Rubén Gómez Martínez
executiveGood morning, and welcome to the first half 2025 results presentation for Grenergy Renovables. I'm Rubén Gómez, Head of Investor Relations. Our Chairman and CEO, David Ruiz de Andrés, will lead the presentation, along with Daniel Lozano, our Chief of Strategy and Capital Markets, and Rocío Fernández, Head of Sustainability. Together they will walk you through our business, financial, and sustainability review. At the end of the presentation, as usual, there will be a Q&A session for sell-side analysts. Please remember to ask just one question per participant. Okay, David, the floor is yours.
David Ruiz de Andrés
executiveThanks a lot, Rubén, and good morning, everyone. We'll begin, as usual, with the business highlights on slide number three — the key highlights from our first half 2025 results. Above all, it's really important to point out that we continue converting, as we like to say around here, rotation into value. It's very encouraging to see substantial appetite for our hybrid assets in Oasis of Atacama. We're bringing major players to the table, such as ContourGlobal, a KKR company, and most recently DIF, which is part of CBC. In early September, we announced the rotation of Gabriela. That's phase four of Oasis of Atacama. As you're aware, we sold a total of 272 megawatts of solar and 1.1 gigawatt hours of BES to DIF at an enterprise value, earnouts included, of approximately $475 million. The transaction multiple came in at 1.8 times invested capital. Delivery of the asset is scheduled for the first half of 2026. We're hopeful it will be operational as soon as Q1, with COD reached in Q2 of next year. The plan is going well, construction is progressing very well, and we're already very near mechanical completion. Through this operation, as you know, we will have divested phases one through four of Oasis of Atacama at an enterprise value of roughly $1.4 billion, which, as we've said, accounts for approximately 33% to 34% of the overall project size.
David Ruiz de Andrés
executiveLet me stress again that what we're selling is a 100% stake in the projects — not a participation across all of them. If you look at the projects we've rotated, they represent only 33% of the total megawatts in the project. Through this transaction — and this is one of our key KPIs — we've now reached 55% of our asset rotation proceeds target. Keep in mind we spoke about €800 million, as laid out at the Capital Markets Day three months ago. For us it's a highly important KPI. Along with our CapEx targets, I'd say these are the most critical KPIs we're focused on right now. It matters a great deal to us that we're already hitting more than 55% two and a half years ahead of the target. Also — and this is a significant milestone, announced recently, two weeks ago — we closed financing for 3.5 gigawatt hours of BES. This is the biggest BES plan we've done to date at a single location, and it's phase six of Oasis of Atacama, which we call Elena. We raised $270 million from a syndicate of four banks. As you know — and we'll walk you through it later — we expect this plan to be operational in the first quarter of next year, which is at least two quarters sooner than originally anticipated.
David Ruiz de Andrés
executiveI think that's really crucial for us. Greenbox was introduced by us at our Capital Markets Day. We're making strong progress. It may be the most thrilling project that lies ahead of us, correct? As you're aware, it will be split across six countries. It's our separate division for Europe. As you know, we're building one of Europe's largest standalone pipelines, presently at 32 gigawatt hours. We're moving forward. Many of these projects, as I'll now explain, are at an early stage, and you will see them. BES projects typically progress quicker than PV projects. In upcoming updates, you'll notice that certain of these projects have already reached advanced development. As you know, our flagship project is in Spain — Oviedo — with 150 megawatts of capacity. Our target is to install four hours. In total, that comes to 600 megawatt hours. We expect to announce a tolling agreement very soon. We'll also announce the banks we are mandating for this project. On our financial highlights, Daniel will provide you with far more detail, right? I believe we've achieved quite solid service results. It's been affected very favorably by the M&A deals of Oasis of Atacama. During the first half of the year, revenues rose 128% year on year.
David Ruiz de Andrés
executiveEBITDA came in at €86 million. Of that total, €76 million was contributed by the M&A transaction. Net income was €35 million. Gross CapEx totaled €421 million. For us, that is a hugely important KPI. It's almost 127% above the figure for the same period a year earlier. We're nearing half a billion within a single semester, correct? That should give you a sense that we're truly hitting the cruising speed we've been aiming for — at least €1 billion of new CapEx annually. As you'll recall, our goal stood at €3.5 billion across the coming three years, 2025 included. My sense is we're almost there. I'd expect us to pick up pace during the second semester. Turning to net debt, it stands at €815 million, consistent with the quarter's rise in net CapEx. That's essentially what we had anticipated. Total leverage is 3.8 times against 6.6 in the equivalent period last year. Corporate leverage fell to 1.3 times. Finally, a redemption of 2.44% of share capital took place following the latest share buyback we carried out in the first part of this year. To wrap up this slide on ESG, I believe Rocío will go into more detail later. We take real pride in noting that our biodiversity policy has now been published.
David Ruiz de Andrés
executiveWe earned an A- in the CDP 2024 Supply Engagement Assessment. We joined the EBEX ESG Index, which I think is great news. As you know, we hold the top rank in our industry across most of the most relevant ESG ratings, including S&P, MSCI, and Sustainalytics. Turning to slide number four, this is where we show our platform overview for solar, hybrid, and then on the next slide, standalone projects, which we unveiled at the last Capital Markets Day. Before diving into details, I'd like to start by sharing some context. You know, we've carried out a very in-depth review of our entire pipeline. This has led to some adjustments. As you know, we really want to optimize our investment allocation. I think it's very essential that we focus on these projects where we really believe we have high chances of success, right? We have a high degree of confidence. We want to focus on developing projects which can achieve really ready to build in the next two to three years with good returns and real opportunities for securing PPAs, right? In parallel, we are relocating some resources, moving some development resources from purely solar PV to more hybrid and standalone storage projects where we are definitely making high returns at the moment, right?
David Ruiz de Andrés
executiveAs of September 2025, our platform stands at 12.5 gigawatts of solar plus 72 gigawatt hours of BES. That number matters a great deal, I believe — and 35 gigawatt hours of it comes from hybrid projects, while 40 gigawatt hours is standalone. Worth noting: altogether that adds up to a really impressive BES pipeline exceeding 70 gigawatt hours. Over on the right side of this slide, our three core geographies are laid out. There's Latin America, with Chile at a very high %, leading in solar and hybrid plant capacity. Europe takes the lead on standalone through our Greenbox platform. Let's move to slide number five — we won't linger there too long. As you're aware, transparency is something we take seriously. We refresh the breakdown by geography and by country. Here you can see we continue making headway on hybrid projects in Chile with Oasis of Atacama and Frontal Oasis, and in Spain with Escuderos. Our optimism about Chile genuinely remains strong. Stakeholder appetite for contracting energy looks very robust to us. Further development potential exists, in my view. There are fantastic money opportunities, as demonstrated by the project we acquired from Repsol and Ibereolica last year.
David Ruiz de Andrés
executiveThe market looks genuinely, genuinely strong. In my view, Chile is beginning a really, really favorable cycle, with substantial investment flowing into new mining projects and a highly promising data center sector expanding rapidly across the country. They require a great deal of energy, correct? We observe that the country's growth in energy consumption is extremely, extremely encouraging. Turning to slide number six, a very brief update. This is the pipeline I mentioned earlier. You can see the 600 gigawatt hour figure, right? That one corresponds to the Oviedo project. After that, we have the remainder at close to 40 gigawatts, and those are progressing across the six geographies in Europe, chiefly where we operate, correct? As I said before, I think that when we refresh the pipeline in November, you'll notice that a number of these projects are set to enter advanced development. I believe we have a highly consistent business plan covering the period from 2026 through 2028, on a standalone basis within our Greenbox platform. On slide number seven, we typically present the key figures and planning for the entire Oasis of Atacama. As you're aware, that amounts to a total capacity of 2,000 megawatts, 2 gigawatts, and 11 gigawatt hours. Keep in mind, when this project was first unveiled at the initial Capital Markets Day we held almost two years ago, its capacity stood initially at merely 1 gigawatt and 4 gigawatt hours.
David Ruiz de Andrés
executiveRight now, the platform has doubled in size to 2 gigawatts of solar, and storage has tripled to nearly 11 gigawatt hours. Our performance and execution are very strong. We've rotated phases one through four of the project. Kigawa one and two — the first two phases — are connected and operating, and both platforms are doing very well. Pictor Hara remains really well on track. All the batteries are installed already, and we expect interconnection very, very soon and COD before the end of the year. Gabriela is also moving forward ahead of expectations. All the batteries, in this case from CATL, are already on site, and we expect the connection in the first quarter of 2026. We're very happy. We are executing and arriving at and reaching COD of these very large assets above initial expectations, right? If you compare to PMDDs, the type of projects that we were mainly doing before, we are executing earlier. Everything is on us. The problem we had before with the small distribution assets is that we had to rely on distribution companies for interconnection. In the case of large projects, everything is on us. We are performing really well. We are delivering ahead of estimated dates, at least in the first four phases.
David Ruiz de Andrés
executiveOn Elena, phase six, we're going to roll it out in two stages, correct? It's a plan where the interconnection was already constructed, along with the substation interconnection line. 77 megawatts of solar were already operating there. At first we're installing battery capacity of 3 gigawatt hours to shorten the time to market. I think that's really important. That's the reason we've signed this $270 million financing. Let's call it a bridge to PPA. We have roughly a three-year financing. We're working very intensely on the PPAs. As soon as we sign the final PPAs, which I think will happen during this year, we'll move toward refinancing this project. We'll build the PV part depending on, right? That's the plan. I think it's the right strategy for this large asset. On phase number five, Algarroal, we're making progress on the PPAs. I think we may announce them very soon. We believe it will be a basket of two or three PPAs. I think definitely before the end of the year, we'll announce the PPAs for this plan. We're mandating the project finance. Only phase seven will still not be mandated at the end of this year. Turning to slide number eight, we saw the main achievements.
David Ruiz de Andrés
executiveI believe you know most of these quite well. I won't take much time on them. As I said earlier, Kigawa one and two are linked together. At night they're selling energy. We sold Gabriela. The financing for phase six has been closed. We're making progress on PPAs for phases five and six. Financing for phase five will be mandated very soon. All of it is going quite smoothly. Slide number nine. This is something we take real pride in. Taking Elena into account, we've already raised $1.2 billion in project financing together with 12 top international banks. The big names, I think, are all there. The most recent development was that more banks joined the syndicate for Gabriela for phase four. Among them are Rabobank, EIB, Bank of America, BBVA, JP Morgan, KFW. I think what we're accomplishing makes us very proud. Nearly every international bank that's active in project finance is now present in Oasis of Atacama. Most of these lenders show a very high level of interest in working with Greenergy on new projects. That, I think, is very good news. Slide number 10. We've included, I believe, what's relevant here. This is the newest slide, and it gives more detail on the asset rotations we've completed for phases one to four, which brought an enterprise value of $1.4 billion.
David Ruiz de Andrés
executiveAll told, those deals implied 723 megawatts of solar plus 3.6 gigawatt hours of BES, correct? The most recent sale implied an enterprise value-to-invested-capital ratio of 1.8. At Kigawa, we hit 1.5. Victor came in at 1.7. That's far above the 1.3 guidance we provided for Capital Markets Day, which in our view was conservative. It was solid, yet conservative. We're demonstrating that we're achieving much higher ratios. A brief recap on Central Oasis. It's akin to a new — well, not new, but it's the platform we laid out at Capital Markets Day. Its size resembles what Oasis of Atacama had at the outset. We're examining M&A opportunities to grow it further. Central Chile has very high energy demand, and we think it must be addressed through projects in the center, right? We present the key data here, and the bulk of the platform is already contracted. I believe the next mandate after Elena is already underway, and that's Gran Teno Tamango, where we're hybridating those plants, along with Planchon, a plant next door to Gran Teno. The mandate immediately following will be Algarroal in Oasis of Atacama and Monte Aguila phase four here, right?
David Ruiz de Andrés
executiveAs you can see, this remains an ongoing process. Once more, we're raising funds—there's substantial appetite coming from lenders—and these projects are already under contract. Things are progressing very well. We're just finishing up. Again, we're showing—I don't want to dwell on this too long—but we've addressed every point regarding the key achievements of Oasis of Atacama. Moving to the next slide, to wrap up, we present our inaugural flagship Greenbox project located in Oviedo. For anyone unfamiliar, that's a region in northern Spain, and its capacity stands at 150 megawatts and 600 megawatt hours. We believe it will be the first large standalone project in Spain. Once again, we anticipate announcing the tolling agreement very soon, and we're on the verge of mandating a syndicate of banks. There's extremely strong interest in financing this inaugural large project in Spain. I believe we will once again be pioneers in signing a tolling agreement for standalone batteries in a country such as Spain. On the construction side, we expect to begin construction as early as Q1 next year. We're already locking in some of the main components on traffos. This is something we do quite frequently—that ahead of the official MTP, we already secure some of the materials with the longest delivery times, right?
David Ruiz de Andrés
executiveThanks a lot. I'll hand things over to Daniel for the financial review. Thank you.
Daniel Lozano Herrera
executiveThanks, David. Let's now review how the company performed operationally in Q1 2025. Total installed capacity fell 4%, going from 950 megawatts down to 914 megawatts, which is explained by the assets rotated in Chile. On production, we saw a 36% rise in total output. That gain came mainly from Gran Teno Elena, at 77 megawatts, and to a lesser degree from PMGDs and Tamango. Contracted volumes were up 62% and accounted for 87% of our total electricity production. Our business model takes a conservative approach, closing PPAs for most of what we produce. Realized prices dipped slightly, to €44 per megawatt hour from €45 per megawatt hour, partly affected by the Forex dollar-euro difference. Over on the right-hand side, there's a summary of the key financial KPIs, and we'll go through those on the next slide. Turning to slide 15, total revenue for the first half of 2025 came to €438 million, an impressive 128% increase year on year. That growth was largely driven by the successful M&A transaction through asset rotation in Latin America, as you know, which contributed significantly to a plus 149% growth in the development and construction division.
Daniel Lozano Herrera
executiveOn energy revenue, it went up 33%, primarily because of the Chilean assets. The power division posted 103% organic growth, while the service division saw a slight decline of 8%. EBITDA for the first half of 2025 came in at €86 million, an impressive 176% increase, which shows we can rotate assets successfully while continuing to grow the portfolio. Turning to slide 16, CapEx. As David mentioned, this is impressive. In the first semester last year, we had €186 million. That was nearly the same figure as 2023. In this first half of the year, we're hitting €421 million. That's more than double, driven mainly by hybrid project construction in Chile, which proves execution is well on track toward the business plan we presented in May. As the chart shows, almost half of the invested amount belonged to Oasis of Atacama, first three phases, already sold, plus another €155 million in hybrid projects in Latin America. The rest of the CapEx goes mainly to Spain, into the project we're building. A further €18 million went to development initiatives across our three main geographies. On slide 17, cash flow, as of June 2025, our cash position reached €283 million.
Daniel Lozano Herrera
executiveOur cash position remains solid even as we ramp up CapEx, which we're doubling versus last year. As you can see, CapEx has been the biggest outflow, at $421 million. That said, a portion of the CapEx we're investing was previously agreed to be sold for phase one, two, three of Oasis of Atacama. We also carry more financial debt, mostly project financing from deals we're successfully closing, plus a minor corporate impact from Forex of $42 million. With the cash we currently hold, along with the expected project finance still to come, M&A deals already signed, such as Tabernas and Jose Cabrera, that should land in the coming months, and the sale of Gabriela, we have sufficient cash to continue self-funding our business plan. Lastly, on slide 18, total leverage — net debt stood at $815 million. Consequently, the reported leverage ratio of net debt/EBITDA stayed at a level of 3.8 times, with corporate leverage at just 1.3 times. However, taking into account the deal we've already agreed and that is pending an impact on cash flow, on a pro forma basis this ratio will fall to 0.2 times and corporate will even turn positive, to minus 0.3 times.
Daniel Lozano Herrera
executiveThat demonstrates how rapidly we’re able to bring this ratio down following the solid asset rotation we’re carrying out, even as we grow our pipeline, with additional opportunities and further projects ahead, delivering positive updates each time. That’s everything from me. Rocío will now walk through the key messages on ESG.
Rocío Fernández Flores
executiveThank you, Daniel, and good morning to all of you. I'd like to invite everyone to go over how our sustainability progress unfolded during the first semester of 2025. We're now in the second phase of the ESG roadmap 24 to 26, and it's my pleasure to share the goals we've managed to accomplish successfully up to this point. On the climate change side as well as the environmental dimensions, our policies covering climate change and biodiversity were drafted and then approved by the Board of Directors — a holistic framework that laid out objectives, key principles, and the mechanisms for both implementation and monitoring. Turning to the governance dimension, the annual sustainability report, prepared in line with TCRD, came out earlier this year. Beyond that, I want to highlight a significant milestone we reached: a corporate sustainability social management plan received approval from the Management Board, setting the guidelines to follow whenever any voluntary social or environmental initiative is carried out with communities near our projects. Against that backdrop, we're proud to note that during this year we have invested approximately €200,000 so far in vulnerable communities in Chile. Now, if we move to the next slide, on the subject of where we stand in ESG ratings, I'd like to stress that Greenergy once again consolidates its leadership position in the most prestigious ESG ratings.
Rocío Fernández Flores
executiveIn Q2 2025, a few ratings got refreshed, and the outcomes came in stronger both versus our competitors and versus our own prior-year figures. Sustainalytics is one example — it still places us within its low-risk band. S&P is another: following a half-point score improvement this year, it now puts us in the top 16% globally within the electric utility sector, which is above the sector average. It's also very noteworthy that we were recently added to the EBEX ESG Index this year. In addition, Greenergy received an A- score in the CDP 2024 Supplier Engagement Assessment. One more thing to note: certain other ratings — ETI Finance, CDP Climate, and MSCI — haven't been updated as of yet. We'll share more details on those with you over the course of this year. That's everything from me. Thank you all very much for listening.
Rubén Gómez Martínez
executiveThanks a lot, Rocío. At this point we'll begin the Q&A. If anyone has a question, just raise your hand. Our first question comes from Alexandre Roncier at Bank of America. Go ahead, please.
Alexandre Roncier
analystMorning, and thanks for asking. What leaves me somewhat puzzled today, including in certain discussions we've had with investors about how the stock has reacted, is essentially that there may have been expectations that we'd announce something on tolling agreements today. I'm aware you've all clearly been putting in a great deal of effort to speed up the pipeline and push things into advanced development. Everybody is essentially waiting for those to materialize. I'd welcome any detail on how that's progressing, and also on the points you raised about the pool of PPAs tied to certain other hybrid projects ahead of year-end. Actually, reaching the market before year-end is quite a long way off. I know you're all working extremely hard. Any detail on that front concerning tolling agreements would be super interesting — whether you believe some new kind of structure might be agreed, or whether you're already considering geographies outside Spain on a standalone basis. Thank you.
David Ruiz de Andrés
executiveThanks. Thanks, Alessandro. Yes, I was looking at the screen. Yeah, perhaps some of you might have been expecting a big announcement. I don't know. I think we are really on track. For us, once again, it's extremely important to be on track to what we promised concerning CapEx figures, execution, and asset rotation. That's mostly linked to Oasis of Atacama. Let's not forget that, and correct me if I'm wrong, Daniel, but I think out of the $3.5 billion, more than 60% or even 70% would be coming from the large Chilean platforms. We are really focused executing there and rotating the assets. I think this is being great news. We have made these two very important announcements in the last few weeks. Believe me, we will make announcements concerning tolling agreements. We are working very hard. We have several options, but some of them are very advanced. Unfortunately, sometimes, when you have on the other side of the table large utilities or large corporations, they cannot move as fast as we can move. We only make announcements when we have something really binding. Even if we have a term sheet signed, if we don't feel that that's fully binding, we don't announce that to the market.
David Ruiz de Andrés
executiveOn the question about other geographies, I believe we've already said that along with Spain, Germany is going to be the next market for us. We've also spent a very long time negotiating large tolling agreements. I think at least one of those announcements will come in Germany before the year is out. It'll function as a big framework within which we could allocate projects later on. We'll make the announcement for Oviedo, for Asturias, and also for the first hybrid project in Spain, which is the Escuderos plan. As we've explained, we have several options there, since we're in talks with the current staker, GAL. They have seven years left on their PPA. They're interested. They might be interested in converting it, extending it, and turning it into a hybrid PPA. We could close a tolling arrangement that would coexist alongside the existing PPA, a financial PPA for solar. That's it. We're working very hard. I'm confident that at our next presentation in November, we'll announce something. If not, then certainly before the year ends.
Rubén Gómez Martínez
executiveAlright, many thanks. We'll take the next question from Fernando García at RBC.
Fernando García
analystGood morning, and thanks for taking my questions. I saw that you're splitting up the Atacama phase six Elena project — the battery portion is now slated to begin a quarter sooner, while the rest of the solar piece comes in the final three quarters, and this is for an asset where you're still in advanced PPA negotiations. It seems like you'll be running this asset as what's probably a quasi-standalone battery for roughly 1 year. I wanted to check what strategy you have in mind for this asset in particular. David, let me ask about your asset rotation strategy. Following the deal to sell Elena, as you mentioned, you're surpassing your asset rotation targets. My guess is there are two main paths here: either higher gains and lower debt by the end of the plan, or taking this stack of proceeds and investing more. I wanted to check on that. I know it's only 4 months since the CND, but I'd like to hear your thoughts on it. Thank you.
David Ruiz de Andrés
executiveAlright. Thanks, Fernando. It is accurate that, well, with Elena, alternative approaches were available to us. We might have held off until the PPA was in place. This is a really big project, correct? Let's remember, Elena on its own. Just Elena by itself. It's over two times larger than any earlier project such as Gabriela. It's comparable to combining Kigawa, Victor Jara, and a bit extra, right? This is a sizable project we're discussing. There won't be just one PPA. What I mean is, a large anchor PPA will exist. That's how we're handling it — we've been in negotiations for a very long time with a major name. Several PPAs will form a basket. In addition, a retail unit is going to purchase a portion of the energy. This deal is more complicated, correct? A few months will be needed. We talked with the banks and we said, okay, well, there's a chance to pursue a fast track using the BES, since a great opportunity exists if we get the BES connected sooner. We get roughly a year of upside from having the plant connected and taking advantage of high nighttime prices, right? They presented this product to us like, okay, let's complete a project finance rather than a mini-perm, which is typically five years.
David Ruiz de Andrés
executiveSo in this case, three years have passed. Our leverage is lower, but even so, we've borrowed in excess of $250 million, which is essentially what we required. We have three years. Three years won't actually be necessary for us, but they're there to bring in the PPAs and refinance. At that point, we'll build the PV plant. Right now, prices during the day are quite low, or there's even cool payment in northern Chile. As many more batteries come in, we expect those daytime prices to rise as well. Eventually, I think it's wise to have your generation — you know, your energy factory — next to your battery as early as 2027. Over the long term, in countries such as Chile, we definitely favor hybrid PV BES over being just standalone. That's roughly the strategy for Elena. I believe we can begin getting revenues as early as February next year. The sooner the better, right? There's a big incentive. This plan alone, just Elena, once it's an operational PV BES, will be close to $100 million EBITDA. The sooner it gets connected, you know, every month really counts. As for your question, after Gabriela's rotation, it's true that we're getting really on track with the rotation target, right?
David Ruiz de Andrés
executiveAll right, so yes — additional projects exist, and further rotations will be announced. They won't be as large as Gabriela, though it's fair to say we could hit that target sooner than we had anticipated. Next year, possibly — if not in February, then May. We'll provide visibility on our 2028 targets, as we do annually. If that rotation financial target has already been achieved, there's a chance that, should the right opportunities appear, we accelerate CapEx. Provided we hold the view that the alternative is what you described — fine, we cut debt, adopt a more conservative stance, and continue investing at the level we committed to. A great deal will hinge on how fast we can execute in Greenbox. Let's remember that Greenbox's numbers are extremely demanding when it comes to CapEx. I mean, diversifying into other European markets would be very interesting for us.
Rubén Gómez Martínez
executiveAlright, we’ll take the next question from Anna Webb at UBS. Anna, please go ahead.
Anna Webb
analystThanks very much. Hello, and I appreciate you fitting in my question. My question concerns the pipeline as a whole. I believe there was a somewhat modest decrease, most notably in the standalone BES pipeline. So I'm curious about what's mainly behind that. You mentioned being eager to adopt a fairly cautious stance and to include only those projects in the pipeline that you believe stand a realistic, genuinely strong likelihood of being realized. What particular difficulties are you encountering with certain projects that you're removing? Or perhaps not difficulties, but what leads you to conclude those projects are less probable? Is it grid connections, the market outlook, prices — what exactly is causing those projects to drop out of the pipeline? Thank you.
David Ruiz de Andrés
executiveThanks, Anna. That's a really solid question. The reason is that the company's profile is shifting somewhat, correct? A few years back, we aimed for 90% using our own staff. Our projects were greenfield, built from scratch by us. Now that we've shifted heavily into the BES space, especially standalone, time to market matters above all, right? We need to ensure we have the right staff, but what matters even more is having them at the right time. That's what we're aiming for, so whatever we develop, we'd really like to be certain it will succeed, but succeed at the right moment. Because in PV, I believe we could wait four, five, six years. Some plants we're building in Spain took us over six years to develop. Take a Jora plant — that's been seven years. I don't think we want that with BES. The opportunity is enormous and it's excellent, but for the next three, four years, we have visibility over the next three, four years. What we're doing is recycling some of the projects that we don't expect to happen.
David Ruiz de Andrés
executiveOn our buy side, the M&A team is putting in a lot of effort to uncover ways we can grow. Sure, one illustration is our flagship Asturias project in Oviedo, which stands at 150. We developed 100 of that, and the additional 50 came from a neighbor who owned those 50. We combined it with the 100, giving us 150. Something comparable is underway right now for our first big project in Germany. A significant number of buy-side elements will be part of our pipeline going forward. That has also been true in Chile. One of the biggest — our largest project at present, Elena, as you're aware, was at first developed and constructed purely as a PV project by Repsol and Ibereolica Renovables. It's simply that you shouldn't assume what we'll be executing comes only from what sits in our pipeline. Certain projects will also arrive from outside sources.
Rubén Gómez Martínez
executiveOkay, we’ll take the next question from Beatriz at Mediobanca. Go ahead, please.
Beatrice Gianola
analystYes, thanks. Morning, everyone. Appreciate you taking my question. I was hoping for an update on the Oasis of Atacama platform. You talked about the PPAs that you've more or less negotiated across that region, but I'd like to get a bit more detail on how the platform is being realized. How is that moving along, and what's the timing on it? Thank you.
David Ruiz de Andrés
executiveThank you, Beatriz. Let me turn to Central Oasis. I think this one is pretty straightforward to explain. Central Oasis came about with phases one and two already in place — two operational projects, Gran Teno and Tamango, purely as PV projects, right? They were financed a bit over two years ago by BNP and SocGen, the French banks. As with everywhere else, we see a business case for hybridization. That's the first mandate. We've already mandated, right? You know, we normally don't give — we don't, when we mandate, we don't really make it public, only when we close the financing. I think after Elena, the next large financing we're working on will be the hybridization of Gran Teno and Tamango and Planchon. Planchon is a new plant, but it sits next door to Gran Teno. All three together fall under a single mandate. I think it should be — it should get closed in Q4 before the year ends, right? Phase four will follow. It's very, very similar. It's farther south. It's quite a large plant. In fact, we're starting construction very, very soon. We've already ordered the traffos. It will have a similar PPA structure, right?
David Ruiz de Andrés
executiveFor phases one, two, and four, we have PV PPAs signed a while back with a major utility. Roughly 40% — somewhere between 30% and 40% of revenues — comes from those PPAs, investment grade, solar only. Then there are capacity payments, approximately 25% here. We're looking at four to five hours of BES. All the nighttime energy will be bought by our retail arm, GR Power, mostly to cover the power we need for Cobelco and the other large PPAs we hold. That's the model. Monte Aguila — I don't want to say copy-paste, but it's a very, very similar model to phases one and three. We are mandating — we've already mandated phases one and three. That's the first closing, Q4. Monte Aguila comes next. We expect financial close in Q1. That doesn't mean we won't begin some construction work. Soldecano is more of a late 2026, 2027 project. We're pursuing several off-take opportunities. There are many processes in Chile right now involving mining. There are very significant opportunities with data centers. We're reaching out through our retail unit. I believe there are plenty of off-take opportunities in Chile, particularly in central Chile.
David Ruiz de Andrés
executiveMy expectation is that this platform could expand a bit more if we identify the right projects, and we are currently analyzing some. We will let you know as soon as we have something in hand.
Rubén Gómez Martínez
executiveWe’ll take the next question from Henry Tarr at Vandenberg. Go ahead, please.
Henry Tarr
analystHey, thanks for taking my questions. I had a couple of things. First, could you expand a bit on the economics of the Greenbox BES projects you're evaluating and how that would break down? What would you say is the primary risk for you when you look at these tolling agreements? Is it simply the physical usage of the batteries, or are there additional risks we ought to be considering? And staying on pricing, looking at the PPA pricing and environment — you're obviously in discussions right now regarding further phases of Atacama, etc. How does appetite look, and what are the pricing and returns you're seeing on those projects as we sit here today? Thanks.
David Ruiz de Andrés
executiveThanks. I think I'll answer this one on the Atacama side, and I may hand it over to Daniel for the Greenbox economics, right? Since I think you know that well. I should say that no two tolling agreements are alike, and the revenue stacks differ somewhat from one market to the next, right? We may take a different approach, say, in Germany than in Spain, or certainly than in the UK. Still, there's a lot that's common. I'm sure Daniel can give you more visibility. On Chile, again, I'm fairly optimistic. We don't expect IRRs for Central Oasis to match those of Oasis of Atacama, mainly since the northern plants' yield comes in near 3,000 hours. That means perfect cycling, and we managed to secure some PPAs at the right time. CapEx came down quite a lot. I think CapEx — and we may discuss this in other questions — we feel that CapEx for BES has currently kind of hit some bottom at the moment, right? We aren't expecting it to go up, but we aren't expecting it to go farther down either, at least now over the next couple of months.
David Ruiz de Andrés
executiveI believe solar CapEx is trending a bit upward — up 10% to 15%. Yeah. When you combine those two factors, we're still definitely achieving double-digit returns on the Central Oasis projects, right? For the new PPAs up north, even if PPA prices won't sit in the mid-80s as they did initially, even at high 60s or low 70s, CapEx has come down substantially. We're quite pleased with those returns, right? We will be getting. Daniel, I'll leave the economics of Greenbox to you, along with a bit of visibility into those economics.
Daniel Lozano Herrera
executiveAll right, thanks, David — I mean, Henry. Look, when it comes to a standalone business model, where the revenue comes from really hinges on each individual market: regulated revenue, ancillary services, capacity payments, and the day-night spread. The fact is, for us — and we're trying to keep this simple, since the banks in particular are asking us to simplify it so it can be financed — as you know, we're going to attempt to sign tolling agreements running 8 to 10 years. Keep in mind that for Oasis of Atacama, Central Oasis, since we're running just one cycle per day — charging, discharging — the asset's lifetime could be 25 years. If you run 1.5 cycles, two cycles — if you're doing two cycles, the lifetime will be half of that, so 12 years. If you're closing in Germany with a tolling agreement of, say, 8 to 10 years, and starting — you know — in the first year, normally we prefer to have it merchant. Starting one year after the merchant period while you're connecting, so as to avoid any production risk — that means you'll have a fixed payment across 90% or even more of the battery's lifetime. It's going to be really easy to model.
Daniel Lozano Herrera
executiveOur guidance for Spain is a project IRR above 12%, and that holds even though capacity payments aren’t regulated. That represents upside. As soon as we finalize the tolling agreement — which hopefully happens soon, before year-end — we’ll tell you how to model it. Keep in mind that it’s a fixed payment. They run the battery. What we sell isn’t energy; we sell that battery’s service to our customer, who could be a utility or a prescalier trading company.
Henry Tarr
analystAll right, thank you so much, everyone.
Rubén Gómez Martínez
executiveAlright. We'll take our next question from Flora at Kaisa Bank. Flora, the floor is yours.
Flora Trindade
analystYes, hello. Good morning, and thank you for taking my questions. Regarding the CapEx you just brought up, I was wondering whether any negotiations have taken place following the customer-driven rise in lithium. On the CapEx in BES, you said we are likely at a bottom. Could you explain how you expect this to develop given the volatility we're seeing in lithium prices? To keep expectations in check, and to be clear, do you anticipate announcing anything about tolling agreements in the November release? Second, do you have any range for the potential level of those tolling agreements? I believe that in some discussions, we do mention certain numbers that I'm not sure are within the investor base. Just to manage expectations when this comes up. Thank you.
David Ruiz de Andrés
executiveThank you, Flora. I've been thinking about this — I'm not certain whether we've given an update on it — and I'm comfortable with this presentation. You know, lithium prices obviously do have an effect on what battery packs cost, right? That's not — I think it's not higher than 50%, 15%, 1%. Even if lithium's price skyrockets, I don't think that will happen, right? We have seen some increases. I think even the Chinese government, either directly or through CATL or other players, temporarily shut down some mining activity, right? That's not by chance. I mean, they're looking at raising lithium's price because it was so depressed. It's happening, but even if lithium goes up by 10%, 20%, 30%, the impact on battery pack prices is quite limited. Let's say between 5% and 10%. There are other factors. Basically it's supply and demand that could push battery prices higher. I think EV, electric vehicles, demand is surging, and that's a factor. Finally, and mainly in Europe and China, other regions, not as quick as they were expected, but we see a lot of oversupply or overcapacity in many factors in China.
David Ruiz de Andrés
executiveThe productivity improvements are really quite striking. Just the day before yesterday, I believe, BYD unveiled their new product, which will be a battery of 14 megawatt hours in total — like combining two containers. My sense is that CATL is placing more of a bet on the two-layer approach, which would give a product of 12 megawatt hours. Keep in mind that just a year and a half ago, the first battery was only six megawatt hours. Things are moving very quickly. They keep packing more and more capacity into the same space, and that pushes the price down too. We've seen a sharp drop in price. My belief is that prices will hold steady or might even rise slightly. I think we'll see a further decline. I think it's a similar story to what we experienced in PV, right? It's a bumpy road. It's been falling, but it's also been rising, then falling again. Look, for the same panels, we used to pay $3. Now we pay $0.08, right? Just 15 years later. I think it's a comparable story. Regarding the tolling agreements, Flora, we're working on it — the sooner we get a binding agreement, and we're, I think, quite close, we'll make an announcement.
David Ruiz de Andrés
executiveMy guess is Elena will be first, for sure. Things are moving along nicely on one of — we’ve got 3 big negotiations going in Germany. I think there’s also a chance that at least 1 of them gets announced before the year is out, right? We’ll make sure you have visibility on that. I’ll do my best to walk you guys through how the economics work. Again, each tolling arrangement will differ somewhat — by geography and by project. We’ll really put in the effort to explain it to you.
Rubén Gómez Martínez
executiveWe'll take the next question from JB Capital. Ignacio, the floor is yours.
Ignacio Domínguez Ruiz
analystYes, Daniel and the rest of the team, thanks for the presentation. I have two questions. First, on the tolling agreement in Spain: Daniel mentioned that capacity payments in Oviedo would come on top of that 12% project IRR, and I'd assume that's a fairly significant upside. I don't know whether you can quantify it. If you could give us some color on any regulatory developments that you, or that we, are expecting in Spain for this technology to take off. The second question relates to how power prices have evolved in Chile. We saw a decline in the second quarter, which I believe was mostly tied to the PMGDs. If you could also give us some color on the latest situation there and maybe how we're heading into the second half of the year. Thank you very much.
David Ruiz de Andrés
executiveThanks. Thanks, Ignacio. Apologies — regarding your second question on Chile, was it PMGDs specifically that you meant?
Ignacio Domínguez Ruiz
analystNo, the prices. If you'd like, maybe I can hop on that.
David Ruiz de Andrés
executiveAll right.
Daniel Lozano Herrera
executiveChilean prices have been impacted, partly because, first of all, our solar PV matrix is more diversified now. With that portfolio, PMGDs—which used to carry more weight—no longer matter as much as they once did. As you know, PMGDs come with a fairly high price, roughly $65 to $70 on average. These days, with additional projects selling at energy output price or through PPAs, the average price in Chile ends up lower.
David Ruiz de Andrés
executiveRegarding FX, I believe that's for you, Daniel?
Daniel Lozano Herrera
executiveRight. As you know, some of our agreements are denominated in dollars while our accounting is done in euros. The investments we hold are in dollars, yet the currency we use for accounting is the euro. So foreign exchange has had an effect.
David Ruiz de Andrés
executiveAlright, thank you. Regarding the tolling agreements and the capacity market — I believe some of the bigger utilities in particular are saying there's no regulation in Spain for BES, and they're waiting on capacity payments. In my opinion, that isn't a good way of approaching it. The IRR guidance we've provided completely excludes any capacity payments. I think we'll finally see that mechanism published within the next few weeks. At least, I don't know — our regulation team seems to tell me every time I run into her, and our regulation manager, she keeps saying that, okay, next week, next week. Finally, it seems we're nearly there. There will be an option at the end of the year, we believe. Don't expect very great upside coming from capacity. That's our expectation, right? We'll be lower than many people think. For us, it might be like 10%, maximum 15% upside, right? That's similar to what we are going to see in other markets like Italy and Poland, and nothing to do with the auctions two years ago and a year and a half ago for storage where most of the revenues were coming from capacity payments. Now it's going to be a lot more contenders.
David Ruiz de Andrés
executiveMy view is that the auction will produce much lower prices. Our estimate is that capacity ought to make up 10%, 15%. In Chile, in certain cases — in the north — that figure stands at 15%. The mechanism operates automatically, yet it is 15% in the north, with 20% as the ceiling in centralized. That is how we look at it.
Rubén Gómez Martínez
executiveAll right, thanks a lot. That's all the questions we have. Thanks so much for joining us, and we'll see you in 2 months at our Q3 results presentation. Many thanks.
David Ruiz de Andrés
executiveMuch appreciated. Enjoy the rest of your week. Take care.
Operator
operatorThe recording has ended.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Grenergy Renovables, S.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Grenergy Renovables, S.A. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Grenergy Renovables, S.A. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.