unknownHello, and good day. Welcome to the Hochschild Mining call covering production results for Quarter 1 2023. Right now, I'll hand things over to Ignacio Bustamante. His line is open. Thanks.
Speaker
unknownThanks, Carolina. Hello, everyone, and welcome to the conference call where we'll go over our Q1 production results. With me here is Idema, along with Eduardo Noriega, our CFO, and in London we have Charlie Gordon, our Head of Investor Relations. Clearly, it hasn't been very long since we reported our full year results, so I'll keep my remarks brief and then we'll move to questions. Group production for the quarter came in at slightly above 64,000 gold equivalent ounces, which equals 5,400,000 silver equivalent ounces. Adi Ma Culada. At this point, I'd like to hand the conference over to Adi Ma Culada — that figure was a bit more than 31,000 ounces of gold plus 1,300,000 ounces of silver, giving us total gold equivalent of 46,600 ounces. The timing around the approval of operations and the modified environmental impact has, as we anticipated, affected mine development during Q1. Anne. As you're aware, we also experienced some local and national disruption, though better than expected grades provided an offset. To restate what we mentioned 3 weeks ago, we still anticipate a prudent government decision regarding the modified environmental impact assessment within this quarter. And assuming we receive that approval, we remain confident the mine will achieve its guidance for the year, just as it has done every year since commissioning.
Speaker
unknownIn Argentina, the first quarter always includes the seasonal vacations for personnel, and as a result, tonnage going through the mill was lower during the period, along with some grades that came in below expectations. Output came to 1,900,000 silver equivalent ounces, which represents a big improvement over last year's results, when we were still dealing with COVID as well as a fire in the crushing area. This mine has always been weighted toward the remaining quarter over the quarters of the year, and we expect the same in 2023. Over at Pallancata, production was 514,000 0.3 ounces, which reflects the long-term decline in the 0.3 profile Anna Mining area that is close to completion. As we have previously indicated, we expect to place the mine on current maintenance later in the year. On costs, I am pleased to say that we are reiterating our 2023 guidance, which, if you remember, is between $13.70 and $14.50 per gold equivalent ounce. Turning to our Maradrosa construction project, we have had a good start to the year, with total project progress now at 77%. Diesel engineering is 99% complete and deliveries of key project equipment are all on schedule; Wael's civil works for the processing plant area is 86% finished.
Speaker
unknownAnd last, the mine's power supply should be finished in July. We're still on schedule and within budget, and it's exciting to note that commissioning remains on track for the first half of next year. I won't go into much detail about exploration, since the timing of the brownfield program in Peru depends on approval of Irma Guadalaj's modified environmental impact assessment. We have made a
Speaker
unknownI'll begin with the start of it.
Speaker
unknownWe're drilling in Argentina, and we expect to see results start to show over the coming few months. Financially, we hold roughly $103,000,000 in cash, which works out to net debt of $218,000,000. Annette, that puts net debt at about $0.95 times EBITDA for the trailing 12 months. The cash balance, of course, mirrors capital. So to wrap up, we're reaffirming our guidance for the year, even though Q1 will be the weakest of the 4, and we're continuing to make solid progress on our Marabrosa project in Sergio. Last and most importantly, we anticipate Inmaculada's revised environmental impact assessment process will wrap up by the close of this quarter. With that, I'd like to open the floor to any questions you might have.
Speaker
unknownThanks. The first question comes from Ian Russell at Barclays. Your line is open now, so please go ahead.
Speaker
unknownThanks. Hi, Ignacio. I just wanted to explore a little further what you said about production being weighted toward the second half. Presumably, if the MEA — if the permitting has sort of held development back in Q1, should we expect that to carry into Q2 as well? And then perhaps you could give us a sense of what we should expect for the H1, H2 split across the various operations. If you could give us maybe a percentage of full year, etcetera, that would be great. Thank you.
Speaker
unknownOkay, so, yeah — as Margiela Galla was saying, our output during Q1 tends to be the softest of the year, as we mentioned. That's especially noticeable at San Jose, where staff take vacation for a significant chunk of that stretch. And those conditions shift over the remainder of the year. For Inmaculada, Q2 ought to come in stronger than Q1, given how the mine plan for the year is laid out. It's been scheduled that way on purpose. So grades will begin climbing. That means we should be looking at higher production during the second quarter. Moving into the second half of the year, that's where we anticipate the largest grade improvements, because we'll be moving out of the new zones at the mine — assuming we get that decision on the modified environmental impact assessment, per our guidance in Q2 of the year. So the 2nd quarter should top the first one, and then the remaining 3 quarters — the 3rd and 4th quarter of the year — should be even stronger. As for Pallancas, that one's a bit more unpredictable, since we're in the final stages of the mine.
Speaker
unknownWe're basically mining material right at the border, and that border area comes with a lot of variability. That said, we still anticipate grades will begin to improve over the rest of the year. But again, there's more uncertainty given that variability, the grade in the border areas. At San Jose, although it came in better than Q1 of last year — for the reasons I mentioned, the COVID situation last year and the problems in the crushing area — the grades are also below what we expect for the remainder of the year, due to mine planning, programming and scheduling. So we should also expect to see an improvement as we move through the remaining quarters of the year. So in short, we should expect better 2nd quarter production and an even much better second half of the year at our operations in the end of
Speaker
unknownAlright, thank you.
Speaker
unknownThanks, Ian.
Speaker
unknownThanks. The next question comes from Daniel Major at UBS on line. Your line is open now, so please go ahead.
Speaker
unknownHey, everyone. Yeah, thanks. Appreciate the questions. My first one is about getting that environmental permit approved. With the final full year results, you sort of laid out 3 scenarios: a worst case with a long, drawn-out delay, a brief delay, and approval. Could you tell us, first, whether you can give any hint as to what the critical path item is that's holding up the approval, if there is one? And second, on probabilities, where do you land among those three outcomes right now?
Speaker
unknownRight, right, Daniel. Essentially, we're restating what we told everyone 3 weeks ago at the time we announced results for the full year. So those 3 scenarios remain on the table. Our view is that the odds overwhelmingly favor the first one — the scenario we laid out to the market, under which a decision comes by the close of Q2 this year, meaning before June ends. And what we expect is that the outcome will be favorable. That said, as you're aware, it rests on a government decision, though based on what we know as of today, we see no reason for a denial or for any delay. So that's the core assumption guiding our current work, and the one we think carries the greatest likelihood right now.
Speaker
unknownAll right. And could you share anything — I mean, is there a particular thing still pending that's holding up the approval? What exactly is the item?
Speaker
unknownNothing significant is still outstanding. What remains is really about finishing the work and wrapping up the review of the observations that came out of the reviews by the governing entity, which is an asset, as I go through any additional questions they might have. So this will be a stretch where there should be plenty of interaction with the organizations in charge of granting the permits. As you can imagine, this is a top priority for us. So all the researchers of the company are dedicated to answering the potential remaining questions. But so far, no, I would say it's just going through the administrative work of reviewing the final observations and completing the overviews.
Speaker
unknownAll right. Moving to the next item, which concerns your balance sheet and the downside scenario where Inaki Lada gets closed at year-end. Based on your internal assessments, with gold and silver at present levels, would Maro Rossa and San Jose generate enough EBITDA on a forward-looking basis to keep you from breaching a covenant in the second half of 2024?
Speaker
unknownSure. I'll hand that question over to our CFO, Eduardo Nuria, who's here alongside me, Dan.
Speaker
unknownThanks, Dan. So for sure, if the mail doesn't come through, we need a solid plan to secure an engine, and we'll have to take internal steps to resize the company to the new reality of operating for a period of time with Maria Rosa and San Jose. So we'll act to adjust the company and be able to guarantee its continuity. Regarding the covenants we have, we should be fine for this year. And so the positive thing here is that we're in close contact with our lenders and we've built a good relationship with them. So we are — and they are prepared to respond in the event of an unexpected scenario as
Speaker
unknownThe one you mentioned. Throughout this period, the banks have been applying to us, so they know quite well where the permitting process currently stands.
Speaker
unknownAlright. Appreciate it. Thanks, Otello. Best of luck getting that permit through its final approval.
Speaker
unknownWe'll go to Richard Haig from Berenberg for the next question.
Speaker
unknownHi Ignacio and Eduardo, hope you both are doing well. I was just wondering whether I could dig a little into San Jose. Obviously, grades dropped quite a bit quarter over quarter and year over year. I'm just curious if you could give us some color on how we ought to think about grade progression at San Jose as we move forward. And then, looking at McEwen's results, they mentioned negative grade reconciliation versus the model. I just wonder if you could talk a bit about that. That's the first one.
Speaker
unknownOkay, so on the first part — on the left-hand side of the note, about rate reconciliation — what I'd say is that this is fairly normal for these kinds of operations, underground veins with that level of variability. So no, there's nothing there that should really be materially concerning to us. Where differences exist, they usually get reconciled, or they need to be identified, so we'd expect that some of those differences versus the model will be recovered over the remainder of the year. So that's a work in progress. And on grades, roughly speaking, for Gold we've been averaging around 4 grams or so. For silver, at the No. 220, 230,000 in Q1 of the year, oscillating through January, February, March. We'd expect that in Q2 of the year we'll be somewhere around the low 5s for gold and around the high 290s or low 300s for silver. And for Q3 and Q4 of the year, we should be more in that low-to-mid 5s for gold. And for silver, we should be around 350, 360 grades Inaraj for the second half of the year.
Speaker
unknownSo that's how you should expect the grades to trend for the remainder of the year.
Speaker
unknownAlright. I mean, the fact that you’re doing that while you talk sort of suggests that you have to drive some throughput. I mean, I think the plant came in a little light, didn’t it? Q1, but that’s seasonal. So is the plan to sort of run the plant as hard as you can, around 150,000 tons The quarter — is that kind of where you’re thinking? Sort of really try to push it a bit higher? And is that how you make up for that sort of softer grade in the Q1?
Speaker
unknownDuring Q1, the most significant storage problems stemmed from staff taking vacations. That's a once-a-year occurrence. So the plan, Richard, is that for the rest of the year we'll be running the plant at full capacity.
Speaker
unknownAlright, cool. Thank you very much. Alright, cool. Then regarding Pankata, could you remind us of the timeline for volumes coming out of that mine? And maybe, I mean, it has only been a few weeks, but on Rura Apata, could you give us an update on what you're seeing there, recent drill results? I don't believe we've got any drill results in this release. But is there — how is that progressing, and is it coming along as you'd expect?
Speaker
unknownSure. So for Ayelqata, what we're aiming at right now is a possible wrap-up of operations before this year is over. When exactly that happens will hinge on — and naturally, there's also a bit of extra ramp-up activity we're carrying out on the operational side. So it's difficult to predict, but the best steer we can provide is that it will land near the close of this year. And no. And once more, the big — we think this will rest heavily on how the model reconciles. There's plenty of variability in that. And the second piece of your question concerned Royal Lopata. At Royal Lopata, we wouldn't be undertaking any further work right now; we already hold a very substantial resource base, more than 50,000,000 ounces, with grades near 8 50, 5 meter wide width, so it looks quite promising and holds considerable upside to grow, because we've drilled as far as we're able to from the area currently permitted. So at this stage we have to await further permits before we can drill additional ground and expand the resource.
Speaker
unknownBut what we already have is more than sufficient to project the growth of the mine and to begin work on permitting for that section of the mine. Ann, the permitting process is already underway. We have already begun that work. So we continue to believe that this process could take us roughly 3 years. And we are going to push as hard as we can. And hopefully, the government also moves in the same direction on ways to shorten the timing of the permitting process for the entire sector in the country, which is something that is really needed. And we can optimize those filings. Furthermore, Barossa, it will be very encouraging with plenty of geological potential, and we have already started the permitting process and we're moving at full speed.
Speaker
unknownThanks a lot, Ignacio.
Speaker
unknownThanks, Richard.
Speaker
unknownThanks so much. We don't have any more questions right now. I'll turn it back to your host for the closing remarks.
Speaker
unknownThanks, Caroline, and many thanks to all of you. I appreciate it very much, and have a great day.
Speaker
unknownI appreciate everyone for joining in. At this point, you're welcome to hang up.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Hochschild Mining plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Hochschild Mining plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hochschild Mining plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.