P. Hari

executive
#1

Good afternoon, everyone. Can those of you at the back hear me? All right, thanks. It's been close to 1 year since we last met. I saw most of you roughly an year ago, and here's something interesting: I've just arrived from Kolkata, and the contrast in traffic between Kolkata and Mumbai is striking. There, vehicles do move, though at a snail's pace. Here, they simply don't move at all. I was putting up at the MDL Guest House, and reaching this venue took me nearly half an hour. Apologies if I've kept you waiting, in case you've been here for a while. Good day, everyone, and thank you for joining this call. Today we'll go over GRSE's results for the quarter and the nine months that concluded on 31st December 2023. I'm confident that many of you have tracked how the company has been doing for quite a long while and have kept in touch with us—perhaps through face-to-face meetings like the one we held last year, or via the quarterly virtual sessions. Here's how I plan to proceed: I'll give you an overview of the company's financial results, then the operational performance that produced those numbers, followed by the current position of our order book, our approach to executing the orders we hold, and what the future holds for all of us. That's the sequence I'll be following today. Before I go further, let me note that this is the seventh quarter in a row where our financial metrics have headed higher. And again, for the quarter that closed on 31st December 2023, together with the nine-month period ending on that same date, we've delivered the strongest results the company has ever recorded. Revenue from operations across the nine-month period came to INR 2,576 crores, up by nearly 31% compared with the matching nine months of FY '23. Total income grew along similar lines, rising 34%. EBITDA stood at INR 367 crores, a gain of 41%. PAT went up 42%, reaching INR 245 crores. Put simply, from our perspective, the company's financial performance has been solid. So what is it that has driven this performance? By December 31st, the order book we currently hold is valued at INR 23,592 crores. Shipbuilding accounts for the largest share, while ship repairs and our other verticals—portable steel bridges among them—contribute a limited portion. Within that INR 23,592 crores backlog are 4 projects underway for the Indian Navy: the 3-ship P-17 Alpha project, the 4-ship Survey Vessel (Large) project, the 8-ship Anti-Submarine Shallow Water Craft project, and the 4-ship Next-Generation Oceangoing Patrol Vessel project. Turning to the past year, we handed over 2 platforms. The first was the initial unit among the 4 Survey Vessel (Large) ships being built for the Indian Navy, and that delivery took place in the most recent quarter. The handover happened on December 4, 2023. For the record, let me repeat that this ship ranks as the largest survey vessel ever built in our nation; it was commissioned afterward in February — only last month it began serving with the India Navy; in addition, we delivered an oceangoing passenger-cum-cargo vessel to the Government of Guyana. Delivery and commissioning of that ship took place on April 23, 2023. Those are the 2 platforms we have delivered. On top of that, in shipbuilding last year — as I mentioned in our early conversations — launching a vessel marks a major milestone: when enough physical progress has been made and the ship reaches its full form, it goes into the water, and outfitting follows. So I'd describe last year as the year of launches. Over the past nine months we launched 7 platforms, among them the final P-17 Alpha vessel. That ship went into the water on 17th of August 2023, with the Honorable President of India doing the honors. I'll briefly walk you through where each of the ongoing projects stands, so you have a clear picture of our position on every one of them. Starting with P-17 Alpha, that's a three-ship project. Physical progress on the first ship is currently at roughly 66 percentage. The second P-17 Alpha ship sits at 55%. As for the third ship — the one I just noted was launched on 17th of August — it's at about 43 percentage of physical progress right now. On delivery, here's the plan for this ship: the first ship is intended for delivery during mid of 2025, meaning August '25 is the target date for handing over the first ship. The next vessel is due in February 2026, and the one after that by August '26. That's the schedule for delivering these ships, and at the moment we're on track. Moving on to the Survey Vessel (Large) program: as I noted, the first vessel was handed over last year. The second, third, and fourth vessels are now being prepared for delivery, and the first among those three is already in the harbor trial space. We plan to send that vessel out for sea trials next month. My estimate for handing over that ship would be May or June of this year. Following that, in December, we'll deliver the second of the remaining three vessels. The final vessel is scheduled for early next year—the first half of 2025. There's a chance it slips into the start of Q1 of FY '26, so we're looking at delivering around April or May 2025. Now, on the Anti-Submarine Shallow Water Craft project, for your information, this is an 8-ship program we're carrying out. Yesterday we launched the fifth and sixth ships of this project—those two vessels went into the water yesterday. Of the four ships launched previously, the first one is currently going through harbor trials, much like the survey vessel I mentioned, and we expect to hand that ship over by June this year. Following that, one vessel from this program will be delivered every six months. We therefore expect to complete the Anti-Submarine Shallow Water Craft project around mid-2026. Regarding physical progress, the first ship is at about 77%, the second roughly 62%, and the third is nearly the same at 62%. The eighth and last vessel stands at approximately 20% physical progress. Our next endeavor—the fourth project—is the Next-Generation Oceangoing Patrol Vessel, which involves four ships. The contract for it was signed on March 30, 2023. We have achieved solid headway on this project; and all the—we have begun production on all 4 ships, and for all 4 of them we have in fact adopted a strategy of building them concurrently rather than sequentially. All 4 ships are presently at roughly 10% of physical progress. Completion of this project is expected by FY '28.

P. Hari

executive
#2

What I'm getting at is that these vessels will start being delivered in 2026, then every 6 months after that, continuing until early '28. Beyond these 4 projects we're doing for the Navy, we're also carrying out a project for the Government of West Bengal, and that one is a fully electric vessel. Once handed over, it will be the biggest in passenger capacity ever built in India. The vessel has already been launched and is presently going through river trials. We plan to deliver this vessel to the Government of West Bengal next month, which is April, we will be delivering this vessel. To clarify where things stand, among the companies building green vessels — that's the term we use — Cochin Shipyard is one of them. They're somewhat ahead of us right now, but with this delivery we feel very confident about closing that gap and even moving past them, since this segment offers solid market potential. In addition, we've been named L1 for an oceanographic research vessel for the Ministry of Earth Sciences — an order worth roughly INR 840 crore. The LOA has already been issued, and we expect to sign the contract during March itself. We've also been declared L1 for an autonomous platform for the Ministry of Defense, DRDO. Although this order is modest, I want to point it out because anything being developed today in the autonomous platforms space carries market potential. It's a very small, very low-value order—roughly INR 20 crores. For them, it serves only as a technology demonstrator, yet the opportunities here are abundant, since both the Navy and the Coast Guard are seeking autonomous platforms going forward; we are also moving into the other segments. Exports have been one of our focus areas. As you're aware, back in 2014 we delivered two defense platforms to the Government of Mauritius, and more recently in 2021, another platform went to Seychelles. Through a global tender, we've once again been declared L1 for a dredger for the Government of Bangladesh. That's still in liquid form — the contract hasn't been signed yet. The L1 declaration has taken place. Given their recent government change, we expect the contract to be signed within another 3 months. We've also been declared L1, again for the Government of Bangladesh, through a defense line of credit for a tug — an oceangoing tug. Each of those two orders might land somewhere in the INR 150 crore to INR 200 crore range. The reason I bring this up is that while the amount isn't large, these are export deals. On exports, we've concentrated first on defense, second on the IOR region—especially friendly foreign countries—and now that commercial shipbuilding demand has emerged, after we expressed our wish to get involved, quite a few Scandinavian countries plus customers from Germany have contacted us. Hopefully, when we talk again after the quarter, I'll be able to bring you the good news that we expect to have finalized some commercial shipbuilding orders by that point. Even with orders in the pipeline in those segments I mentioned, warship construction would stay our primary focus, because that's where the order value is. Let me give you just a glimpse of what's coming, and this also follows up on what I said last year. The major orders in the pipeline. First, the Indian Navy’s next-generation corvettes. We anticipate that the request for proposals will come out in June or July of this year—the RFP, that is. And our odds of securing this contract are quite strong. It’s a large-value deal; the total order value, the AP value—the AON value stands at INR 36,000 crores. The split: this is an eight-ship project shared between the L1 and L2 shipyards on a 5:3 basis, meaning five vessels go to the L1 yard while the L2 yard receives three, so the stakes are high here. Four shipyards have been shortlisted for this. We stand a good chance of winning it. We're going to bid aggressively for this order since it falls within one of our areas of specialization. I'd like to state for the record that every corvette currently in service with the Indian Navy was built by GRSE — that reflects the kind of expertise and experience we bring to corvette construction. The next project coming up would be the next-generation survey vessels. That project involves 5 ships. On approximate order value — the government has already issued an AON. The approximate order value would be about INR 3,000 crores, and this RFP is expected to come out during the second quarter of the current financial year. Because the AON has already been granted, and this work is simply a follow-on to ships we're already building, our understanding is that the RFP won't be delayed. Once again, we definitely stand a strong chance here, since we're currently building Survey Vessels (Large). The next RFP that will probably be issued covers 2 multipurpose vessels. That one is also for the Indian Navy. Its order value could be roughly INR 1,200 crores. Beyond that, there's another project in the pipeline that we're bidding on aggressively and pursuing aggressively — the P17 Bravo project. The Navy needs 7 additional vessels of this kind. Right now, we can't say for certain when the Navy might move, since the AON for this hasn't been taken yet. Our sense is that it could happen early next year, meaning early '25. The landing platform dock, or LPDs, is another project with high value. This one has been in the works for almost 10 years now. We're also hopeful that it will finally move forward. But given the size of the value, the order value is large, so even if the Navy opts for 2 of them, the order value could come to roughly INR 40,000 crores. On top of that, the Coast Guard is going to come up; they haven't taken an AON as yet. From what we gather, an AON is expected to come their way during the first quarter of FY '25 covering 5 additional oceangoing patrol vessels. An order for 6 of these has just been placed by them with Mazagon Dock. That makes 5 more oceangoing petrol vessels, and the RFP is probably going to be issued in the first quarter of FY '25. Beyond that, here's a quick glimpse of what else is on the way: 120 fast interceptor crafts for the Indian Navy, 1 hospital ship for the Indian Navy, 22 follow-on waterjet FACs — fast attack crafts for the Indian Navy. In my view, the RFPs would only come out in early — that is, the first quarter of FY '26.

P. Hari

executive
#3

So this provides a picture of our order book—what's in hand right now plus the orders in the pipeline available in the market. You've probably seen the GRSE corporate movie by this point. It shows that we can build 20 warships at the same time. During the past three to four years, we've come to feel that this capacity needs to go up. That process is already underway. And as an initial step, before we put capital into our own infrastructure, we adopted a lease strategy. We've taken over three dry docks from our neighbors — that's Syama Prasad Mookerjee Port — and those are being put to effective use and set aside for ship repairs. Beyond that, we're looking at one additional dry dock from Kolkata Port, which is Syama Prasad Mookerjee Port, and we'd like to designate it for shipbuilding. On top of that, two facilities at GRSE, within our captive setup, are undergoing refurbishment. The goal here is to raise our shipbuilding capacity from building 20 warships at the same time to 24 warships, and we plan to hit that target by calendar year 2025. New technology adoption has been one of our key focus areas. As I noted, the government is concentrating on developing autonomous platforms—surface, subsurface, and of course aerial—and the Armed Forces are doing the same. We've already begun, and across those three areas—autonomous platforms—we're working with start-ups, and two of our products have already been launched successfully: an unmanned surface vessel and an underwater surface platform. For that underwater surface platform, we conducted user trials with the Indian Army. They asked for some modifications, which are currently being made; and we plan to productionalize this underwater platform by the end of this calendar year. On the surface platform side, we already hold a developmental order from DRDO, and we plan to finish it by April — that's next month, the coming month. On commercial shipbuilding, as I said earlier, I'll now give you a sense of where we stand. We're serious about commercial shipbuilding. Many negotiations are at final stages, and our assessment is that within three months we'll be closing contracts for it. Ship repairs is another area we began concentrating on only about two years ago. So with that goal in mind—development, shipbuilding, and ship repair—we acquired three dry docks, and they're running at nearly full capacity. Up to now, though, our work has mostly been smaller refits for the Indian Coast Guard. In fact, we handle all of the Coast Guard's requirements across the Eastern region. That said, I wouldn't claim we're a fully mature ship repair operation yet. Our target is 2025, with a few orders expected from the Indian Navy—high-value ones. There's another business line you know about: portable steel bridges. We lead the market in India in that segment. Of course, the market share—the market overall is fairly small. At present we hold roughly 65% of the market share. This division is performing well since we have an ongoing MOU with the Border Roads Organization covering more than 75 bridges, and close to 40 of those are already finished. We also fulfilled an order for the Government of Bangladesh for these bridges via DLOC, meaning the defense line of credit. And this year we launched another product in this segment. It's a Bailey bridge with a 5.3-meter carriageway, which is a proprietary item of GRSE. That should give us a head start when it comes to meeting national highway requirements — essentially, 5.3 meters is the carriage width of a highway. This should let us gain more ground in that segment. Something else that sets us apart is the breadth of what we make. Our lineup spans everything from warships to weapons. Why bring up weapons? We moved into gun production last year. The Indian Navy placed an order with us for 10 30mm Naval Surface Guns, worth roughly INR 250 crores. The Navy has since indicated it wants to raise that order value. Interest has come from the Coast Guard too. We want to grow this vertical. As I mentioned, our order book right now sits at INR 23,592 crores. We aim to keep order value in a comparable range — specifically, an order book of INR 23,000 crores to INR 25,000 crores, or more, over the years to come. So we'll pursue orders aggressively — additional orders from the Indian Navy and, naturally, from other segments too. That's all from me. I've simply provided a summary of where we are now and how we intend to proceed in the years ahead. If anyone has questions, I'm happy to take them.

Keshav Harlalka

analyst
#4

Everyone who put money into GRSE has gained enormously from that investment. This is Keshav Harlalka calling from BHH Securities. Can you hear me?

P. Hari

executive
#5

We can hear you, though your voice comes through a bit distorted.

Keshav Harlalka

analyst
#6

Okay. Is it better now?

P. Hari

executive
#7

It's better.

Keshav Harlalka

analyst
#8

Yes, sir. So you've given me — you're delivering so many warships across so many time periods; so could you give us this on a timeline, like this is the timeline this year, this quarter, these many warships will be delivered; this quarter, these many. Like it's very — in an orderly fashion? And what's the value of the warship, and what's the approximate margin? If you could give us some sense of that, it would — the entire presentation will flow better because somewhere it's '26, somewhere it's '24. So if you could give us some timeline on an Excel sheet or something or even verbally, that would be very helpful, sir.

P. Hari

executive
#9

See, I will only talk about the orders that we're currently executing. And in the financial year '25, we will be delivering 2 Survey Vessel (Large), 2 Anti-Submarine Shallow Water crafts. And...

Keshav Harlalka

analyst
#10

Roughly which quarter would that fall in — the first quarter, the second quarter, or the third quarter — and about what value would each vessel carry?

P. Hari

executive
#11

I can give you an indicative figure.

Keshav Harlalka

analyst
#12

Roughly indicative — yes, yes.

P. Hari

executive
#13

I can give an indicative figure off the top of my head. During the first quarter of FY '25, we will deliver 1 Survey Vessel (Large) plus 1 Anti-Submarine Shallow Water Craft. Now, this is quite interesting: the Navy runs project reviews on us. Every quarter, the Navy reviews all of our projects. That is precisely the question they put to us, so I attempt to provide this, and then they push back, "Give me the date. When will the ship be delivered?" So I hand them a range. Therefore I'll give you a delivery range. So in the first quarter, 1 ASW Shallow Water Craft and the survey vessel. Second quarter, nothing, since the ships haven't reached that stage yet. Third quarter, 1 Survey Vessel (Large) — that's the second among the 3 remaining. Fourth quarter, one Anti-Submarine Shallow Water Craft, meaning 2 Anti-Submarine Shallow Water Crafts and 2 survey vessels across the current financial year; beyond that, we will also deliver the next-generation electric ferry to the Government of West Bengal in the first quarter of FY '25. I doubt you'll have much interest in the small projects such as that small unmanned surface vessel and — because they are largely — they carry only academic interest and the order value is miniscule. There's also 1 order from the Government of Bangladesh for patrol boats, though the order value isn't much. It's really just about our presence there. For your interest, 2 survey vessels, 2 Anti-Submarine Shallow Water Crafts.

Keshav Harlalka

analyst
#14

And roughly what would each vessel's revenue be worth, what amount would land in the company's books?

P. Hari

executive
#15

Approximately?

Keshav Harlalka

analyst
#16

What's the approximate amount that would show up as revenue for us once we hand over the vessels? Or does it work the other way — as we build, do we bill the client for it? Does it go onto our books?

P. Hari

executive
#17

Absolutely, absolutely. The reason is that with shipbuilding, revenue gets accrued step by step as we carry out the project. Let me give you an example. That survey vessel — the one where I mentioned the order value is INR 511 crores per ship — right now that ship stands at roughly 82, 83 percentage of physical progress, which means I would already have accrued the bulk of its INR 450-odd crores, that amount would already be accrued by me. So the thing you're trying to ask about, you may not get a clear answer unless I tie it back to the physical progress. So as far as you're concerned, delivery, I mean, when it comes to revenue accrual, it makes no — let me put it a different way. I understand what it is you're trying to ask.

Keshav Harlalka

analyst
#18

Broadly speaking, what sort of revenue growth should we expect over the coming 2, 3 years?

P. Hari

executive
#19

Yeah, so I think that's — my throat would've been in better shape. Alright. Let me just gather my thoughts; in FY '22 we stood at around INR 1,756 crores. Then FY '23 took us to INR 2,561 crores. And across the 9 months of FY '24, we'd already reached INR 2,577-odd crores, so we've gone past last year's figure already. Okay. Now, being halfway into this, we ought to be crossing INR 3,000 crores within the current financial year. Now the big — the large ticket item within this INR 23,792 crores is the P-17 Alpha project. That P-17 Alpha project is worth INR 19,000 plus crores, INR 19,293-or-something crores, a INR 19,293 crores project. And there the first ship has just crossed 65%, the second ship stands at 54%, and the third ship sits at 45%. The first ship still has room before she reaches roughly 75% and delivers more revenue to the company. The second and third ships are really hitting, about to hit their peak now, and given that situation, for the moment I'm just leaving aside the <<inaudible>> project, that is ASW and the survey vessel. With P-17 Alpha alone, backed by the other 2 projects, we should be delivering revenue growth of plus 25%, around 20%, 25% at minimum over the next 3 years.

Keshav Harlalka

analyst
#20

So roughly INR 3,800 crores to INR 4,000 crores by FY '24, '25, and let's say INR 5,000 crores by FY '25, '26?

P. Hari

executive
#21

At least 1 year — you see, in my initial remarks, I had said that the current order book, leaving aside what may yet come, since that is for anyone to guess. The current order book will be completed by FY '28.

Keshav Harlalka

analyst
#22

So your guidance is for a 25% CAGR over the next 4 years, broadly speaking, sir? Could you take a look at that?

P. Hari

executive
#23

The next 2 years.

Keshav Harlalka

analyst
#24

Next 2 years?

P. Hari

executive
#25

Next 2.

Keshav Harlalka

analyst
#26

Over the coming 2 years, we expect growth of roughly 25% CAGR, generally speaking.

P. Hari

executive
#27

Usually, this sort of question comes up a bit further along. And the following question, at some point it'll be about margins. All right.

Rohit Natarajan

analyst
#28

This is Rohit Natarajan calling from Antics Stockbroking, and my first question is this: the awarding from Navy was somewhat low this year. The next-generation corvette, I believe, has been around for a while now. We have been discussing it. Yet the awarding appears to be moving rather slowly. What is the exact reason for that?

P. Hari

executive
#29

Look, in 2020 the government revised the Defense Procurement Policy, DPP. Under that policy, between the issuance of an AON and the issuing of the RFP — from when the AON is obtained until the RFP comes out — there is a 30-month slack, a 30-month period. Now, we have been pressing Navy. Navy has been pressing itself. The Ministry has been pressing Navy. So, taking all of that together, at present — we are tracking that particular project very closely, and our assessment, as I mentioned, is that the RFP will probably come out in June or July this year. Does that answer your question?

Rohit Natarajan

analyst
#30

Yes.

P. Hari

executive
#31

Officially speaking, they're comfortably inside the timeline, since June and July will bring it to roughly 26 months, 26 or 27 months. They're comfortably within that timeline. But the ships are what they need. Orders are something we need as well. So they're putting pressure on themselves. That case is moving along a fast track. The Statement of Technical Requirements is ready. Now it's just the process, and at this point we're at the end of March. So my expectation is roughly 3 more months. June, July, it might come out.

Rohit Natarajan

analyst
#32

The reason I'm asking you this is that the other 2 major shipyards are now eager to look into smaller-ticket orders too. It appears there's been some kind of slowdown in order inflows, and at this point they're considering low-value platforms as well.

P. Hari

executive
#33

Look — there are 5 to 6 of us, 4 different shipyards, Cochin Shipyard and L&T. At the moment, every one of us holds a reasonable quantity of orders. So that kind of desperation hasn't set in yet. And for projects such as the next-generation corvettes, the Navy carries out a capacity assessment, and eligible shipyards get determined based on certain conditions. So I believe I said earlier that for the NGC, only 4 players will be in the market — I mean, in the game. So we don't — 4 shipyards, and on top of that the order is being split between 2. I think even if you apply simple probability factors, we have a very good chance.

Rohit Natarajan

analyst
#34

Understood, sir. Sir, my next question is this: you mentioned increasing capacity to 24 vessels by FY '25, and right now you're able to handle platforms of roughly 20 vessels at this point. But you also said something toward your closing remarks — you said you want to keep your order backlog at INR 240 billion, INR 235 billion. Yet you're adding capacity as well, so do you think that's somewhat a conservative signal you're putting out? Would you like to build a bigger order backlog? I mean, do you want to grow much higher than where you are now? Is that the kind of thing you have in mind?

P. Hari

executive
#35

Let me explain. In shipbuilding, the key assets are the dry docks and building berths where a ship's initial construction takes place, and there the occupancy period is long. That's known as the prelaunch phase. After it's done, the ships come out and move to the jetties and berths where outfitting takes place. Our purpose in raising capacity: first, we should never be found short if additional orders arrive; second, we won't let this capacity — this enhanced capacity — sit idle, because the way we see it, I stated with confidence that we will receive commercial shipbuilding orders. And that's one area where we simply cannot afford to miss a date; so we didn't want to end up in a situation where we have orders but no capacity to execute them. Third, even back when our capacity was 20 ships, at that time too, to enable concurrent construction, we had entered into a partnership with private shipyards. And it's a highly successful partnership. I mean — it's all open-source information, nothing confidential about it. We partnered with a major Indian private shipyard, 3 of our ships for part construction, very effective. All the ships are back at GRSE premises right now being readied. So capacity is not a constraint. Why the enhancement? It's to cater to more and more load. Now to the figure you mentioned. I myself said that our intent at this moment is to — I use the phrase at this moment because the — let's take the NGC project, which is a big ticket — the first big ticket item that is going to come from the Navy. The order would come, again, on a conservative note — it will come only by mid of 2025. From mid of 2025, for revenue to start coming in, it will be end of '26, because in the initial period, not much revenue comes in. The proprietary design work alone, along with placing orders for equipment and everything else—that's why I said I'd like to, we'd like to keep things as they are—once that comes through, and if you get, say, let's imagine you land the P17 Bravo, then the whole picture shifts. Let's hope that happens.

Rohit Natarajan

analyst
#36

Understood. Sir, my last question concerns why you steered clear of the next-generation destroyer in your target market. Is a destroyer beyond your capacity, so to speak, to take on? Is GRSE genuinely considering destroyers, or perhaps such advanced vessels are on the table?

P. Hari

executive
#37

Under today's scheme of things, what used to be termed a corvette — because I've served aboard corvettes and I've now also built them. What was called — let me just build up to what you're getting at. So what used to be called a corvette was only about 70 meters in length with a displacement of only about 1,000 tonnes; and the last project we finished, the anti-submarine shallow water craft — anti-submarine corvette, it's roughly 110 meters long. That too is called a corvette. Now coming to the frigates. We built earlier the P16 Alpha project, the Brahmaputra-class project roughly 10, 12 years ago. In terms of the weapon package, at that time, called — termed a frigate, but a conservative frigate. What we are building today, the P-17 Alpha, is the most advanced frigate, absolutely weapon intensive. So the gap between frigates and destroyers, that band of ships, is shrinking. We have full capability to construct destroyers. But at this juncture, the next-generation destroyers — at this juncture, the need is very much there, but the processing of the case for AON and those things is still in a fluid state. It is a bit away. It's a bit away, as in it could be 2 to 3 years away. And when that situation comes, we'll definitely be pitching. And we'll be one of the shipyards who would be shortlisted for this project. These are our expectations.

Ramesh Bhojwani

analyst
#38

Sir, Ramesh Bhojwani here from Mehta & Vakil. Your presentation was quite comprehensive. There are a few points I'd like clarified. First, do we possess the technology and the capability to construct and deliver stealth ships? I'm asking this from a defense standpoint.

P. Hari

executive
#39

Okay; stealth ships are already being built by us. The P-17 Alpha that we're building at present is a stealth vessel. It's known as the P-17 Alpha stealth frigate; so India as a whole, Indian shipyards as a whole, and GRSE specifically, we have the complete capability to build stealth ships.

Ramesh Bhojwani

analyst
#40

Great. And second, do we have the ability to construct submarines as well?

P. Hari

executive
#41

When it comes to submarine construction, there are 2 Indian shipyards — 2.5 to 2 Indian shipyards, namely Mazagon Dock, your neighbors right here, entirely capable, with demonstrated capability in submarine construction. Hindustan Shipyard, at present, they are engaged in submarine repairs. But the simple fact that they are able to do repairs means that, with a little augmentation, they can undertake submarine building. Larsen & Toubro Shipyard, they put substantial investment into submarine design and construction, and they have been backing the Navy for the project — the other project. So in — that is why I said 2.5. 2.5 shipyards are already there; as far as we are concerned, at this point, we are not considering submarines; we are fine with the surface ships. And the Navy is, even now, the Indian Armed Forces, certainly the Indian Coast Guard, and mainly the Navy, they are oriented toward surface platforms. And that is where we specialize. So we would like to hold on to that core strength.

Ramesh Bhojwani

analyst
#42

The reason I raised that question is that our coastline is extremely long, and the threats coming from all 3 sides have risen exponentially.

P. Hari

executive
#43

At this point, no, not submarines. Let me add one more point so we're all clear. Look, shipbuilding expertise, whether for ships or for submarines, never arrives suddenly. It takes decades upon decades of accumulated know-how. Individuals may come and go, yet the systems, the design skills, all of it stays in place. So starting submarine construction from scratch, ab initio, might not serve our business interests. Secondly, you brought up India's coastline of 7,500-odd kilometers, 7,512 kilometers. What we require more than submarines is ships, surface vessels, and anti-submarine platforms to guard those coastlines. That is where we specialize.

Ramesh Bhojwani

analyst
#44

Absolutely, that's right. That's right.

Analyst

analyst
#45

Swechha here from Whitestone Financial Advisors. You've provided a solid picture of the bid pipeline and the RFPs that will be coming out and that you plan to bid on. Could you help us get a sense of which orders you have already bid on and are now awaiting awards for, or something along those lines — perhaps some kind of number?

P. Hari

executive
#46

Look, at this point, as of today, I'm speaking as things stand right now, none of the RFPs from anyone's life that would be — we have bid on a few export projects, again, through DLOC. And a small one — that's what is available in the market right now. Not much is available right now, as of today; but 4 months, 5 months from now, the flow will begin. At that point, I can just list them off: INR 36,000 crores for the NGC, INR 3,000 crores for the next-generation survey vessels, roughly INR 1,200 crores for the multipurpose vessels; and P17 Bravo, when it arrives, 7x10, INR 70,000 crores is available — across the next year, the next 1 to 1.5 years.

Analyst

analyst
#47

Right, got it. Fine. Then for my second question, sir, it's about commercial shipbuilding. Could you provide a bit of context on the types of orders you're aiming to bid for there again? What sort of opportunity exists for us on the commercial shipbuilding side too, sir?

P. Hari

executive
#48

So your question is specifically about commercial shipbuilding...

Analyst

analyst
#49

Yeah, sure.

P. Hari

executive
#50

Regarding commercial shipbuilding, again, just for some context, China used to be a big player — it still is one — but at the moment China doesn't appear very keen on constructing smaller vessels, meaning medium and smaller ones; their attention is on far larger platforms. Korea and Japan are the same way. So the majority of European clients are turning to either India or Turkey. India has thus turned into a destination since they're aware production costs will be considerably lower there. And building warships is something India has done traditionally. The capability and quality are there. Now, regarding your specific point: clients in the Netherlands and Germany have shown very strong interest. That's why I asked for a bit of patience—give us another three months and we'll report back on what we've secured. The thing is, I could share the figures, but most of these deals are in the final negotiation stages, so even an indicative number wouldn't really be useful to you. I mention this simply to give you confidence that we're active in this area and feel very confident about winning orders.

Analyst

analyst
#51

All right. And would it be reasonable to expect that the margins on commercial shipbuilding would clearly be greater than the margins we have now?

P. Hari

executive
#52

Yes, they will be greater, though we would prefer to begin in a modest way. The reason is that, unlike — we don't need to demonstrate anything to the Indian Armed Forces, since they have known us for the past 64 years; but when it comes to commercial shipbuilding, we must demonstrate our own worth. What we have delivered up to now is a passenger cum cargo vessel to Guyana along with a few such projects; so we will begin in a modest way; we won't be overly aggressive when it comes to securing margins. The aim is to demonstrate our capability, so that they build confidence and we obtain more and more work; that is the intention.

Amit Anwani

analyst
#53

This is Amit Anwani from PL Capital. I wanted to ask about the order book. You mentioned that the present order book stands at roughly INR 23,000 crores, INR 25,000 crores, and that we'd want to keep it at a comparable level across the coming 3, 4 years. The existing book will be completed within the next 4 years, so that implies we are building in total order intake of INR 23,000 crores to INR 25,000 crores combined across those 4 years. The pipeline you pointed to seems fairly strong, including the INR 36,000 crores next-gen project, plus the next-gen vessel project and P-17 Bravo. So altogether the pipeline appears to exceed INR 60,000 crores, INR 70,000 crores. So is our order intake guidance on the conservative side? That's my first question.

P. Hari

executive
#54

Okay. As things stand, it is approximately INR 23,792 crores. Given how our revenue is expanding, across the coming 2 to 3 years, if no fresh orders come in, that will get used up. What we see as the first major order at present would be the Next-Generation Corvettes. That INR 36,000 crores covers 8 ships, and it will be divided across 2 shipyards. So let's suppose for a moment that we end up as L1, in which case our order value would be roughly INR 22,500 crores. Turning to P-17 Bravo. P-17 Bravo is somewhat further off. Somewhat further off, perhaps an additional year beyond the NGC. That one is a 7-ship project, again to be constructed by 2 shipyards — divided across 2 shipyards. The total order book value, if you take 10,000 — approximately INR 10,000 crores per ship, so INR 70,000 crores. That means the L1 shipyard would receive roughly INR 40,000 crores. There too, revenue recognition will start only another year or 1.5 year later once the project is — I mean, once the contract is signed. So I wouldn't say I'm being overly conservative. I'm simply attempting to give you a reasonably realistic assessment.

Amit Anwani

analyst
#55

Okay, sir. Moving to the next question about the areas outside shipbuilding that you pointed out, including commercial ships, ship repair and the LD, and I believe a few other areas, the autonomous ones. Could you shed some light on what order potential each of these areas might hold for us over the coming 5 years?

P. Hari

executive
#56

Look, here it's the — once again, as a country, autonomous platforms are still at a developmental stage. We've been uniquely fortunate to have secured — already secured one order with another one in the pipeline, but at least for the next 3 years, I don't see major orders coming in this segment; they would all arrive piecemeal, perhaps INR 50 crores, INR 100 crores, only to that extent. When it comes to commercial shipbuilding, though, yes, there's ample scope. Allow us a bit more time, and I'll be in a position to paint a clearer picture regarding commercial shipbuilding. Perhaps 3 months from now, we can discuss that; on the — my next vertical is portable steel bridges, and here, just to give you this, I had said that our market share stands at around 65%, with the overall market being small. We're drawing over INR 100 crores to INR 120 crores from this segment by itself. I mean, these are small, small items that accumulate. Ship repairs. At present, it's only about INR 100-odd crores, 70 — sorry, INR 85 crores to INR 100 crores. Potential exists here, but we haven't yet managed to break into the Navy. As soon as we break into the Navy, which we will during the current year, and if not the current year, then the next financial year, that is the current calendar year, revenue there will rise. Perhaps once again, our target — the internal target is that by 2025, at least INR 200 crores, INR 250 crores should come from ship repairs. Moving to the fourth or fifth vertical, namely Naval guns. A very, very interesting segment, with almost a monopoly in that particular type of guns; we've already secured the first break. We're capitalizing on it. Ample opportunity exists there. We began with INR 250 crores for a project spanning 1.5 years. More and more is coming into this segment. Another area, which I haven't touched upon previously, is that we also have a planned production facility at Ranchi, the diesel engine plant at Ranchi. We had a license agreement with MT Rolls-Royce, Germany for assembly and testing of diesel engines, and the revenue accrual was miniscule. But now we've moved to the next level. That is co-production of engines. And why is this attractive? It will again take time for it to fructify. At this point, the license agreement is signed already. Turning that into an actual order will require another 3 years, since the engines to be coproduced by Rolls-Royce and GRSE are intended for installation in Indian Naval ships — the smaller vessels, meaning the fast patrol vessels or the water-jet FACs. So roughly 2 to 3 years from now, orders will begin coming in for us in that segment as well. A further area: we have likewise moved into developing green vessels, a green platform. This is a space where, as I said a moment ago — sure, there are quite small players building boats, but at present only Cochin Shipyard and GRSE are in it. Should the government take decarbonization seriously and go green across all our ports and inland waterways, the sky is the limit. So on this I can offer only a general statement, because all of it remains at the developmental stage. I am referring to green vessels and autonomous too; the other items are clear.

Amit Anwani

analyst
#57

One final question about the imported portion across each of the platforms you're currently running. And are there any constraints around raw material supply, or any components you might encounter or are already encountering right now?

P. Hari

executive
#58

Look, an impact did occur. It did occur, though this happened during — initially, it stemmed from the COVID situation. Supply chains broadly were definitely affected. Regarding import content, frankly, not a great deal from COVID; after that the Ukraine situation arrived. A lot of these — our items arrive by sea, so the effect was minimal. The reason it stayed minimal is that most of our items had already arrived prior to that. Next, prices rose. Fortunately, every order for the projects already underway, every one, I'll say it again, every order for existing projects had been placed beforehand; they are all fixed price orders with our OEMs. So no price impact has arisen; so to sum up, yes, an impact occurred, a marginal one on overall project timelines, though not a significant one.

Amit Anwani

analyst
#59

Sir, there are two kinds of contracts in general: nomination and bidding. With a nomination, my understanding is that we receive a fixed margin, and P-17 Alpha falls into that category. So the margins—I think that's the one question that hasn't been addressed. The next order of INR 36,000 crores, which is out there, will be on a bidding basis; it's a nomination. And how do the margins differ between the two?

P. Hari

executive
#60

I was speaking at a forum recently that effectively included the Indian defense manufacturing industry, so my starting point was this: the shift away from the cost plus and nomination era toward fixed cost and a competitive era took nearly a year—a decade ago—and we're comfortable with that. To answer your question, yes, P-17 Alpha we've got as a nomination, 2 shipyards. Every other project has been won through competition. The Next-Generation Corvettes project is on competition.

Amit Anwani

analyst
#61

Sir, that nomination leaves us with a margin of about 7.5%, so whenever we bid, what kind of range might those margins fall into? Could you put a number on it? My future order book pattern is one matter. Understanding how the margin shifts also matters to us, so?

P. Hari

executive
#62

Look, let's say — I'll take just 2 projects so you get the picture, 2 projects awarded through competitive bidding. There will be a waterjet FAC project covering 22 waterjets FACs for Navy. Roughly, I believe, 5 plus 2, that's 7 shipyards are involved. For the Next-Generation Corvettes, 4 shipyards. Our approach to bidding will differ entirely between the two. For instance, if at that moment we aim to win the contract, the waterjet FAC, I'll accept very thin margins and then concentrate on efficiency, concurrent construction, and so on and so forth; whereas with NGC, my approach will be altogether different since only 4 players exist. And in many areas I don't need to put in investment because capability, capacity, infrastructure, design, all of it is already with me. So in that scenario, the margins are certainly — the bid margins at the time we bid, those margins will sit on a higher scale relative to the other project. Yet the reality stays: it's competition; that's how it will be for each shipyard. At least, that is, for the shipbuilding industry.

Amit Anwani

analyst
#63

Sir, just one more question. The company has recently raised its authorized share capital, correct? So what exactly are we looking at, I mean?

P. Hari

executive
#64

Look, at this point, all I can say is that this is a government — a DIPAM directive. As things develop, we'll give you more clarity on it. Right now, all I can say is that this is — we're a government company, this is a directive from the government, coming through DIPAM, and we'll offer further clarity as it evolves, perhaps in the next interaction.

Amit Anwani

analyst
#65

All right. Sir, allow me to add one more point, if I may, and this is more of — well, we have — a good number of us in this room hold shares in the company in addition to being investors. We've been keeping our stake in the company for quite a lot of years now, perhaps 3, 4, back in pre-COVID days. We've watched the journey unfold and the whole quarter-on-quarter climb that we had imagined is in fact being delivered. Once more, looking ahead, we see that INR 23,000 crores order coming to fruition across the coming 4 years. So purely as a rough rule of thumb, I'm not attempting to nail down exact figures or anything like that. We are simply using as a benchmark that this year, should we do INR 3,000 crores, we do INR 4,000 crores revenue, INR 5,000 crores, INR 6,000 crores, INR 7,000 crores, that's a wider track along which, thematically, our thinking runs. Is our thinking more or less pointed in the right direction, or are we expecting too much, or is it just a ballpark?

P. Hari

executive
#66

Were I seated in your chair, I would be entirely in agreement with you.

Amit Anwani

analyst
#67

Sir, we are — yes, we're on the opposite side. So I just want to get a...

P. Hari

executive
#68

Sir is saying something, that is...

Amit Anwani

analyst
#69

Sir, what's your view on this? If you work out the simple math, 4, 5, 6, and 7 add up to 22,000.

P. Hari

executive
#70

Sir, the math and the logic line up with each other. They agree.

Amit Anwani

analyst
#71

All right. And sir, approximately...

P. Hari

executive
#72

Sir, unless — let me phrase it this way, barring anything unexpected occurring, should this whole matter fall apart or, say, another conflict breaks out or something disastrous takes place, we remain on course regarding what he was referring to.

Amit Anwani

analyst
#73

Sir, I have just one question. Over the next 2, 3 years, do we have the capacity to reach INR 10,000 crores per year in — after '28?

P. Hari

executive
#74

Honestly, that is the intent, sir; but then again, it is not a — I can say with confidence — I mean, I can say with comfort since this is open-source information. As of today — today, we are a Miniratna Category I Schedule B company. We want to become a Navratna company, and for me to — for us to become a Navratna company, what you are mentioning is precisely what we are looking for. When it comes to capacity, there is no constraint. On capacity, absolutely no constraint.

Amit Anwani

analyst
#75

And sir, when it comes to increasing the authorized capital, I believe there must be some reasoning behind why you need to raise it — DIPAM has instructed you to raise the capital, but...

P. Hari

executive
#76

So just give us — I understand your thinking. Just give us a bit more time, let a little more clarity come through, and we will definitely brief you. Just give us 3 more months. By then, we'll know precisely where we stand. At this point, I would like to keep my answer to that.

Amit Anwani

analyst
#77

Sir, to put it another way, is there any need for capital, or for debt, or anything of that kind on your side for expansion down the road?

P. Hari

executive
#78

Not right now; we have no plans, and at this point we don't need to raise capital or take on debt.

Amit Anwani

analyst
#79

All right. Sir, the Board meeting has been moved to 21st March. Does that also come from a DIPAM instruction?

P. Hari

executive
#80

No, the reason is our own constraints, since we had a couple of cases that needed to be put before the Board. We weren't ready with them because some of the — we are executing — since you asked, I'll just tell you; we are currently executing a project for the Navy, the Next-Generation Oceangoing Patrol Vessel. Certain procurement cases, high-value procurement cases, go beyond my direct financial pass. So we had to approach the Board to get approval. Some clarifications were still pending. That's why the delay. I think now it's on 21st? 21st or 22nd?

Amit Anwani

analyst
#81

The 21st of March.

P. Hari

executive
#82

The 21st. So we're fine to proceed further. There's no other reason. This has absolutely nothing at all to do with...

Amit Anwani

analyst
#83

Sir, are you working out the bonus check?

P. Hari

executive
#84

Does anyone else have a question?

Amit Dixit

analyst
#85

This is Amit Dixit with ICICI Securities. Most of my questions have actually been answered already, so just a few remain. You spoke about what we're hearing regarding the order book and execution; and naturally, we anticipate orders for Next-Generation Corvettes and P-17B. Could there be a phase, say in FY '27 or '28, when execution falls off considerably, since we'll now wrap up at possibly 7,000, whatever figure has been mentioned. But going forward, revenue will essentially need time to build up. So do you foresee execution declining, or do you expect NGC and similar programs to contribute before that, or perhaps other avenues you've highlighted?

P. Hari

executive
#86

As I think I mentioned briefly, let me just restate it. Once the RFP is issued for the Next-Generation Corvettes, logically a year will be needed for contract conclusion, a year. Given how the Navy is progressing, it might even be 10 to 11 months. Let's assume a year; that places it around mid-2025. After that, for the actual revenue to be recognized and accrued, it will take another year, or another 1 to 1.5 years; that's when the ship will begin at 10% to 15%, 20%, whatever is at sea. So that lands us somewhere in 2027. That's when our current orders — the existing order book only. I'm not referring to commercial shipbuilding, other verticals; once the existing order book begins depleting, it will be padded up by NGC; now P-17 Alpha, P-17 Bravo trails NGC by roughly a year. So once NGC kicks off in, let's say, an aggressive manner with respect to revenue recognition, P-17 Bravo will start contributing something, and that will peak during 2029, '30. That's our present estimate. At this point, I'm not even discussing NGSV or the smaller project or waterjet FAC, only the big ticket.

Amit Dixit

analyst
#87

Understood, sir. So the second question basically concerns raising capacity from 20 ships at the same time to 24. Do you need any additional CapEx for that? Or — I mean, most of it is already finished. Could you also point out the extra CapEx for the coming 3 years?

P. Hari

executive
#88

Let me first set out some background, and then I'll address that. Look, we put in a significant CapEx infusion back in the latter part of the last decade, roughly INR 610 crores. After that, as a strategic call, we chose to spend perhaps a modest INR 40 crores to INR 50 crores annually, replacing equipment and similar items. That's the approach we've followed since. Along the way, we bought a crane costing about INR 150 crores. What we plan to do over the next 3 to 4 years is stick with the INR 50 crores to INR 60 crores approach — that is, depending on requirements, INR 50 crores to INR 60 crores each year at minimum for the next 3 years, since we have projects in hand. As for this capacity increase, I don't know whether you recall, we took over a facility from Central Inland Water Transport Corporation known as Rajabagan. It's a distinct, fully dedicated production unit. And it may well be the sole facility in India today devoted specifically to small and medium-sized warships. Now, this was a fine facility with several docks and slipways that are genuinely needed for shipbuilding, but it was in a completely dilapidated state. So what we did was develop it step by step. At this point, about 70% of it — the facilities are usable, meaning we are using them and building ships there. The reason I cited calendar year '25 for the rise to '24 is that we will rejuvenate the remaining 30%, which we are already working on. I mean working on in the sense that the refurbishment is underway; it isn't capital intensive. This will fall — fall within our overall plan of INR 50 crores to INR 60 crores each year. To answer your question, no major capital infusion is unnecessarily needed at this point for capacity enhancement.

Analyst

analyst
#89

Sir, I have one more question to ask. Sir, only a quick follow-up. So where revenue is concerned, right. So at present the order book stands at roughly INR 23,000 crore, INR 24,000-odd crores; and across 9 months, we've already recorded revenue of INR 2,600 crores; so as you said earlier, in the shipbuilding cycle, the bulk of revenue gets booked during the mid-cycle, correct? There is a peak, and after that revenue declines. Now most of the order book, the ships, I think, are already at an advanced stage. They would have gone past that line, right? So in light of this, do you believe the peak revenue from the current order book has already been booked in, during this year? Or, as you also mentioned earlier, that you would see a CAGR of 20%, 25% over the next 2 years. So is that achievable, because my sense is most of the ships would have gone past that peak revenue booking cycle, right?

P. Hari

executive
#90

Let me just take 3 projects. The fourth project, NGOPV, is still at a nascent stage. It has only reached about 10%, with hardly any revenue recognition. I'll set that aside for now. Turning to the P-17 Alpha, the first ship has reached 65%. And as I said, there is still room — sufficient room for value to be recognised on the project, up to 70% to 75%. As for the second ship, it currently stands at 65% — sorry, 54%. 54%, 55%; that is at a pace — I mean, at a stage where it is delivering for us, and that would carry on over the next 1 year. The third ship is at only 44%, 45% — 44%; and if you look at the delivery schedules as well, the first ship is slated for delivery only in August; that means perhaps July, August next year. The following ship is February 2026, and the third ship is August 2026. So I think you can be reassured that all these 3 ships are in the right phase where they will begin yielding returns for us in terms of revenue. And this will be complemented by the other ships. See this waterjet — the Anti-Submarine Shallow Water Craft Project is an 8-ship project. The first ship is at about, I think, 80% — 77% to 80%, and the last ship is at 15% construction; so they will all mature to the point where they will boost the revenue.

Analyst

analyst
#91

So am I correct in thinking that, based on the order book as it stands now, revenue will top out somewhere in FY '25 and then begin to decline? Of course, you'll have additional ships contributing. But looking at the current order book, would FY '25 be the peak revenue year?

P. Hari

executive
#92

Look, FY '25 and FY '26, because in FY '26, as I had mentioned, the P-17 Alpha deliveries are scheduled — one in February '26 and the other in August '26.

Analyst

analyst
#93

Sir, would you mind shedding some light on the landing platform dock? Who are all our competitors, and why are we somewhat hopeful about it?

P. Hari

executive
#94

The landing platform dock was initially conceived as a project of 4 ships, a high-value one. Every ship is expected to come in at around INR 18,000 to INR 20,000 crores. The shipyards that could be in the running for this are Cochin Shipyard, Larsen & Toubro, us and HSL; but once again, I would like to offer a bit of a reality check that this has been going on for the last 10 years, this project has. That is why we have not factored it into any of our projections.

Analyst

analyst
#95

So what is it, sir, that gives you hope at this point?

P. Hari

executive
#96

No, what I said was that this project has been talked about for the last 10 years; so it could happen, it might not happen, at this point we don't know, and neither does the Navy, even though they do have a requirement. You see, necessary project approval is granted on the basis of fund availability as well. So priority naturally shifts to projects such as corvettes or frigates or even the Next-Generation Destroyers, which could arrive even ahead of the LPD; that is my assessment. We shall see. What else?

Analyst

analyst
#97

Sir, just one more thing I wanted to ask. Could you shed a bit of light on what kind of export chances exist when it comes to the lower value vessels and those sorts of ships?

P. Hari

executive
#98

There are export opportunities, yes — and let me just share with you what we've already managed to achieve. By already achieved, I mean the point where we stand as L1 and are waiting for the orders, for the contract to be signed. The first one is a dredger destined for the Government of Bangladesh, and there's also an ocean-going tug being done through the LOC for the government of — these — and the order values fall somewhere between INR 150 crores and INR 200 crores.

Analyst

analyst
#99

So other than the smaller shipbuilding side? China or Japan...

P. Hari

executive
#100

No, those are small vessels. Right. When it comes to the commercial ships, what we'll be going after — just so everybody's on the same page here — is multipurpose vessels in the 80 meters to 120 meters length range, plus tankers. By tankers I mean small tankers, not the big ones, which run to roughly 100 to 120 meters in length. At this point, as ma'am asked, I said I won't be — I shouldn't give you a clearer picture than this, because we're in the middle of negotiations. Perhaps next time we meet, I'll be able to offer you better clarity. Other nations have expressed interest — some of our friendly foreign nations have shown interest in smaller platforms, meaning weapon platforms, but where defense exports are concerned, the government has a major say in that, so, for instance, if today Maldives or Sri Lanka or Mauritius or Seychelles want the ship, the routing goes through the government.

Analyst

analyst
#101

Yeah. So I've just got one question about margins. You saw it coming right at the start of your remarks. I'm just trying to see how margins will play out from here across the next 3, 4 years?

P. Hari

executive
#102

Sorry, could you say that again?

Analyst

analyst
#103

Yes. My question concerns margins, right; shipbuilding moves through stages in which the value added differs. So should we expect margins to stay steady or to rise going forward?

P. Hari

executive
#104

At this point, since most of our revenue comes from warship — shipbuilding, I'm leaving aside the other verticals because their margins are better, but they barely make up 5% — under 5% of our total revenue. We can give you margins that hold steady at what we're delivering now, no more and no less at this point, unless some policy changes occur.

Analyst

analyst
#105

I just want to clarify one thing—for the gentlemen over here, when he suggested 4, 5, 6, 7 as a probable growth trajectory for your revenue, you responded that yes, that's quite possible, and to the lady over here, you indicated that—when she asked whether peak revenue might come in '25, '26, you agreed with that too. So I'm a bit confused: which one is it?

P. Hari

executive
#106

If everyone is agreeing, then even I agree, no problem. This side, that side, and the center have all agreed. Who am I to...

Analyst

analyst
#107

I'm not agreeing here—I'm seeking a clarification. Which one is it?

P. Hari

executive
#108

It's exactly what sir referred to; that's just logic. Right now, we don't foresee any delay. I said unless—suppose India all of a sudden picks fights with everyone, or some—I mean, if some worldwide situation arises, we don't foresee any delay. So if no delay is anticipated, then the order book is this large, the percent progress is this much, the order book left over is this much; that's simply arithmetic.

Analyst

analyst
#109

Last hypothetical: 4 years out, your whole order book has been invoiced. And you're saying you plan to keep that order book within the same corridor.

P. Hari

executive
#110

For sure.

Analyst

analyst
#111

So four years from now, when we reach the end of that period, the order book should be comparable, at INR 25,000 crores.

P. Hari

executive
#112

Or perhaps higher; that is the goal we have set. Like, if you — I mean, again, it is...

Analyst

analyst
#113

So does that mean we should expect a noticeable deceleration in revenue growth starting 4 years out?

P. Hari

executive
#114

Right now, no. Right now, no, since if an NGC order comes in, and we are hopeful it will, then there is simply no way it declines. And we will — that is precisely why we are moving into commercial shipbuilding, isn't it? It is meant to cushion things. Should a downturn occur somewhere, we cushion it with those orders.

Analyst

analyst
#115

But when it comes to commercial shipbuilding, what sort of scale are we talking about, say over a 5-year horizon?

P. Hari

executive
#116

Over 5 years we'll get started — perhaps I'm unable to give you the figures, but we'll begin with multipurpose vessels along with tankers, or tankers of smaller size. And should the business prove good and the margins appealing, we'll put more focus in that direction. That's just a hunch, since I don't believe I have a clear answer.

Harshit Kapadia

analyst
#117

Harshit Kapadia here, from Elara Securities. Sir, on that order book figure of INR 23,700 crores, could you break it down for us — what portion would be for P-17 Alpha, what for SWC, and what for the ASW corvette?

P. Hari

executive
#118

You want the order book split across the different projects. How much is left in P-17 Alpha? For P-17 Alpha, roughly INR 12,700 crores is still remaining. That figure is as of 31st December; for the Anti-Submarine Warfare Shallow Water Craft, roughly INR 5,000 crores is left. On the survey vessel, about INR 1,050 crores remains. And for the OPV project, approximately INR 3,388 crores is remaining.

Harshit Kapadia

analyst
#119

All right. Just to finish on the last point...

P. Hari

executive
#120

So I believe this ought to answer the question from ma'am there that P-17 Alpha continues to account for nearly INR 12,000 crores.

Harshit Kapadia

analyst
#121

Yes indeed, sir, certainly. One final item on the commercial shipbuilding side. A different PSU has likewise stated that it intends to enter commercial ship construction as well. So would that turn into more of a competitive tender for the very same project? Or is it split by region — meaning you would focus on Europe while the other PSU would not be targeting…

P. Hari

executive
#122

Look, at this point European owners aren't considering China for the platforms we're pursuing. Among all of us — ourselves, Cochin Shipyard — just 3 have expressed active interest in the MDL. What we've determined up to now is that even as recently as yesterday — both yesterday and today, actually — the proprietors of two companies have been here at my offices. They aren't involved in anything competitive. Their focus is a shipyard. They carry out an independent evaluation of that shipyard, and once they learn we have an interest in the commercial side, they come to us. That's the approach they typically take, which differs from a standard government tender for building domestic warships. So it's one-to-one. Should the price be acceptable, should the classification society certify us as competent, and should the price be mutually agreed, then you're through.

Harshit Kapadia

analyst
#123

Got it, sir. Just one thing on indigenization: are there other products you figure you'll build in-house, or do you see yourself teaming up on them down the road the way you did with diesel engines? Is there any other item you're looking at that carries high value, maybe even critical value, that you could point to?

P. Hari

executive
#124

Beyond diesel engines, on the smaller vessels there's waterjet propulsion; a handful of OEMs have the capability — Wartsila, Kongsberg, Rolls-Royce and others — and we've partnered with Kongsberg. An MOU is already signed. Now that MOU has to become a license agreement. That's what we did for the engine. I figure another 3 to 4 months to wrap it up. The upside again: plenty of the platforms the Navy and the Coast Guard need run on waterjet propulsion. So — with indigenous content — given the government's push on indigenization, with indigenous content above 50 or — and should that turn into the RFP criteria, our chances are good. And since you raised indigenization, nearly all the autonomous platforms coming — you've surely seen in the news that many of those platforms are being imported right now. That can't continue indefinitely; so I won't attach any figure to it. I'll just say that segment has a future too — and on purpose, we're only working with startups; we aren't partnering with any major industry, because that suits us economically as well.

Analyst

analyst
#125

Sir, about the question you raised when we got here — we watched a corporate film on GRSE. In that film, you had a document in your hands titled Vision 2030. So could you expand on that for us — our interest lies solely in the financial side of Vision 2030. From a financial standpoint, what's your vision?

P. Hari

executive
#126

Sir, it was along the lines of Dr. Abdul Kalam <<foreign_lang>>, his point being nothing — I mean, there's simply no limit to dreams, yet those dreams ought to be realistic. We — my company's vision is to turn into a Navratna company by 2030. Now, to turn into a Navratna company by 2030, we must first become a Schedule A company within another couple of years. This year, next year, or the year after next. And our present revenue of INR 3,000, INR 4,000 crores amounts to nothing. So we aspire to turn into a Navratna company carrying a turnover of roughly INR 10,000 crores by 2030. That is an ambitious target, very, very aspirational, yet it isn't impossible. It is very much achievable.

Analyst

analyst
#127

We're just allocating INR 10,000 crores by 2030. 4, 5, 6, 7?

P. Hari

executive
#128

Why haven't I set aside INR 15,000 crores? Why haven't I gone for Maharatna, which means...

Analyst

analyst
#129

That can be done.

P. Hari

executive
#130

It can be done — in fact, it has been done. There is no doubt it can be done.

Analyst

analyst
#131

And sir, to hit that INR 10,000 figure, what are you expecting from the Government of India?

P. Hari

executive
#132

Our expectation from government is clear. First, we want the P-17 Bravo project. Second, on our own internal side, we expect that we must win the 5 ships of NGC. We should become the L1. Third, no project of ours should cross — the existing order book should not cross 2028. Not a single one should cross 2028. Fourth, in commercial shipbuilding, we should start off on the right foot. If we do start on the right foot — I mean, just now, we had a tanker OEM who had come — I mentioned that yesterday — we're hesitant to commit to him because we have a multipurpose vessel owner who is about to sign a contract. So at this point, what I'm trying to say is that there are plenty of opportunities and leads. So that's the fourth thing. And fifth, of course, supplement this with all our other verticals. Because today, among Indian companies, among all Indian companies taken together, all of them, I say with confidence that we are the only fully diversified company. Among — take private, public, everyone together, we are the only truly diversified one, which means if you talk shipbuilding, commercial ships, we have delivered; we will deliver more. Ship repairs, you talk about bridges, which has nothing to do with ships, weapons, diesel engines, so the capability exists.

Executive

executive
#133

Are there any further questions? All right, I believe that covers everything. Many thanks to all of you. Thanks, Commodore Hari. Thank you, Mr. Dash. And thank you, Sandeep, sir.

P. Hari

executive
#134

Thank you, ladies and gentlemen. It was a real pleasure to interact with all of you, and we look forward to meeting you soon. We will not let you down. And I would ask every one of you to join with us in IT.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Garden Reach Shipbuilders & Engineers Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Garden Reach Shipbuilders & Engineers Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Garden Reach Shipbuilders & Engineers Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.