Hecla Mining Company (HL) Earnings Call Transcript & Summary
November 7, 2023
Earnings Call Speaker Segments
Anvita Patil
executiveGood morning, Mondeep, and thanks to everyone for being here on this call about Hecla's financial and operations results for the third quarter of 2023. This is Anvita Patil speaking; I serve as Hecla's Vice President of Investor Relations and Treasurer. The news release covering our financial results, which came out yesterday, and the presentation for today can both be found on Hecla's website. Joining us on this call are Phil Baker, Hecla's President and Chief Executive Officer; Lauren Roberts, Hecla's Senior Vice President and Chief Operating Officer; Russell Lawlar, Hecla's Senior Vice President and Chief Financial Officer; and Carlos Aguiar, Hecla's Vice President of Operations. When members of the management team make forward-looking statements today, they do so under the Private Securities Litigation Reform Act, and those statements carry risks, which are laid out on Slide 2 as well as in our earnings release and in the 10-K and 10-Q documents we filed with the SEC. Those risks, along with others, might cause actual results to diverge from what the forward-looking statements anticipate. Any non-GAAP measures referenced on this call and in the accompanying slides are reconciled either in the slides themselves or in the news release. One reminder: should you wish to schedule a call with management, you may do so through the link located under the section titled Virtual Investor Event in the earnings release we issued yesterday. With that said, I'll hand things over to Phil.
Phillips Baker
executiveThank you, Anvita. Hello, everyone, and good morning. We appreciate you being on the call. Prior to walking through the slides, let me take a moment to note that Lauren will be retiring when this year comes to a close, and I want to express my gratitude to Lauren for the time he has spent at Hecla. A great many things have been achieved while he was here — accomplishments both by the company and under his direction. What stands out most to me, though, is that at the point he came to Hecla, we remained at the Lucky Friday, where our focus was on cutting rock through mechanical mining. Yet we took the first steps that ultimately produced the new mining method at the Lucky Friday. Absent his backing, expertise, and guidance, I question whether the UCB would ever have been built. A patent for a new mining method would not exist. So thank you, Lauren, for everything you have contributed. I would also like to introduce Carlos Aguiar, our Vice President of Operations. Carlos comes from Mexico, became a U.S. citizen 2 years ago, and has spent a total of 27 years with the company, 17 of which were spent working for us in Latin America, in Mexico as well as Venezuela. He brings nine years of experience as a GM for us at San Sebastian and Lucky Friday Mines, and he is also familiar with Casa Berardi. It was really he who got the mill modifications underway. I have now known Carlos for roughly 20 years. My first encounter with him was on a tour of the mill in Venezuela. His leadership skills and dedication to operational excellence have truly shown up in the steady and improving results he has delivered wherever he has worked. With him at the helm, every operation has improved significantly; so you will take pleasure in getting acquainted with him, and with that interaction, I'll begin with Slide 3. Let me pause for a moment to step back and talk about how we have performed over a longer horizon. This is something we normally do; it reflects how we view the businesses over the long term. Across the last five years, you have watched our revenues increase 27%, silver reserves 79%, silver production 37%. And as we strive toward producing as much as 20 million ounces by 2025, that means we will come close to doubling our silver production relative to 2018. Perhaps even more striking is the figure that follows, the $767 million in free cash flow that our three operating mines produced. This has, naturally, translated into strong share performance. And it comes down to the quality of our assets. These assets offer long reserve lives, high grades, low cost, consistent performance and significant exploration potential, which is what enables this kind of performance over time. And I would put it to you that Greens Creek satisfies all five of those criteria; long reserve lives, high grade, low cost, consistent performance and significant exploration potential. Lucky Friday, as things stand, satisfies four of the five. Casa and Keno pass on three of those criteria, yet every one of the mines satisfies the long-life requirement. So our emphasis is on positioning the mines for the long haul, driving toward continual gains, and letting innovation make fundamental improvements to them. My belief is that eventually, every single one of them will satisfy all five criteria. With that background on the quarter, I'll turn to Slide 4, beginning with Lucky Friday, where there will be no output before early 2024, since we are sealing off the bottom portion of the two shaft and constructing a fresh secondary escapeway of ventilation raise. This project, which takes 3 months, is progressing well. Meanwhile, we continue moving other projects forward and finishing our equipment acquisitions. In fact, 10 pieces of equipment sit on surface, ready to head underground. We anticipate ramping back to full output in Q1 and watching Lucky Friday carry on through 2024 with the production growth and free cash flow we experienced prior to the fire. Turning to Keno Hill, output has been held back because of the delayed commissioning of the shotcrete plant just yesterday and the cement rockfill plant, which is slated for completion later this month. Once those are finished, we'll be positioned to push development and production ahead more quickly. What's more, the ore grade has actually exceeded our block model's forecast. That said, the safety culture at Keno worries us. Our all-injury frequency rate there stands at roughly 4, which we cannot accept. Compare that with Greens Creek and Lucky Friday, both of which come in under 1. Over the past 2 months, and more recently within the past 2 weeks, several near misses occurred that caused no injury or equipment damage but had the potential to, and that is unacceptable to us. Consequently, I've assigned Carlos and his team to systematically examine every process and procedure we have so we get safety right, since we understand that strong safety doesn't just stop injuries, it also brings consistency to activities, boosting predictability and production. So the safety review at Keno will probably lead to modifications in our processes, schedules, equipment, and mining methods. To make the mine safer, we'll re-engineer particular processes. Given that the mine is just beginning operations and has a long expected life, we have to start safety off correctly; therefore we'll take all the time necessary for that. Greens Creek delivered yet another steady, robust operational quarter, and we're raising silver production guidance for that mine. Greens Creek has already produced more than $100 million in free cash flow this year. Casa Berardi just turned in a strong quarter as we move forward with the shift to operating solely as an open pit mine. The cash costs and all-in sustaining costs we posted sit comfortably inside guidance, and the infrastructure we're putting in place positions that mine to do well over the coming ten years. Back earlier in this year, we recognized that fundamental changes were necessary, we started putting those in place during the quarter just completed, and the advantages are already showing up; as things stand now, for the whole company, our silver production guidance is down only a touch. The guidance midpoint represents a reduction of merely 400,000 ounces of silver. Our silver costs haven't moved, gold hasn't moved apart from a modestly lower cash cost; and lastly, safety results across our operations, leaving aside Keno Hill, rank among the strongest in the sector, with an all-injury frequency rate that runs below the U.S. national average on a consistent basis. With that said, I'll hand things over to Russell.
Russell Lawlar
executiveThanks, Phil. I'll begin with Slide 6. When we look at how this year has gone, despite Lucky Friday being offline for the majority of the third quarter, silver made up 38% of revenues, and our silver operations produced over $120 million in free cash flow. Thanks to robust gold output of 39,000 ounces, gold represented 36% of revenues, while base metals added 25%. We're on track for silver to provide more than half of our revenues. A solid balance sheet and financial flexibility have consistently been top priorities, with the aim of keeping a leverage ratio below 2x and preserving substantial liquidity. During the third quarter, our leverage ratio rose to 2.2x because of the production halt at Lucky Friday and our ongoing investment at Keno Hill. While we anticipate the leverage ratio will stay elevated in the next quarter, we view this rise as temporary. At $165 million, our liquidity is sufficient. That said, I anticipate the leverage ratio will drop below 2x and our liquidity will increase considerably once Lucky Friday resumes production and Keno Hill reaches maturity. I'll now move to Slide 7 to point out some key characteristics of our silver mines, particularly as we navigate a period of investment. Our silver mines have reliably delivered strong margins; the graph on the left illustrates this, showing that across the past four years, the margin has been close to or above 50% and has resulted in steady free cash flows. The chart on the right demonstrates just how powerful this free cash flow generation from our silver mines is. Since 2020, Lucky Friday and Greens Creek have produced over $800 million in cash flow from operations, and even more striking is the almost $600 million in free cash flow. These robust margins and the free cash flow they generate let us invest in capital and exploration at these mines, along with our extensive exploration portfolio, while also returning capital to shareholders through dividends. And now, I'll hand the call over to Lauren.
Lauren Roberts
executiveThank you, Russell. I want to offer a few remarks about my tenure at Hecla. My journey with the company started when I joined as a summer intern back in 1988, and I transitioned into a full-time role in 1989. I was with Hecla for just shy of eight years, and I couldn't have hoped for a finer way to launch my professional life. So when the chance came to come back to Hecla roughly 20 years afterward, choosing to return home was incredibly straightforward for me. Being able to contribute something in return mattered a great deal to me, and these past four years have been deeply fulfilling. So I want to express my gratitude to the Hecla family for all of that; with that said, I'll begin on Slide 9. Greens Creek, which serves as our flagship mine, delivered yet another robust and steady quarter, generating 2.3 million ounces of silver, consistent with the 2.4 million ounces from the quarter before. Thus far, the mine has produced 7.5 million ounces across the first three quarters of this year and is still on pace to hit its throughput goal of 2,600 tons per day by year-end. Cash costs and all-in sustaining costs per silver ounce came in at $3.04 and $8.18, respectively, and these were elevated relative to the second quarter as a result of reduced gold output and weaker gold prices. Capital spending during the quarter was $12 million above the prior quarter, which was anticipated because of equipment acquisitions and seasonal surface work. The mine delivered $28 million in free cash flow during the quarter and has already surpassed $100 million in free cash flow for the year. We are raising our silver production guidance to a range of 9.8 million to 10 million ounces for the year. Owing to mine sequencing, zinc output is anticipated to be somewhat reduced, which pushes up our cash costs and all-in sustaining costs per ounce guidance because of lower expected byproduct credits. Capital guidance remains the same at $47 million to $50 million. Greens Creek genuinely stands as a premier silver mine, ranking as the 11th largest globally. And I want to commend the team for achieving excellent and consistent results from this truly world class asset. Moving to Slide 10. I'm pleased to share that we've been executing effectively on our plan to shift Casa Berardi to a fully open pit operation by mid 2024. The mine yielded approximately 24,000 ounces of gold at a cash cost of $1,475 and an all-in sustaining cost of $1,695. Mill throughput came in below the prior quarter because of a planned upgrade to the gravity circuit. We are currently optimizing that circuit and anticipate it will improve overall plant recovery. The first phase of the in-house open pit fleet was commissioned during this quarter, leading to record tons moved, with our plans proceeding on track and solid performance on cost control; we are reducing our cash cost guidance to 1,600 to 1,800 per ounce. The mine remains on schedule to meet its production and all-in sustaining cost guidance. Up until only a few months back, Carlos held the position of General Manager at the Lucky Friday mine, at which point he moved up to Vice President of Operations. Much of the improvement and steady performance that the Lucky Friday has delivered across the last few years came about thanks to Carlos and the people working under him. Since my retirement is set for the close of this quarter, I'm going to pass things over to him so he can talk through the rest of the operations.
Carlos Aguiar
executiveThanks, Lauren, and good morning to all. I'll begin with Slide 11. But before we get into the progress at Lucky Friday, I'd like to congratulate our Lucky Friday team for winning the 2023 NIOSH Mine Safety and Health Technology Metals Sector Innovation Award for the UCB Mining Method; on top of that, we also got the U.S. patent during the third quarter. In August, we reported a fire at Lucky Friday in the #2 shaft, which also serves as the secondary egress. That fire was put out in September. But the mine's operations are halted for the rest of the year until the secondary egress is in place. Our mitigation plans involve driving a ramp, a vertical escapeway and a vein raise to get around the damaged section of the shaft. The ramp and a ladderway raise will act as a secondary egress, with the vein raise serving as a bypass for ventilation. To walk through our mitigation plans in more detail, I'll go to Slide 12. Let me begin with the graphic on the left. First, I want to point out that Lucky Friday has two shafts that started at the surface. The silver shaft, shown in the left graphic, is the left of the two shafts, along with the number two shaft. Silver shaft is our main production shaft. It's a circular concrete lined shaft. It moves people, equipment, materials, and it's essential to our operations at Lucky Friday. This is the shaft where the service hoist was installed early this year, and it wasn't affected by the fire. To the right of the silver shaft in the graphic is the number two shaft, where the fire happened about halfway down. This shaft provides ventilation and, in an emergency, an alternative way out of the mine. Between the two shafts is the new 850-foot vent raise we're driving for ventilation. The graphics on the right show the future plans to reestablish the secondary egress. Those plans include an extension of a 1,600-foot ramp. And from this ramp, we'll install a 290-foot vertical escape raise, basically a ladder with landings. Once it's complete, this infrastructure will let the mine restart production. The escapeway is the critical path to production and is on schedule, with 35% of the ramp and 10% of the raise complete. The ventilation raise work has just started. These mitigation plans are expected to cost roughly $10 million, and we expect the mine to restart production in January of next year. We have property and business interruption insurance with an underground sublimit of up to $50 million. I'll now move to Slide 13. As Phil mentioned earlier, the safety performance at Keno Hill has not met Hecla's standards. So I'm on my way with my team to assess what needs to be done to get safely where it needs to be. Since the mine is only beginning operations, now is a pivotal moment to set the culture we operate under at Keno Hill — doing so is simpler at this stage than it would be afterward. Keno has yielded nearly 900,000 ounces annually, with 700,000 coming in Q3. My expectation for Q3 is output somewhere between 800,000 and 1 million ounces. We have the Shotcrete plant commissioned at the portal, camp facilities that have been expanded, 8,000 feet of development, 10 headings, plus the modified secondary crushing. If we manage to get safety right, we're positioned well for a robust 2024. Slide 14 displays a pair of our key projects — the secondary crusher on the left side and the Shotcrete plant on the right. Having said that, I'll hand the call back over to Phil.
Phillips Baker
executiveThanks, Carlos. Now, regarding Slide 15, I want to give a quick update on what’s happening with exploration at Keno. Based on the tonnage we’ve mined, we’re very happy with the grade we’re seeing at Keno — 33 ounces per ton. The rock’s NSR value is over $700. Our exploration crew keeps uncovering more across several deposits, but let’s focus on Birmingham for now. Let me walk you through this slide. Birmingham contains multiple zones — Bear, Arctic, and Northeast deep — and we’ll be mining there for many years. The pictures you’re looking at show just the Bear area; the left image is the Bear Vein, and the one on the right is the Footwall Vein. There’s also a third vein not pictured, known as the Main vein. Thinking about all these vein names can get a bit confusing — so you’ve got the Bear Zone, which includes the Bear Vein, the Footwall Vein, and the Main vein. If you check the image on the left toward the Northeast, beyond the current design stopes, we’re spotting another mineralized <<inaudible>>. The grade looks high enough that it could potentially increase our resource. The top hole is roughly 163 ounces across seven feet. Now, looking at the image on the right — that’s the Footwall Vein. It sits inside the stopes we’ve already planned. We have 36 feet of 36-ounce material, plus 17 feet at 56 ounces. We don’t have results yet from drilling the Main Vein. The key takeaway is that we see a real chance to keep expanding high-grade resources at Keno. We’re incredibly enthusiastic about the exploration results we’re getting and what’s possible going forward. Slide 16 lays out our production cost guidance for the year. We’re reaffirming our consolidated cost guidance for silver, though we’re nudging silver production guidance down a bit, as I mentioned earlier. Gold cash costs are somewhat lower, and capital remains the same. On this slide, you can also see the ramp-up costs for Keno and the suspension costs for Lucky Friday this year. Exploration spending hasn’t changed. Looking toward 2025, we believe we’re still on course to produce as much as 20 million ounces. Now, if you turn to Slide 17 — before I take questions — I’d like to wrap up our prepared comments by highlighting the expected growth in solar energy. Globally, 269 gigawatts of solar were installed last year. The International Energy Agency projects that in seven years, the world will install roughly double the solar panels it will this year — around 500 gigawatts. That’s a reasonable forecast. It represents a 9% growth rate. And that really stands against the 12% growth we saw across the past 10 years. Right now, each gigawatt that gets installed requires half a million ounces of silver. So last year that worked out to 140 million ounces, which was 12% of all silver demand, and by 2030, with 498 gigawatts, we'll be using 100 million ounces more, or nearly 250 million ounces, and that would represent 21% of demand assuming overall demand stays flat. That's unlikely, though — other silver users will also see their demand rise. To give you a sense of what 100 million ounces of demand means, the yearly output of two more of the biggest silver mines on earth — two more of those — matches it. They aren't really silver mines. It isn't a silver mine, yet it yields roughly 50 million ounces, or equivalently it's 10 Greens Creeks, which ranks as the 11 largest silver mine. Plainly, the extra silver demand coming over the next seven years won't be satisfied through additional mine production. Even if new silver discoveries happen, you cannot get a perimeter built within that seven-year window. So meeting that demand will have to come from above ground supply, and mobilizing that will demand substantially higher prices. Last, I'll serve as Chairman of the Silver Institute for the next two and a half years, and because of that role, I was asked to speak at the LBMA conference three weeks ago. What struck me there was that highly respected, knowledgeable market participants still think about silver the same way they have for the past 40 years — mainly as torqued gold. I'd simply urge you to think about silver differently, since silver demand is so linked to changing our energy sources, it won't behave the way it has before. So when gold rises, I'm sure silver will too, and when copper rises, I'm sure silver will too. But if solar demand is what I've outlined, then a higher silver price is inevitable no matter what gold and copper do. With that, what I'd like to do is — Anvita, you mentioned you had a question from one of the analysts who's traveling, so why don't you tell me what that question is?
Anvita Patil
executiveCorrect, Phil. A question has come in from Mike Parkin at National Bank. He's currently traveling. So let's pass this one along. Management's views are being sought on how long it might take before Keno Hill is running in line with Hecla's standards of practice.
Phillips Baker
executiveOkay, I suppose I'll offer a few remarks, then pass things over to Lauren and Carlos. But at the most basic level, our standard of practice is something we'll never actually arrive at; it's an ongoing effort at improvement, so it's going to require time; to actually get there — basically, you never will. Still, we're going to send — Carlos and his team are going to head out there, and they'll simply verify that we are — that every process is in place, every procedure, and we'll confirm there's an awareness at the site regarding how much safety matters and regarding following the practices and procedures. That genuinely is where you begin. And after that, how do you design risks away. Luckily, given the infrastructure we're installing, we're positioned quite well to watch that occur. With that said, I'll hand things to the two of you. Lauren, is there anything you'd like to add?
Lauren Roberts
executiveAll right, I'll kick things off, and then hand things over to Carlos. When it comes to Keno, here's how I'd frame it: over the last 12 months, our attention has been squarely on getting the first mine development done and putting the infrastructure in place. That stage is basically wrapping up at this point. And like Phil mentioned, our process kept evolving even while we were in that stage of work. So now our attention has to shift toward how we run operations day to day and toward meeting the commitments we've made on that front. With that in mind, Carlos plus several colleagues from our corporate tech services group are traveling up there this week to get that effort underway. Carlos, can you walk everyone through the specifics?
Carlos Aguiar
executiveCorrect. We're nearing that point, and things are moving forward — safety comes first for us, and we're making certain the proper personnel are available at the proper moment, in the proper location, with every material and piece of equipment ready. So this will require a certain amount of time, and we still lack certainty. Our expectation is that we will wrap up that first evaluation prior to the year's end; following that, we'll carry out the plan.
Lauren Roberts
executiveOkay, so here's what I'd tell you: Keno is going to deliver a meaningful amount of output during 2024. When we provide our 2024 guidance early in the New Year, you'll get the precise figure we're expecting. So, Anvita, anything else before we go to the operator?
Anvita Patil
executiveThat is all.
Lauren Roberts
executiveOkay. Operator, you can open the call for questions.
Heiko Ihle
analystHi there. I appreciate you answering my questions, and I want to add my thanks alongside Phil to Lauren for everything he has contributed to the company. I had no idea you'd been with the organization ever since your time as a summer intern.
Lauren Roberts
executiveThat's right. It all began quite a while back, Heiko.
Heiko Ihle
analystThis follows up a bit on what was asked via email, though what I mean is, at Keno Hill there have been a few delays related to mine infrastructure. That doesn't worry us, particularly given that drilling on site appears to be progressing rather nicely. Still, could you give us some detail on what precisely you're observing, and then as well the schedules and expected expenses for fixing the problems you continue to deal with?
Phillips Baker
executiveWell, I'd say the brief response is that it involves multiple factors. There isn't only a single item. That therefore ties back to the culture being built at the location. And we are only — when you consider it, we have been running for roughly 5 months now. Consequently, and you've got individuals arriving from every part of Canada, out of various mines. Their expectations have differed, their practices have differed, yet they'll explain the identical situation. You employ alternate terms for the identical situation, and that turns into a communication problem. Thus it isn't, there isn't a single item we must address. It truly concerns the culture. Would you fellows like to chime in.
Lauren Roberts
executiveAbsolutely, Phil, I’d say that’s right. Keno stands out because it truly acts as a blend of Canada’s mining regions, stretching from the east to the west. That means you don’t get a real concentration of workers or oversight stemming from any single place. Because of that, we have to create the culture from nothing, shaped the way we at Hecla want it to be. That will require some time from us. Yet output will follow as that cultural shift unfolds, and once the culture gels, output will get better. So really, this is a typical early-stage mine process, though at Keno it’s somewhat distinctive because of how varied the workforce is there.
Phillips Baker
executiveYet it comes down to actions, actions taken by the miners, by those supervising them, and across the entire company. And what we're doing is shifting mindsets, which is what allows those actions to shift.
Heiko Ihle
analystOkay, that's logical. Moving to an entirely separate topic. Your capital guidance stayed the same. Could you give us some detail about the inflation you're observing on the expense side? Specifically, how do things stand relative to your expectations, and more broadly, what are you noticing when it comes to cost inflation — which line items are doing better, and which ones might be somewhat worse than you'd anticipated? And along those lines, are there any bottlenecks affecting the availability of anything?
Phillips Baker
executiveI'll hand things over to Lauren, Russell, and Carlos. From where I sit, the pressure from inflation has eased. There's no question in my mind that certain items in both capital and operating costs are still experiencing inflationary pressure, but it's nothing like what we saw before.
Lauren Roberts
executiveYeah, absolutely. Inflation has a way of hanging around, Heiko — it shows up fast and then it takes forever to come down — but the huge jumps we saw earlier aren't happening anymore. I'd describe the situation as pretty much level. Fuel costs are beginning to ease off, so nothing dramatic is shifting at the moment. When it comes to supply, my guess is we can obtain the equipment and materials we require. Certain items take longer to arrive than they did before COVID. Transformers, for example, are extremely slow with really extended lead times, though even those are starting to get shorter on the lead time front. Skilled trades are likely the toughest piece. And I believe everyone across the industry deals with that identical problem. It's partly generational — older workers are beginning to retire while not enough new people are entering. So we bring on fairly inexperienced individuals and provide training. We've encountered this situation in the past, maybe around 20 years ago, and now we're going through it again.
Heiko Ihle
analystThat's all I had. I'll rejoin the queue. Thanks.
Lauren Roberts
executiveThank you, Heiko.
Michael Siperco
analystThank you. I really appreciate everyone letting me ask. Perhaps we can turn to Lucky Friday now. You laid out what seem to be the three main things that have to get finished before the mine can restart. From what was said, though, it sounds as if roughly 15% of that work across all three items is complete. Would that be accurate, or how ought we to think about the schedule and the effort needed to finish that rehabilitation?
Phillips Baker
executiveThe brief response is that, barring any big unexpected development, we'll have it wrapped up quite early in January. Carlos?
Carlos Aguiar
executiveYeah. Right now, we're sitting at somewhere from 35% to 40% done with the project. And like you mentioned, we're looking at getting the mine going again beginning in early 2024.
Lauren Roberts
executiveCarlos and I actually went down into the mine yesterday to check on how things are going, and in a few areas we're running a little ahead of the plan, so what we saw made us happy.
Michael Siperco
analystAll right, so has the bypass event—has the raise actually begun at this point? From what was said, it doesn't quite sound like…
Lauren Roberts
executiveBoth raises have kicked off, and where does the ramp stand? Carlos says 35% done, so yes, both are underway.
Carlos Aguiar
executiveThat figure is 40%.
Michael Siperco
analystUnderstood. And after that…
Phillips Baker
executiveMichael, this involves a contractor—one who arrived and got going roughly a month back, starting first on the escapeway. Then, more lately, that contractor shifted to the ventilation. We understand the ventilation raise isn’t required in order to resume production. What sits on the critical path is the escapeway. For a stretch of time, we can manage with the ventilation we already have.
Michael Siperco
analystAll right, that actually leads into what I was going to ask next. So the escapeway sits on the critical path, and you feel good about — I think we've got roughly 2 months to wrap that up and have Lucky producing again by, let's say, February? Does that sound like a reasonable way to frame it?
Phillips Baker
executiveJanuary.
Michael Siperco
analystWe'll be back up and running in January.
Phillips Baker
executiveShould it be February, then something we didn't anticipate will have occurred.
Michael Siperco
analystGot it. Alright, so regarding the insurance side, could you tell us whether you expect to gain clarity on what's going to be reimbursed, and when that might happen? Should we assume that the full $25 million in expenses you described — Lucky's costs plus business continuity — will be covered? Is that the correct interpretation?
Phillips Baker
executiveWhat I can tell you is this: the figure definitely won't exceed $50 million. As is always the case when you file a claim with an insurer, there's a procedure involved, and we're currently working through it. I can't say with certainty how it will turn out, but we have strong confidence that a substantial share of the costs and business interruption, reaching as high as $50 million, will come through. Russell, is there anything you'd like to add?
Russell Lawlar
executiveYeah. It's clearly still developing as we go through the steps of bringing Lucky Friday back up — we've been in touch with the insurer, and right now we're just moving through that process. Then, whenever additional details emerge or things become clearer, we'll be able to share that with the market.
Michael Siperco
analystis it right to view this as roughly a 6-month type of process, or might it be something that gets finished around the time Lucky resumes production?
Phillips Baker
executivethe response to that depends on which person at Hecla you approach. Look, Michael, to stay on the cautious side, I'd suggest thinking closer to 6 months rather than right away, though in my view they ought to pay us right away. So that part I'd agree with. From a conservatism standpoint, you probably should push it further into the future somewhat, but that could shift at any moment while we work through this process.
Michael Siperco
analystAll right, that makes sense. I really appreciate it. I'll hand it over to someone else.
Phillips Baker
executiveAll right.
Lucas Pipes
analystThanks a lot, operator. Lauren, congratulations from me as well. For my first questions, I'd like to turn to Phil. Regarding what you brought up about silver on the solar side, if someone wanted to replace silver in a PV solar panel, what would they use?
Phillips Baker
executiveIn the end, copper is what serves as that replacement. The difficulty lies in the fact that when it comes to the manufacturing methods for making solar, those processes mean you have to rely on our buildings — yes, solar — you have to rely on silver; and beyond that, when copper is used, the solar panels' performance along with their durability drops considerably. So does a price exist at which the industry would switch? Yes, certainly one does; yet at the same time, copper prices are rising, and so is copper's availability. So it's definitely not something anybody expects to happen over the coming 10 years. Another point worth noting is that new processes exist — the new plants currently under construction all use processes that call for still greater amounts of silver. That need arises because building this way is not only less expensive, but it also delivers better efficiency, and keep in mind these solar panels run at roughly 25% to 30% efficiency when silver is used. With these new processes, that figure reaches the top of that range.
Lucas Pipes
analystThat's useful. Phil, looking at things from your position as someone who provides silver, does it change anything for you if those solar panels get made over in Asia versus being produced closer to the U.S., just as an example?
Phillips Baker
executiveI suppose in a real-world sense, it makes no difference when I'm simply considering the supply chain; it would be wonderful to see manufacturing happen in the U.S. or in nations that are allies of the U.S. — friendly might be a nicer word to use there. That would avoid possible interruptions with the cells originating from China, since China accounts for, I'm not sure, 80%, 90% of the entire solar panel output.
Lucas Pipes
analystYes. Would you be having discussions regarding offtake or supply arrangements with prospective buyers?
Phillips Baker
executiveYes. Keep in mind that what we generate is a concentrate destined for smelters, and sadly, no smelter is capable of — bear in mind that within the U.S. there are very few smelters, and not one of them can truly handle our material; up in Canada, a handful of smelters are able to handle it, but honestly, we must send the material all the way to Korea and Japan for processing; therefore, we sit one step removed from that end customer. It enters the smelter. The metal does not come back to us. We incur a fee, a treatment charge, for working that material.
Lucas Pipes
analystYeah. All right. No, that helps. I'll definitely be watching that closely. Turning back to Keno, could you refresh our memory on precisely what led to the deceleration in the infrastructure work?
Phillips Baker
executiveI mean, I'd say the reason for the slowdown is partly our location — getting personnel and supplies into the Yukon. That's likely been the largest, largest hurdle we've faced. Having camp capacity, getting — you need to get everything more or less lined up so that the camp capacity has been expanded. Then you'll have the space to bring personnel in to perform the work. Lauren?
Lauren Roberts
executiveCarlos?
Carlos Aguiar
executiveSure. Contractors make up nearly 25% of the people working for us, and since they all come on board around the same time, that leads to certain slowdowns when it comes to getting projects done.
Phillips Baker
executiveWell, Lucas, here's the positive side of things — since those infrastructure efforts are basically wrapped up, we've still got a bit of tidying to take care of over the course of November on a few of them. By the close of this month, the rockfill plant is going to be finished. Aside from some electrical tasks scheduled to take place during November, the crusher is complete. So we've put all of that behind us, and as we look toward capital spending for the coming year, it's considerably lower than what we currently have; and although the budget isn't finalized and we aren't ready to offer guidance on what that capital figure will be, it's significantly reduced.
Lucas Pipes
analystThat's useful. At what point would you anticipate letting go of a portion of the contractors and the workforce at that location?
Phillips Baker
executiveA portion of that is occurring right now, though mostly in December.
Lucas Pipes
analystAll right, that's useful. I really appreciate the detail. Thanks, and good luck.
Phillips Baker
executiveMany thanks.
Steven Green
analystHey, everybody. I've got one quick question about Greens Creek. Right, you raised the guidance somewhat for this year. And you came in somewhat above guidance last year as well. It looks like grades are what's driving that. Could you verify that, and is what you're seeing a favorable reconciliation on grade, or is it simply that you're in a few stopes with higher grades?
Phillips Baker
executiveGrades are what's driving it, and it's a touch higher. You know, it really doesn't require much extra grade for the effect to be fairly significant. Gold especially has been — reconciliation on the grade side has come in higher, and that's a thing we've needed to contend with over the entire life of the mine; the distribution of gold is pretty nuggety. And naturally, we've had metals at lower grades. So because of that, we've had lower — it's a strange situation, honestly. You get more gold, you get more silver, yet since there's less lead and zinc for each ounce and gold for each ounce, your cost for each ounce ends up higher; but then again, since you've got more ounces for that to be spread across; but yes, the grade reconciliation is slightly positive. Lauren, anything you'd like to add?
Lauren Roberts
executiveNo, you've got that right.
Steven Green
analystAll right. We're only 2 months out from 2024 at this point, and my recollection is that your earlier longer-range outlook pointed to somewhat weaker grades — at least where silver is concerned — during 2024. What does it look like today, and do you anticipate this latest showing carrying over into next year too?
Phillips Baker
executiveYes. Look, on a broad basis, what you're going to observe across the coming 10 years is somewhat reduced grades at Greens Creek, and that simply comes down to our effort to get the most NPV possible out of the asset. So yes, count on weaker grades, and one way we're working to counterbalance that is by pushing more throughput. That explains why you've watched us work toward reaching 2,600 tons per day. For some perspective, back when we became operator of Greens Creek, at the point we bought the stake we didn't already own in 2008, throughput stood at approximately 2,100, or perhaps slightly under that many tons per day. So today we sit at 2,600, and we've moved from around a quarter of the tons being long hole to an extremely small share. That's a massive achievement inside the mine. And as for the mill, it's accomplishing far more than anybody ever imagined that mill could handle. So it's quite an achievement that the team has pulled off at Greens Creek. I would — they never stop hunting for ways to make the operation better, so it wouldn't shock me if they manage to uncover further improvements. But on a broad basis, we ought to see somewhat reduced production as grades come down. Okay. Just keep in mind on recoveries, recoveries have risen enormously. I'm attempting to recall the figures, but it's 5, 6 percentage points.
Lauren Roberts
executiveRight, it's a substantial amount. And despite going from 2,300 to 2,600 tons per day, we observed no significant drop in recovery.
Phillips Baker
executiveSo don't get overly excited about what these folks are capable of. Let's begin with what the grade and the figures would indicate. Still, this is an excellent crew that operates at Greens Creek.
Steven Green
analystAlright, that's reasonable, and it does help. Appreciate it.
Phillips Baker
executiveAlright. Thanks for those questions. The engagement we get from you is something we truly enjoy. So let me note that the chance exists, should anyone wish to speak one-on-one with any of us. We've arranged time for exactly that, so please make use of it. I'd also like to express appreciation to the groups of individuals at Hecla, since they're the reason Hecla stands out as a distinctive silver producer. And once more, my thanks go to Lauren for what he has given us. With that, enjoy the rest of your day.
Operator
operatorI want to express appreciation to the people who spoke during today's presentation, and thanks to everyone for being with us. That brings today's call to an end, so you're free to hang up at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Hecla Mining Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Hecla Mining Company earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hecla Mining Company or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.