Garden Reach Shipbuilders & Engineers Limited (GRSE) Earnings Call Transcript & Summary
November 15, 2022
Earnings Call Speaker Segments
P. Hari
executiveThank you, Yashashri, and I appreciate the chance to talk with all of you. Good afternoon, everyone. I'm Commodore P.R. Hari, Chairman and Managing Director of Garden Reach Shipbuilders & Engineers. With me on this call are our Director of Finance and CFO, Shri Ramesh Kumar Dash; Ms. Aparajita Ghosh, Finance Head; and the Company Secretary, Shri Sandeep Mahapatra. I want to welcome all of you to this conference call, during which we'll go over the company's financial results for the second quarter and the half year that closed on 30th September 2022. I'll structure my comments into a few sections: the financials, where we stand with the order book, how we plan to execute the current order book, and a quick view of what lies ahead. For the six months that ended on 30th September, the financial results have been quite heartening — revenue from operations climbed from INR 726 crores to INR 1,262 crores. That works out to a 74% gain when you set the half-year figures for FY '22 against those for FY '23. If we look at revenue from operations for Q1 '23 versus Q2 '23, it grew by 18%, moving up from INR 580 crores to INR 682 crores. In the same way, comparing one half-year with the next, total income rose 67%, moving from INR 802 crores to INR 1,344 crores. EBITDA climbed between the two half-years, going from INR 125 crores to INR 163 crores — a gain of 31%. Between Q1 of '23 and Q2 of financial year '23, EBITDA grew 20%, rising from INR 74 crores to INR 89 crores. PAT — profit after tax — on a half-year versus half-year basis increased 37%, from INR 79 crores to INR 109 crores. In Q1 of FY '23, PAT stood at INR 50 crores and then advanced 17% to reach INR 59 crores. Earnings per share moved up from INR 6.93 to INR 9.51, which works out to a 37% rise comparing the two halves of the year. Overall, then, our financial results have been satisfactory, and we have strong confidence in sustaining the momentum built up over the first half of this financial year, carrying it into the second half, and in that way delivering solid financial performance for the year as a whole. Turning now to where our order book stands: as of 30th of September 2022, it is at INR 22,930 crores. Within that figure are 7 shipbuilding projects, which together amount to 24 platforms — marine platforms. On the Indian Navy side, there are three programs: P-17 Alpha, which involves three ships; the Anti-Submarine Shallow Water Craft effort, covering eight vessels; and a Survey Vessel Large program with four ships. Altogether, those three Indian Navy efforts come to fifteen warships. Beyond that, we have a project underway for the Government of Guyana—a passenger cum ocean going ferry vessel—along with an Indian Coast Guard order for a Fast Patrol Vessel. We are additionally building six patrol boats for the Government of Bangladesh, and we have another effort for the Government of West Bengal involving a next-generation electric ferry. Shipbuilding accounts for the bulk of our order book — close to 97% to 97.5% — and the rest is spread across diversified segments: Bailey Bridges, deck machinery, diesel engine and ship repairs. Turning to how we're executing current projects: out of the 7 shipbuilding projects underway at present, 2 are slated for completion within this financial year. That is the project for the Government of Guyana — an ocean-going passenger cum ferry vessel. At this point the vessel's physical construction stands at roughly 75%, and we plan to finish this project in the final quarter of this financial year. On the Fast Patrol Vessels for the Indian Coast Guard, physical progress has reached nearly 81%, and the ship is currently undergoing trials. Delivery is scheduled once more for the final quarter of this financial year. Turning to our other shipbuilding efforts, I'll begin with P-17 Alpha. As mentioned before, we are currently building 3 P-17 Alpha Frigates for the Indian Navy. Physical construction on the first vessel stands at roughly 43%, the second at about 35%, and the third at around 16%. We are satisfied with how these ships are progressing. Under the current build schedule, the initial vessel should be handed over around mid-2025, with the final one following near mid-2026. Turning now to the Survey Vessel Large program: we currently have 4 vessels in construction there. The lead vessel, launched late in 2021, has already reached 65% physical completion. It is about to enter the trial stage, and our plan is to deliver it in the first quarter of the coming fiscal year. The program's second vessel now stands at roughly 58% physical completion. That vessel should be handed over toward the close of the following calendar year — specifically, the third quarter of FY '24. Work on the final two ships in this project is progressing well too, with those two having reached 38% and 14% completion respectively. Turning to the Anti-Submarine Shallow Water Craft project, it involves 8 ships, and production has already begun on 5 of them. Construction on the first ship stands at roughly 38 percentage, and it is set to be launched — and in shipbuilding, launch is a milestone moment when the vessel enters the water for the first time once its hull is fully formed. The launch of this specific vessel under the ASW Shallow Water Craft project is set for next month. Similarly, about 23% completion has been achieved on the second ship of this project, while the other vessels are moving forward according to the build schedule. Based on the present strategy and our construction approach, these ships should be delivered by FY '27. That should give you a sense of how our ongoing shipbuilding programs are advancing and their current status. As you can observe, the INR 22,930 crores order book we currently hold will sustain a consistent workload for us through FY '27. Now let me shift to the pipeline orders and what comes next. On a previous earnings call, I mentioned that GRSE had secured the L2 position in an Indian Navy RFP covering construction of 11 next-generation ocean-going patrol vessels. Per the tender rules, the L1 bidder receives 7 vessels, whereas the L2 bidder — GRSE — receives 4 vessels. Based on how things are moving forward, finalisation of this contract ought to happen during the present financial year, with an anticipated value of roughly INR 3,000 crores to INR 3,200 crores.
P. Hari
executiveWhat I want to get across is that on one hand we're working through the order book we have now, and on the other hand that gap in the order book keeps getting steadily refilled as we execute. So this INR 3,200 crores, together with what we will execute over the course of the current year, should be enough to keep us at an order book position of roughly INR 23,524 crores at the close of the current financial year as well. Turning to the other orders in the pipeline, one big one GRSE is really eager for is the next-generation Corvette. The Defence Acquisition Council has already granted an approval of necessity for this Indian Navy project, and it's a high-value one at almost INR 36,000 crores, and based on our present estimate, the Indian Navy will likely release the RFP for this project by end of calendar year '23 or early 2024. Also, based on — again, based on how we understand and appreciate it, this is an 8-ship project involving 2 shipyards, 5 and 3, 1 ship — the L1 shipyard will build 5 ships, and the second shipyard will build 3 ships. Given how much experience GRSE has in constructing and handing over Corvettes — and this one is the next-generation Corvette — so, considering GRSE's history of building and delivering Corvettes, plus the experience, expertise and resources at our disposal and our bidding strategy, I'm confident we'll do what's appropriate to ensure we have a very strong likelihood of securing this bid. Beyond the next-generation Corvette, the Indian Navy has another project — a high-value landing platform docks project. For that one, the RFP is again expected to be issued in 2024. Beyond that, the Navy also intends to construct twenty follow-on waterjet FACs. As some of you might be aware, GRSE has delivered the highest count of FPVs and waterjet FACs—vessels of the same class—with over thirty such craft supplied to both the Indian Navy and the Indian Coast Guard. Therefore, as with the next-generation Corvettes, when we continue to pursue this tender, our approach would be suitable to provide our contemporary shipyards with adequate competition. In addition to these three projects for the Indian Navy, the Indian Coast Guard has a few projects expected to arise soon. One project involves 14 Fast Patrol Vessels, and its RFP will probably be released before this calendar year wraps up—so either this month or the following one. The order's value should land somewhere near INR 1,500 crore to INR 2,000 crores. Beyond that, the Indian Coast Guard will likely issue an RFP next year covering 18 next-generation Fast Patrol Vessels. That, in short, gives you a picture of what's coming down the pipeline. So that's the shipbuilding side. Turning to ship repairs, as I noted on an earlier investor con call, we acquired the 3 drydocks along with long-term leased spaces from the Kolkata Port Trust. At present, all three drydocks are heavily utilized for work connected to ship repair. Our goal in acquiring these drydocks was to boost ship repairs, which is another vertical GRSE is now viewing very seriously. Although we acquired the facility roughly 11 months ago, the results achieved to date have been encouraging, and occupancy of this dock has been nearly 100%. We also have an Indian Coast Guard order for carrying out refits of their vessels, along with a few commercial vessels for which we are performing drydocking and repair. Looking ahead, ship repair is one focus for our yard over the next several years, and among our diversified segments sits the Bailey Bridges division. GRSE currently holds roughly 65% to 70% of the Indian market in Bailey Bridges — those are portable steel bridges, as you likely know. We have signed an MOU with the Border Roads Organization covering supply of a specific modular bridge type, and the shipyard holds proprietary rights to it as an IPR; that gives us an advantage when it comes to securing additional orders from prospective customers — namely the Indian Army and the Border Roads Organization. Now regarding the Diesel Engine Plant — we operate one in Ranchi under a licensing arrangement with MTU of Germany. That agreement gives us the facility and capability to assemble MTU diesel engines and to carry out trials and acceptance testing. In this segment, we anticipate orders from the Indian Navy for its projects that call for medium- and small-sized diesel engines. Beyond that, this unit — the Diesel Engine Plant — has secured an order to supply 28 diesel alternators for the P-17 Alpha projects, which are being executed by both Mazagon Dock and our own shipyard, GRSE. There's also a separate division that builds and provides deck machinery for vessels under construction at GRSE as well as at the other shipyard. So across all of these areas — meaning the shipbuilding segment, which is unquestionably our largest source of revenue, together with Bailey Bridges, ship repair, deck machinery, and the diesel engine verticals — we feel highly confident about a growth path in the years ahead that will be extremely encouraging for you, the investors. That concludes my remarks, and I'm ready for questions, so moderator, you may take over.
Venkatesh Subramanian
analystSir, I have 2 questions. The first concerns that last item you brought up regarding various other things, such as ship repair and steel bridges, et cetera. Taking all those units together, let's say across a 3-year span starting now, sir, roughly what top line would you picture from these projects? That's my first question. My second question concerns the INR 36,000 crore RFP for next-generation Corvettes. As the L2 bidder, we'll receive — my sense is we'll receive orders for 3 vessels. And what might that value be, sir?
P. Hari
executiveThank you, Mr. Venkatesh. I'll take your second question first, while in my head I'm working out what INR 36,000 crores multiplied by 3 and divided by 8 gives. So that works out to, one second, roughly INR 13,500 crores; but let me tell you, bidding at L2 is not what we're looking at. In the end, it comes down to how we bid and how the others more — how our competitors are going to bid. But seriously speaking, L2 is not at all what we're looking at for this project. So, answering your question, if you become L1, the value accrued from this project comes to roughly INR 22,500 crores, and if it's L2, roughly INR 13,500 crores.
Venkatesh Subramanian
analystRight, sir, great. And the other point concerned the INR 3,000 crore orders, sir.
P. Hari
executiveWell, that INR 3,000 crores order — whether you call it INR 3,000 crore or INR 3,200 crore — the bid for this project was opened at the end of February this year, and of course it sits between the tender stage; the participants were every one of the shipyards, all 5 of us, meaning 4 <<inaudible>> L&T, Cochin shipyard and so forth. So we ended up as L2, and under the tender terms, 7 of these ships go to the L1, which is the Goa shipyard, while the 4 ships come to us. So as things stand, the project is in the negotiation phase between the bidders — the winning bidders — and the Indian Navy; and going by the indications, the contract will probably be signed by — during this financial year itself. So that gives us an order book value of roughly INR 3,000 crores to INR 3,200 crores.
Venkatesh Subramanian
analystSo what you're saying is roughly INR 3,200 crores for about 4 vessels, sir?
P. Hari
executiveYes. That's right. 4 vessels, roughly INR 3,200 crores.
Venkatesh Subramanian
analystAll right, so that comes to INR 800 crores for 1. Just one more quick question, sir. Regarding those 18 next-generation patrol vessels, you mentioned the RFP will be issued next year — what value would that carry, sir?
P. Hari
executiveThose 18 next-generation vessels, for which the Coast Guard RFP is expected to be released next year. Right now, all I can offer is an indicative number, which in my appreciation could be approximately INR 3,000 crores. That's it.
Venkatesh Subramanian
analystSo 8,000 crores of rupees, sir?
P. Hari
executiveIt's 3,000 crores of rupees. These are genuinely small vessels, all right?
Venkatesh Subramanian
analystYes. And sir, for these smaller vessels, is the execution timeline generally shorter?
P. Hari
executiveYes. Absolutely, the time it takes to execute any war ship hinges on, first, the price and, second, the complexity. Now, when we talk about complexity, that complexity hinges on what kind of weapon and sensor get fitted on the ship. These Fast Patrol Vessels are compact ships with, let's say, a very dense concentration of equipment and systems. So although the price is small, the complexity is certainly not as small as it sounds, which is why it's called FPV and so forth. Since you asked about a conventional Fast Patrol Vessel, what — right now I'm executing an order for a Fast Patrol Vessel for the Indian Coast Guard. The build period is 20 to 24 months; so starting from when the design is chosen, it takes roughly 2 years for a ship — for the first ship of a class to be delivered. And after that, we can deliver a ship of this particular type at about one ship per 3 months from there on — thereafter.
Venkatesh Subramanian
analystGot it, sir, got it. Great. My question is about the other 4 business divisions — ship repair, steel bridges, and similar lines, roughly speaking — could you give us something looking out over a 3-year horizon, maybe some kind of guidance on where we might end up, sir?
P. Hari
executiveFine. Like I mentioned at the start, shipbuilding is our primary job and where our attention goes. We've been constructing vessels — constructing war ships. And because we're a separate public sector shipyard, supplying quality war ships to the Indian Navy and the Indian Coast Guard, in line with their expectations, would be our focus and aim. So, with that as our main focus, we've also expanded—as you know, we're the only ones doing this kind of diversification in India right now. Given that diversification, as I mentioned before, there are four verticals we need to look at. The first is the Bailey Bridges segment. While I said on one hand that we hold about 65% to 70% of the Bailey Bridges market share, you have to understand that the total market in India is itself limited. Now, with our new products—the modular type of bridges—and with some aggressive marketing strategy that we've adopted, there's been an improvement. On the Bailey Bridges side, our revenue is really quite tiny — though it's twice what it was three years ago. So I'd expect that business to grow at most twofold, or maybe double, over the coming three years. Now, turning to ship repairs: some shipyards have an advantage over us when it comes to repair experience. They've concentrated on ship repair for 10, 15, even 20 years, whereas we only began treating it as a serious vertical starting last year. As I noted before, we've acquired 3 drydocks specifically to give ship repair a boost. To reiterate, we entered this sector on a small scale. Yet this is a space where possibilities have <<inaudible>> since both the Navy and the Coast Guard clearly require vessel repairs at regular intervals. So right now I cannot quantify what the expectations are, but I can assure you — perhaps what I would propose is that a year from now, let us review where we stand; we began quite modestly. Let us stabilize, and this is the priority area where management's full attention is directed, and I anticipate sharp growth in this segment over the next 3 years.
Rohit Natarajan
analystSir, a competitor of yours mentioned some landing platform dock orders coming up soon, and there's also a chance that P-17 A — a repeat of P-17 A — could be considered in the near to medium term. Do you have any color on those points, sir?
P. Hari
executiveThank you, Mr. Rohit. As of now, the color is gray. On both of those projects — look, the Navy issued an RFI for the landing platform dock a while back. Since then, it hasn't really moved forward. But the fact remains that the Navy does have a requirement for landing platform dock, and from our understanding, the RFP for 2 landing platform docks should come out by 2024. That's our appreciation. And it is certainly going to be a high-value order; and yes, yes, the competitors in this field are only our sister shipyards; and as for the P-17 project; right now the P-17 Alpha project we are executing covers 7 ships <<inaudible>> both MDL and GRSE. MDL is building 4 of these ships, and GRSE is building 3 ships. Under the current execution plan, these ships are likely to be delivered by FY '27, that is mid third quarter of 2026. So that is when this project will reach a closure. So the Navy definitely has plans to go in for a follow-on of the ship, but that is still at the discussion stage. So if the Navy decides to go for a follow-on or more numbers of this, clarity on it will emerge sometime, in my appreciation, only during 2024.
Rohit Natarajan
analystOkay. Sir, my second question is going to lean more toward the margin side. On one hand, we get that 1.5% represents the physical execution progress made at each ship unit level; but in margin terms, what does that amount to? I mean, is there any lumpiness as more brought-out items get sold as something that feeds into our fitting or advanced outfitting stage? How does that really shape up? Could you give us some color there?
P. Hari
executiveOkay. Let me walk you through the shipbuilding process briefly so that things are seen in the right perspective; shipbuilding, you see, starts with preparatory activities. So that's the design phase — the prep work that happens before actual ship construction starts. During this stage, the vessel's design gets finalized, the equipment gets finalized, and once equipment is finalized, orders go out to prospective OEMs for that equipment. After this process wraps up, and once steel has been procured, construction begins based on the design. Construction kicks off with plate cutting and block fabrication, followed by block erection. At that point, the equipment that was already ordered begins arriving; it gets lowered in and outfitting gets underway. After a ship’s hull form is essentially complete, that vessel is put into the water, its buoyancy and floating capability are verified, and then outfitting proceeds at full pace. When outfitting is finished, trials move forward, culminating in the ship’s acceptance following the relevant harbor speed trials and speed trials; that, in brief, gives you a summary of the four stages of ship construction. Also note that, measured by overall cost percentage, this accounts for roughly 5% of a ship’s cost. When you consider the vessel's build, the whole thing—the hull plus the fundamental fittings—accounts for roughly 18% of the ships over; if the ship is taken as 100%, it's about 18%. In the early phases of vessel construction, progress tends to sit near 1% to 1.5%. Later, once equipment begins being lowered in, progress climbs, and then a point arrives where equipment is integrated into the vessel and systems are buttoned up. So every ship's construction will have a stage where progress jumps from 1% to 1.5% to 2% to 2.5%, depending on the vessel's size. Let me give you an example. For a Fast Patrol Vessel, we're talking about a small ship. At the start, since the vessel is small, progress runs about 1% to 1.5%, and after that it jumps to roughly 3%. There are phases where the ship delivers approximately 7% of physical progress each month. With a large vessel, hitting 7% may not be achievable for us, though at times it does reach 3%. Translating that into VOP—revenue from operations, that is, the value of production—is simple. Value of production means the stage at which equipment and systems, along with labor, go into constructing a ship, though that isn't comparable to profit. These are completely separate matters. Profit depends on many factors, from how equipment is procured, to revenue expenditure, to internal efficiencies, and so forth. So as for physical progress—since your question was about physical progress—where there's a gap of 1% to 1.5%, yes, that occurs at a certain stage of construction, but a stage will come when it picks up, and that will happen once the ship reaches roughly 60% to 65%.
Rohit Natarajan
analystAppreciate that, sir — quite comprehensive. I'd like to dig a bit deeper here. If we take a specific project running at, let's say, 7.5% EBIT margins, there's likely some capacity utilization factor behind it. At that level, were your estimates built around roughly 75% of the shipping capacity you have, or the full 100%; and when margins come in better than expected, is that driven entirely by additional capacity utilization? Am I framing correctly where those margin surprises come from?
P. Hari
executiveSee, how much capacity you utilize depends on the resources and infrastructure you've got. I'm not certain if this point came up before, but allow me to restate it. At present, we can build roughly 20 warships concurrently; and that figure actually understates things, since in any given project — take a four-ship program — the vessels won't all sit at an identical stage at any moment. So if ship one is in outfitting, ship two will be in prelaunch, and ships three and four will be somewhere else along the build sequence. Turning to GRSE specifically, regarding P-17 Alpha: the first and second vessels have already reached outfitting, while just the third remains at prelaunch. On capacity, we face no restriction whatsoever. Another point worth noting is that, as I mentioned, we opted for 3 drydocks, which we've taken on a long-term basis <<inaudible>>. Beyond that, we've adopted a PPT arrangement with two shipyards — one located in Kolkata and another in the Eastern upfront — where partial construction of certain vessels of ours is currently underway. So the resources held captive inside our campus are definitely not a limiting factor when it comes to carrying out concurrent projects. What I mean to say is that capacity poses no constraint.
Rohit Natarajan
analystReally, I appreciate your response, sir. That was very useful. I'm looking forward to further questions. I'll rejoin the queue.
Analyst
analystCongrats on an excellent set of figures. So I simply wanted to ask about the monthly physical execution progress for P-17 Alpha and Survey Vessels and the ASWs; so I just want to know, does it differ from 0 to 40 <<inaudible>> revenue booking being the highest and then from <<inaudible>> to the next level?
P. Hari
executiveThank you, Mr. Bharat. If I take just the P-17 Alpha project, the first ship has reached 43%, the second ship stands at about 35%, and the third ship is at roughly 16%. Now the physical progress from, say, 0 to 20, on a conventional basis, we achieve about 1% to 1.5% each month. Then it begins to pick up — the pace accelerates and we get about 2%. The rate at which this growth speeds up is during a phase when the ship has reached around 60% of construction, where most of the equipment would already have been lowered and the integration and setting to work of the system begin, which means the percentage progress — monthly percentage progress rises when the ship is at a stage where it sits between 60 and 80. If you bring it down to a smaller ship — size ship, then if you're taking, say, a Fast Patrol Vessel, the Fast Patrol Vessels in the first 0% to 15% begin at about 2% per month. And then it picks up perhaps around 2.5% between 15% to 40% and 3% to 3.5%. And there will be one phase when the equipment trials are actually underway, it reaches about 6.5% to 7%. But seriously speaking, the monthly progress is definitely good to monitor. It needs to be monitored. But what we actually focus on is the milestone. The major milestones in ship construction are one, the plate cutting, where we begin production next to the keel laying, when the blocks, which get manufactured at various locations, get lowered onto the building dock or the building dry dock. And once they get consolidated, the next milestone we look at is the launch of these ships. The next milestone is the basin trial. So seriously speaking, we should not really be looking at monthly progress points, <<inaudible>>. It is good to understand, but it doesn't matter. What we must look at is the launch, then the launch to trials and delivery.
Analyst
analystSir, regarding that second P-17 Alpha, when do you expect it to be delivered?
P. Hari
executiveAs things stand right now, the second P-17 Alpha should be handed over in the final quarter of the financial year — FY '26, which runs from January through March 2026.
Analyst
analystAll right. Now regarding Survey Vessel number 3 and number 4 — those — when will those 2 be delivered, sir?
P. Hari
executiveOn the Survey Vessel, we expect the first 2 ships to be handed over in 2023. As for the final 2 ships, those are scheduled for delivery in calendar year 2024.
Analyst
analystOkay, so my understanding is that the shipbuilding process involves 15 milestone payments. How long do those payments take?
P. Hari
executiveWell, it's really about the stages rather than the timing. It starts with — a payment is made when the contract is signed, for the — 10% for proprietary activities and related aspects of that, and then there's a 10% payment for ordering various equipment and for providing the plan for construction of the ship, and so forth. After that, at different milestones, you pay, one will be for so many — 40%. To keep it simple, I'll cite just a single number: at 40% of physical construction, a stage payment is triggered. At launch, another stage payment comes due. When basin trials are conducted, that also brings a stage payment. At 85% of construction, you receive a stage payment, and this leads up to stage 14, which is the point when the vessel is finally handed over to the customer. Stage 15 then arrives when the ship finishes its guarantee period — a one-year guarantee period — and that is the moment the 5% payment comes in. So in a nutshell, this adds up to the full 100% payment, spread across 15 levels, from 1 through 15.
Abhineet Anand
analystSir, I just wanted to check something: you said that by F '27, that entire order book of roughly INR 23,000 crores will be finished. Is that correct, sir?
P. Hari
executiveYes, the order book as it stands today — I'm not counting the order that will probably come in for the next-generation ocean-going patrol vessel, which I also mentioned earlier. Leaving that aside, for the current order book, according to our execution plan, the execution period runs through FY '27, correct. You're right.
Abhineet Anand
analystSo, in very broad terms, could you help us get a clearer picture? From now until '27 is about 5 years, correct? So across the coming 3 years, what would the broader execution look like — say, in terms of broader revenue? I'm not asking about guidance, just, maybe, a ballpark...
P. Hari
executiveI would rather speak in terms of ship deliveries during this financial year...
Abhineet Anand
analystI get it, but when it comes to the ship, what we understand is...
P. Hari
executiveAll right. Let me give you a sensible figure you can use to extrapolate or work out the numbers yourself. Look, on this ship we've already finished the first half. We're sitting at INR 1,262 crores. As I said, production progress across the various ships is satisfactory. And 2 of these projects are — of course, these are small projects, and we plan to complete them this year. So let me frame it differently so you can have more confidence. See, the order book we have left right now is INR 22,930 crores. And I've also said that under the current execution plan, that order book will be used up by 2027. If I include the next-generation, it goes entirely outside that figure. Over the next 5 years, that means INR 22,930 crores divided by 5 comes to roughly INR 4,586 crores. So that's for you to, I mean, extrapolate or calculate. Some financial years could see revenue higher than that. Other financial years will see it lower than that, depending on what stage the ships have reached in construction, but it certainly won't be uniform. Just to reassure you — and I've said this repeatedly in the last 2 investor con calls as well — as per our assessment and taking into account the physical progress of ship construction, because that is what ties directly to payments, I mean revenue recognition. Taking both these aspects together, the current year — see, last year our turnover was INR 1,758 crores; so when I closed the last financial year, when we were discussing the results, we said that the next 3 years, that is FY '23, '24 and '25, will be the best in terms of revenue regulation for the shipyard. So I've given you both perspectives. I've told you what the total order book is, and I've also stated what our execution plan is. So I've even gone to the length of dividing it and spelling it out for you, and I've also assured you that this year, next year and the year after will be — growth will be steady, with perhaps FY '24, '25 or '26 being the weakest.
Shalini Gupta
analystI have two really simple questions, sir. If I've got this right, the revenue you generate per ship comes to roughly INR 700 crores. Is that correct?
P. Hari
executiveMa'am, that differs depending on the project. I'm not certain which project you mean...
Vignesh Iyer
analystNo, sir. I'm simply attempting to arrive at a rough estimate, purely for my own projections. So would it be accurate to say somewhere between INR 500 crores and INR 700 crore — would that be right?
P. Hari
executiveNo, ma'am, let me put this to you and give you the proper context. As you can see, our order book currently stands at INR 22,930 crores. Just a moment, yes — out of that, roughly INR 14,997 crores relate to the P-17 Alpha project covering 3 ships. That leaves a balance of about INR 5,000 crores per ship. Taking the Anti-Submarine Shallow Water Craft, INR 5,821 crores were still left for execution, which divided by 8 comes to nearly...
Executive
executiveThat comes to roughly INR 727 crores.
P. Hari
executiveFor each ship, about INR 725 crores is still left. As for the Survey Vessel, with 4 ships, INR 1,600 crores remains outstanding. Which works out to about INR 400 crores still to come; and for the FPV, the Fast Patrol Vessel, INR 23 crores is left, on 1 ship. So it all hinges on how big the vessel is and what the order is worth. Have you — are we on the same page here? Could you...
Analyst
analystSir, I'll go back and listen to the conference call once more. Should I have any further questions, I'll likely drop you an email or something, because sir, I'm simply trying to figure out how I ought to build my projections. Sir, my second question is just this: what sort of EBITDA margin should we assume, because you were explaining how you get to your EBITDA margin; but I mean, it will be very hard for me to work out the kind of EBITDA margins you might reach? So would it be right to say your EBITDA margins will land somewhere around 17% to 18%, would I be correct?
P. Hari
executiveAt present EBITDA margin stands at roughly 12.7% to 13%. So we — taking into account our current order book, the margins at which we have bid for and won the project, the EBITDA margins, what we expect over the coming years, is for them to be steady, more or less steadier within this range, at least 12.7% to 13%.
Analyst
analystCongrats, sir, on a solid set of numbers. About Alpha <<inaudible>>, I just wanted to ask: what's the original order value behind these 3 figures we're making?
P. Hari
executiveOkay. Regarding those 3 figures we're making, the order value — the total order value — comes to INR 19,296 crores, and what's left of the order value is INR 14,997 crores.
Analyst
analystSo it's about INR 15,000 crores, correct?
P. Hari
executiveRight. Approximately INR 15,000 crores.
Analyst
analystAll right, and the original figure stands at roughly INR 19,296 crores, is that right?
P. Hari
executiveThat's right. That's right.
Analyst
analystAll right, yes. All right. That settles it. The second thing is, sir, if things — word has it that plenty of vessels are in fact scheduled for maintenance, and we're also involved in the maintenance contract side of it. So could you give us a sense of — on that side of the business, as in when a ship needs to go in for maintenance, perhaps once every 2 years or so. So if you...
P. Hari
executiveAll right. I'll take that question. Ships belonging to both the Navy and the Coast Guard undergo repairs at regular intervals, which is known as refit and repair. So depending on the — at the time a ship is constructed, an operation cum refit cycle gets established, under which the maintenance routines for the ships are determined; and at fixed intervals, a ship goes, say, every 2 years for a short refit and drydocking to inspect the underwater package and so forth; and every 5 years a ship goes in for a major refit; now, to carry out these refits and repairs, the Indian Navy has a Naval Repair Organization; but given the range and scale of the ships the Navy handles, the yards or repair yards, Naval Repair Organizations <<inaudible>>, face capacity constraints. When such capacity constraints arise, they outsource these refits to capable shipyards; now the Coast Guard, on the other side, doesn't have a similar repair setup or infrastructure like the Indian Navy. What I mean to say is that each Indian Coast Guard ship goes for refit and repairs to outside shipyards and private firms. So — and similar to perhaps these refits and repairs come up for a short duration, every 2 years, and for a longer duration, every 5 to 6 years. So the opportunities available here — on this front, both with the Navy facing capacity constraints and with the Coast Guard presently lacking any captive repair organization, are huge. It is precisely with this intent that we have entered this ship repair segment in a fairly aggressive manner; and for this, as I've said, we have taken over 3 drydocks in the Kolkata Port Trust; and we have already completed 5 projects for Indian Coast Guard, including 2 major refits and 3 minor refits over the last 1 to 1.5 years; we are — right now, as of today as well, we are carrying out a project for the Indian Coast Guard refit; and we have 1 more ship arriving for refit in the next year. So to answer your question, yes, both the Indian Navy and the Indian Coast Guard follow a methodology in which maintenance is performed periodically. And as a business entity, we have a huge opportunity in this segment.
Venkatesh Subramanian
analystYes. So really, most of what I asked has already been covered, but let me just quickly confirm again; so FY '23, '24, '25 are the peak years for the execution. Is that correct, sir? Just confirming once more.
P. Hari
executiveFY '23, '24, '25 and now I'll also add FY '26 to that, in the sense that the peak might be reached during FY '25 or '26 given our delivery schedule and with the order book that is planned for execution by FY '27; so if you look at '23, '24, '25, what I can assure you is that revenue growth will be upward, on a steady upward trajectory, with either '25 or '26 being the peak years.
Sumit Chandwani
analystYes. So sir, since the majority of these are fixed contracts — fixed price contracts — in what way do you safeguard your margins? Could you give us some sense of how you protect your margins, and these are projects of 3, 4 years?
P. Hari
executiveOkay. Thank you, Sumit, quite an interesting question. Now there was an era much before we were listed and well maybe 10 years back, when the shipyards were having contracts that were cost-plus contracts, then came an era of nomination contracts; and now we are at a very, very interesting phase where we have all the contracts on competitive bidding phase; and let me give you confidence and assurance that the transformation of the shipyard from, first, the cost-plus era to the nomination, of course, it was tough. And from nomination to fixed cost and competitive has been successful and smooth. So how do we keep our margin? Since we're pursuing competitive bidding alongside our peers, the other shipyards, the bids are naturally very competitive and margins <<inaudible>>. So what's our approach to preserving the margin? Look, over a period of time, we've revamped all of our production processes; we've introduced automation. You may appreciate that shipbuilding, unlike any other manufacturing industry, is labor intensive; but even in this segment, we've introduced measures to automize areas where automation is practically feasible; we've reduced our revenue expenditure by rationalizing a large amount of <<inaudible>>; and as a business strategy, our focus is that noncore activities are outsourced. Our captive workforce is retained solely for core functions—specifically, core production and shipbuilding. Through these steps, we've managed to hold margins at the level we're targeting.
Sumit Chandwani
analystSir, my question focuses more on the costs of equipment and materials, since steel prices have swung quite a bit this year. So how are you <<inaudible>> with the part involving...
P. Hari
executiveI understand, and I'll respond to that question...
Sumit Chandwani
analystAnd in the same way, what about foreign currency risk? You've got a lot of imported equipment, so how do you hedge against that? It'd be great if you could give us some color on your procurement policies.
P. Hari
executiveOkay. I'll answer both questions. Both of them relate to procurement of equipment and systems. Now, in a shipbuilding project, as you may be aware by now, equipment and systems account for nearly 60% to 65% of the project cost, and all these projects are fixed-price contract projects. And these projects, both P-17 Alpha and the Survey Vessel — I'm only thinking about the major key projects, which contribute the majority of — major chunks of our order book. All these contracts were concluded before the financial year 2019. These are fixed-price contracts, and since these contracts were concluded before FY '19, all our equipment orders have been placed well in advance, which means well before the market fluctuations started, first because of covid and because of the current situation. So just as we have fixed-price contracts from our customers, all our contracts with our equipment manufacturers and the major contractors are on a fixed cost base. So what I'm trying to convey is that there's no impact with respect to price fluctuation. Now a small component that isn't the equipment, isn't the major systems, but the yard material — we call that yard material, which mostly comprises steel and certain fasteners and insulation and so on — that makes up only a very minuscule scale of the overall project. Even within the steel, we have an understanding, a memorandum of understanding with another PSU, that is the Steel Authority of India, where a decent amount of protection exists against the variation. Coming to the balance material, which comes to, if you're looking at the overall project cost, around 5%, that is the yard material less steel. Yes, there have been fluctuations that have had an impact because many of these are supplied by MSME vendors, but — and there have been escalations; but if you're looking at it from the overall perspective, the impact is minimal. Coming to the ERV, the projects, the key projects, that is P-17 Alpha and the Survey Vessel project, they're protected against the ERV because an ERV variation clause exists in the contract with the customer. So there's no impact with respect to the value of these projects.
Prabir Adhikary
analystI have a few questions. First, sir, I'd like to get some clarity on these shipbuilding phases. You mentioned that it begins with plate cutting and runs through to the delivery stages. Since most of the equipment consists of bought-out components, could you give us a sense of what the gross margins should look like at each of the different phases?
P. Hari
executiveWould you mind repeating that question one more time?
Prabir Adhikary
analystYes — what I mean is that building a ship normally proceeds in stages, from plate cutting all the way through to delivery, and the majority of equipment fitted on board is bought-out items. So that has to mean your gross margin moves around as well; could you therefore clarify what sort of gross margin comes up in each of those stages?
P. Hari
executiveLook, at present we are running several projects — several projects, as I just said in my <<inaudible>> I noted that we are constructing 15 ships for the Indian Navy itself, and every one of those vessels sits at a different point of construction. Taken holistically, in shipbuilding the conservative optimal profit margin sits at roughly 7% to 7.5%. To give you still more insight into the shipbuilding cycle, as you correctly put it, ahead of plate cutting — of course, I would add one more phase, in which preparatory activities are carried out — comes plate cutting, then the block stage, meaning panel fabrication, block fabrication and block assembly, which takes place in the dry dock. Equipment that has been ordered begins arriving across these phases, is lowered onboard, then integration begins, followed by the launch, then outfitting, final outfitting, and the trials and acceptance. Now, if you take a shipyard, when we examine gross margins, you should view it holistically, yard to shipyard. I currently have 7 projects under execution, shipbuilding projects. Each of them is at a different production stage. Certain ships are at the final stage. Certain ships are at the preparatory phase. So once again, as I said, the margin — the overall margin per shipbuilding project sits at around 7% to 7.5%; now the question of how we push past that 7% to 7.5% is where the difficulty lies. That is where, in answer to your earlier question, I noted that we have adopted a series of measures, from automation to the extent feasible, manpower rationalization, resources utilization, moving to PPP, outsourcing, and through that we have managed to keep margins above.
Prabir Adhikary
analystSo is my understanding correct that the 7% EBITDA margin for the current quarter could rise to somewhere around 12% to 13%...
P. Hari
executiveLet me address that. For the current quarter, the EBITDA margin stands at 12.16%, not 7%, and for the half year ended 30 September our PAT margin itself is 8.11%. So I'm referring to the PAT margin. The PAT margin itself is plus 8%. As for the EBITDA margin, and to also answer a previous question, I did mention that our EBITDA margins have been hovering between 12.5% to rather 12% to 13%. And we will be able to maintain this in the coming days and years.
Vignesh Iyer
analystI just wanted to ask about something — on our balance sheet, right, we have a fairly substantial sum sitting there as an advance tied to project execution, correct? So my request would be that you present the amount received as an advance separately from the cash and cash equivalents that we're actually generating from our internal approval, because it's somewhat misleading — we can't use all of that cash since it's essentially an advance from customers, from your clients, right? So we'd like — to work out free cash flow in a better way, right, and to determine the closing free cash flow, cash and cash equivalents. It would be better if the advance from the customer and the amount you hold in your account, which you're free to use, were shown separately.
Ramesh Dash
executiveYes; this is Director of Finance, R.K. Dash. First of all, what I want to say is that the money we are showing is not an advance, because in shipbuilding projects, wherever we have submitted our report, we have not taken...
Ramesh Dash
executiveYes. Can you hear me now?
Ramesh Dash
executiveSo here's the thing — we have no financing cost at all, since our contract is structured so that the customer funds our working capital. That means each time we reach a particular stage of completion, or hit a particular milestone, we receive money at that point. So first, I want to make clear, this is not an advance. The second point I want to make is that whatever balance sheet we're looking at, our line items, it isn't up to us how to present them. You know that it's already in line with whatever is prescribed under the company act. That's how we present our items. So in this case, whatever money we receive, it comes into our account. The cash I'm showing is my cash as well as the customer's cash. I don't have a separate bank account to keep — to show my accruals and the customer's separately. It can be worked out from the balance sheet itself. A financial analyst can figure out how much is own cash and how much is also customer cash, because everything is a <<inaudible>>, we also show that advance from customers <<inaudible>> whatever money we've received. On the asset side too, utilization <<inaudible>> also inventory, that we're also showing; so there's no room to show our own money and the customer's money separately.
P. Hari
executiveAlright, I want to say again that this question comes up frequently in shipbuilding projects. Under the contract as it stands, there isn’t any concept of an advance. Instead, those are all payments at different stages meant to cover the different project requirements.
Abhineet Anand
analystSir, regarding the project orders in the pipeline, you had to — first, you brought up these 11 next generation <<inaudible>>. So who was the L1 in that case, sir?
P. Hari
executiveThe L1 is <<inaudible>>. Goa shipyard is the L1.
Abhineet Anand
analystAll right. And regarding those 3 Navy orders you brought up. First, clearly the Corvette one, as you said, that RFP will probably arrive in FY '23 or early '24. So when should we anticipate that contract appearing?
P. Hari
executiveLook, that contract, based on how things stand now or what we've observed, whatever our experience from the previous RFPs and how contracts get finalized. If the RFP does come out, suppose we take a cautious timeline of the start of 2024, then the contract will be wrapped up, most likely wrapped up in the first quarter of FY '23.
Prabir Adhikary
analystI'd like to get a handle on the execution cycle for ASWC, since these vessels are on the smaller side and order sales come to roughly INR 700 crores to INR 800 crores. Also, the launch date fell somewhere around '22 to '23, if I'm not mistaken. So, if my understanding is right, is it true that you're able to execute — given work has already begun and there's a launch date — that you can deliver all 5 ships by 2024 or 2025?
P. Hari
executiveOkay. As you correctly pointed out, these ships are smaller in size. However, they're complex vessels, since they're pure weapon platforms. So even with a smaller shipping size, when weapon intensity is high, the complexity of shipbuilding is just as high. Now, turning to these 8 ships, we plan to launch the first ship. That ship has already reached the launch stage. The first ship is set to be launched next month. In other words, we're as close as 1 month away from launching the first ship. Under the execution plan, this project is scheduled for completion. For the 8 ships, delivery is planned to be finished by end of 2026.
P. Hari
executiveThank you, Yashashri. Before I move into my closing remarks, there is one aspect I want to bring to investors' attention. We've had some very interesting questions today, and a few of them centered on margins. While we have made plans to address all of those questions, what I want to emphasize and restate is that our revenues have risen and our net worth has risen. In fact, our net worth has increased to INR 1,360 crores from INR 1,257 crores at the end of last year. Our earnings per share has risen. <<inaudible>> investment has risen. Market capitalization, another interesting point, has risen by 400%. While this shows the confidence investors place in the shipyard, what I want to restate is that we are fully aware of your expectations and every effort will be made to meet them. With that, let me thank Yashashri once again, and thank you, Gaurav from Concert IR, for organizing this conference call. I want to express my sincere gratitude to all my analysts and investor friends who have taken time from their busy schedules to listen to us today. Should you have any further questions, I would ask all of you to please reach out to us, and we will be glad to address them all. Thank you once again. Jai Hind.
Operator
operatorThank you, sir. That brings this conference to a close on behalf of Garden Reach Shipbuilders & Engineers Limited. We appreciate your participation, and you are welcome to disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Garden Reach Shipbuilders & Engineers Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Garden Reach Shipbuilders & Engineers Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Garden Reach Shipbuilders & Engineers Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.