Hydro One Limited (H) Earnings Call Transcript & Summary

November 7, 2024

Toronto Stock Exchange CA Utilities Electric Utilities earnings 29 min

Earnings Call Speaker Segments

Operator

operator
#1

Morning, everyone, and thanks for joining the Hydro One Limited Third Quarter 2024 Analyst Teleconference. <<operator_script>> Just a reminder that this call is being recorded. At this point I'd like to hand things over to your host for today, Mr. Omar Javed, Vice President, Investor Relations at Hydro One. Go ahead, please.

Omar Javed

executive
#2

Good morning, everyone, and thanks for being with us on Hydro One's quarterly earnings call. Our President and CEO, David Lebeter, is here today, along with our Chief Financial and Regulatory Officer, Harry Taylor. During this call, we'll walk through an overview of the quarterly results, and afterward we'll spend some time taking questions as time allows. What we discuss today will probably include estimates and other forward-looking information. Please take a look at the cautionary language in today's earnings release and in our MD&A, both of which we filed this morning, covering the various factors, assumptions and risks that could cause our actual results to differ — all of which apply to this call as well. With that, I'll hand the call over to our President and CEO, David Lebeter.

David Lebeter

executive
#3

Thank you, Omar. Good morning, everyone, and thanks for being with us on our earnings call for the third quarter of 2024. I want to start by noting that National Indigenous Veterans Day in Canada falls tomorrow — a day set aside to recognize and honour the contributions and sacrifices of First Nations, Inuit and Métis soldiers who have served our country. Also, please keep in mind that this day is just a few days off. It is an occasion for all of us to come together in remembering and paying tribute to those who gave — and those who continue to give — in service to our country amid war, conflict and peace. It gives us a chance to stop and feel grateful for the freedoms we have today, which exist because of what others have sacrificed. I'd also like to pause briefly to think about the many conflicts happening around the globe. As developments play out worldwide, they can affect all of us deeply and profoundly. Hearing about innocent lives lost can feel overwhelming, and supporting each other matters greatly in such times. My support and sympathy go out to everyone impacted by these global events. Now, on to the quarter. This morning I'll walk you through an update on what we've been doing recently, and after that Harry will guide you through the financial results for the third quarter.

David Lebeter

executive
#4

When it comes to taking care of each other, I feel tremendous pride in the Hydro One crew members who stepped away from their families — including during Canadian Thanksgiving — to help with relief work after Hurricanes Helene and Milton. Our thoughts and prayers go out to our neighbors who were affected by those catastrophic events. In response, Hydro One dispatched 150 skilled employees to Georgia and Florida to bring power back. We take pride in answering the call when people are in need. Again and again, our teammates show that Hydro One is always there to care for others. That dedication to caring also showed during our annual Power to Give campaign. During September, Hydro One employees showed their generosity and community spirit by donating and contributing over 4,500 volunteer hours that month. That is a remarkable achievement, and it will make a meaningful difference for people in need across our communities. I could not be prouder of our employees' efforts and generosity — not just in September, but all year long. Giving back and supporting our communities is a core value of Hydro One's culture, and one our people live out daily. As I've said on previous calls, electricity demand in Ontario keeps growing.

David Lebeter

executive
#5

Population growth, the energy transition, and fresh manufacturing capacity—like the investments Stellantis, Volkswagen, and Honda are making—are what's driving this. That all translates into more economic growth across the Province. As a result, the Independent Electric System Operator, IESO, recently raised its forecast for energy demand out to 2050. IESO now projects electricity demand will rise 75% over the coming 25 years, up from the 60% it had forecast before. According to IESO's estimates, new large potential projects—data centers, electrification of commercial sector buildings, EV production and its supply chain—will contribute to that projected demand increase. To satisfy the higher electricity demand, work across the province is well underway: more generation is being built, new transmission lines are being built, new technologies are being integrated, and energy efficiency programs are being expanded. Hydro One is part of this growth and keeps playing a critical role in meeting the higher demand and supporting the province's electrification goals. Whether through our investments in transmission and distribution systems, connecting new generation and energy storage solutions, or applying new technology in our control systems, we are building a grid to power Ontario's future. Alongside industry and indigenous communities, we will ensure a reliable, resilient and sustainable energy system for our children and grandchildren.

David Lebeter

executive
#6

I'm pleased to share that our new transmission projects are still progressing. In the quarter, Hydro One obtained approval from the Ministry of Environment, Conservation and Parks regarding the final Environmental Assessment Report for the Waasigan Transmission Line. That green light opens the door for construction work to get underway, enabling shovels to hit the ground before year-end. The line's total expected investment stands at $1.2 billion, and it will deliver an additional 350 megawatts of electricity to the region, addressing present and future energy requirements of Ontario's Northwest communities. As a reminder, the line will be finished in two phases, with Phase 1 of the project aimed at being in service in 2025 and Phase 2 in service in 2027. Our Chatham to Lakeshore Transmission Line project, which started construction in the Spring of 2023, remains on track for completion by the end of 2024. Commissioning tests are going well, and we anticipate the line will be fully operational by year-end, finishing the project 1 year ahead of schedule and under budget, as previously disclosed. Once finished, the line will supply clean electricity to support growth in the agri-food and manufacturing industries as well as a growing population in Southwestern Ontario, adding 400 megawatts of clean electricity to the region.

David Lebeter

executive
#7

We're proud that Hydro One's equity partnership model means both the Waasigan and Chatham to Lakeshore Transmission Lines will be co-owned with nearby First Nations. We're also happy to share that our regulatory work has moved forward considerably. Settlements in principle are now in place for 3, 5-year revenue requirement applications covering three of our transmission partnerships: the Bruce-to-Milton Limited Partnership, the Niagara Reinforcement Limited Partnership and the Chatham to Lakeshore Limited Partnership. Working alongside the parties involved in the settlement conferences, Hydro One filed settlement agreements on October 21, 2024 with the Ontario Energy Board, or OEB, for the Bruce-to-Milton Limited Partnership and the Niagara Reinforcement Limited Partnership. Under those agreements, total revenue requirements came to $193 million for Bruce-to-Milton and $45 million for the Niagara Reinforcement across the 5-year period. The settlement proposals accepted the rate-making framework the partnerships put forward, including a modest 3% reduction in proposed OM&A expenses over that period plus an additional 0.15% stretch factor. As for the Chatham to Lakeshore Limited partnership, Hydro One has reached a settlement agreement in principle and expects to file this proposal with the OEB shortly. These settlement proposals back investment in our infrastructure so we can keep the system safe and reliable and meet our customers' needs, and they underscore the constructive regulatory framework in Ontario.

David Lebeter

executive
#8

These accomplishments represent meaningful progress for Hydro One and our First Nations partners. When approved, the proposed settlement will give the projects certainty on revenue and costs covering 2025 through 2029. We anticipate final approvals from the OEB by year-end. On a separate note, late in October the OEB issued its cost of capital parameter for 2025. A deemed ROE, updated by formula to 9.25%, will serve as the applicable rate under these settlement agreements. That rate stays fixed throughout the rate period. Turning to other news, I'm glad that our solid work and shared efforts keep getting noticed by others. Newsweek has just named us one of Canada's most responsible Companies for 2025. That list honors companies spanning 13 industries for their dedication to climate, social welfare and responsible governance. This recognition speaks to the hard work and commitment of our whole team in making a positive difference for our communities and the environment. Hydro One is committed to responsible business practices that balance sustainability, social responsibility and governance. We approach corporate responsibility holistically, considering how these matters are woven deeply into our business. Through what we do, Hydro One aims to be a responsible corporate citizen helping build a better future for all Canadians.

David Lebeter

executive
#9

We also felt honored to be given the Powerline Safety Award by the Electrical Safety Authority, which recognized the part we played in helping deliver a very large piece of equipment safely to a brewery located in Southwestern Ontario. Working together with our partners, Hydro One raised and lowered conductors over a route of 117 kilometers, which allowed that equipment to be moved safely while keeping the impact on customers to a minimum. This award shows what partnerships can accomplish and reflects our joint work toward a goal without any compromise on safety. On that note, I'll hand the call to Harry so he can go over our financial results. Harry, the floor is yours.

Henry Taylor

executive
#10

Thank you, David. It really is an exciting period for the province, and Hydro One is positioned well to help with the energy transition and electrification efforts now underway to serve the needs of every Ontario resident and business. Now to our third quarter financial results. Basic earnings per share came in at $0.62, versus $0.60 in the third quarter of 2023. The main factors driving that year-over-year change were higher revenues net of purchased power, partly offset by higher income tax expense, largely from unfavorable timing differences relative to last year and higher pretax earnings, higher depreciation and amortization and asset removal costs, along with higher interest expense. As a reminder, both the transmission and distribution segments carried net income-neutral items in revenue, including normal course regulatory adjustments such as OEB approved recovery of historical cost deferrals. These items have corresponding offsets in tax expense and in OM&A, which makes them net income neutral. Our third quarter revenue, net of purchased power, rose 6% year-over-year. Transmission revenues were up 5.7%, mainly from changes in OEB-approved rates for 2024 and higher average monthly peak demand. Those gains were partly offset by the revenue impact of the net income neutral items I mentioned earlier.

Henry Taylor

executive
#11

Turning to distribution revenues: on a net-of-purchased-power basis, they rose 6.1% compared with a year earlier. The drivers were the revised OEB-approved rates for '24, greater energy consumption, and growth in our customer count. Where costs are concerned, operating, maintenance and administration expenses for the quarter came in essentially flat versus the prior year, edging up just 0.3%. Over in the Transmission segment, costs ran 1.8% higher, largely on greater work program spending tied to stations, lines maintenance and vegetation management. Beyond that, we recorded certain net income neutral items, with an offsetting effect in revenue. For the Distribution segment, costs declined 4.3%, chiefly from reduced corporate support costs and regulatory adjustments, partly counterbalanced by increased work program expenditures, mostly for customer programs and emergency power restoration. Depreciation expense in the third quarter climbed 6% relative to a year ago, reflecting capital asset growth and greater asset removal costs, partly offset by reduced amortization of regulatory assets. On financing, interest expense was up 10.5% versus the prior year, primarily from a higher weighted average interest rate on long-term debt and additional long-term debt arising from issuances during the second half of 2023 and year-to-date in 2024. Partly offsetting these charges were a reduced average volume of short-term notes outstanding and increased capitalized interest stemming from a higher average balance of assets under construction.

Henry Taylor

executive
#12

In the quarter, Hydro One brought $1.2 billion of medium-term notes to market. That was made up of $700 million in 4.25% notes maturing in 2035, plus another $500 million in 4.85% notes maturing in 2054. We issued them through our sustainable financing framework. A key differentiator for us is how strong and stable our balance sheet is, and our creditworthiness as well — we're glad to say both stay robust. Our FFO to debt metric right now, which serves as a solid proxy for creditworthiness, continues to sit well above the threshold limits that the credit rating agencies apply when qualifying our credit rating. Now on to taxes. Income tax expense for the quarter came in at $56 million, versus $36 million in the same quarter a year ago. Unfavorable timing differences relative to last year contributed to that increase. As a reminder, in the third quarter of last year we placed several information technology initiatives in service that qualified for 100% capital cost allowance. This year we also had higher adjusted pretax earnings, and those were partly offset by the impact of the net income neutral items we discussed earlier. The effective tax rate for this quarter was 13%, compared with an effective tax rate of 9.1% last year.

Henry Taylor

executive
#13

For the nine months, our effective tax rate came in at 14.5%, versus 15.3% a year ago, and that prior-year figure reflected the deferred tax asset recovery through June 30, 2023. The present rate aligns with what we expect for the rest of the JRAP period, which is 13% to 16%. Turning to investing activities: during the third quarter, we put $597 million of assets into service for our customers, down 14.6% from the same period last year. Within Transmission, we recorded a 2.4% decline year-over-year, driven mainly by fewer line refurbishments and by the timing of assets placed in service for information technology initiatives. Partly offsetting those factors were an increase in assets placed in service for grid operating and control facilities, along with the timing of investments placed in service for customer-driven work. Over in Distribution, in-service additions fell 22.9% versus the prior year, a result of the timing of investments placed in service for information technology initiatives and the timing of assets placed in service for system capability reinforcement projects. Partly offsetting that were greater spend on customer connections and a larger volume of wood pole replacements.

Henry Taylor

executive
#14

When you look at capex, Q3 saw us put in $773 million, representing a 21.2% rise compared with 2023. That growth came from both the Transmission and Distribution segments, driven by greater investment in new transmission and distribution infrastructure, more customer connections, and a larger volume of line refurbishments and wood pole replacements. Those factors were partly offset by reduced spending on information technology initiatives. Moving to Broadband. We were quite encouraged by what the Ministry of Infrastructure announced last week — subsidies for Internet service providers tied to work on designated broadband projects. This $400 million program is meant to give ISPs financial support so they can carry out their work and bring high-speed Internet access to rural communities. It's too early to say what impact this program will have on our magnitude of work, but we are hopeful this move will speed up the pace of orders. Our expectation of the magnitude of work remains between $300 million and $700 million of incremental rate base in the Distribution segment. As a reminder, this is not included in our capital investment projections nor in our earnings guidance at this point. With respect to LDC consolidation, we continue to be active in engaging with local distribution companies and their respective municipalities to facilitate further consolidation within the sector.

Henry Taylor

executive
#15

We stay disciplined in how we work through things. So because of that, we won't chase opportunities that fail to satisfy our stringent investment criteria. As we look forward, we're keeping our guidance of 5% to 7% compound annual growth in earnings per share for the 2023 to 2027 period, with normalized 2022 earnings per share of $1.61 as the base. And lastly, I'm glad to share that our Board of Directors declared a dividend of $0.3142 per share, payable to common shareholders of record on December 11, 2024. With that, we'll open up the phone lines and we'll be happy to take your questions.

Omar Javed

executive
#16

Thanks, David and Harry. We'd like the operator to walk us through how they'd prefer to run the Q&A polling process. If we don't manage to reach your questions today, my team and I are always on hand to answer any follow-ups. We'd ask that you keep your question to one question plus one follow-up. Should you have more questions, we'd ask you to get back in the queue. Please go ahead.

Operator

operator
#17

<<operator_script>> Jessica Hoyle from Scotiabank has our first question.

Jessica Hoyle

analyst
#18

To begin with, since the IESO has issued a forecast showing greater demand, could you elaborate a bit on the incremental transmission opportunities you foresee going forward?

David Lebeter

executive
#19

Jessica, this is David Lebeter. We’ve been collaborating with the IESO on the forecast they produced, and we’ve pinpointed regions in the province where capacity constraints exist that we expect will be dealt with going forward. The next step—since the IESO has revised its projected growth—is for them to return to their planning process and bring that planning up to date. We anticipate hearing something from that effort early next year.

Jessica Hoyle

analyst
#20

Thanks. So with electricity demand rising the way it is — in Ontario and really all over the continent — how are you weighing the supply chain and inflation risks that come with that?

Henry Taylor

executive
#21

Jessica, this is Harry Taylor. We have a procurement team that has been well ahead of the curve since the pandemic in getting contracts signed with our vendors and vendor partners, anticipating supply chain problems, and locking in supply with pricing tied to indices, et cetera. So I'd say there really isn't anything new to report. Supply chain challenges have been with us for some time. And so for all our major vendors and material requirements, we hold long-term agreements with multiple vendors to make sure we have sufficient supply while also making certain our pricing is at least market-based, if not better.

Operator

operator
#22

Mark Jarvi from CIBC has our next question.

Mark Jarvi

analyst
#23

Perhaps just regarding government backing for broadband — when do you expect to have clarity on that? And do you believe the dollar figure that has been proposed is sufficient, maybe to lift things toward the top end of that $300 million to $700 million rate base growth on your side of the equation?

Henry Taylor

executive
#24

Mark, this is Harry — Harry Taylor. At this point, it's too soon to say if we're at the low end or the high end of that range. I realize the range is broad. We definitely welcome the incentive very much. We expect it will clear the backlog when it comes to the orders and applications we're seeing. Frankly, if this doesn't do it, I don't know what would. But right now, we simply haven't — it was only announced last week. We haven't yet seen the uptick. So it's hard to pin down a broad range at this stage. We'll provide updates whenever we see the trend taking shape and do our best to narrow the range. Naturally, we'd prefer it to land at the top end so we can serve Ontarians and include it in our rate base, but that depends on the applications from the ISPs.

Mark Jarvi

analyst
#25

Got it. And David, to build on what you said regarding the discussions with the IESO about transmission planning demand down the road — the government has also been quite outspoken about becoming an energy exporter, more or less. What kinds of talks are you involved in on that front, specifically around transmission interconnects and the part Hydro One could play if we end up sending additional power south?

David Lebeter

executive
#26

Mark, I appreciate that question. It's genuinely an interesting one, and there's a lot happening here. So the first objective: the government has stated that we will achieve energy self-sufficiency and will be positioned to handle the growth we're seeing across the province. That growth will be the 75% or 70% increase — a 75% increase. The second goal they've named is keeping things affordable, and that's where exports come into play. When you're building out an energy system, you want to make sure you lean toward having somewhat more than you require, since coming up short is a genuine problem. So you need access to export markets. That's why we've collaborated with both the IESO and the government to pinpoint, first, constraints — as I mentioned earlier — where extra flow or ties would be needed heading south, or heading east or west too, since we can move power in three separate directions. Not everything has to go south — as well as where they're considering siting the added generation, which creates opportunities. So what I'd anticipate seeing over the next year is the government announcing further details about what an energy superpower entails, where that generation will come from, and added transmission build-out extending past 2030.

David Lebeter

executive
#27

That likely lands somewhere between the late mid-2030s and the late 2030s, especially in the case of nuclear. Does that address what you were asking, Mark?

Mark Jarvi

analyst
#28

Right, no. So from your perspective, you'd still see yourself as essentially the preferred transmitter, and when it comes to how large these projects are, that's something you figure you'd be the first to get a look at?

David Lebeter

executive
#29

Yes, absolutely. That is going to be where we start from. We think we are the best fit to run these projects and construct them. We showed that with Chatham to Lakeshore, which came in early and under budget. We showed it with the Waasigan Transmission Line through how fast we have moved into construction. We have shovels in the ground this year. We have a strong relationship with the indigenous communities, our partners as well as with government. Government ultimately gets to make the decision, as you saw with the Wawa, to Porcupine — they did put a competitive process in place, but I think they are going to find — and at the end of the day, they did award that to us. So obviously, they are seeing the value we bring to these lines. So that is our hope, that we get designated. But if that is not the case, we are certainly confident in our ability to compete.

Operator

operator
#30

The next person in the queue to ask something is Maurice Choy, who's calling from RBC Capital Markets.

Maurice Choy

analyst
#31

Perhaps a brief follow-up regarding Wawa to Porcupine. You mentioned that it was awarded to you. I believe they designated you — they proposed designating you as a transmitter option. But has the award actually happened? If not, is there any reason for the holdup?

David Lebeter

executive
#32

The project was assigned to us. After that, there was a 45-day consultative period during which the award was available for discussion and feedback. That wrapped up a couple of months ago. I remain confident that we'll receive the final letter assigning that project to us, which will let us start moving ahead with it. They're simply using this time to ensure they've gone through all the comments and sent responses back to everyone who was involved. In my view, though, it's unlikely that they'll alter their designation. So we're quite confident that we'll get some favorable news on that later this year.

Maurice Choy

analyst
#33

And just to wrap up on what you said regarding the Ontario government and its vision for the province's energy future. Obviously, they're aiming to kick off their first integrated energy resource plan next year, as you noted. What are your thoughts on what would genuinely be different — meaningfully different — from what's being done today, and what does that mean for you?

David Lebeter

executive
#34

To expand on what an integrated plan involves, it means they will examine how to combine gas and electricity so the system gets built out in the most sensible manner. That gives certainty to the gas companies and to the electricity companies alike. Given their ambition to become an energy super, I'd expect this to be a long-term vision. So instead of the IESO's present process, which looks ahead a couple of years, my expectation is a 5- to 15-year outlook, which lets you actually follow a trajectory and begin making investments.

Operator

operator
#35

That brings today’s question-and-answer portion to an end. I’d now like to hand the call back to Omar Javed so he can offer any closing comments.

Omar Javed

executive
#36

Thank you, Shannon. Everyone at Hydro One's management team appreciates you all spending part of your morning with us during such a busy stretch. Your interest and ongoing support mean a lot to us. Should any questions remain that we didn't get to on this call, don't hesitate to contact us, and we'll make sure you get answers. Thanks once more, and have a great rest of your day.

Operator

operator
#37

Ladies and gentlemen, we appreciate your joining today's conference. That brings today's program to a close, and everyone is free to disconnect now. Have a wonderful day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Hydro One Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Hydro One Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hydro One Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.