come down — but my focus was somewhat more on mining costs, which rose a bit this quarter?

Louis-Pierre Gignac

executive
#34

Apologies, I didn't quite catch the whole question, but regarding mining costs for the quarter, they did come in somewhat higher, which is fairly typical for us during the rainy season. By Q2 we're basically coming out of the rainy season near the end of that quarter, and costs usually decline thanks to somewhat better productivity — mainly because road maintenance expenses are lower and tire usage improves considerably once the rainy season ends. Those are among the sensitivities we see in our mining cost.

Anita Soni

analyst
#35

And finally, regarding Oko, please remind me — I'm certain it's been mentioned somewhere — but when do you anticipate completing an integrated study and the key deliverables toward that goal during this year?

Louis-Pierre Gignac

executive
#36

I would say no exact date has been set for when we expect a technical report to come out on the integrated project, but at a high level we're scheduling mid-2027. That timing really hinges on finishing the infill drilling required to move the inferred resource up to indicated category so it can be folded into the feasibility. G2 is carrying out infill drilling at present, and after the transaction closes we'll assess where that program stands and will need to continue it. Once the deal closes, we'll have clearer visibility on how much work remains and when we can complete it. At a high level, our target is to have that study finished by mid-2027. Alongside the infill drilling, we also need to finish some metallurgical test work and geotechnical studies so we can deliver a feasibility-level integrated project. Those are among the main work streams.

Anita Soni

analyst
#37

Appreciate it. That wraps up what I wanted to ask.

Operator

operator
#38

Once more, should you wish to pose a question, please press *1 on your phone’s keypad. Since the phone line has no further questions right now, we’ll move on to questions submitted online. One has come in via the web: “Could you address AISC and C1 looking ahead? Given that this quarter came in above guidance, do we expect the remaining quarters to bring the average down so that AISC stays in line?”

Louis-Pierre Gignac

executive
#39

Right. This is an impact tied to gold production. During the second half, as we access better grades, gold output will rise, and that should push our average AISC down in that period, essentially putting us within the range we guided to for the year. That's what we expect at this point.

Operator

operator
#40

That brings our Q&A portion to an end. At this point I'll hand the call back to Jean-François Lemonde, who has some closing remarks for us.

Jean-François Lemonde

executive
#41

Thanks, operator, and I appreciate all of you being here for G Mining Ventures' conference call on our First Quarter 2026 results. Within 24 hours, a replay is going to be posted on our Investor Relations website. If any follow-up questions come up, please don't hesitate to get in touch with the IR team. Have a great day.

Operator

operator
#42

That wraps up today’s conference call, everyone. We appreciate each of you for taking part. You’re free to hang up at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete G Mining Ventures Corp. transcript — plus 133,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to G Mining Ventures Corp. earnings transcripts and 133,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in G Mining Ventures Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.