operatorHello, everyone, and thanks for joining us for the Hochschild Mining webcast and conference call on our half year results. Right now, I'll hand things over to our CEO, Ignacio Bustamante. Ignacio, the floor is yours.
Ignacio Bustamante
executiveThanks, Katy. Good afternoon, everybody. I'm Ignacio Bustamante, and joining me are Ramón Barúa, our CFO, plus Charlie Gordon, who leads Investor Relations. Thanks so much for being with us for the presentation of our 2021 interim results. Let's move directly to Page 3 of the presentation, where the main highlights for 2021 are as follows. On the production side, we remain on track to hit our target of 31 million to 32 million silver equivalent ounces. During the first half of the year, we achieved all in sustaining cash costs of $13.2 per ounce of silver, which sits below our 2021 guidance range of $14.1 to $14.5 per silver equivalent ounce. On the financial side, Ramon will go into greater detail later, but the headline numbers are extremely positive and very strong. As you can see, revenues rose 70% to $395 million, EBITDA climbed 146% to $199 million, and the cash balance increased 11% to $257 million. Lastly, on exploration and business development, the news is also very encouraging: Inmaculada keeps performing extremely well. We are reporting a year-to-date addition of roughly 410,000 ounces of gold at an equivalent grade of 10.6 grams per tonne, which is a fantastic discovery, and there is still plenty of upside in that area.
Ignacio Bustamante
executiveWe've also been getting additional drilling results, high grade at the Snip project. As you may remember, our option runs out in October. So we'll discuss Snip a bit more later in the presentation. And lastly, we've announced our rare earth capital market presentation for September 8, and we're looking forward to that as well. So as you can see, a very strong financial rebound from a 2020 that was impacted by COVID. If we go to the next slide, Page #4. You've probably seen that we recently published our 2020 sustainability report. If you haven't, I really encourage you to read it. It's available on our website. Moving to the right-hand side of that chart, you can see safety performance. Safety is a top priority for the company. You can see there in the chart, the blue dots, how we have performed since the IPO, where we're at about 7.6 and now we've gotten into the low 1s over the past 4 years. And since 2017, we began monitoring another one, which is in green, which is the high potential event that is also showing a very positive trend. Just for information, the safety KPS excludes the June 2021 bus accident in line with the guidance that is present or established from the International Council on Mining and Metals and also based on our internally approved Hochschild protocols.
Ignacio Bustamante
executiveWe've also introduced a new tool called SEGU score — quite close to the ECO score — that essentially factors in many different elements beyond frequency and severity, along with the usual safety and recruit order measurements like inspection behavior audits, on a scale from 1 to 10. We've begun tracking it, and we're very pleased about the tremendous support this tool will give us, our management, and the operations. And finally, on safety, one of the key things we deal with in safety tends to be risk perception and safety culture. So we're working on developing a tool that will let us significantly raise or enhance how our people perceive risk and how they behave. It's a long-term project, but we expect to implement it during the second half of the year. Moving to the next page, Page 5, there are also some environment highlights. We keep monitoring our ECO score and making good progress. For the first half of the year, we stand at 5.6 out of 6. Inmaculada and San Jose achieved a perfect score of 6 for the first half of the year.
Ignacio Bustamante
executiveWe keep demonstrating gains when it comes to using less water and producing less solid waste. An external certification is under way for our ECO score as well as for our carbon footprint. Consultants have been appointed by us to handle our cargo disclosure project and the transfer regarding climate-related financial disclosures, and our net zero carbon strategy is also being developed. Turning to people and culture, as you can imagine, COVID remains the key priority, and our COVID protocols continue to be monitored strictly. In addition, we keep actively promoting diversity and inclusion initiatives through several programs across the company, and some results of that are that we have run 4 out of 16 extractive companies for gender equality in Latin America. We have also improved 43 places from 2019 in the <<inaudible>> ranking, and we currently are placed second among all mining companies in Peru. And finally, on communities, we continue monitoring closely the situation because with the new government in place, we believe that there are certain increased social tension and expectations in the country and also in our Southern Peru. So we continue to monitoring that very closely. And in parallel, we continue strengthening our social engagement strategy by working on initiatives to promote local employment, procurement of local goods and services, investment in social community programs, support of local governments, stakeholder engagement in general.
Ignacio Bustamante
executiveAnd lastly, we’re also expanding—on a permanent basis—the reach of our award-winning Internet connectivity program to 13 communities, ensuring the service keeps getting better and better over time. So that’s the interaction. At this point, let me pass the presentation to Ramón Barúa so he can walk you through some detail on our financial—our interim financial results.
Ramón Barúa
executiveThanks, Ignacio. Scott, I just want to confirm we're looking at Page 7 of the presentation, please, with the P&L. So, I mean, we're really pleased with this first half of the year. From an operational standpoint, the company is clearly nearly back to normal, even though, of course, we're still applying a number of COVID-related protocols. But basically, all the mines are running at full speed. And comparing to the first half of 2020 is quite unfair, because that first half of last year was, of course, the period hit hardest by COVID. So as you can see, revenue for the period came in at almost $395 million. We had more volume than last year, and silver prices were also much higher. Gold prices were pretty much unchanged, still slightly higher, but silver rose from $16.6, which was our average price in the first half of 2020. And in 2021, that figure was $27.2 per ounce of silver. Our costs were well controlled, which led to a gross margin increase from 36% to 43%. Administrative expenses are also trending back toward normal, though we see a slight increase versus last year, but most of that relates to the worker profit-sharing calculation, which is directly in line with the higher prices we're seeing in the market.
Ramón Barúa
executiveWe've seen exploration execution rise across every operation, most notably at Inmaculada. We'll go into that a bit, and it ties as well to the discovery Ignacio brought up. Greenfield activity has also picked up during the period. Other expenses came in higher. Notably there, we ran a voluntary redundancy program in Argentina, aimed at swapping nonlocal workers for workers from the province of Santa Cruz, where we operate. Finance costs were higher, really. I mean, the interest rate we're paying hasn't gone up. As you know, we have a fantastic rate of LIBOR plus 1.15% on our main debt facility, but there was a loss booked as finance costs tied to acquiring dollars in Argentina. As you know, that's not too easy and not too available these days. These results brought us to a profit before taxes of $97.8 million, and we've calculated an effective tax rate of 61.1%. Of course, the statutory tax rates in Peru and Argentina are much lower than that. So the difference is explained mainly by 3 impacts. The first one is the devaluation in Peru and Argentina. Because, you know, in Peru, due to some political noise, the exchange rate has moved up from around PEN 3.6 per $1 to PEN 3.9 by the end of the period.
Ramón Barúa
executiveAnd in Argentina, the rate moved from ARS 0.83 up to ARS 0.95, again for that same period. That has an effect on our tax basis in both Peru and Argentina, which are denominated in local currency. So those evaluations do have an impact on the deferred income tax asset we hold. And importantly as well, in Argentina the government lifted the corporate tax rate from 30% to 35%. The impact of that increase also has to be brought forward. So it hits not just the current tax but the deferred tax too. We also paid higher royalties and special mining tax in Peru. As you know, when operating margins rise, we have a higher scale and a higher rate, and that likewise feeds into the tax calculation. So absent those effects, really, the tax calculation would have landed at 31.7%, which is much closer to the statutory rate we have in these countries. After all of those effects, the attributable net profit to Hochschild shareholders came to $42.1 million, representing $0.08 per share. All of this on a pre-exceptional basis. We did book around $14 million of COVID expenses, which for this year continue to be booked as exceptional items. If we move to the next page, what we have is a cash flow cascade, but I think I like this slide very much because it represents very well, you know, the activity that has been transpiring through the year or through the half year.
Ramón Barúa
executiveAs you can see on the left-hand side, we began this period with $232 million of cash. And our 3 operations — Inmaculada, Pallancata and San Jose — every one of them produced strongly positive cash flow. The cash flow figures shown here are what you get after accounting for all CapEx, infill drilling included. On top of that, brownfield and admin, as I said earlier, returned to normalized levels. So following operations and admin, we produced $145 million, which lifted cash to $377 million, and that cash went toward repaying debt, paying interest, paying taxes, naturally, paying dividends to Hochschild shareholders, and paying dividends to our partner in Argentina, McEwen Mining. We put $7 million into our BioLantanidos project. After that come 2 categories — unabsorbed fixed cost and COVID response costs — and both are temporary, tied to the virus. So with vaccinations continuing in Peru and a return to normal, we expect these 2 items to nearly fully vanish. There were mine closure costs and current maintenance as well. And we saw working — negative working capital during the period, mainly because we weren't able to ship all of our material.
Ramón Barúa
executiveLately we've been running into some trouble getting containers for international shipping and trade, and that created a bit of strain. Our hope is that this will prove short-lived too, and it ties back to COVID rules at various ports, both in Peru and around the globe. That left us with a cash position of $257 million at the close of the period. Let's move to the next slide, please. As Ignacio noted during the introduction, we felt very good about delivering an all-in sustaining cost of $13.2 per silver equivalent ounce for the half. The three primary cost drivers, as you're aware, are CapEx, production cost and grades. CapEx came in temporarily lower because of reduced execution on mine developments at San Jose and certain infill drilling at Inmaculada that is slated for the second half of the year. Production costs were held in check nicely as well. We saw more mechanized mining at Inmaculada mainly, again, because of temporary factors. That's the reason we aren't really altering this year's guidance. We think there is -- we continue to think that this is the strongest assumption we hold for costs in 2021. We also ran some low-cost stockpiles through at San Jose.
Ramón Barúa
executiveAnd naturally, the currency devaluation that hit the tax also hit costs, and I'd argue it did so in a way that matters much more. So we're seeing that advantage in both Peru and Argentina. As for grades, Inmaculada came in above what we expected, though lower grades at both Pallancata and San Jose cancelled that out. On this all-in sustaining cost figure, I really want to stress that it leaves out the external items tied to COVID as well as the unabsorbed fixed cost of $6.2 million — those sit in our cost of sales, not in our cost of production. Moving to the next slide, please — at the top of the chart on the left, you'll see our CapEx guidance remains $120 million to $130 million. During this half we spent $57 million on CapEx. So, as I said, we're not quite at the halfway mark, but the remainder should come in during the second half of the year. On the right-hand chart, you'll also notice that our exploration expenditure has risen considerably versus last year, again, of course, because COVID restrictions have been lifted. And notably at Inmaculada, so — and in Greece, we're very excited about the prospectivity of Inmaculada.
Ramón Barúa
executiveWe have plenty of targets, and we're pursuing them without hesitation. Greenfield activity also improved. The majority of our overseas projects are beginning to gain momentum. That shows up in our exploration spending as well. By the end of the half, we had spent $21.4 million across both brownfield and greenfield. Moving to the next slide, please, this gives a summary of our balance sheet. What I mean is, our financial position remains extremely strong. Cash keeps building on the balance sheet. At present the net cash position stands at $51 million, compared with $22 million at the close of 2020. As you can see, our debt profile remains very comfortable. We anticipate beginning to repay debt next year, and we also have equal payments over the next 3 years. Turning now to dividends, you will have noted that we have been unable to declare a dividend, as we speak, alongside this announcement, since shortly before today's announcement we learned of a technical noncompliance with U.K. law concerning those dividends. Unfortunately, a number of historic dividends were paid at a time when Hochschild Mining plc, the specific parent entity, had sufficient distributable reserves.
Ramón Barúa
executiveWe now have a plan, first, to pay a dividend as soon as we can by way of a capital reorganization at the subsidiary level. So we expect to announce that interim dividend by month-end. That ought to be fairly easy and quick to arrange. And second, in due course we'll set up a shareholder meeting to put the historic dividend position right and to free shareholders and directors from any liabilities tied to it. With that, Ignacio, I hand the presentation back to you. And afterward, I'm available for any questions. Thank you.
Ignacio Bustamante
executiveThanks, Ramón. Let's turn to Page 13 of the presentation, please. That brings us to our operational update. As Ramón said, every mine is running normally at present. We've posted quite strong H1 recoveries following the stoppages tied to COVID in 2020. We keep enforcing very rigorous protocols across all of our operations. And the operation probably hurting the most at the moment from COVID-related issues is in Argentina, where strict limits on people's movement are still in force. Still, as Ramón also noted, we keep expecting to hit our production guidance for the full year. We're on track with our 2021 guidance for production, as I said, and also for all-in sustaining cash flows, CapEx, and brownfield and greenfield expenses. So we do expect that strong free cash flow generation will carry on through the second half of 2021. Turning to the next slide, Page 14. Our growth strategy is still intact and rests on 4 pillars: brownfield, greenfield, early-stage projects and strategic alliance. On the first, brownfield, the focus is on continuing to extend life of mine, which we're in the process of achieving, on improving resource quality as well, and on trying to use as much of the spare capacity we have available as possible.
Ignacio Bustamante
executiveRegarding greenfield efforts, we keep refining our project portfolio across the Americas, maintaining our practice of taking on high-quality properties and moving 4 to 6 projects forward annually — meaning 4 to 6 distinct projects across 2 to 3 different countries. With respect to early stage projects, we keep optimizing our real estate projects, specifically Azuca, Cresco and Volcan, addressing them from both the geological and technical angles. We also keep advancing our BioLantanidos deposit, and we'll say a bit more on that shortly. Lastly, when it comes to strategic alliances or acquisitions, we keep evaluating those opportunities provided they meet our criteria: early stage, meaningful geological potential, strongly value accretive, and something we can control as an asset. Turning to the following slide, Page 15. As I noted during my introduction, Inmaculada has delivered a fantastic first half of the year. We achieved a very significant discovery at Angela North. That discovery carries strong potential for enhancing the average quality of our resource base. What we've identified to date is slightly more than 400,000 ounces of gold equivalent material, averaging 10.6 grams per tonne. Those ounces come mainly from Angela North, with a smaller contribution from Angela Connection and Juliana South.
Ignacio Bustamante
executiveWe keep drilling in that area. We keep drilling Angela North. We keep drilling Juliana, both from an inferred resource and infill drilling too, to try to convert those resources into reserves as much as possible before year-end. So drilling carries on at Juliana, Angela East and Huarmapata, and we also have other very attractive areas where we are simply awaiting the final permits expected in Q3 of this year, namely Minasucho and Lineamiento 3. And there is also the area you can see on the map at the bottom called Inmaculada East, where we are just waiting on the permit, which we expect by the end of the year or early 2022, with the aim of beginning to drill them in Q1 of 2022. So there is still plenty of potential and fantastic results at Inmaculada. Turning to the next slide, Slide 16, Pallancata. We continue seeking to extend the life of mine at Pallancata. You may remember that we managed to secure production for Pallancata for 2021 and 2022. We are continuing to examine our current resource base to see whether we can extend the life of mine even further with the resources we have.
Ignacio Bustamante
executiveSo ideally, some extra production in 2023 and hopefully for part of 2024. So we keep examining those alternatives. And in the meantime, we're drilling a lot of different areas like Marco, Pallancata West, Yurika, Pepita and so on. We just got the permits for Paola and Luisa, so that project will get underway shortly. And we're also continuing to work on our medium- to long-term projects, which are Corina, Cochaloma and Palca. So there are still plenty of opportunities at Pallancata that we plan to evaluate and deliver over the coming months. For San Jose, on Page 17, we also had a very good start to the year, with the first half letting us find 7 million ounces of resources — almost a kilo of silver equivalent material, found particularly at Calandria, Esmeralda, Escondida and Isabel, all structures very close to the current operating area, which is very positive. We also have many targets for the second half of the year, including San Jose Sur, San Jose West and Saavedra. The drilling campaign is aimed at proving the extension of existing veins such as Pilar, Frea, Micaela and also hopefully trying to find additional structures.
Ignacio Bustamante
executiveAs you might remember, we carried out that Titan geophysical program, and Titan has already delivered 2 successful targets for us — the Betania and Emilio veins. We also have high expectations here, since Betania is a vein that could run along a 2-kilometer trend to the Northeast. So there are still plenty of areas and targets to drill during the second half of 2021, adding to the fantastic result we achieved in the first half of the year. Turning to Page 18, opportunities to deliver upside. First, our focus will remain on the Americas. We have strong portfolio optionality throughout all the Americas. We've just named a new Vice President of North America, Tom Elliott, who will be based in Toronto and will support us on all our North American related efforts. We're also ramping up activity in North America through our options at Snip, for example, and also in our greenfield work — through our greenfield drilling projects. As for Snip, we're currently conducting the due diligence, which I'll explain later, with the aim of reaching a decision before the option expires in October. We're also advancing our near-term projects with significant potential at our former mines and our near-term projects in the Southern Peru Cluster.
Ignacio Bustamante
executiveRight now, drilling is underway at Arcata, Azuca and Crespo. Optimization efforts at our Volcan project in Chile are continuing, and naturally, we're moving ahead at a very strong pace on the BioLantanidos rare earths project, also in Chile. And lastly, on the greenfield program: we have numerous greenfield projects across the U.S., Mexico and Peru. At present we're concentrating on North American opportunities, partly so we can diversify our geographical risk somewhat. On top of that, talks are ongoing with partners regarding 7 more prospects in the U.S. that we hope to drill in the months and years ahead. Turning to the next page, Page 19, we cover Snip. Snip, as you might remember, is a past-producing company located in the Golden Triangle in Northwest British Columbia, Canada. An option lets us acquire 60% from Skeena Resources. That option runs out in October 2021. Historically, from 1991 through 1999, Snip turned out more than 1 million ounces at an average grade of 27.5 grams — a fantastic grade. The company has been doing work on Skeena, carrying out geological work. And in July 2020 they announced and delivered a resource of roughly 650,000 ounces at an average rate ranging from 13 to 14 grams.
Ignacio Bustamante
executiveAnd following that, the business has kept up a highly significant amount of drilling activity. So we are currently working on our own geological model and carrying out our own due diligence, with the aim of being in a position to reach a decision prior to October of this year. Turning to the next page, Page 20. We have the BioLantanidos rare earths project. As you might remember, this is among the handful of heavy rare earths projects located in the Western World, in Chile. It is an iron adsorption clay deposit, similar to those that for the most part are found only in China. And those remain low-cost sources of rare earths worldwide. This project features a highly distinctive concentration of the rare earths that are in high demand, including neodymium, praseodynium, dysprosium and terbium. We made very solid progress during 2021. We placed essentially all of our attention on delivering the initial production model, working on the engineering for the first 500 hectares, developing the mining plan, and working on enhancing the metallurgical recoveries as much as we possibly can. We expect the results from the PEA shortly, and environmental permitting is likewise in its final stages. So we look forward to the Capital Markets presentation on September 8, and we anticipate providing you with considerably more detail about this highly attractive project.
Ignacio Bustamante
executiveTurning to Page 21, the following slide. In our view, Hochschild still offers shareholders a highly attractive value proposition. Relative to our peers, you'll notice we rank among the lowest on valuation. Looking at the price earnings and EBIT to EBITDA ratios, we sit at the bottom of the list. Conversely, our free cash flow yield and dividend yield place us among the industry's best. So, on that basis, and taking into account all the various factors we've discussed, we think we offer shareholders a very compelling value proposition at present. Then, last page, Page 22, by way of conclusion, we're showing a very robust operational recovery from 2020 after the COVID-19 disruption we went through last year. We're on track to hit the 2021 production guidance as well as our cost targets. For the year, we expect very strong free cash flow generation. Our brownfield program has us very excited, and we've already added a material amount of resources during the first half of the year, and we expect to keep doing so through the second half of 2021 as well.
Ignacio Bustamante
executiveThere's appealing optionality for us when it comes to greenfield and early-stage projects, and the same goes for how we approach M&A. And, as I said, we're eager for what should be a very exciting presentation on Biolantanidos rare earths coming up on September 8, 2021. With that, we'll wrap up the presentation, and I'd like to open things up to whatever questions you might have.
Operator
operator<<operator_script>> Daniel Major from UBS has our first question.
Daniel Major
analystI have a couple of questions. First, regarding production, there are 2 parts to this. You talked about the drilling work at Pallancata, but for 2022 production, could you give us some indication or guidance on the mill's throughput rate and the production outlook? Do you think you can keep production at a comparable level — around 5.5 million ounces of silver equivalent — next year? Or will output begin to fall because reserves are being depleted? That is my first question.
Ignacio Bustamante
executiveSure, it makes sense that when a mine reaches its later years, the geological information becomes somewhat less precise. What we’re observing at the moment is that 2022 output should land somewhere in the range of 4 million to 5 million ounces. We’ll do our best to push it as near to 5 as we can. But you might remember that for 2021 and 2022 we’ve hedged 4 million ounces per year, aiming to lock in that production plan. So I’d say 4 million ounces is the absolute floor, though ideally we’ll exceed it. Exactly how much above that depends heavily on what we ultimately discover from the geological models we’ve got and the work we’ll be carrying out there. What I can tell you, Daniel, is that on this basis, every ounce we produce at Pallancata will also be profitable — or very profitable — ounces.
Daniel Major
analystAnd then, Inmaculada, earlier you mentioned raising throughput to, I believe, 4,200 tonnes per day at some point. What is the plan for debottlenecking the plant, and does the scope include increasing throughput and production on a 2022, 2023 basis, along with what you are seeing in your exploration efforts?
Ignacio Bustamante
executiveYes. What I can say regarding Inmaculada is that the discovery we've made at Angela North East has been fantastic. As you can see, the grade there is significantly higher than what we're currently mining at Angela. So that's going to be a fantastic addition to the high-quantity but lower-grade resources we found in 2018 and 2019 in the Millet and Divina areas. So our goal is to try to achieve balanced production across Divina, Millet and Angela North East, and hopefully whatever we can keep finding in that hybrid area, to try to take a balanced production approach similar to what we have right now. So at this point in time, we have no plans for a capacity increase, because that would allow us to maintain production. That said, we're also evaluating this ore sorting project that could allow us to significantly upgrade the grades at Divina, Millet and those areas by putting all the material with lower grade through this ore sorting technology, in which we can separate the lower-quality material and put only the higher grades into the plant. So if we're successful in that effort, we wouldn't need to increase the plant's capacity to get the uplift in production in that area of lower grades at Divina, Millet.
Ignacio Bustamante
executiveThat remains a moving target, but what I can say is that what we've found at Angela North East has been fantastic, and it's going to let us move closer to historical production rates at Inmaculada. And of course, there's still significant upside to come from additional drilling work.
Daniel Major
analystAll right. To put that in a nutshell, though, the bigger benefit likely comes from the grade rather than from raising throughput — is that right?
Ignacio Bustamante
executiveRight now, I'd say it's more about the discoveries in the new resources and the ore-sorting technology than about raising the plant's capacity, yes.
Daniel Major
analystAll right, great. The following question concerns Peru's political environment. Obviously, discussion surrounding taxation in general keeps going in Peru and Chile. Have you held any conversations, or meaningful ones, with the incoming administration? How would you remark on and connect to the dangers tied to, especially, possible tax modifications affecting the sector?
Ignacio Bustamante
executiveAbsolutely. Daniel, it’s still too soon to tell. We ourselves haven’t sat down with the authorities. We’re aware that Peru’s National Mining Association has already held meetings with them. Their sense of it has been favorable, and Mr. <<inaudible>> is someone keen on encouraging mining activity. He has also said verbally that he wants to serve as a channel for cutting down or removing bureaucratic obstacles that might be in place, and he has been quoted publicly about fostering certain investments for the country and being enthusiastic about them. On top of that, Pedro Frank has been appointed Minister of Economy, and Julio Velarde will stay on as Chairman of the Central Bank. I’d say those are relatively encouraging signals. As for possible extra taxes on the mining sector, they’ve been outspoken on that too. So we think a conversation and a negotiation are coming. What we’re doing is coordinating every effort across the sector via the Mining Association, so that whatever the negotiation produces in the end is something workable and a solid long-term answer for the companies and the country alike.
Daniel Major
analystUnderstood. Still, is there any signal at all regarding when negotiations or discussions might take place? I realize it's early days, but could you offer any further detail on that?
Ignacio Bustamante
executiveThere's no timing guidance yet. That said, Daniel, judging by the priorities the government has set out, my expectation is that this probably lands in Q4 of this year. The new cabinet hasn't even been formed yet. They'll be presenting themselves to Congress on August 26. So I'd say we'll likely begin seeing more details once the cabinet gets Congress's approval. So in all likelihood, it will be for Q4 of this year.
Operator
operatorThe next person to ask a question is <<inaudible>> from Bank of America.
Analyst
analystI've got a few questions. The first one concerns Pallancata's costs. In H1, AISC went a bit above the guided range, landing at roughly $17.3 per cell equivalent ounce versus $16.8 to $17.2. Also, the cost discussion on Page 7 of the release indicates a substantial rise is anticipated in H2. So how do you still intend to hit that guidance range?
Ignacio Bustamante
executiveAbsolutely. What I can share regarding Pallancata is that our initial guidance for the year was built mainly around 2021 production, which was the situation we had at the start of the year. After that point, we approved a fresh budget for Pallancata tied to those hedges we put in place at $27 for 2021 and '22, which would let us achieve profitable output in 2022 as well. The extra ounces we're going to approach for 2022 arrived together with added CapEx at Pallancata for mine development that we have to carry out this year. That's the reason we noted Pallancata costs being higher during the first half of the year. And we will also keep seeing that development spending through the second half of 2021. Even so, we believe that although those CapEx at Pallancata will rise in the second half of the year too, we do believe that thanks to all the other benefits we are seeing at Inmaculada, at San Jose and additionally with a favorable exchange rate effect that we are seeing in Peru, we will be in a position where the overall guidance we have provided to the company will be achieved.
Analyst
analystAll right. Then regarding the remaining operations — once more, the cost commentary you'll be given does point to somewhat elevated costs. And is that again tied to CapEx? Or are you noticing any inflation-driven pressures?
Ignacio Bustamante
executiveNo, I'd say we aren't yet seeing any significant cost components tied to inflation. In fact, what we're seeing is a favorable effect from the exchange rate. That's what lets us absorb this extra mining development cost while still keeping the guidance intact. So no inflation pressures at this point.
Analyst
analystAll right. And regarding Pallancata, circling back to that point, is there any guidance or estimate you can give for what exploration CapEx will look like across the next 2 years?
Ignacio Bustamante
executiveNot at this point—we're still working through it. Finishing in 2022 isn't the objective; we also want to generate extra profitable resources from the resource base we currently have for 2023 and, we hope, for part of 2024. Those areas have already been pinpointed, and right now we're putting together a mine plan that could let us produce profitability from them. Should that prove to be the case, we might have to approve some additional CapEx for this year as well. So I'd say that will probably be the subject of an update either at the end of the year or, if we have it sooner, we can likely do it when we announce our Q3 results.
Analyst
analystAll right, and for my final question, could you provide a bit more detail on the political and COVID circumstances in Argentina? Also, what steps are you taking to keep this under control, and what would your worst-case scenario look like?
Ignacio Bustamante
executiveRegarding Argentina, we’re hopeful we’ve already hit the worst-case scenario, since many restrictions are still in force there—lots of protocols, testing requirements, and that kind of thing remain in place—and at this moment, from our perspective, those measures are likely excessive given what we’re actually observing in the country. It’s a country whose situation has also been improving. The pace of vaccination has picked up substantially. At present, the share of vaccinated people we see is far higher than in Peru, for example. Even so, the protocols are considerably stricter. As a result, we’re prevented from having the critical personnel for the operation who can’t get to the mine because of travel restrictions. So we do expect that, hopefully, in the coming weeks, that situation will be fixed, the government will revise the protocols in light of the new, better COVID situation in the country, and that could let us have the people we need and also bring some relief on the costs tied to keeping these COVID protocols in place. So I’d say the country is heading in the right direction.
Ignacio Bustamante
executiveOur hope is that the new rules and protocols will also adjust rapidly to this better set of circumstances.
Operator
operatorTyler Broda from RBC has our next question.
Tyler Broda
analystI have just 2 questions. Apologies if this was covered before, but regarding Inmaculada, you have the new ounces coming through. The grades are obviously at 10.6, which I believe is above where the current reserve sits and what you're currently mining. When should we expect that material to come through? And do you have any targets for how much additional material can be delivered over the next 12 months? My second question concerns the Snip option. Is there a specific day on which you get to choose, or can you choose at any point leading up to October? And if that's the case, then why are you -- what are you waiting for in order to make the decision?
Ignacio Bustamante
executiveThanks, Tyler. I'll begin with Snip. Snip is the option we hold. It runs until October, though we're able to exercise it at any time. What we've done is kick off a due diligence process to confirm that everything meets what we understand and expect. That due diligence should wrap up by September of this year — the end of September. So once it's finished, we'll be in a position to decide. So we should be finding time. And the moment we're ready, we can make a solid decision. On Inmaculada, the additions we've reported for the first half of the year are being infilled so that we can convert them into reserves by year-end, or as much as possible by year-end. Beyond that, we're continuing to drill further to identify additional inferred resources. So we do anticipate those converting to reserve at the end of the year. That means we should see a material improvement in our reserve, grades and reserve ounces by the end of the year as well.
Ignacio Bustamante
executiveBeyond that, we anticipate that we'll keep discovering further inferred resources. As for how soon these can be mined, I'd note that because these are fairly new zones situated near existing operations — fairly new zones — development work is required on them. So in all likelihood, throughout 2022, the effect from these new zones will be quite small. The most substantial effect will begin to show in 2023 and 2024.
Tyler Broda
analystAnd regarding Snip, is October 31 the exact date, or is it simply one more day within October?
Ignacio Bustamante
executiveRight, I get it — that's October 31.
Operator
operator<<operator_script>> Ian Rossouw from Barclays has our next question.
Ian Rossouw
analystSorry if the discussion already covered this, but regarding the CapEx guidance — I don't see the $7 million for the ore sorting plant included there. Will that spending still go ahead this year?
Ignacio Bustamante
executiveYes. Ore sorting remains in the pipeline. Right now we're finishing up certain items tied to the permit for the ore sorting plant, and we're still making some adjustments on the engineering side. But our aim is to move ahead with it as fast as we possibly can. A final review of the project is scheduled for the end of August of this year. And as soon as that's ready and the permitting has been adjusted, we'll proceed at full speed on the project. So that's where things stand on that. We remain very excited about the prospectivity of that plant.
Ian Rossouw
analyst<<inaudible>>.
Ignacio Bustamante
executiveI'm sorry, Ian, but the line is cutting out on you—I'm having trouble hearing you clearly.
Ian Rossouw
analystDepending on when the spending happens, there’s a possibility that a portion of that $7 million will roll into 2022.
Ignacio Bustamante
executiveYou've got it right. Yes.
Operator
operatorAt this point, there are no more questions coming in. I'll hand the call back to Mr. Bustamante now for his closing remarks.
Ignacio Bustamante
executiveThanks a lot, Katy. And thanks to all of you for joining this call — we really appreciate your time. If any questions are still outstanding, don't hesitate to reach out straight to Charlie Gordon at our London office. Many thanks, and have a great day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Hochschild Mining plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Hochschild Mining plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hochschild Mining plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.