Hindustan Oil Exploration Company Limited (500186) Earnings Call Transcript & Summary
September 8, 2020
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to the Q1 FY '21 Earnings Conference Call of Hindustan Oil Exploration Company Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Anuj Sonpal from Valorem Advisors. Thank you, and over to you, sir.
Anuj Sonpal
attendeeThank you, Stephen. Good morning, everyone, and a warm welcome to you all. My name is Anuj Sonpal from Valorem Advisors. We represent the Investor Relations of HOEC Limited. On behalf of the company, I would like to thank you all for participating in the company's earnings conference call for the first quarter ended of financial year 2021. Before we begin, I would like to mention a short cautionary statement. Some of the statements made in today's earnings conference call may be forward-looking in nature. Such forward-looking statements are subject to risks and uncertainties, which could cause actual results to differ from those anticipated. Such statements are based on management's beliefs as well as assumptions made by and information currently available to management. Audiences are cautioned not to place any undue reliance on these forward-looking statements in making any investment decisions. The purpose of today's earnings conference call is purely to educate and bring awareness about the company's fundamental business and financial quarter under review. I would now like to introduce you to the management of HOEC Limited participating with us in today's con call. We have with us Mr. P. Elango, Managing Director; and Mr. R. Jeevanandam, Whole-Time Director and Chief Financial Officer. Without much delay, I request Mr. Elango to give his opening remarks. Thank you, and over to you, sir.
Pandarinathan Elango
executiveThank you, Anuj, and good morning, everyone, and a very warm welcome to our call on quarterly results of Q1 FY '21. Hope all of you are safe. I have with me our CFO and Executive Director, Mr. Jeevanandam; and Valorem Advisors, our Investor Relations advisers. I hope you all have received our updated earnings presentation. We've also uploaded that on our website. For the last couple of weeks, the company has been in the news for wrong reasons. The issues raised about the liabilities of the company are important to all stakeholders and naturally so. We believe that this earning call is the right forum rather than media to state the facts, clarify specific issues and address any remaining concerns. And we will spend as much time as required to do so. But first, please allow me to update you with highlights of Q1 FY '21. Our Dirok field in Assam continues to set new benchmarks on safe operations. The field is producing at its full capacity safely, amidst raising COVID cases in the region. From producing around half of its capacity in April 2020, Dirok production has increased gradually reaching full capacity in June 2020. Average daily Dirok gas sales during Q1 was 28.3 MMSCFD. Increasing demand from consumers in the region for additional gas gives us confidence to achieve consistent long-term performance in Dirok asset. However, further investment to expand the capacity will have to await policy reforms on free market gas pricing. Industry has represented to the government to do so before gas prices for the next 6 months effective October 1, 2020 are announced. In PY-1 in South there had been prolonged customer shutdowns and inconsistent offtake, which have impacted performance of our wells, which needs some workover. This situation continues with the COVID-related lockdowns that resulted in reduced demand for power. Gas-based power plants continue to ramp low in the power purchase merit order in Tamil Nadu. During Q1, we had to temporarily suspend the operation for 10 days as a safety measure. Overall, PY-1 average gas offtake during Q1 was 1.5 MMSCFD. To enhance production, workover of existing offshore wells and new wells will be required. Geological studies are ongoing to plan the next drilling campaign in this unique fractured basement reservoir. Applications for environmental clearance have been filed and under process. Plan is to commence drilling in PY-1 after first oil from B-80. In B-80, Mumbai offshore, our project planning is gearing up to mobilize men and material when the monsoon window opens in November 2020. We are currently in the market to source flexible oil and gas export pipelines and the CALM buoy mooring system. The Mobile Offshore Processing Unit called MOPU, is ready to sail from Lamprell shipyard in Sharjah. Floating storage and offloading tanker, Prem Pride, is in Sri Lanka and will undergo drydocking soon. Considering the prevailing uncertain operating and business environment, our 100% focus is to complete the ongoing project works, install and commission all the facilities during the November, April weather window to deliver first oil from B-80 as soon as possible. Let me now turn to a few important issues raised in public domain about HOEC. First, did the company delay in disclosing about the interim order of the honorable High Court of Gujarat? Answer is no. We received the order by mail only on 25th August 2020 and promptly made the disclosure. Second, what is the amount quantified in arbitration award? Was it INR 27 crores? Answer is, again, no. Estimated amount of award involving HOEC share is USD 1.65 million. The award amount included certain ancillary items subject to reconciliation among all parties in regard to cash costs, payments and other credits between parties. If this reconciliation effort fails, the matter needs to be referred back to the arbitrators for determination. So far, no reconciliation effort has commenced. Third, when ONGC could reach a settlement on the award with Hardy, why did HOEC choose to appeal? The award by majority was in favor of claims made by Hardy against the 3 nonoperators, namely ONGC, HOEC and TPL. TPL and Hardy are controlled now by the same group. ONGC and HOEC were to jointly appeal, but then Hardy made an exclusive settlement offer to ONGC, waiving claims of more than half of the award sum. Details of the settlement have not been shared with us as yet. We will seek them in the appropriate JV forum. HOEC, based on legal opinion, believes that there are multiple grounds to challenge the award and has already filed the appeal in the High Court of Malaysia. Fourth, where did this INR 720 crores liability figure cropped up? And what are the current liability numbers? Section 9 of the Arbitration Act allows a successful claimant to secure an award if it has reasons to believe that responder would be unable to play -- pay the award sum if and when the award becomes enforceable at the end of an appeal process. It is a matter of public record that HOEC has a group balance sheet strength of over INR 1,000 crores, net worth of INR 665 crores and cash balance of INR 171 crores as on March 31, 2020. And the amount being claimed by Hardy was only INR 27 crores without any details. The claimant can request court to order appropriate security to secure the award as sum. Instead, Hardy chose to file an affidavit clubbing all current liabilities, noncurrent liabilities, contingent liabilities, claims not admitted by the company as sums payable to arrive at INR 720 crores. These items are not homogeneous. Apples and oranges can't be clubbed and counted in 1 category. Company has made a detailed disclosure, providing breakup of current, noncurrent and contingent liability. The sums under these various heads can't become payable together at any single point in time. Let me explain the largest single item in the basket of contingent liabilities so that you all can understand and appreciate the probability of its occurrence. Demand for service tax were received by operators of unincorporated joint ventures by wrongly treating operators such as HOEC as contractors who provide services to government and JV partners. Demand notices running to several hundred crores were slapped on multiple operators to pay service tax on work programs executed by operators on behalf of JV, cash costs issued to partners and royalty and profit petroleum paid to government. Industry made series of representation and Ministry of Petroleum supported the stand of the industry and wrote to finance ministry to issue clarifications that operators as co-owners with participating interest cannot be treated as contractors rendering service to companies. Operators would not provide services to government either. Including interest, the demand on this account is INR 173 crores and it is appearing as a contingent liability. Also, part of this sum pertains to joint venture are not this company alone. On merits, the companies have a strong case and hence all avenues, including legal remedies, if required, will be pursued in due course of time. On all such liabilities that are contingent in nature, the management will continue to make its judgment, explain the rationale to its auditors and classify them appropriately following standard accounting and industry practices and never ever will seek to hide anything from any of its stakeholders. I wish we had the time to get into details on each item. We don't. So I would make 2 broader points, and we will address specific questions in the Q&A session. Ever since the opening of upstream sector for private players in mid-'90s, there have been 3 policy regimes: pre-NELP, NELP regime under production sharing contracts and now HELP regime under revenue sharing contracts. Under PSC model, 2 legacy issues are: #1, penalty for unfinished minimum work programs; and #2, disputes on calculation on eligible cost petroleum to determine cost recovery and profit petroleum. Under revenue sharing contract model, there is no cost recovery involved and liquidated damages for unfinished work program is quantified as $1 million for onshore wells, $3 million for offshore wells. Since in PSC, liquidated damages have not been provided, almost every operator in the country has several ongoing legacy issues on this account. And many representations had been made to government and government has made several process improvements to govern future blocks under HELP. But unfortunately, legacy issues of pre-NELP and NELP blocks linger on. It will take long time to bring these issues to closure. Methods of calculating cost petroleum, profit petroleum, statutory levies such as royalty and cess and service tax computations are complex and their details give rise to claims and counterclaims. On such common issues, the company works with the industry to seek policy relief from the government. The company is actively involved in these industry matters. We realized that we cannot let these legacy issues linger on forever. We'll have to -- we will have these matters legally examined and seek resolution of issues, including through dispute resolution committees constituted by the government. This will be a time-bound and cost-effective way of resolving the long outstanding issues that add up as contingent liabilities. Finally, I would like to recall that when we began this turnaround journey of this company in 2015, with INR 36 crores cash balance without raising new capital or borrowing, team HOEC has developed feeds and acquired companies to grow the gross operator production from 750 barrels of oil equivalent per day to 7,500 barrels of equivalent per day and set to double that once B-80 is on production mode. In B-80, our G&G team has been diligently working even during the lockdown on interpreting a large volume of critical new data that we acquired by drilling 2 new wells with 5 existing wells' data. These internal interpretations have now been completed, and the results meet more than our expectations. These are right now being reviewed in London by Gaffney, Cline & Associates, GCA, a globally reputed firm that carries out independent assessment of reserves and resources. We expect this to be completed over the next few weeks and would present it for review by DGH and share the results publicly. Overall, the company is managed by professionals who value integrity more than anything else in life. We have an eminent board to guide the management. We assure you that the company has sufficient cash and revenue streams to meet all its liabilities, present and future. We will continue to focus on our operations, bring B-80 to production while following best practices in our accounting, reporting and communication. I now invite our CFO, Jeeva, to take you through the financials. Thank you.
Ramasamy Jeevanandam
executiveThanks, Elango. We report that the company made a revenue of INR 27 crores in the current quarter against INR 35 crores in the previous quarter. In the consolidated account, it is INR 29 crores against INR 40 crores in the previous quarter. This reduction in revenue is mainly due to reduction in the gas price realization from $3.57 per MMBtu to $2.64 in the current quarter. Though there is a little -- the production was almost stabilized, and this is -- the price is an impact for this reduction. This quarter, profit on stand-alone is INR 13 crores against INR 19 crores in the previous quarter. In the consol account, it remains the same level. Total expenses of stand-alone is INR 14 crores, comparing INR 17 crores in the previous quarter. Statutory levies such as royalties ad valorem and some other costs are optimized results in the reduction for this quarter. For this quarter, the total expenses, including depreciation and depletion in the consolidated account, is INR 18 crores comparing INR 30 crores in the previous quarter. Operating cash flow stand-alone for this quarter, including interest income, is INR 18 crores comparing INR 20 crores in the previous quarter. In the consolidated results it remains the same. The company stand-alone cash and cash equivalents of about INR 128 crores as on June 30, 2020. In case of B-80 development, Mobile Offshore Processing Unit is ready to move from yard, and we will be settling all their liabilities there on. Similarly, associated -- floating storage offshore, Prem Pride, is to be drydocked in Sri Lanka, and we will be able to meet their obligations to make the vessel ready to receive the oil in the field. These facilities are resourced through our own subsidiaries with borrowed capital of about INR 85 crores, which levers around 33%. These assets such as MOPU and FSO are mobile assets, and there is a value uptick and -- when it is put to use in the field. This will enable us to operate the B-80 fleet with a marginal cost, which ensures most recovery from the field. We submit our current liability and the consolidated accounts as on June 30 is INR 221 crores and the noncurrent liabilities such as provision for site restoration INR 143 crores. And we still has a site restoration deposit with the State Bank of India for INR 66 crores. Our contingent liabilities as on March 2020, which is widely being discussed, it's mainly on service tax demand on the cost petroleum of INR 59 crores and cash cost from the JV partner is INR 28 crores, which makes a total of INR 87 crores, and the equivalent amount as penalty, which makes a total of INR 174 crores for the period from 2010/'11 to 2014 and '15. We submit this is an industry issue. You are aware that service tax is subsumed with GST, but no GST on this as on date. Department needs a clarification on this issue from the Ministry of Finance, and it is recommended by MoPNG that it is not leviable on cost petroleum on cash call receipts. August 5, 2019, MoPNG sent a letter to Ministry of Finance stating that circular number February 12, 2018, cost petroleum is not a consideration for service, therefore, no service tax should be leviable. It has been taken as a contingent liability and disclosed as demand exist in form, but in substance, it would not just allow as a liability as all inputs, which construe the costs are already subject to service tax, which was duly paid. Hardy arbitration, contingent liability already exists for INR 16 crores. And for ongoing arbitration by Hardy and Aban, yes, we were a -- we are a partner there with 21%, an amount of INR 15 crores is also considered as a contingent liability. Hardy already -- as Elango rightly said, Hardy already challenged it in the court of Malaysia. PY-1 royalty demand was INR 13 crores. As per the PSC, as per the subsequent surplus, it should be on the wallet price, not on the realized price. This issue is hovering around since the commencement of the production in 2009, and our claim for refund of excess paid is INR 15 crores. This issue starts from 2009 and '10. In case of CBOS1, immediately before surveying the block, ONGC carried out a soil survey and made a claim along with G&A cost for INR 12.45 crores, which was disputed, and the matter is before the tribunal with a counterclaim of INR 65 crores. In Arunachal Pradesh, the block called Jairampur, that's called AAO1-2003-2. Geopetrol even after considering the drilling pad could not drill the well as the foundation collapsed being a hilly area. The estimated liability thereon is $4 million and $2.23 million has already been paid. And in the books, we still carry a liability of $1.64 million. The demand in addition to $1.64 million is not tenable, and is also shown in the books as a contingent liability to the tune of INR 12.36 crore. This makes a total contingent liability of INR 244 crores. It is also some news item appeared in Kharsang block, a demand letter was issued on June 4, 2020 for USD 18.6 million as a principal and $6.2 million towards the interest on a disputed related to the cost recovery limit and it is to state that cost recovery limit and enhancement for 85 months government delay and fixing the base year as '92/'93 and not as '95/'96, is a 2-year -- 2-decade old dispute. This was immediately refuted by the operator on June 10, 2020, itself saying that the demand has no basis. Immediately thereafter, NMC was called by the DGH on June 15 and agreed to consider about 5.6 years as delayed by government of India and agreed for the indexation of the cost recovery limit. The computation of the liability is yet to be worked out by DGH and we are awaiting for it. As per the operators estimation for the share of Geopetrol is less than INR 2 crores payable and the dispute through DRP is about INR 8 crores. In case of block RJ-1 was surrendered under the policy with no cost for minimum work program not completed because there was a delay in government clearance for more than 3 years. In RJ-2 block, OIL is the operator and as per the estimated liability created as per the operators for our share is INR 6.7 crores, which has been duly accounted in the books of accounts. We are confident that we'll meet all our obligations with overall growth of E&P assets in HOEC and its subsidiaries in oil field services. This could be met by cash in hand, internal accruals and asset-backed borrowing through its subsidiaries. Thanks, Elango.
Pandarinathan Elango
executiveThank you, Jeeva, and we can open up the forum for questions, please.
Operator
operator[Operator Instructions] The first question is from the line of Riddhesh Gandhi from Discovery Capital.
Riddhesh Gandhi;Discovery Capital;Founder
analystJust a couple of questions. On actually B-80, can you just actually run us through the time lines for -- actually, when we expect to start production [Foreign Language] of actually first oil? And how good a ramp-up schedule would you look at? And how long it would be for us to be at 100% actually the production levels?
Pandarinathan Elango
executiveYes. Thank you, Riddhesh. On -- in B-80, as we said earlier, there are 3 modules to the project. The first module is the Mobile Offshore Process Unit, which is completed. And right now undergoing some minor modification in Sharjah, Lamprell yard and will be mobilized once the weather window opens in November. Second module is actual drilling of the wells, which have been completed, tested and varletries have been installed. The third module, which is to be installed, is really related to export system, which is the gas pipeline will have to be connected to the existing ONGC pipeline system and the oil pipeline will be connected to the FSO Prem Pride along with the CALM buoy mooring system. All this works we expect to take about 45 to 60 days and can only be done during a fair weather window, which typically in Western offshore, commences sometime in November and goes on till end of April. So we already are in touch with the major installation contractors who have contracts with ONGC and would be mobilizing the spread to fit a right schedule to complete this installation. So our endeavor would be to do all of them before March 31 of this financial year so that the production can commence from April 1. We do not expect any much ramp-up time to achieve the target production rate of 5,000 barrels of oil and 50 million cubic feet of gas. The ramp-up would be fairly quick but the work on installation is fairly complex and will be done following the right processes.
Operator
operatorMr. Gandhi, you have any more questions?
Riddhesh Gandhi;Discovery Capital;Founder
analystYes. And how much is our current cost of actually the extraction for the oil and gas in B-80, incremental power start -- production start?
Ramasamy Jeevanandam
executiveThis is having 2 element of cost. One is development cost. The development cost to us is about $55 million. And out of $55 million, if you look at the volume we are estimating is about, say, assume it should be more or less, we will be waiting for the GCA results. If you assume it is a 10 million barrel, it is in a nonaverage, without giving a time line of money, it is $5 -- $5.5 development. And the operating cost would be around $60. If we produce around, say, 6,000 barrels, it is $10. If you produce 8,000 barrels it will be around $8 to $9. So total cost basis would be on -- without giving time line, it should be around $14 to $15.
Riddhesh Gandhi;Discovery Capital;Founder
analystGot it. Sir, and the last question which I had was in the lines of this service tax liability and the claim for operators. I mean, effectively, this would be a claim on -- which would be on all operators and for others, for example, Reliance and all this number would be extremely large. So -- and is that accurate in terms of is this a claim on all operators effectively or only us? Or how should we look at it?
Pandarinathan Elango
executiveIt is on most of the operators, but these demands are issued by different regions. And for us, we understand that such a demand has been made on several other players. I don't want to name them all. But ONGC is clearly one of them. And all the major operators have received the demand.
Riddhesh Gandhi;Discovery Capital;Founder
analystGot it. Got it. And -- but our -- actually the view is that there isn't any like -- there's -- it's an extremely like a low likelihood that we're going to have to pay this?
Pandarinathan Elango
executiveYes. That is our view.
Operator
operatorThe next question is from the line of [ Sushil Agarwal ], an individual investor. As there is no reply from the current participant, we move to the next question from the line of Sunil Bhalotia (sic) [ Sumit Bhalotia ] from MK Ventures.
Sumit Bhalotia;MK Ventures;Fund Manager
analystYes. First part of the question, you already responded in terms of time line of B-80. Secondly, I wanted to get some more color on the quality of output and quality of crude oil that will be -- that we're expecting from B-80 in terms of whether any processing is needed for loading and AP and sulfur content. One is that. And secondly, on the realization front, the number that you had shared in the last quarter, I think they were based on assumption of oil being at $30, $35. So assuming $45 realization of crude oil, how does the government sharing change? And what could be the possible numbers from B-80?
Pandarinathan Elango
executiveSee, first of all, on the quality of oil, it's sweet waxy crude oil, there is no sulfur content. It's light. We have send the samples for detailed analysis. And once the results come, we will share it with the refineries to determine the pricing on the quality of oil. As far as the cost, as Jeeva explained, we are looking at a netback of about $20 to $25 per barrel in the $40, $45 regime.
Sumit Bhalotia;MK Ventures;Fund Manager
analystThe government sharing would be the same?
Pandarinathan Elango
executiveAs sharing with the revenue. Revenue sharing with the government is on a percentage basis, which is if the daily revenue, which we expect average to be in the range of about 23%, 24%, average over is life of the field. It starts with the lower end of 12% and goes to 56%. When the revenue per day is more than $1 million, it is 56%. And the revenue -- gross revenue per day is less than $10,000, it is 12%. So average, you can take about 24%.
Sumit Bhalotia;MK Ventures;Fund Manager
analystOkay. Okay. Sir, 1 more question on the cash numbers, and maybe I missed out or misread the numbers. The cash equivalent that we have as of March end was around INR 170 crore, INR 171 crore. And I think you mentioned that cash equivalent as of June end is around INR 128 crore. Is that right?
Pandarinathan Elango
executiveCorrect. It is on stand-alone accounts. And in consol accounts, it is a little more than -- it is about 1 -- just a minute, I'll just tell the numbers. In consol account, we have got about INR 167 crores -- INR 166 crores we have got.
Sumit Bhalotia;MK Ventures;Fund Manager
analystConsol INR 167 crores. Okay. Okay. So the movement in cash balance on stand-alone from March to June would be how much?
Pandarinathan Elango
executiveThe movement is -- the reduced movement, I can tell you. That's about some -- it's with INR 140 crores, it becomes INR 128 crores. There is about INR 13 crore reduction. And after adjusting the INR 18 crore cash inflow, it's about INR 31 crores as such.
Sumit Bhalotia;MK Ventures;Fund Manager
analystOkay. And this has been used for the expansion?
Pandarinathan Elango
executiveFor the -- about INR 20 crores we spent on the B-80 development.
Sumit Bhalotia;MK Ventures;Fund Manager
analystOkay. In this quarter?
Pandarinathan Elango
executiveYes.
Operator
operatorThe next question is from the line of Varatharajan from Systematix Group.
Varatharajan Sivasankaran
analystLook at the expenses for the quarter, other expenses and employee expenses seem to be down quite sharply and as you mentioned there...
Pandarinathan Elango
executiveVaratha, can you be a little louder? Your voice is breaking, please.
Varatharajan Sivasankaran
analystYes. Is it better now, sir?
Pandarinathan Elango
executiveYes, Varatha. Yes.
Varatharajan Sivasankaran
analystYes. The employee expense as well as other expenditure for the quarter seem to be down quite sharply. So any reason why that is so?
Pandarinathan Elango
executiveSo it's not very sharp. INR 17 crore, we have reduced about INR 14 crores. We are trying to optimize all the possible costs during the shutdown period, and that has reduced about INR 3 crores, roughly about INR 1 crore per month.
Varatharajan Sivasankaran
analystSo should we take this as a run rate from here on?
Pandarinathan Elango
executiveI think, see, it all gets momentum, then you'll have some travel and other expenses will come. So we can say that INR 17 crore is our -- is the basis. And the 3 months because no movement at all, the offices stand closed and however we are maintaining our fields operations as far as...
Varatharajan Sivasankaran
analystSure. The second part was on the production rate at both North East as well as like PY-1. North East is your claiming it is almost back to normal. Should we take it as sustainable from here on note period to that production?
Pandarinathan Elango
executiveYes, Varatha, it is right.
Varatharajan Sivasankaran
analystOkay. As far as PY-1 is concerned, that plant offtake issue remains. But you had created a contingency, some other player who could potentially take it. Any update on that, sir?
Pandarinathan Elango
executiveVaratha, there is a -- in the current situation, there is no other really willing player as such. So we will have to wait for our job to increase production in PY-1 at the end of [Technical Difficulty] in their alternative arrangements. Right now, no.
Varatharajan Sivasankaran
analystThese guys don't seem to be coming back online anytime soon?
Pandarinathan Elango
executiveNo.
Operator
operatorThe next question is from the line of [ Sunil Joshi ] from Sapient Wealth Advisors. [Operator Instructions] The next question is from the line of Ashwin Reddy from Samatva Investments.
Ashwin Reddy;Samatva Investments;Founder
analystI have a question on the Dirok gas field. Can you clarify if the scale-up to 55 units, which we had planned, is that linked to the freeing up of the gas pricing?
Pandarinathan Elango
executiveYes. What we have done, Ashwin, is we are continuing with the project, but we are focusing on the critical part items like getting the forest clearance and also focusing on laying the pipeline along that route as such. So we have ordered the -- for the pipes and pipes have arrived. So we have commenced the project, but further investment, which is to take it to 55, we will wait for -- by this month end, what kind of policy decisions government makes on the gas pricing side. We -- there are 2 elements to the project. One is laying the pipeline, which we have started now because that is a long lead item. The other part is investing to expand the processing facilities which we have not made the commitment. But we have completed the engineering work. We know the contractor will be the same company, Expro, because it's a modular concept and which we should be able to do that in 9 months. So 2 things we want to watch out for one is a consistency in offtake, which we are seeing now. In fact, as we speak, the volumes have further increased. And then the second part is what is the government finally decides on the pricing front.
Ashwin Reddy;Samatva Investments;Founder
analystOkay. Okay. Understood. And the offtake, which has come back, is it back to the same fertilizer clients, which used to take it before? Or have we found any new clientele? And that's how it's come back to the higher level now?
Pandarinathan Elango
executiveYes. Now these are the same consumers like BCPL, fertilizer and power plants. And so there are no new consumer. But the old -- these consumers are taking and partly driven by the fact that you must have heard about the oil blowout in Baghjan field. Therefore, the Oil India is unable to supply the full volume, so that is helping us to supply more as such.
Ashwin Reddy;Samatva Investments;Founder
analystOkay. Understood. Helpful. And finally, sir, in terms of the Dirok field revenue sharing, which has changed from July 1, 2020. Can you explain in detail about the impact on the P&L and the cash flow statement -- on the cash flow from this field based on the new terms from July 1?
Ramasamy Jeevanandam
executiveThis will impact us about -- say about 7% to 8% of the revenue, and gas price impact also would be around some 12% to 13% we estimate. Total, there would be an impact of 20% of the revenue. But that has now been offsetted by the increase in volume. So overall, the top line would be a reduction of about 4 to 5 million -- INR 4 crores, INR 5 crores, and the bottom line would be about INR 2 crores. That's what we expect.
Ashwin Reddy;Samatva Investments;Founder
analystSo because this happened from July 1, right? So you're saying as compared to June to July, June to September quarter is what you're saying, right, in terms of the revenue?
Ramasamy Jeevanandam
executiveYes.
Operator
operatorNext question is from the line of [ Tejas Shah from Unique Stockbroking ].
Unknown Analyst
analystYes. On the Dirok field, I think the fleet out to the normally what, 33 MMbtu or 40, where I said, I think, a peak price in last year?
Ramasamy Jeevanandam
executiveCorrect. The full production capacity of the -- along modular plant is about 36 million cubic feet, which is equivalent to 1 million cubic meters per day.
Unknown Analyst
analystSo any -- will it reach to that level? Or you are saying 29 is fixed out?
Pandarinathan Elango
executiveNo, no. 29 average was for the last -- Q1. In the current quarter, we are doing better than that. It has increased further.
Unknown Analyst
analystTo what level is possible?
Pandarinathan Elango
executiveAlmost full capacity we are doing, which is about 35 -- so kind of ranges average between 30 to 33, 34. And some days, it goes up further. And what we have done, just to explain further, we've also opened up the additional pipeline, the 4-inch pipeline that we had. Some of you would remember, in Phase 1, when we commenced production, we used the old well and supplied the gas through a 4-inch existing line to Oil India facility. Once the new plant got commissioned, we have laid a 12-inch pipeline through which the new plant output is going. Whenever we see a demand, which is beyond the 36 million cubic feet on odd days, we also have the ability to open the 4-inch line so that we are able to deliver on a single day up to 40 million cubic feet also. And that happens occasionally. But all that makes up -- and the idea is to ensure that on an average basis, we are maintaining well above 30 million cubic feet per day, which we are able to do in this quarter.
Unknown Analyst
analystOkay. Another thing, I think B-80, operational, you are saying it will take around 2 months' time to deploy and function everything, correct? Starting window is around November?
Pandarinathan Elango
executiveThe window for weather starts in November. The work involved, first to bring the Mobile Offshore Unit from Sharjah to Mumbai and position it at the designated site near the well. That is the first activity. Then we will have to lay a pipeline, which is what we call a flexible pipeline between the well and the Mobile Offshore Process Unit that is infield -- similar to an infield pipeline. Then between the MOPU to ONGC's existing gas pipeline. That is basically a pipeline. And thirdly, we will deploy a CALM buoy mooring system and bring the vessel, which is in Sri Lanka, which will undergo drydocking over the next 3 or 4 months period and have the mooring system and have that installed. Finally, the oil pipeline will be connected to that system. So there is -- while the scope of the work per se, because we are talking about 5 kilometer of pipeline total, so it's not a large volume in terms of scope, but the spread that is required is very similar. Suppose if you are laying 100-kilometer pipeline in Bombay High, what's the type of vessel you need? You need a similar type of vessel even for this operation. These are very sophisticated vessel, which can lay that price for us. So what we are doing is to mobilize the spread exclusively for this kind of a small work would be very, very expensive. And remember, we are developing a marginal field in Mumbai High, which ONGC thought is not economical to develop. So obviously, we need to kind of do our own set of innovation. So we are in touch with the contractors who are already mobilizing a spread for ONGC work. We will look for a window of opportunity and get our work done. That will be the cost-effective way. That's why I'm unable to specifically state by which month we will actually finish. But the clock stop date is really April because the weather window ends in that. Our endeavor would be to finish by end of March, which is still doable.
Unknown Analyst
analystOkay. Another thing is last time you had shared [Foreign Language] B-80 is a prepricing market for that. Okay. And you'll be getting some clients from Gujarat, which will build at $4-plus pricing? So any thought on that?
Pandarinathan Elango
executiveYes. The -- it is a free market pricing. There are no pricing controls when it comes to B-80 gas. And the gas will flow through the ONGC pipeline system to reach Gujarat market, specifically the Hazira. A couple of interesting developments since our last call. The gas -- Indian Gas exchange, which is similar to the Power Trading exchange platform, has already been launched. And a small volume of trial trade has been done as well as -- and Hazira is a designated delivery point, which effectively means some of the volume you could trade it in the exchange for physical delivery at Hazira. And there, we have seen prices thereon $4 prices we have seen in the exchange. We have not concluded the pricing discussion. What we thought we will look for what signals government is going to send with any gas pricing reform, which we expect by end of this month, hopefully. And based on that, we will conclude arrangements. But we have established, there is enough demand. The demand has been established, confirmed by GSPL as well as by GAIL and some direct consumers also. But we will be most likely partnering with an aggregator like GSPL or GAIL to ensure our offtake is there. As I was telling, we will commit, let's say, 70%, 80% volume under this model and keep about 20%, 25% model volume for try and do the trading where the trend is now a premium price, whatever is a prevailing market price. At the trading counters, it draws premium, but we will take a call as we come closer.
Unknown Analyst
analystAnd lastly -- okay. So I will come again on the end.
Operator
operator[Operator Instructions] The next question is from the line of Chintan Sheth from Sameeksha Capital.
Chintan Sheth
analystIn your opening -- first on the Hardy issue. In your opening remarks, you mentioned -- as well as in your clarification, the total sum of all the contingent and the reported liabilities adds up to INR 600-odd crores as per your Monday's morning clarification. But if we look at the news articles, they are stating INR 722-odd crores. In your opening remark, you mentioned that this is an apple-to-apple comparison. They have also included the claims. We cannot yet -- management has not yet put a word on it, and that is not getting reported. So I'm just trying to reconcile the differential amount of INR 122-odd crores, which the newspaper articles are suggesting. That is first part of the question. And second is on the contingent liabilities, the counterclaims, if you can put up a separate press release, which Mr. Jeeva has already verbatim pointed out in his opening remarks. If you can put a separate press release citing that these are the claims on the company and these are the counterclaims on the company just to get a more clearer clarity on what company stand that is second part of it?
Pandarinathan Elango
executiveI'll answer the second part and ask Jeeva to answer the first part. In terms of going public on counterclaims on individual court cases or dispute resolution arbitration will not be a correct thing to do. But on the overall, your first number, Jeeva will start giving.
Ramasamy Jeevanandam
executiveWe have given the full details in the annual report, which I think might have been circulated. You can refer to that. No issues on that. We have stated about each claim, what is the nature of the claim, what is the claim made, what is the counterclaim made by us. It is all there. Now if you wanted to have the reconciliation, the total we have current liabilities, there is an undisputed price. The current liability is INR 214 crores and the noncurrent liability is INR 142 crores. And the INR 244 crores is a contingent liability as on March 31, 2020. The difference of INR 722 crores, if you look at, we have already captured about INR 600 crores. INR 122 crore, I will explain what are those amounts. Royalty demand is -- the royalty is based on the wallet value. But it has been government is demanded on the gross price of the sales going on from 2009 and '10 since the field has been put on production. Now if we made actually, there are an excess payment there on -- we made a counterclaim of around INR 15 crore thereon to it. Now the liability there are, we put it into the books of account as a contingent liability, expected liability is INR 13 crores. For that, this newspaper item which says actually INR 41 crores. There is a INR 22 crores sits there into it, okay? And similarly, when you look at our contingent liability on account of the service tax, we take if the demand notice comes to the company, we don't pass on to the same thing because it is not a -- in substance, there is not a liability thereon. So we want to head our dispute with the department. And we don't pass on that to the -- our JV partners, and take this is only my liability. That is to be a liability, right? If that is the case, my INR 173 crore liability is only INR 123 crores. But in the similar case, Hardy claims, there is about INR 12 crore liability thereon, the service tax thereon on 2010 and '11 when they shut the field down. So that is the liability of -- same liability extent of INR 12 crore there, INR 11.9 crore to be exactly. Then there is a block called RJ-1, which we have 25% participating interest. The block has 4 parties. One Jindal, they walked away from the block from the beginning. Then we carried out the seismic. And after that, there was no clearance from defense ministry for a period of 3 years. By using the policy regime of the government of India, where there is a more than 3 years' delay without submitting any work program, you can surrender the block. Using that policy, we have surrendered the block. That is claiming a INR 16 crore liability thereon. Then RJ-2 block, which is operated by the Oil India, and they have completed 2 wells drilling. After that, they start -- this is not contingent to drill any more wells there in, and they've decided to surrender the block. They've surrendered the block. In that, our participating interest is only 20%. The estimated liability thereon is about INR 6 crore for us -- INR 6.7 crores for us, estimated by the operator. We provided it in the books of accounts. There is no further liability exists thereon. So that is another INR 16 crores. Then come to a block called Mizoram. Mizoram is a block, wherein 4 parties were there, and one of the party has submitted some wrong statements. And the PSC itself is nonlist. There is no claim there. No claim is entertainable by us because the PSC itself has not commenced. So that in the statement they are saying, that it's a INR 10 crore liability in their own estimation, right? Then we are talking about a block in Kharsang. This is a dispute goes back from 1995/'96. The PSC was signed in 1992/'93 with the cost recovery limit stated in that. But when the PSC was signed in '95/'96, that should be the starting point. But when this was submitted, it was '92/'93, right? In that case, it's a government delay of about 86 months. That is virtually about 7 years delay. And the 7 years delay, the cost escalation has to be granted by the ministry. If the cost calculation is granted, then there is no issue at all. And this issue has come up suddenly as a consideration of some $24 million is payable by the consortium, wherein we have got only 25%, and then it has come up here in 4th of June. Immediately, it has been refuted by the operator on June 10 stating that this liability is not tenable. There is no basis for it, and you have never accounted the increase in cost escalations as for the PSC. And you have not determined the effective date as '92/'93. This hovering many issues have been raised on the letter on 10th of June. Then immediately thereafter on 15th of June, a management committee meeting was called. In the management committee, as government has considered, there is an accepted fact by the DGH, there is about 5.6 years delay is admissible. Therefore, the escalation benefit is to be given. And now we rework out the liability and then pass on to the companies as such. In the estimation of the operator, this liability is about less than INR 2 crores towards immediately payable. And in the liability, which will be referred to the dispute is about INR 7 crore to INR 8 crore. So there is no basis exist for INR 55 crores. So the total claim of INR 138 crores has no relevance whatsoever.
Chintan Sheth
analystRight. Okay. Sure. And lastly, on your annual report, if I look at your reserve or resource data, there is hardly any movement -- noticeable movement in that number from '19 to '20. Does this mean that we have not yet added the B-80 resources in our reserve data? Or is it included?
Ramasamy Jeevanandam
executiveThe B-80 is a probable reserve data. It is included there.
Chintan Sheth
analystIt's in the -- okay.
Ramasamy Jeevanandam
executiveAnd what we are doing as such, as soon as the GCA report comes, we've made it public to everyone to know what is the volume of probable -- proven reserves, probable reserves and possible reserves there are, and the lead there on and what is the quantum there on. We will make it open to the entire shareholders, and it will be published in the S-8 itself.
Operator
operatorThe next question is from the line of [ Nirbhay Mahawar from N Square Capital ].
Unknown Analyst
analystSir, some follow-up on B-80. What is the total CapEx -- fee level CapEx you have done till now? And what is the balance?
Ramasamy Jeevanandam
executiveSee, we have -- this is essentially a block where the 2-well development and this 2-well development. And then it will be connected through the gas export line. MOPU is also through our subsidiary a contracted facility. And SBM and the floating storage offshore also a contracted facility through our subsidiary. If you look at the B-80 stand-alone development, we have built the 2 wells. The cost of these 2 wells is somewhere around less than $40 million. Now we have to put the gas export line. And there are 2 flow lines, 2 umbilicals and 1 export line to this one -- to floating storage offshore to SBM. The total estimated cost to us should be in the order of say, $10 million to $12 million. We are in the process of getting the quotes. It should be around $10 million to $12 million. Total project by any means, it is not exceeding $53 million for the B-80 development.
Unknown Analyst
analyst$53 million. Okay. And how much of it has been incurred, sir, already?
Ramasamy Jeevanandam
executiveWe have incurred probably exactly about $39 million to $40 million. And that is -- our share is only $20 million because other company has 50% stake. They have about $20 million.
Unknown Analyst
analystFair enough. So close to -- INR 150 crores CWIP has come in our balance sheet?
Ramasamy Jeevanandam
executiveYes. I'll tell you the exact number, investment in properties and there is a stand-alone balance sheet number. Our capital work in progress is about INR 156 crores, INR 156.97 crores. Out of that INR 145 crores goes for the B-80.
Unknown Analyst
analystINR 145 crores is for B-80. And after incurring this CapEx, we have got net CapEx in the balance sheet. Is that correct? How much is the net cash level?
Ramasamy Jeevanandam
executiveThe net cash level is, I told you no, that is about INR 129 crores existing as at the moment on June. And we have certain internal accruals, which comes in total about INR 5 crores to INR 6 crores per month, which comes on it. So we are slowly building up this actually to meet our -- some of the suppliers, which is pending for payment, which we have to make the payment. And then the additional, I told you about $10 million to $12 million, $6 million, our share comes around INR 35 crores. By -- before March, we should spend that money.
Unknown Analyst
analystSo all of it is done through internal accruals, and then also we have been able to maintain this deleverage status of balance sheet.
Ramasamy Jeevanandam
executiveAnd what we are delevering is only with reference to the facilities, which we are using through our subsidiary. For example, FSO, we are taking a loan. That would be deployed for B-80 itself. That is a full year an asset back. Our leverage is only 33% to 40%, max.
Unknown Analyst
analystOkay. Sir, another -- you've been talking about this changes in gas pricing and some of the forms taking place there. What could be the -- what is anticipated? And what could be the implication for HOEC, particularly for Dirok and B-80?
Pandarinathan Elango
executiveAs far as B-80 is concerned, we have a complete marketing and pricing freedom. So clearly, it is an open market basis. Dirok. Dirok we are selling the gas-based on the 6 monthly pricing announced by the government. Every 6 months, the government announces the pricing based on international cocktail of gas prices and Henry Hub and nationally balancing the market in U.K., Russia, Japanese. It's a cocktail formula as such. So the demand from the industry has been that provide us complete marketing and gas pricing freedom, which the government has given to all the fields, which are to be developed after the field development plan approved effective April 1, 2019. In other words, any FDP that was approved after April 1, 2019 is eligible for free marketing and pricing rights. However, some of the old blocks, which were developed in the previous regime, do not enjoy that freedom. And particularly in North East, we are the only private operator supplying and selling gas. You know North East is a very limited market, where the major players are ONGC and Oil India, and the major customers are essentially central government customers. If the new policy of the government opens up marketing and pricing freedom for ONGC and Oil India fields as well, then the whole market is opened up, and we expect market determined prices. You would recall, at one point in time throughout India, the market price -- the uniform price for all NELP and pre-NELP gas was $4.2 per MMBtu. So I broadly take that, the market in India has accepted a price of about $4 throughout. And therefore, if it opens up, you have to give a discount for the current economic situation. But for that in -- the general trend should be the Indian market should be -- in my view, should be able to comfortably absorb a $4 per MMBtu gas price.
Unknown Analyst
analystOkay. So, for Dirok definitely, it will have a positive impact. But what about for B-80? Can it result with this free market pricing? Can it translate into lower-than-anticipated realization or will it...
Pandarinathan Elango
executiveNo. It will -- it already enjoys free market pricing. And because the B-80s will be sold in the Gujarat gas market, which is the most premium paying market in the country, where the majority of the imported LNG is being consumed in the Gujarat market and some of the long-term impact imported LNG prices are still high because they are committed on a fixed basis as such. So overall, we expect Gujarat prices to be on any day better than the rest of India prices.
Operator
operator[Operator Instructions] The next question is from the line of Yash Mandawewala from Mandawewala Enterprises.
Yash Mandawewala;Mandawewala Enterprises;Director
analystSo my question is actually on the oilfield services business that we're entering into. So what is the arrangement for the pricing at which we will lease the MOPU and the floating storage unit to the B-80 block?
Ramasamy Jeevanandam
executiveSo this being related for the transaction, we would like to go to the market and take the price. And we don't want to charge even a single penny more than on B-80 because we have got a partner therein. So it would be flat and...
Yash Mandawewala;Mandawewala Enterprises;Director
analystSo as of late, we have not fixed up the prices.
Ramasamy Jeevanandam
executiveYes. We -- it would be an arm's-length price. We know the trend in the market. So accordingly, we are looking at that. But the price would be for a fairly long period of about 7 to 8 years. So that would be at an arm's length.
Yash Mandawewala;Mandawewala Enterprises;Director
analystGot it. Got it. And sir, just a second question, leading up to that. So we were supposed to take some asset-backed loans in order to fund these 2 units. So the court order under Hardy Oil, I think it also mentioned that we are not allowed to encumber any assets or anything of that sort. So has that actually impacted our ability to raise debt now against these 2 assets that we need to buy?
Pandarinathan Elango
executiveIn the Gujarat court order, as we kind of explained, the amount in -- declined amount is -- by the other side, is only INR 27 crores. And as we speak today, the matter will come up for hearing. We have sought advanced hearing on this matter. Today, it will come up for hearing. We hope to provide the required guarantees to the court and then reget these orders vacated so that we can continue with our plans.
Yash Mandawewala;Mandawewala Enterprises;Director
analystGot it. But until we get this order vacated, till then we cannot actually avail more debt in order to fund MOPU and B-80?
Pandarinathan Elango
executiveWe have availed part of the debt but whatever need to be created, yes. We have to explain that. The second thing, this is on the company. The 2 subsidiary companies, there is no order, that is not get tainted. Loan is only on the subsidiary companies. HOEC as a company has not borrowed anything.
Operator
operatorThe next question is from the line of Sunil Jain from Nirmal Bang Securities.
Sunil Jain
analystMy question relates to why we are making appeal into Malaysian court, whereas the order is from Gujarat [indiscernible].
Pandarinathan Elango
executiveSunilji, the -- under the production sharing contract, any arbitration between the parties to the contract, the designated venue for arbitration is Kuala Lumpur. So this initial arbitration between -- sorry, Hardy as operator, and ONGC, HOEC, TPL as nonoperators, therefore, had to be held in Malaysia. So the arbitral tribunal sat in Malaysia in Kuala Lumpur and finally made the award. Therefore, any appeal to that award will have to necessarily take place in the High Court of Malaysia. There has been several precedents of this kind. Because in the initial days, the government always wanted the seat of arbitration to a neutral place in which neither the party -- neither of the parties to the production sharing contract originate from. That's how the Malaysia came into being. These contracts were signed in 1994. That's how the Malaysian jurisdiction assumes. The case in Gujarat High Court is really simply related to securing that award, not even enforcing, just securing that award, for which the party went and got some interim relief, which, as I said, we have filed for negating that order.
Sunil Jain
analystOkay. And the second thing about the -- your view on oil prices and gas prices. That is the key thing which will drive profitability of our company?
Pandarinathan Elango
executiveYes. As you've all seen that oil prices have been slowly moving up and are mostly in the range of $40 to $45 range, which works very well for us from B-80 point of view. We had stated earlier our breakeven price in B-80 would be somewhere between $25 to $30. So anything $40 and $45, we should be able to comfortably operate the fee on the oil price front. On the gas price, what we are really looking forward is the freedom for ONGC and Oil India to fix the gas price. That would indirectly help us to compete effectively in the Northeast region where our Dirok field is located and which produces a very rich quality gas, which is very much in demand by the petrochemical sector as such. And as I said in response to the earlier call, if you discount the current economic situation caused by the pandemic, on a normal sense, my take is that Indian market would -- comfortably would be able to absorb about $4 per MMBtu of gas price, gas price of $4 per MMBtu.
Sunil Jain
analystFurther to this question, looking at the current international prices of gas, do we expect a formula-driven price to improve from October 1?
Pandarinathan Elango
executiveNo. If you look at the current basic -- the government chooses to continue with the current pricing formula. The price is expected to decline from about $2.39 to about $2 or $1.95 to $2. That's what the -- our calculation indicates. But you would have seen that at these prices, which is a $2.38, the gas business of both Oil India as well as ONGC have reported cash losses in their results. Therefore -- and have made a strong recommendation to the government to allow free gas marketing and pricing. The rest of the private sector has also been making this demand for a long time. The government is fully aware of it. We expect some decision to be taken either way by the government by end of this month. Obviously, we don't have any details on that. But we expect either government will take a considered decision to continue with the pricing formula or open up the sector with certain conditions around it. We don't know, but we only hope it gets opened up.
Sunil Jain
analystSir, you said that the realization for the gas for us was around $2.64, whereas this price is around $2.39. So how we get a bit comparatively higher premium?
Pandarinathan Elango
executiveSee, our gas price in PY-1 is a fixed gas price at $3.65 per MMBtu. So what we have reported is the average realization per unit. So in PY-1, we get $3.65 per MMBtu. In Dirok...
Ramasamy Jeevanandam
executiveNet and gross we can...
Pandarinathan Elango
executiveThen net and gross value realization also.
Operator
operatorThe next question is from the line of Kishan Mundhra from Systematix Group.
Kishan Mundhra
analystJust 1 question from my end, sir. You've given the bifurcation of B-80 CapEx, but can you give us a company-wide guidance on the amount of CapEx that you intend to spend this year and next year? So I think you've mentioned that you've already spent INR 20 crores in the first quarter. So what is the guidance for the rest of the year and then for the next year?
Ramasamy Jeevanandam
executiveSo if you look at by next end of this year, that is about $12 million CapEx. Our CapEx would be $6 million. $6 million would be around INR 45 crores. That is our intended plan thereon and settling the liability there on to the cost, which has already been communicated.
Kishan Mundhra
analystAnd next year?
Ramasamy Jeevanandam
executiveNext year, see, we wanted to put B-80 into production, and that is our prime focus at the moment. Then by the time our people will be doing the reworking on the PY-1 and they revisit the entire thing, they go to the drawing board again and what used to be done on the block. And we will start sometime in the next -- in January or -- November or December only, we'll start that block operations.
Kishan Mundhra
analystOkay. And any update on Kherem, Kharsang? Any update there.
Ramasamy Jeevanandam
executiveKharsang is a block where it is under production at the moment. There is some more work is to be done. Because out of the 3 parties are existing, one is Oil India, another one is Geopetrol and another one is GeoEnpro. And one more fourth party is JEKPL which is on the -- went into the IBC process. Now still, to our knowledge, only RP is coming and attending that. Whether the other parties will be taking over fully and control and they come on it only, we can look at the block development thereon.
Operator
operatorThe next question is from the line of Sreemant Dudhoria from Unifi Capital.
Sreemant Dudhoria
analystA couple of questions. One, in the today's presentation, I think you've highlighted about the drilling campaign -- plans for drilling campaign in the Cambay region. So could you please elaborate what we are planning there further?
Pandarinathan Elango
executiveYes. What -- in Cambay, as you know, we have this through margin -- 3 marginal fields, which are producing very small volumes of oil. And a couple of the PSC was -- came up for extension. And those extensions have been done. And we also went with a -- as part of the PSC extension requirement, need to submit additional field development plan, which have been submitted. What we thought was to -- we had 2 plans in mind. One is to secure the R2 area in the block through a recent production sharing contract, which is in the final stages of government -- for quite some time, approval by the government for quite some time. Once we have that, because we club all the additional well program in Cambay and carry out one drilling campaign, it's a simple onshore-driven campaign. We -- in good earnest, we commenced the first step of applying for environmental clearances and preparing the activities for that. So we'll take a call on them once we have the R2 PSC signed in.
Sreemant Dudhoria
analystSo what kind of production levels are we planning with the plan that we are proposing in this region?
Pandarinathan Elango
executiveThese are very, very marginal field, Sreemant. We are -- we have overall visionary kind of a target to see we can achieve about 1,000 barrels of production in Cambay by adding some more portfolio of assets. I had mentioned earlier about our bidding for some of the blocks in GSPC, where we were the highest bidder, but the existing party had matched those rates and going ahead with the -- with acquiring those assets. But at some point in time, we do expect, based on our operating experience, if the parties will be willing to partner with us, we can develop some program as such. But these are plans that have already gone up in the pre-COVID day plans. Right now, as I emphasized, our focus is 100% on B-80. We wake up thinking about B-80. We go to bed thinking about B-80. So until we deliver that, we will not be doing anything else.
Sreemant Dudhoria
analystSure, sir. And finally, sir, you mentioned about 1.5 MMSCFD from PY-1 in the first quarter. Has the production ramped up to the 4 to 5 MMSCFD levels in PY-1?
Pandarinathan Elango
executiveNo, Sreemant, unfortunately not. It is continuing at the same level.
Operator
operatorThe next question is from the line of Manan Patel from Equirus PMS.
Manan Patel
analystThank you for a very nice explanation of all the liabilities. So my first question is, sir, on the B-80 part, where you said you have all the data for new wells and you have submitted to London agency. So I just wanted to understand if all the plans of yours have come to fruition, then how long will it take for those wells also to come online? And do we have to make any changes of the terms of government sharing? Or how does government play a role in the additional part of this B-80 block?
Pandarinathan Elango
executiveYes. Manan, in -- when we bid for this B-80 block, we committed a 1-well program only. We were supposed to drill only 1 well. And we initially after the analysis that we carried out, we went with a 2-well drilling program, which we have completed. Now earlier, ONGC had drilled about 5 wells in the block, and we had -- as part of this data package, we had access to those data. With the data gathered from these 2 wells, we went with the program together, some additional new data that our team has been working on to do a new interpretation. And as I said, that is under review at -- by GCA. Now the revenue sharing contract allows us full freedom to do as many number of wells as we can drill. And the revenue sharing only happened based on the gross revenue that field generates, which is if it is below $10,000, it is 12%, and if it is above $1 million per day, it is 56%. So irrespective of how many wells and what is the price, whatever the total revenue only accounts as such. In terms of our own planning, what we have done is, when we went and designed the Mobile Offshore Process Unit, we designed it for 10,000 barrels of oil processing capacity, the MOPU, so that we have adequate capacity in case of any future upside in the block. Second, when we bought this FSO Prem Pride, it has got a storage capacity of 900,000 barrels, which means it can effectively store any volume of production. And the deliveries happen on a tradable parcel size only. And the pipeline that we'll be having will be having adequate capacity to handle any upside volume that may come in future. So all that would be required is drilling additional wells. And of course, there will be connecting systems and pipelines will be required in future. But we will undertake all this program only after putting these first 2 wells on production, watching their performance and its behavior before we go ahead with additional well drilling program, which will not be at least 2 years before we think about the next drilling campaign. Our priority is to bring the first one to production, yes.
Manan Patel
analystYes. Understood, sir. And just 1 more thing on this. So when you said $10 million of the well capacity, so the new wells will have the additional capacity or $10 million is for all the wells combined?
Pandarinathan Elango
executiveNot $10 million. I said...
Manan Patel
analyst10 million barrels.
Pandarinathan Elango
executive10,000 barrels as such. The existing wells, as we have reported the testing results totally produced about 5,000 to 6,000 barrels of oil and the balance of 2,000 to 3,000 in form of gas -- oil equivalent gas, which is in simple term, 5,000 barrels of oil and 15 million cubic feet of gas. That is what we will be producing. What I meant for 10,000 was the MOPU, which is the surface facility, will have the capacity to handle production from any future wells.
Manan Patel
analystRight. Right. Sir, I understood that part. I just -- initially you mentioned that total cost is $55 million and 10 million barrels is a well capacity and you divided that to arrive at a cost of $5.5 per barrel.
Pandarinathan Elango
executiveWhat Jeeva said is, he was giving an example. The total CapEx is about $52 million. And the reserves, reserves is 10 million barrels. Then development cost per barrel is about $5. That's what he said. We will tell you the reserves number once the third-party audit is completed.
Manan Patel
analystUnderstood. And sir, my second question is on the vision that we initially laid out. So by FY '22 or '23, we wanted to be a gross production of 25,000 barrels. So where on that vision are we? And are you -- like do you think it will take a few more years to reach there? Or are you open to taking inorganic route for that?
Pandarinathan Elango
executiveI think the portfolio of assets we already have could support that level of gross-operated production, the portfolio that we already have, gross-operated production. In terms of execution, we want to set the priorities. As we said, the most important development is B-80. If B-80 doubles the production -- gross-operated production of the company, and therefore, depending on where the oil price and gas price will increase the revenue accordingly. That gives us the capacity to kind of execute multiple projects at the same time, which we would look at, depending on how the current COVID situation pans out and how things shape up as such. All I'm saying is we have the resource base to achieve that level of production. Execution really depends on, first, getting the B-80 right and then we will prioritize based on that.
Operator
operatorThe next question is from the line of Sadanand Shetty from Truequity Advisors.
Sadanand Shetty;Truequity Advisors;Sr. Fund Manager
analystSo Mr. Elango, what is the status of pipeline that you wanted to relate to Duliajan?
Pandarinathan Elango
executiveSadanand, for that pipeline is about 38-kilometer distance pipeline, for which we divided that into 2 phases. One is about 12-kilometer or so, goes through the forest area, for which we have applied for the forest clearance, and that is in various stages of clearance. And on the non -- we wanted to commence the work from -- in the non-forest area once we get a clear signal from the forest clearance side. So in parallel, we have ordered the pipes, and part of the pipes have already reached the site. We haven't yet commenced the work but the planning is on. We would be laying that line.
Sadanand Shetty;Truequity Advisors;Sr. Fund Manager
analystHave you signed up any EPC contractor? And also, whom have you ordered these pipes from?
Pandarinathan Elango
executiveWe have ordered the pipes from Asian -- Arabian oilfield services company. And then for the construction contract, we have awarded the contract. We have selected the vendor. We have not awarded the execution work. We will do that. What happens is in a COVID-type situation, managing the operation from a closed environment like a plant is one thing, but opening up the entire front, which involves laying pipeline, mobilizing a lot of people is a different element. So we need to take a look at the safety element before doing that. But we have our eyes sharply focused on critical path items, so that we move accordingly.
Sadanand Shetty;Truequity Advisors;Sr. Fund Manager
analystOkay. One last question. Can you share your view on state of the industry companies who have bagged DSF -- multiple rounds of DSF, oil and gas fields, especially considering COVID-19 and the liquidity situation? And do you smell any opportunity in some of those situation?
Pandarinathan Elango
executiveSadanand, we are kind of -- we believe that the strategy that we followed of focusing on discovered resources and following a fast-track development model with a limited CapEx and converting the part of the CapEx into OpEx model has played well and helping us during these times. So what we did in Dirok, where the investment on process securities were done by Expro and operation and maintenance being done by Expro efficiently. Same model has replicated in B-80. In B-80, MOPU also the Expro has installed the oil and gas processing facilities. They will be operating and maintaining it. We invested on the remaining region marine facilities. So we believe this model is a successful model where we are able to maintain a low cost. So in a situation like the current situation, we are able to comfortably operate our plant, also make some money. So we believe if we stay tuned with this model, we should be able to scale up significantly, but all after B-80. We just want to be very clear and very sharply focused on B-80. And once we do the B-80, it is not about just how much production B-80 brings to the company, how much of the experience it has added to the company in terms of executing a project. We did the 2-well program amidst the lockdown, of course, supported by all the contractors. We have done the subsea well completion using a jackup rig, which is, again, the first time in India by a private company. So gaining that offshore development experience and when we pull off the remaining part of the work, we would be really adding a lot of competence within the organization. That should help us be part of any future development that happens in the country.
Operator
operatorMr. Shetty...
Sadanand Shetty;Truequity Advisors;Sr. Fund Manager
analystRight. I have 1 last question. I'll just finish it. I know one of the question was what is the state of industry people who have bid for and won DSF multiple rounds? Do you think some of them may give up the fields and all?
Pandarinathan Elango
executiveI really don't know, Sadanand, what is the situation. We've also kind of locked ourselves at home and trying to do whatever we can. Really don't know what the situation because the interaction at Delhi has really come down. So I don't get access to as many news I used to get in the past.
Operator
operatorThe next question is a follow-up from the line of [ Tejas Shah from Unique Stockbroking ].
Unknown Analyst
analystIn this, Reliance, I think, is also coming up with that gas production from the gas space, I think, in the next 3, 4 months, if I'm not wrong. Can you elaborate on that? And how it will impact the Gujarat market?
Pandarinathan Elango
executiveI think I don't really have the latest update on the status of their project. But all I know is they went to -- went in the market to determine a gas price. Obviously, the volumes are larger volume, and the target is the Gujarat market. But please remember that India imports roughly 50% of its requirement through imported LNG. And some of them is on a long-term contract, which the -- mostly the government companies contractor supplying to government companies in fertilizer and power sector. The rest of the industry is open. Therefore, any new volume that comes to Indian market would effectively replace the imported LNG market, and some of them on a spot basis. Pricing would really be a issue in the sense that depending on how the international LNG prices move, things will be determined on that basis. We also need to keep in mind that the government has really opened up the CGD. The overall city gas distribution network is expanding rapidly. And that should also help in growing the gas demand. Overall, I expect a scenario where the gas would over a period of time substitute the liquid fuel in the country, and that should help the industry as a whole. But I don't know really the correct status or the current status of the Reliance project.
Unknown Analyst
analystOkay. Two things. One is, will we have the same problem like how we have lack of clients when we started the B-80 production? And secondly, what is the turnover that we are looking from April onwards once the oil prices are also likely to go up once everything happened and it slows down and overall business?
Pandarinathan Elango
executiveI didn't understand your first question.
Unknown Analyst
analystWill we have the same problem of clients not of -- picking up the uptake when we start the B-80? Like B-80, we have capacity of X amount, but then we don't have clients who are ready to pick up. Will we have the same problem over there?
Pandarinathan Elango
executiveNo. We don't expect that problem in B-80 because it will go to the -- first of all, our volume in B-80 is not very large. It is only 15 million cubic feet, which is about 0.45 million cubic meters per day, which is roughly half -- less than half of the Dirok output. So -- and because it is going to the Gujarat market once again, I don't see -- once we have identify a contractor and sign a contract, we don't expect any problem in the actual uptake as such. What is your second question?
Unknown Analyst
analystSecond question was from April onwards what is the turnover we are looking at? And once the oil price also goes up, it will add up to the bottom line by March I think. So what is the expectation from April onwards on the turnover side?
Pandarinathan Elango
executiveLast year, turnover is about INR 179 crores, INR 180 crores standalone. And at the current level, if we go through that, we will be reducing ourselves on to that about INR 100-plus crores and in the current year. If the B-80 comes on it, it will be about say -- you can say, $2,500 multiplied by the price there on. And the gas price at -- 15 million cubic feet of our share is 50% of that and multiplied by $4. So that all more driven by the price. The volume is almost prefixed and the price only the determinant. Second thing, we have got a volume of about 0.9 million barrel on which we can store it. So we had a flexibility to ourselves to go to the market at the right price.
Unknown Analyst
analystSo are we looking at INR 200 crores of turnover?
Pandarinathan Elango
executiveI think we can't -- till we want to put something in production, I don't want to speculate the numbers irresponsibly.
Operator
operatorThe next question is a follow-up from the line of Chintan Sheth from Sameeksha Capital.
Chintan Sheth
analystIn terms of Dirok, you mentioned once the B-80 gets over, the pipeline and other facility will be taken up. So any time line you want to provide right now to take this 35 to 55 that was our earlier target? Any timeline for that project?
Pandarinathan Elango
executiveI would be able to provide the time line maybe in the next quarter call because we just want to see how the...
Chintan Sheth
analystNew pricing.
Pandarinathan Elango
executiveNew pricing pans out. Because if you put the excess volume into the market, then you will be detrimental to the existing volume also. But we are able to meet the current demand. And we will give you guidelines maybe after a quarter.
Chintan Sheth
analystRight. And the oil field, which was -- the fire incident over there, how bad it is because that is one of the reasons you mentioned that, that is also helping us to ramp up our production right now? So do you think that, that field will come back on stream or...
Pandarinathan Elango
executiveNo, the incident itself is controlled now. The [ failure ] associated with the incident is controlled now. And -- but overall, we are seeing increase in demand trend in the sector as well. So therefore, we expect that the current trend to continue.
Operator
operatorThe next question is from the line of [ Rohith Potti ], an individual investor.
Unknown Attendee
attendeeSo my first question is on what you mentioned in the conference call about how from April 2019 onwards all gas production is on free market pricing. So does it mean that all the fields that we have with us which we have not begun work on like the R2 PSC, the Kherem, et cetera, once you submit the field production plan, even though they are in Northeast, et cetera, they are eligible for free pricing?
Pandarinathan Elango
executiveCorrect. Correct. The cutoff is based on the date on which the field development plan in a block is approved by the government. Therefore, any new developments even in Northeast, we will be eligible for free market pricing and free pricing.
Unknown Attendee
attendeeSo before, I think, I believe the rule was that if it is difficult to bring on to the stream oilfields or anything of that sort, which -- was allowed free market pricing. Going forward, even if it is easy to produce as compared to deepwater, it will be allowed free market pricing. Am I right?
Pandarinathan Elango
executiveCorrect. Correct. Correct. You're right.
Unknown Attendee
attendeeOkay. Okay. So that was helpful to hear. So second, broadly on this Hardy Oil issue. So first off, thank you for explaining everything so clearly and transparently. My follow-up is these things tend to take, I believe, a lot of bandwidth, even though it is not initiated by our -- at our end. Given we have, I believe, partnership with the said company in the Kharsang block also and we have -- the relationship has been a little rocky in the past on a couple of other bids as well, is there any way to -- what is the management thought on future in terms of the Kharsang field? Do you intend to exit or proactively do something about it? Or will you see it as and when it comes...
Pandarinathan Elango
executiveNo, no, we intend to. Wherever we have invested, wherever we have a stake, our intention is to continue to develop them. There are 2 things. Where we are operator we are able to drive it forward following a particular strategy that you've seen yourself and the industry recognizes that. Where we are nonoperators, obviously, we have a limitation because, ultimately, the operator of the block only is the driving fee to drive things. But as a nonoperator, I would ultimately decide based on -- my priorities of investment will be purely based on what kind of return investment in any particular block could see, right. So that's our view. We have no plans to exit any of the blocks.
Unknown Attendee
attendeeUnderstood. That was helpful. And my last question, is it a little premature to ask -- we have a lot of -- I mean, as you mentioned to a previous participant that the current portfolio of assets we have can help us reach the regions with -- that we had to reach, let's say, 25,000 BOPD of oil. So the question I had is, is it possible to give us a broad range of what the breakeven price for the assets -- portfolio of assets that we have because I believe for something like PY-3, that would be higher, while the others might be lower? So is that something you could help us on?
Pandarinathan Elango
executiveIt is a little premature. What I kind of really said was to reach that level of gross-operated oil equivalent production, BOEPD, which will be a mix of both gas and oil. Just based on the resource base that we are operating, we will be able to reach that kind of a number over a period of time. But our success really lies in focusing on one thing at a time so that you do a good job of TAT as such. So we will give you individual block update as and when we have a clearly defined project. And obviously, as a new -- it will all be undertaken only if it makes economic sense. Now because our cost base is low, most of the opportunity that we have would make economical sense. It's a question of prioritizing and execution.
Operator
operatorThe next question is from the line of [ Sharat Sharma ], an individual investor.
Unknown Attendee
attendeeSir, can you clarify about the current stay order, that freezing your assets, are there any impact? Is there any impact on operations, one? If the prospective stay order doesn't get vacated in the upcoming hearing of September, what is the plan? And are you paying on the protest? Or are you just challenging the full order, please?
Pandarinathan Elango
executiveSo one is the order basically put a stay on any disposal or creating mortgage of any of the company assets. It has no impact on our operations. The operations are continuing.
Unknown Attendee
attendeeSo cash is -- like cash is usable, right?
Pandarinathan Elango
executiveAbsolutely. Absolutely. Second is we have already filed a petition in the Gujarat court. Original date of hearing was 11th September. We have sought the permission of the court to advance the hearing. And once we know the outcome, we would move accordingly.
Unknown Attendee
attendeeGot it, sir. Typical, same, the Indian judiciary, suppose it gets extended or something, would you be paying on protest? Or I mean just -- would it just continue types, another date or sort?
Pandarinathan Elango
executiveNo, I think it's immature to speculate on the court outcome. We've just -- we moved as quickly as possible.
Operator
operatorAs there are no further questions, I now hand the conference over to Mr. Elango from Hindustan Oil Exploration Company Limited for closing comments. Over to you, sir.
Pandarinathan Elango
executiveSee, thank you for participating in the Q1 FY '21 results. Last couple of weeks have only helped us to further strengthen our commitment to follow the highest principles of transparency and continue to improve the quality of our communications with all the stakeholders. I assure you that the company is fully focused on project execution of B-80. We are well positioned to withstand this and thrive in this lower for longer oil and gas price scenario. For any further questions, request you all to please reach out to us or our Investor Relations advisers. Thank you all. Have a good day.
Operator
operatorThank you. Ladies and gentlemen, on behalf of Hindustan Oil Exploration Company Limited, that concludes this conference. Thank you all for joining us, and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Hindustan Oil Exploration Company Limited transcript — plus 252,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Hindustan Oil Exploration Company Limited earnings transcripts and 252,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.