operatorGood afternoon, ladies and gentlemen. My name is Navya, and I'm the moderator for this conference. Welcome to the conference call of Garden Reach ShipBuilders and Engineers Limited, arranged by Concept Investor Relations to discuss its Q4 and FY25 results ended March 31, 2025. We have with us today Commodore P.R. Hari, Indian Navy Retired, Chairman and Managing Director; Shri. R.K. Dash, Director Finance and CFO; and Shri. Sandeep Mahapatra, Company Secretary and Compliance Officer. Please note this conference will be recorded. I would now like to hand over the floor to Commodore P.R. Hari, Chairman and Managing Director. Thank you and over to you, sir.
P.R. Hari
executiveThank you, Navya. Good afternoon, everyone — ladies and gentlemen. I'm P.R. Hari, the Chairman and Managing Director of the company. Joining me on this call are Shri. Ramesh Kumar Dash, our Director Finance and CFO; Mrs. Aparajita Ghosh, General Manager, Finance; and Shri. Sandeep Mahapatra, the Company Secretary and Compliance Officer. Before we begin, my warm regards go out to all of you who have carved time from your busy schedules to join this call. I'm looking forward to this analysis and interactive investors meet — interacting with all of you is always a pleasure. It also gives me the chance to lay out the highlights of how we performed and to take up your questions concerning the financial performance. We've delivered yet another very strong set of numbers. At this point I should give my stock dialogue. For the quarter and the financial year that ended on 31st March 2025, the performance has been the best ever in the company's history. If you compare quarter against quarter, revenue from operations has climbed from 1015 crores to 1642 crores, which works out to a growth of 62%. EBITDA has risen from 166 crores to 335 crores, a growth of 101%.
P.R. Hari
executiveProfit after tax rose from 114 crores to 244 crores, which works out to 118% growth. Operating profit likewise climbed from 77 crores to 209 crores. On a financial year to financial year basis, our revenue from operations came in at 5075 crores. That means we crossed the 5000 crore mark, with growth of 41%, while profit after tax increased by 46%, from 360 crores to 527 crores, and operating profit went from 181.30 crores to 368 crores, a rise of 103%. All of this rests on very strong physical performance, helped along by a treasury management system that is both efficient and effective. Our order book stood at rupees 22,652 crores as on 31st March 2024, and even though we accrued strong revenue of nearly 5000 crores, we still held the order book at Rupees 22,680 crores as on 31st March 2025. That covers 9 projects made up of 40 platforms, among them 16 warships for the Indian Navy drawn from 4 projects, 3 P17 Alpha Frigates, 7 Anti Submarine Shallow Water Crafts, 2 Surveyors Large and 4 Next Generation Offshore petrol vessels. Beyond that, we are carrying out an eight ship multi purpose vessel project for a German client, along with one acoustic research vessel for one of the DRDO organizations, the NPOL Kochi, an ocean resource vessel for the Ministry of Earth Sciences, specifically one of their units, the NCPOR Goa, and 13 hybrid ferries for the Government of West Bengal.
P.R. Hari
executiveBetween the end of the last financial year and today, we have handed over one Surveyors and large — that vessel being the second in a set of four ships we are constructing for the Navy. We are also pleased to report that we delivered the first anti-submarine shallow water craft to the Navy quite recently, in fact as early as the second week of this month. That milestone is very prestigious and a source of pride for Team GRSC, since this is the first ship in a series of 16 ships being built for the Navy by two shipyards — another PSU shipyard and ourselves — and we are glad to have delivered the first of these 16 ships. Beyond that, we delivered an unmanned surface vessel to a DRDO organization, the NSTL Vishakhapatnam, and we also finished the petrol vessel petrol boat project for the Government of Bangladesh. Let me now give you a glimpse of how the ongoing project is progressing. As I said, we are building three T17 Alpha ships. I am happy to report that the first ship remains well on track for delivery, and we have completed the final machinery trial. By final machinery trials, I mean the trials carried out at sea with customer representatives, that is, Navy representatives, present.
P.R. Hari
executiveSo at this point we're getting the vessel ready to hand over, and construction work on it is already about 95% physically complete. Our plan is to deliver this vessel in two months, which puts us ahead of the contractual delivery window. The second vessel is progressing nicely. It stands at 73% physical construction, and we plan to deliver it early next year. As for the third vessel, it has reached 54% physical progress, and delivery is scheduled for August 2026. Turning to the survey vessel Large project, I noted earlier that two of these vessels are already delivered, with the most recent one handed over last year. Vessels three and four remain firmly on schedule for delivery. The third vessel is at 88% physical progress. It has finished its contractor fleet trials, and at present it's being readied for final machinery trials ahead of delivery. We expect to deliver this vessel by July this year. The final vessel in the project, survey vessel Large 4, stands at 77% physical progress, and before this year ends — this calendar year — we will be delivering that vessel. Moving on to the anti-submarine shallow watercraft project: as I said, the first vessel has already been delivered, the second vessel has finished its final machinery trial, and that vessel is slated for delivery in July this year.
P.R. Hari
executiveShip number three now stands at 82% completion, number four at 68, and it continues in that vein. Based on our present assessment, every vessel in this project will be handed over within calendar year 2026, with four of these ships — meaning three additional vessels — scheduled for delivery across 2025-’26. Turning to the next generation offshore petrol vessel project, the initial two ships have gone past 50% of physical progress, while the final two ships in that project have likewise advanced quickly, reaching 43% physical progress. What I want to say regarding the next generation offshore petrol vessel project is that keels for all four ships have already been laid, and we plan to launch two of these vessels in the current financial year. Furthermore, among the other non defence platforms, production on the ocean research vessel has already begun, its keel was laid in March 2025, and handover of this ship is scheduled for October 2027. Also, for the acoustic research shift for the DRDO, design and pre production work is under way and the project remains well on track. We are additionally carrying out one project for the Government of Bangladesh, a Draja project.
P.R. Hari
executiveWork on design and pre-production is moving forward, and the hybrid series is at the same stage. The 13 hybrid series. Launching the keel for all 13 of the series is scheduled for the end of this month. That gives you a quick picture of where the projects underway stand; now let me turn to the projects on the Anvil. In an earlier interaction I noted that we had been declared L1 for two vessels — the Geological Survey of India coastal research vessels. The letter of intent has already come to us, and signing of the contract for these vessels is expected during June this year. We also anticipate the formal bid declaration for the next generation Corvette project within a couple of days. Beyond that, the Navy has already issued an RFP covering five next generation survey vessels. Large and GRSC will certainly bid for this project, and with our experience of building the survey vessels large as well as earlier platforms of a similar kind. In our appreciation, we stand a good chance of putting in an aggressive bid for this project. One more bid that is live is the bid for 18 next generation fast patrol vessels for the Indian Coast Guard.
P.R. Hari
executiveGRFC is going to put in a bid for this project. It's an interesting one. It isn't a standard fast patrol vessel. It's an advanced ship that has a hello helicopter staging facility, so GRSP would be keen to participate in this project. Those are the 2 live RFPs that exist at present. Beyond that, beyond those 2, we anticipate RFPs for 6 next generation Ocean going petrol vessels for the Indian Coast Guard, 2 multi purpose vessels for the Indian Navy, 120 fast interceptor crafts for the Indian Coast Guard, and 31 follow on water jet fascists for the Indian Navy to be released in the near future. All of these are small to medium sized projects. What we're looking forward to eagerly, as I've said repeatedly over the last 2 years, is the next generation Corvette project. Another project for which we expect the RFP to be issued is the P17 Bravo follow on of the P17 class of ships. As you know, we're building 3 of these vessels right now, and with that experience we're once again confident of putting forward a good bid, a competitive bid, for this project. In our assessment the RFP is likely to be issued during the calendar year.
P.R. Hari
executiveBeyond that, where Navy is concerned, they've already secured the Defense acquisition council's approval for 12 mine countermeasure vessels — main countermeasure vessels — plus the other two large projects. Right now there's no clarity on when the RFP will come out, but from Navy's perspective plan standpoint, the LPD project and the next generation destroyer project are also certainly on the anvil, to give you. This has provided you. What I've attempted to give you is a glimpse of our financial performance and how that financial performance has been derived through our physical performance, the status of the ongoing projects and the orders on the envelope. As far as yard capacity goes, we had a shipbuilding capacity to construct 20 ships concurrently, but during 2024 we enhanced this capacity from 20 to 24 through rejuvenation of our existing facilities, and we feel this capacity itself is inadequate to meet the ongoing and the future requirements. So we have put in capital to revive some of the defund facilities earlier held with us and also through certain long term lease of dry docks from one of the other agencies in Kolkata.
P.R. Hari
executiveOur plan is to raise shipbuilding capacity from 24 to 28 ships by the end of 2025. Beyond that, we're exploring opportunities beyond Kolkata for setting up shipbuilding facilities. That aligns with rising demand for both defense and non defense platforms. And we believe there's opportunity there — ample opportunity. To capture that opportunity and the potential present in both the defense and non defense markets, we'll be seeking facilities outside Kolkata and perhaps looking at creating a greenfield facility. I'd also like to mention that to address the current capacity constraints and to handle the leads we're receiving for commercial ship construction, we've entered into a memorandum of understanding with capable shipbuilders on both the east and west. That, in a nutshell, sums up what we're pursuing in the near term. One of our core focus areas will be capacity enhancement. 2. Technology adaption to boost production efficiency. 3. Development of autonomous platforms, where we see opportunities with both the Navy and the Coast Guard. And four, toward developing green energy products. Thank you ladies and gentlemen.
P.R. Hari
executiveThat concludes what I wanted to say. At this point, I'd like to open things up so you can ask questions. We'll do our best to respond to each one. Thank you.
Operator
operatorThank you so much. We're going to start the question-and-answer portion now. <<operator_script>> Our first question comes from Vaibhav Dalal of Niveshaay, who is on the line. Please go ahead.
Vaibhav Dalal
analystHi sir, can you hear me okay?
P.R. Hari
executiveYes, we can hear you, Mr. Dalal. Go ahead, please.
Vaibhav Dalal
analystWell, congratulations, sir, on a solid set of numbers. My question is quite general. I just want to ask about the shipbuilding opportunity here in India. So at present, how many neighborships do we have with the Indian Coast Guard and the Indian Navy? And how much does the Ministry of Defense plan to add to each fleet? And the second part of my question would be, of the new ships the MOD plans to add, tendering has been done for how many of these ships, roughly? Any idea? That would be great. Thank you.
P.R. Hari
executiveMr. Dalal, I’d like to respond to that in two parts. First, regarding the present fleet strength of the Navy and the Coast Guard: the Navy has roughly 150 platforms, and the Coast Guard, taken all together — and when I say platforms, that covers small vessels such as fast intercept aircraft as well as larger ones — has nearly 100 platforms at this time. Right now, 61 platforms are under construction for the two forces combined, and among those, 6160 are being built by internship yards at present, moving on to their capacity augmentation plans. Both forces have their respective perspective plans, and based on what is available in the open domain, both the Navy and the Coast Guard wish to grow their numbers — the Navy perhaps to a figure of +200 and the Coast Guard perhaps to a figure of around 150. The reason I add the word perhaps is that I do not have absolute clarity on the exact numbers they are looking at. Now turning to the RFPs that are live, as I mentioned during my initial statement: second, in addition to the next generation Corvette project, where the bids have already been opened and the formal results are awaited, we expect it to come in a couple of days from now.
P.R. Hari
executiveRight now, two pieces of work under the services segment are live. The first is an 18 fast patrol vessel effort — next generation pass patrol vessels — for the Indian Coast Guard, plus a five-ship next generation subway vessel program for the Indian Navy. Beyond that, as I said before, a number of projects sit on the anvil, and for a few of them DAC approval has already come through. Take the 12 mine countermeasure vessel project for the Indian Navy, the P17 Bravo project — a seven-ship program for the Indian Navy — two multipurpose vessels for the Indian Navy, six next generation offshore petrol vessels for the Indian Coast Guard, and so on. What I'm getting at is this: what's in hand today, the order book of the Indian shipyards, and what will likely surface soon. The opportunities are phenomenal. Does that answer your question, or would you like something more? Any further clarification you need?
Vaibhav Dalal
analystI believe that covers everything, sir. Thanks very much for your response, and the best of luck to you. Thank you, sir.
P.R. Hari
executiveThanks.
Operator
operatorThanks. Our next question comes from Harshit Kapadia at Elara Capital. Go right ahead.
Harshit Kapadia
analystGood evening, sir, and thanks for the chance to speak. Congratulations on a really strong set of numbers. First, I'd like a sense of how the order book breaks up, project by project. Second, on the order inflow you mentioned in the pipeline, could you also share the size — roughly what order size one might expect? And on NGCU, you said in a few days the order will be announced — do you mean the bids will be out within a few days, or what is likely? Is there any LOI expected? Any clarity there? And last, sir, on the other expenses side, if you could explain: there was a provision write-back of 433 crores that you did. What was that related to? And by when will this entire amount be dispensed out — that is, added back to profit? Yeah. Thank you.
P.R. Hari
executiveThanks. I'll begin with a breakdown of the order book. As I said, our order book is at 22,680 crores. P17 Alpha remains our largest contributor. About 11,435 crores is still left from the P17 Alpha Project. The Anti Submarine Shallow Watercraft Project is 3,946 crores. The survey vessel large project — it's actually at the point of closing — so 530 crores. The offshore petrol vessel NGOPV project is 3,327 crores. The non-defence platforms: the NCPoR ocean research vessels 785 crores, the acoustic cruiser ship 466 crores, the ferry project 226 crores. And the export projects — the multi purpose vessel dredger and so on — around 1,200 crores. And the 30mm gun project 201 crores. So that's the order breakdown. Now, coming to the question you asked about what the likely value is. Value? Yeah, the value of the projects that are on the anvil. As I mentioned, the next generation Corbett project is a hybrid value project. And here we expect — our anticipation is that the total order value could be to the tune of 40,000 plus crores. But this 40,000 crores would be split between two shipyards, with the L1 shipyard getting five ships. That means five by eight.
P.R. Hari
executiveThat points to the L1 shipyard. The value of that order might come in at roughly plus 25,000 crores. That's a really large order heading toward the next generation survey vessel. Our sense is that the order value might land at approximately 3,500 crores. The 18 NGFPV project might come in at about 3,000 crores. The OPV project might be around 2,500 crores. The multi-purpose vessel might be approximately 1200 crores. The Water Jet FAC project — the 31 Water Jet FAC project — might be around 3000 crores. That could be plus or minus 200 crores, depending on how the bidding goes. The fast interceptor craft vessel might be around 1500 to 1800 crores. The big ticket items — the mine countermeasure vessel project. The Aon itself has been taken for 32,000 crores. And that's a 12-ship project. A single shipyard getting all the 12 ships as per the Aon conditions. And the P17 Bravo project. This again is a high value project. There are two shipyards. There is a fellowship project. Two shipyards would be involved in this project with the total A1 value at roughly 70,000 crores.
P.R. Hari
executiveAt this point, I'd rather not offer any assumptions regarding LPD and NGD, since those are still in liquid form. Anything further — you had asked something about that. 433 crores.
Harshit Kapadia
analystYeah, so you mentioned INR433 crores of provision write-back in the press release. What exactly is that tied to, and when would it be…
P.R. Hari
executiveThat was tied to the P17 Alpha project. The first one, because that initial vessel is really right at the point of handover. I noted that the first ship has finished her final missionary trials and is in fact preparing for delivery. So we have decent visibility on what it will cost to finish. As a result, the provision was reversed and we will be. This profit will be recognized across the coming 1 to 2 years and the whole project is finished, meaning this three-ship project. So the first ship is now ready for delivery and the next two vessels, as I said, one of them will definitely spill into the next financial year. So this will be regularized within 1 to 2 years.
Harshit Kapadia
analystAll right, sir. And could this figure potentially rise even further? Given that additional vessels will now be in the compass and nearer to the completion mode, is there a chance that an increase would occur to INR433 crores? Any figure might be greater than —
P.R. Hari
executiveIt should be roughly the same. Because we already know the costs — the cost to complete the first ship. Conditions will be pretty much the same, and that's the positive part.
Harshit Kapadia
analystGot it, sir. And then lastly, sir, an NGC. Sir, you brought up when that order is probably going to be awarded. Sir, this last item.
P.R. Hari
executiveYou're just as seasoned at this as I am, given how things usually go. Once the L1 is announced, that's when contract talks begin. For big projects like this one, those negotiations tend to drag on. Our very, very optimistic estimate for wrapping up the contract is December this year, and a conservative one is March next year. Still, my own view is that if the L1 shipyard, whoever it turns out to be, and the Navy push together, the contract could be signed by the end of this calendar year.
Harshit Kapadia
analystAll right, sir, I have a handful of additional questions. I’ll get back in line, sir. Thanks to everyone. Best wishes to all of you.
P.R. Hari
executiveThanks.
Operator
operatorThanks. Our next question comes from Rohit at Aditya Birla Sun Life. Go ahead, please.
Analyst
analystThanks for giving me the chance, sir. So, first question from my side. From what I understand, our order backlog stands at close to 230 billion. And normally, our execution cycle runs about five years. Would it be reasonable to describe the present revenue as roughly the peak level? And perhaps we'll stay flat, considering we already have around 20 yards that we're working with. And even supposing the new order — let's say, hypothetically, you win the next generation Corvette. It might not begin for at least one to one and a half years. So would it be fair to think RB is currently in a somewhat peak execution phase?
P.R. Hari
executiveThank you, Mr. Rohit. Of course, when it comes to revenue accrual and revenue recognition, it all hinges on which phase the project execution is in. Right now we're in an execution phase where the largest amount of revenue accrual occurs, thanks to our main breadwinner — the P7 Alpha project — which sits at a mature state, where the greatest number of equipment items get lowered and integrated into the ship system. As for your question on whether we've peaked, I wouldn't want to say that, because in our appreciation — okay, let me put it this way. At the start of the last financial year, our order book stood at 22,651 crores. And as of 31st March 2025, it's at almost the same quantum. That means 2680 crores, which means that over the last one year, while we generated revenue of over 5000 crores, we also brought in orders worth 5000 crores. So in our appreciation, the peak year might perhaps be the next one. That is, financially, the current year. What I mean is that financial year 25, 26 could be the peak year. After that, it could flat out. And hypothetically, if a big project comes to us, as you rightly said, revenue recognition from that project will only begin two years down the line.
P.R. Hari
executiveThat gap that might open up is already getting filled by a wide range of orders — orders coming from non-defense platforms as well as commercial ships. So, to put my answer to your question in one simple sentence: this is probably not the peak year. The peak year has yet to arrive.
Analyst
analystThanks for that. My next question is really about how we stack up against competitors. We're seeing Musgrove Dock pursue a greenfield expansion, and Cochin Shipyard has greenfield plans too — they're eyeing a port close to Cochin port and working up something there. So what's our plan? We've done a bit of leasing here and there, but do we have a concrete greenfield roadmap that could put us on a different trajectory?
P.R. Hari
executiveYes. Today, with the Ministry of Shipping having launched a clear roadmap to raise India's share of the worldwide shipbuilding market from under 1% to 10% within a defined timeframe, every Indian shipyard needs to expand its shipbuilding capacity. What we began — I noted this in my opening remarks — was that our capacity only about two years ago was to build 20 warships, 20 ships, large and medium combined, at the same time. We began by revitalizing our current facilities and raised capacity to 24 ships. In addition, we had also moved ahead with acquiring dry docks in Kolkata, long-term leased dry docks that now belong to us. So through this, we intend to lift that capacity to 28 ships by the end of this year. But we completely recognize that this alone will not be sufficient to satisfy demand — the shipbuilding demand that will exist over the coming five to 10 years. So yes, in answer to your question, we are, like MDL or like Cochin Shipyard or any other shipyard in India, at this point in the process of establishing a greenfield shipbuilding facility.
P.R. Hari
executiveBecause talks are still underway with several agencies on both the west and east coasts, the only thing I can tell you is that yes, we're in that process as well, and we anticipate having clarity on it within the next six months to nine months.
Analyst
analystUnderstood, sir. So my last question leans more toward the industry side of things. Regarding that naval perspective plan for 200 vessels that we had previously — there seems to be a certain delay, both when it comes to awarding and then to commissioning those vessels. Is there a strategic realignment taking place at the country level, or is it something like the priority is moving backward on the naval front and perhaps more is being put toward electronic warfare funds? Because we've been reading quite a few of these defense analyst reports. You know, they've been saying that even the Chinese threat we face is oriented more toward the territorial side rather than the naval side. And we had a military exercise previously — I mean just a few weeks back — where we observed it was more about electronic warfare. So I'm just trying to understand what happens to that naval perspective plan of 200 vessels. And we've also seen the next generation Corvette getting delayed for a long time. AON happened a long way back, and yet the awarding hasn't been taken up in a. The last big order I could make, at least, was with ngopv.
Analyst
analystDo you have any thoughts on those aspects?
P.R. Hari
executiveLet me frame it a different way. Yes, Navy has. Honestly, I wouldn’t want to say I agree with you, and I wouldn’t want to say I disagree either. But let me offer a totally different angle. For any country, for any country to be a global power, it must. What I mean is the country must possess a blue water navy. And India’s coastline, from roughly 7,600 km, has risen according to the most recent survey to more than 11,000 kilometers. So there’s no chance that the naval province—meaning navy plans to augment, or coast guard plans to augment, their capability—is shrinking. Even under present circumstances, naval platform deployments can be found in open media. Now turning to ships being built. When I mention 61 ships under construction, 61 warships under construction, that’s no small figure. 61 is how many platforms many countries collectively possess. 61 platforms are being built, and out of these 61, 60 are being constructed by Indian shipyards. The figures, if you look at 18 NGF, that is next generation fast patrol vessels. 6. 5. Sorry. 5 survival large 18 plus 5 23, 31 watered FAS. You add this figure plus 120 FICs, plus 8 NGC’s.
P.R. Hari
executiveThose figures aren't insignificant at all. Sure, these processes take time, but once fractify happens, construction kicks off. Take the NGP — according to our own procurement timeline, from the moment an AON is accrued by DAC, the acquisition side, or rather the Ministry of Defense, gets a defined 30 month window for issuing the RFQ. They completed it comfortably inside that window. So I. I don't see any shift in focus when it comes to developing maritime capabilities. And I've just laid out the numbers. The numbers are right there for you to see. And I — from GRC's perspective, out of the 16 platforms we're currently building, four of them we've already delivered in the current calendar year. And three additional ones we're confident of delivering this calendar year, plus one more in the financial year. So I don't see any, any dilution — whether from the government side or from the shipyard side — regarding focus and delivery. Delivery in terms of placing orders. Delivery in terms of publishing the RFP. Delivery in terms of actively delivering the ships.
P.R. Hari
executiveI appreciate that.
Analyst
analystAppreciate it, sir.
Operator
operatorThank you. Ladies and gentlemen, so that management can get to questions from every participant, we ask that you keep your questions to two per participant. We now take the next question from Dhavan Shah of AlfAccurate Advisors. Please go ahead.
Dhavan Shah
analystYeah, thank you for giving me the chance, sir. So my question concerns that agreement you've signed with Swan Defense, the top player in the Western market. What's your strategy and what are the plans for that side? Could you share your thinking on it?
P.R. Hari
executiveAlright, regarding Swan Shipyard and infrastructure — they rank among the country's biggest shipyards, and Dryadoc is arguably the largest nationwide. Their infrastructure is also among the finest in the country. Based on what's out there in open media, and as you already know well, the facility hasn't been used for a while, for reasons that are known. Being a shipyard situated in Kolkata, with the order book we're currently executing plus a few assured orders on the anvil, we saw the need to establish a presence on the Western Front — a front in the west where we can partner and develop commercial business. That's the intent behind the MoU we signed with SWAN, under which we'll jointly build commercial ships of the large size. It's an MOU at this stage; we're in negotiations with a few clients for orders. Once those materialize, the MoU will convert into actual co-production. Thank you.
Dhavan Shah
analystGot it, sir. And, and typically, within a 12-month period, what number of vessels would you expect could be built? The commercial ones there?
P.R. Hari
executiveYou were referring to commercial vessels —
Dhavan Shah
analystYeah, yeah. On this one. On this one. Defense, you know where it's located.
P.R. Hari
executiveIt really comes down to the order. Let me frame it another way. At this moment, I’m working on an order for a German client covering eight multi-purpose vessels. Those are medium-sized ships — advanced platforms, but medium-sized vessels in that case. For all eight ships together, the contractual delivery timeline is four years. So the duration shifts based on how big and how complex the ship is. It’s possible the first ship might be handed over within a period of three years. That’s because the first ship always takes time. The follow-on shifts — the second, third, fourth in a series of four. If it’s a series of four, it could be six, six months after that.
Dhavan Shah
analystGot it, sir. Yeah, I’ve got nothing further to add. Thanks.
P.R. Hari
executiveI appreciate that.
Operator
operatorThanks. Our next question comes from Divya Shah at Uchit Capital. The line is yours — go ahead.
Analyst
analystGood morning, sir. Congratulations on an excellent result, and first, our best compliments go out to the entire Defense department of India. Thanks to Operation Sindur, we have come to realize how important defense is. So through you, I convey my heartiest congratulations to all three services — Army, Navy and Air Force. Please pass this on to the respective departments, sir; we Indians are proud of you, sir. Turning to the follow-up on my earlier question about Swan Defense, sir, I want to know where we stand. Have we taken over the entire Swan Defense facility, or only a portion — what exactly is the understanding between the two companies? What will the financial implications be? Is it structured as revenue sharing or as a lease agreement, and how will it be carried forward? That is my — okay. Any more questions? Then I will answer them together. Any more questions? Yeah. My second question is similar. We have entered into a lease agreement with Shama Prasad Mukherjee Port Kolkata. So what will the financial implications of this agreement be? And what will the payout per year be for this facility? How many ships will we be building there? These are my two basic questions.
P.R. Hari
executiveAlright. First off, let me express our thanks for the kind words you offered regarding the Indian Armed forces. Because we work so closely with the services, we'll pass along your appreciation to them as it relates to Swan Defense. This agreement is tied to specific projects, meaning that each time a project gets executed, it will rest on a revenue sharing model. Again, that's project specific. When a project arrives, we will finalize the terms and conditions for that project coming to Shyama Prasad Mukherjee Port. We have fully taken over three dry docks from this port, and those have been acquired under a long term lease. We pay them a nominal rent, and we have a profit sharing methodology in place with them. In addition, we very recently took over one more dry dock. It's the 125 meter by 25 meter dry dock, again under a similar model. Now, what we intend to do at these facilities for dry dock — and just to put you in the right perspective — dry docks are very vital towards shipbuilding and ship repair. Since our primary facilities sit within the physical confines of the company, my three shipbuilding units are focused on shipbuilding, and since we wanted to venture into ship repairs.
P.R. Hari
executiveThat wasn’t today—it goes back almost 3 years, when we made the decision that we needed a facility entirely separate from the shipbuilding facility. And that’s how it is. Attention doesn’t get diluted. That’s why we took over these facilities from Shama Prasad Mukherjeel Port. To date, we’ve completed close to 41 refits at this facility, including multiple Costa ships and naval ships. We will also be carrying out the refit of an export platform there. This works on a profit sharing methodology with them. So far, the project—the project relationship has been successful. Thank you.
Analyst
analystAnd sir, about what our total capacity will be — assuming everything goes smoothly with Shyama Prasad Mukherjee and the others you just mentioned — so from 28, where will we get to in the next three years? Shipbuilding capacity. Y
P.R. Hari
executiveYes, yes. As of today, the count stands at 24. 25. 24. Our intention is to raise it to 28 by the end of this year, and we are well on track for that — we feel confident we will hit this target. And since you raised that question, two to three years down the line, including the greenfield facility we have at our plants — setting that aside from the current discussions, because it is still in liquid format and under discussion — so with the facility in Samarpasad, the Mukherjee port, and our existing facility, including rejuvenation and modernization, we intend to take it up to 30 within the next few years. How much, or how much please? Did I miss? 30 ships.
Analyst
analystAnd sir, just one final question from me. Sir, this year we achieved an excellent EBITDA margin of roughly 13%. Sir, is that same margin sustainable, or is it one of—sir, could you please give us some guidance for the future?
P.R. Hari
executiveThat's a really interesting question. You brought up the one-off point. It hasn't been a one-off. Over the last several quarters, margins have been fribbler along similar lines. Yes, this time around we've reached a new high. It certainly isn't. It's not a one-off. But in shipbuilding, you... ideally, a quarter-to-quarter comparison isn't something we should be doing. You look at a year. Because the majority of our projects are long drawn out, with execution stretching across a period ranging from, for a small platform to a big platform, five to six years. So, to answer your question, we'll be able to maintain more or less the same margin. It's not one of those anyway.
Analyst
analystAlright, sir, I really appreciate it.
P.R. Hari
executiveThanks.
Operator
operatorThanks. Thanks. The next question comes from Utkarsh Somaiya, who is calling on behalf of EIKO Quantum Solutions Private limited. You may proceed.
Utkarsh Somaiya
analystThanks for the chance to speak. You mentioned your delivery timeline near the start of this call. Could you put a number on it — how much you think you can execute in FY26, and probably 7 and 8 as well? Even a ballpark would be helpful. I'll give you a ballpark. Thank you. Thanks for the question. I'm sure that's what you're asking.
P.R. Hari
executiveRough figures, then. What are the actual numbers when it comes to how many ships?
Utkarsh Somaiya
analystWas that ships or revenue — which one are you asking about? Revenue?
P.R. Hari
executiveI'd prefer to go by ship count. Hold on a second. Yeah. So in 2025, '26 we will be — I'll also try to tie that to revenue. To give a rough picture, though I won't get into specifics, I'll try to link it to the projects. Can you — can you make an estimate? So in 2025, '26, we will deliver one P17 Alpha, two survey vessel large, and four anti-submarine shallow watercraft. That alone accounts for four, two, one, seven ships. In 2026-'27 we will deliver two P17 Alpha. These are major high-value projects. Three — the last three survey vessels. Sorry, the last three anti-submarine shallow watercraft, and one next-generation offshore patrol vessel, plus the acoustic research ship. And the following year, that is FY '27-'28, we will deliver two next-generation offshore patrol vessels, the oceanographic research vessel, and the coastal research vessels, for which we are going to sign the contract. Now I haven't mentioned the hybrid ferries we're building for the government of West Bengal, or the Treasure, because those are small-value projects that will get covered during this period. Perhaps this year itself we'll be able to deliver a couple of ferries and so on.
P.R. Hari
executiveSo does that give you a sense of it? Because most of the project—there's a P7 Alpha first ship this year, and then the following two ships come next year.
Utkarsh Somaiya
analystRight? Yeah, that helps. And I'd guess the realization per ship would be different in each case, right?
P.R. Hari
executiveRight. Yes. As I mentioned with the P7 and Alpha — the P7 Alpha — what's left on revenue comes to roughly 11,000 odd crores.
Utkarsh Somaiya
analystAlright, thank you very much — that’s useful.
P.R. Hari
executiveI appreciate that.
Operator
operatorThanks. Our next question comes from Sanjeev Zarbade at Antique Stock Broking. Please go ahead.
Sanjeev Zarbade
analystGood afternoon, and thank you. Yes, sir. My question concerns the outstanding order book for P17. We have 11,400 or crore. So, roughly speaking, what account revenue might we book in FY26 and FY27? Would it come in the ratio 1.
P.R. Hari
executiveThere's a break in your audio. Could you say that again? I wasn't able to make out what you said.
Sanjeev Zarbade
analystHi there. Hi there. Hi there. Hi there. Yes, sir. Can you hear me at this point?
P.R. Hari
executiveYes, we can hear you fine.
Sanjeev Zarbade
analystYeah, yeah. Sir, apologies for interrupting. Sir, my question concerned the P70A, for which we hold an order worth 11,400 crore. That pending order book — how does it break down in terms of revenue booking across FY26 and FY27? You did share the delivery timelines, but will revenue booking follow that same kind of ratio, meaning more gets booked in FY27 since we'd be delivering two vessels that year, or would it work the other way around?
P.R. Hari
executiveYeah, roughly 11,400 crores was left as of 31st March 2025. And one of these shifts we plan to deliver within the coming three months. And on this ship, we've already accrued the majority of the revenue. And the larger portion of it would be coming from the second and third ships. So, so if you, if you're asking me what proportion of revenue from the project will be accrued this year versus next year, I'd say 40. 60.
Sanjeev Zarbade
analystAll right. For FY26, that's 40, and for 27, it's 60.
P.R. Hari
executiveRegarding FY27.
Sanjeev Zarbade
analystIs that 60 in 26 and 40 in 27?
P.R. Hari
executive40 in FY26 and 60 in FY27.
Sanjeev Zarbade
analystAll right, so in that scenario, sir, FY27 might end up being the year when revenue hits its highest point.
P.R. Hari
executiveGo ahead and take a guess. Possibly. Possibly this year. Because look, the other projects are maturing as well now, since we have roughly 4,000 crores left in the ASW shallow watercraft. Around 3,000. I mean, in response to a question earlier, I had mentioned that a very specific question was asked. Are you flattening out the flat? Are you flattening? I said no. So I think that ought to be sufficient for you.
Sanjeev Zarbade
analystYes. Yes. And sir, regarding the cost revision, if I’m understanding it right, for the two frigates that remain, there’s a possibility we could record an additional 200 crore of cost division in profit terms, because for the first project we may have — we have taken 100 crore as profits related to cost revision.
P.R. Hari
executiveYeah, you've got the gist of it, more or less.
Sanjeev Zarbade
analystAll right, sir. Best of luck going forward, and keep up the good work. Many thanks.
P.R. Hari
executiveThanks. Thanks a lot.
Operator
operatorThanks. Our next question comes from Sunil Shah at SRE PMS. Go ahead, please.
Sunil Shah
analystThank you for the chance to speak, sir. To start, my warmest congratulations go out to everyone. My friend Vivesh Bhai, I believe, already said as much at the outset. But truly, a sincere bow to each of you for what has been accomplished over the past month. So my genuine congratulations to all. Sir, I have just two questions. Within the next couple of days, we expect to hear about the next generation Corvettte project, which has been pending for a long time. So what should we expect to be announced in the next couple of days? Will it be that L1 and L2 get decided, and after that we enter a price negotiation process? How does this work, for a layman like me to grasp it? That is my first question. My second question: since we now have a tie-up with Swan Energy, Swan Defense — so we are. When we met last time, we were discussing clusters that, you know, the Indian government is considering for shipbuilding. Now that we have entered an MoU with Swan, does that address the cluster matter that we intended to eventually use for our growth? Those are my two questions, on Swan and on the next generation.
Sunil Shah
analystThanks, sir.
P.R. Hari
executiveThank you, Mr. Sunil Shah. And right at the start, thank you on behalf of—since we're a Ministry of Defense entity, on behalf of the Indian Armed Forces, thank you for the good wishes and the appreciation. First, on Swan and Clusters, I want to clarify plainly that I had replied to an earlier question. We hold MOUs or agreements not just with Swan; we also have them with capable private players—private and public players—for collaboration on vessel construction. An example: I have an ongoing collaboration with one of the south-based shipyards for construction, part construction, of a few vessels. So these are project-specific. And this has nothing to do with the clusters I mentioned. A cluster—what the Ministry of Shipping had conceived of, and what we expect to be implemented, was the creation of a greenfield facility. When I say a greenfield facility, that means a shipyard surrounded by its ancillary industries. This is still in liquid form. Multiple state governments—this is all open-domain information—multiple state governments such as Gujarat, Maharashtra, Karnataka, Orissa, Andhra and Tamil Nadu have shown interest and approached various shipyards and also floated the expression of interest for creation of greenfield shipyards there.
P.R. Hari
executiveWe've also responded to a few of these points. The SWAN relationship regarding shipbuilding collaboration is specific to each project and limited to large commercial vessels. I'd like to reiterate once more that we maintain similar relationships with multiple shipyards, and we've already exercised a few of them successfully. On your first question about the next generation Corvettes, what will likely happen over the next couple of days is the L1 declaration and L2 declaration by the Ministry and Navy. A natural process of contract negotiations will follow, depending on how complex a project is. This project is definitely complex and high-value. In my appreciation, this could take a very optimistic timeline of around six months from now. That means, let us say, December this year. The concrete conclusion, or a conservative timeline of another — you add another three months — March 31, 2026. I hope this clarifies.
Operator
operatorThanks. Our next question comes from Hardik Gandhi, on the line from HPMG Shares and Securities Private Limited. Go ahead, please.
Hardik Gandhi
analystHello, sir. Kong, is it possible for you to hear me?
P.R. Hari
executiveYes, I’ve got you. Go right ahead.
Hardik Gandhi
analystOkay, so thanks for giving me the chance and congratulations on the strong set of numbers. So I've just got two questions from my side. First, on the execution front, are you running into any headwinds? And second, since I know this question usually comes up, but given that Mazgaon and Cochin operate in a similar industry, their operating margins are quite high compared to ours. Of course we've improved our margins over the quarters, but. But again, is there room for further improvement, or do we see margins holding at these levels?
P.R. Hari
executiveAlright, thanks for the question, Mr. Hardik. I'll take the second one about margins first. Traditionally, one of the shipyards you brought up has been running projects that were handed out on a nomination basis. The other shipyard you referred to has mainly been doing ship repair work. Plus one nominated project of very high value. And we've more or less been working on projects that come through competitive bidding. Right now, every project coming out from the services side goes through competitive bidding. So even though we've made improvements, there could be a scenario where all Indian shipyards, including the ones you named, end up on an even footing. As for margins reaching the headway — I'm sure you would have. Your question was probably about project progress specifically. Yes, we're pleased with how the projects are progressing despite the challenges we faced and the cascading effects of COVID, which many. The impact is still there even after five years. There is impact. But we've overcome these challenges effectively. And that's how the ships are being delivered. I specifically mentioned in my opening remarks one particular project that is a matter of great pride for us and every for all.
P.R. Hari
executiveLet me say this: a 16-ship project is under construction for the Indian Armed Forces — that is, the Indian Navy — namely the anti-submarine shallow watercraft project. The first of these is being built by two shipyards: eight by us and eight by another shipyard. We're proud to say our first ship has already been delivered and will join the naval fleet a month from now. The second ship has also gone through contractor sea trials. The first P17 Alpha is ready for delivery. Two months from now, that ship will be delivered. So yes, there is definite headway. And with the figures — the numbers I mentioned regarding ship deliveries in response to an earlier question — we are confident of meeting the timelines we've committed to our customer for the ongoing projects.
Hardik Gandhi
analystGot it. So as a quick follow-up, are there any supply chain problems right now, given the geopolitical tension, and also, if so, how much are we bringing in from outside, and is there a bottleneck there?
P.R. Hari
executiveAs of right now, no, there isn’t any direct impact. Yes, some import content exists, particularly for the export platforms we’re building. However, the sources we’re procuring from haven’t been affected by the current situation. And given that the overall situation, including conflicts in various parts of the globe, is still ongoing, we still haven’t faced any impact at all, and we don’t foresee any impact on our supply chain regarding the ongoing projects we’re executing.
Hardik Gandhi
analystGot it, sir. Thanks very much, sir. Wishing you all the best going forward.
P.R. Hari
executiveThanks. Appreciate it.
Operator
operatorThanks. The next question comes from Parimal Mithani at Credential Investments. Your line is open.
Parimal Mithani
analystThank you for the chance to speak, sir. Every one of my questions has now been addressed. And sir, my congratulations go out to you and your team on that wonderful set of numbers.
P.R. Hari
executiveThanks. Thanks, Mr. Mithani. And we appreciate you saying that. It means a lot to us.
Parimal Mithani
analystAppreciate that, sir.
Operator
operatorThanks. We’ll take the next question from Vikas Kasturi at Focus Capital. Please go ahead.
Vikas Kasturi
analystGood evening, sir. First off, congratulations on a fantastic financial year. And thanks as well to you, sir, Amodar, for answering every question so patiently and with such detailed responses. Thank you, sir. Sir, I just had one question. So regarding the ships we are going to deliver, is there any retention amount the client will withhold as a warranty or a guarantee kind of a thing?
P.R. Hari
executiveThank you — I appreciate that. And under the contractual terms, there is a certain percentage fee on washbuilding orders, and most of the orders are washbuilding orders. Across all these contracts, per the DAP, which is the basis on which these contracts are formulated, there are various stage payments. One of those stage payments is the retention of, I think, 10% of. 10% of the project cost until completion of the guarantee refit, which in the conventional sense, the guarantee, if it will happen one year, it means we are bound to provide one year of guarantee. And once the guarantee period is completed, the ship will undergo a guarantee, and on completion of that, the retained amount will be paid.
Vikas Kasturi
analystUnderstood? And roughly speaking, this 10% is held back across every ship and all of your platforms, right?
P.R. Hari
executiveApologies. So that 10% — yes, yes, yes, that's right. It's strictly in line with the DAP, and it applies to every order currently being executed. And in my view, this holds for all shipyards carrying out similar orders.
Vikas Kasturi
analystOkay, sir, thanks very much, sir.
P.R. Hari
executiveThanks. Thanks a lot.
Operator
operatorThanks. Our final question comes from Vaibhav Dalal of Niveshaay Investments. The line is yours — please go ahead.
Vaibhav Dalal
analystThank you very much, sir, for taking my question. Once again, I have a question about one very specific product that is used in your shipbuilding. These are the bulbars that go into building the hull of a ship. So I just want to understand how many bulbars are needed for the overall making of a ship, both in terms of volume as well as in terms of the value of the ship?
P.R. Hari
executiveThat's a really intriguing question, and honestly it's quite an unusual one for me to be dealing with. I've been going around to analyst and investor meetings — this is actually my 12th one in a row now. Yeah, the 12th or 13th meeting in this stretch. Really interesting question. Bulb bar. Because I have a shipbuilding background, I'm in a position to answer it. Roughly 10% of the total steel is involved. So if we're talking about how much the ship weighs, or its displacement, I'd frame it like this. Take a ship — let's say we're discussing a 3000 ton vessel. When you refer to a 3000 ton ship, the steel weight would come in at about 2000 tons, somewhere between 1800 and 2200 tons, and that depends on which grade of steel gets used. If it's a warship, warships use a specific grade of steel, and that's actually public information — PMR249 Alpha Steel is what's employed. So this can vary based on size, type, and the kind of platform. At times thin steel goes into the hull. At other times thick steel is used. All sorts of thicknesses go into a given ship. So if you want a ballpark figure, it works out to 1800 to 2000 tons of steel in a vessel displacing 3000 to 3300 tons.
P.R. Hari
executiveThe balance weight is attributable to the equipment and systems — that means the plumbing, the main propulsion system, blah blah blah. Now, inside this, inside this 2000 tons, roughly 10% is from the bulbars.
Vaibhav Dalal
analystThanks. Understood, sir. Yeah. And for my final question, sir: where exactly do you get these bulbars from? Are you bringing them in from abroad, or are there domestic suppliers you purchase these bulbars from and have already procured? Yes, and on the last point. Yeah, sure.
P.R. Hari
executiveGo ahead, please. Please proceed. You have a question.
Vaibhav Dalal
analystSo the final piece of what I want to ask is this: given that 61 warships are being built here in India — of those 61 warships, 60 are under construction at Indian shipyards — I'd just like to get a sense of whether procurement for these bulbas has already been completed with the shipyards, or whether that process is still underway. That's really what I'm trying to understand.
P.R. Hari
executiveAlright, I’ll tackle that question from a wider angle. Shipyards function as platform integrators — really significant platform integrators. We procure equipment; everything gets sourced, from steel to what Finsey referred to as bulbars, to piping material, to items as small as cables, cable clamps, cable trays, to whatever you can think of, up to the two major equipment items. As platform integrators, we work with customers — the Indian Navy or the Indian Coast Guard — who carry out capacity and capability assessments of suitable firms and make them eligible in certain equipment categories. Take, for instance, the main propulsion system, main propulsion engines. Maybe, for example, for a project, four firms might be shortlisted based on capacity and capability. In the same way for steel, the Navy or the Coast Guard decides which qualified sources steel should be procured from. They conduct a capacity assessment, with the customer coming to the bulbar — that’s your specific question about bulbars. Bulbars aren’t procured indiscriminately either. They must be obtained from sources — more precisely, the manufacturer — that were qualified by the customer. That’s the name. Shipyards receive this list, then go through a procurement process and source from those firms. So, since you raised this question, any firm that considers itself capable of manufacturing bulbars — to address your specific query — can register itself with the Navy, get a capacity assessment completed, get that formally communicated to the shipyard and to the Navy, and the shipyards would definitely purchase from them.
Vaibhav Dalal
analystThank you. And just as a quick follow-up, sir, do you have any suppliers that the Navy has approved for this? For instance, are there Indian suppliers, or suppliers from —
P.R. Hari
executiveRegarding the question about Indian suppliers — yes, we do have suppliers in India.
Vaibhav Dalal
analystIs there any particular name that comes to mind for you, sir?
P.R. Hari
executiveWe won’t be in a position to respond to that. So if there’s a particular query you have, my suggestion would be to put that specific question to Navy. They can give you complete clarity regarding which firms are qualified to build—sorry, to fabricate the bulbas. That would give you a clearer answer than anything I could offer during an investors meeting. Sure, sir. Thank you very much, sir. And thank you very much for taking my question. Have a great day. My pleasure. Thank you. Thank you.
Operator
operatorThank you. Ladies and gentlemen, since we need to keep an eye on the clock, that question was our final one. At this point, I'd like to pass the conference back to management so they can offer their closing remarks.
P.R. Hari
executiveThanks, Navya. And thanks to Gaurav from Concept IR for putting this conference call together. I want to express my genuine appreciation to all my analysts and investor friends who took time from their very busy schedules to listen to what I had to say and also to ask such interesting questions, covering everything from profit margins to Bulbas. Thank you, and I look forward to the next time we meet. Thank you.
Operator
operator<<operator_signoff>>.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Garden Reach Shipbuilders & Engineers Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Garden Reach Shipbuilders & Engineers Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Garden Reach Shipbuilders & Engineers Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.