IDACORP, Inc. (IDA) Earnings Call Transcript & Summary
October 29, 2026
Earnings Call Speaker Segments
Amy Shaw
executiveThank you, and good afternoon to everyone. We're glad you could join us on this call. The slide deck we'll be referring to throughout today's discussion can be found on IDACORP's website. As slide two indicates, today's remarks contain forward-looking statements, covering items such as earnings guidance, capital spending projections, financing strategies, regulatory plans and actions, plus estimates and assumptions that represent how we currently see the future. All of these carry risks and uncertainties. Such risks and uncertainties could cause actual outcomes to vary materially from what is said today, and we urge you not to place undue reliance on any forward-looking statements. Our cautionary note regarding forward-looking statements, along with various risk factors, appears in greater detail for your review in the filings we make with the Securities and Exchange Commission. As slide three shows, joining us today are Lisa Grow, our President and CEO, Brian Buckham, our CFO, and John Wonderlich, Investor Relations Manager. Slide four provides a summary of our third quarter financial results. Diluted earnings per share at IDACORP came in at $2.73, up from $2.26 in the third quarter of last year. Over the first nine months of 2026, diluted earnings per share reached $5.76, compared with $5.13 in 2025. Those figures reflect only $6.3 million of additional tax credit amortization during the first nine months of 2026, versus $39 million across the same period a year earlier, which highlights how strongly 2026 has performed to this point. Turning to our key operating metrics, we are lifting our full-year IDACORP diluted earnings per share guidance range by $0.10 at the bottom and $0.05 at the top. The updated range stands at $6.40 to $6.50 per share. This raise stems from our robust operational results in the third quarter. It incorporates our expectation that Idaho Power will utilize under $10 million of additional tax credit amortization for the full year, down from the under $15 million assumed in our previous guidance. These estimates further presume historically normal weather conditions through the remainder of the year; with that, I'll hand the call to Lisa.
Lisa Grow
executiveThank you, Amy. And thanks to all of you for being with us today. I'll begin by pointing out the strong growth that we keep seeing throughout our service territory. That growth is varied — it's occurring among every kind of customer, across a broad range of industries. On slide five, you can see that our customer count is up 2.2% compared with the third quarter of last year, and that figure includes 2.4% growth in the residential segment. Industrial revenues deserve special mention this quarter: they rose by an incredible 27% versus last year's third quarter. After years of careful planning and diligent project execution, we are now seeing meaningful revenues arrive from large contract customers as those customers build out their facilities and bring them online. We're excited to play a part in their success. Meta officially started operations at its data center south of Boise in September and is now ramping up, and the Micron Fab 1 and Fab 2 expansions in Boise keep making impressive progress; photos appear on slide six so you can see how large these projects are, along with a couple of others. Our preliminary load growth CAGR for the 2027 IRP is 8.9% for retail sales over the next five years. That figure incorporates the higher base year load in the calculation. Although it remains preliminary, you can see the substantial growth on slide . For context, that works out to a load forecast of roughly 19,000 GWh in 2027, rising to roughly 29,000 GWh by 2032. This is considerable growth, and we're working hard to make sure Idaho Power remains ready to meet it — and that we meet it responsibly. As a reminder, where large contract customers are concerned, our preliminary load projections capture only those customers that have signed contracts or made significant financial commitments to Idaho Power for infrastructure build-out. Beyond the large customers we've already covered, a diverse set of new and expanding customers is interested in investing in our service area — among them manufacturing, mining, food processing, transportation, data centers, and other energy-intensive industries. So far in 2026, we have received 76 inquiries from projects whose energy needs exceed one megawatt, which puts us on pace for another year of historically high project activity. These projects could bring new jobs, investment, and long-term economic opportunities. They also underscore how important thoughtful planning is, so that we keep delivering affordable and reliable service to our customers. To spotlight a few other projects: this month Idaho Power broke ground on the transmission facilities required to serve Perpetua Resources' Dibbie Creek project, which will support domestic production of critical minerals and strengthen U.S. supply chains. We also recently celebrated the grand opening of Tractor Supply Company's new distribution center in Nampa — another great example of the economic growth and business investment taking place across our service area. Idaho Power keeps affordability front and center as we grow, and we're proud that our prices remain 20%-30% lower than the national average. Slide eight shows that since 2016, average electric rates across the country are up 41%. Boise rents have risen 85%, CPI inflation is up 39%, and over that same stretch Idaho Power residential rates are up 24% — only about 2.2% per year on average. We strongly support Idaho's growth-pays-for-growth regulatory model, and our agreements with big contract customers are designed to shield Idaho Power and our current customers from risk and cost shifting. Slide nine shows several of the contractual safeguards we pursue in energy services agreements with large contract customers. As I noted on last quarter's call, the big revenue gains we're getting from those customers were a major reason Idaho Power didn't file a rate case in 2026, which helps show the value of the growth-pays-for-growth approach in Idaho; we're proceeding at full speed, carrying out projects to serve our expanding customer base and strengthen our grid. Slide 10 shows we're making excellent progress on the Boardman-to-Hemingway transmission line. So far, over 1,200 structure pads are complete, 1,100 foundations are in place, and roughly 780 towers are standing — about 60% of the project total. We've also installed approximately 100 mi of conductor. B2H is still on track for an in-service date in late 2027. Construction also continues in Nevada on the SWIP- North Transmission Project, which should wrap up in 2028; on the Gateway West Transmission Project we keep advancing, and the transmission line construction is out for bid. Turning to slide 11, we're still progressing on three company-owned natural gas-fueled projects. Work is underway on a 167 MW resource being built beside our existing Bennett Mountain gas plant. The new Bennett facility has a scheduled in-service date of 2028, and we have a CPCN air permit and EPC contract in hand. CPCN applications are filed for South Hills, a 222 MW project set to operate in 2029, and for the 430 MW Peregrine project, slated for 2030. Equipment supply agreements are executed for all three projects. We also signed an EPC contract for Peregrine, and we're negotiating one for South Hills. Dispatchable energy from these plants will help us cover projected load deficits and serve customers with the least cost, least risk resources. Looking toward further capacity and energy needs, our evaluation team got more than 100 bids for the 2032 RFP and has narrowed to a final shortlist of 11 projects, shown on slide 12. As in past RFPs, Idaho Power has several company-owned projects on the final shortlist, and we were glad to see competitive bids; in fact, the 2031 South Hills project on the slide ranks first. The list also features third-party owned solar, wind, and battery facilities, plus a few market purchase bids. At this point, we aren't planning to sign contracts for all of the projects on that list. Altogether, that's a large quantity of megawatts—a higher megawatt figure than our revised load forecast includes through 2032. That said, in line with our past practice, our final shortlist is able to absorb possible additional growth, and having that flexibility is valuable. We're striving to secure contracts and anticipate advancing the chosen projects before this year ends. So watch for CPCN filings. Last, regarding the Oregon sale, we still anticipate closing it in spring 2027, subject to favorable regulatory results. We got FERC's approval not long ago, and the regulatory proceedings in Oregon and Idaho are ongoing. With that, I'll hand things over to Brian.
Brian Buckham
executiveThanks for joining us, everyone. I'll jump right into what shaped this quarter's results, beginning with slide 13. The biggest driver, as you can see, was higher retail revenues, stemming from a combination of increased benefits under existing base rates and customer growth. Those two factors together added nearly $44 million of benefit in the quarter and about $90 million year to date. Overall, usage per customer was essentially unchanged in the quarter. The fixed cost adjustment mechanism lowered retail revenues this quarter, which occurred because sales to residential and small commercial customer classes came in slightly higher. The fresh revenue category we rolled out during Q2—income from big contract clients—boosted operating income by close to $12 million for that quarter. On a year-to-date basis, it came to roughly $20 million, illustrating how the ramp-up is advancing. Why does this matter? Because gains from large contract clients are now materializing, and they account for a meaningful chunk of the 27% increase in industrial customer revenues that Lisa mentioned. O&M expense, as we expected, ran higher in Q3, driven chiefly by amortization of costs previously deferred for the Jim Bridger and Valmy plants, plus our wildfire mitigation program. Bear in mind that we recover a considerable share of those items through rates and regulatory mechanisms. Depreciation and amortization came in a little over $7 million higher this quarter. That’s also not unexpected, given that we continue to put substantial money into system infrastructure so we can meet rising customer demand — which translates into more plant in service. Operating income got a $10.6 million lift from other shifts in operating revenues and expenses. Similar to what we saw in the first half of the year, this gain was driven primarily by reduced net power supply expenses that aren’t accrued through the power cost adjustment mechanisms; the main reason was updates to the Idaho jurisdiction PCA mechanism base from last year’s rate case. A lower property tax bill contributed as well, thanks to an Idaho legal change taking effect in 2025. Non-operating expense came in a bit higher: larger construction work in progress balances—once more the result of substantial infrastructure spending—generated more AFUDC, which mostly canceled out the rise in interest expense. On the balance sheet, CWIP stood above $2.1 billion when the quarter closed, a figure that truly highlights what Lisa said about how active we have been as a company. And that is exactly what makes financial statements so valuable—sometimes the figures alone convey a story as well as finely crafted writing. Income tax expense, leaving out ADITCs, delivered a $6.7 million benefit during the quarter. The main driver was flow-through items tied to plant. Amy mentioned that Idaho Power has booked just over $6 million in additional ADITCs this year to date, compared with $39 million in the same period a year ago, which is a favorable and sharp difference. I think that really stands out when you factor in the bigger projected book equity at year-end in the Idaho jurisdiction this year, and it reflects the solid financial results the company has produced so far this year. We've been working through our capital budget forecast, which means updating project timing and pricing and also adding new projects. The capital expenditure chart we showed in prior quarters is no longer current and, predictably, might not fully reflect how we see our capital shaping up over the planning horizon. We plan to provide a refreshed CapEx outlook during our Q4 earnings conference call, keeping to our more customary schedule, and that update will carry our usual revisions plus the CapEx impacts of company-owned projects selected from the 2032 RFP—at minimum those advanced enough in the process and ready for prime time. Before we expect additional detail on the Q4 earnings call, I'd like to spend a bit of time on financing, which takes us to slide 14. In Q3, we put in place an extra $268 million of forward sale agreements via our 2026 ATM program. That came in addition to the $265 million sold under the same program during the first half of the year. Every one of those shares sits in forwards. We also have proceeds still available from unsettled forwards tied to both our earlier 2024 ATM program and last year's follow-on offering, as the chart on the slide shows. The main takeaway, I'd say, is that at present we have about $873 million in forwards ready for settlement. We intentionally raised equity capital ahead of time, which lets us combine debt and equity financing and remain near our desired capital structure of roughly 50/50 debt to equity. As of the close of Q3, leaving out unsettled forwards, equity made up 51% at both Idacorp and Idaho Power—fairly near our goal, leaving some room to add debt. We'll update that figure for the Q4 call alongside the updated CapEx outlook. Slide 15 shows that most of the equity required under our present plan is already taken care of. We have the equity needed for the current plan through 2027 and probably into part of 2028, and at this point we expect to cover whatever equity remains to fund our current CapEx plan by using ATM issuances. Any extra CapEx would call for some added debt along with growth equity, and how much would depend heavily on when that CapEx gets paid. In financing, we will keep being careful about managing dilution through tools such as forwards and payment timing, reimbursable customer funding, and other methods. On that note, given the recent pickup in volatility and rates, I figured it made sense to address interest expense looking ahead. It helps that we have few long-term debt maturities to refinance across the coming five years — only $80 million comes due in 2030. Beyond that, there's no holding company debt on our books, and we hold no long-term variable rate debt. Additionally, we now operate in a more frequent rate case mode, which allows us to adjust cost of capital sooner when rates climb. All of these factors lower our interest rate risk exposure going forward. Regarding regulation, we should now begin crunching figures for a possible rate case submission in June 2027. The money we received from last year's general rate case outcome, plus revenue from major contract clients and growth in customers across every class, collectively allowed us to avoid a rate case this year despite inflationary pressure. Although we have considerable infrastructure being built this year, we anticipate that certain bigger projects constructed to serve our wide customer base won't shift out of CWIP into plant in service until 2027. Examples include B2H, other transmission efforts, hydroplant refurbishments, and system hardening that serve all customers. Now, compare that to the infrastructure we build for big contract customers, where we get our money back through ESAs with those customers. With a substantial share of our broad customer projects entering service in 2027, the odds rise that we'll file a general rate case next year, though we'll be running the numbers on that. Entering the final couple of months of the year, large contract customer revenues keep ramping following years of investment from both them and us; our financial results so far this year have been strong, and things look good as we head toward year-end, which we expect to mark a 19th straight year of EPS growth. We're keeping affordability in mind for our customers, and at the same time we're moving at full speed to develop and build a number of transmission and generation projects for customers we have today and those we'll serve down the road. We're now two years into a plan to more than double our rate base across a five-year span, and we're carrying out our financing plan efficiently to make that happen. I feel good about where we stand today, and I feel good about the direction we're going. If you'll be there, we look forward to seeing you at the EEI Financial Conference coming up in sunny Arizona. As a lot of you know, that's among my favorite events each year. I'll stop there and turn things over to America's top IR professional, John Wonderlich.
John Wonderlich
executiveThanks, Brian. If you go to slide 16, that's where we lay out our guidance for full year 2026 on earnings and the key operating metrics; we've seen some solid gains in both our earnings guidance and our ADITC guidance. As we always do, our guidance assumes weather will be normal for the rest of 2026. Given continued strong operating performance, Idacorp's diluted earnings per share for this year is now expected to land between $6.40 and $6.50. We raised both the bottom and the top of that range. We're also seeing better ADITC expectations. So we're taking $5 million off what we previously guided. Our expectation now is that Idaho Power will use under $10 million of additional investment tax credit amortization in 2026; that's far below the $40 million we amortized across full year 2025, particularly given the significant growth in year-end book equity; full year O&M expense is now expected to come in between $535 million and $545 million. CapEx for 2026 is still anticipated to be between $1.3 billion and $1.5 billion. As we mentioned on the second quarter call, at this point it's fair to say we're trending toward the high end of that CapEx range. Given how we currently forecast hydropower operating conditions, hydropower generation for the year is now expected to fall within 5.5 million-6.0 million MWh. With that, we're happy to take whatever questions you have.
Lisa Grow
executiveHi, Shar.
Whitney Mutalemwa
analystGood afternoon, everyone. Good afternoon. Whitney Mutalemwa here, speaking in place of Shar.
Lisa Grow
executiveHello there, Whitney.
Whitney Mutalemwa
analystYeah, thanks for taking my question. If the shortlist turns out bigger than the committed forecast, what needs to occur before you sign contracts past committed need? Is it required that a pipeline customer signs and then secures commission approval within those 270 days before you'd commit to additional self-build?
Lisa Grow
executiveThat can be the case, but beyond that, whenever a customer has a signed ESA or has put in a significant financial commitment, we would then add them to the load forecast. So it doesn't necessarily have to go all the way through commission approval.
Whitney Mutalemwa
analystAll right, got it. Given that the 29,000 GWh covers only customers who've signed or committed, what's the size of the pipeline outside that, in megawatts, considering the 76 inquiries this year?
Lisa Grow
executiveThat sits at roughly 4,000 MW, and I realize that figure sounds familiar. We've mentioned it on a number of calls. The thing is, it isn't the identical 4,000 MW, since when projects move into construction we take them out of that pool while other projects come in. I think — Adam, do you want to add anything?
Adam Richins
executiveYou know, I believe you brought up the 4 GW figure, and that is exactly what we have referenced previously. Just a few quick points. That 4 GW does not count Micron Fab 1 or Meta 1. As we said on the call, Meta 1 is obviously finished. Micron Fab 1 is moving along; so the 4 GW figure we discuss is genuinely a future pipeline. Within that 4 GW, roughly 1 GW is what we frequently call promising; typically that involves a financial commitment, and those entities are headed toward construction or possible construction. Another 1 GW out of the 4 GW is under active study, so we usually describe those as being in the study phase. Perhaps there are no significant financial commitments at this point, but we have been paid to study those projects. Then approximately 2 GW of the 4 GW feel preliminary is, many times, how we describe them. But an additional 3 GW have arrived since we discussed the 4 GW number. So really, 5 GW are preliminary, and again, another 1 GW is promising and another 1 GW is being studied. Just to give you an overall picture of where we stand.
Whitney Mutalemwa
analystYep, I'm ready to go. Thanks, Lisa. And thank you, Adam.
Lisa Grow
executiveThanks.
Lisa Grow
executiveHi everyone.
Michael Lonegan
analystGood afternoon, and thank you for the questions. On the RFP, my understanding is that the total resources on a final shortlist could exceed what your capacity requires. I was wondering if you could share the exact amount of resource and megawatts you anticipate procuring. Then, regarding the self-builds, could you discuss when capital spending will begin and what the profile of that investment looks like?
Adam Richins
executiveMichael, Adam here. As I recall, slide 12 that we presented to you indicates a resource for 2031, and that resource is the 430 MW gas plant. In fact, it's an advanced simple cycle plant. Work on that project has begun. Reservations for the turbines are in place, the EPC contract has been granted, and for that year it ranked as the top project. Right now, the effort we're examining most closely is the 2032 project, which is 432 MW. It's a combined cycle plant, and it too was ranked number one, though in 2032, and at present we're assessing load to confirm this is the project we'll proceed with. As for CapEx, it is distributed across the years; clearly we have projects in 2020, 2028, 2029, 2030, 2031, and 2032. We're also constructing transmission lines over that same span. Spending patterns are holding fairly steady. What we're seeing more often now is that for many of these projects, capital expenditure has to be committed somewhat sooner than was previously the case—so some of that outlay may show up a couple of years before the project actually begins operating.
Michael Lonegan
analystThanks. So that expenditure — I think you were alluding to this — could be financed with additional capital, possibly divided evenly, half equity and half debt. Is that correct?
Brian Buckham
executiveCorrect. Brian here. The extra expense on top of what's already included in the current plan — if you revisit the slides from our prior quarter, there's a projected capital forecast you can see. Whatever costs exceed that figure, our expectation would be to cover them with debt and equity at a 50/50 split. That said, there are exceptions. For instance, in some cases a customer might fund part of one up front. Build-transfer structures could allow payments to land later in the cycle. As I noted, milestone-based payments are the usual approach, though that remains open for discussion during our RFP processes. One thing I'll add: the CapEx forecast you've seen previously does not include either of those two plans. Should they proceed, they would be fully incremental to what you see.
Michael Lonegan
analystThanks. One last thing from my side about Micron Fab 2 — could you tell us where the negotiations stand, and when you think an ESA will be signed? I believe you said earlier it would happen before year-end. Does that still hold, perhaps something very close, within the next couple of months?
Lisa Grow
executiveWell, we're definitely still working with them. It feels to us as though things are progressing well, and we're certainly hoping those timelines will be met. Once we do, you'll see the filing.
Michael Lonegan
analystAlright, thanks a lot for taking the question.
Lisa Grow
executiveThanks.
Adam Richins
executiveThanks.
Lisa Grow
executiveHi, Chris.
Chris Ellinghaus
analystHi, everyone. How's it going? Taking a look at slide 12 — you've had a steady stream of new resources coming in. When does a standard combined cycle begin to be worthwhile, to kind of fill the gap or pick up somewhat better efficiencies?
Lisa Grow
executiveWell, we definitely would have grabbed a few of those by this point if we'd been able to; but for sure, once you begin looking toward the 2032 timeframe, I think that's the point where that's a combined cycle.
Adam Richins
executiveChris, Adam here. Regarding that 2032 project, it comes in at 432 MW, and it's a combined cycle facility.
Chris Ellinghaus
analystAll right. Could you put some numbers on how much the weather helped during the quarter?
Lisa Grow
executiveI don't know whether I have that on hand. Brian, do you have it?
Brian Buckham
executiveSure, I can offer some color there. A major factor, naturally, was irrigation on a year-over-year basis. Q3 was fairly solid, actually, so we picked up some gain from that. Probably the clearest way for me to frame it is through weather-normalized sales, which you can set against the non-normalized figures reported in the 10-Q. Overall, our weather-normalized sales came in at 2.9%. Much of what's behind that, I'd say, relates to certain large loads and special contracts now coming online — weather tends to matter less for those. For industrial and special contract together, though, it was 5.8%, and that's sales volume, so a fairly meaningful lift; then Lisa covered the other dimension, the revenue side, a 27% rise from large load customers. On the weather front, the timing of precipitation during the second quarter drove some irrigation sales, roughly in line with last year in Q3. Past that, weather's effect was more limited. Looking at heating and cooling degree days, they did depart from normal, though less so year-over-year.
Chris Ellinghaus
analystAll right, then. So, Brian, with that dividend payout goal in mind, you're keeping up the same pace as before — clearly the case with the latest dividend raise. You're beginning to hit the lower edge of the payout range. Is there a firm target in place? Is there a floor you're prepared to reach? Or just tell me what you're thinking, since we're not that far away from it.
Brian Buckham
executiveYes, Chris, I'd say as you look at it, we're not too far from that point right now. If for some stretch of time we drop under that 50%-60% dividend target range, we aren't worried about it; in fact, we may very well end up doing exactly that as we put capital back into the business instead of paying it out as dividends. What that does give us, though, is a great deal of dividend capacity down the road. We do understand how important the dividend is, but we also see the value to our owners in reinvesting that capital. So if we did drop below, I believe we'd receive pretty substantial backing from our shareholders for making that reinvestment.
Chris Ellinghaus
analystAll right. On the IRP, the preliminary figures for load growth have picked up somewhat. What portion of that comes from some of the large projects — the big-ticket ones such as Micron Fab 2 — and how much can you describe, given the higher base, where that acceleration is originating?
Lisa Grow
executiveGo ahead.
Adam Richins
executiveChris, it's Adam here. So the 8.9% figure we presented a moment ago takes in Micron Fab 1 along with Micron Fab 2. It also takes in Meta 1, the one we discussed that has only just come online; beyond that, it takes in a further data center that remains unnamed as of now, so I'm not really in a position to discuss it, though it carries other varied loads; it takes in Perpetua as well, and it takes in INL and Chobani. So those are the components behind that load growth. Clearly, we're also witnessing a good deal of residential growth. I believe that accounted for roughly 1% of that growth-
Lisa Grow
executiveYeah, that's finished.
Adam Richins
executiveThe growth is residential; we're also seeing some pickup in irrigation. I believe irrigation loads accounted for a bit over 0.5% of it. What isn't captured in that — that 8.9% doesn't capture, say, Micron going ahead with a Fab 3 or Diode, which we've discussed previously, or any additional data centers — just to give you some sense of what's in there and what isn't.
Chris Ellinghaus
analystAll right, that's genuinely useful. Thank you. Very well. We'll be seeing you in about a week. Thanks. Much appreciated.
Lisa Grow
executiveSounds good. Until then, Chris.
Lisa Grow
executiveHello there.
Brian Russo
analystGood afternoon to you. I'd like to line up the 8.9% IRP load growth against the 2032 RFP — in principle, what level of 2032 needs would that RFP suggest?
Lisa Grow
executiveApologies, I missed the final part of what you said.
Adam Richins
executiveAdam here. I believe we've covered this only briefly, but the main issue regarding 2032 is, once again, that combined cycle facility of 432 MW. It appears we're heading that way, yet we still have to review the load forecast and a few other items, and after that we'll decide on that matter. That said, to your point, 2032 will probably require some resources, or it will require something beyond what we have in 2031.
Brian Russo
analystAll right, understood. So based on that pipeline you mentioned before plus this new IRP, should we anticipate a comparable pattern of yearly RFPs even beyond 2032, similar to what we've probably witnessed over the last four or five years? Is there still considerable additional load to come, for instance behind Micron Fab 2?
Lisa Grow
executiveAbsolutely. As more load keeps arriving and we keep negotiating those ESAs, that's certainly possible; and that's been the great thing about our growth story — with some of these customers we're looking into the 2030s; though naturally, it will depend on how the final negotiations go. But yes, the way we see it, I think it's possible.
Brian Russo
analystAll right, sounds good. Well, thanks so much.
Lisa Grow
executiveThanks.
Alexandre Zimmermann
analystHello, Alexandre Zimmermann here, speaking on behalf of Dave. I appreciate you taking my question.
Lisa Grow
executiveHello.
Alexandre Zimmermann
analystTurning to the ADITCs, your current expectation is that you'll use under $10 million this year. Looking ahead, do you believe you might earn above the minimum ROE within the next two years and stop needing the ADITCs?
Lisa Grow
executiveWell, that will largely hinge on the timing of projects and the financing plan, but our objective is certainly to use as few as possible. What would you add?
Brian Buckham
executiveOkay, Alex — if you take each year on its own, this year, with a figure below $10 million, zero is achievable and you can grow from there. Getting there would require quite strong operating results in the fourth quarter, and part of that would likely come from weather. Looking toward 2027, something I've really homed in on is what's taking place operationally that year when it comes to plant closings. You're seeing a great deal of CWIP convert. When that occurs, absent a rate change to absorb it at the start of a year, you wind up losing AFUDC and picking up depreciation; that makes 2027 difficult to get through without drawing on some ADITC usage; then in 2028, if a rate case gets filed in 2027, 2028 would capture the benefit from it. Once again, a substantial amount of plant enters service, though large contract customer revenues offset much of that; that's the analysis we must examine annually. But as I see 2027 right now, our forecast for earnings and ADITC usage will come in February, though my preliminary view is that I do believe we use ADITCs in 2027.
Alexandre Zimmermann
analystUnderstood. That's very clear. Turning now to the supply chain: you've got a big CapEx outlay coming, and since the last update you've signed additional contracts. Where do you see the primary supply chain bottlenecks, from your viewpoint, and how are you getting ready to deliver on that plan and on the possible extra CapEx to be announced at the next update? How much of it has already been procured or is on track?
Lisa Grow
executiveWhen it comes to the turbines, we hold either reservation agreements or supply agreements, so we feel very confident about the plant. Naturally, breakers, transformers, and conductor always seem to pose a challenge, but we stay ahead of it. I think we're in a very good position for those projects. Would you like to add anything, Adam?
Adam Richins
executiveNo. The one possible exception is that the EPC contractor market has also been difficult, and in that respect we have been quite lucky, since we have managed to award and choose EPC contractors for all of these plants except one so far. That was a matter that concerned us somewhat. My sense is that contractors find our diverse load very appealing, so they have wanted to bid on these projects, and the range of contractors and bids we have gotten has been a pleasant surprise.
Alexandre Zimmermann
analystUnderstood. That's very clear. Thanks a lot.
Lisa Grow
executiveThanks.
Nicolas Woods
analystHi there. Good afternoon, everyone. Hey, could you perhaps give me some idea of which of those data center loads referenced a bit earlier are already baked into the demand assumptions behind the 2032 RFP?
Adam Richins
executiveYeah. Adam here. So just one data center would have been part of that 2032 RFP, and that's Meta 1.
Nicolas Woods
analystAll right.
Adam Richins
executiveAs for other data centers considering us, or — I brought up one data center I didn't name that we're fairly confident about — those weren't part of that load forecast, which I believe came from the 2025 IRP.
Nicolas Woods
analystUnderstood. You said that you folks are crunching the figures to determine whether you'll file a 2027 rate case. When might we hear an update on whether you'll go ahead with that or not?
Lisa Grow
executiveTypically, we aim to file in June. In Idaho, a 60-day notice of intent to file has to be given. That's how we're approaching it, when we believe we'll have a solid view of what's headed our way. I think that's broadly what we're concentrating on.
Brian Buckham
executiveAnd yeah, Brian here. I’ll just add that when we get to the fourth quarter call, we’ll have completed some early analysis. Putting a rate case together takes so long that we’ll at least have preliminary financials, which will let us make a preliminary call on whether or not we file a rate case. As Lisa Grow said, that notice of filing is the definitive moment. We may be able to offer a little insight on the Q4 call.
Nicolas Woods
analystAll right. Understood. Thanks a lot.
Lisa Grow
executiveWell, thanks to each of you for being with us today and for the ongoing interest you show in Idacorp. I'm looking forward to catching up with all of you at EEI, and I hope your evening is a wonderful one, and I wish you a very happy Halloween. Here's hoping your candy is all dark chocolate. Thank you.
Operator
operatorThis concludes today's call. Thank you for attending. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete IDACORP, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to IDACORP, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in IDACORP, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.