Hydro One Limited (H) Earnings Call Transcript & Summary
August 9, 2023
Earnings Call Speaker Segments
Operator
operatorGood morning, everyone, and thank you for joining Hydro One Limited's analyst teleconference for the second quarter of 2023. <<operator_script>> Just a reminder that this call is being recorded. At this point I'd like to hand things over to your host for today, Mr. Omar Javed, Vice President, Communications, Marketing and Investor Relations at Hydro One. Please go ahead.
Omar Javed
executiveGood morning, and thank you for being with us on Hydro One's quarterly earnings call. With us today are our President and CEO, David Lebeter, and our Chief Financial and Regulatory Officer, Chris Lopez. During this call, we'll review the quarterly results and then devote most of our time to answering as many of your questions as time allows. There are also a number of slides that illustrate some of the points we'll address shortly. Those should be up on the webcast now, or if you're dialled into the call, you can find them as well on Hydro One's website in the Investor Relations section under events and presentations. Today's discussions will likely touch on estimates and other forward-looking information. You should review the cautionary language in today's earnings release and our MD&A, which we filed this morning, regarding the various factors, assumptions and risks that could all cause our actual results to differ as they all apply to this call. With that, I'll turn the call over to our President and CEO, David Lebeter.
David Lebeter
executiveThanks, Omar. Good morning, everyone, and thanks for being with us on our second-quarter earnings call. This morning I'll give you an update on what we've been up to lately, and after that Chris will walk you through the Q2 financial results. I'm happy to say our teams are doing a great job moving our capital program forward, and we've hit a number of important milestones since the last call. The money we're putting into monetizing and growing the grid is playing a key part in speeding up adoption of sustainable electricity solutions that will help drive Ontario's economic growth. At the same time, we keep pushing ahead with reconciliation work alongside our First Nations Partners, making sure they share in the growth we expect. A couple of strong project execution, our commitment to sustainability, namely people, planet and community and our focus on delivering unparalleled service to our customers. It comes as no surprise that we're still the transmitter of choice for the province of Ontario. Now to recent achievements: first, on July 31st, we filed our leave to construct application, otherwise known as a Section 92, for the Waasigan Transmission line. As we mentioned on last quarter's call, Phase 1 of the Waasigan Transmission line is a double circuit 230 kilovolt transmission line from Thunder Bay, Atikokan which is expected to be in service by the end of 2025.
David Lebeter
executivePhase 2 consists of one 230 KV transmission circuit running between Atikokan and Dryden, and it is scheduled to enter service by the close of 2027. Through Waasigan, an extra 350 megawatts of electricity will reach the region — greater than double the amount needed to supply the city of Thunder Bay. I feel good about what our teams have done and the dedication that brought us here. I also wish to recognize and express gratitude to our First Nations Partners, who backed the application and the project. Across both phases, the expected infrastructure investment comes to roughly $1.2 billion. Hydro One takes pride in co-investing alongside our First Nations Partners in the Ontario Grid, which will benefit Ontario's economy. After construction, the Waasigan Transmission line project will deliver clean, reliable electricity to northwest Ontario, satisfying forecasted energy demands there while fostering economic growth, job creation and mining operations. Nine First Nations in the region are partnering on this project, and when it is complete they will have the chance to invest in owning as much as 50% of the transmission line component.
David Lebeter
executiveNext, we've begun construction on the Chatham-by-Lake-Shore line, and once finished, it will deliver clean power supporting expansion in the agri-food and manufacturing sectors across Southwestern Ontario. That line contributes roughly 400 megawatts of clean electricity to the area — sufficient to power a municipality the size of Windsor. Completion of this $268 million project is targeted for the close of 2025. Third, following a comprehensive review of multiple routes, we unveiled the preferred route for the St. Clair Transmission line. This line is set to stretch from close to Sarnia <<inaudible>> down to Chatham, with a goal of finishing in 2028. Beyond technical and cost benefits, the chosen route minimizes effects on the natural environment, biodiversity, Indigenous values, landowners and agricultural operations. Existing transmission corridors account for 80% of the route, and it upgrades a transmission line already in place. These milestones represent a vital part of our ongoing growth, and while seeking further growth opportunities, I was glad to witness the province's dedication to economic development and energy transition as laid out in its Powering Ontario's Growth Plan. That plan sets out backing for essential transmission infrastructure over the years ahead, giving Hydro One further growth opportunities.
David Lebeter
executiveUnder the plan, the government put forward giving priority in the regulatory approval process to 3 transmission lines located in North, Eastern and Eastern Ontario. That way, those projects can swiftly serve the region's fast-growing demand. The ministry also suggested naming Hydro One as a transmitter so it can carry out the development work and obtain every approval required to build these priority projects. I have no doubt the government's trust in Hydro One stems from how we have executed and from our continuing work with First Nations communities in support of reconciliation. Not one bit of this progress would be achievable without the devoted staff of the Hydro One family. The people who work here are the heartbeat of our organization, and we acknowledge the invaluable contributions they make to our success. I am glad to say that we have reached tentative settlements on 2 collective agreements — the main collective agreement and the customer service operations agreement — with the Power Workers Union. These agreements cover employees in frontline and customer facing roles throughout the company's operations. I want to thank the respective teams for negotiating in good faith toward an agreement that satisfied the needs of employees, customers and Hydro One. Out of respect for the bargaining process between the teams, we will not comment on the specifics of the agreement until the Power Workers Union has ratified it.
David Lebeter
executiveTalks with the Society of United Professionals are still underway, and both sides are working toward getting a deal done. As usual in a bargaining process, we won’t be offering any additional remarks about it. Earlier today, we published our newest sustainability report, which covers three priority areas: people, planet and community. Those areas show how we’re committed to doing business responsibly and energizing life for all Ontarians, while keeping our focus on delivering a sustainable future. In the people section, we put priority on employee safety, health and well-being, and on offering a welcoming, inclusive, equitable workplace where each employee can thrive professionally and personally. Nothing matters more than making sure our people get home safely. This year, we are on track to equal our lowest ever recordable injury frequency — 0.62 per 200,000 hours worked — which was achieved in 2022. Still, we know more work remains before we reach a workplace with no life-altering injuries and no fatalities. We also highlight our continuing efforts to advance diversity, equity and inclusion across our organization. We’re building an inclusive workplace where diverse perspectives flourish and allow us to, one, better understand and serve the needs of our varied customer base, two, innovate, and three, keep finding and putting into practice efficiency improvements. Although we continue to surpass our targets for gender diversity at both the board and executive levels, we have not yet fulfilled our commitments to the Black North Initiative.
David Lebeter
executiveWe keep working to eliminate biases and obstacles in how we hire and select people. We do this through educational sessions on anti-Black racism and on diversity, equity and inclusion, along with foundational trainings. Still, there is more work ahead of us. The Planet section of our report lays out our comprehensive approach to environmental stewardship. It describes the efforts and the work involved in building, operating, and maintaining a grid that is resilient and can reliably serve the needs of Ontarians today and for generations to come. That grid has to be environmentally sustainable and able to adapt to future, worsening climatic change impacts. We keep making progress toward our goal of achieving net zero greenhouse gas, or GHC, emissions by 2050 and 30% GHC reduction by 2030. Our GHC reduction figures from last year were rebased to account for new Canadian industry guidelines. As a result, 2021's reduction from a 2018 base year, which was reported last year, was recalculated from 9% to 4%. Using the same guidelines, at the end of 2022, we had reduced GHC emissions by 7% compared to 2018. After a slow start in 2021, due to vehicle availability, we converted 17% of our fleet of SUVs and Sedans to Electric Vehicles or Hybrids at the end of 2022.
David Lebeter
executiveOur expectation remains that half of our fleet will be converted to EVs or hybrids by 2025, and all of it by 2030. In the community portion of our report, we emphasize how committed we are to acting as a responsible corporate citizen. Our success, we believe, is tightly connected to the health of the communities we serve. Because of that, we put substantial investment into a range of social and philanthropic efforts that empower and lift up communities. With focused programs, charitable giving, and partnerships, we work to create a positive and enduring difference in the lives of our customers, neighbours, and partners. One major achievement in the last year was the introduction of the equity partnership model, which lets First Nations communities invest for 50% ownership in the transmission line portion of Hydro One's new-build transmission line projects exceeding $100 million. This distinctive milestone agreement leads the industry and represents a meaningful step toward reconciliation. I'm also proud to report that in 2022, we beat our targets for Indigenous procurement with our highest spend ever, and we likewise surpassed our targets for corporate donations and sponsorships to Indigenous communities. In the past quarter, storms and wildfires confronted us. As a utility that serves diverse geographies, we recognize the profound effect severe weather and natural disasters can have on our customers and communities.
David Lebeter
executiveAlthough wildfires haven’t caused us any major effects so far, our response crews stand ready to act—restoring electricity and health and delivering relief to people impacted. Our focus on readiness, early-warning systems, and substantial infrastructure spending lets us react quickly and effectively to the difficulties these severe events create. We’re extremely proud of how we handle these kinds of situations so that power comes back fast and efficiently for the communities we serve. Our work in disaster management goes well past bringing power back. We keep reviewing and drawing lessons from what we’ve been through, sharpening our procedures to strengthen our disaster-response abilities further. We aim not just to reduce outages during emergencies but also to help actively build communities that are more resilient. I’m pleased to report that Hydro One earned our 14th award from the Edison Electric Institute for outstanding storm-restoration work following Winter Storm Elliot. That honor shows our employees’ commitment and toughness, the strength of our disaster-management procedures, and the steady upgrades we’ve made to boost how we respond. Alongside that, Corporate Knights has again named us one of the best 50 citizens in Canada, citing our unwavering dedication to sustainability and environmental stewardship.
David Lebeter
executiveThis acknowledgment reflects how committed our teams are to advancing our sustainability efforts and putting the strongest practices into place across everything we do. These honors leave us both grateful and motivated. Such recognition reflects what our employees, partners, and stakeholders have accomplished together, and their contributions have mattered enormously to what we have achieved. Turning to another item, I am glad to report that three new board members were elected successfully. Brian Vaasjo, Helga Reidel and Mitch Panciuk, all at our annual general meeting of shareholders in early June. A board with strong experience and diversity, we believe, is vital for sound corporate governance and strategic decision making. Our new directors bring extensive experience across a range of industries, and their appointment makes our company's leadership even stronger. With that, I will hand things to Chris to cover our financial results for this quarter. Over to you, Chris.
Chris Lopez
executiveGood morning, everyone, and thank you for being with us today. I want to recognize the significant progress our team keeps making as we move our capital projects forward to secure a better, brighter future for all Ontarians. Filing the lease construct application for the Waasigan Transmission line was tremendous work that, once approved, will start another phase of continued economic growth for Northwestern Ontario and our First Nations Partners. I also want to recognize the efforts of our team members on the front lines who are watching the wildfire situation very closely. They are taking proactive steps to protect our infrastructure and stand ready to support our customers. Turning to our financial results for the second quarter, basic earnings per share came in at $0.44 compared with $0.43 in 2022. The main drivers behind the change in earnings this quarter were adjustments to OEB-approved rates for transmission following approval of the joint rate application, or JRAP, higher energy consumption in distribution, and lower depreciation, amortization, and asset removal costs, mainly due to fewer asset removals, resulting from fewer storm-related asset replacements. These were partly offset by higher operating, maintenance, and administration, or OM&A costs, mainly resulting from higher corporate support costs and work program expenditures, as well as higher financing charges attributable to higher weighted average interest rates on long-term and short-term debt.
Chris Lopez
executiveFor the second quarter, our revenue net of purchase power rose 7.2% compared with a year earlier. Transmission revenues were up 8.3%, mostly because of greater revenues stemming from rates approved by the OEB, including recovery of regulatory assets after the joint rate application decision took effect. Those regulatory asset recoveries were offset in OM&A and income taxes, so they had no net income effect. Partly countering the higher revenues was a decline in average monthly peak demand of 1.2%. Distribution revenues net of purchase power grew 5.4%, largely on greater revenues from recovery of regulatory assets — which, as noted, are net income neutral — along with a 0.8% rise in energy consumption by Hydro One customers. Turning to costs, operating, maintenance, and administration expenses were up roughly 17.5% year-over-year. That increase might look big, but it comes mainly from items that will either be offset later in the year or are net income neutral. The biggest factor was higher corporate support costs across both segments, chiefly from lower capitalised overheads. As we mentioned on last quarter's call, these costs went up because we capitalised common costs at a lower rate, reflecting the timing and volume of capital work relative to the remainder of the year.
Chris Lopez
executiveWith the capital program ramping up in the back half of the year, we expect to capitalize common costs at a higher rate, which will substantially offset the corporate support cost increases we incurred in the first two quarters. The next impact of both segments was higher expenses tied to the recovery of regulatory assets that, as discussed earlier, are net income neutral since they are fully recovered in revenues. Beyond these costs, we had higher work program expenditures, including vegetation management, station maintenance, information technology initiatives, and emergency restoration. Recall that we had higher capitalized storm costs last year that favorably impacted O&MA. Finally, these O&MA expenses were partially offset by a lower allowance for doubtful accounts, stemming from the macroeconomic issues over the past couple of years. Depreciation expense was lower year-over-year by 4.3%, primarily due to lower asset removal costs resulting from fewer storm-related asset replacements. As a reminder, with fewer significant storms experienced in the quarter, we saw a lower level of storm costs capitalized compared to the same period a year ago. Partially offsetting these amounts was an increase in depreciation amortization due to the growth in capital assets, which is consistent with our stated capital investment program.
Chris Lopez
executiveRegarding financing, our financing charges rose 21% compared with a year earlier. The main driver is increased weighted average interest rates on long-term debt and short-term notes. Those financing charges stem from issuances and refinancings across the past two quarters, among them the $1.5 billion <<inaudible>> inaugural medium-term notes issuance in the first quarter under the Sustainable Financing Framework, the refinancing of short-term notes, and long-term debt repayment. We remain pleased with how stable our balance sheet is and with our robust investment grade credit ratings. Income tax expense came to $65 million for the quarter, versus $68 million in the comparable quarter a year ago. The decline in income tax expense reflected higher deductible timing differences, partly offset by higher earnings and the tax on the disposition of the regulatory accounts, which, as discussed, is net income neutral. For the quarter, the effective tax rate was 19.6%, compared with 20.9% a year earlier. That aligns with the annual guidance given earlier this year. As a reminder, we expect an effective tax rate of 13% to 16% across the next five years. Note that the deferred tax asset, or DTA, amounts shared previously were fully recovered as of the end of June.
Chris Lopez
executiveNow turning to what we spent on investing activities. During the second quarter, we put $413 million of assets into service, and that represents a 24.5% decline relative to the same period a year earlier. In the transmission segment, the drop was mainly tied to when investments were placed into service, partly offset by a greater amount of work on replacing wood poles. In the distribution segment, the decline was mainly tied to fewer storm-related asset replacements, partly offset by a greater amount of work on dusted connections, line refurbishments and wood pole replacements. Our capital investments came to $649 million in the second quarter, up 6% from the second quarter of 2022. The transmission segment recorded larger capital investments tied to the new channel intellectual and Waasigan Transmission line projects, along with more station refurbishments and equipment replacements. Capital investments in the distribution segment fell because of lower spending on storm-related asset replacements, partly offset by the timing of work on system capability reinforcement projects, a greater amount of work on customer connections, a greater amount of externally driven work attributable to joint use assets and line relocations, and a greater amount of line refurbishments and wood pole replacements. Given the recent announcement about filing the lead to construct application for the Waasigan Transmission line, we have updated the future capital investments table, which lays out the regional and system growth outlook, so that it accounts for the $1.2 billion of expected capital investment in this line.
Chris Lopez
executiveThe capital is going to come in 2 phases: we expect phase 1 to wrap up by the end of 2025, and phase 2 to arrive by the end of 2027. Just to remind everyone, those capital investment and rate-based figures for future years are still subject to OEB approval. Also, the table leaves out any future investments tied to the three Northeastern and Eastern lines that David mentioned earlier today. As we said on our last conference call, we're still working alongside internet service providers to bring broadband internet access through the infrastructure we already have. Our ecosystem is ready to take on the work volume we anticipate from this initiative. That said, progress on the initiative is still slower than we'd expected, though we're standing by and ready to help bring connectivity to families and businesses across Ontario. We're also still engaging with local distribution companies, or LDCs, to help facilitate consolidation in the sector. We're in active talks with several LDCs, but so far there are no definitive agreements. Turning to guidance, we remain committed to our target of 5% to 7% earnings per share growth through 2027 on the normalised 2022 EPS of $1.61, and we affirm it.
Chris Lopez
executiveJust to remind everyone, that EPS growth range excludes contributions from broadband, from LDC consolidation, and from the transmission lines already awarded that currently carry only preliminary estimates or await approval — the Waasigan Transmission line being one example — along with any amounts arising from externally driven variance accounts. Lastly, I'm happy to share that we declared a dividend for common shareholders of $0.2964 per share. That's all from me, and we'll be glad to take your questions.
Omar Javed
executiveThanks, David and Chris. We’ve asked the operator to describe how she would like to run the Q&A polling process. If we aren’t able to get to your questions today, my team and I are always available to answer follow-up questions. Please keep your questions to one question and one follow-up. If you have more questions, please rejoin the queue. Go ahead, operator.
Operator
operatorThanks. <<operator_script>> We'll start with a question from Ben Pham at BMO. Your line is open now.
Ben Pham
analystHello there, and thanks — good morning. I'd like to begin, perhaps, with those critical infrastructure projects, which are once again being added to the CapEx plan. Could you comment on what debt financing your balance sheet will need next through 2024 given this CapEx, and then on how that affects guidance along with EPS growth rates?
Chris Lopez
executiveHi Ben, this is Chris Lopez, and I appreciate the question. Let me begin with how the financing plan factors in. It falls inside the financing guidance we've given before. Keep in mind that we're working in partnership with First Nations. That does mean that as we proceed, they will take on their portion of the equity investment. So that's the first piece of the financing. We will handle financing while construction is underway, and that's what we'll do. Even so, it doesn't affect our capacity to finance it. If that's what you're asking in light of today's announcement, there's no equity requirement. As for EPS guidance, we'll stick with standard practice, which means we update capital guidance at filing once it's approved, Section 92, and we anticipate that within the next six months. It might land before year-end or a bit after. At that point we would update EPS guidance if warranted. What I can say is that we previously issued five to seven. This would move us nearer to the upper end of that range, though we'd need to work through that guidance before making any change.
Ben Pham
analystAll right, that’s excellent. Could you also comment on First Nations—perhaps more specifically on the process, and on whether the injection from them is weighted more toward the back end in terms of the construction cycle?
Chris Lopez
executiveYes, Ben. At Hydro One, we take care of construction, and the point at which the asset enters service is when First Nations would put in their equity share of that investment. On this particular project, the split works out to approximately 60% Hydro One and 40% First Nations. The line component is 50:50, but there are also further investments related to stations, and those are Hydro One investments.
Ben Pham
analystUnderstood. All right, thanks.
Operator
operatorThanks. The next question is from Maurice Choi at RBC Capital Markets. Your line is open now.
Maurice Choy
analystAppreciate it, and good morning. I'd like to briefly address the LDC consolidation. Chris, you noted that as of now there aren't any definitive agreements to announce. My understanding is that tax incentives came in, perhaps back in 2015, which include a lower tax rate on transfers, and possibly an exemption on capital gains when one exits the payments in lieu of corporate tax regime. Since these incentives are scheduled to lapse at the end of next year, do you think sellers could be more inclined to transact, or do such incentives carry less weight?
Chris Lopez
executiveHey Maurice, it’s Chris. I believe those incentives are beneficial. My expectation is that they could be extended too. But let me speak more broadly about what we’re seeing in terms of activity. Municipal elections took place last October. Things began somewhat slowly. We’ve observed more activity and more conversations with different councils and LDCs directly about what possible opportunities could look like. So activity has picked up. As I mentioned in my remarks, there are no definitive agreements. I would anticipate that the incentives currently offered for consolidation will be looked at for extension. Consolidation remains the right approach for Ontario.
Maurice Choy
analystThanks. And to wrap up, I’ll ask something a bit broader. You clearly will have seen that yesterday the federal government released a vision document titled Powering Canada Forward. Do you have any general thoughts on that document, on what it means for Ontario and even for Hydro One?
David Lebeter
executiveMorning, Maurice — David Lebeter here. I think that document is genuinely an excellent piece, a strong announcement, since what it accomplishes is showing that the government remains committed to developing a clean electricity system in Canada by 2035. It acknowledges the distinct roles that provinces, territories, and the federal government each play in getting there. And it sets out a path forward for how the federal government will keep working with provincial governments to make this happen and to keep funding the energy transition as part of the tax base. So it's a good document that points us in the right direction, and I look forward to the clean energy regulations coming out later on.
Maurice Choy
analystAnd maybe just to follow up quickly on that, is it your interpretation that the federal funding is somewhat linked or tied to the provinces' climate goals, or is your view of how ITCs might be received unchanged even, say, before this document came out?
David Lebeter
executiveRight, I can’t really give you a read on that yet. Maurice, that’s a matter we’ll simply have to hold off on until we see what gets announced going forward and how each of those announcements actually ends up being put into effect.
Maurice Choy
analystThat’s great—thanks so much.
Operator
operatorThanks. Linda Ezergailis from TD Securities has the next question. Your line is open now.
Linda Ezergailis
analystThanks. I'd like to ask something further about the Waasigan line. Could you split the $1.2 billion between phase 1 and phase 2? Also, does construction on phase 2 begin in 2025, or after 2025?
Chris Lopez
executiveHey Linda, this is Chris. That figure appears in the Section 92 application, but let me give you a quick summary. We expect Phase 1 to come in at roughly $700 million, with it entering service near the end of 2025. My expectation is that Phase 1 and Phase 2 will proceed together. They won't kick off at precisely the same moment, but the work will move forward in tandem. Phase 2 accounts for $500 million, which makes up the remainder of the $1.2 billion, and it will enter service in 2027.
Linda Ezergailis
analystThat's useful, thanks. Next, on the St. Clair Transmission line that's been proposed, you've offered a 50% equity stake as well. Would that too be a 60:40 split, and the same question for the Chatham to Lakeshore transmission line when it comes to First Nations participation?
David Lebeter
executiveMorning, Linda. Each line differs somewhat, since it hinges on which transmission stations the mix calls for and how long the line runs. So no details are being put out on that right now. You'll need to hold off until we file the Section 92, which is the point when the detailed engineering gets underway. We do have a final cost estimate, broken down across the project's various aspects.
Linda Ezergailis
analystAll right, thanks. And one brief follow-up regarding your broadband initiative — I understand it’s ramping more slowly. Are you receiving additional feedback or insight into what’s driving that lag, and are you reconsidering your offering in order to generate some momentum, or could you update us on how you’re thinking about it?
David Lebeter
executiveLinda, you've got that exactly right. The ramp-up has been slower than our forecast, though it is beginning to gain traction. Our partnerships with the various government ministries involved are very strong, and in addition we're holding really productive talks with internet service providers. Together we've cleared away a great many of the concerns that were raised — in fact, every concern raised has now been resolved — and we keep searching for ways to simplify the project and accelerate it. So while things haven't moved as fast as we'd have wanted at this stage, we stay optimistic and dedicated to delivering by the end of 2025.
Linda Ezergailis
analystThanks a lot — I really appreciate it.
Operator
operatorThanks. Mark Jarvi from CIBC has the next question. Your line is open now.
Mark Jarvi
analystMorning, everyone — thanks for joining. Could you remind us once more what the authorized ROEs will be for the transmission lines once they're approved? Would those be tied to the existing one under the JRAP, or does each year's approval set them according to the newly updated cost of capital parameters?
Chris Lopez
executiveHi, Mark. This is Chris. Yes, that depends on which year the asset is approved. So for Waasigan's Phase 1, the prevailing rates will be used. The application goes in during 2025, so the rates in effect at the close of 2024 are the ones that will apply. Then for Phase 2, it will be the prevailing rates as of the end of 2026, and those will apply to 2027.
Mark Jarvi
analystUnderstood. And when you return for the following multi-year cycle in the transmission business, does that then get folded back in?
Chris Lopez
executiveNo, those are going to be filed separately, since this falls under a different agreement. So the applications will probably run for five years, and at the close of each cycle they'll be renewed at whatever rate applies then.
Mark Jarvi
analystAll right. So when we look at some of the big projects throughout North America — phase cost overruns, labour markets being tight — what’s the process, or I guess the mechanism, if cost overruns do come up, whether from labour or any other cause, on those major projects? Is there a route to fully recovering any additional proven cost? Basically, how well protected are you when it comes to any cost pressures?
David Lebeter
executiveHey Mark, David — those are great questions. So clearly we're in an inflationary stretch the likes of which we hadn't seen for some time. Materials are in tight supply, and that can put upward pressure on projects too. Take the Waasigan Transmission line. You file your Section 92 4 with the OEB, and they'll examine how prudent your costs are. They'll ask whether this is a reasonable cost estimate for the project. Then, assuming they determine it's reasonable, they'd go ahead and approve it. As construction proceeds, we as the constructor will do everything possible to stay inside that budget, and in cases where there are legitimate reasons we can't stay inside it, we document them. We perform a very thorough review of what else might have been done to keep that from happening. Then, once the project is complete and has gone into service, we return to the OEB and take them through actual cost versus budgeted cost. That's when the OEB determines whether your costs were prudent after the fact. So ultimately it comes down to showing due diligence.
David Lebeter
executiveYou’ve taken every possible step to keep operations within the current budget and to show that the higher costs are justified and outside your control.
Mark Jarvi
analystAnd is it possible to accomplish that quickly enough? There's no need to hold off until the following five-year rate cycle comes around before raising any costs?
David Lebeter
executiveNo, that occurs separately once the project wraps up, and Hydro One's record is really solid. I don't think a cost disallowance has ever come our way. I can see folks nodding in the room.
Chris Lopez
executiveMark, to give you one illustration, Mark: Phase 1 will be placed into service during 2025. The OEB will approve the actual expense of bringing it into service at that time. Accordingly, whatever revision occurs to the estimate will receive approval at that moment.
Mark Jarvi
analystAlright, then. Thank you, Chris. And thank you, David.
Operator
operatorMuch appreciated. <<operator_script>> We now go to Robert Hope of Scotiabank for the following question. Your line is open at this time.
Robert Hope
analystMorning, everyone. I just have a quick follow-up question about the broadband initiatives. I appreciate the commentary that it's ramping up slower than expected. When you look at the issues — sorry — could you maybe give a little more color on what's slowing it down, as well as the fact that the ISPs have a lot going on right now? Is there a potential that we could see this bleed beyond 2025?
David Lebeter
executiveRobert, this is David. Honestly, I don’t see this extending past 2025. Every government ministry involved — the Ministry of Energy, the Ministry of Infrastructure, us, and the ISPs — is dedicated to finishing by 2025. A great deal of effort has taken place behind the scenes. For our part, we made the joint use application process more efficient. We set up a warehouse devoted specifically to joint use. We bought inventory of raw materials, since we recognize the need to keep that moving. We revised the standards so Ontario has consistency throughout. We’ve collaborated tightly with the Electrical Safety Authority to confirm those standards line up. And the ISPs, the Internet Service Providers, have stayed with us throughout this journey. So together, whenever we found something that could make the process run more smoothly or be completed more efficiently, those items were dealt with and cleared away. So there isn’t one specific problem that stands out. It’s simply that plenty of work must be completed, plenty of process that had to be — or plenty of preliminary work before shovels go into the ground. As I mentioned, I believe we’re getting there — we’re watching it begin to ramp up.
David Lebeter
executiveThe pace isn't what we'd hoped for, yet we've watched it scale, and our commitment to 2025 stands, just as it does with every other partner.
Robert Hope
analystOkay, great. As a follow-up, you pointed out several transmission lines that aren’t included yet in your capital outlook or guidance. How are conversations with the market authorities progressing regarding the next batch of transmission projects? And when do you anticipate having visibility into those that aren’t in guidance right now, along with the following tier of transmission projects?
David Lebeter
executiveRobert, I take it you mean the three that came out as part of the Powering Ontario's Growth Plan?
Robert Hope
analystCorrect.
David Lebeter
executiveRight. We're still having really productive talks with the government about that. Their proposed approach has our backing — a comment period so that every interested vendor, or rather every interested proponent, can give feedback. That runs through September 8th. We feel optimistic that we'll be named a developer for those projects, though I'd say the government has taken a quite sensible path on how to proceed.
Robert Hope
analystI appreciate that.
Operator
operatorThanks. Andrew Kuske from Credit Suisse has the next question. Your line is open now.
Andrew Kuske
analystThank you. Good morning. Perhaps we could return to the topic of municipal consolidations. The Ontario Energy Board is currently in the process of starting a review of the policy on consolidations. So clearly, you're able to keep having discussions with the munis, but how do you expect that to affect any potential consolidation efforts you might be involved in?
David Lebeter
executiveAndrew, that's a genuinely fascinating question. From an economic standpoint, merging utilities is highly logical for Ontario. That point has been thoroughly demonstrated. Every municipality has its own particular set of motivations for whether it wishes to go ahead and sell off those assets or hold onto them. So what you're partly requesting is that we guess at what their motivations could be, and that is genuinely difficult to do. As I see it, what the regulatory framework is exploring is how to simplify the procedure, make it more efficient, and how to cut red tape. So in cases where municipalities want to divest their local distribution company and a buyer is willing, that process can proceed rapidly and with a reasonable level of certainty. I believe that is truly where their attention will be directed.
Andrew Kuske
analystThanks for that, Color. And then, perhaps somewhat tied to possible consolidation, there's the question of the IT spending you saw this quarter. You had a modest uptick in OM&A. You mentioned IT as one of the contributing factors. Clearly, that's an area where a consolidation effort can deliver scale. Maybe you could walk us through a bit of a breakdown — how much went to cyber, and how much was perhaps tied to big data and AI, to sharpen decision-making going forward as you expand the grid and distribution efforts grow more dynamic?
Chris Lopez
executiveYes, that's a fair question, Andrew. We're not going to give you details on the spending. What I can say is that it's the smallest piece of that group, and that's exactly why it's listed in that position. We keep investing steadily in our IT platforms, cybersecurity among them, and that leaves us well positioned for consolidation. So we're aware the OEBs took a specific look at cybersecurity and at how LDCs throughout Ontario will compare over time. We believe we're leading on that front, and we'll keep investing to stay there.
Andrew Kuske
analystAll right, that added detail is helpful. Thanks.
Operator
operatorThanks. We now take our final question from Patrick Kenny at National Bank. Your line is open.
Patrick Kenny
analystYes, good morning. I was hoping you could give us something of a real-time update on how things look for affordability in Ontario, especially since we've noticed that some other provinces and jurisdictions have scaled back or paused particular infrastructure investments, whether that's T&D or generation. I'm aware that significant progress was achieved on overall customer bills a few years back, but I'd just like to hear your perspective on how you might be positioned in Ontario compared with other regions.
David Lebeter
executiveYeah, thanks for that question, Patrick. A few things come to mind. First, in many of those other jurisdictions where you've seen pullback, it's because they had commodity exposure to the natural resource — to the resources they use for generating electricity. Ontario didn't experience any of that, because largely nuclear followed by hydro and renewable, so it didn't suffer that same spike up in natural gas prices that you saw elsewhere that translated into very high energy costs. That'd be the first thought I'd make about that. The provincial government has remained committed to capping the increase on electricity bills to the rate of inflation, recognizing, I believe, that the energy transition is a multi-generational journey that we need to go on and that there's a role for the taxpayer to play in transitioning through that journey. So you've seen steadfast commitment from the Ontario government to cap those rates to the rate of inflation and support residents and businesses of Ontario as we go through this transition. And I think with the latest report that came out, the Pathways of Powering Canada Forward, you've seen the federal government step up looking for other options that they can help contribute to financing this transition as well.
David Lebeter
executiveAnd actually, you’re beginning to see proof at this point that after we complete the transition, a consumer’s overall energy bill could end up being lower once this is behind us, after adjusting for inflation. So some genuinely positive developments are beginning to appear on the horizon, and more and more you’re hearing discussion about affordability. How do we ensure this advances at a pace that consumers find acceptable and keeps energy affordable for every consumer.
Patrick Kenny
analystAll right, that's excellent, thank you. And perhaps a brief follow-up question for Chris. Now that you have six months of earnings behind you, how is the year shaping up regarding the excess earnings portion compared with historical performance, and what could that mean for some of your FFO to debt metric targets in relation to the rating agencies? Thanks.
Chris Lopez
executiveOur long-term guidance is in that 5% to 7% range. So the actual figure came in at 6%. As a reminder, when we established that target at the start of this year, we set it at 100 basis points above it. So we're on track with that. On that specific point, we'll hit the goal we intended for this year. How does that flow through to FFO? FFO has declined somewhat this year, really because of shifts in regulatory accounts. And the other factor would be the deferred tax asset. As a reminder, we finished recovering that deferred tax asset through rates here in June. So we've recovered roughly $260 million across the last 24 months. And that concludes here in June. So you'll see FFO come down somewhat, but there's still ample financial flexibility to fund the growth we've included in this plan.
Patrick Kenny
analystI appreciate that a lot.
Operator
operatorThanks. We’ve got another question, this one coming from David Quezada at Raymond James. Your line is open now.
David Quezada
analystThanks. Good morning, everyone. I’ve just got one more question for you. It seems as though this has been a fairly busy wildfire season in Ontario, so I’m wondering whether that has any impact on how you plan routes from a transmission standpoint, or possibly on costs. Do you think there’s a chance that this could influence your costs going forward?
David Lebeter
executiveMorning, Raymond. The first thing I’d note is that Ontario’s fire season has been somewhat busier than the 10-year average, though definitely not on the scale of what’s been happening out west in B.C. and Alberta. To get more specific about your question on how this affects our transmission as we head into fire season: every year we follow certain standard procedures to ensure everyone is properly trained on working in fire houses. We make sure we’ve got the right equipment. We coordinate with the various government officials so we understand any concerns they may have, and then we keep an active watch on the fire season. And we do adjust our work plans and our work schedule according to the fire conditions and the particular area where the crews are working. This year, even with the overall increase in fire activity, the fire hazard hasn’t been severe enough to have any impact. But this is just normal course of business for us. We monitor it and we make adjustments as per the particular conditions. So no impact.
David Quezada
analystThat’s great—thank you very much.
Operator
operatorThanks. That brings our question-and-answer portion to a close for today. I'll now hand things back to Omar Javed in case he has any closing comments.
Omar Javed
executiveThanks, Shannon. Everyone on the Hydro One management team appreciates all of you spending part of your morning with us, especially since this is such a busy stretch. We're grateful for your interest and for your ownership. Should anything come up that we didn't get to during the call, don't hesitate to get in touch and we'll make sure you get answers. Thanks once more, and enjoy the rest of your day.
Operator
operatorLadies and gentlemen, we appreciate your joining us for today's call. That brings today's program to a close, so you're welcome to disconnect at this point. Have a wonderful day, everyone.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Hydro One Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Hydro One Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hydro One Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.