Garden Reach Shipbuilders & Engineers Limited (GRSE) Earnings Call Transcript & Summary

June 9, 2020

National Stock Exchange of India IN Industrials Aerospace and Defense earnings 101 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, ladies and gentlemen. I'm Inba, and I'll be moderating this conference. Welcome to the conference call for Garden Reach Shipbuilders & Engineers Limited, organized by Concept Investor Relations, where we'll be discussing the Q4 and FY '20 results. Joining us today are Rear Admiral Shri VK Saxena (Retired), Chairman and Managing Director, along with Shri Sarvjit Singh Dogra, Director, Finance. <<operator_script>> Kindly be aware that this conference is being recorded. At this point, I'd like to turn the conference over to Mr. Irfan Raeen. Thank you, and the floor is yours, sir.

Irfan Raeen

unknown
#2

Hello, everyone, and good morning. We appreciate your making time to join the Q4 and FY 2020 Conference Call for Garden Reach Shipbuilders & Engineers Limited. Joining us are Mr. VK Saxena, the company's Chairman and Managing Director, along with Mr. Sarvjit Singh Dogra, Director, Finance. Mr. VK Saxena will start us off with his opening remarks, after which we'll move into a question-and-answer session. So I'd now like to turn the conference call over to Mr. VK Saxena. Sir, the floor is yours. Please go ahead.

Vipin Saxena

executive
#3

Good morning, ladies and gentlemen. I am Rear Admiral VK Saxena, Chairman and Managing Director of Garden Reach Shipbuilders & Engineers Limited. I welcome all of you to this conference call, where we will discuss the financial results of FY '20. Before I actually get into the details and other parameters, I would like to give you a quick briefing about the company, because some of you must be joining for the first time. As all of you know, Garden Reach Shipbuilders & Engineers Limited is a pioneer shipbuilder of the country, and we are part of the Ministry of Defence. We have delivered almost 105 ships till date. We are a diversified company. Apart from shipbuilding, we also have a division, which is the Engineering Division. That is why the name Garden Reach Shipbuilders & Engineers Limited. Under the Engineering Division, we have a unit that manufactures portable steel Bailey bridges of a variety of sizes, which are supplied to the Indian Army, BRO and many state governments for civilian use, et cetera. We also have a deck machinery manufacturing unit at Kolkata, Taratala, which primarily goes onboard warships. We have with us another unit at Ranchi, which is called the Diesel Engine Plant, where we undertake the overhaul and repair, testing, tuning of MTU made by these diesel engines, which again goes on board warships.

Vipin Saxena

executive
#4

So those are the kinds of activities we carry out as part of the Engineering Division. Now I'd like to share some very good news with you. Just an hour ago, I finished handing over the final one of the Fast Patrol Vessels, which belonged to the Coast Guard project, where we received an order to build 5 warships for the Coast Guard. This is the large ship, Kanaklata Barua — an hour ago I handed it over to Coast Guard headquarters. With that, GRSE has completed delivery of 105 warships to the Indian Navy and Indian Coast Guard. Now this ship, as I told you, is part of the 5 FPV project, and what makes it even more, I'd say, interesting is that we only opened up a couple of days back — although delivery of the ship had been planned for the month of March 26, the COVID-19 lockdown meant we couldn't do it, but the moment we opened up, we reached this important milestone. Another thing is that it was a 5-ship project. The fourth ship — that is the #4 ship, the fourth of the project, which was to go to the Coast Guard — the Ministry of Defence and the MEA, Government of India have earmarked it for export to a friendly foreign country.

Vipin Saxena

executive
#5

Discussions have been underway with this friendly foreign nation, though COVID has caused certain postponements; I'm confident that before long every one of these matters will be settled, and this vessel will head out for export as well. The implication is that GRSE — what I have in fact been focusing on is broadening the export side — that genuinely assists us considerably in fulfilling those obligations to export our warships too. Although we held the contract for delivery of 5 ships, that means I must build one more warship for the Coast Guard, for which we'll get an additional order from the Coast Guard on identical terms and conditions. The implication is that GRSE will hold one more order, for a sixth FPV as well. One more positive development occurred during the prior financial year, that being FY '20, when we finished delivering the final ASW corvette vessel. You're surely aware that we have been building 4 warships. Of those, 3 had already been handed over to the Indian Navy. And the final vessel, named Kavaratti, is a substantial weapons platform that was still being built, and it was delivered in February 2020 to the Indian Navy. With that, the ASW corvette project reaches its conclusion.

Vipin Saxena

executive
#6

In a similar way, the FPV project has wrapped up, assuming we secure the order for the sixth FPV. At the moment, we're working on — if you set aside those 2 projects, we're working on 4 Indian Navy projects. Of those 4 projects, 1 is the LCU project. You'd be aware that we were given a contract to build 8 LCUs for the Indian Navy, Landing Craft Utility ships. 7 ships have already been delivered. The last ship, the seventh, was commissioned recently, last month, at Port Blair by the Commander-in-Chief of the Command on 14th of May. Now this eighth ship, which was planned for delivery in the month of May through June, has been delayed somewhat because of the COVID lockdown, but we have every plan to deliver this ship by somewhere at the end of August or September at the latest. Now we'll be working on these 3 new Indian Navy projects. You're aware that we're working on the biggest and largest project, the P-17 Alpha stealth missile frigate construction, 3 in number, which is a very large INR 19,260-plus-odd crore worth of the cost.

Vipin Saxena

executive
#7

Work on the first hull part of the ship is already progressing at a solid pace. Naturally, a lockdown took place, which meant that no work was possible. For the second vessel in this specific project, we have already finished laying the keel of that ship — the second one, I mean. Production on the third ship got underway early in March. So all 3 vessels in this particular project are now advancing at a reasonably solid pace. We plan to deliver — to launch, rather — the first vessel of the P-17 Alpha project around the end of this year or the start of next year, which falls in the last quarter of this FY. That means it will be ahead of schedule relative to the plan originally worked out with the Indian Navy. If we get the ship launched by December, it will be ahead of schedule. The project we are handling next involves 4 vessels — that is quite a large undertaking. The keel of the first vessel has already been laid at the GRSE. As for the second vessel, we have started production at L&T Kattupalli, since we outsourced hull construction to L&T Shipyard, and production on that second ship also began in the month of December.

Vipin Saxena

executive
#8

Also, in about 2 or 3 months from now, we will begin building the third vessel at that location. Turning to the third project — the order we received during April 2019 from the Indian Navy to construct 8 ASW Shallow Water Crafts, valued at roughly INR 6,311 crores — it is what I would describe as a sophisticated weapons platform; not especially large, but a small and compact platform, which means considerable design work has to go into it. At present, this project sits in the design phase. We therefore anticipate that by the close of this year, or possibly in the final quarter of the financial year, we will start production on this ASW ship too. I would also like to give you an update on the Engineering Division, where a very notable accomplishment has taken place, especially in the Bailey bridge area. We had been investing substantial R&D to create a fresh design for a portable steel bridge with two lanes. The double lane version measures 7.50 meters in width, spans 160 feet in length, and is capable of bearing 100 metric tonnes of load.

Vipin Saxena

executive
#9

We completed the R&D, and we're able to manufacture — and we've successfully finished load trials in-house. We've received the directives from the BRO for these bridges: one bridge, for which we've already completed the load trial, will shortly be given on an NCNC basis to the Border Roads Organisation. Beyond that, we've also experimented with and designed a new single-lane bridge — 190 feet in length, roughly 4.25 meters wide, with a load carrying capacity of 100 metric tonnes — that was supplied to the BRO, and this bridge is modular in nature and has a new 7-foot panel. So altogether it's a new design, and this bridge has been installed over the River Asiganga in the Uttarakhand region, very close to the China border, and so far the trials have been successful. With this new model, we expect orders from the BRO and other organizations. Third, as you'll recall, we were also developing a portable assault bridge of small size — 30 feet in length — using a completely different kind of carbon fiber material, which made it very light. That bridge has also been developed successfully.

Vipin Saxena

executive
#10

The trials are finished. This bridge can now be marketed and supplied to the Indian Army in particular, along with other customers, and it could also offer solid export potential. Those are the developments on the physical side—delivery of the ships and the progress of the projects we are currently handling. Let me give you a quick briefing on how COVID has affected us, since you will be very keen to know. Without a doubt, the lockdown began at GRSE on 24th of March. The shipyard had planned many things to be finished over what I would call the final 8 to 10 days. In shipbuilding, a great deal happens in that manner as well. We had in fact planned to hand over this ship that we have just delivered, Yard 2117, to the Coast Guard on 26th of March, but that was not possible. In the same way, many components for the Bailey bridges that were meant to go out with the Indian Army and the BRO and Nagaland, et cetera, could not be dispatched, because the trucks, et cetera, had come to a halt. Then there were also a lot of B&D spares that were to be provided to the Indian Navy, and those could not go either.

Vipin Saxena

executive
#11

The impact did hit us during the final 8 to 10 days of the prior financial year. With the lockdown, however, no work at all was possible at any of GRSE's new production units. Every one of those units sat inside a containment zone in Kolkata. Permission came through only partially, letting us reopen just 2 or 3 units starting 1st of June. Then, from 8th June onward, approval arrived for another 2 units too, and production activity has begun there. Even so, the headcount showing up remains short of what's needed, owing to assorted restrictions and problems, though things should gradually ease. As all of you are aware, shipbuilding is an activity that leans heavily on manpower. A great deal of work, including non-core activities, has been outsourced to contractors, and those contractors bring in large numbers of migrant workers. Those workers have headed back to their home villages and locations. So some time will pass before they come back. Getting back to normal, to the level we began from, will therefore take a while. On top of that, when it comes to yard material supplies, major equipment and so forth, everyone sought force majeure, which we are obliged to grant.

Vipin Saxena

executive
#12

As a result, on that side too, we anticipate certain delays regarding material availability and so on. However, a plan has been put together by us. We are operating on a shift basis with fewer staff, aiming to ensure compliance with required safety measures and social distancing rules. And naturally, the personnel arriving at the site must not contract the infection. So every precaution has to be taken, and the shipyard is making its utmost effort to guarantee that whatever is needed gets done. Amphan, as all of you are aware, the super cyclone that struck on 20th of May last month definitely wreaked havoc across the whole of Kolkata and West Bengal. We too were heavily impacted. Roofs of numerous workshops were torn off. Substantial water logging occurred in the substations and so forth, and many trees came down. As a consequence, quite a few walls and similar structures have been damaged. Fortunately, none of my assets suffered any significant setback that would have affected my operations. So that is one positive outcome. And the insurance surveyor has already visited and inspected everything, and we are filing the claim in line with that.

Vipin Saxena

executive
#13

Alright, those are the problems and how the shipyard has performed when it comes to delivering vessels and the projects currently underway. Let me now give you a quick rundown of the yard's financial results for FY '20 versus FY '19. As you're aware, total income at the shipyard rose 6.49%, moving from INR 1,557 crores to INR 1,658 crores. Operating revenue improved only marginally — 3.38%, from INR 1,386 crores to INR 1,433 crores — and that came despite plenty of difficulties and challenges. PBT climbed 25.10%, from INR 178 crores in FY '19 to INR 223 crores in FY '20. Profit after tax, I'd say, also posted very impressive growth of 48.70%, rising from INR 109 crores to INR 163 crores. Earnings per share likewise improved quite well, going from INR 9.60 — yes, INR 9.60 — to INR 14.27 per share. On top of that, we secured an order worth INR 6,311 crores for building 8 ASW Shallow Water Crafts ships. We signed it in April 2019. Thanks to that, the order book increased by 29%.

Vipin Saxena

executive
#14

EBITDA margins have likewise improved nicely, moving from 13.56% to 15.39%. PBT margins rose as well, climbing from 11.49% to 13.50% in FY '20. The PAT margin has similarly posted a solid gain, going from 7.06% to 9.86%. As for dividend per share, you'll recall that it stood at INR 6.9 per share last year. The Board of Directors has now proposed INR 7.1 per share. We've already disbursed an interim dividend of INR 5.74, with the remaining INR 1.40 having been proposed. So in total, the dividend comes to INR 7.14 per share. I'd also like to draw attention now to Q4 of this past financial year versus Q4 of FY '19. All the figures are available, but what I want to do is simply point out, and put before all of you, that in warship building, where the gestation period runs very long, the full shipbuilding cycle doesn't trace a straight line or a steady course. That entire curve looks quite different, as I explained earlier to investors and analysts. As a result, setting Q4 of this financial year against Q4 of the prior financial year may not be appropriate. That is why I'm not attempting a comparison here. Still, should any questions arise, we'll do our best to answer them to your satisfaction.

Vipin Saxena

executive
#15

The key point I want to emphasize is that I assumed leadership of this company in March 2017, and my effort since then has been to establish a performance baseline from that point. As all of you know, FY '17 proved a difficult financial year for us. From that point through FY '20 — across the last 4 years — we have truly performed quite strongly in every operational area. We've delivered steady growth across every segment. Notably, operating revenue rose 54%, climbing from INR 929 crores in FY '17 to INR 1,433 crores in FY '20. PBT climbed from INR 20.12 crores to INR 223 crores — an improvement of roughly 1,120%. PAT, which matters greatly, expanded from INR 11 crores in FY '17 to INR 163 crores in FY '20, representing growth of 1,482%. That is the sort of steady growth we've delivered in spite of challenges and in spite of issues, and we're working hard to keep delivering strong financial results as well as progress on construction across our various projects. In fact, EPS stood at INR 0.94 in FY '17 and has risen to INR 14.27.

Vipin Saxena

executive
#16

On the PAT margin side, it stood at merely 1% back in FY '17. As of today — FY '20 — that figure has reached 9.86%. Beyond that, over the course of the last 3 years, we handed over 13 warships to the Navy as well as the Coast Guard, which amounts to something of a record, with the gap between the 2 deliveries coming in at under 3 months. So I would say the shipyard has performed really well across every dimension, and we remain committed to getting past the COVID challenges that have arrived at our doorstep. We genuinely hope the company posts an improved result during this current financial year. That covers what I have to share for the moment. I'm available for whatever questions you may have. Many thanks.

Operator

operator
#17

<<operator_script>> The first question comes from Umesh Raut, who is calling from YES SECURITIES.

Umesh Raut

analyst
#18

Sir, I noticed what you said regarding the earlier launch of the first vessel from the P-17 Alpha project. So I just wanted to learn more — I mean, how are we attempting to recover the execution shortfall for April and May as we move forward? I mean, is there any room to bring in extra shifts during working hours, or add another day, or put more labor onto our sites? And also an update on labor availability across our sites, the various sites. And — say, labor migration has — I mean, it's kind of a major problem for the industry. So how do you intend to, I mean, kind of get back the skilled labor, or the substitute for that skilled labor?

Vipin Saxena

executive
#19

Yes, a very good question. I've already mentioned that the real difficulty right now, over the next few months, will be getting those laborers who returned to their home locations to come back. That said, we've laid out our plans. As you noted, we've prepared plans for working on the ship systems. The effort is to raise time on task using whatever headcount is available to us. We must revise the whole sequence of activities. We need to alter the entire planning process so that it accommodates fewer people, with fewer groups operating inside the tight spaces of the compartment. We recognize this will be difficult, but as a shipyard, as I've said, GRSE always strives to meet these difficulties, to meet such hard circumstances. We're attempting to operate in a way where, given the constraints and the limited manpower that will be available to us, we've set the target for all offices, the entire workforce and the contractors, everyone, that I have to launch the ship. Under the contractual provisions, I had the time to launch the ship by February 2021, but I'm always trying to set a tough benchmark in the sense that I should be able to launch the ship with whatever, I would say, if it was 35% or 36% of the hull construction, with that I would have launched, but I can launch it with 30% also, 29% also, it makes no difference.

Vipin Saxena

executive
#20

However, the launch event by itself, once it receives substantial momentum, will shift the whole mindset and approach of everyone involved, customers included. That's because a great many things can occur when a ship is launched. So that's where my strategies stand at present. And we genuinely hope that, even if not fully, at least in part or to some degree, I'll be able to recover the ground that was lost.

Umesh Raut

analyst
#21

All right, all right. Sir, turning back to the CapEx program we have at Rajabagan Dockyard — given the COVID impact and the crisis and everything, do we think there could be any delay there? And if that delay does happen, would FY '22 execution be affected as well?

Vipin Saxena

executive
#22

So for the projects we've scheduled in FY '21 for the CapEx infusion, we've earmarked roughly INR 52 odd crores in spending. And I do expect there will be some hiccups — I've mentioned this — on account of labor and so on, but I'm confident we'll be able to make up for these CapEx plans that we have in mind.

Umesh Raut

analyst
#23

Alright, alright. Sir, returning to the pipeline for your orders — as you noted on the previous con call too, there were close to 6 projects in that pipeline. And the company has submitted the RFPs as well. So how do you view the progress on those projects at this point? Given the government's fiscal situation right now, do we expect any delays when it comes to the awarding side?

Vipin Saxena

executive
#24

To start with, several responses to RFPs have already gone in to the Ministry of Defence. On the RFP for the PCV project — that's the Pollution Control Vessel for the Coast Guard — we submitted our response, the bid has already been opened, and we did not come out as the winner on that contract. Then there's the 12 ACV, the Air-Cushion Vehicles, where we've put in our bid. We've likewise submitted our response to the RFP for building 8 Fast Patrol Vessels for the Coast Guard. We've also bid for the New Generation Missile Vessels, 6 in number, for the Indian Navy — that one is a big project. And at this point we're about to submit our bid for the multipurpose vessels, 2 in number, for the Indian Navy. The submission date for that bid is 14th of June. After that, we also have the RFI that has come in for the NG-OPVs, 6 in number. So what I'm seeing right now, given that bids have already been submitted and with the lockdown, is that the Ministry of Defence, the Coast Guard and the Navy will take their time opening the bids and carrying out the technical negotiations and all the many other steps involved, because as you'll appreciate, from the day a bid is opened until a contract is finally signed takes no less than 12 months to 18 months, if everything goes well.

Vipin Saxena

executive
#25

So because of that, even if I end up being the winner, those items aren't going to come up right away when it comes to signing the contract.

Umesh Raut

analyst
#26

Right, understood. Sir, regarding payments, do you expect any shift in government policy when it comes to stage payments? Because at the moment, I believe most of the collections are still outstanding from the government side across the various industries. So how do you intend to manage if, say, collections are delayed?

Vipin Saxena

executive
#27

Look, the way to grasp this properly is that the country’s whole attention—the government’s attention—is on the social sectors, the health sectors, and all the other areas that have been hit hard, plus MSMEs, and many other sectors as well, infrastructure, et cetera. There’s going to be some strain when it comes to stage payments. We know that. And there could be some in the first or second quarter—that’s the hint we’ve received. But the good part is we’re hopeful that we can keep our operations going without being badly disrupted by this situation. So we’ve got a plan worked out, together with the Finance Department and the Director of Finance, on how to move forward, how to keep production activities going, et cetera, and procurement of various items. So I don’t foresee any major impact on production and procurement actions for my projects. So I don’t see projects being badly hampered because of this issue.

Umesh Raut

analyst
#28

Right, right. Sir, there are two accounting-related questions regarding the FY '20 figures. I'd just like to get the revenue contribution by project for the full year '20 — specifically for P-17 Alpha, then the Fast Patrol Vessel, and the LCU?

Vipin Saxena

executive
#29

All right, I’ll have that removed. Actually, he prefers it broken out by project — whatever item, the VOP that has been recorded. 17 Alpha <<foreign_lang>>. As you’re aware, the total VOP stands at INR 1,433 crores. Of that amount, INR 1,250 crore has been contributed by the ship division, correct? And everything remaining actually belongs to the — all right, everything remaining belongs to what I’d call the other engineering divisions. Now, looking at the LCU, it has provided roughly INR 61-odd crores of the VOP. The FPV project has contributed approximately INR 79.34 crores of the VOP, the ASW corvettes have provided INR 270 crores of the VOP, mainly upon completion of the stage payments and delivery of the final corvette. Then 17 Alpha has contributed the largest amount, INR 754 crores. Actually, this is the biggest one, and it is generating the highest revenue as well as the profit margins. On survey vessels, the encouraging news is that work has already commenced, roughly INR 75 crores of revenue has been booked against this project, and it will keep rising and improving further as construction progress moves considerably faster on the survey vessel project. So those are the key projects and the revenues that, as I mentioned, have been booked against this project in FY ’20.

Umesh Raut

analyst
#30

All right, all right. Then, sir, my second question concerns the liquidity provisions. So what figure was recorded in FY '20?

Sarvjit Dogra

executive
#31

On the liquidity front.

Vipin Saxena

executive
#32

So you're asking — hi there, you want to know about the damage to our liquidity?

Umesh Raut

analyst
#33

Yes, yes. Yes, sir.

Vipin Saxena

executive
#34

I’ll just go ahead and say it.

Operator

operator
#35

Mr. Raut, apologies for cutting in. Once this question has been answered, could we ask you to go back into the queue, please?

Umesh Raut

analyst
#36

Yeah, yeah, yeah.

Vipin Saxena

executive
#37

We've gotten this to INR 24 crores.

Operator

operator
#38

<<operator_script>> Our next question comes from Jonas Bhutta with PhillipCapital.

Jonas Bhutta

analyst
#39

I want to start by saying I hope everyone at GRSE is safe and well. So I have 2 questions. The first one is, and it also ties into something you mentioned in the earlier participant's question. Regarding execution, with the time that's been lost, do you think sales for the current year will be significantly below what you achieved in fiscal '20? And what would be the cause of that? Because with survey vessels, some parts have already been outsourced, like the survey vessel project. How much of that can still be recovered through other means? So what strategies are being pursued? Could you briefly elaborate on that? That's my first question.

Vipin Saxena

executive
#40

Alright, thank you so much for inquiring about how we're doing. Everyone here at the shipyard is in good shape. We're observing every precaution available. And I sincerely hope each of you is also taking plenty of precautions for yourselves and your loved ones. Now, back to what you raised regarding time misplaced because of the lockdown — we're completely conscious that production activities came to a halt, and there will be difficulty obtaining workforce, particularly contractors, migrant laborers or skilled workers, since they've returned to their homes. Still, I believe an extraordinary circumstance like this hands you a chance to devise extraordinary measures. We've come up with fresh strategies, and with those strategies now in place, I'm just hoping for the best — that if not a full 100%, then somewhere near 90%, I should be able to — or 80% or 90%, I should be able to recover the ground we lost, provided solely that people keep trickling in and contributing their effort. I'm going to raise the productivity norms, the throughput norms, attempting to do certain things in such a way that whatever level 1 person achieved should rise by 20% to 30% in his productivity.

Vipin Saxena

executive
#41

Regarding your question on the probable effect during this financial year relative to the prior one — right now, I’m fairly hopeful and confident that this year won’t turn out badly. It should be just as good, perhaps even great; my own view is that it ought to be decent, and I’d call that good when set against the previous FY '20. That’s the strategy I have at present. We’ll see how matters unfold. Still, as CMD of this shipyard, my belief is in tackling the difficulties and applying every one of those sorts of steps so the targets get met. Let’s see what happens.

Jonas Bhutta

analyst
#42

All right, my second question is this: given that nearly all of your legacy vessels have now been delivered, apart from 1 LCU, what level of LD provisioning do you expect for fiscal '21? Also, have you begun making provisions for LD on the comparatively newer projects — 17 Alpha and the survey vessels — or do you plan to start? After all, you already know that, with the time lost, the delivery timelines for these may ultimately get pushed out. So would you begin preempting LDs on 17 Alpha and the survey vessels immediately?

Vipin Saxena

executive
#43

Yes. Once more, let me make it clear to you that for the last LCU in question, provisions have already been made. So nothing remains at this point. No LD is going to arise going forward. Regarding projects currently underway, the survey vessel you mention, or P-17 Alpha, still have delivery periods that are quite far off. Once we get a sense that known delivery delays are going to occur, we begin addressing that. Right now, I don't anticipate delays happening on survey vessels broadly. Also, with respect to whatever lockdown-related delays have occurred, force majeure has already been sought, and it will be granted. So those matters will be factored in. Therefore, at this point, in this FY '21, we are not looking at any LD provisions or any other LD expectations at the end.

Jonas Bhutta

analyst
#44

Sir, that INR 24 crores figure will drop to 0 in FY '21. Effectively, in FY '21, this INR 24 crores would come down to 0.

Vipin Saxena

executive
#45

For FY, INR 24 crores — this was essentially taken for the last ASW corvette we delivered. I think roughly INR 22 crores of that relates to just 1.4 months of LD on that ship. So that's now been handled, INR 22 crores. And INR 2 crores comes from other sundry delays tied to the Engineering division, et cetera. So at this point there won't be — with this done, nothing further is going to be fresh. There could be some write-backs. That's what I'm looking at.

Operator

operator
#46

The next question comes from Abhijit Mitra of ICICI Securities on the line.

Abhijit Mitra

analyst
#47

I've got two questions. First, because of the lockdown, what amount of sales have you lost? If you could quantify the lost sales figure for March or for Q4, that would be helpful.

Vipin Saxena

executive
#48

Could you go over your final question one more time for me?

Abhijit Mitra

analyst
#49

Yes. So what amount of sales did you lose during Q4 as a result of the lockdown?

Vipin Saxena

executive
#50

Look, let me put it this way: for the final 8 days of March, we had anticipated roughly INR 80 crores to INR 90 crores in sales in terms of VOP, and that clearly did not materialize. Had it come through, our top line for FY '20 would have looked considerably stronger. So that revenue now moves forward, since those items are nearly finished or were close to completion. Yes, that will now land in Q1 of this financial year, now that we have reopened. On the ongoing projects — 17 Alpha and the survey vessel specifically, and naturally the LCU minor works, of which 2 months of the job remained — we have not yet arrived at an exact quantification of the financials and so forth. That said, yes, the lockdown has had an impact on production progress, and we will determine the precise amount. Right now, we have not reached the figures, because during the lockdown people were unavailable, and we need to confirm with all the groups, group heads, and subgroup heads what was targeted and how much has actually been achieved.

Vipin Saxena

executive
#51

We'll learn more about it, but I don't anticipate anything that would seriously or severely hamper us or have a major impact. What I'm saying is that we'll be mitigating those delays over a period of time. And I certainly hope we should be able to catch up a lot. That's my expectation.

Abhijit Mitra

analyst
#52

Okay, okay. So what do you expect from P-17 Alpha in FY '21?

Vipin Saxena

executive
#53

Look, I've mentioned that 17 Alpha delivered solid revenue from operations in FY '20 — INR 700-plus crores — and with luck it should be far, far stronger during this financial year, because — yet the reality, Abhijit, I have to say, is that after it's launched, achieving the hull construction alone won't lift your revenue all that much higher; it's once the launch takes place and then, gradually, the equipment and so forth begin going onboard the ships. So as equipment starts going onboard ships, you'll begin seeing the better, I'd say, revenues. You can book revenues on that basis. So from the end of FY '21 onward, and in FY '22, we expect things will be extremely good for the first ship and on 17 Alpha. But FY '21 too should be better than the prior year, this FY '20. Yet the survey vessel is likewise going to deliver quite good, I'd say, revenues. It was INR 75 crores. It is set to rise.

Operator

operator
#54

We’ll take our next question from Dixit Doshi, who is calling in from Whitestone Financial Advisors.

Dixit Doshi

analyst
#55

Sir, you brought up the effects of COVID and Amphan, and you explained how we intend to handle them. Still, do you think that because of any delays, there could be an adverse effect on our margin?

Vipin Saxena

executive
#56

My view is that the plans we’ve set out shouldn’t produce an impact—or at least not a significantly bigger one—and under my plan and my strategies, I want at minimum, even if I don’t move much higher, to stay where I am; that is what my strategy and plans involve when it comes to catching up and doing things in a completely different manner. The things that have never been attempted in shipbuilding—the warship building process—I’m going to try all of those techniques, tactics, and measures so as to hold those levels and not decline at all. So that is what my thinking and strategy are.

Dixit Doshi

analyst
#57

So, if there’s any delay and some cost ends up rising, even then our 7.5% margin — the PBT margin — stays protected, is that right?

Vipin Saxena

executive
#58

From my perspective, based on what we can see right now, that kind of thing really shouldn't be arising. Whatever signals come from the market, whatever suppliers tell us, whatever other sources we have access to — unless something drastic happens with labor costs, like the government stepping in and doubling wages and so on, then sure, there could be some effect. But at this point, you'll notice nothing has emerged, nor is there any major impact when it comes to the cost of items and so forth — although that is, no such sign exists, so for me it would be pure guesswork to make any statement on this front.

Dixit Doshi

analyst
#59

Right. And second, sir, although you did say that comparing revenue quarter-on-quarter isn't a good idea — still, when I look at your Q4 revenue from last year versus this year, revenue has declined, yet contracting charges, subcontracting charges, have jumped by almost 50%. Could you explain that?

Vipin Saxena

executive
#60

Look, I have to mention this, and I actually explained it to someone: the last quarter, Q4, would have come in higher versus the prior year's Q4, because of COVID — during the final 8 to 10 days, I had planned roughly INR 80 crores to INR 90 crores of revenue that would have flowed in from delivery of the last ship, the one I handed over just today, plus a substantial amount of base and depot spares valued at about INR 30 crores to INR 40 crores that were meant to be sent out to various locations. On top of that, many components for the Bailey bridges were supposed to go out by truck, so none of that could take place. Had it gone through, the numbers would look different. Q4 of FY '20 would have come out stronger than Q4 of last — FY '19. That's the reason I keep saying the cycle — when you're talking shipbuilding and the revenue generated there, the cycle works completely differently. And once more, I'd like to make the point that it won't be a good idea, I think it won't be appropriate, to attempt quarter-on-quarter comparisons; that span is simply too short.

Vipin Saxena

executive
#61

And it will — our graph is — generally, our shipbuilding cycle never moves straight ahead; it doesn’t follow a particular gradient. It’s going to be absolutely different. At 35% of the ship construction time, it starts going up, when the hull is almost complete, then the equipment and our installation will start from 35% to 65% of the construction time and construction progress, you will have the maximum values getting booked and then it starts declining. So it is all based on that. So therefore, which ship falls in which quarter, at which point of time, it will all depend on the progress of the work.

Dixit Doshi

analyst
#62

And then, second, sir, during your opening comments you said we’ve received a new order for the sixth FPV, worth INR 8,600 crore — is that correct? So is this a new order?

Vipin Saxena

executive
#63

No — I think perhaps — look, I hold the build order for 8 vessels, the ASW Shallow Water Craft program, valued at INR 6,311 crores, awarded by the Ministry of Defence on behalf of the Indian Navy, signed in April 2019. That said, I am also likely to receive the 1 FPV, which I am redirecting toward the export side. As you may recall, I mentioned having a contract to deliver the 5 FPV to the Coast Guard. Delivery of the 4 ships is complete. However, the 1 ship has been set aside for handover to a friendly foreign nation. So in place of that vessel, which will now go for export, the Indian Coast Guard and MoD will grant me an order for an additional FPV. That, then, is what I would call the sixth FPV. We held an order for 5; 1 more will now be constructed by us. So my expectation is that this order arrives once the contract is signed with that particular foreign country.

Dixit Doshi

analyst
#64

All right, and sir, this is my final question. In our other expenses, we see a very large increase, going from roughly INR 34 crore up to INR 53 crore. So does that come from LD, or is there some other item involved?

Vipin Saxena

executive
#65

Could you please say your most recent question one more time?

Dixit Doshi

analyst
#66

Looking at our Q4 figures, other expenses went up from roughly INR 30 crore and INR 34 crore to INR 53 crore. So is that LD charges? Or is something else behind that increase?

Vipin Saxena

executive
#67

Correct — as I mentioned, the LD charges come to a total of INR 24 crores. Of that, INR 22 crores relates to the last ASW corvette we took, while INR 2 crores covers other sundry equipment, et cetera. That INR 24 crores arises on account of the LD charges.

Dixit Doshi

analyst
#68

So that's only in Q4, then?

Vipin Saxena

executive
#69

Yeah, that's right.

Operator

operator
#70

The next person to ask a question is Lakshmi Narayan, calling in from ICICI Mutual Funds.

Lakshmi Narayan

analyst
#71

Just a couple of things I wanted to ask. First, on your cash on the books — we show roughly INR 2,600 crores, which is cash and cash equivalents plus bank deposits, held in cash. So could you reconcile whether that cash figure is accurate? And second, how much of that is actually customer advances, and how much falls outside customer advances?

Vipin Saxena

executive
#72

Banks hold -- hold on a second. Yes, and at present, within the banks, we have roughly INR 2,600 plus crores sitting there, which, again, I want to make clear is not the customer advance. In warship construction, stage payments exist, and the customer pays against those stage payments. That money is then expected to be used for specific activities that are meant to be carried out. Until you perform and complete that work, it stays in the bank. So that is how you should view them — they are there in the bank, but when the need arises — now the COVID situation has arrived — you will not have those stage payments coming forward. But these are the things that will be used properly for expenditure and for procuring material items and so on and so forth. So at times there will be delays between the stages. So all of that is taken into account in our costing, whenever we do the costing and submit it to the Navy and the Coast Guard or any other customers. So these types of stage payments are factored in, and they would be available to us for various kinds of activities.

Vipin Saxena

executive
#73

So those aren’t advances at all.

Lakshmi Narayan

analyst
#74

Understood, understood. So what you're telling me is that, for all intents and purposes, this really is 100% the company's?

Vipin Saxena

executive
#75

Could you say that again? I didn't catch it clearly.

Lakshmi Narayan

analyst
#76

So is it fair to say that this cash is simply the company's own, and that it isn't an advance — correct? So that's just up to you.

Sarvjit Dogra

executive
#77

That doesn’t represent an advance.

Vipin Saxena

executive
#78

Look, that's the point I made clear to you — it isn't an advance. Nowhere in our accounting system do we ever use that word, advance. We call it stage payment, always stage payment, and that gets factored into all of our costings, into our whole planning process and our construction process.

Sarvjit Dogra

executive
#79

That cash belongs to us.

Vipin Saxena

executive
#80

That cash belongs to us.

Lakshmi Narayan

analyst
#81

Alright, alright. Sir, regarding your order book, I missed part of it since I joined a bit late. At the close of the year, financial year 2020, what does your order book stand at?

Vipin Saxena

executive
#82

Right now, my order book stands at INR 26,544 crores. Within that, the biggest portion comes from the Shipbuilding Division — INR 25,281 crore relates to shipbuilding, all of it ongoing projects. Everything else belongs to the Engineering Division.

Lakshmi Narayan

analyst
#83

Alright, so my third question is this: we build the P-17 Alpha, the LCUs, and those other vessels — so between them, where do we actually stand in a stronger position? And from an orders standpoint, just how big is that?

Vipin Saxena

executive
#84

I didn't catch that.

Operator

operator
#85

Mr. Lakshmi Narayan, if you happen to be on speakerphone, could you please pick up the handset instead?

Lakshmi Narayan

analyst
#86

No, I've only got a handset here. Sir, I suppose what I'm asking is this: out of the 3 or 4 kinds of vessels that we actually build, which one gives us a clear edge over everyone else?

Vipin Saxena

executive
#87

Look, when it comes to what sets us apart from the other competitors, I'd say yes, there are certain strengths we hold, particularly the type of infrastructure we have — very, very modern infrastructure, I would say. I have 3 units. I have a great deal of flexibility for building ships of different sizes across different units, which I don't believe others possess. I have a very strong, competent, capable 100-member design team, an in-house design team, which is a very, very major plus point, I would say. On top of that, I have 60 years of experience building warships. 105 warships delivered — nobody has achieved that. So these things are certainly a big advantage for us relative to other competitors. And I would say that, you will appreciate that, 2 projects I've won through a competitive bidding process. That is the survey vessel project and 8 ASW Shallow Water Craft project. Both projects, having been won through competitive bidding, things are moving along quite nicely. You can see my margins, that is PAT margins and EBITDA margins and all, how they have shown improvement. So that certainly demonstrates the kind of improvement, efficiency measures, and certainly, these trends are really paying us those dividends when it comes to getting better margins in all areas.

Operator

operator
#88

Our next question comes from Bhavin Vithlani, who is on the line from SBI Mutual Fund.

Bhavin Vithlani

analyst
#89

First, I want to congratulate the management team on delivering such a strong performance given the difficulties out there. Now, a question on the numbers side. If you could help us with this, you said the order book stands at INR 26,500 crores — if you could walk us through the key projects in there, the P-17 Alpha survey vessels, how would you break that down?

Vipin Saxena

executive
#90

So look, I’m telling you we’ve got the P-17 Alpha order, and that’s worth roughly 9 — INR 19,260 plus some additional crores for 3 ships. Then there’s the contract for 4 large survey vessels, okay? This project costs INR 2,435 crores. After that, INR 6,311 crores is the project cost for 8 ASW shallow water aircraft. On the other projects, I’ve already finished the FPV, and we’ve delivered it as well, but there are some final-stage payments and so on that should still be coming to us. That’s why I’m saying that, taken together, right now we have 26,000-plus something at DEP, Ranchi — around INR 230-odd crores’ worth of the 28 1-megawatt diesel alternators being assembled there for Project-17 Alpha, plus the Bailey bridge and the other deck machinery orders and so forth, but those make up a fairly small share compared with the Shipbuilding division. So I think these are the main pieces of the current order book that still has to be excluded. So the excludable order book we have available is INR 26,544 crores.

Bhavin Vithlani

analyst
#91

Okay, sir. For the second question, could you help us with this: right before the lockdown actually started, what was the total workforce at the site, including contract workers? And as of today, what's the current workforce present there? Related to that, you said every crisis calls for a change. So with the disruption you're seeing right now, are you also considering more automation and robotics in your manufacturing process?

Vipin Saxena

executive
#92

That's a very – I think that's a quite interesting question. And the answer to the first one is that our own manpower, our own workforce, including the offices, is around 2,000-odd people; the workers number roughly 1,500-odd – workers – and the remainder fall in the officer and supervisory category. Then we were deploying, on our own, an average of 3,500-odd workers, which also took in support services like housekeeping, like ship cleaning, shop cleaning, et cetera, et cetera. But for the core activity, I would say altogether 35-plus 100-odd people were working from the outsourced contractors. Now, this was the situation prior to lockdown. Now, when we opened up, because of the restrictions placed by the respective state governments and the need to work in shifts, you cannot have so many people working concurrently, whether it's office white-collared jobs or whether it's a blue-collared job that gets performed in the workshops. I have said that we are working out the revised plan; the entire planning process is being revised – working in the shift, working in smaller sizes of the groups. But I must say that warship building is manpower-intensive work. Robotics – while it is easy to say – but anything we want to get in a warship is different than the commercial ship, because commercial ships, you can see it as like a matchbox or the box.

Vipin Saxena

executive
#93

On the warship side, hulls have varying curvatures, the vessels are small, compartments are extremely tight, and there is very little room, among other factors. That makes the whole fabrication effort a challenge and something quite different. As for how much automation could be introduced, there certainly are opportunities, and we are examining that in some areas — for instance, inspections such as radiographies can be automated, and plenty of other tasks could be handled through what I would call automation, or through AI, as it were; those items are being planned. However, you won't see immediate results, since it will take a couple of months, perhaps 6 months or 8 months, before you have a proven AI or automation product that can actually be deployed. We are pursuing a smart shipyard concept in which every machine, piece of equipment, and operation can be interconnected, with the aim of reducing the headcount needed to work, man, command, and control those things. All of this has already been planned. I've laid that out. I've mapped out some strategies, so that even with a limited number of people we should still be able to keep operating them, and we are also exploring reskilling, upskilling, and multiskilling of the existing workforce so that their throughput rises as well.

Vipin Saxena

executive
#94

Productivity standards need to go up, and the benchmark needs to get better—only then will we be able to catch up. So I think COVID has brought challenges, but it has also brought plenty of opportunities, and we have certainly seized them, and plans have been drawn out. Only time will tell how much we succeed.

Bhavin Vithlani

analyst
#95

Sure. Sir, roughly how many people are on the total workforce right now, counting the contract workforce as well? Even an approximate figure would be...

Vipin Saxena

executive
#96

Operations began on the 8th. We received approval to reopen at 2 of our major production sites — the main unit and the Raja Bagan Dockyard. Those locations only got the go-ahead to start on Monday. Permission was granted for 2 units to run partially, though they weren't really part of the big production work. Now, however, we're bringing people in at 35% of the shift, all right? We're also making certain that older employees who travel from far away or have co-morbidities and other illnesses aren't put at risk. So all of that will be in place. On any given day, I'd say with a 2-shift setup we could have 60% — or 70% — of the total workforce allowed inside. That said, contractor labor will pose a difficulty. Their headcount will be considerably lower, I'd say, within 1 or 2 months. In June or July, we don't anticipate the same numbers coming back. So we'll have to plan around that. I hope that answers your question.

Operator

operator
#97

Sunil Shah from Turtle Star Management has the next question on the line.

Sunil Shah

analyst
#98

To start, congratulations on delivering the 105th warship. A big thank you from all of us for working toward the safety of our country. That is my first point. Sir, I have 2 questions. The first one being that on the Project Alpha, 17 Alpha, the frigates business. Sir I understand that the entire manufacturing of frigates takes multiple years. And once we cross some 18 months to 24 months into the production process, the revenue actually shoots up and it moves in a bell curve. So is my understanding correct? And where do we stand on the 3 frigates? Meaning in the first one, I think you were saying that by the fourth quarter of this year we should really reach that point of inflection for our revenue recognition. Could you just help us understand for the 3 frigates where we stand?

Vipin Saxena

executive
#99

Yes. I believe you got the right picture regarding the type of curve that complex and major warships typically follow. Building the hull accounts for the first 30% to 35%. That hull is extremely large — a very, very big hull. Naturally, it doesn't bring in very substantial revenue. But prior to that comes what's known as the design phase, the pre-production phase, and for a ship of this kind that takes a minimum of 18 to 24 months. So with that in mind, we were in the predesign phase. Production then began around late 2017, somewhere in that month range. And at this point — right now, we sit at roughly 20% of hull construction. Once hull construction reaches around 30% to 35%, she is about to be launched, or is being launched, and then equipment starts going onboard the ship. So from 30% to 35% it climbs and peaks at 65%, after which it begins to come down. So regarding the delay, I would say there's another 10% that must be achieved before we launch the ship, at least where the hull is concerned. So we haven't yet arrived at that particular stage, which is what we're asking for.

Vipin Saxena

executive
#100

My expectation is that in FY '22, in a real sense, the large equipment will begin going on board ship. So FY '22 would be interesting to see.

Sunil Shah

analyst
#101

Okay, so that applies to frigate number one. At what point will we get there with frigates two and three?

Vipin Saxena

executive
#102

Yes. So if you look at the first and second ship, the second one is running behind by 1 year, in line with the contractual provisions. The hull progress and everything else is therefore proceeding on that basis. Resources are being allocated to match, and manpower is being assigned to match, so that we stay aligned with that kind of ship construction plan. So the second ship will be trailing by that much time. So when I say that in FY '22, at some point, we might get to that 30%, 35% figure when it begins rising sharply, that means the second ship will be 1 year behind — by the time it reaches 35%, this ship would have gotten to roughly 20%, 22% of construction, the second ship.

Sunil Shah

analyst
#103

Okay, so the third one, sir, is going to be roughly FY '24, FY '25?

Vipin Saxena

executive
#104

What does that refer to?

Sunil Shah

analyst
#105

Would the third frigate get to that same stage at some point in FY '24 or FY '25?

Vipin Saxena

executive
#106

I mean, I'd put it this way — yes, if you're suggesting that the first ship would get to a certain level in FY '22, let's say <<inaudible>> and past that. So as you can tell, the second ship comes 1 year later, meaning it lands in FY '23 through the close of FY '24.

Sunil Shah

analyst
#107

Right. Sir, my second question is about margin. Sir, I understand this is a fixed-margin business. So for the most part, these things would be pass-through for us. Sir, does the margin also follow a similar bell-curve pattern? Or is it that at the designing stage margins are very high, and when we are uploading the equipment, margins are low? I just want clarity on how margin moves along with revenue recognition.

Vipin Saxena

executive
#108

You know, one thing I should point out is that revenue recognition depends on the percentage of progress you achieve. That's the first thing we need to keep in mind. The second thing is that profits are tied to whatever production we've completed. So in this case, 7.5% is the fixed figure. But nothing prevents us from earning more profit, because Navy will only give you 7.5%, yet nothing stops me from performing better within my own internal operations when I negotiate various items and equipment that fall within my purview. If I do that better, I'd obtain better margins, which means lower cost. And I can beat what I've costed, so the material itself can give me — if I negotiate better, if better cost is paid to the various suppliers, that's where I can make the money; if I'm able to work more efficiently with fewer people, fewer contractors, I'd have to pay a smaller amount of money to the contractors and the workforce. In the same way, there are many ways in which 7.5%, there's a fixed margin that Navy will give you whatever you claim, but internally nothing stops me from being more efficient.

Vipin Saxena

executive
#109

So that's kind of where I am — and you can see I'm sitting at a margin of 9-point something percent, 9.86%. It's better to focus on the question of whether, if my margin is 7.5%, I could ever push past that. Well, now you're seeing the results: I have pushed past it.

Sunil Shah

analyst
#110

Yes, yes. Sir, thank you for that. I was just hoping to get some clarity that the margins will move in tandem. So as we go along completing the project, at that point in time, also, the margins would be there at least minimum of 7.5%, and our efficiencies will help us to gain higher margin. So that is what I wanted to get clarity on.

Vipin Saxena

executive
#111

Okay, so our margins really shouldn't drop below 7.5%. But if serious inefficiencies start creeping in — or if there are major delays — either way, because of a delay, you end up paying more for the guarantee, for warranty, for escalation tied to the cost of service engineers and their own contract workers; all of that will eat into your profit margins, right? So we have to stay alert and agile to make sure we stay on track.

Operator

operator
#112

The next caller we have is Ravi Naredi with Naredi Investments.

Ravi Naredi

analyst
#113

Regarding other current liabilities, sir, the number stands at INR 3,523 crores compared with INR 2,563 crore — so what exactly is that figure?

Vipin Saxena

executive
#114

Could you say that question again? I’ll have my finance team respond to you.

Ravi Naredi

analyst
#115

The next item is other current liability.

Vipin Saxena

executive
#116

Say it one more time, and they'll write it down and give you a reply.

Ravi Naredi

analyst
#117

Other current liabilities, those are included there...

Operator

operator
#118

Mr. Naredi, sir, we can't hear you very well.

Ravi Naredi

analyst
#119

Other current liabilities — hello?

Vipin Saxena

executive
#120

Yes.

Ravi Naredi

analyst
#121

Other current liabilities came in at INR 3,523 crores, compared with INR 2,536 crores. So that number is INR 3,523 crores, correct?

Sarvjit Dogra

executive
#122

This is the Director of Finance speaking. Because of the payments we've received from the customer, and since the work is currently in progress, that's the reason it appears under other current liabilities.

Ravi Naredi

analyst
#123

Right, right, right. So the advance has come in for the content, correct?

Vipin Saxena

executive
#124

That does not constitute progress.

Sarvjit Dogra

executive
#125

It's not an advance. This is a stage payment, and the work is still ongoing — it isn't finished. If you look for a similar item, it will also show up under other current assets, where we've performed the work. But the credit payment hasn't come in, and the bills aren't certified. So that similar item will appear on the asset side as well.

Ravi Naredi

analyst
#126

Okay, got it. And sir, just to add one more thing. This year our top line came in at INR 1,433 crores, while our order stands at INR 27,000 crores. So for this INR 27,000 crores order, how many years will it take to complete?

Vipin Saxena

executive
#127

Look, this is a bit of a misnomer, because right now what you're seeing is that our top line stands at INR 1,433 crores. The reason is that all the new projects — the old ships that were just delivered last year — were in the final stage of construction, and the VoPs were nearly fully booked on them. The new projects of 17 Alpha are only at the fabrication stage. That is, our first ship of 17 Alpha, which is the biggest project, is going through the hull construction phase. The second ship is also of 17 Alpha and is going through the hull construction phase. But somebody already asked me about this, which I have clarified. The shipbuilding you're looking at is not going to follow a straight line. It's a different curve — at some point in shipbuilding, when it reaches around 30% to 35% of the construction, revenue from operation goes up tremendously. It starts moving up and goes up to, say, 65%, it peaks at 65%, where the maximum equipment would have gone on board the ship. Therefore, you would have booked considerable revenue. So whenever we reach the figure of 30%, 35% of construction of the first 17 Alpha, and then we move beyond that, in that financial year, we will have the maximum booking against the first ship.

Vipin Saxena

executive
#128

Suppose the first ship's price is around INR 6,000-odd crores; then the largest revenue from that INR 6,000-odd crores would be recorded by me during that financial year. Therefore, for FY '22 and afterward — regarding the first ship, I stated that from FY '22 on, that vessel will begin recording significantly greater revenue and significantly greater expenditure, all right? In some years it will actually be quite substantial — let's say FY '22 through FY '25, until then, or perhaps a bit longer, depending on how the first ship progresses. Once the first ship reaches 65% of your recorded maximum revenue, that figure will begin to fall, since most of the equipment has already been accounted for. At that point it will be in the trial, testing, tuning, and acceptance stage. By that time the second ship, one year later, would reach 35%; when you get to 65%, the second ship has reached 30%, 35%. That vessel, too, will begin recording its maximum revenue. So this target applies to the third vessel as well. You will see that in certain years — from, say, '22, or '21 as well — it will be, I would say, a good year, but the increase will never follow a straight line. It will be an entirely different curve each time.

Ravi Naredi

analyst
#129

Okay. But to put it in summary form, if I follow your line of thinking, that INR 27,000 crore order — will it be finished in 5 years or in 7 years?

Vipin Saxena

executive
#130

Look, under the present delivery schedule for the 17 Alpha survey vessel and the ASW shallow-water craft, the first survey vessel should be handed over in October 2021, which is next year. Due to COVID, post measures, it may take 2.5 months. By the end of '21, next year, the large survey vessel will go. Now the price of 1 survey vessel would be roughly — you see, INR 2,400 crores covered 4 ships, so 1 ship would cost about INR 600 crores. So I'd say the first ship <<foreign_lang>> delivery around end of May, early next year somewhere, I'll be booking the maximum revenue on the survey vessel itself, the first ship. The second ship would also be at some stage of construction, and I'd be booking on the survey vessel. So overall, I'd say this INR 27,000 crores, INR 26,500-odd crores that you're seeing, the current order book, the executable order book, I'll start getting good revenue from these survey vessel and 17 Alpha projects somewhere from the last quarter of '21, then '22, and it continues after that. So that's how I see it — and then '22 and beyond is going to be something of a golden period for GRSE.

Vipin Saxena

executive
#131

So here's my current take: starting in '22, we're heading into a golden period. It should run for 3 years — 3, 4 years. By the end of '27, I'd be finishing delivery of the final 8 ships of the ASW shallow watercraft. So through '27, the 3 projects we currently have will be sitting in various different stages of delivery. So it won't be — right now we're in 2020, 7 years.

Operator

operator
#132

Our following question comes from Parimal Mithani at Credential Investments.

Parimal Mithani

analyst
#133

Sir, this concerns your Project 17 Alpha. So, because of the coronavirus, if there’s any delay, is there any room to negotiate with the army regarding the LD charges, since it’s not an internal event—it’s due to external events? Is there any…

Vipin Saxena

executive
#134

Right, a force majeure clause is already in place, and that request has already been submitted to the Indian Navy and Ministry of Defence. Because of the COVID, LD should not be charged to us.

Parimal Mithani

analyst
#135

Sir, the second thing I wanted to ask about — earlier in your call, you mentioned certain orders that the government had in the pipeline for the advanced corvette. Is there any update on where any of those stand, sir? Are they on hold, or what is the situation at present?

Vipin Saxena

executive
#136

Right now, nobody has informed us that those have been put on hold — that's simply not something we're aware of. We've turned in RFP responses for 3 or 4 odd Navy and Coast Guard projects. In fact, on 14th of June, we will be handing in our response to the RFP for building 2 multipurpose vessels. So at this point, I don't believe any signal has come from the Navy or the Ministry of Defence that they're holding up any of these new projects.

Parimal Mithani

analyst
#137

Then, sir, the second one is the financial question regarding those 2 critical projects, Project 17 Alpha and the ASW corvette. Sir, given that these involve milestone payments and we receive funds from the government against milestones, do you see any point, or anticipate going forward, that the government might ask us to borrow the money because their own finances are under strain? Or is that provided for, sir?

Vipin Saxena

executive
#138

Yes, government funding will undoubtedly create pressure. We anticipate some strain when it comes to the stage payments that are scheduled. But right now, yes, in the first quarter, certain payments we had expected to receive have been delayed. Still, I genuinely hope the government will find some way forward, and we'll have to wait and watch how they respond. But as I said, this year — this financial year — we shouldn't be hurt by any lack of funds or stage payments. We're reasonably comfortable. That's the reason we refer to them as stage payments, to cover all such eventualities. We have sufficient cash in the bank. And operations will carry on. I see no reason why any of my investors or companies should worry about this at present.

Parimal Mithani

analyst
#139

Okay. And sir, lastly on LD charges, has any of that LD charge amount come back to us during this year — in the current year?

Vipin Saxena

executive
#140

Any LD charges that came back in…

Sarvjit Dogra

executive
#141

Yes, yes.

Vipin Saxena

executive
#142

No — at this point, I'm expecting that during this financial year, in '21, something could come back to us.

Operator

operator
#143

We’ll take our next question from Bharat Parekh, who is calling in from CLSA.

Bharat Parekh

analyst
#144

Well, congratulations on winning that competitive bid for the ASW Corvette. If you could help us get a clearer picture, sir — regarding the FX component, meaning those foreign exchange purchases, how much breaks down between direct imports and what you're able to source from your vendors? And then as well, could you walk us through the price variation clause, considering the delivery timeline runs something like 6 to 7 years? If you could shed some light on that, that would be helpful. That's my first question.

Vipin Saxena

executive
#145

Look, Bharat, the situation is this: for both the survey vessel and the ASW shallow watercraft project, the contracts are fixed-price, since we won them through competitive bidding. On the price variation clause — the survey vessel has one, whereas the ASW shallow watercraft, that craft project, does not. Right, when it comes to the survey vessel, we don't expect any major equipment to be involved. Sure, there is some equipment, but not in large quantities that would be sourced from suppliers abroad. With the ASW shallow watercraft, we do have some, and there will be, I'd say, some pressure arising from currency movements, given that the dollar and the euro have risen. Yeah, that's the area where it will be difficult — in fact, the ASW shallow watercraft gives us no means of getting help.

Bharat Parekh

analyst
#146

Sir, hello.

Vipin Saxena

executive
#147

Yeah, I can hear you.

Bharat Parekh

analyst
#148

Sir, could you give us even a rough estimate of the potential foreign exchange component in ASW, and any potential given the government's plan to indigenize? Do you also have a plan, sir, given that FX has already moved 10% over the last 1 year, which is very difficult to bake into any bid — otherwise, you won't win. So can you help us understand the approximate percentage of the foreign exchange component of ASW?

Vipin Saxena

executive
#149

Look, Bharat, at this point I don't believe that can be done. We'll make it available to assist you and put you in touch with the finance department — that's the Director of Finance. They can provide you with every detail on all of these matters. That said, where indigenization on the survey vessel project is concerned, I can say we've already moved forward on one item given its substantial value. We've successfully completed — some firms have been identified that are capable of manufacturing and supplying that particular item for the survey vessel project. On the ASW shallow watercraft as well, we've made a representation to the Ministry of Defence and the Indian Navy with the background. We have certain important sensors that could be sourced within India. That also appears to be taking shape in some manner, though we're still waiting for what I'd call a definite final answer from there. But certainly the government and all of us are working jointly toward maximum indigenization of the important and major equipment, et cetera. So all of this is in progress. But since these are all ongoing projects, indigenization is a long-term activity.

Vipin Saxena

executive
#150

With major equipment and items, it doesn't happen in 1 month or 2 months. So it's a process that we've started, and maybe over the long term it may deliver some good dividend. But as of now, whatever is feasible — we collectively, together with the Ministry of Defence, defense production, the Navy and the shipyards, are working alongside the industry to see what all things we can perhaps indigenize.

Bharat Parekh

analyst
#151

Thank you, sir, and best of luck with that. Sir, my second question concerns the second vessel — the survey vessel — for which the hull will be built at Kattupalli. Could you help us understand the logistics, sir, including whether some of the assembly work might also take place there under the contracts that follow? Or is it just the hull that comes back here, with the fit-out done at this location? If you could walk us through the logistics for the remaining three — that is, the second, third and fourth vessels?

Vipin Saxena

executive
#152

Yes, Bharat, the situation is like this: those 3 ships we've contracted out for construction — mainly the hull work — went to Kattupalli so that we could make use of their idle capacity, and we believe that will pay us a solid dividend. It also allows faster construction, since we already have a large number of projects underway here. So Kattupalli took on that particular job from us at a very good cost. Now, for the first ship, we expect to receive it with roughly 50%, 55% of the hull finished plus certain equipment. So that's the percentage of construction that can be and will be done on the first one as per the contract. That's the first hull under the Kattupalli contract. What that means is the second ship will be delivered with 50%, 55% of the construction done. The second ship will be beyond that. Then the third as well. For that, we have already drawn up the plan for supplying the material, which includes the steel, which includes certain equipment, which includes the double chain machinery, which will be installed by them under the supervision of GRSE and the Indian Navy representatives and class authorities. So all those things — all the equipment and the steel plates — are being supplied to them, and everything has been well planned now to make sure it proceeds systematically and seamlessly.

Bharat Parekh

analyst
#153

Yes. Thank you. Just to clarify, sir — for the second, third, and fourth, will all 3 of those ships, at the 50% to 55% level, be built in Kattupalli?

Vipin Saxena

executive
#154

Right. The third and fourth ones might come in slightly above that, or it really depends on how things advance and what kind of progress they demonstrate. We do have the choice to ship additional equipment out there and have it installed.

Bharat Parekh

analyst
#155

Thanks, that's genuinely useful. And finally, sir, on the project pipeline you mentioned — I realize the final bid is competitive and confidential. Still, if you could offer any sense of the scale of value those tenders represent, that would be a big help, sir. Whenever it gets decided is fine, but just to get a sense of the 12 SEVs, 8 SPVs, the 6, the next-gen missile vessels and 2 MPVs, yes?

Vipin Saxena

executive
#156

This is what is — something referred to as AIP value by the — provided by the DAC, that's the Ministry of Defence, you know defence acquisition comes... <<inaudible>> Bharat, are you able to hear me? We'll move on to the next question.

Operator

operator
#157

Sir, Bharat is right there, sir.

Bharat Parekh

analyst
#158

Yes, sir, go right ahead.

Vipin Saxena

executive
#159

Yes, Bharat, to give you a sense — say, for the 16 new generation missile vessels, these are quite complex ships. They're not large in size, but they are complex, so the cost would fall somewhere around INR 12,000-plus-odd crores, as per the AIP. I don't have the exact figures with me at this juncture, but it's in that range. Similarly, around 8 FPVs, which we have responded to, would come in at roughly INR 700 crore to INR 800-odd crores, okay? So those are the things — PCB has already opened up, so that is already out. So likewise, I'd say this is what the likely cost of the projects is. So NGMV is certainly going to be very, very high value.

Operator

operator
#160

Our next question comes from Ritika Agarwal, who's on the line with QUEST Investments.

Ritika Agarwal

analyst
#161

Sir, my question concerns the ship repair business you mentioned during the previous quarter. So, have you managed to enter that segment yet?

Vipin Saxena

executive
#162

Yes, regarding the ship repair business, we are genuinely putting in a lot of effort on that front. We have already — as I mentioned to you previously — set up a dedicated department for it. Certain officers have also been assigned. It is led by officers at the AGM rank level. And we have been working diligently with the Indian Navy to secure the refit contract on a long-term basis — what we refer to as a multiple refit contract for the ships we built as LPUs for the Indian Navy, all of which are stationed at Port Blair. But I believe some decisions and discussions are taking place at Naval headquarters. Still, we are very much engaged with this — and we have actually been bidding, looking for the refit work with the Coast Guard; we did bid, but unfortunately, we did not end up as the L1. Nevertheless, we remain active in this particular business vertical. We have just received some repair contracts from the Coast Guard — not high-value, but it is going to be roughly — shortly, we will be receiving the order for that INR 3 crore to INR 4 crore. So we have made a start in that direction, and we are sincere and serious about it.

Ritika Agarwal

analyst
#163

Okay. Okay, sir. Sir, for my second question, would it be right to assume that projects secured through competitive bidding would carry somewhat higher margins compared with nomination-based projects, which have a PBT margin of 7.5%?

Vipin Saxena

executive
#164

Look, I’d say disclosing those strategies wouldn’t be appropriate. On the nominations, as you know, it’s 7.5% under the norms in place now — the government-approved norms. With competitive bidding, it could be anything. And it wouldn’t be right for me to share those strategies; it could be higher as well, or lower, depending on what type of project it is and who the competitors are. So that really varies, based on all sorts of possibilities and other market conditions.

Ritika Agarwal

analyst
#165

Right. Sir, got it. Sir, for my final question, I'd like your take on export orders — how do you see the company's export orders shaping up going forward.

Vipin Saxena

executive
#166

Yes. I just walked someone through the fact that there is 1 hospital vessel built for the Coast Guard whose trials are already finished. The positive side is that the Government of India, through its different programs with various friendly foreign nations, will be handing over this ship, and it will go out as an export. So GRSE would soon deliver that vessel as an export order to a friendly foreign country. We keep working hard with plenty of foreign nations, along with Defense Attaches and numerous agents and so on, who operate in certain countries that we are targeting. And we do hope that in the times ahead we should secure some orders. But this is not something within your control, and all we can do is make the attempt and keep trying, and international markets are not that simple. So we must keep attempting and keep trucking.

Operator

operator
#167

Our following question comes from Deepak Poddar at Sapphire Capital.

Deepak Poddar

analyst
#168

Sir, in one of the questions, you mentioned that for FY '21 you're looking to maintain or looking to reach the targeted revenue. So I just wanted to understand what the targeted revenue is for FY '21? And for FY '22, we've been talking about higher growth from FY '22 onwards. So do we still maintain that?

Vipin Saxena

executive
#169

Right, so I'm targeting that as FY '20 into '21. And my hope is that FY '22 will begin delivering a huge amount of happiness — really huge — for GRSE, for all the shareholders, for everyone, in terms of revenue generation, with all of it doing much better. That is what the plan is.

Deepak Poddar

analyst
#170

So for fiscal '21, what's the MOU target? Are there any effects from the MOU target?

Vipin Saxena

executive
#171

Look, it's due to the COVID lockdown and so on — lots of things still aren't happening at the deep sea MOU committee. But I told you it won't be hugely — it won't be below last FY '20, but it will be — look, we ought to aim at minimum to do somewhat better than FY '20, that's what my...

Deepak Poddar

analyst
#172

Alright. Alright. Got it. And sir, my second question is about whether there's any thinking on consolidating the defense companies, basically, or any kind of merger with other defense companies. So is any sort of thought process underway within the ministry, or anything on that?

Vipin Saxena

executive
#173

No, no such communication has come to me. I’m not aware of anything like that, and I don’t know at what level it would be — all of this is hearsay, and nothing of that kind has reached me, and I’d say very much so as GRSE and continuing with — because we have so many projects in hand, we have — our hands are completely full. We’re all looking forward to doing good things in the shipyard and delivering good results.

Operator

operator
#174

The following question comes from Hardik Jain with ISJ Securities.

Hardik Jain

analyst
#175

Sir, nearly all of my questions have been addressed. I just have one very small point to clarify, sir. So when you mention that the Ministry has — we are seeing some form of pressure regarding the payments coming from the customers. And — but you will have enough — you have enough cash on the books, and you're able to use that cash for operations during this year. However, that could impact our other income — is that — is my assumption correct?

Vipin Saxena

executive
#176

Yes. I think we really need to strike some kind of balance here instead of going hungry while waiting for the customer's funds to arrive. When you've mapped out milestone payments that are tied to reaching certain stages, and you haven't hit that stage yet, you haven't finished that piece of work, so these things are already baked into your various factors as part of your overall costing. So it's very much on that basis that I have to use this money that's sitting with us — maybe it will certainly have an impact on our other income. But I think, in the bigger game, if you plan for how much you'll be affected if your production gets disrupted, then it's wise for anybody to use the money available with you, because you aren't earning a great amount of interest — interest rates have dropped drastically — so it's better that you use this money appropriately, wisely, okay.

Hardik Jain

analyst
#177

All right. And is there any chance we might take on some kind of borrowing to finish carrying out our operations? Or should the cash we're holding on the balance sheet be enough?

Vipin Saxena

executive
#178

Hardik, right now I don't believe I really need to consider that direction. Whatever items exist under my plans and my assessment—coming from the finance team, given this year's funding needs across various activities—I think we should be comfortable.

Operator

operator
#179

Following that, we'll take a question from Manoj Shah at LEFCO Investments.

Analyst

analyst
#180

I also have a question about receivables. They've climbed from INR 220 crore to roughly INR 535 crores. So I just wanted to ask whether any payment has come in from the government over the last 6 months. And what are they telling you about when the payment will arrive this year? In the next 6 months? Or how does it stand? Has that communication come through?

Vipin Saxena

executive
#181

Could you say that again? What exactly is…

Sarvjit Dogra

executive
#182

And what about the receivables from the most recent setting, or the actual payment — is that the reason the cost has risen?

Vipin Saxena

executive
#183

Manoj, our Director of Finance, made it clear that yes, owing to the COVID situation, certain payment that should have reached us did not arrive. That is the reason the existing receivables figures have risen. And the first quarter, naturally, is under stress. And I really do not see — anticipate that the whole amount would be coming to us. There could be certain reductions, and so on. So — but we will have to wait and watch.

Analyst

analyst
#184

So you're figuring that only in the second half will there be any payments coming in — some payments during the second half. Is that the right way to look at it?

Vipin Saxena

executive
#185

That's purely a guess, yes — we're hoping things improve starting in the second quarter, even if they don't become great. But hopefully we should begin getting something, and that's what my expectations are.

Analyst

analyst
#186

Right. But nothing official has come through saying, okay, your payments may be delayed, so we’ll get it that way, sort of thing? Has there been any communication on that or not?

Vipin Saxena

executive
#187

Yeah, the ministry has given some signals that owing to COVID and the need to spend in other areas—other segments of the department—we might see some cuts, okay? A certain percentage was indicated right in the first quarter, but the funds haven't been released yet, and only after that will we be able to see how much of the cuts they've indicated will actually take effect and be implemented. But there is going to be...

Analyst

analyst
#188

Regarding that percentage — yes, the percentage cut — does that mean you'll receive that money at a later point? Or is it money you won't receive at all?

Vipin Saxena

executive
#189

No, no — the money will reach you. The only issue is that right now, when they process the payment, you might not receive the entire sum. For instance, take INR 100 crores: if there's a 20% reduction, or 30%, or 40% trimmed from the payment itself, then they'll deduct that portion, and it would be handed to you afterward, at whatever point the government receives...

Analyst

analyst
#190

So essentially, you’ll receive partial payment, and that’s how it’s going to work.

Vipin Saxena

executive
#191

Yeah, yeah.

Operator

operator
#192

That brings us to the end of the Q&A session, everyone. At this point, I'll return the call to the management team so they can offer their closing remarks. Sir, the floor is yours.

Vipin Saxena

executive
#193

I appreciate all of you, ladies and gentlemen, for joining this conference call. I truly hope I've managed to lay out before you the different operations — both the physical side and the financial side, along with performance. We did our utmost to respond to every question you raised, and so on. But let me assure you that — notwithstanding the constraints and difficulties caused by COVID, or the challenges — we are getting ready. We've mapped out our strategies for getting past all those setbacks and issues as time goes on. FY '21 definitely comes with challenges, yet we have plenty of opportunities to work with fresh philosophies, fresh techniques, and fresh tactics. That is my plan, and I will try to put it into practice, though only time will reveal how far we succeed. So let me assure you that the company ought to perform still reasonably well in spite of these troubles in FY '21. Once again, though, my request is this: comparing one quarter to another will not be the right approach. We will face trouble in quarter number one, the first quarter. And we would hope that starting with the second quarter, at least the physical things, the physical activities onward in the shipyard, would pick up.

Vipin Saxena

executive
#194

So overall, I expect the shipyards to perform well, and we will put all the new measures into practice, potentially across various operational areas. And once more, I want to express my gratitude and give you my word that the company will keep delivering solid results and will aim to grow further. Many thanks, <<foreign_lang>>. And should you have any additional questions regarding any account, you may kindly — whether on financial matters or anything else, you can reach out to the Director of Finance and the Chief General Manager of Finance. They will be ready, and they will gladly provide answers. If there is anything more — something beyond that, you can also get in touch with me if I can help answer it. Thank you very much.

Operator

operator
#195

Much appreciated, sir. Ladies and gentlemen, many thanks to each of you for joining today's conference call. Should you require any additional clarification or details, please send an e-mail to gaurav.g@conceptpr.com or irfan@conceptpr.com. Ladies and gentlemen, that brings today's conference to its close. Thank you for using Chorus Call conferencing services. You can disconnect your lines at this point. Thank you, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Garden Reach Shipbuilders & Engineers Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Garden Reach Shipbuilders & Engineers Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Garden Reach Shipbuilders & Engineers Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.