Greatland Resources Limited (GGP) Earnings Call Transcript & Summary

October 25, 2026

Australian Securities Exchange AU Materials Metals and Mining earnings 54 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone being on the line, and we’re glad to have you join the investor call for Greatland Resources covering the September 2026 quarter. <<operator_script>>. Please be aware that a recording is being made of this session. At this point I’ll hand things over to Shaun Day, our Managing Director, to open the conference. Shaun, the floor is yours.

Shaun Day

executive
#2

Thanks, Paul, for getting us started, and welcome, everyone. Thanks for joining the call on Greatland's September 2026 quarterly results. Sitting with me today is essentially the entire executive team. We have Andrew Rowan Krasnoff, Richard Maniola, and also Nick Strong, our new Chief Operating Officer, is with us on this call. What I'll do is begin by moving to Slide 5. Look, we felt it was just a really solid quarter from an operational standpoint. We beat the street on both gold production and all-in sustaining costs, with both coming in better than planned. And that was really driven particularly by strong processing performance. That was particularly encouraging given we had the planned major shutdown for the year of 15 days, and it ran like a Swiss lapsed — that site did a great job to bring that back online, and a really significant just derisking as part of the -- in terms of production, doing just over 70,000 ounces of gold, we thought was very strong, particularly the copper production of well, just over 2,900 tonnes of copper. We thought was really encouraging. And this just puts us very comfortable in terms of that guidance range of 260,000 to 300,000 ounces for FY '27.

Shaun Day

executive
#3

On all-in sustaining costs, I felt that result was especially robust, landing at AUD 2,925. That sits right at the floor of the guidance we issued for all-in sustaining costs this year. Looking at it, the operation generated operating cash flow of $289 million. We recorded a net cash build, and that build came even though we paid 5 months of tax in the quarter as we move from paying quarterly to paying in monthly installments. So despite that added tax load this quarter, cash build performance remained solid. On top of that, naturally, we secured full permitting on Caverin, so we began ramping up spending there. We ended the quarter with more than $1.3 billion cash at bank and no debt. Combined with the undrawn $500 million debt facility, that leaves us with $1.8 billion of liquidity on hand. What matters greatly there is that it reduces risk and provides a clear route to deliver the organic growth profile we hold at Haveron Bullosa across Telfer, which we'll cover a bit further in these slides. The main highlights this quarter, in my view, were the permitting coming through on Hain.

Shaun Day

executive
#4

It has been quite a road, yet we are very pleased to have secured it. And at this point we are able to move into the construction stage at our flagship HAVEN development. Since that approval came through, the team has done an excellent job getting things moving within the week, and you have observed activity, especially at surface, connected with preparing those evaporation pond builds, along with clearing the pads for the ventilation blind boards. That wraps up the third quarter summary, so I will hand things over to Otto Richter.

Otto Richter

executive
#5

Thanks, Sean. Moving to Slide 7, we'll examine what's driving this solid beginning to the fiscal year. First we consider the Wisdom open pit. Total material mined in the orbit rose once more versus the prior quarter, reaching slightly below 8 million tonnes, 7.9%. That marks our seventh straight quarter-on-quarter gain in total material mined since Greatland became the owner, and it amounts to a 79% productivity improvement compared with our March quarter of last year. This ongoing expansion stems from better trucking availability thanks to our new and rebuilt trucks, consistently larger productivity, and sustained efforts to boost bench turnover and to open up those bigger, more productive working fronts in Stage 7. Ore mined from the open pit also set a record under Greatland ownership, at 4 million tonnes for the quarter. Grade held steady quarter-to-quarter at 0.45 grams per tonne. Growth stripping in Stage 7 is ongoing, with 2.8 million tonnes of waste mined this quarter at a strip ratio of roughly 1.7%, lower again than the 2.3% strip ratio recorded in the previous quarter. For the rest of FY '27, the Stage 7 strip ratio is anticipated to be approximately 1.4 to 1.5 million.

Otto Richter

executive
#6

Now shifting our attention to the main dome underground — as you can see, the underground ore mine also set a record, along with a great land ownership, at 0.4 million tonnes for the quarter, which is up 19% quarter-on-quarter. The underground grade came in at 1.33 grams per tonne gold, and that aligns with what we planned for the quarter. On underground development: a seventh quarter in a row of record development meters, with just over 2 kilometers achieved. A good focus area, or highlight, there is the second development drive to West Dome underground, which is now complete, with the breakthrough happening just after the quarter end. The big benefit here is that this extends the primary ventilation circuit to the Western Dome underground platform location and now lets us open up more headings on that West front. Turning then to Slide 8, we can see the processing outcomes from the quarter. We milled 4.9 million tonnes at 0.5 gram per tonne gold head grade, with mill tonnes being a key area of strength, while successfully executing the planned 15-day mill shut, as Shaun highlighted. Our gold recoveries of 85% were in line with the plan and our prior guidance commentary at 85%, while our copper recoveries at 83% were definitely a standout for the quarter.

Otto Richter

executive
#7

Turning now to our stockpiles. During this quarter, we processed roughly 0.4 million tonnes of stockpile material, which is a significant decrease from the 1.3 million tonnes we saw in the previous quarter. The reason for this is the record times coming directly from the open pit, along with lower processing volumes during the plan in the quarter. Although we note that stockpile will continue to be an important contributor to our mill feed in FY '27, we want to remind our listeners that our remaining 1.4 million tonnes of high-grade stockpile will be blended into the mill feed evenly over the rest of the year. At quarter end, our stockpile balances totaled 21 million tonnes, containing approximately 236,000 ounces of gold and an additional 10,000 tonnes of copper, which significantly derisked the remainder of the year. Moving to projects, looking at the TSF8 Stage 4 construction, it remains on schedule for completion in our third quarter of FY '27, and this will give us capacity for processing out to the second half of FY '28. And — I'll now hand over to Mani to talk to the costs.

Monique Connolly

executive
#8

Thanks, Anne. Moving on now to Slide 9. As Sean mentioned before, our all-in sustaining cost came in at 2,925 for the quarter, which sits comfortably inside the FY '27 guidance range of 2,900 to 3,330 per ounce. That strong all-in sustaining result reflected solid cost control, robust copper output and pricing, and gold production running ahead of plan. For the quarter, our all-in sustaining cost margin came in a little above $3,000 per ounce, which works out to an all-in sustaining cost margin of more than 100%. If we look at the key operating items, mining costs came to $88 million, lower than the prior quarter even with higher total material moved, mostly because of better productivity helped by a larger share of mining volumes coming from the mill productive Stage 7 mining areas. Processing costs reached $90 million, in line with plan but up quarter-on-quarter, mainly from costs tied to the planned major maintenance shutdown in July. Sustaining CapEx came in at $37 million, in line with plan though above the previous quarter because of more underground development activity. And lastly, SatService costs were $42 million, consistent with plan and with the prior quarter's performance. Now turning to cash flow and finance on Slide 10.

Monique Connolly

executive
#9

Net revenue came in at $485 million, driven by sales of 72,000 ounces of gold along with 2,700 tonnes of copper. The average realized price on those gold sales was a touch under $6,000 per ounce. That gave Telfer operating cash flows of $289 million and a cash build of $25 million, after a tax payment of $100 million and a step-up in growth investment that followed formal project commencement at Havieron. We ended the quarter with $1.3 billion in cash, no debt, and $1.8 billion of available liquidity. As a reminder, Greatland keeps full exposure to any upside in the gold price, with downside protection coming from gold put options through September 2027 at an average strike price of 4,850. On the tax side, the $100 million paid in the September quarter was made up of June's quarterly tax installments of $64 million plus an additional $36 million in tax payments for July and August, as we shifted from quarterly to monthly installments during the quarter — so effectively 5 months of tax were paid in the September quarter. Looking ahead, monthly tax installments will continue for the rest of FY '27, based on an assessed rate of approximately 12% of revenue from the ATO.

Monique Connolly

executive
#10

Also, we expect a catch-up payment tied to FY '26 amounting to $155 million to come through in the December quarter, since tax installments won't begin until the June 2026 quarter. And lastly, depreciation and amortization came in at $73 million. For the full year, we expect depreciation and amortization to land between $280 million and $320 million, weighted toward the second half of FY '27. The rise in depreciation from FY '26 to FY '27 comes from the larger capital base set up at Talpa after the substantial investment made since acquisition, especially the underground development Stage 7 stripping and the TSF construction list. With that, I'll turn things back to Shaun for the rest of the presentation.

Shaun Day

executive
#11

Thanks, Monique. Moving over to Slide 12, I'll touch on CapEx quickly. During the period, though, we put more than $37 million into Telfagrowth capital. That's simply the continuing spend on extending mine life at Telfer. For me, the quarter's standout was finishing the second drive out to the West Dome underground. With that, the ventilation circuit to West Dome underground is complete. I think that genuinely positions us well for what we can deliver out there over the rest of the year. And you've seen that sustained investment in the open pit mining fleet that made possible 7.8 million tonnes of total material moved in the quarter, which is now a 79% increase over the open pit's productivity as measured by TMM when we first took it over. So that's just an outstanding result from the team. Going to Slide 13. The story here, I think, is really that we're in this investment phase, and you will see the genuine benefits of this investment phase flowing through in future years. But you're only beginning to see the benefit of that open fleet renewal in FY '27. You'll see it consistently through FY '28 and beyond.

Shaun Day

executive
#12

Plus there are items such as the power station upgrade. Upgrading that power station along with the switch room acts as a derisking event for us. In our view, that provides a foundation to be, once again, more derisked and more consistent going forward. Then, naturally, you have Havieron ramping up — we've completed the evaporation clearing for the evaporation ponds, plus the clearing for the blind bars, which forms a key element of the ventilation circuit in that area. You've also seen the start of tendering, and up to now that tendering has been encouraging. So we keep pushing that ahead, though we remain early in this Havieron process. I'll now move over to Slide 15. Basically, you're able to see our guidance metrics for FY '27. On gold production for the quarter, we were ahead, or slightly ahead. And we're also right at the bottom end of that all-in sustaining cost guidance. We still believe we're modestly second half weighted when it comes to ounce production, now that the the largest of the planned shutdowns for the year is behind us. I think that was really positive. Once again, the team did a good job, and it's a derisking for us.

Shaun Day

executive
#13

So all in all, our guidance hasn’t changed — whether you look at gold production, all-in sustaining costs, or CapEx. I’ll move now to Slide 16. For roughly the past 2 quarters, it’s really been about carrying out that first growth phase from Telfer. But as we head through the rest of this financial year, we believe quite a few catalysts are lining up. First, the underground drilling at West Dome, the Pinnacle step-out, extended West Dome underground’s strike length from 600 meters to 1 point — potentially 1.2 kilometers. So that’s something we’re excited about. As you’ve seen, we’ve finished roughly 12,000 meters of underground drilling in that West Dome underground zone. That’s the core area. That’s where we’ve actually driven out to. Then there’s also — we’ll go from 1 surface rig to 3 service rigs as we gain a better understanding of that extra 1.2 kilometers of strike length, which could take West Dome underground to a 1.8-kilometer strike length that remains open in both directions, plus vertically up and down and farther out to the West. But the expansion opportunity there is something we’re really excited about. Then we move on to updating the Dark resource.

Shaun Day

executive
#14

This is a pretty meaningful development for us. Right now we have 12 rigs onsite. They’ve been active for the bulk of the past 12 months, and the drill cutoff for our most recent resource update was 31 December 2025. So we view this as a substantial update, with a lot of attention on target conversion, but you’ll also see that growth, especially at West Dome underground and West Dome open pit, and we’d also like to establish a maiden resource around that name in open pit. That matters because, again, we really like that we have this life extension availability at West Dome open pit, but having the contingency, flexibility, and resilience of also having a mine plan around that main Dome oven pit is, I think, very encouraging for us. And historically, that was a notch high grade. So again, it may give us some flexibility in how we approach that. We then move into the studies, the West Dome underground. That should be the first cab off the rank. It’s really a Phase I study because we’re just going to be looking at where that 12,000 meters of underground drilling has gone into that first 600 meters of strike length.

Shaun Day

executive
#15

But with those 2 drivers in place, work has already begun on the third one — the haulage drive — going straight back to the underground crusher and then up the hoist to surface. That drive carries a lot of latent capacity. Its rating is 6 million tonnes per year. Right now, we've been using it for 1.25 million tonnes annually. So having this high-grade opportunity is genuinely encouraging. Next we turn to the vertical software study. It sits beneath the old sublevel cave. Once more, we believe there's a chance to potentially bring it online. That material amounts to about 35 million tonnes, and it holds certainly well north of 1.2 million ounces. And again, we could bring it up through that late infrastructure — meaning the underground crusher and hoist. So those studies, in my view, are really encouraging. After that, we should complete our jaws reserve. That positions us to really begin describing how a long-term integrated intel and have Ron look together. And then last, obviously, we have this world-class Acalaans tungsten deposit — we're examining multiple ways to unlock value, but unpacking it during the course of FY '27 is certainly a focus for us. With that, I'll now just move to the summary slide, which really just covers this being a strong quarter in terms of north of 70,000 tonnes of gold production, plus the outperformance on copper and a bit of a derisking event in terms of the processing infrastructure Haveron is now underway.

Shaun Day

executive
#16

We secured those secondary permits. So at this point we're essentially ramping up, and we're genuinely delighted, and it's a tremendously hard-working team. With liquidity and a strong treasury position — $1.3 billion of cash at bank, no debt — plus undrawn debt, that gives us $1.8 billion to deliver that growth, that portfolio of growth projects, and worth highlighting as well that not only West Dome underground but we're now also underway at Havieron. And then finally, look, we still have 12 rigs turning on site and the chance to update that Joc resource, cork reserve, and then be in a position to describe not just a multi-decade mine life at Havieron. But both Telfer and Havieron as a gold copper mining complex, with multi-decade life. With that, and just before I hand back to Paul for questions. We do have our new COO on deck, Nick Strong. We're delighted to have Nick with us, he joins us from Northern Star, but he's really hit the ground running over the -- since joining at the start of this, I've spent a lot of time with the team at site. And it really completes that executive team. But also I'd like to just acknowledge to who's done a magnificent job as COO over the last 3 quarters, and you can see the success we've had Autos has also been very focused on our long-term mine planning.

Shaun Day

executive
#17

He’s going to keep the Chief Technical Officer position, and that will be where his attention sits — really acting as the connection between the auto operation and these various open pits and multiple underground production centers, drawing them into mine planning and into the life of mine. Then it hands over to Nick for execution. So the way Nick and Otto work together is going to be a really important part of how we move forward. And I think it’s been really encouraging to see that since Nick came on board. So with that, I might just hand it over to Nick here and ask him to share his first impressions now that he’s joined Greatland’s month.

Nick Strong

executive
#18

Yes. Thank you, Shaun. So, as Sean said, I came on board at Greatland roughly 3 weeks back, on the fifth of October, and I've been mostly at the site during that period, familiarising myself with the team and getting up to speed on the operations. What strikes me first is that we have a genuinely strong and motivated group here, and both the operations and the infrastructure are in very good condition. It's an exciting moment to be part of this, and there is definitely plenty of work ahead as we aim to substantially improve our mill feed through the delivery of several high-grade underground growth projects. The main areas I'll be concentrating on in FY '27, I think, are operating discipline and risk management, given that we're managing several expansion fronts while continuing to deliver against the FY '27 plan. Havieron is clearly a growth front for us. That said, Telfer underground seems to have a great deal of life left in it, and it's a very exciting place to be operating and expanding right now. I want to express my appreciation for Otto, who has done an excellent job leading our operations since February, and that shows in these operating results. Otto and I will be working closely together going forward as we plan and execute the integrated Telfer have online plan.

Nick Strong

executive
#19

I'm really looking forward to engaging with all of you investors and analysts. My friend is now at the desk, and things have gotten off to a great start so far. Thank you, Shaun.

Shaun Day

executive
#20

Thanks, Nick, and welcome to Board. So with that, Paul, let's go ahead and open things up for questions.

Operator

operator
#21

<<operator_script>> The first question comes from Kate McCutcheon at Bank of America.

Kate McCutcheon

analyst
#22

Nice work on the new Ronick. Just to clarify, the September quarter, when annualized, comes in under the CapEx ranges in the full-year guidance. How should we think about the cadence across the next few quarters for that Telfer growth CapEx?

Shaun Day

executive
#23

So for Telfer, I see it as a gradual build through the year. It picks up somewhat over the course of the financial year, in my view. You'll likely notice that we're running as well, naturally, as the year unfolds. Still, we ought to remain inside that guidance as it stands today.

Kate McCutcheon

analyst
#24

All right. So, Haveron, I realize you're only just beginning with tenders and so on, but set against what you expected at the time of that FID, are there particular areas where you're ahead of schedule? And on the flip side, any areas that I suppose need some catching up?

Shaun Day

executive
#25

Okay, so we're 3 weeks in, and I'd say the setup is spot on. That said, I think you should give us perhaps one more quarter before we try to identify any divergence. But so far, what I find impressive is that permitting came through at 10:00 Australian Western Standard time on a Friday, and by 3:30 that same afternoon, work had begun. We'd been in frequent contact with the EPA and the National EPA, so we had a sense that this was coming that week. We spun off during the week, so we got off to a genuinely strong flying start. Probably the other key item for us — I think the surface works are going to schedule. I think the other element, which I believe will play itself out, is the tendering we're currently doing to get some of those EPCs squared away. So far it's encouraging, but again, give us a little time to get them contracted before we start being too definitive.

Operator

operator
#26

The next question is from Levi Spry, who's on the line from UBS.

Levi Spry

analyst
#27

Shaun, could you walk us through what comes next in a bit more detail? Just to confirm on the permits — what's still outstanding? Are any activities outstanding, and what's happening for the rest of the year? And then this year, you brought up the EPC for tendering — what are the big ones on the horizon?

Shaun Day

executive
#28

Yes. Thanks, Levi. Look, in terms of — well, let me begin with the terminal: every one of the secondary permits is now in place. So effectively, we're actively working both at surface and underground there, and indeed doing — starting the process for upgrading the haul road back from Telfer to have Ron, and indeed doing the plant modifications at Telfer. So everything is spinning up. What you've seen initially, the focus for us is the worth the evaporation pond that surface — you might recall we're just sitting above that lower confined aquifer. We wanted additional evaporation pond capacity so that we could pump through that <<inaudible>>. So that's effectively been the focus for us with that clearing. We've also been doing the blind pool pads. Those blind flows are also on the critical path in terms of getting that ventilation down into that underground before we do stoping. So that's encouraging in terms of the underground decline itself. Just to remind people, we are 340 meters vertical because this is already effectively half filled. So we've started moving that forward. But again, it's very measured progress until we actually have those evaluation ponds or at least evaporation ponds online, which is still more at the end of October before we have that actually online.

Shaun Day

executive
#29

And as far as tendering goes, that work is already in progress. The EPCM tender has been finished. Then there's the haul road, the mill modifications, the power line, and the blind boards. Under the 80/20 rule, those are likely the 5 main contracts that come to mind. We've got the blind boards secured with <<inaudible>>. That's again largely in line with the study vagaries — an Australian group, 1 of probably the 4 top blind ball organizations globally. They're heavily involved in that Hunter Valley. We believe they're very well positioned to partner with us. And bear in mind, windborVR1 is already in place, so this is essentially adding VR2 and VR3. The power line, the haul road, and indeed the mill modifications are all tenders currently live. So we feel positive about where things stand. But yes, as I mentioned to Kate, just allow us weeks and months to actually obtain those outcomes before things are more definitive. Hopefully, though, that gives you fairly good color on where we are with that.

Operator

operator
#30

The next question is from Adam Baker at Macquarie.

Adam Baker

analyst
#31

Sean — and Nick, welcome. Thanks for the update. Maybe just touching on the underground volumes for a moment. I mean, that was a pretty solid performance during the quarter; 378,000 tonnes looks like your best underground result in 3 years. And you also noted record development meters during the quarter, over 2,000 meters. So I'm just wondering, could that flow through to higher state volumes in the quarters ahead? And what are we expecting from underground volumes for the rest of the financial year?

Otto Richter

executive
#32

Yes, this is Otte, and I’ll handle that question. As we look at the balance of the quarter, the trend we expect is quite comparable to the one we see right now, particularly when it comes to ounce production. Telfer underground really delivers a broad spread of mineralization—anywhere from narrower zones with fewer tonnes and better grade to wider areas with more tonnes at a lower grade. At present, as we’re developing the West Dome underground, our emphasis is on extending the areas we already have, but we’ve also devoted some attention to the ESC during the past few quarters, and today that ranks among our key production areas. So in terms of the ounce profile for the rest of the year, we anticipate it staying steady, and as I mentioned, it will be a blend of higher tonnage at lower grade and lower tonnage at higher rates, depending on which areas fall in the mining sequence as the year progresses.

Shaun Day

executive
#33

And adding to that, Adam, I believe the genuine breakthroughs will come once we bring the West Dome underground into operation. Otto is, of course, heading up the study on that front. But it represents a wonderful coming-together of very high grade — the best grade Telfer has recorded since 2005, or an even higher average grade — plus a separate mining area, which I think will let us lift terms. That is precisely why that dormant infrastructure matters, with an underground crusher and an underground hoist rated for 6 million tonnes. We are currently using roughly 25% of that capacity. So we view the capital intensity of getting West Dome underground up and running as highly attractive. At present, we expect that in FY '28. Still, the development progress out there has been very encouraging. And then, naturally, given Nick's background and pedigree, we are eager to turn him loose on that underground too.

Operator

operator
#34

The following question is from David Radclyffe at MR.

David Radclyffe

analyst
#35

My first question is really just a follow-up to what Kate asked regarding the Telfer growth CapEx. That figure is clearly running well under the guidance pace, and to reach that level you would probably need to average around $100 million across the remaining 3 quarters. So if I may press a bit further just to get a clearer picture of what is going on there: is the spending running behind schedule, and if that is the case, what is causing it?

Monique Connolly

executive
#36

I'll take that one. Basically, growth CapEx at Telfer was always going to be somewhat slower in Q1, simply because we were looking to place some low lead items. So it's definitely a ramp-up that was planned across the remaining 3 quarters of FY '27. I'd also point out that we have roughly $25 million of CapEx spend on the mining open pit fleet that we've already spent, but it hasn't yet been converted into CapEx — purely from an accounting perspective, we treat that as a prepayment until it's delivered to site. So those long lead items, while we're progressing them, just haven't actually hit CapEx yet. So I think we're very much on track to meet the guidance for FY '27 with a lower.

Shaun Day

executive
#37

And importantly, regarding what Monique said, the cash has been spent, though it shows up in prepayments rather than in CapEx.

David Radclyffe

analyst
#38

Yes. No, I understand. That's actually — that's quite useful. So perhaps a follow-up on that. I mean, you said the ventilation work at West Dome is finished now. The plans point to '28, but it really does feel as though it could arrive much sooner. So what still needs to happen at West Dome before we get any production this financial year instead of next?

Shaun Day

executive
#39

Let me break my answer into two parts. First, we're completing this third drive. It's going to be a dedicated haulage drive, roughly 1,500 meters of development, and it will carry ore straight back to that underground crusher in voice — which we see as an elegant, eloquent long-term training solution. At present, with that ventilation and the two drivers, we have access. My sense is we'll fit 4 headings in there, and we believe those can be productive. We sit about 280 meters away from that ore body. So the drilling we're doing right now matters most — it's about placing that infrastructure in the best possible position so West Dome underground delivers efficiently across the medium to long term. If we chose to, we could likely drive in a bit faster. But at this moment, doing it well is what counts. In terms of gray and volume to that Telfer underground, this could be transformational. It's simply that record quarters aren't our focus — consistent delivery is. So while we're feeling genuinely pleased with where we stand and could probably consider speeding things up, and maybe there's a small amount of development ore in that June quarter, which isn't in our budget or plan, that's definitely the opportunity available to us.

Shaun Day

executive
#40

At this moment, though, the priority is making sure we do it properly.

Otto Richter

executive
#41

And from a static standpoint, if I could just jump in here — that infill drilling is scheduled to continue until approximately year-end. That will subsequently provide us with our resource update. And should you review the earlier resource released for waste per miner ground, there is a substantial resource requiring conversion into reserves. So, as Shaun mentioned, we are simply awaiting completion of that drilling, receipt of the assays, revision of the resource model, and then finalization of the study within this Phase I process to complete the reserve and the placement of that major infrastructure — and then we wait with considerable anticipation for the remaining Pinnacle sales to arrive.

Operator

operator
#42

Daniel Morgan from Barrenjoey has the next question.

Dan Morgan

analyst
#43

Is there a plan to increase output in the December quarter? I simply hadn't worked that through. There's no mill shutdown — the mill has been shut — and mining productivity has clearly been getting better. So I suppose it comes down to what you expect for grade and recovery. Could you just address the December quarter?

Otto Richter

executive
#44

I’ll respond to that in 2 ways. As you noted, clearly the mill isn’t shut, so we aren’t factoring in downtime from mill time. We’re heading into the beginning of our wet season, and that has to be considered. At present, we’re planning a modest increase in throughput compared with the first quarter. As we’ve mentioned before, we are somewhat weighted toward the second half of the year. At a high level, though, I think we’ll see a modest increase over the first quarter but largely in line from an ounce production profile?

Shaun Day

executive
#45

Yes. And just to build on what you said there, Daniel, I believe the genuine increase arrives during the back half of the year, including Q2, subject to — we've likely surpassed the mining productivity levels we had forecast and budgeted, especially at that open pit, which again reflects very well on the team. As things stand, though, our forecast assumes a somewhat larger amount of stockpile feed in that second Q. Regarding what you observed in the September quarter, I believe we drew only 300,000 tonnes of stockpile feed, a touch under 300,000 tonnes. The high-grade stockpile, as you saw, essentially stayed flat at 1.4 million tonnes. There is some — we do treat it partly as working capital, so to speak. So tonnes go onto that stockpile and tonnes come off it. Still, we're pleased with how things are progressing. That said, we probably formally expect that increase to truly materialize in the second half instead of the December quarter. But if we can hold the productivity we achieved in this first quarter, that puts us in a strong position.

Dan Morgan

analyst
#46

Regarding that point about mining productivity compared with filling the mill — obviously, this is a major year of investment to bring new ore sources online. I'm just wondering, conceptually, when do you think you might be able to fill the mill from fresh ore, or is that FY '28?

Shaun Day

executive
#47

Thanks, Daniel. I believe we're at just under 5 million tonnes — pretty close — and 4.7 million tonnes of that was fresh ore. So yes — and do we have 21 million tonnes of stockpiles sitting there? So when we draw it down at 300 tonnes a quarter, that gives us a plus 20-year kind of stockpile. So yes, we feel that's beautiful, both for derisking and for consistency of performance. We really like that. But again, if we can bring on the West Dome underground, if we can keep that improvement going in open pit productivity for FY '27, we still forecast using some of the stockpiles. And then, of course, in time, there's also the potential to bring on Havieron underground, and the turn back on that BSE. So we think we have multiple pathways where we're not using that stockpile and it's just a long-term buffer for us. And we love the idea of having it there. But there are multiple pathways where, through productivity, through bringing on West Dome underground, the VSC and Havieron, we effectively park up those stockpiles into the more medium to long term.

Otto Richter

executive
#48

Just to remind everyone, while July was the biggest shutdown we had, there's also one in November. It's smaller, yes, but we aren't heading into the next quarter with no shutdowns at all.

Operator

operator
#49

We'll now take our next question from Hugo Nicolaci at Goldman Sachs.

Hugo Nicolaci

analyst
#50

Okay, first, regarding a few of the earlier questions. Perhaps we could begin with the open pit. You mentioned the strip ratio for Stage 7. Could you speak more generally about how you expect total material movements from the open pit to develop through the remainder of the year?

Otto Richter

executive
#51

Right now, material is being sourced from 3 stages: Stage 7, Stage 8, and Stage 2. Our 2 deeper stages are Stage 8 and Stage 2, and that is where most of the higher grade ore comes from. If you check Figure 1 in the release we posted, you can see that. And then, clearly, Stage 7 is what opens up the bigger surface areas. So for the rest of the year, most of the material movement will come out of Stage 7, but the high grade is mainly from Stage 2. So Stage 8 is nearing the end of its life, and it is now tied into Stage 2, and the higher grade will come from Stage 2 — obviously, the longer haul and a somewhat higher cost. And then, well, our main focus will shift to Stage 7 in terms of volume opening up, putting in 2 diggers up at the top toward the second half of the year, opening up the front in Stage 7 and bringing that down to where the high grade in Stage 7 kicks off?

Hugo Nicolaci

analyst
#52

That's useful context, thanks. Now, along similar lines regarding the underground pace: looking back historically, my understanding is that your 2-year outlook had planned underground material for '26 and '27 at roughly 3.5 million tonnes. Clearly, various industry ratings around productivity and availability could be affecting that. Could you speak to the tonnage rates you anticipate as the Telfer underground continues ramping up from here? And what exit rate do you expect by the end of FY '27?

Otto Richter

executive
#53

We anticipate an increase of roughly — just estimating offhand — around 30% above our current output by late in the year, coming from underground. That said, it hinges on how we develop those underground faces; the ESC is at full production right now. So we had been directing considerable development effort there previously. Then in the deeper section of the mine, most of what we produce originates from Aries, with a smaller portion from the Bay area. For underground operations, one major priority is the copper that underground supplies to supplement the open pit copper feed. Consequently, we evaluate those areas not solely on gold grade, but also for the copper they contribute and how that blending affects the open pit ore.

Hugo Nicolaci

analyst
#54

Thanks, that's useful. Then perhaps just on the copper pace. If you look at some of your peers lately, they've reported very strong realized prices for the September quarter, roughly around professional pricing and matters on copper, while you were probably more in line with the quarter average. Could you just remind us what your quotational periods are on the Copico.

Shaun Day

executive
#55

Shaun speaking. We don't generally disclose specifics about our offtake arrangements. What I can tell you is that no long-term offtake agreement exists, so we can take full part in the market, and that's a major advantage. And yes, I'd say it's genuinely a fairly strong strategic asset for us that we produce this copper concentrate. I think people sometimes overlook that within our peer growth we're a copper producer too. The TCRCs, the pricing, the payability on it are really appealing. That said, there's gold in it as well — it's a gold copper concentrate. So it also matters to us that we keep focus on the return we get from that gold content too. But we believe pricing on concentrate sales will keep getting better. And I think if you look at us, we follow the market quite closely, which demonstrates there are no unusual quotation periods in what we hold. And yes, I sold a couple of kind during the late 2000s, when the copper market saw a big correction. So I think I grasp some of the risk profile that goes with that.

Shaun Day

executive
#56

And I believe our strategy for selling copper concentrate is quite low-risk at this point.

Hugo Nicolaci

analyst
#57

And just to be clear on one last point, your integrated Tehan study is now expected in the June half of next year.

Shaun Day

executive
#58

When you ask about that — I think the step we'd have to take prior to releasing an integrated study is finishing the draw reserve. As you know, that serves as the basis for us building out the life of mine at Telfer, which is scheduled for roughly May, June 2027. So this year, we clearly already need to have 1 element settled through that feasibility study, at the stage where we can combine them. That said, I wouldn't characterize it as us raising to get it out. We'd want to be sure we put in the time to get it right. Yes, making certain we work through the nuances and how we present it. But I believe we'll have every building block required in place by May, June 2027.

Operator

operator
#59

<<operator_script>> Our following question comes from Ben Lyons, who is calling on the Jarden line.

Ben Lyons

analyst
#60

Sean, Monique, and Otto — a fast 1 on Haveron, if I may. Apologies in advance if I got your remarks about where things stand wrong. Did I hear you say the underground mining contractor at Havieron is being retendered? Donatas has clearly been up there for many years, on standby for the decline to restart, right? If that's the case, how are you balancing the chance to maybe shave a few bucks off costs against reducing the risk posed by potentially difficult brand conditions? Thanks, Shaun.

Shaun Day

executive
#61

Ben. No, I didn't say Dan handles that Dona role — you're right about that. Look, we feel very confident about the work with Bernat. I noted earlier as well that the 340 meters vertical was accomplished alongside Bernard. What we've really aimed to do with Bernard is reassemble the band, so to speak, by bringing in many of the people from that team who had been through Havieron before. So in our view, that track record, that know-how, that experience helps reduce the risk, given they've already been through the upper consigned aquifer, been through the middle confined aquifer, and are now moving into that low confined aquifer. We believe the proper balance of risk management is to do that once more with Bernardo at Telfer. So we've had some of the advantages of being able to swap personnel and equipment between the 2 sites, which has also proven useful. So at this point, we're quite comfortable with Bernard. I think once we get through the Tanium layer and down to those beautiful rock conditions in the basement rock, then I think we can truly consider this from first principles. But look, we have a good relationship with Denka.

Shaun Day

executive
#62

They've performed well. We hold them in high regard — in my view they're likely the top underground contractor in Australia. So the relationship is a solid one, though of course we're always looking to make it as efficient as possible. And as you put it, should a chance arise to trim some costs down the road, that's something we'd want to act on.

Operator

operator
#63

We'll now take our following question from Branco Scocic, who is on the line from JPMorgan.

Branko Skocic

analyst
#64

Starting with the Tungsten topic — I wanted to ask how far along those talks about the calendar are, since it does look as though the timing has shifted somewhat toward the later portion of this financial year. And I'd also be curious whether they've received any inbound interest from governments or quasi-government bodies regarding the asset.

Otto Richter

executive
#65

Yes, thanks — I'll take that one. Sorry, just a quick reminder regarding the helicals at Tungsten deposit. Discussions are ongoing, and look, I'd rather not name any parties or get into specifics here. I think, as we mentioned on the previous quarterly call, we were anticipating a result within this financial year, and that's still the situation. We're very focused on it, and every option remains open on that front. So that spans anything from a spin out to a possible divestment, or perhaps a joint venture. Our aim is to optimize and maximize value for our shareholders, and we're intentionally being patient. We don't want to force an outcome we wouldn't be happy with. So that's roughly where things stand. We continue to target a result within this financial year.

Branko Skocic

analyst
#66

Okay, thanks. And going back to the FY '27 guidance: I'm just curious why you haven't felt comfortable raising it, or at least tightening — narrowing, I should say — the range, given how strong the first quarter of the year was.

Shaun Day

executive
#67

Branko, I'd take that as a compliment — it was a solid first quarter. That said, we're only 1 quarter in. So give us a bit of time here; there's still a way to go, though it's an encouraging start. Still, at this point, 1 quarter in, we're genuinely pleased in the sense that I think we're derisking delivery of that guidance, and then we'll go from there — but one step at a time.

Operator

operator
#68

That brings today’s question-and-answer portion to an end. I’ll now hand things back to Shaun so he can offer his closing comments.

Shaun Day

executive
#69

Thanks, Paul. I just want to express appreciation to everybody who joined the call. We value the time you’ve given us and the truly strong standard of the questions. So thank you for taking part and reading through the materials, and thanks to the team here for organizing this. Thanks once more, and we look forward to connecting again in the next quarter.

Operator

operator
#70

That wraps up today's conference call. Thanks to everyone for being with us. You're free to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Greatland Resources Limited transcript — plus 130,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Greatland Resources Limited earnings transcripts and 130,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Greatland Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.