Godawari Power & Ispat Limited (GPIL) Earnings Call Transcript & Summary

November 6, 2023

National Stock Exchange of India IN Materials Metals and Mining earnings 63 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to Godawari Power & Ispat Limited Q2 FY '24 Earnings Conference Call, hosted by Go India Advisors. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Ms. Sana Kapoor from Go India Advisors. Thank you, and over to you, ma'am.

Sana Kapoor

attendee
#2

Thank you, Yousuf. Good afternoon, everybody, and welcome to Godawari Power & Ispat Limited Earnings Call to discuss the Q2 and H1 FY '24 results. We have on the call Mr. Abhishek Agrawal, Executive Director; Mr. Sanjay Bothra, CFO; and Mr. Dinesh Gandhi, Executive Director. We must remind you that the discussion on today's call may include certain forward-looking statements and must be, therefore, viewed in conjunction with the risks that the company faces. May I now request Mr. Dinesh Gandhi to take us through the company's business outlook and financial highlights. Subsequent to which, we will open the floor for Q&A. Thank you, and over to you, sir.

Dinesh Gandhi

executive
#3

Thank you, Sana. Good afternoon, everyone. And thank you for joining us, everybody, for today's conference call to discuss earnings results of Godawari Power & Ispat Limited for Q2 and H1 FY '24. Our financial results and earnings presentation is available on our website and on the stock exchange's website. I believe you had a chance to review the same. I will take you through the results post which we will have the question-and-answer session. I'm happy to [indiscernible] performance in Q2 FY '24 led by higher production volume of value-added products and the cost savings achieved through the reduction in power and fuel cost on Y-o-Y basis. First, coming on the quarterly results, the revenue for the quarter showed marginal decrease of 3% and 1% to INR 1,291 crores quarter-on-quarter and Y-o-Y basis mainly because of decrease in the realization of value-added products other than iron ore pellets. EBITDA margin increased 18% on quarter-on-quarter basis and 2% on Y-o-Y basis to INR 361 crores and to higher realization of iron ore pellet in Q2 FY '24 as compared to Q2 FY '23 and lower iron and fuel cost. Operating margin increased to 29.63% as compared to 19.90% in Q2 FY '23 and 25% in Q1 FY '24. PAT attributable to the owners increased to INR 257 crores, up 11% quarter-on-quarter and 52% Y-o-Y. PAT margin also increased to 20% for Q2 FY '24. The company continues to remain net debt free, the net cash on the balance sheet of the company as on 30th September 2023 was INR 650 crores. Coming on the half yearly number, revenue during H1 was lower by 9.6% as compared to H1 of the last financial year due to fall in realization across product range except pellets. However, operating margin was higher at 27% as compared to H1 of the last year at 25%. Despite fall in the sales realization across value-added product and lower production volume of iron ore from the captive mines. The higher operating margin was led by directly power and fuel cost in the steel division. Coming on the operational performance, I'm delighted to mention that GPIL has achieved the highest year production volume of steel billet, captive power generation, and silico manganese on a quarterly basis and sponge iron, steel billet, and power generation on half-yearly basis. Production volume for iron ore mining is -- was lower as compared to the guidance and also as compared to the last financial year, mainly on account of lower production volume in Boria Tibu mine owing to lower quality of iron ore grade in Boria Tibu mine, higher volume of [ BMT ] material resulting in higher cost of mining as compared to market price of iron ore. We have, therefore, decided to operate the Boria Tibu mine at a very low volume level. And in order to have -- to at least economical operations at the Boria Tibu mine, the company plans to [ upgrade ] the mining plant with enhanced mining capacity of 2.5 million tonne per annum and also install a beneficiation plant at Boria Tibu mine. The company has initiated process for revising the mining plant and also applying for -- plans to apply for environment approval to increase the mining capacity and for setting up the beneficiation plant. Therefore, the company would presently be focusing only on Ari Dongri mine to meet its captive requirement of iron ore, and accordingly, guidance is revised. The pellet iron ore requirement is sourced from the market, which is cheaper as compared to cost -- present cost of operations from Boria Tibu mine, and therefore, there is no impact of the reduction in the captive iron ore production on the overall iron ore cost consumed despite lower production from the mine. Further, iron ore volume during the quarter was also impacted by the [ prolonged ] monsoon. Normally, during the monsoon period, the production volumes get reduced. Iron ore pellet production increased 21% quarter-on-quarter and marginally down by 1% on a Y-o-Y basis. I may remind you that during the last quarter in Q1 FY '24, the pellet plant was taken for shutdown, and therefore, in the last quarter, the volume was lower. Production volume on sponge iron, steel billet, MS rounds, HB wires increased both on Y-o-Y and quarterly basis. On a half yearly basis also, steel billets, MS rounds, HB wires increased by 28%, 27%, and 71%, respectively. Coming on the sales volume number, iron ore pellet sales increased 44% -- 45% quarter-on-quarter basis to 432,697 metric tonnes. Sales of steel billets and HB wire also increased both quarter-on-quarter and Y-o-Y basis by 41% and 15% and on quarter-on-quarter basis by 72% and 44%, respectively. On half yearly basis, sale of the steel billets, MS rounds, HB wire, galvanized product increased 30%, 9%, 64%, and 39% respectively. Realization of iron ore increased 22% to 9,955% (sic) [ INR 9,955 per tonne ] on Y-o-Y basis and declined marginally by 2% on quarter-on-quarter basis. On a half-yearly basis, realization of iron ore pellet increased by 4% to INR 10,055 per metric tonne. Realization of other products showed a decreasing trend both on quarterly and on an half-yearly basis. I would like to give some highlight on the strategic updates. I'm happy to mention that CRISIL has upgraded the credit rating of the company both for long term and short-term bank facility to CRISIL AA- stable from CRISIL A+ positive. And similarly, credit rating for the short-term bank loan has also been upgraded to CRISIL A1+ from CRISIL A1. Coming on the updates on the CapEx plan, just to remind you that GPIL had announced ambitious CapEx plan aimed at significantly enhancing the iron ore mining pellet capacity and setting up a new integrated steel plant. The plan intends more than doubling the iron ore mining capacity at Ari Dongri mine, expanding it from 2.35 million tonne to 6 million tonne per annum and also setting up a beneficiation plant with the capacity of 6 million tonnes. The project time line for completion is about 15 months with an estimated CapEx of INR 200 crores. GPIL also plans to enhance the pellet capacity by 3 million tonnes resulting in increase in capacity from current 2.7 million tonnes to 5.7 million tonnes and by constructing additional pellet plant. The expected completion -- time for completion is approximately 30 months from now, and estimated CapEx is close to about INR 800 crores. GPIL has also decided to increase the capacity of integrated steel plant by 1 million tonnes from -- by additional 1.1 million tones from 0.5 million tonnes and taking it to 1.5 million tonnes. The CapEx for the same is estimated to INR 2,500 crores. For all these projects, the company has applied to the Ministry of Environment and Forest for environmental approval. The -- there are 3 separate applications, one is for expansion in Ari Dongri for expansion of pellet at existing plant and for setting up a new integrated steel plant by -- closer to about 30 kilometers from our existing plant. The public hearing for setting up of an iron ore pellet has already been completed, and we are waiting the final approval sometime in the Q4 FY '24. The public hearing for Ari Dongri mines expansion as well as for the steel integrated plant is awaiting the time, and presently because of the state election -- assembly election in the state of Chhattisgarh, the same is getting delayed. We hope that the public hearing shall take place in Q4 FY '24, and we should get the approval soon thereafter. The time line for public hearing has got delayed because of the declaration of the state results, but we are quite hopeful that by the end of the current financial year, we should be able to get the approvals in place. Further, as you're aware that GPIL is focused on reducing carbon footprint and is taking concrete steps towards this goal by establishing solar power capacity of 155 megawatts. As of FY '23, 100-megawatt solar power plant have already been commissioned and are actively contributing to the cost savings. 30-megawatt solar power plant of GPIL and 25-megawatt HFAL are expected to be commissioned in Q2. These projects were earlier expected to be commissioned in Q2; however, because of the monsoon, the commissioning got delayed, and now, we expect the commissioning to be over in the current quarter. I'm also pleased to announce that the Board Meeting held on 3rd November is also approved, setting up an additional 20-megawatt captive solar power plant with an investment of INR 80 crore to meet the captive power requirement of our fabrication and galvanizing plant in Urla, Raipur. The project is expected to be completed by June 2024 and will result in saving of power and fuel cost by INR 3 per unit besides reduction in the carbon footprint. As regards to the CapEx in our steel plant, we have already commissioned the steel -- increase in capacity for announcing the -- sorry, increase in capacity of the steel billet from 400,000 to 500,000 tonnes. And now, we are awaiting the consent to operate. We are hopeful that the consent to operate shall get -- to be received by the end of this current quarter and shall start contributing to the higher production volume. The debottlenecking CapEx for replacement of our turbine rolling mill modification are progressing and are expected to be completed in Q4 FY '24. The balance CapEx to be incurred for debottlenecking CapEx is close to about INR 71 crores in the current financial year. Coming on the market outlook on international front, the global iron ore prices have touched $133 CIF China in mid-March 2023 on the back of reopening of China. However, sharp increase in iron ore supplies by global majors as iron ore -- lower-than-expected demand pickup in China has led to correction to about $120. Recent announcement by China to support housing and infrastructure might lead to increase in the consumption of iron ore prices. The current iron ore prices, CIF, China, is hovering around $125 to $127. The World Steel Association is forecasting steel demand to increase by a healthy 2.3% in 2023 and another 1.7% in 2024. This augurs well for demand for iron ore, and we expect prices to be well supported around the current level. On domestic front, iron ore prices by NMDC have seen slight increase from INR 3,660 a tonne in January to INR 4,460 a tonne currently. Prices have recovered well from the lows seen post imposition of export duty, but remains well below the last year level of INR 5,000 a tonne. It is -- this is on ex-mine basis. On the other hand, pellet prices are touching at about -- touching INR 8,800 a tonne in July 2023 has increased towards INR 9,000 a tonne in September and are currently hovering at around INR 10,000 a tonne. Given the positive demand outlook, pellet prices should be well supported at current level. India remains one of the bright spots globally for steel demand. World Steel Association forecasts India's steal demand to increase by 7.3% in 2023 as compared to 8.2% in '22. Indian government push for infrastructure with 33% increase in capital outlay in addition to 75% increase in outlay for [ railways ] augurs well for the steel demand, especially for the long steel product. Overall, we expect the different steel prices should remain supported looking at the demand level. And, therefore, we expect that our profitability also going forward should remain more or less supported at the current level. With this, I conclude my opening remarks, and now, we can open the floor for question and answer. Thank you very much.

Operator

operator
#4

[Operator Instructions] Our first question is from the line of [ Jatin Damania from Svan Investment Managers ].

Unknown Analyst

analyst
#5

Just wanted to understand on our mining business, now, because of a lower grade in Boria Tibu, we have lowered our guidance by almost 20% for this financial year. So just wanted to understand if you want to look from the FY '25 on our expansion perspective. So can you throw some guidance in terms of our mining for FY '25? And will we be able to ramp up our production? And in terms of the approval, where are we for the expansion of the iron ore mining? That's the first question.

Abhishek Agrawal

executive
#6

I mean just to answer you, we have this year lowered the volumes, this financial year. But if you look at the numbers, earlier also, we were buying close to about, say, 20% from the open market. So in this financial, there will be no financial impact on the closure of Boria Tibu mines because the mines was commercially unviable at these prices and the grade we have. And going forward, we are very confident that we will be receiving the permission for expansion of the Ari Dongri mines, and we will increase the capacity from 2.35 to as stated at 6 million. And we are confident for next financial year, the current requirement of iron ore for a pellet plant will be 100% captive.

Unknown Analyst

analyst
#7

So is it fair to assume that the guidance of 3 million tonnes which you were giving earlier for FY '24 holds true for FY '25 or it might...

Abhishek Agrawal

executive
#8

Yes, yes. Subject to government approval, but I think with the election getting over, and if the global government comes into power, I think the things will start moving. So we're very hopeful the next financial year, we should be able to -- I wouldn't say the volume, but yes, whatever requirement is there from a pellet side it will 100% captive.

Unknown Analyst

analyst
#9

So that's assuming a 3 million tonne requirement, then that will be suffice from our captive...

Abhishek Agrawal

executive
#10

Correct. If it is 3 million tonne, then, yes, it will be 100% captive. Correct.

Unknown Analyst

analyst
#11

Yes. And with our pellet capacity, now definitely, we have seen some improvement in the realizations of pellet. So can you help us in understanding what was the high grade with about 65% grade of pellet that we sold this year? And once our new pellet capacity comes in place, what will be the proportion of the higher-grade pellet in the same?

Abhishek Agrawal

executive
#12

See, so just to correct you, firstly, we have stopped making 65% pellets. Now, the pellet we produce is a 66% grade, a notch higher. And in terms of production level, from day 1, it's 65% so in the bigger plant, 65% in high-grade pellet and 35% in lower-grade pellet. In terms of sale, so we sell 50/50. So you can pay 50% sale is of 63% and 50% sale is 66% pellets. And that 66% will be consumed in house from DRI steelmaking.

Unknown Analyst

analyst
#13

Okay. And -- okay, so the proportion will continue to remain at 50-50 only once the capacity...

Abhishek Agrawal

executive
#14

Yes, yes. Because we produce about 1.5 lakh tonnes of high-grade, out of which 50% is consumed in-house for my steelmaking.

Unknown Analyst

analyst
#15

Right. Now, on to your new CapEx, which is going to lined up on the integrated plant, we are waiting for an approval since quite a long time. So -- I mean, at what stage we are -- because on the pellet, definitely, as per your presentation indicate that we have already done a public hearing and we are looking for a clearance. But in terms of the integrated steel plants, where are we in the stage of approval? And as a Board, have we decided whether we'll be going into a long-steel production or a flat-steel production? I mean, how shall one look into this overall CapEx?

Abhishek Agrawal

executive
#16

See, so on the approval side, we are, I would say, just one step behind the pellet plant. In pellet plant, the public hearing has already been concluded. In this case, because of the election we couldn't do it. So after elections, I think we are confident December public hearing will happen, and if everything goes well, we should be able to get the clearances by March of this financial year. And once we have clearances, we can start the groundwork immediately.

Unknown Analyst

analyst
#17

So probably the groundwork will start in FY '25?

Abhishek Agrawal

executive
#18

Yes, you can say that, yes. So groundwork probably -- because, of course, we can't start the groundwork before even we get the approval. And in the meantime, to your second question about the capacity and where we want to be moving ahead, so I would say they're still evaluating because we still have further time. But to be honest, we're not looking at the long product side. We are mainly looking at the flat product side because we realize where there is -- additional margins are there, and with demand of automobile going up because of spacious EVs. So we'll start product the right way to go forward. Still a final decision will be made probably next 3, 4 months.

Unknown Analyst

analyst
#19

Okay. And last question, which is a bookkeeping question from my side, can you help us in terms of the coal sourcing mix in the last quarter? And how much coal did we import in Q2? And what is the current inventory as on date?

Abhishek Agrawal

executive
#20

See, so the coal mix remains the same. We only use RB1 coal for DRI making, for which we have to import throughout the year. That hasn't changed even for a bit. And for our power plants and for our -- for the [ steel ] operations, we keep sourcing from domestic. We have certain engages from Coal India, and the additional quantity required, we source it from the market because Raipur being a big coal belt it's easy to source. On the import side, we -- our import remains almost same any -- quarter on quarter because with the market being so volatile, it doesn't make sense at all to stock up extra inventory by buying more or buying out like -- so I prefer to move with the market in current scenario. So we import about, say, 1.5 lakh tonnes on quarterly basis, and that remains -- that will still continue to be the same.

Operator

operator
#21

Next question is from the line of Vikash Singh from PhillipCapital.

Vikash Singh

analyst
#22

Sir, I just want to understand, given there's a mismatch in the time line of our iron ore capacity coming in and pellet coming with a lag of 15 months, is it any provision which allows us to sell iron ore in the market or we will just bring down the Boria Tibu to 0 and start utilizing on the Ari Dongri. So what is the plan there?

Abhishek Agrawal

executive
#23

See, see we are definitely allowed to sell iron ore in the market after the new MMDR Act. But as a company, we have no intention selling iron ore in the market because eventually, even mining will take some time to ramp up from 2.35 million to 6 million. So the time period, say, from now on to the next pellet planning commission in, say, about 15 to 16 months, even we would want that time for ramping up the mining capacity. So I think both the projects are in tandem, and we're hopeful once the pellet plant is commissioned before that we're able to ramp the capacity in mining. But we have no intention of selling iron ore in the market, that's for sure.

Vikash Singh

analyst
#24

Okay. But even if you want to, there would be some additional premium which you need to pay, right? That 25% premium that we give...

Abhishek Agrawal

executive
#25

No, no. There's no premium on it because our mines -- as before -- the delivery is due before the MMDR Act. But the rule says, if we have to sell in the market, you can sell it to 50% as a part of commercial mining, but then you have to pay additional royalty, which comes to about INR 1,000 a tonne. So straight away our license will be INR 1,000 less. So it doesn't make any sense to sell in the open market.

Vikash Singh

analyst
#26

Understood. My second question pertains to Boria Tibu. So is it the lower grade is the same problem or we are experiencing this problem with the entire mine or almost all of the [ teams ] are of low grade and which will be in future would haunt us?

Abhishek Agrawal

executive
#27

No, no. So that is no -- see so this is how mining is. That's all the reserve you get. That is -- so till now, we were able to mine, bring it to plan, beneficiations around with the other mines. But then with the current prices, we feel it's commercially unviable because of the recovery percentage, so it's better to install a plant in the mines and then beneficiate and then bring into the plant. So commercially, it doesn't make sense to operate Boria Tibu at the moment, right now.

Vikash Singh

analyst
#28

And at what price basically you feel that it would be commercially viable?

Abhishek Agrawal

executive
#29

See, the problem is we can't start and stop a mine, right, because there are lot of other factors as well. But where I'm -- say another INR 2,000 from now on -- from here on if the current prices go up in India, then it makes sense to use that mine. But still, the impact of Boria Tibu going out of the production doesn't make sudden low volume, doesn't have impact on us because we are still buying from the market, and our first focus is to make Ari Dongri ramp up the production, and make it captive.

Vikash Singh

analyst
#30

Understood. Just one question on Ari Dongri, with the heightened capacity, how does it impact our mining life because I think we had just 30 years of mining life previously? Would it come down to less than 20? How does it plays out?

Abhishek Agrawal

executive
#31

See, our lease is till 2057. So we still have about 34, 35 years in terms of the lease. But in terms of -- we have already declared a reserve of say 165 million tonnes. And further exploration is going on where we feel there is a potential of further deposits. So as and where, probably we have some data, we'll definitely share with everyone. But at the moment, you can say we are at least for the next 2 decades, at least 20 years with a increase in mining capacity.

Vikash Singh

analyst
#32

Okay. So even with the increased mining capacity, 20 years is covered...

Abhishek Agrawal

executive
#33

Yes, yes. With increased capacity, it's 2045, so nothing to worry on that front.

Vikash Singh

analyst
#34

Understood. And just one last question in terms of our integrated steel plant. So just wanted to know if we have already purchased the land bank, what's the status of that? And this INR 2,500 crores seems to be a bit low for an [ HRC ] plant. So is the module is something different, we are going in a narrow place while...

Abhishek Agrawal

executive
#35

No. No, no. See, when we envisaged this budget, we were thinking a mix of flat, long. We were trying to explore other market as well because till now we have been doing long products. So this CapEx was decided long back, once we have the -- probably the final figures, then we decide on the capacity and what would -- probably then we can always amend and give you data. But at the moment, since we don't have the numbers, which you are alluding, so we want to keep it to INR 2,500 crores only. If it goes above, we will definitely share with everyone.

Operator

operator
#36

[Operator Instructions] Next question is from the line of Satyan Wadhwa from Profusion Investment Advisors.

Satyan Wadhwa

analyst
#37

Just wanted to know what sort of margin expansion you are taking out of the steel plant? Is it because you think demand for pellets will be lower going forward as China sort of slows down, and that's why you have to get into steel because in terms of this capital intensity, steel is quite capital extensive compared to your existing businesses, which are quite profitable?

Abhishek Agrawal

executive
#38

No. I would like to defer on that. The reason why we entered into steel is because we see an additional EBITDA over the pellet margins. Because we are into high-grade market, we made a specific pellet. And so I don't think there is any pressure on us to sell pellets because the kind of capacity we are coming up in India and you see Middle East, right? So Middle East is increasing capacity like anything because of the gas being available. So I don't see challenge in selling up high-grade pellets, which will be the main center of volume. But when we evaluate -- so when we consider the pellets at today's cost and transfer to the steel making, we further see an EBITDA of at least about INR 8, INR 10. So that is the reason we want to power integrate into steel rather than only remaining as a pellet player.

Satyan Wadhwa

analyst
#39

Right. So like the additional EBITDA over pellet EBITDA would be how much in terms of steel?

Abhishek Agrawal

executive
#40

Say, at current prices, say, about current market, it should be about INR 10,000 a tonne.

Satyan Wadhwa

analyst
#41

INR 10,000 a tonne?

Abhishek Agrawal

executive
#42

Over and above the pellets EBITDA?

Satyan Wadhwa

analyst
#43

Above -- over and above the pellets EBITDA?

Abhishek Agrawal

executive
#44

Of course. Of course.

Operator

operator
#45

Next question is from the line of Rakesh Roy from Omkara Capital.

Rakesh Roy

analyst
#46

Sir my first question is regarding, just you told -- said your mining capacity is you have to revise due to the low grade from the Boria Tibu mine, sir?

Abhishek Agrawal

executive
#47

Yes. See, we are not revising the mining capacity. All we've done is because in today's market that mine has commercially become a little unviable, so we have decided to lower the volumes. And then put up a beneficiation plant there and then adopt that process of beneficiating and then bringing it to the plant for usage. That's the only reason.

Rakesh Roy

analyst
#48

Sir, is there any impact on revenue from this only? Or is there any impact of this so we have to lower mining from Boria Tibu or could this...?

Abhishek Agrawal

executive
#49

No, so financially, there is no impact in this financial year and going forward also. Because at the moment, also, commercially, the mine is not viable. So it's better to source from the market rather than mining and then moving it back. So financially, this financial year and going forward, so we don't see any impact.

Rakesh Roy

analyst
#50

Okay. So next financial, we hope this mining will start normally?

Abhishek Agrawal

executive
#51

No. Boria Tibu will take time because we will be putting up a plant to integrate, and we will further enhance the mining capacity. So we need to take the required approval from the state and the central government, including the mine's industry. So that will take some time. So we can expect Boria Tibu can come back into production with beneficiation, say, next 20 to -- 24 to 30 months. We're looking at FY '27 probably.

Rakesh Roy

analyst
#52

So we have to set up a new plant near to Boria Tibu?

Abhishek Agrawal

executive
#53

Yes, yes, we will set up a new plant, beneficiation plant in the mines itself. So for that all the required approvals and other infrastructure has to be created, so that will take some time. In the meantime, for next financial year we will finally increase the capacity of our other mines, Ari Dongri.

Rakesh Roy

analyst
#54

Okay. So we have to -- sir for example, Boria Tibu, we have 85 million tonnes of capacity reserve is there, yes? Or...?

Abhishek Agrawal

executive
#55

Yes, as of now explored data, what you said is right, correct. Yes.

Rakesh Roy

analyst
#56

Yes, sir. So, sir, in that case, can we ramp up our Ari Dongri mines? Is there a provision...?

Abhishek Agrawal

executive
#57

Yes. I've just spoken to -- I have just spoken sometime back. We are waiting for the approval for the Ari Dongri mines, and once we have the approval, which we should have in hand in next 3, 4 months. From next financial year, we will make the capacity from 2.35 million to 6 million tonnes.

Rakesh Roy

analyst
#58

Okay. Okay. Sir my next question is regarding, sir, can you help me -- help us to please tell you if you're able to achieve your FY '24 guidance for ferro alloy and pellets?

Abhishek Agrawal

executive
#59

Yes, yes. So whatever guidance we've given this financial year, apart from mining, we are very much on track, and we are confident we'll be able to achieve it.

Rakesh Roy

analyst
#60

Okay. And in margin front, sir, can we hope this margin will sustain? Or is there any margin changes in the next 2 quarters, sir?

Abhishek Agrawal

executive
#61

See, at the moment, things look good because China is buying a lot of iron ores, so the prices of pellet has gone up in India as well. And with festive season getting over after Diwali with -- and this is being the peak demand in purchasing in India, and with [ government ] spending, we are -- I'm confident to see the prices to sustain. And we should be able to maintain this EBITDA going forward unless, of course, there is change in the market. But at these levels, we are confident we should be able to maintain EBITDA at this level.

Rakesh Roy

analyst
#62

Okay. Sir, any -- your outlook on the margin front especially ferro alloy or this margin will -- this realization will be sustained for next 1 quarter or any downside is there, sir?

Abhishek Agrawal

executive
#63

See, it is very difficult to predict, yes, because even ferro alloy is globally connected. So one thing is for sure that pellet -- the pellet prices are at the rock bottom at the moment. And with the current raw material prices, the margins are bare minimum, which used to be earlier. The only saving -- the only positive side for us is with the new solar plant getting commissioned our power costs will go down, which will improve the margins in ferro alloys because ferro alloys is a high-power captive unit. So we see an upside there. Apart from that, market looks quite stable, and depends how globally steel plays because in India, ferro alloys has a big market for export as well, especially Europe and all.

Rakesh Roy

analyst
#64

Okay. Sir, your view on domestic steel market size and especially how is the market in -- steel market in India, sir, in next 1 year, sir, from here?

Abhishek Agrawal

executive
#65

See, I am bullish with the government spending. So let's see. Let's hope for the best.

Operator

operator
#66

[Operator Instructions] Next question is from the line of Dhyey from Niveshaay Investment Advisors.

Dhyey Desai

analyst
#67

I just had this question that as we are adding another process of beneficiation -- like beneficiation in our manufacturing process. So what is the improvement in margins that we expect from this expansion?

Abhishek Agrawal

executive
#68

See, as I said earlier, the only reason we are installing a plant of beneficiation in mine is to grow the cost saving part because earlier we were beneficiating everything by bringing it to Raipur because of the complex. So we were losing on the transportation because when you beneficiate there is some tailing -- there is yield loss as well. So to save on that cost, which is substantial, say, INR 150 at the moment, we are installing a plant in the mines. So the process -- the quality of the pellet we make will remain same. The cost of mining and everything will go down.

Dhyey Desai

analyst
#69

Correct. Correct. Sure, sir. And what is the kind of EBITDA expansion that we are looking per tonne or EBITDA expansion in terms of margins?

Abhishek Agrawal

executive
#70

See, the margin is going to be -- see, it's a small saving of INR 150. But when you look at the volumes we're going to be doing, so the payback is quite large. So it's not substantial improvement on INR 150, INR 200. But when you look at 6 million tonnes going forward, it becomes almost INR 100 crores a year. So with the amount of CapEx we're doing, the payback is hardly 18, 24 months. So that's the reason we're doing in the mines itself right now.

Dhyey Desai

analyst
#71

Correct, sir. And also I had...

Dinesh Gandhi

executive
#72

Plus saving on royalty, plus saving on some part of royalty.

Abhishek Agrawal

executive
#73

Exactly.

Dhyey Desai

analyst
#74

Okay. Correct. And I just had this question sir what is the captive consumption of every level -- at every levels of manufacturing process, if you could give us any guidance?

Abhishek Agrawal

executive
#75

See, at the current market levels, I think all the different products are in positive, be it pellets on their end, billets or -- but it's difficult to comment on individual performance because when it's a complete steel plant, so you have to look at from backward to forward. So to -- it will be difficult to comment on individual product profitability, but I can assure you, all the divisions are making -- are doing good.

Operator

operator
#76

[Operator Instructions] Next question is from the line of Jathin Kaithavalappil from InvestSavvy PMS.

Jathin Kaithavalappil

analyst
#77

We'd like to know, one, your plans to split have actually got postponed or canceled? So is it like -- or is there a time line on which you will reconsider that? The other is that with the new emphasis on solar plants and power and fuel savings, while you are saying you'll be able to maintain the current EBITDA with the new power capacity, et cetera, which you are planning, will there be a benefit of that coming into the EBITDA margin as well? And finally, how are you seeing your pellet exports going forward in terms of growth on that...?

Abhishek Agrawal

executive
#78

Okay, so the first part, Dinesh-ji will take care. I will answer the technical part, and then, Dinesh-ji can take over. So see, on the solar side, definitely, we can -- once the entire plant is commissioned and with our CapEx of debottleneck, we can see an actual EBITDA of [ INR 700 crores ] going forward annually on the power side itself. On the export side, we are always there in the market, but for us, domestic prices are still better than the export market. And because of a high grade, we don't have any pressure in selling domestically. So till the time we don't -- the license doesn't come at par with domestic, we are happy selling domestic. So we have no -- we are always open, but then it's not guaranteed when we will start exporting again because for us, I guess, expansion -- license is the topmost priority.

Jathin Kaithavalappil

analyst
#79

And how do you see revenue growth going forward?

Abhishek Agrawal

executive
#80

See, it depends on the steel prices because -- and for us, we are operating at almost at 100% capacity, 98% capacity across the plants. The -- so the only thing we should add up is our additional 1.5 tonnes of steel billet. So depending on the market prices, the revenue should go up going forward because I see the demand in India for steel is going to be an upside with the government spending.

Jathin Kaithavalappil

analyst
#81

Okay.

Abhishek Agrawal

executive
#82

Dinesh-ji, question for your...

Dinesh Gandhi

executive
#83

Yes. I will have -- make some addition on the volume growth and the sales growth. In fact, the sales growth is going to come with the setting of an additional -- as Abhishek told you, that the plants are running almost at 95%, 100% capacity utilization. So volume growth will come only when we set up the additional pellet plant and additional steel plant, which we have announced. Till then, this is the sales -- growth will come only with the price growth. If there is a degrowth in price, there will be a degrowth in sales. If there is a growth in the pricing, then the sales will also grow. Coming on the split side, see, we had initiated a proposal to split share, but our Board of Directors felt that the current volume and the price of the share is not very high, which requires the split of shares. And we had almost about 1.5 years split the share from INR 10 to INR 5. So board suggested to wait us for some time. And at an appropriate time, the proposal should be revisited. But there's no time line for revisiting the proposal.

Jathin Kaithavalappil

analyst
#84

Okay. And practically speaking, when do you expect this additional capacity to start kicking in?

Abhishek Agrawal

executive
#85

Start kicking what?

Jathin Kaithavalappil

analyst
#86

So you are saying your operating...

Dinesh Gandhi

executive
#87

New capacity, new capacity he is asking.

Abhishek Agrawal

executive
#88

See, so for the steel division, I think we are waiting for the pellet approval which should be in hand probably very soon. So I think for next quarter, you can see the additional capacity of steel melting come into production. And for the pellet plant, Q1 -- sorry, Q4 of FY '25 is what you're looking at for the additional volume, Q4 of FY '25.

Operator

operator
#89

Next question is from the line of Siddharth Gadekar from Equirus.

Siddharth Gadekar

analyst
#90

So my first question is on the pellet side. Now, given that our expansion will be starting somewhere in 4Q or early FY '25, when do we expect the first capacity to come online? And what should be a fair assumption in terms of volumes in FY '26? Or we will see the entire volumes coming in FY '27?

Abhishek Agrawal

executive
#91

No, no, as I mentioned see Q4 FY '25 means, which is like a 3 months from now on, right? So from FY '26 we can start seeing the additional volume of the pellets capacity, which we will be putting up. And no, no, FY '27, is too far, we will be able to commission the plant 12 months earlier.

Siddharth Gadekar

analyst
#92

Okay. So -- and so pellet should be roughly around 1 million tonne of contribution in FY '26 and the balance will be coming in FY '27, is that a fair assumption?

Abhishek Agrawal

executive
#93

No, no, no. See, the pellet plant -- see the first pellet plant we will be putting up, it will be commissioned in Q4 FY '25. And so simply in FY '26, we can realize the entire production volume. Nothing we will pass on to '27. Of course, we are confident we should be able to achieve 100% capacity within 3 months of starting the plant.

Siddharth Gadekar

analyst
#94

Okay. So our ramp-up will be much faster than normally you are...

Abhishek Agrawal

executive
#95

Yes, yes, because I think we have good expertise on our hands. We are running -- we are already running 2 pellet units, so we don't see a challenge in ramping up the capacity.

Siddharth Gadekar

analyst
#96

Okay. Sir, and in terms of our steelmaking capacities, is it fair that our CapExes should get over anywhere end of FY '26 and FY '27 will be a meaningful volume growth on the steel side as well?

Abhishek Agrawal

executive
#97

See, if we have the required approvals, then we will start the groundwork. We can -- we are confidently the new steel plant will take about 30 months from date of groundwork. So if that happens and everything is within the time line, you should be able to see significant volume growth.

Siddharth Gadekar

analyst
#98

Okay. Sir, and once the approvals come in, that is when we'll finalize that what processes are we going to use to make the steel and...?

Abhishek Agrawal

executive
#99

No, no, see, that working strategy is going on. We've been evaluating because for us also, this is something new, till now we haven't done it. So we have been evaluating with all the stakeholders, the experts in the market, and I think we should be able to close everything in next 3 to 4 months. So that -- once we get the permission, we can straightaway start the groundwork.

Siddharth Gadekar

analyst
#100

Okay. Got it. So broadly by FY '26 end all these CapExes should be completed, that is a fair assumption I...?

Abhishek Agrawal

executive
#101

So the steel plant -- so I think steel plant can probably overlap...

Unknown Executive

executive
#102

Spill over to FY '27.

Abhishek Agrawal

executive
#103

Yes, depending on the approvals and everything else.

Siddharth Gadekar

analyst
#104

Okay. So assuming things come by this year-end, we should be on track for a healthy volume growth in '26 and '27 driven by pellets and steel, that is a fair assumption, right?

Abhishek Agrawal

executive
#105

Correct. Correct. This is a fair assumption. Correct. Correct.

Siddharth Gadekar

analyst
#106

Sir, and then, once our incremental pellet capacities come online, how should we look at the mix between high grade and the normal pellets?

Abhishek Agrawal

executive
#107

No. So see the new pellet plant, which is coming up, is going to be again on the high grade. So the mix will change. So the product capacity, we should be able to produce, say, close to -- 75% will be the high-grade pellets and 25 -- 20% will be of low-grade pellets, the normal pellets only.

Siddharth Gadekar

analyst
#108

Okay. Sir, and the 66% pellets are currently at a INR 1,000 premium to the normal pellets?

Abhishek Agrawal

executive
#109

So the normal pellets, yes, the premium is anything between -- depending on the market condition, it's INR 1,000 as well as INR 2,000. But I would say, on a fair basis, about INR 1,500 on an yearly average basis, about INR 1,500 from the 63% pellets.

Operator

operator
#110

Next question is from the line of Aditya Welekar from Axis Securities.

Aditya Welekar

analyst
#111

Sir, so a couple of questions. How is the ferro alloy business doing as of now, if you can individually throw some light on GPIL, HFAL, and Alok ferro alloy business?

Abhishek Agrawal

executive
#112

See on the ferro alloy side, in terms of market, I would say the prices are exactly rock bottom because globally, the market is quite weak because India is suffering in terms of pellet capacity, so a lot of alloy has to be exported to attain -- achieve that balance between domestic and export. Because the export market is quite subdued, so it has the same effect in the domestic pricing. So I would say right now, the margins are between INR 2 to INR 3, but going forward, we hope the margins will improve when the demand comes back into the market.

Aditya Welekar

analyst
#113

Understood. And second one is on thermal coal. So what is the thermal coal cost you incurred in Q2 of this fiscal? And...

Abhishek Agrawal

executive
#114

See, Q2, average price was about INR 12,000 a tonne. And Q3, we still -- the international market has started going up, so there will be a margin increase. And Q4 onwards, let's see how the market plays. But Q3, we are below INR 12 and Q3 will be marginally above INR 12 because the incoming coal is on the higher side.

Aditya Welekar

analyst
#115

Understood. And lastly, I missed on that part on Ari Dongri beneficiation plant. So what's the CapEx -- incremental CapEx for that? And what is our CapEx guidance for...

Abhishek Agrawal

executive
#116

See, total we have envisaged within mining capacity enactment as well as the beneficiation plant, the total CapEx envisaged is about INR 200 crores, and we should be able to complete the desired projects within the budget.

Operator

operator
#117

Next question is from the line of Moksha Shah from YellowJersey.

Moksha Shah

analyst
#118

So my question for the management was, there are market rumors about the company getting into forward integration, expanding into new business verticals. So what are your views on that?

Dinesh Gandhi

executive
#119

No, so there is no market rumors, Moksha. We are in the process of building up a new steel plant. And there the value-added steel will be manufactured, what steel, what kind of product will be manufactured will be decided as Abhishek mentioned earlier. And hopefully, we should be able to make a concrete -- announce a concrete plan on which kind of products by maybe end of the current financial year or maybe at the time of the results call for Q4 FY '24.

Operator

operator
#120

Next question is from the line of [ Marshall ], an Investor.

Unknown Attendee

attendee
#121

Yes. First of all, my humble request, sir, you are speaking through speaker, so your voice is very much getting echoed. We're not able to fully understand it. So if you could kindly speak a bit slowly, it will be really helpful, sir.

Abhishek Agrawal

executive
#122

Thank you. I will do that.

Unknown Attendee

attendee
#123

Yes. Second thing, sir, regarding this -- the price of a different product, can you please give some idea that what was the prevailing average price of pellet, sponge iron, billet, MS round, and the HB wire during the month of October or if you can say recent price, please?

Abhishek Agrawal

executive
#124

See, month of October, the pellet prices have been around INR 10,000 domestically. And for sponge iron, it was about INR 30,000. The market has gone down by over 5% due to weak demand in the festive season. Sponge iron was about INR 30,000. Billet was about INR 42,000, INR 43,000. Wire was about INR 48,000. And the prices remained to -- at these levels only because of the subdued demand, and it should improve going forward when the festive season is over.

Unknown Attendee

attendee
#125

And MS round, sir?

Abhishek Agrawal

executive
#126

MS, I said, INR 48,000.

Unknown Attendee

attendee
#127

INR 48,000, okay. Okay. And my second question is regarding this -- the new CapEx. So first of all, like this new CapEx of our integrated steel plant. Are we going to do it the existing site, wherein like, for example, this existing common facility will be used or it will be also a greenfield plant?

Abhishek Agrawal

executive
#128

It will be a different location, and it will be a totally greenfield project. It will be in the Godawari Power, the same company. But then, of course, it is going to be a new location with a totally greenfield project.

Unknown Attendee

attendee
#129

Okay. And like, are we going to make the similar product like this MS round and HB wire? Or are we going for the coal rolled...?

Abhishek Agrawal

executive
#130

No, no. So that -- so see, currently, we follow the secondary of steelmaking, which is the coal-based DRI for the induction furnace. And going forward, we will be putting up a blast furnace and make value-added products like others.

Unknown Attendee

attendee
#131

It's like this hot rolled coil, cold rolled coil, like this, right?

Abhishek Agrawal

executive
#132

Yes, depending if we go with the hot rolled coil or we go for -- so whatever products we choose, we should be able to freeze on those in the next couple of -- in 2 or 3 months.

Unknown Attendee

attendee
#133

Because I was just like making a small analysis here because our current capacity, for example, of this MS round and HB wire is 60% and 75% all utilized. So I was thinking if you are explaining the same thing, then like it will be difficult. But if you are adding new product, then it's fine.

Abhishek Agrawal

executive
#134

Yes, yes. So we don't intend to -- to be honest, at the moment, I think the long products have taken a backseat and we're focusing on value-added steel.

Unknown Attendee

attendee
#135

Okay. But like there is 1 point, I want to play this like, for example, devil's advocate here. We have come a long way. In 2017, we had net debt of INR 2,000 crores. Now, we are INR 600 crores plus net debt. If we are going to have the INR 2500 crore CapEx at one shot, means like whether we will be able to fully market it and however -- yes, and more so we don't have coal linkage also -- sorry, like we don't have the coal mining, our own captive mining. So like how are we sure that like we will not again fall in the -- I will not say like, for example, debt trap. But for example, even if we make such a huge investment and if we are not able to fully utilize it, then like it will be a burden of depreciation or loss of, for example, like this funding revenue like which you could invest somewhere else and like...

Abhishek Agrawal

executive
#136

No, no, see, to be honest, when we have first put up a pellet plant almost 15 -- in 2008, 2009, we were the one of the first movers in India to put up a pellet plant. So we don't see a challenge, with every new challenge -- so we are very confident with the team we already have and further we are going to recruit. And I don't see any challenge being not able to produce at the desired levels or market it. Secondly, since you mentioned, we don't have any coal mine. But we have an iron ore mine, which is a big, big plus. So one side of our steelmaking is always covered with the captive iron ore mining. So even if the cost implication is because of no coal mines, I don't see a challenge in achieving the profitability we desire to.

Unknown Attendee

attendee
#137

But sir, like since we already have expertise in the mining sector, so why we are not bidding for the coal mining? Because government is like every third month or eighth month, the government is opening so much like the government is opening so many coal mines...

Abhishek Agrawal

executive
#138

See, I'll tell you the reason why we're not doing it because for DRI, the coal available in India is not up to the same mark. If you start using the domestic coal, production in the DRI will go down, which we don't want to do. So we have to keep importing for our DRI, which is about 0.5 million tonnes annually or 0.4 million tonnes annually. That is the first thing. For power plants, as we have announced, we have been expanding aggressively in solar to look at the cost savings as well as in terms of the green initiative of the carbon emission. Early, the remaining volume, or whatever we need to source from the domestic market, we have integrated with Coal India, which is almost at the market price depending on the auction. So we don't see a very cost implication on the coal side compared to iron ore side. So since we have iron ore side covered, so for us, it's good enough to move forward. And on the CapEx side, see, we are a surplus cash company. And with the plans going forward, we should be able to [ edit ] damaged EBITDA on a year on year basis so that we can fund it internally.

Unknown Attendee

attendee
#139

So like, if you're not going to have any debt, like new debt for this integral plant, then it's a good thing.

Abhishek Agrawal

executive
#140

See, that's the intention. But depending on the capacity, we will go forward in which value product to choose. Even if we have to take some debt, it's going to be within the limit because in the end we have realized where we had gone wrong 12 years back. So we are very sure how to proceed forward so that the balance sheet doesn't come under stress any forward -- going forward.

Unknown Attendee

attendee
#141

Just like 1 input. We have seen that like another -- for example, other major player in the steel, they have tied up or they have acquired some stake in the overseas, for example, coal mining companies. So I don't know the name exactly, but like you know it very well. So suppose -- since you are saying you have a logical point that this domestic available coal is not good for the DRI, that's fine. So why don't we acquire some stake overseas, in Indonesia or Africa or some other companies...?

Abhishek Agrawal

executive
#142

See, again, again, again, as I'm saying. See, all these assets are not available at cheap value. And to secure certain volumes of coal for a captive production, we don't see any value addition compared to investing the same money probably, again, going forward in steel plant. So you've rightly mentioned we should, but I think on the cost implication side, I would say, we are very much covered because of iron ore, and we want to utilize our money probably at making value-added steel rather than going backward and making coal captive.

Unknown Attendee

attendee
#143

Okay. But like this is very small point. So since you mentioned about the DRI, that's fine. So suppose if you take a local -- like suppose if you participate in any bidding of the coal mine auction so that coal can't be utilized for this manufacturing of sponge iron or this pellet or billet...?

Abhishek Agrawal

executive
#144

See, as I said, all these coals -- mix of -- in the past also, we have bid for a few of the coal mines, but we were never very aggressive. And in terms of quality, all the coal produced in India is possible to use in our domestic production. But as I mentioned, if you use that coal, our production volume will drastically go down, especially in DRI because in domestic coal the ash is very high. And because of the higher ash, our production volume will go down, which we have no intention to reduce.

Unknown Attendee

attendee
#145

No, sir, I'm not saying about DRI use for that area. I'm only saying for manufacturing of our current product, for example, billet or for example...?

Abhishek Agrawal

executive
#146

See, for billet, we don't -- see, see, billet doesn't require any coal. As we generate power, we have -- we are already having integrated Coal India for our thermal power plants so that is covered. For DRI, we keep importing. And for pellet plant, we have an exposure of about, say, 2 to 3 lakh tonnes annually, which is not a big exposure. And the domestic coal is readily available nearby.

Operator

operator
#147

Next question is from the line of Rucheeta Kadge from iWealth.

Rucheeta Kadge

analyst
#148

Congratulations on a good set of numbers. Sir, I had a few questions regarding your volume growth. So going ahead, do we -- like in the next 2 years, do we see any incremental capacity coming in other than the mining capacity that we have mentioned? So if you can give a little clarity on that.

Abhishek Agrawal

executive
#149

See, the pellet capacity will further add up, as we've mentioned before also. The -- we expect the pellet plant approval to be in hand in the next couple of months. Once we have that, we'll start the work. And in FY '26, we can see the entire pellet volume coming into production, which is as desired. And parallelly, next quarter, Q4 of this financial year, our additional steel capacity of 125,000 tonnes, 1.25 lakh tonnes will also be operational. The project is completed. We are just waiting for the required approvals. When we have the approvals, we will start the operations.

Rucheeta Kadge

analyst
#150

And that is Q3, right, you will like...?

Abhishek Agrawal

executive
#151

Q4. So Q3 is already running, so that will be Q4. And then next financial -- FY '26, you can see the entire volume of pellet into production, the new pellet plant.

Rucheeta Kadge

analyst
#152

Okay, pellet by FY '26. And sir, as you've mentioned, that you'll not be selling this extra mining capacity in the market, right?

Abhishek Agrawal

executive
#153

Yes, we won't be.

Rucheeta Kadge

analyst
#154

You won't be doing this. And...

Abhishek Agrawal

executive
#155

Yes. Because we want to preserve the iron ore for our captive convention, plus as per the new law, we will have to pay additional royalty for selling anything in the market. And so we have no intention of selling anything in the market.

Rucheeta Kadge

analyst
#156

Okay. Sir, one more thing, currently -- a ballpark number, basically, your EBITDA per tonne is around INR 6,099. So do we see this settling at the current rate or we see it deviating? And what would be the reason?

Abhishek Agrawal

executive
#157

So see, as I mentioned earlier also, depending on the market scenario, if the market sustains at these levels, we are confident of maintaining the current EBITDA levels. And of course, if things here and there. Of course, there can be deviation, but we are confident with festive season over and the demand is going to be picking up going forward, we should be able to maintain such EBITDA levels.

Operator

operator
#158

Next question is from the line of [ Anant Mundra from Mytemple Capital ].

Unknown Analyst

analyst
#159

Sir, how much of our current power sourcing is from the grid?

Abhishek Agrawal

executive
#160

See, from grid, we are not importing -- we do import, but the portion is hardly, I would say, 2% or 3% of the entire requirement because we have commissioned our first set of solar plant of 70 megawatts under the banking policy of the state government. And so whatever we are importing from the grid is mainly on account of solar power we generate, and the remaining is from the grid power. So in terms of -- you can say about 2% or 3% of the entire requirement only.

Unknown Analyst

analyst
#161

Okay. So it's majorly captive?

Abhishek Agrawal

executive
#162

It's majorly captive, but I would say 98%, 99% captive only here.

Unknown Analyst

analyst
#163

All right. All right. And sir, Boria Tibu, also, we are planning a beneficiation plan, right?

Abhishek Agrawal

executive
#164

Yes, we are. We have started to apply for the required approvals and other things. And we will be putting up a beneficiation plant in Boria Tibu going forward.

Unknown Analyst

analyst
#165

So until then, I think the plant is going to be shut unless obviously, you said...

Abhishek Agrawal

executive
#166

The plant will not be shut. We will be operating it at a quite low -- we will be operating at lower volumes because as I mentioned earlier, at the current prices, the mines is commercially unviable, so it's better to operate at minimum levels and then put up a plant going forward and then bring the ore to the plant for usage.

Unknown Analyst

analyst
#167

Okay. Okay. And so we are not planning any expansion at Boria Tibu, all our mining CapEx is happening at Ari Dongri?

Abhishek Agrawal

executive
#168

At the moment, it's happening at Ari Dongri. Once everything is finalized in terms of Boria Tibu, we will share the required CapEx and the enhanced capacity and everything else. It's a very early stage, probably going forward when we have all the details in hand, we will definitely share.

Operator

operator
#169

Next question is from the line of [ Jinesh Shah ], an Individual Investor.

Unknown Attendee

attendee
#170

Congratulations Abhishek-ji and entire team for the excellent set of numbers. The first question is, as I understand, the current product mix for pellet is 50-50 for 62% and 66%. Do we have any plan to improve that percentage for these high-grade pellets in this financial year?

Abhishek Agrawal

executive
#171

Thank you for the congratulations. No so see, there is a confusion. Right now, the production of high grade is about 65% compared to 63% of 35%, but in terms of merchant sales, the ratio is 50-50 because the remaining is used in our in-house for steel making, the high-grade pellets. And going forward, the new pellet plant, which is going to come up, will also be producing high-grade. So the charge mix will change. It will be about -- 80% will be about high grade and 20% will be of 63% grade pellets.

Unknown Attendee

attendee
#172

Okay. The next point is regarding the CapEx plan on Slide #10, Page #10 of the PPT where you've mentioned that you will be taking 15 months for iron ore mining and iron ore beneficiation vis-a-vis the pellet plant will take 30 months. But based on today's conversion, what I understand, this 3 million capacity will be available by next financial year. Is this the right understanding?

Abhishek Agrawal

executive
#173

So see, the mining and the pellet plant, so the 30 months were desired from data of -- once we applied for the permission. Once we have the permission, which will happen in probably the next couple of months, the execution time of the project will be about 15 to 16 months. So we see the entire capacity of pellet coming into production in FY '26.

Unknown Attendee

attendee
#174

Okay. But in that case, you will be having your iron ore mining beneficiation plant will be...

Abhishek Agrawal

executive
#175

Yes. That's the whole idea. We have parallelly applied for permission for our Ari Dongri mine capacity expansion as well. And once we receive the permission, so gradually, we'll also ramp up the capacity so that there is no lag between the new pellet plant and the new mining capacity. So there we remain fully captive going forward.

Unknown Attendee

attendee
#176

Okay. The next part is regarding your integrated steel plant, which you are increasing from 0.5 to 1.5 million tonne with the investment of INR 2,500 crores. Are we looking at any opportunity in terms of inorganic in terms of accretion of any existing steel plant?

Abhishek Agrawal

executive
#177

See, see we have always been open for any inorganic growth. So given if there is an opportunity where we feel that there is value to a certain asset, we will definitely look for it. But to be very honest, we haven't come across such at the moment and we're not [indiscernible] also. And parallelly, if we had the required approvals, then we were happy to go ahead with the greenfield today.

Unknown Attendee

attendee
#178

And what will be the ROI or payback period for the 1.5 million tonnes steel plant?

Abhishek Agrawal

executive
#179

See, it's too early to call. But what we have envisaged with the current market scenario, we can see an additional EBITDA of, say, [ INR 8,000 ] over the current EBITDA of the current complex. So if we'll go back that -- and second question is depending on the CapEx. We have envisaged INR 2,500 crore, but it remains INR 2,500 crore or it goes up, it goes down. So I think it will be difficult, but with the current -- with our own captive mines, we don't see a ROI of more than 2.5, 3 years, to be very honest.

Operator

operator
#180

Ladies and gentlemen, as there are no further questions, I would now like to hand the conference over to the management for the closing comments.

Dinesh Gandhi

executive
#181

Hello. Thank you, participants for joining us with the conference call of Godawari Power & Ispat Limited. If there is any question left to be answered or if you need some more clarity on the company's performance, you can approach us directly or our Investor Relations agency, Go India Advisors. Thank you very much for joining this call, and with this we conclude this call. Thank you very much.

Operator

operator
#182

Thank you. On behalf of Go India Advisors, that concludes this conference. Thank you all for joining us, and you may now disconnect your lines.

For developers and AI pipelines

Programmatic access to Godawari Power & Ispat Limited earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.