GMR Kamalanga Energy Limited (533148) Earnings Call Transcript & Summary
February 17, 2020
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to the analyst call hosted by JSW Energy Limited. We have with us the senior management of JSW Energy, represented by Mr. Prashant Jain, Joint Managing Director and CEO; Mr. Sharad Mahendra, Director and COO; and Mr. Jyoti Kumar Agarwal, Director of Finance. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Prashant Jain [indiscernible]. Over to you, sir.
Prashant Jain
executiveThank you. Good evening, ladies and gentlemen. Today, JSW Energy has signed share purchase agreement with GMR Energy for acquiring 100% stake in their subsidiary, GMR Kamalanga Energy Limited, which is owning and operating 1,050-megawatt thermal power plant in Orissa. This asset fits in our stated strategy. It is a textbook case wherein the asset is having close to 85% of its capacity tied up for a long-term PPA, diversified both PPA portfolio with PPAs with Orissa, Haryana and Bihar. It operates a pit-head plant with a dedicated railway line from the nearest railway station, which ensures low variable cost, which makes this power to be dispatched on priority in merit order dispatch and also minimize receivable or offtake risks. The -- out of the overall total power PPAs, the average fixed cost is -- which will be realized in the current financial year is INR 1.61, and average variable cost will be to the tune of INR 1.50 to INR 1.60, including the coal pass-through, which means the average power cost will be at the CTU periphery between INR 3.10 to INR 3.20, which makes it in the bottom quartile of the purchase basket for the respective DISCOMs. That's why it fits in our stated strategy. It also has 150-megawatt of the open capacity, which offers us the further upside potential, which requires new FSAs close to the quantum of 850 -- between 800,000 to 850,000 tons per year, out of which 400,000 tons FSA has been secured in recent SHAKTI auctions 2 weeks ago. This asset is also -- has been able to lock 150-megawatt of the capacity as a L1 basket bidder in recent Pilot II Scheme. This acquisition will enable us to expand our geographical footprint in Eastern region and also help us to diversify our asset portfolio across fuel sources and off-take arrangements. If we look at the transaction value, the deal has been done at an enterprise value of INR 5,321 crores. The asset is having a target, outstanding debt of INR 3,951 crore and balance consideration of INR 1,370 crores will be payable, of which INR 755 crore will be payable upfront subjected to the working capital adjustment, primarily by means of debt and internal accruals and balance INR 615 crores will be kept as a holdback amount, which will be payable on certain milestones and shall also be paid or funded through debt and internal accruals. This asset will be having a base EBITDA of close to INR 900 crores, with a upside potential of another INR 150 crores. At INR 900 crore base EBITDA, the asset is at -- valued at 5.9x EV/EBITDA multiple. There are other various potential upside, which JSW Energy will be able to bring in. One is reduction in O&M cost, and second is tying up the untied capacity and tying up the fuel supply linkage because when you buy coal in the open merchant market or forward e-auction or spot auctions, your fuel price is higher. Therefore, the dark spread is lower. But once you tie up a long-term PPA as well as a FSA for that, your fuel cost goes down, which is in this case is close to INR 1.55 to INR 1.60. And if you are selling power at a -- even at a low cost at CTU bus, then your dark spread improves. There is also a upside opportunity available for certain provision which is being made on a regular basis on account of environment management fund as well as the electricity duty, which is paid on the auxiliary power consumption or the units sold outside Orissa. That amount is close to INR 60 crores per year, which is not considered in this base case EBITDA, which is after making that provision. This amount is accruing as a free cash flow, and we see that these are the industry-wide dispute, which is on a very strong footing and at some point of time, they will be decided in the favor of the thermal generators. So that EBITDA can be recognized at that point of time. But on a free cash flow basis, that will be also coming up. With this, I conclude my opening remarks, and we are happy to take any questions and answers if you are having. Thank you.
Operator
operator[Operator Instructions] The first question is from the line of Mohit Kumar from IDFC Securities.
Mohit Kumar
analystYes. Can you hear me?
Prashant Jain
executiveYes, please.
Mohit Kumar
analystYes. Congratulation on the acquisition of the asset at an attractive valuation. Sir, my first question, is that the -- you said that INR 6.2 billion is contingent on achieving certain milestones. Can you please quantify those milestones?
Prashant Jain
executiveJyoti, you would like to?
Jyoti Agarwal
executiveYes. So look, the key milestone here is a particular dispute on the target asset with one of the contractor. And the holdback amount as well as the deferred consideration is basically linked to that. There are some time-based payments also which are there. But ultimately, if the dispute is not resolved with the passing of time, then those time-based milestones also get deferred till the time the dispute is resolved. This is the main one. Then there are some other contingent receivable and contingent payable, which are basically linked to various tariff orders as well as true-up petitions which are lined up, which will happen over the course of the next 18 to 24 months. But those are the minor components. The major one is the particular dispute with the project contractor, and the payment is to be made only after the dispute is settled with the contractor. And based on the nature of settlement, the amount will also be decided.
Mohit Kumar
analystSo what is the disputed amount with the contractor?
Jyoti Agarwal
executiveSo the -- it's a complicated dispute, to be honest. And based on how the dispute is settled, the amount could range anywhere between the amount that we are holding back to a little bit higher or to a little bit lower as well. The way the SPA is constructed is that the entire liability on account of that contracted clean is actually to the seller's account other than a certain amount up to INR 315 crore which is to the buyer's account. So what that means is that if the liability is up to INR 315 crores, then the buyer pays. If it is higher than INR 315 crores, then the seller actually is responsible for the liability. Now the amount of holdback that you can see is actually INR 615 crores, so which comprises of INR 315 crores, which, anyways, we are responsible as buyers, plus another deferred consideration component of INR 300 crores. This is basically to ensure that there is enough holdback amount available should the dispute amount finally rise higher than the INR 315 crores, right? So depending upon how the dispute is actually settled, the amount, in our opinion, should be around the INR 500 crore, INR 600 crore mark, which is equal to the amount that we have held back.
Prashant Jain
executiveBut our purchase consideration -- our EV in all situation remains limited to INR 5,321 crores.
Operator
operatorThe next question is from the line of Sumit Kishore from JPMorgan.
Sumit Kishore
analystMy first question is, in relation to the historical performance of Kamalanga, so in FY '19, Kamalanga's EBITDA was INR 7.4 billion and 9-month FY '20 has been reported at about INR 5.6 billion. So basically, there appears to be a bit of pickup in FY '21 to reach your base case EBITDA of INR 9 billion. Could you help us reconcile the same?
Jyoti Agarwal
executiveSo Sumit, a good question. If you look at our base case EBITDA estimate for FY '21, you will see that there is a contribution from open capacity, which is almost INR 125 crore. Now you would know that GMR is quite stretched at the moment really. It will not have the ability to raise debt at any of their company levels other than probably the airport business. And for this asset also, they are constrained to have working capital line, for which they are not able to buy coal to be able to feed through to the merchant capacity. So this entire merchant capacity accrues to 170-, 175-megawatt is currently lying idle. On top of it, even the contracted capacity, they are not able to run it completely, primarily because of scarcity of working capital. So the delta, as you can see, from a, let's say, average EBITDA of about INR 750 crores, INR 775 crores, which they are anyways achieving, just this INR 120 crores, INR 130 crores of open capacity takes you to the INR 900 crores. So the base cases are all pretty robust. It does not depend on any sort of leaps of faith which are stretched leaps of faith. Essentially, we believe that in our hands, the working capital lines will be there. We will be able to get those lines revised and raise the right kind of money to be able to buy-in and normalize the working capital. And as Prashant was mentioning, this is a low-variable cost plant because of being close to the coal mining region, right? So even taking coal under the auction route should not lead to your coal cost higher than INR 2. It will actually be lower than INR 2. And you can see that even in these sort of pretty average and sort of downbeat times, the average merchant tariff is around the INR 3 mark. So about INR 1 dark spread on the open capacity is a very reasonable assumption. And we believe that will be the major part of the swing. If you look at the potential EBITDA part, right, which is the INR 1,050 crore mark, here, again, there are 2 elements primarily. One is, in our opinion, a low-hanging fruit. The plant today has an O&M cost structure, which is not aligned with, let's say, the JSW O&M cost structure. So we believe that we can easily shave off close to INR 2 lakh, INR 2.5 lakh per megawatt, maybe about INR 25 crores, INR 50 crores from the O&M. This, we believe, should happen very, very quickly, maybe 2 to 4 months into the -- into running the project. The other one is the PPA-linked upside. We believe that because the variable cost under linkage-based coal is even lower, close to INR 1.50, it should be possible to tie up either a short-term or long-term PPA with a dark spread of close to INR 1.75 to INR 2, and so that would be another INR 125 crore upside, making it to a potential of INR 1,050 crores. Now this INR 125 crores could take a little bit of time. But we believe that the INR 900 crore base plus maybe a INR 25 crore to INR 50 crore upside should be possible 6 months into owning the asset.
Sumit Kishore
analystSure. Just a couple of follow-ups on what you said. So if I back calculate and look at the contribution you have from open capacity, it appears that on the 150-odd megawatts, you have taken a fairly high plant load factor, I mean, upwards of 90% or so?
Jyoti Agarwal
executiveYes, it's actually 170-megawatt and...
Sumit Kishore
analystYes, after auxiliary. Yes.
Jyoti Agarwal
executiveYes, yes, exactly. So we have taken 90% PLF for the merchant fees. And on top of it, we've taken about 7% off. So the net PLF will be close to 84%, 85%. I think that's not a very unreasonable assumption given what we are doing in some of the other plants where we are able to sell under merchant, yes.
Sumit Kishore
analystOkay. And the provision for ongoing disputes, this is like a onetime item and will stop in FY '22 or how does it...
Prashant Jain
executiveSo basically, it's a -- it's not a onetime item until the dispute is settled. That provision will continue to happen. But we will be having that free cash available with us until that time. And we are having a clear visibility because the way we look at it, this is specific to Orissa state. And you are talking about that electricity duty is to be payable on the auxiliary power consumption for the unit which are exported out of the Orissa state. Whereas the state, if you look at the -- it is on the consumption point and power generators are not consuming electricity. So that's the point number one. Second thing is there is an environment management fund which has been created and under the act, central government can only put this kind of cess or duties, which Orissa state has, levied came out with a notification that for every power generation, there has to be a close to INR 0.06 per unit for -- to be payable for any electricity which is sold outside the state. With -- both the cases are specific to Orissa state, we believe that these are the ultra-virus cases. This is applicable for all the generators which are present in the state of Orissa and at various stage of litigation. We believe these cases will be settled in the favor of the generators. But as a prudent accounting practices, we will be making the -- we will continue to make the provision. But this money is not deposited with the state authority. So this is a free cash available. So the INR 60 crore is available for repayment of debt or the other various purposes for the period. But we believe that there is a strong case that will be coming in favor of the power generators.
Sumit Kishore
analystSo the project has made how much cumulative provision against this dispute so far? And has there been any cash outflow on account of that?
Prashant Jain
executiveNo, there is a stay granted on this particular dispute. So they have made a regular provision every year and -- in the balance sheet. And they are not depositing any money.
Sumit Kishore
analystThey're not depositing any money. Sure. Sir, just last question. You mentioned in your presentation some quantum of past disputed receivables net of contingent liabilities. So what is A and what is B, so what is this amount coming to?
Prashant Jain
executiveThere is a visibility what we are seeing that it will be a net positive receivable. And at this point of time, in our enterprise value, we have not considered because there are various receivables towards the coal pass-through billing. Recent Act 10 orders have settled all these cases in favor of GMR Kamalanga. And based on the receivables and payables, there will be a positive cash flow towards the GMR Kamalanga asset, which will accrue to JSW Energy because both the things belong to JSW Energy pursuant to the transaction. So there is a potential upside for us, whereby this enterprise value of INR 5,321 crore will go down and our EV/EBITDA multiple will further go down.
Operator
operatorThe next question is from the line of Abhishek Puri from Axis Capital.
Abhishek Puri
analystSir, thanks for the opportunity and congratulations for closing this deal. Just quickly on the amount that you mentioned that has been provided for environmental management fund, is that INR 50 crores, you said?
Prashant Jain
executiveSo it is every year different. For future, we are talking about it will be to the tune of INR 60 crores because it is depending upon the units which are exported out of the Orissa state. So for the past years, it has been provided in the range of INR 40 crores to INR 55 crores every year because depending upon the kind of export. On a normative availability basis and normative PLF basis, what we have calculated, this amount will be close to the tune of INR 50 crore per year next year -- next financial year onwards when it is under the management of JSW Energy because the asset will be running full. That's the quantification.
Abhishek Puri
analystSo in INR 900 crores, this INR 60 crores is not included?
Prashant Jain
executiveThat's right. And also, the potential upside also this INR 60 crore is not included.
Abhishek Puri
analystRight. Okay. INR 150 crores also does not include this INR 60 crores?
Prashant Jain
executiveThat's right.
Abhishek Puri
analystOkay. In terms of the total amount that we have paid INR 5,321 crores that we have agreed for, does this include the amount to be spent on environmental management for NOx and SOx solutions?
Prashant Jain
executiveNo, that will be over and above that. But then based on that, we will be getting the change in law.
Abhishek Puri
analystOkay. In terms of the debt that is transferred, so INR 3,951 crores is what you mentioned, right?
Prashant Jain
executiveYes.
Jyoti Agarwal
executiveIs the asset on the...
Prashant Jain
executiveThis is the term debt on the target asset.
Abhishek Puri
analystOkay. And how much is the working capital debt in this?
Jyoti Agarwal
executiveSo it's a moving number. The final number will be at the time of closing. But it is, on an average, about INR 175 crore to INR 200 crore, but that will be the working capital adjustment to be made, like from the balance sheet amount.
Abhishek Puri
analystOkay. Okay. So that INR 175 crores will be deducted from this INR 5,321 crores?
Jyoti Agarwal
executiveIt will be a part of the working capital adjustment. So the net working capital will have a negative INR 175 crores if there is a -- the working capital debt is that amount.
Abhishek Puri
analystRight. Okay. And in terms of the PPA that have been mentioned in the presentation, sir, 263-megawatt, Odisha; Haryana, 334; and Bihar, 283. These are the net PPA numbers or gross PPA numbers?
Jyoti Agarwal
executiveThese are gross.
Prashant Jain
executiveThese are gross numbers.
Abhishek Puri
analystOkay. Because I remember reading in one of the CERC filing or petition that the Haryana PPA was 350-megawatt, right, or that has been changed?
Prashant Jain
executiveSo these are the correct number what we have given you.
Abhishek Puri
analyst334 is the gross PPA?
Prashant Jain
executiveYes.
Abhishek Puri
analystAnd just one more point. So the Odisha one had 2 separate contracts, right? So 263-megawatt was at -- or the 25% of the capacity was at a cost-plus kind of a basis. And balance, was there any quantity on variable cost also in this PPA?
Prashant Jain
executiveNo. No. If you look at our presentation, we have given the fixed cost also, and how we are going to get. And so all these PPAs are actually 2 parts. This Odisha 1 and Haryana and Bihar are Case 1 PPA. And balance life of PPA is 19 years, so.
Abhishek Puri
analystRight. Why I'm just trying to clarify because some of the other projects had this issue. So I was just trying to be sure.
Prashant Jain
executiveSo in this asset, it's not like that.
Abhishek Puri
analystOkay. Understood. And lastly, just one more point on the funding mix you said will be from internal accruals and debt. Any breakup that you can provide on this?
Jyoti Agarwal
executiveWell, it will depend upon the final amount. As you can see that the target debt is completely taken over. Now against the INR 755 crore that we need to pay as balance consideration upfront, there will be a net working capital adjustment. Our sense is that it could be in the range of between INR 150 crores to INR 250 crores. So the net consideration that we have to pay upfront from an equity point of view will be around INR 500 crores, INR 550 crores, right? So I do have enough capability to be able to fund this either through my cash equival or through debt taken at the top core. So we'll look at that when the closing happens and take a call at that point of time.
Abhishek Puri
analystRight. And lastly, in terms of the holdback amount of INR 650 crores. What is the long short -- long stop time line here, I mean, in terms of resolution of this contractor amount as well as the balance receivable and payable amount?
Prashant Jain
executiveIt's totally ring-fenced in terms of the performance. There are certain expected time lines. But if those time lines are not met, then this holdback amount will continue.
Abhishek Puri
analystSo the time line is 6 months, 1 year? I mean -- and what happens if, say, 1 year has passed?
Prashant Jain
executiveAs you know, these are the legal disputes, it may take longer time. That's why it will continue until the disputes are settled or we get a complete confidence and reasonability, we will continue to hold back this amount.
Abhishek Puri
analystOkay, okay. So there is no fixed time line as such?
Prashant Jain
executiveYes, it is -- the time line is that dispute has to be resolved to our satisfaction.
Abhishek Puri
analystOkay. And if it is not resolved to the satisfaction here and supposedly, the amount which has to be paid to the contractor is say INR 415 crores. So do you pay INR 315 crores or -- and the seller pays INR 100 crores, the balance on that?
Prashant Jain
executiveSee, our liability is limited to INR 315 crores for that particular contractor liability. That's why we said that our enterprise value is constant and limited at INR 5,321 crores.
Abhishek Puri
analystFair enough.
Prashant Jain
executiveAnd any other liabilities which are coming on that account is to be payable by GEL. And for that comfort itself, we have increased the holdback amount by additional INR 300 crores so that in case there is anything happening more than that, we are having at least that much of holdback amount and which we'll continue to hold back until the dispute is settled.
Abhishek Puri
analystSo if I understand this correctly, INR 305 crore is the holdback amount that you will continue until the dispute is resolved and the balance amount INR 315-odd crores, which is remaining, will have to be paid on a time basis?
Prashant Jain
executiveNo.
Jyoti Agarwal
executiveLet me explain, Abhishek. The INR 315 crore is an explicit holdback amount against the liability. The additional INR 300 crores has 2, 3 components. Some of it is time-based, right, some of it is contingency-based. But in any case, this amount, even if the time milestone has been achieved, if the contractor settlement has not happened, we will continue to hold this. So for all practical purposes, the weakest link in the chain, as they say, is the contractor settlement. And we will hold back this entire INR 615 crores till the settlement with the contractor happens, irrespective of whether the time milestone has been reached or not. So for example, if, let us say, in 6 months of time, we -- the contractor claim is settled, right, then some portion of the INR 300 crores, which is time-based may not payable, it will be payable only when the time milestone arrives. But if the time milestone has been achieved but the contractor settlement has not happened, we will not pay that amount till the time the settlement with the contractor takes place. Yes? I hope it's clear.
Abhishek Puri
analystVery clear, very clear. Absolutely clear on this. And just as a -- just to complete the loop here. If the dispute does not get resolved and keeps on dragging in the court for, say, 5 years' time, the amount will not be paid?
Prashant Jain
executiveWe continue to hold back.
Operator
operatorThe next question is from the line of Rahul Modi from ICICI Securities.
Rahul Modi
analystSir, congratulations on the completion of the acquisition. Sir, just a couple of questions that I had. Firstly, with regard to the tariffs that you mentioned in the PPT, are these taking into account all the recurring change in laws and everything which was pending historically due to the cess and other things which had come in for coal and other things? So that is the final amount that will be billable?
Prashant Jain
executiveIt is the variable cost, if you're talking about. This is including the current change in law and SHAKTI DISCOM. However, the coal pass-through is not included into that. But as a thumb rule, I can just give you on an average, will be around INR 0.11, INR 0.12 you need to add for coal pass-through. Because coal pass-through is different for different year, but you can say reasonably between INR 0.11 to INR 0.13 will be the coal pass-through which will be there because that orders have not yet been implemented. They have recently come in, in the last 4 weeks' time.
Rahul Modi
analystOkay. So this will be regarding the imported coal usage or any other source?
Prashant Jain
executiveCoal pass-through is from any source.
Rahul Modi
analystAny source, yes.
Prashant Jain
executiveThis is -- yes, this variable cost is based on the coal-linkage coal. Any deficiency in the coal-linkage coal because of the quality or quantity has to be compensated by the -- from the -- any other source which has been -- it has been sourced. For that, necessary CERC orders came in and which have been now settled by Act 10 in the -- in case of various orders, which have been awarded in favor of GMR Kamalanga. That means that this asset will not have any under-recovery for the clients towards this PPA on account of the fuel cost.
Rahul Modi
analystRight. Okay. Understood...
Prashant Jain
executiveBecause of the deficiency in the quality or quantity of coal supply component, yes.
Rahul Modi
analystSure. Sir, secondly, on -- can you help us if there is any accumulated losses which can lead to tax savings going in the future once -- because historically, I believe we are showing profit, but the interest cost and all is quite high. So anything on that?
Jyoti Agarwal
executiveThere are some accumulated losses, which should provide us the tax shield at least for the first few years.
Rahul Modi
analystOkay. First few years would be 2, 3, 4? Any thoughts on that?
Jyoti Agarwal
executiveWe will let you know once we have been able to get a final evaluation done. But there is a sufficient amount of carryforward losses which will give us tax shield for a few years, yes.
Rahul Modi
analystOkay, okay. And sir, one more question I had was on the incremental INR 350 crores. Any thoughts on that? What would the incremental CapEx on a ballpark number once you decided on installing that unit and any major land acquisition or anything that needs to be done?
Prashant Jain
executiveNo, no. In fact, no acquisition is to be required to be done. And there is a -- balance of plant is also ready for that. And these are -- did a rough estimate lower than INR 3 crores per megawatt capacity can be commissioned.
Rahul Modi
analystOkay. And anytime soon you're looking to start on that?
Prashant Jain
executiveOur first focus will be to integrate the asset and then to tie-up the untied capacity and to achieve the targeted upside potentials. And as and when we find the right opportunities, this option could be exercised.
Rahul Modi
analystRight. Sir, in terms of the refinancing, I'm sure you would be going in for -- and so it will be with the same lenders or a new set of lenders in this?
Jyoti Agarwal
executiveYes. So we are taking over the debt. And based on the new credit assessment post the takeover of the asset by JSW, we will be approaching the lenders for repricing the loans accordingly.
Rahul Modi
analystOkay. And obviously, you will be looking at some moratorium as well?
Jyoti Agarwal
executiveI think we are comfortable with the repayment schedule of the debt. I don't think we have an issue with that. It's just that the pricing of the loans are a bit high right now being GMR asset and in B-rated category. So we'll only be looking at repricing the loans and not really tinkering so much with the repayment schedule.
Rahul Modi
analystRight. Sir, and with the 150-megawatt Pilot II Scheme where we've got LOI. Sir, what is the time lines you're expecting that to commence if once it's signed?
Prashant Jain
executiveSee, this Pilot II Scheme has recently been concluded and then now we have to see how the DISCOMs are working on that side. But you will get the visibility in next 2 to 3 months' time frame. But given the tariff which has been discovered, I think it is very, very attractive tariff for the distribution companies because the merchant tariff on a -- for the -- such a washout year for 2018-'19 is close to the INR 3.05, INR 3.10. And it has been at the time when there was a very poor economic activity, and then there was a power demand, degrowth was taking place. At that point of time also, the power tariff was INR 3. And this tariff of INR 3.26 is a 3-year fixed tariff without any kind of a change in law on -- for coal prices or anything. So it is very attractive tariff. And I think DISCOMs should lap up this. But we'll be able to get a good visibility between next 6 to 12 weeks' time frame.
Operator
operatorThe next question is from the line of Santosh Hiredesai from SBICAP Securities.
Santosh Hiredesai
analystSir, many congratulations on the deal. Just couple of questions. You've given us INR 940 crores as the contribution from the existing long-term PPAs. I'm just trying to understand the trajectory of this number because we really don't have the tariffs going into the next 15, 18 years. I just want a broad sense as to how this will behave, let's say, going into the next 2, 3 years? Will it keep decreasing by, let's say, 2%, 3%? How should one look at this contribution?
Prashant Jain
executiveIt's a -- as per the standard bidding document Case 1 PPA because it goes down by 2% and certain component of O&M goes up by certain percentage of WPI index.
Jyoti Agarwal
executiveSo it will be going up.
Prashant Jain
executiveYes. But effectively, it is...
Jyoti Agarwal
executiveIt will be going up. Basically because all the components is going up. So because the inflation is not a prominent comparator.
Prashant Jain
executiveYes, but, I think, our team will be able to provide you. If you can connect off-line, they will help you to provide this detail. But it is typical like Case I PPAs, but...
Santosh Hiredesai
analystMy understanding was that this was bit under the previous regime, right, even before the new bidding documents came in where you actually had to quote tariffs for 25 years as such? I'm sure there will be some sense of how this will pan out, let's say -- anyway, I'll take it off-line with Nitin, so that shouldn't be a problem. Sir, second question I had was -- hello, am I audible?
Prashant Jain
executiveYes, yes, please, please.
Santosh Hiredesai
analystYes, sorry. So Bihar, for the PPA, you said it is INR 1.52, but I was just looking at the tariff orders, it's INR 1.03.
Prashant Jain
executiveVariable cost is INR 1.52.
Santosh Hiredesai
analystCorrect. So variable you say is INR 1.52, but I was just looking at the tariff order, it says INR 1.03. And even the merit portal, of course, it's now not showing up, but I recollect looking at it in December, it shows INR 1.03 only. So is there something that I'm missing here? Is it that you're just billing them INR 1.03 and...
Prashant Jain
executiveYes, yes, because this order -- this is including change in law, it is including that -- whatever the change in law with claims which have been approved. And on top of it, there will be the coal pass-through which will be also coming up.
Santosh Hiredesai
analystOkay. So this INR 1.52 includes all those things, but currently it is not billed to the DISCOMs at this rate?
Prashant Jain
executiveIt is billed.
Santosh Hiredesai
analystOkay, okay. And sir, last bit. So again, you've got INR 125 crores as contribution coming in from...
Prashant Jain
executiveBut I think, you should look at this way. See, with the recent all orders which have been coming, there is no coal variable cost under recovery in this asset. So whatever is my fixed cost recovery I will be getting that subjected to the -- we get a proper -- we have a complete working capital and we are making unit available for scheduling of the power. So that's why it is very important that -- so far this asset was not being made available completely because of the working capital deficiencies, number one. That will go away and then the contribution of INR 940 crores will be very clearly visibly coming. Number two, because of the various orders come recently in last couple of weeks on the Act 10, all tariff disputes for under-recovery on account of variable cost or coal pass-through have been settled. And that's why we say that there will be no under-recovery in the variable cost.
Santosh Hiredesai
analystSure. Noted, sir. The -- second bit, again, going back to the last slide, you talk about INR 125 crores contribution coming in from the open capacity and INR 125 crores more if we get a linkage coal. But I was just trying to get a sense if this medium-term tariff, we were to go by that which was discovered, and you mentioned that with linkage coal your cost of generation -- variable cost generation is in the range of about INR 1.30 to INR 1.50, in that range. So do you foresee -- I mean, this incremental INR 125 crores coming in now because you've locked in that tariff at -- yes, just wanted to get your sense on that as to what is the arrangement right now for coal and so on and so forth.
Prashant Jain
executiveYes. So long-term PPA when we talk about, we look at this way, that if you want to -- in a normative case, we have considered a INR 1 dark spread. But in the long-term PPA consideration, we consider INR 2 dark spread. At a INR 1.30, INR 1.50 kind of a variable cost, if you are doing a -- at least CTU bus, if you are selling power at INR 3.40, INR 3.50, you will be making INR 2 dark spread, okay? And that's where the situation is changed.
Jyoti Agarwal
executiveBihar is already at INR 1.87.
Prashant Jain
executiveYes. And in case of like you look at Bihar, the fixed cost is INR 1.90, INR 1.87 for the first year -- for this fifth year. So INR 3.40 CTU power is delivered at INR 3.90 to the distribution company which is in the bottom quartile of the power, and that's why we are taking. If you consider a Pilot II Scheme, the tariff is INR 3.26 and the coal linkage, you will be having INR 1.50. So you will be making close to INR 1.75 contribution. So you will be able to recover that 75% or 80% of a upside with this Pilot II Scheme. But you -- we would like to do a PPA for balance 25 years or 20 years life of the plant. And that's where we are envisaging that we will be looking for a new PPA.
Santosh Hiredesai
analystSure, sure. Basically, we don't have to bid for these linkage coal is it, sir, it's at notified price that will be made available under the current medium-term PPA. Is that understanding correct?
Prashant Jain
executiveNo, no, no. We have to make a bid for the coal linkage. We have already secured 50% of the coal linkage that means out of the balance 150-megawatt of the open capacity. For 75-megawatt capacity, we have already secured in the first week of February. There was a coal linkage. And from the Talcher area, we have already secured for 75-megawatt. Balance 75-megawatt, we are envisaging in next 6 months' time frame. So until that time, we will be buying coal in the advanced e-auction because these are the mines -- pit-head mine plants. And one more thing which is very, very important for you to take a note that maximum capacity is coming up in the MCL region. In next 3 years' time frame, 100 million ton coal production will be increased in the MCL region. Second point is maximum capacity for the commercial mining is coming in the MCL region. Therefore, it is fitting in our strategy for both Ind-Barath as well as this that we are having a full security of the fuel supply and the visibility is there for the future. Also whatever coal is the shortfall, you can secure at a very low cost because the coal supply will be the maximum.
Operator
operatorNext question is from the line of Parag Thakkar from ICICI Prudential.
Parag Thakkar;ICICI Prudential;Portfolio Manager
analystCongratulations for the deal. I just wanted to ask about the payer -- receivable payment cycle in Orissa? How is the DISCOM positioned? And overall DISCOM payment situation for the entire country, I just wanted your view.
Prashant Jain
executiveAs far as this asset is concerned, this asset has been securing, while it was for GMR, they have been getting the advance for their working capital management. So there are no delays in the payment other than the disputed receivables because it's a very low-cost power for them. If you look at Orissa, the delivered power cost is INR 3.11 or INR 3.20; and Haryana, it is below INR 3 is the CTU and including that will be -- it will INR 3.30 will be the delivered cost to the power for Haryana. So it's very attractive for them. And Haryana has been giving advance to them in order to make this power available to the DISCOM. And if you look at the country situation, what is happening is after the recent order by the Ministry of Power, the current payment has become on time for the general as a industry. However, the past receivables have not been cleared and they are to the tune of INR 92,000 crore. The situation is becoming worse for the renewable power because it's a must schedule power. And there, the payments are getting delayed more and more, and that's what is the trend which we are observing. For thermal generators, the current bills are being paid on time after the LCs have been put in place. So that's the situation as the industry per se.
Parag Thakkar;ICICI Prudential;Portfolio Manager
analystCorrect, sir. Okay, okay. And sir...
Prashant Jain
executiveBut we believe the only method by which you can mitigate this kind of a risk is only, one, it should be the low-cost power and should be the bottom quartile for the purchase basket of the distribution company. Then only you will get a merit order dispatch and then only distribution company will have a threat that you will discontinue the power supply and serve a default notice and offer that power to some other DISCOM. So that is -- and that is what is the standard strategy of JSW Energy.
Operator
operatorThe next question is from the line of [ Puneet ] from IDFC.
Unknown Analyst
analystYes. I have 2 quick questions. One is, what is the expected amount of working capital adjustment that you are looking for? And second is...
Operator
operator[ Puneet ], I'm sorry to interrupt, but we can't hear you very clearly. Request you to use the handset.
Unknown Analyst
analystI'm saying that what is the expected amount of working capital adjustment?
Jyoti Agarwal
executiveSo the working capital adjustment would happen closer to the closing date, but we are anticipating a range between INR 150 crores to INR 250 crores as a negative working capital adjustment. So the working capital will actually be negative, liabilities being higher than the assets.
Unknown Analyst
analystOkay. Okay. And the second question is that to whose account the EBITDA will accrue from today? That is the share purchase agreement execution date till the actual date of transfer of share. Will it be to the account of GMR or will it be to the account of JSW?
Prashant Jain
executiveYes. So it is to the account of GMR, but there is a certain date by which if the closing can happen, then we will -- we can take the EBITDA from that date till the closing date on to our account. But for all practical purposes, till the time of closing, the profit and losses of the target asset belong to GMR. But there is a governance mechanism here, just so that you are aware, whereby all key decisions to be taken as far as the target asset is concerned will be in consultation and with our due approval so that we get alignment of objectives from today rather than from the time the asset comes in our hand.
Operator
operatorThe next question is from the line of Mohit Kumar from IDFC.
Mohit Kumar
analystYes. Sir, what is the -- how much of the pay receivables at the GMR Kamalanga that exist today? And is there any of the amount disputed as of now? And when do you expect all the amounts to come back to GMR or you? And how will this record in the sense whether the entire trade receivable will come to you or part of depending on is there any -- is there an amount which will go to GMR?
Prashant Jain
executiveNo, no. The receivable -- there is a -- there are certain receivables which are there, those are due and those are disputed receivables. And so they have been quantified and they belong to JSW Energy. And there are certain contingent liabilities also. As we mentioned that net of the contingent liability, these receivables will be a positive cash flow to JSW Energy, which we have not considered while we have announced our enterprise value at INR 5,321 crore. In all probability, this enterprise value will go down once we realize all this and settle all this receivable as well as the contingent liability. We expect, in next 6 to 24 months' time frame, all these things will get settled, and there will be a positive cash flow which will be coming towards that.
Mohit Kumar
analystBut how much are the trade receivables at December 31, 2019?
Prashant Jain
executiveDisputed one?
Mohit Kumar
analystNo, no, total amount.
Prashant Jain
executiveAs I'm saying that the receivables other than disputed are not due. It's a...
Mohit Kumar
analystIn the sense, what is the trade receivables at the end of third quarter?
Jyoti Agarwal
executiveWe will have to come back to you on that data.
Mohit Kumar
analystAnd secondly, sir, on the fuel side, you said that there is a 2.1 million ton of regular coal linkage and 1.5 million ton is the regular SHAKTI linkage. And then there's, again, 0.4 million ton. Is this additional which you've won recently in the second round of SHAKTI coal auction?
Prashant Jain
executiveYes, last one is that, that's pursuant to the open capacity for which we are tying up.
Mohit Kumar
analystNo, no...
Prashant Jain
executiveThat will be used in -- that 400,000 ton is the recent auction in SHAKTI in February this month. And that will be used for Pilot II Scheme or for future capacity tier.
Mohit Kumar
analystOkay. I understood, sir. And thirdly, there is a INR 4.1 billion of promoter debt on the entity, if I'm right. This completely will go away. Am I right?
Jyoti Agarwal
executiveYes. So the consideration -- the balance consideration includes the promoter debt as well. So yes, I mean, the way to look at it is a promoter debt goes away and the balance consideration is the equity consideration. Or if the promoter debt is paid and to that extent, the balance consideration goes down and the net balance becomes the equity consideration, yes?
Operator
operatorThe next question is from the line of Abhishek Puri from Axis Capital. We seem to have lost the line from Mr. Abhishek Puri. We move to the next question. The next question is from Mr. Ashutosh Mehta from Edelweiss.
Swarnim Maheshwari
analystThis is Swarnim. Just one question. So in the presentation, you have mentioned that you require couple of approvals from CCI, from DISCOMs and from Odisha also. Sir, just wanted to understand the time line, so when do we expect this transaction to get consummated?
Prashant Jain
executiveWe are targeting March 31, 2020.
Swarnim Maheshwari
analystOkay. So I mean, that implies by -- from 1st April, the consolidation should start actually?
Prashant Jain
executiveYes, we are striving for that.
Operator
operatorThat's the last question. As there are no further questions, this concludes the conference. Thank you for joining us [indiscernible].
Prashant Jain
executiveThank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete GMR Kamalanga Energy Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to GMR Kamalanga Energy Limited earnings transcripts and 248,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.