Hochschild Mining plc (HOC) Earnings Call Transcript & Summary

March 13, 2024

London Stock Exchange GB Materials Metals and Mining earnings 55 min

Earnings Call Speaker Segments

Eduardo Landin

executive
#1

Good morning, everyone, and welcome as we present the 2023 results. I'll give a short introduction to those results, and after that I'll hand things over to Eduardo Noriega. He'll take you through the financials, and then I'll come back to present an update on the company's strategy. And finally, we'll look at some conclusions. So let's go to the first one. We feel very proud of a year of delivery. First of all, I have to mention that our ESG performance has been very strong, and I'll tell you more about that later. On the results side, revenues came in at $694 million, EBITDA was $274 million, EPS was $0.02, and all-in sustaining cash cost was $1,454, which is better than guidance — I mean, the EBITDA guidance in terms of cost — and we also came very close to the high end of the guidance we presented in the middle of the year. We have to remember that it was a tough year, because we were supposed to get the environmental permit for Inmaculada on the 1st of January, and the budget was done based on that assumption. And we finally got it in August.

Eduardo Landin

executive
#2

Alright, that was a tough one. But in the end, we got there. On growth, Mara Rosa is now producing. We completed the project on schedule and within budget on 31 January. Our first gold pour happened on 22 February. And as of today, we believe commercial production will be reached before the end of June 2024. So that's a great outcome for Hochschild — entering a new country, one where we're quite comfortable operating. We also have Royropata. It's an outstanding deposit containing 50 million ounces. We've already <<inaudible>> to add new resources. And the latest development is that we've signed a new option on Monte Do Carmo with Rado Gold, which opens the door to another operation in Brazil. Our balance sheet, meanwhile, stays very strong. Cash stands at $89 million. Net debt remains at $256 million. And our focus is on repayment, debt growth and capital return. Despite the challenges in 2023, we feel very positive about our ESG results. For the first time ever in Hochschild's history, we've managed to bring our frequency rate down below 1 — 0.99 — which is a fantastic figure not just for open pit mines but, I'd say, remarkable for underground mines.

Eduardo Landin

executive
#3

In addition, our ECO score is the highest ever recorded, hitting 5.75 out of 6. That is quite strong. We managed to construct the Mara Rosa project with 5.5 million hours of work and not a single lost time accident. Doing that in a new country, with new contractors and a new team, is an impressive achievement. We succeeded in raising the local workforce to as much as 61%, and we were also able to attract new businesses into communities, generating $156 million. That comes from services and from local providers. With that, I'll hand the presentation over to Eduardo Noriega to walk through the financials, and I'll be back with you in a minute.

Eduardo Noriega

executive
#4

Thanks, Eduardo. 2023 was a really strong year financially for us, with revenue reaching $694 million. EBITDA came in at $274 million — that's $25 million better, or more, than 2022. Attributable net profit was $9 million, which is $4.1 million above our 2022 figure. Revenue was 6% lower than the prior year, largely because the Inmaculada permit delay hit production. So production came in below the year before. But better prices partly made up for that, as the slide shows. Cost of sales dropped 4% as well, consistent with the reduced production, partly offset by a planned larger share of conventional mining methods at Inmaculada and somewhat higher depreciation. Exploration expenses came in below the prior year, mainly because of the termination of the SNP option and also because we budgeted lower expenses given where the Inmaculada permit stood at the start of the year. Net interest was lower than last year's too, chiefly because of interest cost capitalization on the Mara Rosa project. That was partly offset by the higher debt we took on to finish construction at Inmaculada, plus rising interest rates over the year.

Eduardo Noriega

executive
#5

We booked an FX loss of $15.6 million, tied mostly to the Argentinian peso's devaluation, which hit our monetary assets in Argentina. Our $44 million income tax figure also reflects a $7 million hit to deferred income tax stemming from that same peso devaluation. That number additionally takes in Peru's special mining tax and royalties, which came to $6.8 million. Beyond those items, we booked exceptional items totaling a net $69.5 million, driven largely by impairments at Azuca & Crespo — our 2 noncore assets — amounting to $63 million. We likewise recorded a $17 million impairment at San Jose during the first half of the year, reflecting rising costs and uncertainty ahead of the elections. At Pallancata, we had $9 million in exceptional termination benefits after placing our Pallancata mine into temporary care and maintenance while we finish permitting Royropata, that fantastic Royropata project. Lastly, we took a $7 million impairment at Aclara, the project in which Hochschild holds a 20% interest, tied to the difficulties those projects face in the permitting process. The tax effect of all these items came to $27.4 million.

Eduardo Noriega

executive
#6

On cash generation, I'd say we used a portion of our cash plus the cash produced during the period to finish building Mara Rosa, as you can see on Slide 7 of this presentation. We began the year with $144 million, and then we generated $145 million at Inmaculada and $30 million at San Jose. We spent $4 million of our cash at Pallancata, including the termination benefits we had to pay. Brownfield exploration across our projects came to $17 million. Corporate expenses were $47 million. We paid $10 million in cash. We carried out mine closure expenses, and care and maintenance expenses were $23 million. Net interest paid came to $18 million. We had $5 million of negative working capital movements and other effects. And then our debt rose — net debt went up by $25 million. With those items, as I mentioned earlier, we invested $131 million in Mara Rosa in Brazil, which, as the slide shows, mostly went toward construction of our Mara Rosa project in Brazil. On costs, our all-in sustaining cost was pretty much in line with what we saw in 2022, at $1,454 per ounce on a consolidated basis.

Eduardo Noriega

executive
#7

For Inmaculada, costs came in a bit above what we saw in 2022, yet the figure landed under the guidance we gave you — largely tied to the greater share of conventional mining methods I referenced a few slides back. The permitting delay at Inmaculada also played a part versus what we assumed at the start of the year. Team-driven savings and efficiencies partly offset those negative effects. On San Jose, all-in sustaining cost of $1,570 came in below both what we reported in 2022 and what we guided to the market, chiefly because of FX effects on our costs. The peso's devaluation gave us a lift during 2023. At Pallancata, all-in sustaining costs were lower than the prior year and lower than guidance, thanks to reduced CapEx along with lower exploration and production costs. Turning to capital expenditures, CapEx for the year totaled $129 million, under 2022's CapEx and under the guidance we gave the market — mainly because, again, the permitting delay at Inmaculada meant we couldn't carry out all the CapEx we had originally planned.

Eduardo Noriega

executive
#8

Then for San Jose, our CapEx came in lower than the prior year and below the guidance we gave to the market, largely thanks to a more favorable FX rate for the company. On Mara Rosa construction CapEx, the figure stood at $121 million, which was above our expectations. That said, it's purely a timing effect. We sped up project execution so we can wrap up the note and get the first pour done as early as we can. We remain on track to hit the $200 million CapEx we established for the project. The balance sheet is still very strong, with $89 million in cash and $256 million of net debt. Net debt to EBITDA came in at 0.7x. I believe there's a pipeline on this slide — that wasn't intended. And as Eduardo — as we mentioned at our Capital Markets Day, our target, or the range for the net debt-to-EBITDA ratio, sits between 0.5x and 1.5x, and we're moving toward the lower end of that range. We put some hedges in place to protect our cash flows precisely so we can bring down indebtedness at the company level.

Eduardo Noriega

executive
#9

On this slide, I want to draw attention to the lower hedge—the second one, the 60,000-ounce hedge we put in place for 2025—where the bottom end of the range, which is the cap on the zero-cost quarter, sits at $2,485. That line also contains a typo. And then, last, we are not declaring any dividend at this year-end. We'll take another look at that in the second half of the year. We'll also hold internal discussions on it. But first, Mara Rosa has to go into commercial production, and we need to begin seeing cash generated by the project. Lastly, in the financial results section, I'd like to restate the capital allocation priorities we set out at our Capital Markets Day in November: first, we want to finish the investments in the Mara Rosa project and the Royropata permitting, so the projects we are currently developing must be completed. Second, we invest in brownfield and create value for the company via our exploration programs on the properties and JV properties we hold. Third, we concentrate on repaying debt and reducing indebtedness.

Eduardo Noriega

executive
#10

Fourth, returning capital. As I mentioned, we'll talk about that later in the year. And last, on M&A with clear parameters, and hopefully at some point we can repeat what we just executed on Mara Rosa, which has worked very well for us. So with that, I'll hand it back to Eduardo.

Eduardo Landin

executive
#11

Thank you. So our approach is quite straightforward: stay concentrated on our core assets. Inmaculada serves as our flagship operation. We have 20 years in front of us for brownfield exploration across a very large land package. Mara Rosa is in production now, with a mine life of 10 years and 100,000 ounces of output at a strong all-in sustaining cash cost. San Jose is a high-grade operation that has been producing since 2008. And at present, given the situation in Argentina, we have an opportunity for an improved macroeconomic environment that should show up in our results. Royropata is the new deposit in Peru that draws on the existing infrastructure. And Monte Do Carmo is the fresh option for a new mine in Brazil. Our approach is quite straightforward. Brownfield work is how we generate new resources and create value for the company, extending mine life. And naturally, we must stay focused on mineable resources. Beyond that, there are operational efficiencies. We need a lean philosophy throughout the company. We must pursue process optimization at all times. We have demonstrated substantial capabilities when it comes to developing projects on time and on budget.

Eduardo Landin

executive
#12

We also have to bring in new technologies to cut costs, which ultimately comes down to operational efficiency. Another thing that matters a great deal is staying close to the operations. That is why I traveled to the operation in Q1, and I will travel again in Q3. Joining me will be every executive in the company. On ESG, we must champion responsibility and respect. Our safety performance is world-class, and we have to keep pursuing the 0 accident target, which is our dream. We have already established the ESG KPIs for 2030, and they form part of our objectives. As Eduardo said, capital discipline also matters greatly so we can fund organic growth — I mean debt repayment, capital returns and, naturally, value-accretive M&A, for which Monte Do Carmo is a perfect example, or Mara Rosa, which has been executed and is in production today. What we presented at the Capital Market Day is a projection of our production over the next 3 years showing 20% growth from 2023 to 2026, along with a cost reduction of another 20% over that same period.

Eduardo Landin

executive
#13

The positive part is that starting in 2027, Royropata will also be available to us. And should that option prove viable at Monte Do Carmo, we might additionally have output from Monte Do Carmo beginning in 2027. Turning to Inmaculada. At Inmaculada, as I noted, there's a $45 million CapEx that gets recorded as cost on 2024. However, that reflects the TSF expansion work that we chose not to carry out during 2022 and 2023. We're putting in a reversal of Moses plant. That is why this cost shows up here this year. We have plenty of initiatives aimed at bringing down cost at Inmaculada over the course of this year. But I should note that we're engaged with Boston Consulting Group. As of today, Boston Consulting Group is deploying a SWOT team. Within the first 3 weeks of that work, they identified alongside us 17 initiatives either to boost production or to cut costs. So that's very encouraging news. What I mean is that the goal at Inmaculada is to hold 200,000 ounces across the life of mine and to stay at this cost level, which will be reached in 2025. If we can, bring that cost level down through these initiatives. Moving to what the brownfield strategy at Inmaculada could offer, I mean the near-term objective is to extend life of mine.

Eduardo Landin

executive
#14

Our plan is to produce 2.0 to 2.4 million ounces of gold over the coming 4 years. Right now, the most exciting spot is Eduardo Belt — that gray area there — where we've had fantastic drilling results during the first 2 months of this year. So we think we may be able to share some news once we come out with the new resources later this year. Then there's Royropata. Royropata holds a resource of 50 million ounces. What you're seeing here is the gold equivalent. We have that resource, and we also have the geological potential to extend it — in fact, to double this resource. And drilling has already begun. The grades and the width of the pane are extremely good, so that will lead us to bring in mining methods, productive mining methods, so we can achieve very good all-in sustaining cash costs. And you can see the financials here. All-in sustaining cash cost should come in around $1,000. The internal return will land between 45% and 55%, since the CapEx is quite low for a new mine. Essentially, we'll rely on all the infrastructure we already have at Selene and Pallancata. But that's not all.

Eduardo Landin

executive
#15

I mean, this is the region we're focused on, which we refer to as the Royropata Belt, but we also have the Pacapausa system, Pallancata Northwest and Bolsa — new areas where we could unlock fresh potential. Right now, what we're doing at Royropata is trying to secure the permit as quickly as we can, and we think that in 2 years, in 2026, we'll be able to obtain these new permits. Mara Rosa, well, everyone knows it's in Goias, it's our new mine. We've had the first pour. Commercial production will be reached in H1 2024. Its mine life runs for 10 years. At the moment we're trying to analyze and identify the bottlenecks at the plant so we can try to get extra production that could be a very good upside. On production, Mara Rosa, the plan is to hold 100,000 ounces for the first 4 years of production, and the all-in sustaining cash cost will be between $1,100 and $1,000, more or less, as you can see there. I mean, we had the first gold pour on the 20th of February. But let me say the most important achievement at Mara Rosa isn't the production — it's the safety.

Eduardo Landin

executive
#16

So we managed to complete this project with 5.5 million ounces — sorry, 5.5 million hours of labor, and not a single lost time accident occurred. The project wrapped up on schedule and within budget. Ramp-up is underway, and at this point we aren't seeing any issues. On the ESG side as well, we've put a lot of initiatives in place so that we can maintain a really strong relationship with the Mara Rosa community. We built this trail knowledge place, where lots of schools come by to learn about the project's history and the history of Mara Rosa and all of that. The local government has welcomed that very warmly. We've also been able to purchase roughly $9 million from local producers and local suppliers. And as of today, 320 people are working at the site. That's the ceiling for us, since there's no additional workforce to be had. Sure, we could add more, but there simply isn't any more available. And the goal at Mara Rosa is really to double the resource over the next 6 years. We think there's potential to add a new 1 million ounces of production, which would extend the life of mine by another 10 years.

Eduardo Landin

executive
#17

The nice part is that Pose sits right there, and that’s where the existing deposit is. We’re drilling across this belt, and we think the potential is substantial. There are a few other targets we’ll test over the coming years, but right now our focus is here, where we can add new resources fast and also leverage the plant’s existing infrastructure. Turning to Monte Do Carmo, I think this option makes a great deal of sense for the company and fits entirely with our strategy — with what we’ve laid out as our strategy. First, because we currently hold a resource of 700,000 ounces at good grades. Second, because we believe that, drawing on our brownfield capabilities, we can grow that resource base and try to get this project into a position where it could be very profitable for us. And for that, we have 12.5 months. We didn’t commit much cash — only $50 million, I mean, to secure this option. And afterward, if the project is profitable, we’ll add another $45 million, for a total of $60 million. It’s also very close to Mara Rosa.

Eduardo Landin

executive
#18

It's just 4, 5 hours of driving. So it sits in Tocantins, a state in Brazil that's very friendly toward mining. And bear in mind that for the Mara Rosa project we set up a really solid corporate office in Bello Horizonte. So as of today, we've got a country manager, we've got managers, a finance team. Everything is ready so that we can grow in Brazil. So I think this is a fantastic opportunity for us, and that's why we signed this option. Moving to the conclusion, and this is the last page. We are focused, and we will stay focused, on the core assets. Our focus will be on raising production. And our focus will be on cutting cost. We want to keep up a world-class ESG performance. We have this new low-cost mine in Brazil, a very important asset for us. Inmaculada today is the risk, and we have 20 years to carry out an exploration brownfield strategy so as to bring in new resources and extend life of mine. We have Royropata. We need to secure the permit, which is another 100,000 ounces at a low cost starting from year 2027. We will keep going with the brownfield strategy. We put $33 million into drilling this year, and we are drilling everywhere.

Eduardo Landin

executive
#19

We're drilling in Argentina, in Royropata, in Brazil, and at Inmaculada. Today we've secured a new project in Brazil, and that fits entirely with how we approach brownfield exploration. As Eduardo said, we've put in place a highly disciplined strategy for allocating capital. And last, as you know, we're a new team at Hochschild — new, yet very old, because every one of us has spent many years with the company, and we bring plenty of experience working in Peru, Argentina, and Brazil. That's everything from me. Thank you so much for joining us today for the presentation of our 2023 results. Now we'll move to Q&A. Many thanks.

Daniel Major

analyst
#20

Dan Major here, from UBS. I have a couple of questions. Regarding Royropata, could you take us through the permitting schedule and what's required — the key deadlines and the key dates that are needed to hit that 2027 start-up?

Eduardo Landin

executive
#21

In 2023, we completed the feasibility study and all the engineering work, and those are finished—completely finished. We've also been negotiating easements with the communities, the same communities we had at Pallancata, the same area, but it's additional land we need to negotiate with them. I'd say that as of today, we have about 80% of the land negotiated, and of course there are a lot of expectations from the communities regarding this new project. So we need to finish the baseline study—the dry season and wet season fieldwork has to be done in 2024. In 2025, once we've finished those baseline studies along with the engineering and easements, 2025 will be the year the Peruvian government reviews all the work. We believe that within 12 months, they'll be able to conduct the review and issue observations, giving us the opportunity to respond to their observations. And that process, that evaluation process, should conclude in 2025. So we should expect to receive the permit at some point during 2026. If that happens, in 2026 we'll begin developing the mine.

Eduardo Landin

executive
#22

Right now, the mineralization sits on the wall adjacent to where we're currently operating. That means kicking off development work and beginning to produce isn't hard. Of course, it will be a ramp-up, since we have to develop the mine and open enough working faces to reach, say, 2,000 or 3,000 tonnes. I mean, we have a big plan — a 3,000-tonne flotation plant at Selene — so we need to get up to that production level. But that's where the timeline for Royropata stands today.

Daniel Major

analyst
#23

Okay, so just perhaps as a follow-up on that point — I mean, when you look at this company's history, you've, I suppose, missed the targets that were set out to the market because of delays in permitting. Isn't there some way to try to speed that permit up? You kind of signaled 2027 to the market, and you won't be able to get the permit in 2026. The track record would suggest that permits take longer than people expect. This is still quite some distance off for what is a relatively straightforward restart. What is preventing that permitting process from moving faster? Because it seems to me, if we go by the timeline of the past, 2027 looks optimistic if you only anticipate receiving the permit in '26.

Eduardo Landin

executive
#24

All right. Let me say this — probably, given the consequence, that analysis you've put together rests on the Inmaculada permit, though that is the sole permit where we've faced a delay previously. Yet when we set Inmaculada against Royropata, the differences are many. To begin with, Inmaculada's area came to 10 times that of Royropata, and that makes an enormous difference. Beyond that, we don't have to engage with new communities. Here, these are the communities with whom we already hold a relationship. I'd add as well that the Peruvian government is entirely different. Right now we have a new cabinet, with a prime minister, and they are promoting mining across the world. A few weeks ago they were at the BDC in Canada, promoting mining. So they are willing to grant us those permits so that new projects can be developed. Keep in mind that with the Inmaculada permit, we had COVID. And the authorities could not go to the site. So that evaluation was done remotely. That was an extremely difficult situation. So I would say that today, if we allow a year for evaluation, we believe that the time set — the schedule I just handed to you is something achievable.

Eduardo Landin

executive
#25

Doing it faster isn't possible, because, I mean, as things stand today with the engineering, you need 2 seasons — the dry one and the wet one — and then you need the government's evaluation time, which is — I mean, it's supposed to be 90 days, but in real time it will be a year. So that's why I believe we could get the permit on 2026. So I believe that is realistic.

Daniel Major

analyst
#26

Alright, that's helpful context. Then, if I could, one more question. CapEx guidance for this year sits at roughly $175 million to $180 million. For the new project, should we take it that the extra $15 million lands in the CapEx line rather than being expensed? Or — where exactly would that appear in the financial statements?

Eduardo Noriega

executive
#27

Thanks a lot, Dan. That cost is going to land in CapEx and be capitalized, since it’s a project we’ll be building later on. So yes.

Daniel Major

analyst
#28

So we're looking at roughly $200 million — somewhere around $190 million to $200 million — that's the range CapEx should land in?

Eduardo Noriega

executive
#29

Correct.

Daniel Major

analyst
#30

Alright. And just to follow up on that CapEx dynamic — if we head into 2025 based on the expected sort of rate of spend, how should CapEx trend in 2025 at this stage, without giving us, I guess, clear guidance?

Eduardo Noriega

executive
#31

We haven't given any guidance on CapEx for 2025. For this year, 2024, we have done that. But it's going to be pretty much along the same lines. I mean, with Inmaculada, you need to factor in that $45 million will be expensed this year and won't be there next year — similar, but excluding that effect, since that's CapEx where we're catching up from the last couple of years. Apart from that, it should be fairly comparable.

Daniel Major

analyst
#32

If everything else stays the same, that’s $45 million lower.

Eduardo Noriega

executive
#33

Correct.

Richard Hatch

analyst
#34

Richard Hatch from Berenberg here. I just have a single question about the dividend — you kind of hinted that you could look at it around midyear. So would it be reasonable to expect that a dividend reinstatement might come along with the H1 numbers?

Eduardo Noriega

executive
#35

We haven't proposed that at this point, because our position has been that — thanks for asking, Richard, and apologies. Our priority is getting Mara Rosa into commercial production first. We need to concentrate on generating cash flow and beginning to see our debt ratios decline. After we've achieved that, we'll have a conversation about it. But no decision has been made up to now.

Richard Hatch

analyst
#36

To press you a bit on that—would it be kind of crazy to think that, if everything moves the right way, the balance sheet is in good shape, you're at about 1x net debt to EBITDA, you're in the middle of your target range, and mara Rosa seems to be going well so far—so congratulations to you on that and on generating a lot of cash—so is it wild to think that the Board might perhaps consider showing that? Or do we...

Eduardo Noriega

executive
#37

Absolutely, they'll definitely factor in those points you're raising, and it'll be part of the conversation. It's simply that we haven't reached that decision at this point, and we need to hold off and sort of follow through on what we committed to, and after that have that discussion internally. So that's...

Richard Hatch

analyst
#38

Turning to costs — Eduardo, you brought up Boston Consulting Group, and I have a couple of questions about that. On Slide 15, where the cost guidance appears, could you clarify whether any of those efficiencies are included in it or not? And then second — no? And then second — I've seen this before, and call me a sceptical analyst, right? Boston Consulting comes in and does the work, and then they bill you an arm and a leg for it on top. So what is the actual net benefit to the company here?

Eduardo Landin

executive
#39

No. Essentially, our arrangement with Boston Consulting Group is a fee that varies according to results. So no additional fees will be layered on that would impact the actual all-in sustaining cash cost.

Richard Hatch

analyst
#40

Is there some way you could give us a rough number or target for that, or maybe update us along with the H1s on where things stand regarding the cost of volume?

Eduardo Landin

executive
#41

Honestly, it's still too early regarding the diagnostic — I mean, we do have the diagnostic, but we don't yet have the implementation plan. So I'd rather not provide any — I mean, any figure that would come with no base.

Richard Hatch

analyst
#42

And then the last one — I don't think you'll be able to answer it, though. But regarding Monte Do Carmo, the PFS, or feasibility study, points to CapEx of $181 million. Does that figure sit comfortably with you, or do you believe additional work is still needed on it?

Eduardo Landin

executive
#43

No. We think there’s a great deal of work still to be done there. And during our option period, that work will include analyzing everything — the feasibility study, engineering, resources, all of it, the money method, everything. We won’t make a decision based on any third-party figures, I mean, we have to do our own engineering and our own numbers. And certainly, we’ll bring a figure to the market that can actually be done. We aren’t trying to sell our project. What we’re trying to do is develop a project, get it into production on time and on budget once more, and hit our production and cost targets.

Marina Calero Ródenas

analyst
#44

To build on what Richard asked, could you perhaps share some examples of the initiatives you're examining at Inmaculada aimed at boosting production and cutting costs?

Eduardo Landin

executive
#45

So essentially, at Inmaculada, because we managed to carry out the development work during 2022 and 2023, we now have the chance to — what I mean is — improve ventilation, for instance, and to boost the cycles, the mining cycles, to raise the speed so we can get more production. What I mean is, in 2024, we have a budget for full capacity at the plant. So anything beyond the budget will be upside. So basically all the initiatives are aimed at raising production from the mine and trying to cut cost. That's the sort of initiative. And I believe they are entirely doable. The thing is that, because we had a very difficult years with — I mean, we held back all the capital expenditure until we got the MEIA, today the mine is less developed than it would need to be. So that's why we need to bring in these measures. And it's good to have these consultants to bring energy to the people and to the operation, so they wake up and realize that we are in a totally different situation.

Marina Calero Ródenas

analyst
#46

And one more thing, if I can. At the Capital Markets Day, you talked about possibly raising the capacity of the San Jose plant. Could you update us on where that project stands?

Eduardo Landin

executive
#47

Right. So we're in the middle of completing detailed engineering on that project. It looks like we'll be able to lift capacity to as much as 2,000 tonnes per day, and that's a meaningful capacity increase for San Jose. The biggest benefit there is that we'd be able to process lower-grade material that was mined previously and is already sitting on the stockpiles. That could give us additional material and ounces, essentially at almost no cost. And what's nice about this project is that — we're looking at installing a Verti mill, which is special equipment placed between the existing mills. You get <<inaudible>> material, and that's why you can push 2,000 tonnes through the cells, the flotation cells, and the ILR, I mean the leaching process, at San Jose.

Marina Calero Ródenas

analyst
#48

Could you remind us what additional production you'll get from that? And what did the CapEx come to?

Eduardo Landin

executive
#49

So CapEx is going to land at roughly $10 million. I can't give you the production volume we'll be capable of — but it will be, you know, sufficient, naturally, to make this a highly profitable project.

Eduardo Noriega

executive
#50

If I could just build on what Eduardo said — the payback period we project for a project of that kind comes in under a year, likely 8 to 9 months. So that's — yes.

Eduardo Landin

executive
#51

This is a really strong opportunity.

Marina Calero Ródenas

analyst
#52

So those ounces aren’t included in your production guidance?

Eduardo Landin

executive
#53

No, that’s not right. They aren’t.

Analyst

analyst
#54

I have a few questions about the projects. First, there are a couple of remarks in the presentation. The first one concerns Mara Rosa, under the rainy season impacts. I was just wondering — I mean, obviously, it didn't affect first gold, the budget, the time line or anything. But has it had any effect on stockpiles or perhaps the commissioning process? I was just wondering if you could give us any color, just since you brought it up.

Eduardo Landin

executive
#55

That's a fair question. So, look, the initial schedule called for wrapping up the project in December. That wasn't publicly disclosed, true, but it was the goal. Naturally, we ran into a very intense rainy season, and that's why the project was completed on the 31st of January. Regarding how this affects ramp-up, there is some effect. But, I mean, that effect lasts through March, since the rainy season will wrap up in March. As things stand today, the dry stock operation is something we're still getting familiar with, because there are enormous filters operating there. The positive side, though, is that a dry season lies ahead of us for the next 9 months. So ultimately, we don't — I mean, we don't expect any effect on ramp-up. We'll have enough time to get familiar with that process over the next 9 months. That way, when the next rainy season arrives, we'll be prepared for, I mean, uninterrupted production.

Analyst

analyst
#56

That's great. Then the second 1 is also about Mara Rosa — you just brought up the debottlenecking, that you're working on something that could help with volumes. Are we talking about — I mean, it's so early stage that I would have thought it's something like under a 10% increase in volumes, but at this stage are you looking at something bigger than that?

Eduardo Landin

executive
#57

No. That is precisely the number I have in front of me. Once Inmaculada went into production, capacity stood at 3,500 tonnes, and we hit 3,350, 10%. So we think we can clear all of those bottlenecks and aim for something comparable. That said, we aren't chasing additional output. In other words, capacity is capacity.

Analyst

analyst
#58

That's excellent. Now the final item ties back to what Richard raised. Personally speaking, growth will always be my preference over a dividend, so I felt no disappointment whatsoever that you deferred the div and discussed paying down debt, since that creates far more value. But on the reasoning — and clearly it isn't only your own reasoning, it's the Board's as well — you sit inside that 0.5 to 1.5 net debt to EBITDA band. Do you treat the surplus cash as the floor — once you hit the bottom of that band, is that where you feel quite comfortable, given the div, and bearing in mind you still have further growth opportunities? I mean, there's San Jose, which you've mentioned, there's Monte Do Carmo, which appears phenomenal though it's very early days, and you still have Pine Cotton and so on. So plenty of growth opportunities. With that in mind, I'd have expected surplus cash to mean roughly the low end of that band rather than the midpoint. Is that roughly correct?

Eduardo Noriega

executive
#59

Thanks, Tim, for that question. We don’t have a specific — we’ve set that range so the Board has some flexibility in deciding when to define it, taking into account the opportunities that we — the growth opportunities ahead of us, but also where the market and our operations stand at that time. So we’d like to keep that flexibility. I should say that if you look at the dividends we’ve paid historically, those amounts won’t stop us from also carrying out our growth strategy. So I think we like having that flexibility. And we’re also working on having a more robust framework for capital returns going forward. So we’re thinking about it, and we’d like — but we’d like to retain some flexibility, which I think matters for a mining company.

Analyst

analyst
#60

All right. Given that you're looking at putting a stronger capital allocation and capital return strategy in place down the road, my own preference would be to see M&A come before capital returns — not capital returns come before M&A.

Eduardo Landin

executive
#61

Thanks. We'll keep that in mind.

Patrick Jones

analyst
#62

Patrick Jones from JPMorgan here. I have a quick question about reserves and resources. Clearly, that largely reflects the decrease from production over the year, given the delay in the exploration and drilling program. Could you talk about when you think we might get a bit more of an update on that? Do you think you could provide something, say, alongside the H1 results, so there are a few more resources at Inmaculada, et cetera? And then second, on the Argentina side, since you're planning to spend a little more there at San Jose with that possible expansion, do you think there's any further opportunity to ramp up exploration in the vicinity of San Jose as well?

Eduardo Noriega

executive
#63

All right. Let’s take the first question, on resources.

Eduardo Landin

executive
#64

Yeah, regarding resources, we're kicking off exploration programs across all the mines, as Eduardo mentioned. And drilling is already underway. So at this moment, we're actively drilling. It depends on how far along each site is, but around the half-year mark, we may be able to share some update on where things stand. What I can say is that results from the drilling campaign have been excellent up to now. So yes, we do hold expectations for our brownfield exploration plans. And hopefully, we'll be able to give you more updates soon.

Eduardo Noriega

executive
#65

Then, regarding your question about Argentina: yes, drilling is underway there. We're actually drilling in the southern section of the property, and we do have expectations. As I mentioned in my earlier response, the capital return — sorry, the payback on the investments we'll make in Argentina will be short, so under a year. And I think that's a positive for the projects we're evaluating.

Eduardo Landin

executive
#66

I mean, we hold a really large land position in San Jose. I mean, San Jose is here, and then there's Cerro Negro, the Newmont operation. The two are roughly 30 kilometers apart from one another. Between these 2, we have quite a few mining properties. And we're drilling on a property that sits south of Cerro Negro, which is believed to be the extension of the Cerro Negro veins. So right now we're drilling there. And I mean, we'd expect to have results, probably, around the middle of the year.

Yuan Low

analyst
#67

Yohan from Liberum here. I just wanted to ask about Royropata and its IRR. Which commodity prices did you assume? And can you say what the post-tax IRR would be?

Eduardo Noriega

executive
#68

Are you referring to Royropata or Mara Rosa?

Analyst

analyst
#69

Thank you, and hello, Royropata.

Eduardo Noriega

executive
#70

For every project we have, we generally reference the analyst consensus prices. And I believe we've mentioned that the minimum IRR we demand is 15%. So when assessing each of our projects, we factor that in.

Analyst

analyst
#71

Is that 15% before taxes or after?

Eduardo Noriega

executive
#72

After tax.

Eduardo Landin

executive
#73

All right, no further questions. Anyone else? Well, thanks so much for joining us today. We'll catch up again at any meetings here in London. Thanks a lot. Thank you. Bye.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Hochschild Mining plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Hochschild Mining plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hochschild Mining plc or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.