Indigrid Infrastructure Trust (540565) Earnings Call Transcript & Summary

November 6, 2026

BSE Limited IN Utilities Electric Utilities earnings 44 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and welcome to the IndiGrid Limited Q2 FY '27 Earnings Conference Call, presented by Spark Institutional Equities Private Limited. <<operator_script>> Kindly be aware that this call is being recorded. At this point, I'll turn the conference over to Mr. Dheeraj. Thank you, and the floor is yours, sir. Yes.

Dheeraj Kripalani

analyst
#2

Thanks very much. Good day to all of you. Speaking for Avendus Park Institutional Equities, I'd like to extend a warm welcome to each of you on this 2Q FY '27 Conference Call for Indigrid Infrastructure Trust. Joining us from management are Mr. Harsh Shah, our Managing Director; Ms. Meghana Pandit, Chief Financial Officer; and Mr. Sanil, Chief Operating Officer. So, rather than using up much of your time, I'll now turn the call over to management for their opening remarks, after which we'll move into a Q&A session. Thanks again to everyone, and the floor is yours, sir.

Harsh Shah

executive
#3

Thank you, Dheeraj. And a very warm welcome to everyone joining the call today, on the occasion of Danteras. So wishing all of you a very happy Danteras. As we've done in the past, Meghana, Sanil, and I will walk through the presentation together, and at the end we'll reserve some time for Q&A. Starting off on Slide #3, I'd like to restate our vision of becoming Asia's most admired yield vehicle. We believe the pillars we've outlined for that — a focused business model, value creative growth, predictable distribution, and optimal capital structure — put us on a path toward achieving our vision. On Slide #4, just to give a sense of scale, we stand at about INR 33,600 crores in AUM today, spread across 22 states and 2 UTs. With 94 different revenue-generating elements spanning 10,000 Circuit Kilometres of lines, 34,000 MVA substation capacity, roughly a gigawatt and a half of solar generation, and approximately 2.5 gigawatts hours of projects at various stages of <<inaudible>>. Moving to the quarterly results update in terms of the quarterly highlights. During this quarter, we commissioned 2 projects, the first being Rajasthan BESS Private Limited. 250 megawatt by 500-megawatt BESS projects in Rajasthan.

Harsh Shah

executive
#4

Our stand-alone capacity comes to roughly 1 gigawatt of operating BESS power in India. In my view, that ranks among the biggest in India. We have 3 utility-scale plants running: the first has a track record beyond 1 year, the second is nearing 9 months, and this is the third. So we feel we hold a very solid record of having built and successfully delivered profitable BESS projects. The second one is our 765 kV product, which we have commissioned. That is the Ishanagar Power Transmission Limited project located in Madhya Pradesh. We hit 4,000 in year transformation capacity plus roughly 33 Kv of Circuit Kilometres on the 765 kv lines. Both of these projects were carried out jointly with Energid. Under our share purchase agreement, we intend to acquire them on the terms set out there over the coming few weeks and months. Beyond this commissioning, we signed a definitive agreement with EnerGrid to take over 2 transmission projects once commissioned. Those 2 projects carry a combined enterprise value of about INR 6,650 crores. The first is Shongtong Power Transmission, with around 400 Circuit Kilometre of line and a 630 MVA substation, evacuating hydro projects in Himachal through a larger project worth about INR 5300 crores, whose committing is expected roughly 3 years from now.

Harsh Shah

executive
#5

Luhri Power Transmission Limited is another smaller project, valued at roughly INR 1,350 crores, again located in Himachal, and its commissioning falls in quarter 3 of '30 — so roughly 36 months, or 40 months from today. Turning to financial performance, in quarter 2 of FY '27, operating revenue rose by approximately 8.4% to INR 872 crores. That revenue growth translated into operational EBITDA growth of 7.9% year-on-year, reaching INR 782 crores. Our AUM in net debt to AUM at the close of the fiscal stands at INR 3,667 crores, with 60.4% debt. In quarter 2 of '27, collections came in at 103% for transmission assets and 94% for solar assets. Given this financial performance, and maintaining our distribution track record, we are declaring a DPU of INR 4.12, which aligns with the full-year guidance we provided of INR 16.48. On the operational side, our weighted average quarterly transmission availability is around 99.4%. The solar capacity utilization factor stands at 20.9%, and RTE is at 88.6% versus <<inaudible>>. We believe we have managed to deliver superior total returns and sustain DPUs through stable operations. The next slide simply outlines where we captured the first utility scale back storage project, which you commissioned in Gujarat together with partner ONGC — the story is in the document — and <<inaudible>> tech, and we launched it at the ET Energy Leadership Summit earlier this year.

Harsh Shah

executive
#6

<<inaudible>> has been launched and is now available for publication in India. I really encourage all of you to scan that QR code — it will take you to the documentary, and then you'll hear the story of how we landed our first big project, roughly 380 megawatt hours in Gujarat. Moving to the industry update on the next slide, power demand is now rising quarter-on-quarter. And given the long-term trajectory the government anticipates for both power demand and power consumption growth, we expect that to play out across the next 10 years. With that in mind, various parts of the government are working to make sure enough infrastructure projects get built around that — mainly around transmission and BESS — and you're seeing it just last month, with at least 2 cabinet proposals that have come forward for green energy corridors as well as new battery capacities. So launching these projects is certainly the government's top priority, and we believe we're in a good position to target and win some of them profitably. The next slide addresses what's driving this demand: the grid is becoming the binding constraint, while we, as a country, have mastered the art of building renewable projects and building more.

Harsh Shah

executive
#7

I think the grid has now turned into the binding constraint, and so putting more money into it is essential — something the government has acknowledged, and projects have been announced on that basis. The second essential piece is storage, which previously was optional; if I recall, we were experimenting 3 years back, while today it is mainstream. So various efforts are being made by the government, beginning with stand-alone battery storage — where we also operate SBRE projects — as well as making sure that every renewable project has a couple of hours of storage, including discom, in that, so that you're seeing only BESS turn into 1 big shift to make sure we can mitigate the intermittency of renewables. On demand growth, I mean, demand has a structure that has become seasonal. We are seeing demand growth quarter-on-quarter. And with rising electrification, more access to electricity, as well as affordability, we think this demand will keep growing for at least 10 years. Is that — I mean, our growth has increased and with a imperative, but on the other hand, there are many risks emerging, including grid curtailments and storage issues. So that is something which is the government's priority, and you see opportunities coming up for that.

Harsh Shah

executive
#8

The final item, I'd say, is moving somewhat more slowly than one might have anticipated, but one of the priorities we're focused on is capital recycling in, to genuinely keep capital free around the stocking already <<inaudible>>. We view that as a mid-market opportunity in which we can take part. On the next slide, as we've been doing, we've just shown the bidding activity as things stand today: we have roughly INR 1,24,000 crores of active bids in transmission and that sector, and over the last 12 to 18 months this figure has stayed consistently high. So we do see a very significant volume of opportunities unfolding in the market. Turning to operating performance, I'd like to invite my colleague Sanil to walk you through that.

Sanil Namboodiripad

executive
#9

Thanks, Harsh. Good afternoon, everyone. Slide #11 covers how we performed operationally. On the safety side, we recorded 0 medical treatment cases, first aid cases and lost time incidents. That said, one of our substations — a sonar substation at the Gurgaon Palwal project — had a fire incident, and it impacted transformer availability at that site. Replacement of those transformers is underway, and we expect full operations by May 2027. The cost impact has been factored into the latest valuation. Insurance claims for this have also been filed. That is why, on the right side, you can see the availability for GPTL. Still, every other asset in the transmission business sits well above our targets. Turning to Q2 FY '27 performance, solar generation was good, at 562.3 million units with a 22% COF. For the transmission network, availability on a weighted average revenue basis was 99.37%. On battery storage projects — the 2 operating ones, KBPL and GBPL — weighted average availability came in at 97.7%, well above the 95% requirement, and round trip efficiency was 88.56%, above the 85% requirement, as Harsh was explaining to you. On reliability trends, trips per element were 0.1, and most trips were caused by bad weather, lightning and thunderstone, some insulator failures, and a couple of relay maloperations.

Sanil Namboodiripad

executive
#10

Beyond that, the equipment is performing well. Solar availability averaged roughly 96.7%. That figure dipped somewhat due to inverter breakdowns at our Maharashtra projects. Moving to the right-hand side, if you look at the table, it compares Q2 FY '26 with '27. Trips per element have gone down. Training manhours are nearly unchanged, continuing the pattern of strong training practices we follow across our assets. On lost time incidents, last year we had 1 incident, while this year we had none during the quarter; unsafe-condition reporting and rectification, along with corrective and preventive actions, are in place. <<inaudible>> reporting is likewise in place and being acted upon. Turning to solar generation, you can see improvement this year versus last year, and plant availability has stayed roughly the same as a year ago. Meghana, over to you for the next slide.

Meghana Pandit

executive
#11

Okay, thank you Sanil. On the next slide we have the ESG update, which relates to the sustainability report we began work on close to 2 years ago; the report covering fiscal year '25, '26 came out during the second quarter. Essentially, this sustainability report addresses ESG performance throughout IndiGrid's whole portfolio, and it has been prepared with reference to the GRI standards 2021, while also being aligned with the IFC performance standards and the UN SDG. When it comes to environment, social and governance, all the relevant disclosures — covering the type of renewable energy generated, the type of facilities, the type of governance norms, and the disclosures we make — are captured in this report. We have also included the link on this slide so you can access it. Moving on, Slide #13 addresses our Q2 FY '27 financial performance. Reported revenues for Q2 FY '27 rose 59%, reaching INR 1,315 crores, versus INR 827 crores in the corresponding Q2 FY '26. EBITDA was up 18.3%, at INR 858 crores, compared with INR 725 crores in Q2 of last year. This growth came on the back of acquisitions we completed over the past 1 year in both the transmission and solar businesses.

Meghana Pandit

executive
#12

Operational revenue and EBITDA for the matching quarters rose 8.4% and 7.9%, respectively. NDCF for quarter 2 came in at INR 380-odd crores, up 4.7% from INR 363 crores in Q2 of FY '26. Distribution per unit for Q2 is INR 4.12 per unit, which is 3% higher than INR 4 in the same quarter a year ago. Collection and receivable days across the transmission asset business units came in at 103% versus 108% on a Y-o-Y basis. DSO days — that's days sales outstanding — came in at 37 days as of September 30, against 35 days, more or less in that same range. On the solar assets, collections were about 94% versus 89% in Q2 FY '26. And once again, DSO days improved substantially to roughly 35 days as of September '26, compared with 51 days in September '25. Turning to Slide #14 on the distribution update. As I said earlier, the distribution for the quarter per unit is INR 4.12, split into interest and capital repayment of INR 3.19 and INR 0.93 per unit. Outstanding units are at 95.26 crores following the fund raise we completed earlier this year, versus 83 crore units last year.

Meghana Pandit

executive
#13

The gross distribution comes to roughly INR 396 crores. The record date for that is November 11, 2026, and the tentative distribution date will mostly fall on or before November 18. Net asset value per unit was approximately INR 138.5. This was affected in the second quarter mainly because of the upward revision of the risk free rate, and there has also been a change in the corporate tax rate at the SPV level, which largely impacted things — it's a noncash impact tied to the deferred tax implication. In total, roughly INR 125.56 per unit, amounting to INR 8,433 crores, has been distributed to investors since listing, including the Q2 FY '27 distribution, which works out to an annual distribution trend of about 5.4% CAGR over the last 5 years. INR 4.12 again, in line with the annual DPU guidance of INR 16.48 per unit for FY '27. Slide #15 covers the consolidated EBITDA to NDCF net distributable cash flow waterfall. EBITDA at the SPV level totaled INR 880, which was adjusted for working capital movements, CapEx-related movements and tax, bringing NDCF at the SPV to INR 810 crores. From NDCF at STV to NDCF generated at the trust level, adjusting for expenses — mainly the finance cost and working capital movements.

Meghana Pandit

executive
#14

For the quarter, NDCF came in at INR 380 crores, and with a distribution of INR 4.12 for the quarter, that works out to 392. So effectively, we drew down INR 12 crores from the results during this quarter. Following that, the NDCF reserve balance is roughly INR 510 crores, which again provides coverage for nearly 1.5 quarters of distribution — a healthy level of reserves that ensures stability and sustainability for you. Turning to Slide #16, the balance sheet: Indigrid remains AAA rated by CRISIL, ICRA and India Ratings. As of September 30, the average cost of debt is approximately 7.46%, and net debt to AUM leverage ratio sits at 60.4%. Of the total gross borrowing of INR 215 billion, almost 86% is fixed rate borrowing. The cash balance is again at a healthy INR 15.68 billion, with a very healthy interest coverage ratio of 1.99x. Gross borrowing again consists of NCDs at 69% and term loans and ECB at 31%, all largely diversified and subscribed by various investors. The bottom chart on the slide covers the refinancing schedule, which for FY '27 is a very low figure of INR 8.5 billion.

Meghana Pandit

executive
#15

The remaining piece, once more, is a borrowing profile that is quite well diversified and spread out in terms, so that we avoid clustering any significant portion of refinancing into one specific year. Turning to Slide #17, we go on with the superior risk-adjusted total return for investors — total returns, that is, the sum of distribution plus price change — which for IndiGrid comes to 203% in absolute terms and 13% annualized from the moment we listed. Set against that, beta, the risk metric, is 0.09%, extremely near 0 when compared with both pure-play debt and pure-play equity indices, and we can observe that IndiGrid keeps delivering a risk-adjusted total return. Onto Slide #18, the business outlook. On portfolio strategy, given the healthy pipeline of projects that EnerGrid has won, our focus remains on greenfield development, and we aim to add assets of roughly INR 2,000 crores from EnerGrid in the course of this fiscal. Beyond that, we will proactively take part in greenfield opportunities and in brownfield acquisitions from the market, across power transmission, battery energy and the renewable portfolio alike. Our focus stays on delivering the DPU guidance of INR 16.48 for FY '27, supported by disciplined capital development.

Meghana Pandit

executive
#16

Balance sheet strength remains another key area we keep our attention on. We have to stay highly aware of interest expenses, given where the interest rate cycle sits in the market, and also make sure we extend how the tenure profile is structured. In the same way, keep leverage prudent, with enough headroom to finance future growth. Resilient asset management is the third pillar as well, making sure we hold the highest availability — 99.5% across the operational transmission portfolio, and on the CUF side for the solar portfolio too. We are looking at strengthening — constantly strengthening — our O&M capabilities, working out how digital and predictive analytics can be applied to maintaining and sustaining the portfolio, and also upholding world-class EHS and ESG practices. On industry stewardship as well, we proactively take part in policy shaping and industry dialogues throughout the electricity sector and the InvIT sector, and make sure we build broader visibility for Integrated and InvIT SaaS platforms. With that, we will pause here, and we can move on to the question-and-answer session, please.

Operator

operator
#17

<<operator_script>> Our first question comes from <<inaudible>> at Bhandan AMC.

Analyst

analyst
#18

Nice work on those results. Can you hear me okay?

Harsh Shah

executive
#19

Yes.

Analyst

analyst
#20

Sir, net debt relative to AUM sits at roughly 60-odd percent. So, do you have any plans to approach the capital market soon? Any guidance on that?

Harsh Shah

executive
#21

Like I said, there isn’t any plan right now to go straight to the capital markets. Normally, we’ve headed to the markets for capital once we reach the 64% to 65% range. So yes, as things stand, we have no other plan to go out and do that ahead of time. We’ll hold off until we have additional assets and further growth, and at that point we’ll consider it.

Analyst

analyst
#22

All right. And sir, I believe our NAV has fallen from INR 140 down to INR 138. As Meghna ma'am said, that's because — I mean, it's noted in your PBT that this stems from the risk-free rate rising from 6.8% to 7.2%, and that's largely the reason. So do we have any breakdown showing — I mean, is the INR 10, INR 8 decline attributable to the risk-free rate, or is there some split between the rise in the risk-free rate and the change in the effective tax rate at the SPV level?

Harsh Shah

executive
#23

Absolutely. I believe we've already put out the valuation report along with its underlying assumptions. Someone has to go through that analysis and then arrive at a conclusion. That said, I'd characterize it this way: roughly 50% of the impact comes from the rate increase, or from other G-SEC increases, right, as they move upward. And somewhere between 25% and 30% stems from the notional tax rate being changed, correct? So these are all noncash items, but we have established the standards we follow for valuation. And whenever an assumption shifts — be it tax or anything else — we're required to reflect it. That is exactly what shows up in the valuation figures.

Analyst

analyst
#24

Right. And sir, the remaining 10% — sorry, I mean the 10%, 20% — that will be owed on the distribution that's already been paid out, correct?

Harsh Shah

executive
#25

Right, there’s going to be a bit of distribution — some of the future value of assets will move nearer to that. So yes, it nets out.

Analyst

analyst
#26

Okay. And sir, I think, any plans to change the distribution structure, as in we are very high on interest. And I think we are very light on capital repayment and dividends. But now since dividends have become — I mean, tax-free for unitholders, so are we planning — I mean, if we can kind of make it more taxation efficient for unitholders?

Harsh Shah

executive
#27

Honestly, that isn't something we have control over. Our approach to distributing income is really driven by rules — specifically, by tax law. So, whenever a certain amount of interest comes in from a subsidiary, that same amount has to be passed along to unitholders as interest. And when it's a capital repayment, we have to mirror it as a capital repayment to unitholders. In other words, we simply comply with what the CBDT Act lays out. That leaves us with only limited room to maneuver, right? So I don't see us being able to change that. On top of that, every investor falls under a different tax jurisdiction, right? One person pays tax at the marginal rate, another pays 0 tax, and someone else pays 5%. So for us to work out what would be best for each individual shareholder is extremely difficult. And beyond that, every decision we make will also affect the cash outflow for tax at the SPV level. So our preference is to stay with what we're already doing and keep things neutral.

Operator

operator
#28

<<operator_script>> Our following question comes from Amit, who is calling as an individual investor.

Speaker

unknown
#29

Amit Chakravarthi here, calling from Kolkata. Congrats on the strong results and on being a pioneer in BESS. My question is about BESS specifically: with renewable energy expanding, demand for BESS keeps climbing. And since IndigGate has the knowledge and know-how to support BESS projects, could we grow that into a separate line of business? Any thoughts on that — say, supporting factories with BESS, or EV charging stations? So anything beyond transmission lines where BESS could stand as its own line of business?

Harsh Shah

executive
#30

Thanks, Amit. So I think we’re — okay, so — first, we only engage in businesses that the harmonized list from DEA and the Ministry of Finance classifies as infrastructure. I’m not certain that many of those other businesses are actually categorized as infrastructure, so whether they could come within our scope is unclear. And beyond that, frankly, we really need to pursue things that are scalable. And as we see it today, the opportunities you brought up — whether EV chargers or others — carry, in our view, considerable risk around development, technology redundancy or obsolescence, and on top of that the returns aren’t particularly attractive unless you’re prepared to take merchant risk, which is consumer risk. As you can see across our whole business, we have very limited or essentially no merchant risk where we depend on what price the consumer pays. So we favor long-term contracted cash flow, and the models in many of those segments haven’t evolved to provide that. There are certain segments where it has evolved, but then the scale isn’t there. We wouldn’t want to make an INR 100 crore investment or an INR 200 crore investment, because relative to our size it wouldn’t be economical for us to really concentrate on that.

Harsh Shah

executive
#31

Right, given the magnitude involved, whatever we pursue has to be scalable, sizable, and also deliver a lasting impact on operating cash flow. So as things stand, nothing along those lines is showing up for us in battery storage projects. Instead, what we've witnessed is extremely aggressive bidding on utility-scale battery projects, and that's precisely where we pulled back and chose not to participate, since ultimately we want to conduct business at a sensible return. And if there are parties willing to accept an aggressive return, then I think we're comfortable stepping aside. So it all hinges on scale, return, and the opportunity set that's out there.

Operator

operator
#32

Our next question comes from Pankaj at Avis Capital.

Analyst

analyst
#33

I've got a question about BESS, following on from the earlier participants. What does the revenue model typically look like on the BESS side? Is it very similar to how we do things in solar and transmission projects? And a related question: what's the typical ROI we actually work with on BESS? From what I understand from Layan, it seems to have a much lower residual value. So does it really make a lot of commercial sense for us? Or is it very different from the other businesses we're in?

Harsh Shah

executive
#34

Sure, sure. Okay, so let me respond to your questions on a few levels, roughly 2 or 3. First, is this comparable to what we already do? The BESS portfolio we hold today looks a great deal like the businesses we run now. These are take-or-pay annuity contracts signed with various utilities — BRPL, VNL, and now NVVL. Under these agreements, we're required to deliver RTE efficiency and to be available for either a single cycle of 4 hours or 2 cycles of 2 hours, whichever the concession agreement specifies. But suppose, for instance, our customers don't use that capacity, right? And as things stand, they use only 1 cycle rather than 2 cycles or 4 cycles — or rather 0 cycles rather than 1 cycle. Because of how our contract is set up, we still get paid the amount we planned for, right? So it functions as a fixed take-or-pay annuity contract that pays us provided we keep up our availability and efficiency. That makes it quite close to what we do in transmission or solar — nearer to transmission. So it's very straightforward. Yes, residual value is limited. I wouldn't call it 0, since there's substantial metal recycling value and plenty of instruments that come back at the end of the 10th or 15th year, depending on the concession agreement and on how heavily the battery has been used over that period.

Harsh Shah

executive
#35

That said, it's still a comparatively modest figure. If we're doing battery or transmission, our return thresholds are unchanged. On a battery project, we'd still want to hit 12%, 13% IRR. What I mean is, if it's already under construction, likely somewhat above 13% — so our return threshold stays roughly the same as that. Among the projects we've won, we've achieved considerably more than that, in part due to good fortune. We had built projects earlier, and after that, battery prices came down. Now they've risen again. And we executed with discipline by hedging our cost, dollar, everything. So we've earned somewhat above 13%, but in effect, we aim for somewhere within that range.

Operator

operator
#36

Our next question comes from the line of Raj Kadam from Nuvama.

Analyst

analyst
#37

Congrats on the strong results. I have just a few questions. Historically, Individual has never traded at a premium like this relative to reported NAV. So looking ahead, what could drive NAV growth from this point? And how do you view distribution tax efficiency going forward?

Harsh Shah

executive
#38

Thank you. Now, on NAV growth — I'd say that growth comes from basically 2 or 3 factors. The first is a passive factor that isn't in our hands: it's whatever event has occurred. Take interest rates rising — NAV falls, correct? Simple. It reflects what the assets are fairly worth today. So that's one impact. The market factor moves NAV around. And when it drops, NAV rises. But I'd call that not genuine NAV growth. It merely reflects what the assets are currently worth. Real NAV growth occurs when we buy projects, or we build them and then buy them, at a lower cost of capital. So accretive projects push NAV higher. As of today, EnerGrid is executing roughly INR 12,000 crores of projects for which agreements are signed, and we'll be acquiring them across the coming 3, 4 years. We haven't factored any NAV increase from that into the current NAV. It's essentially just the value of current assets. So as those INR 12,000 crores of projects get added to the balance sheet over the next 3 to 4 years, whatever the case, NAV will see accretion.

Harsh Shah

executive
#39

The exact amount obviously hinges on the timing of our additions, and although the value itself is set, what the rescue rate will be at that point, and so on, remains a question. Still, a reasonably intelligent analysis can be done to reach a conclusion about what NAV will be 4 years out if we simply add these INR 12,000 crore projects. And that's because the cash flows get disclosed. So I think one can run that number, but the sole route to NAV growth is adding projects at good returns.

Analyst

analyst
#40

All right, so you mentioned that the bulk of these assets will likely be picked up in maybe 3 to 4 years. With that in mind, looking at the near term and specifically the distribution piece, do you see the distribution guidance we have for the next few years getting revised upward?

Harsh Shah

executive
#41

Okay, so first, when I mention 3 to 4 years, that refers to the longest project, which will take 3 to 4 years. Some projects are being acquired by us this year, others next year, and some the year after that. So it's a matter of sequence. The overall figure stands at INR 12,000 crores, though it will be acquired across a span of time. And we might win new projects that get added. We might acquire new projects that will be added. So it's quite a dynamic situation. On distribution growth, I think that's a question we answer only in quarter 4, after looking at all the projects we've acquired, what the forecast is, what the cost of capital looks like. All of that analysis gets done before that decision is made at the end of the year by the Board. And this year will be no different. We will decide in quarter 4 whether we are increasing the DPU or not. So I think that's something that will come out in the quarter 4 meeting.

Operator

operator
#42

Our next question comes from the line of Rashmika with Rashmika Enterprises.

Analyst

analyst
#43

I've got 2 questions for you. First, on one of the earlier conference calls, you mentioned keeping the distribution at INR 16.48 per unit. So is the plan now just to hold INR 16.48, or not to raise it? What's the outlook for the next 1 year? Does the distribution stay at INR16.48 -- or does it go up? And if it goes up, how much of an increase do you anticipate?

Harsh Shah

executive
#44

Like I said, each year at our final Board meeting we prepare a distribution forecast, or guidance, and then we disclose it. For this year, in quarter 4 — that is, quarter 4 of last year — we provided guidance of INR 16.48, and that is what we are working toward. Whether it will rise next year is something only the quarter 4 Board meeting will settle. Right now, there has been no discussion on that. Will it stay at INR 16.48? Yes, most likely it will remain at least INR 16.48. Whether it goes up is a decision that will come with the quarter 4 results. But once we have raised the DPU, we have fairly good confidence that we can maintain it for a few years. Otherwise, we would not increase it. So I think for now you can take it as assuming INR 16.48 should continue. Whether it will grow, though, will only be answered at the end of the year.

Analyst

analyst
#45

I realize you'll settle on the size of the increase at a later point. The exact amount doesn't matter to me. What I simply want to find out is whether an increase is going to happen at all down the road.

Harsh Shah

executive
#46

I’m not able to answer that question, correct? Whether we raise it is up to our Board’s decision. That decision gets made only at the end of the year. So right now, there’s no way to answer it.

Analyst

analyst
#47

My next question is this: during the most recent quarter, our revenues rose very substantially compared with the prior quarter, yet profit after tax dropped sharply. Why is there this divergence — revenue going up while profit after tax goes down? What's causing the decline in profit after tax? And when will we return to the earlier levels of tax — the earlier levels of PAT margin?

Harsh Shah

executive
#48

We don’t monitor PAT as a numeric metric. In our view, tracking PAT isn’t essential for an InvIT. What we refer to — what we actually track — is a measure called net distributable cash flow, the NDCF figure we reported, since none of our distributions are tied to PAT, unlike a typical listed company where dividends come from PAT and can only be paid from PAT profits. For an InvIT, we’re able to distribute NDCF, correct, meaning net distributable cash flow. That’s the number that matters to us. Now, one reason PAT rises — or rather PAT falls — is that as we bring in more projects, greater interest expense lands on the balance sheet because we diluted and raised capital early. Then, when we acquire a project, interest for that acquisition comes against the extra revenue, and as a result PAT declines. Yet NDCF increases, because the gap between the EBITDA you generate from the project and the interest cost produces additional NDCF, while PAT may decline. So the key figure for us, and the one we actively monitor, is net distributable cash flows.

Harsh Shah

executive
#49

And to be honest, that figure for net distributable cash flow has risen both compared with a year earlier and versus the prior quarter. So I'd say that's the proper way to view it. PAT is inevitably going to fluctuate based on when we raise capital and when we acquire projects — that number can move either up or down.

Analyst

analyst
#50

All right, my final question for you. Looking out over 5 years, would that INR 16.48 distribution go up, or would it stay where it is? Over a 5-year horizon, does it rise, or does it hold steady?

Harsh Shah

executive
#51

With any luck it will go up, but that's just my hope, right, since plenty of factors have to fall into place. Over the past 7 years we've raised the DPU. In fact, it's more than 7 years — as the track record shows, we have grown the DPU. So our focus, our effort, our approach and intention is to work toward raising DPU. Will it rise or not? Obviously we'll have to wait, because we cannot give a 5-year guidance. But historically, from INR 11.75 when we began to INR 16.48, we have raised DPU consistently on a year-on-year basis. So we've delivered a DPU increase CAGR of almost 5%. Unfortunately, we'll have to lean on our past track record and assume what will happen over the next 5 years. We can't give a 5-year guidance. But as I said, our intention is clearly to raise the DPU. Whether we can or not depends on business performance, acquisition, markets, interest rate, everything, but we are working to increase it. I hope that answers that question for you.

Operator

operator
#52

That brings us to the end of the questions. At this point, I'll pass the conference back to Mr. Harsh Shah, who will offer some closing remarks.

Harsh Shah

executive
#53

Thanks to all of you for being on today's call. I'd like to wish each of you a happy Dhanteras. Then, as I said before, what we're focused on is carrying on with our approach of securing projects, carrying them out, handing them over, buying them and handing them over while producing better risk-adjusted returns, with attention on the distribution yield and, where we can, raising it. We've been doing this for many years. With luck, we can keep doing so consistently, particularly at a time when at least the electricity market is really exciting. We're seeing plenty of development CapEx opportunities arriving. Yet on the flip side, we're also seeing considerable competition, plus the cost of debt is climbing, or rate risk is climbing, which brings added difficulties for us. Still, on the whole, we do see a very positive picture, since we're seeing plenty of opportunities arriving. So thank you for all your backing and for supporting IndiGrid. We look forward to seeing you on the next call, and happy Dhanteras to the rest of you.

Operator

operator
#54

Thanks. That brings this conference to a close on behalf of Spark Institutional Equities Private Limited. We appreciate your participation, and you can go ahead and disconnect your lines now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Indigrid Infrastructure Trust transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Indigrid Infrastructure Trust earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Indigrid Infrastructure Trust or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.