J.K. Cement Limited (532644) Earnings Call Transcript & Summary

August 17, 2021

BSE Limited IN Materials Construction Materials earnings 52 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to the J.K. Cement's Q1 FY '22 Earnings Conference Call, hosted by PhillipCapital India Private Limited. [Operator Instructions] Please note that this conference is being recorded. I would now like to hand the conference over to Mr. Vaibhav Agarwal from PhillipCapital India Private Limited. Thank you, and over to you, sir.

Vaibhav Agarwal

analyst
#2

Thank you, Janice. Good evening, everyone. On behalf of PhillipCapital India Private Limited, we welcome you to the Q1 FY '22 call of J.K. Cement Limited. On the call, we have with us Mr. Ajay Kumar Saraogi, Deputy Managing Director and CFO; and Mr. Prashant Seth, President and Deputy CFO. I would like to mention on behalf of J.K. Cement Limited and its management that certain statements that may be made or discussed on the conference call may be forward-looking statements related to future developments and the current performance. These statements are subject to a number of risks, uncertainties and other important factors, which may cause the actual developments and the results to differ materially from the statements made. J.K. Cement Limited and the management of the company assumes no obligation to update or alter these forward-looking statements whether as a result of new information or future events or otherwise. I will now hand over the floor to the management of J.K. Cement Limited for their opening remarks, which will be followed by the interactive Q&A. Thank you, and over to you, sir.

Ajay Saraogi

executive
#3

Thank you, Vaibhav. Good evening. The Board of Directors met on 14th of August to review the working of the company for the first quarter, that is, April, June '21. I'll just give you a brief outline so that -- and then take up the question and answers for the time. The revenue from operations was INR 1,634 crores as against INR 2,052 crores of last quarter, a decline of 20%. And the EBITDA during the quarter was INR 400 crores as against INR 439 crores, a drop of 9%. The finance cost was INR 56 crores as against INR 53 crores, an increase of 6%. The profit before tax was INR 305 crores as against INR 355 crores, a drop of 14%. And the profit after tax was INR 208 crores as against INR 63 crores, an increase of 229%. This is because in the previous quarter, we had an extraordinary acceptance. The EPS for the year -- for the quarter was INR 26.95 as against INR 8.20. The EBITDA margin during the quarter was 24.95% as against 21.65%. As you would have already gone through the other details, I will just take up the question and answers. Thank you.

Operator

operator
#4

[Operator Instructions] The first question is from the line of Navin Sahadeo from Edelweiss.

Navin Sahadeo

analyst
#5

Hello?

Ajay Saraogi

executive
#6

Yes.

Navin Sahadeo

analyst
#7

Okay. I'm fine. I'm audible. And congratulations on a good set of numbers. So first of all, glad to see the new logo of J.K. Cement brand. Also, it's very nice to see the new template for the quarterly presentation. So it clearly shows the change of leadership at the top. Talking about which, I would like to understand if the young management at J.K. Cement, is there any vision of capacity creation or a milestone set by the company? Recently, we saw some other companies setting milestones or capacity targets. So with a young leadership at J.K. Cement, is there any capacity or any sort of a vision target that you would like to share at this point in time?

Ajay Saraogi

executive
#8

So Navin, at this point of time, we do not have a clear target. We say that we would like to -- in next 5 to 10 years, this would be our vision. We are working at it. We have various opportunities. So we are reviewing all those opportunities. And with that, looking to our working -- or what could be our target. And maybe very shortly, we will share that also with all of you. But at the same time, broadly, yes, we want to maintain our leadership in the region where we are. So we are primarily in the North. And as immediate plan, we are expanding our market. So we are setting up a plant -- green-field plant in Central India, where we have a potential to grow up to -- 15 million tonnes of capacity can be put up at that point -- at that location. So we can say, yes, we have plans for another 10 to 12 million tonnes already there. We have other opportunities, and we are working on that, and we will share the same with everybody shortly.

Navin Sahadeo

analyst
#9

Okay. That's helpful. Sir, my second question then was with regards to ESG. This is with reference to Slide 3 of your quarterly presentation, which has very specific targets set by the company for -- but these are like 2030, mainly towards CO2 emissions, the clinker factor, and most glaring, I think the green power percentage from 25% all the way up to 75%. So can you please help us understand how the company plans to achieve these targets? Are there -- is there any CapEx involved? Are there any milestones towards achieving these targets?

Prashant Seth

executive
#10

Yes, Navin, we have set up the milestone first towards the performance and the efficiencies, like improvement in the clinker ratio, increase in the blended cement ratio and then reduction in the power consumption, thermal substitution -- increase in the thermal substitution by using the alternate fuels and in more green power. One is that green power on account of the core emphasis on the waste heat recovery power now instead of the coal-based power. So one is in the new expansion at Panna, we are only setting up for waste heat recovery power of 22 megawatts. There is no coal-based power plant. Further, we are also looking at possibilities of more tie-up for the solar and the wind power. So these all are the factors that will contribute to the reduction in the carbon emission.

Ajay Saraogi

executive
#11

I would like to add here, we are also planning a waste heat at our south plant. That is the only plant where we do not have a waste heat recovery system. So as a next step, we are also planning a waste heat recovery plant in the -- for the south plant. So we are conscious about our responsibilities, and we are working towards that. And this is a target which -- and we -- definitely, we are going to -- we have a team which reviews it, and it has also been seen by our CEO directly so that we do not slip over there. We are working in this direction. And we hope that we'll be able to achieve it.

Navin Sahadeo

analyst
#12

So just one follow-up on this because 75% to me, at least, it's a bit of a glaring number. So is there a broad breakup that how much will be waste heat? How much will be like the rest of the solar and wind? If you have a very broad breakup to that? Because I'll put it together in a context. C-Cement is probably the one company where the waste heat capacity is the highest amongst all the companies -- per tonne of cement, if I may say so. So that contributes around 50-odd percent of their total power requirements. So I'm just trying to understand that 75% when you say, how much of that will be waste heat and the balance that we're looking at?

Ajay Saraogi

executive
#13

So presently, we are 25%, and it is mainly driven by the waste heat. So as a next step, I don't -- we have -- so we can say definitely, going forward, 50% plus would be waste heat and balance should be for another power. So that's a broad number. So they'll be fine to catering to that. But definitely 50% plus should be waste heat.

Operator

operator
#14

[Operator Instructions] The next question is from the line of Amit Murarka from Motilal Oswal AMC.

Amit Murarka

analyst
#15

So first question is on employee cost. So in this quarter, I see that there's a significant jump in cost on a Q-o-Q basis. So what would be the reason for that?

Prashant Seth

executive
#16

So the increase is really on account of the increments released from 1st of April. So 10% cost increase is on account of the increments quarter-on-quarter. And balance is like some new recruitments are taking place on account of the expanded markets and the expansion.

Amit Murarka

analyst
#17

So we should see this as a sustainable number then?

Prashant Seth

executive
#18

Yes, yes. That is sustainable number. Yes.

Amit Murarka

analyst
#19

Okay. And also in terms of the grey cement revenue, just wanted to confirm, there is no one-off in that, right?

Prashant Seth

executive
#20

No, there is no one-off.

Amit Murarka

analyst
#21

Okay. Okay. No, just on a Q-on-Q basis, the realization seems to have improved quite a bit. I guess that would be because of lower clinker sales in that sense?

Prashant Seth

executive
#22

It has improved, yes.

Ajay Saraogi

executive
#23

No, sir, the per tonne realization improvement is also because of the mix -- change in mix because in the previous quarter, we had clinker sales. And since the volume was also higher in that quarter, the non-trade sales was also higher.

Amit Murarka

analyst
#24

Right. Yes, that's what I guessed. Actually, just wanted to check if there's one-off. Fine. Also, could you share the fuel mix in this quarter?

Prashant Seth

executive
#25

It's around 40% of pet coke, and balance imported coal and the alternate fuels.

Amit Murarka

analyst
#26

Sure. And also, any further update on the Panna plant? The groundbreaking, I believe, has happened, I think, and you mentioned that major equipments have been ordered.

Ajay Saraogi

executive
#27

Yes. So on the Panna plant, we -- the groundbreaking was done on 5th of May. And orders for all the main plant and equipment, the civil contractor and the mechanical, everything has already been finalized. They are already at the site. And the -- I mean, lot of work has already been done in pre-monsoon -- I mean, we've been able to complete the filing. And even the work on the preheater building and everything has already started. So there is a good progress, which has been done so far.

Amit Murarka

analyst
#28

Right. And -- so the Panna plant and the Hamirpur grinding unit, everything will be commissioned by March '23, right?

Ajay Saraogi

executive
#29

Yes, yes. That is our -- by March '23, we should be commissioning everything.

Amit Murarka

analyst
#30

Sure. And lastly, could you just touch upon the pricing during the monsoon months of July and August? How much has the correction been, let's say, post June?

Ajay Saraogi

executive
#31

No, there is a dip in the pricing of about INR 5 to INR 6 a bag.

Amit Murarka

analyst
#32

So INR 5 to INR 6, both in North or South -- and South or South has been more?

Ajay Saraogi

executive
#33

Yes. It is -- the South has been marginally higher.

Amit Murarka

analyst
#34

Okay. And are the non-trade pricing holding -- prices holding on as in the gap between trade and non-trade?

Ajay Saraogi

executive
#35

Well, the gap between trade and non-trade would be around INR 30 a bag.

Amit Murarka

analyst
#36

Okay, sure. And lastly, just quickly on demand. So we saw a good pickup in June. I believe July was a bit softer. And would it be right to say that August would be even softer than July?

Ajay Saraogi

executive
#37

Yes, hopefully, we could may be at the same level, but still, I mean, as of now, it's more or less same.

Operator

operator
#38

[Operator Instructions] The next question is from the line of Prateek Kumar from Antique Stock Broking.

Prateek Kumar

analyst
#39

My first question is regarding the white cement realization during this quarter, they had particularly some pertinent decline of 3.5%, 4% quarter-on-quarter, like versus March quarter? Any specific reasons there or change in product, sir?

Ajay Saraogi

executive
#40

Yes. See, as you know, the white cement is mostly the white business, both white cement and putty, they are more sold in the urban areas. So third quarter had 2 -- practically, 2 months of lockdown. And because of the lockdown and closure of the [indiscernible] has affected the white market. The white volumes are also lower during this quarter. April and May were really bad for the white cement business.

Prateek Kumar

analyst
#41

So the putty component in the mix is higher, so the average price is lower?

Ajay Saraogi

executive
#42

Yes. The putty mix is lower.

Prateek Kumar

analyst
#43

Putty mix is lower?

Ajay Saraogi

executive
#44

Yes. Because there's -- there were lower volumes of putty and white cement during the quarter.

Prateek Kumar

analyst
#45

But I'm asking like on like-for-like numbers only for white cement versus in March quarter -- I mean June quarter versus March quarter?

Ajay Saraogi

executive
#46

That's what I'm saying. In the month of June quarter, the volumes of white was -- I will give you the exact volumes. The white was -- the white volumes was 2,63,000 tonnes as against 3,93,000 tonnes in the previous quarter.

Prateek Kumar

analyst
#47

Yes. Okay. Maybe I'll take that offline. My second question is on -- sir, on your CapEx. So including -- I think you have mentioned some numbers on Panna CapEx on -- in your annual report. You're looking to do INR 1,600 crores related to Panna in FY '23. So what is the consolidated CapEx we are expecting for FY '22 and FY '23?

Prashant Seth

executive
#48

No. CapEx for FY '22 with the balance activities or balance payments of the 4.2 million expansion and the Nimbahera upgradation work which is going on, with Panna expansion, we are expecting around INR 1,250 crores of CapEx in this year. And our total CapEx in the next year would be INR 1,400 crores.

Prateek Kumar

analyst
#49

Okay. But our annual report mentions INR 1,600 crores Panna-related CapEx in FY '23. So that number is not correct or something?

Prashant Seth

executive
#50

No INR 1,600 crore CapEx is on Panna, then we have Hamirpur grinding unit also.

Prateek Kumar

analyst
#51

Right. Okay. And this -- earlier, we were also aggressively like targeting completion of this unit in -- by December quarter itself of '22 -- so December '22. So now we are like quite firm on this getting by March '23?

Ajay Saraogi

executive
#52

So -- see, December is still on, but the cost of the present -- because of the COVID situation, so we are -- I mean to be on a safer side, we are talking about March '23. But internally, we're still work -- we are trying to work towards till December '22 as a commissioning.

Operator

operator
#53

[Operator Instructions] The next question is from the line of [ Shanti Patel ] from [ Shanti Patel Investment ].

Unknown Analyst

analyst
#54

My question is, what is our capacity utilization in the previous quarter, that is, Q1?

Ajay Saraogi

executive
#55

71%.

Unknown Analyst

analyst
#56

71%. Normally, that is the case? Or it is a little lower than what it should be?

Ajay Saraogi

executive
#57

No. See, we have seen a very high capacity utilization in the previous quarter. So we do not expect lower than this because we lost 1 month because of the COVID. That is why, also, the utilization was low.

Unknown Analyst

analyst
#58

Okay. Second thing, after the expansion gets over, either in the last quarter, that is, December, or worse comes, towards March, as you reported, what will be the contribution in terms of turnover from that extra capacity, which will come into force?

Ajay Saraogi

executive
#59

So see, that capacity is 4 million tonnes. So out of -- we have 14 million tonnes present capacity. So around 25% additional volumes comes -- there should be an additional volumes coming from -- after the expansion.

Unknown Analyst

analyst
#60

And that expansion -- the capacity utilization will be -- how it will be, I mean, playing around?

Ajay Saraogi

executive
#61

60% in the year 1.

Unknown Analyst

analyst
#62

50%, correct.

Ajay Saraogi

executive
#63

60%.

Unknown Analyst

analyst
#64

60%, okay.

Ajay Saraogi

executive
#65

So we expect about 50%, 60% in year 1 and ramping up to 75% for the next -- subsequent year.

Operator

operator
#66

[Operator Instructions] The next question is from the line of [ Jiya Chhabria ] from [ Auris Wealth ]. [Operator Instructions] As there's no response from the current participant, we'll take the next question from the line of Shravan Shah from Dolat Capital. [Operator Instructions]

Shravan Shah

analyst
#67

Sir, first of all, the remaining CapEx for the 4.2 MTPA, INR 50 crores, INR 60 crores, is it done? Or is it still pending?

Ajay Saraogi

executive
#68

So part of it is already done, only some balancing for the OLBC remains. So I would say a bit by September, everything should be completed.

Shravan Shah

analyst
#69

Okay, okay. And in terms of the CapEx, when we are saying that INR 12.5 -- INR 1,250 crores for this year, so last time, we probably have given around INR 900-odd crores for Panna this year, and next year, INR 12 crores to INR 13 crores -- INR 1,200 crores to INR 1,300 crores. So that remains the same? Nothing changes?

Ajay Saraogi

executive
#70

Yes. That remains the same. Panna is about INR 900 crores and balance INR 350 crores is towards the normal CapEx and some CapEx on the spillover of 4.2 million tonnes and on the upgradation of Line 3.

Shravan Shah

analyst
#71

Okay. Okay. Got it. And secondly, last time, we have talked about that we are keeping a benchmark in terms of the EBITDA margin, 25%. So that still remains intact?

Ajay Saraogi

executive
#72

Yes, in the first quarter, we are close to -- we are 24.95%. Our EBITDA margins are well in line. So we are working towards that.

Shravan Shah

analyst
#73

Okay. And sir...

Ajay Saraogi

executive
#74

We have 24.95% in the first quarter.

Shravan Shah

analyst
#75

Yes. And sir, I need a couple of data points, trade share, lead distance, OPC/PPC, sir?

Prashant Seth

executive
#76

Yes, one second. The trade was 68% in this quarter. And the blended cement was 62%. And average lead distance was 450 kilometers.

Shravan Shah

analyst
#77

450 kilometers, slightly lower. So income -- yes. So -- and sir, 2 aspects in terms of the pet coke and the coal cost, which is increasing and the diesel price. And at the same time, we are also expecting some savings from the upgradation of the Line 3 Nimbahera. So net-net, how do we see it in terms of going forward cost increase and cost savings on this aspect?

Ajay Saraogi

executive
#78

So -- see, going forward, as far as the cost increase is there, even on the pet coke -- because we had a good inventory and some contracts, we could get some opportunate volumes. So that is why, the whole increase of the pet coke is not expected this quarter. And even in the present quarter also, only part of, say, 50% of the same would be [indiscernible] the full impact of the cost increase of the pet [Technical Difficulty] from the third quarter onwards. The diesel price increase impact is also -- already there with pet costs, but we are able to -- I mean, the benefits of -- I mean, the expansion, which we have concluded and the lower cost -- and the cost -- various cost-cutting measures which we have taken, that -- with that, we are not seeing overall increase in the cost. But even in this quarter, there would be some increase in the cost because of the Line 3 upgradation, the kiln is under shutdown, and we have to operate the low efficiency kiln, where we incurred higher cost. But the real savings of the expansion and retrofit [indiscernible] quarter 3 and -- which should be able to mitigate the cost increase because of pet coke and other things. Let's -- that is what, probably, we see on cost increase.

Shravan Shah

analyst
#79

Okay. Lastly, sir, a clarification in terms of this quarter, if I look at in terms of the -- our net debt has actually increased by INR 265-odd crores. So -- and if I combine the PAT plus depreciation, so that is a INR 274 crores and the CapEx would be around INR 190 crores, INR 200-odd crores. So is it fair to assume that the working capital has increased and that would have led to an increase in the net debt?

Ajay Saraogi

executive
#80

In case of net debt, this is a position of a stand-alone position. But we have also during this quarter, paid about INR 100 crores of debt for Fujairah. So the disposition of the net debt increased. One, yes, we have invested on the Panna, and we have paid INR 150 crores as our debt. That is the major reason for the increase in net debt.

Shravan Shah

analyst
#81

So our guidance of INR 3,000 crore net debt stands -- remains the same?

Ajay Saraogi

executive
#82

Yes, yes, yes. We will not -- I mean, that is a very -- on the higher side only. We -- on a net debt position of INR 3,000 crores, we will never cross that.

Operator

operator
#83

[Operator Instructions] The next question is from the line of Rajesh Ravi from HDFC Securities.

Rajesh Ravi

analyst
#84

Sir, would you please share the revenues and volumes for your U.A.E. operations?

Prashant Seth

executive
#85

Yes, for U.A.E., the volume was 1,03,000 tonnes.

Rajesh Ravi

analyst
#86

1,03,000 tonnes. And revenue?

Prashant Seth

executive
#87

Revenue, I will inform you separately.

Rajesh Ravi

analyst
#88

Okay. And how much of this was already booked in stand-alone?

Prashant Seth

executive
#89

Actually, difference of consolidated and stand-alone is the U.A.E. revenue.

Rajesh Ravi

analyst
#90

Okay, sure. That I'll get through. And how much of these was already booked in the stand-alone?

Prashant Seth

executive
#91

Pardon?

Rajesh Ravi

analyst
#92

How much of the U.A.E. volume is sourced to India operations? How much of it is sourced to India?

Ajay Saraogi

executive
#93

No. That's about 4,000 tonnes on a...

Rajesh Ravi

analyst
#94

Sir, only 4,000 tonnes in this quarter?

Ajay Saraogi

executive
#95

Sorry, 4,000 tonnes per month. It's about 12,000 tonnes.

Rajesh Ravi

analyst
#96

Okay. So the normal run rate was maintained?

Ajay Saraogi

executive
#97

So in this quarter, I mean, this is a normal run rate, but in this quarter because of the pandemic, volume numbers are lower.

Rajesh Ravi

analyst
#98

What was the volume number in this quarter?

Prashant Seth

executive
#99

12,000 tonnes.

Rajesh Ravi

analyst
#100

12,000 tonnes. Okay. And also, can you share what was the average fuel cost for you in Q1? And how is the situation in Q2?

Ajay Saraogi

executive
#101

No. Fuel cost, if you see, there is a 10% increase in the pet coke pricing. So overall, yes, because of the inventory and all that, in our case, the pet coke prices -- but the imported coal price has also gone up to the similar level. So overall, we can see that there is a 10% increase in the fuel cost.

Rajesh Ravi

analyst
#102

That is, you're talking of 2Q or Q1?

Ajay Saraogi

executive
#103

Q1.

Rajesh Ravi

analyst
#104

So Q1, 10% increase on an overall basis was versus fourth quarter, right?

Ajay Saraogi

executive
#105

Yes.

Rajesh Ravi

analyst
#106

And how much -- and what is the scenario in Q2 versus Q1?

Ajay Saraogi

executive
#107

Q2 scenario is even -- I mean, it is higher than the previous quarter. If you see the increase in the pricing, in the last quarter, pricing average at the present situation is like we have seen an increase of, say, INR 2,500 per tonne in the pet coke price from the average price of the previous quarter until now.

Rajesh Ravi

analyst
#108

Okay.

Ajay Saraogi

executive
#109

And similarly, the imported prices have also gone up by $25.

Rajesh Ravi

analyst
#110

Okay. So both of them are up by almost 25% or 25%, 30%?

Ajay Saraogi

executive
#111

Yes.

Rajesh Ravi

analyst
#112

And this is on consumption basis you are talking about or on purchase basis?

Ajay Saraogi

executive
#113

Purchase basis.

Rajesh Ravi

analyst
#114

Okay. So on a consumption basis, because you would be having some inventory of the lower cost, so the impact in 2Q may not be more than 10%, 15%?

Ajay Saraogi

executive
#115

Yes. Yes. On the consumption, it will be about 10% increase. But this is -- the procurement rates have gone up. So because of our inventory and the impact on us even in this second quarter would be only about 10%.

Prashant Seth

executive
#116

So the overall impact will be visible in the third quarter.

Rajesh Ravi

analyst
#117

Third quarter, right, right. And on the putty side, we are now 1.2 million tonne. What was the -- what is the total utilization in FY '21 for the putty?

Ajay Saraogi

executive
#118

So see, again, FY '21 for putty was -- last year was also partially affected because of COVID.

Rajesh Ravi

analyst
#119

Correct.

Ajay Saraogi

executive
#120

But with that, if we see the -- and then you are seeing effective CapEx at the beginning, the capacity were 9 lakh tonnes only. Again, in that, we did about 7 lakh tonnes of...

Prashant Seth

executive
#121

720.

Ajay Saraogi

executive
#122

So we did about 80% or -- if you take out the opening capacity.

Rajesh Ravi

analyst
#123

Okay.

Ajay Saraogi

executive
#124

It's about 80%. On our enhanced capacity, it looks like [Technical Difficulty]

Prashant Seth

executive
#125

So 55% on [Technical Difficulty]

Rajesh Ravi

analyst
#126

Hello? So it is 70% on the expanded capacity, you still have headroom for next 2 years...

Ajay Saraogi

executive
#127

So the putty capacity, now is keeping in view the peak month demand. It is not an average demand. So putty is a secular business. So we have to -- you have to have the capacity to meet out the peak demand.

Rajesh Ravi

analyst
#128

Correct. Okay. I was just looking at an aspect by when would you be looking to add further capacities and do we have brownfield expansion capabilities on the putty side?

Ajay Saraogi

executive
#129

So immediately, there is no need, and we are working out on what are the options and what we need to do looking to the increase in the demand for -- because we don't need any capacity at least for the -- up to fiscal '23.

Operator

operator
#130

[Operator Instructions] The next question is from the line of Hiten Boricha from Joindre Capital.

Hiten Boricha

analyst
#131

Sir, can you let me know what was the volume numbers for this quarter and for the last quarter?

Prashant Seth

executive
#132

Yes, sure.

Hiten Boricha

analyst
#133

Just stand-alone volume numbers, sir.

Prashant Seth

executive
#134

Yes, volume number for this quarter was like, overall, it was 3 million tonnes. And last quarter, it was 3.89 million tonnes.

Hiten Boricha

analyst
#135

Okay. And sir, my second question is on book-keeping side. Any changes in the cash and debt compared to last quarter?

Ajay Saraogi

executive
#136

So that is already given. Our cash position from last quarter has reduced from INR 1,707 crores to INR 1,411 crores, and the net -- the gross debt has also reduced from INR 2,841 crores to INR 2,810 crores.

Operator

operator
#137

The next question is from the line of Prateek Kumar from Antique Stock Broking.

Prateek Kumar

analyst
#138

I have this one question regarding amalgamation. Sir, when can we expect amalgamation of the Panna subsidiary with the stand-alone operations?

Ajay Saraogi

executive
#139

So we have just, I mean, finalized, and we are filing the amalgamation -- the scheme. So I think it should take another about 6 months' time -- 6 to 8 months' time minimum. It depends. We need to have certain confirmations from the various government authorities -- state government authorities for the merger, and -- so that we do not face any problems going forward. So I think keeping that in view, it should take about 6 to 8 months' time.

Operator

operator
#140

The next question is from the line of Amit Murarka from Motilal Oswal AMC.

Amit Murarka

analyst
#141

Sir, just a question on value-added products. So what would be the revenue that you are generating from these products as of now?

Ajay Saraogi

executive
#142

No. So we're not exactly sharing the numbers of value-added products. We would not be able to share the numbers separately because of business confidentiality.

Amit Murarka

analyst
#143

Okay. But when you classify it between grey and white cement, so is it added in white cement revenue? Where is it added?

Ajay Saraogi

executive
#144

Yes. Value-added products are part of the white business.

Amit Murarka

analyst
#145

Part of the white business revenue?

Ajay Saraogi

executive
#146

Yes, yes.

Operator

operator
#147

The next question is from the line of Nishant Bagrecha from InCred Capital.

Nishant Bagrecha

analyst
#148

Sir, I have a follow-up question from the earlier participant. So as your pet coke consumptions formed around 40% of the fuel mix during the quarter -- during the 1Q, and on quarter-on-quarter, it was -- I think in 4Q FY '21, it was 35%. So -- again, so the -- your pet coke prices have further increased by around INR 2,500 per tonne during this 2Q. So what would be the pet coke consumption going forward? It will increase here on? Or it will stay at the same around 40%?

Ajay Saraogi

executive
#149

So -- yes, we plan that we have sufficient inventory, and we could be able to maintain this 40% at least for the next 2 months. And then we will see, I think, for the first -- otherwise, I mean we have to go for imported coal. So we would like to maintain present ratio with a -- with minor tweak of 5%, 7%. So either -- I mean, anything ranging between 65% to 75% should be the pet coke consumption.

Nishant Bagrecha

analyst
#150

Okay. Okay. And sir, lastly, on the last quarter, you have mentioned that you have the balance activity of the OLBC for mines to plant for limestone transportation is going on. So is it completed? Or when are we expecting it to complete?

Ajay Saraogi

executive
#151

Yes, in another 2 months, it should get completed.

Nishant Bagrecha

analyst
#152

Okay. In next 2 months?

Ajay Saraogi

executive
#153

Yes.

Operator

operator
#154

The next question is from the line of Rashesh Shah from ICICIdirect.

Rashesh Shah

analyst
#155

My question is with regards to your U.A.E. subsidiary. What is the current outstanding debt post repayment of INR 100 crores? And are you expecting some further impairment in this fiscal as well?

Ajay Saraogi

executive
#156

See, as far as debt is concerned, the present outstanding of debt is around INR 258 crores.

Prashant Seth

executive
#157

INR 258 crores.

Ajay Saraogi

executive
#158

And that should get repaid over the next 2 years. And we do not foresee any further impairment. So I mean, this is based on how you foresee the business in the current scenario. And we will review the position going forward next year, but we are hopeful that there should not be any further impairment. But it will depend on how the position -- how we foresee the position at the year-end.

Operator

operator
#159

The next question is from the line of Uttam Srimal from Axis Securities.

Uttam Srimal

analyst
#160

Sir, I just need gross and net debt on a consolidated basis?

Prashant Seth

executive
#161

The gross debt on consolidated basis is like INR 2,810 crores plus INR 258 crores.

Uttam Srimal

analyst
#162

Okay.

Prashant Seth

executive
#163

INR 3,068 crores.

Uttam Srimal

analyst
#164

Okay. And net debt, sir?

Prashant Seth

executive
#165

And cash remaining same.

Uttam Srimal

analyst
#166

Cash remaining same? Okay, sir.

Prashant Seth

executive
#167

Yes. [indiscernible] net debt.

Operator

operator
#168

The next question is from the line of Shravan Shah from Dolat Capital.

Shravan Shah

analyst
#169

Sir, working capital loan of INR 115 crores as on March, is it the same? Or has there any change?

Prashant Seth

executive
#170

It is more or less same. It is in the range of INR 125 crores.

Shravan Shah

analyst
#171

Okay. And sir, what is the road-rail mix for this quarter?

Prashant Seth

executive
#172

It's -- rail was 16%.

Shravan Shah

analyst
#173

16%. Road share has increased in this quarter. And in terms of the premium, we said 2% Y-o-Y improvement. So premium share is how much now?

Prashant Seth

executive
#174

It is around 5%.

Shravan Shah

analyst
#175

5%. Okay. And sir, when we are saying that we may look at the WHRS, at our Karnataka South plant and also can look at the solar plants also. So anything specific in this year and any CapEx that -- what we are looking at this year, particularly?

Ajay Saraogi

executive
#176

So as far as solar is concerned, we are going on -- we are not going on a CapEx model. So it is an OpEx model. So it is not reflected in the capital expenditure. And WHRS, we are working out the details. I said that is a part of the ESG and environmental plan going forward. So we are still not -- have not submitted the expenditure. We are working out the details, and there's a possibility of WHRS for the south plant.

Shravan Shah

analyst
#177

But even if it is there, how much broad number, 10 megawatts or it would be around 15, 20 megawatts?

Ajay Saraogi

executive
#178

Yes, it will be around 15 megawatts. The cost should be around INR 150 crores to INR 175 crores, ballpark numbers.

Operator

operator
#179

The next question is from the line of Navin Sahadeo from Edelweiss.

Navin Sahadeo

analyst
#180

So just a couple of questions. Clinker sale was how much for the quarter?

Prashant Seth

executive
#181

One second, Navin. Yes, it was 76,000 tonnes.

Navin Sahadeo

analyst
#182

76,000 tonnes. Okay. Sequentially, like the presentation says blended cement share increased by about 4% quarter-on-quarter.

Prashant Seth

executive
#183

Yes.

Navin Sahadeo

analyst
#184

And in response to a previous question, you also said that it's about 62%. Is that correct? Did I hear it correct?

Prashant Seth

executive
#185

Correct. Correct. Correct.

Navin Sahadeo

analyst
#186

Then the segment overall 62%. So what is like, let's say, a possibility to increase this further realistically in the coming 1 to 2 years?

Ajay Saraogi

executive
#187

So we are working to increase the one more trade sale, which will again increase -- result in increase in the blended cement. So we are looking at maybe down the -- I mean maybe up to 70% of blended cement. But having said so, this is a plan, but it also depends on how the demand increases. If the major drivers of demand are -- is infrastructure and which requires more of speed, then there may be some small [indiscernible].

Navin Sahadeo

analyst
#188

But if I understand correctly, the Central India expansion or the region -- market for Central India expansion, that is largely a blended market? Or is it like not...

Ajay Saraogi

executive
#189

Yes. Yes. That is largely a blended market. Yes. I'm talking about immediate impact of Central India would come in, in '24.

Navin Sahadeo

analyst
#190

Understood. Understood. And then one question on the white cement realization. Sequentially, somebody asked, I mean, previous participant, that sequentially, the realizations are down by about 3%, 3.5%. Is it also fair to assume that sequentially, the margins for this segment also, I know you don't give breakup, I'm not asking for a specific number, just directional sense that is it fair to assume that the margins for white segment also would be down sequentially?

Ajay Saraogi

executive
#191

I will not say so because if we are -- see, earlier with the same thing if we are able to maintain a 25% EBITDA margins for company as a whole, so we should not be either way, anyway, way off whether in white or grey.

Navin Sahadeo

analyst
#192

I was just...

Ajay Saraogi

executive
#193

Company as a whole, 25% EBITDA margin.

Navin Sahadeo

analyst
#194

No, no, sorry. Directionally, I was only seeing at this way that your presentation says grey cement realizations increased by 6% quarter-on-quarter and white cement is down.

Ajay Saraogi

executive
#195

Yes. Yes. Because this quarter I said white cement has been adversely affected because of COVID, and exceptionally, low volume quarter for the white business.

Navin Sahadeo

analyst
#196

Okay. But you're saying margins may not have been hit despite the realization...

Ajay Saraogi

executive
#197

Because -- yes, when -- we had also cut down a lot of expenditure for white business, on the grinding and other things. So which will be done in a normal period, which is now -- I mean we have done quite well in the month of June for the white business. The July month was also good from an -- as compared to year-on-year or any July month.

Navin Sahadeo

analyst
#198

Okay. And my last question. This is about the efficiency. So beginning of like, let's say, I think maybe, if I may say, 2 years back when we were looking to install this 4.2 million tonne of recently commissioned CapEx, we were looking at gains of roughly around -- if I'm not wrong, INR 115 per tonne of overall cost savings coming from, let's say, this 4.2 million tonne capacity, including the waste heat recovery and everything. So is all of that realized or the best is yet to come? How should one look at it?

Ajay Saraogi

executive
#199

Yes, mostly it is realized. The best is yet to come, I would say. This has always been we want to -- I mean from -- not INR 150, we'd like to get INR 160, INR 175. So because we did have -- we would have a continuous running from the third quarter onwards, I think the best would come in third quarter. But out of INR 150, I think over INR 100 a tonne has already been realized.

Navin Sahadeo

analyst
#200

And when you say continuous running in the third quarter, are you referring to the upgradation of Nimbahera, which will then contribute to full-blown efficiencies?

Ajay Saraogi

executive
#201

I'm looking to the demand should be better. Otherwise, there has been -- the demand was -- we expect a better demand from the third quarter.

Navin Sahadeo

analyst
#202

[Foreign Language] demand has its own dynamics, but per se, from an efficiency perspective, Q3 can really see further improvement in terms of overall efficiency that we have achieved so far?

Ajay Saraogi

executive
#203

Yes.

Operator

operator
#204

We take the last question from the line of Rajesh Ravi from HDFC Securities.

Rajesh Ravi

analyst
#205

Sir, on the consolidated gross debt number, March quarter number on the gross side is INR 3,625-odd crores or INR 3,600 crores. So where do we stand versus that number long, short, all included?

Prashant Seth

executive
#206

No. Gross debt, if you see, I mean, we have reduced because we have done repayment in this quarter.

Rajesh Ravi

analyst
#207

INR 100-odd crores, okay.

Prashant Seth

executive
#208

INR 120 crores in U.A.E., INR 35 crores [indiscernible].

Rajesh Ravi

analyst
#209

Hello?

Prashant Seth

executive
#210

Stand-alone -- see, the project stand-alone as on 31st March was INR 2,841 crores, which is reduced to INR 2,810 crores as on 30th June. The gross debt for Fujairah was INR 360 crores, which is reduced to INR 258 crores.

Rajesh Ravi

analyst
#211

And how about the short-term borrowings, which was on a stand-alone basis? Or on a consol basis, INR 150 crores?

Prashant Seth

executive
#212

It is at the same level.

Rajesh Ravi

analyst
#213

So that is at same level. So -- okay. So this INR 3,060 crores, INR 3,070 crores plus INR 150 crores, I should look at the total consolidate, right?

Prashant Seth

executive
#214

If you are adding the CC limits.

Rajesh Ravi

analyst
#215

Yes. Yes. Okay. And one follow-up on the white cement versus grey cement margins. In this quarter, the grey cement realization have summed up by almost 6%, 7% Q-on-Q, part of it is lower clinker and lower non-freight. But is it unfair to assume that sequentially, your grey cement margin would have expanded at a faster pace? And compared to the white putty where you saw a 3% realization debt, so sequentially, the margins would have come off partly in the white cement? And grey cement would have seen some expansion?

Ajay Saraogi

executive
#216

No. No. Not much. Again, yes, there is a dip in the white during the quarter, but the -- so it was a major shift, and it is only a temporary impact, which is not there from, I think, the normal month for the white business over July.

Rajesh Ravi

analyst
#217

Okay. Okay. Lastly, on the pet coke, what was the share you said in Q1, 40% or 30%?

Prashant Seth

executive
#218

Q1, it is 40%, 4-0.

Rajesh Ravi

analyst
#219

4-0. In 2Q, have you cut down significantly? Or is it at a similar level?

Prashant Seth

executive
#220

No, not much of a change.

Rajesh Ravi

analyst
#221

Okay.

Prashant Seth

executive
#222

Because, see, the imported coal prices are also going up at the same pace. So...

Ajay Saraogi

executive
#223

And we have inventory of pet coke. So we will be maintaining the same percentage.

Operator

operator
#224

Ladies and gentlemen, that was the last question for today. I now hand the conference over to Mr. Vaibhav Agarwal for closing comments. Over to you, sir.

Vaibhav Agarwal

analyst
#225

Yes. Thank you. On behalf of PhillipCapital India Private Limited, we'd like to thank the management of J.K. Cement for the call. And many thanks for the participants that joined the call. Thank you very much, sir, management, for joining the call.

Ajay Saraogi

executive
#226

Thank you, Vaibhav. Thank you, everybody.

Operator

operator
#227

On behalf of PhillipCapital India Private Limited, this concludes this conference. Thank you all for joining. You may now disconnect your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete J.K. Cement Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to J.K. Cement Limited earnings transcripts and 248,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.