operatorGood day, everyone, and welcome to the J.K. Cement Limited earnings call for the quarter and half year that closed on 30th September 2026, brought to you by PhillipCapital India PRIVATE LIMITED. <<operator_script>> I'll now turn the conference over to Mr. Vaibhav Agarwal of Phillip Capital. Thank you, and the floor is yours, sir.
Vaibhav Agarwal
analystThanks, Nirav. Good afternoon, everyone. We welcome you, on behalf of Phillip Capital India Private Limited, to the Q2 and H1 FY27 call of J.K. Cement Limited. Joining us on this call are Mr. Ajay Kumar Saraogi, Deputy Managing Director and Chief Financial Officer, and Mr. Prashant Seth, President- Business Information and Investor Relations at J.K. Cement. I want to note, on behalf of J.K. Cement and its management, that some statements made or discussed on today's conference call may be forward-looking statements about future developments and statements based on current management expectations. A number of risks, uncertainties, and other important factors apply to these statements, and those may cause actual developments and results to differ materially from the statements made. J.K. Cement Limited and the management of the company assumes no obligation to publicly update or alter these forward-looking statements based on — based as a result of new information or future events or otherwise. I will now hand over the floor to the manager of J.K. Cement for their opening remarks, which will be followed by interactive Q&A. Thank you, and over to you, sir.
Ajay Kumar Saraogi
executiveThanks, Vaibhav. Good afternoon, and welcome to the call covering Q2 and the six months that ended on 30th September. On 24th of October, the Board of Directors met and reviewed how the company performed during the quarter closing 30th September and also during the half year closing 30th September. Turning to the key highlights: net sales for this quarter rose 21% year-on-year, reaching 3,561 crores, versus 2,932 crores. Against the prior quarter, though, that figure fell 9%. For the half year, net sales came in 21% higher at 7,457 crores, compared with 6,167 crores. That rise in net sales stems mainly from higher grey cement volumes. Across the half year, grey cement volumes grew 19 to 19.38%, hitting 11.3 million tonnes, against 9.49 million tonnes. White cement volumes likewise rose 19%, to 10.32 lakh tonnes during the six-month period, versus 8.62 lakh tonnes a year earlier. The EBITDA standalone — apologies, last time I quoted the consolidated numbers. Let me go through it again. Standalone financial results on a quarter-on-quarter basis actually climbed 28%, to 3,516 crores, compared with 2,754 crores.
Ajay Kumar Saraogi
executiveFor the half-year period, that figure is 25% greater, at 7,301 crores versus 5,823 crores. EBITDA in this quarter came to 500 crores, against 440 crores a year earlier and 639 crores in the quarter just before. Over the six months, it is up 2%, reaching 1,138 crores compared with 1,113 crores. While reviewing this, the board also took note that in this period we commissioned the wall putty plant at Nathdwara, with 0.6 million tons of capacity, which lifts our total capacity for white cement and putty to 3.65 lakh million tons. The review would be of the projects' working, basically at Jaisalmer, so on the integrated side, the work stands at an advanced stage and remains on schedule, and we are confident of commissioning that plant in first half FY28. Likewise, at the grinding stations at Bikaner, progress on the work continues, and we are confident of commissioning in the first half of FY28. At Bhatinda, the approvals have been received and work should begin shortly. And there too, I think by — within September, as of — we are targeting within September 27th, we should commission the plant.
Ajay Kumar Saraogi
executiveThe board additionally took note of and gave the go-ahead to the J.K. Maxx proposal, which involved setting up a white cement — a paint plant of 75,000 KL, carrying a total cost of 130 crores, and that falls inside the overall limit sanctioned for the paint business of 600 crores. So through this investment, we would be just about meeting the total investment in the paint business. And on the working side, the paint business is already on course for break-even in this fiscal. We don't foresee that going forward there would be any additional need for any investment in the paint business. So with this, future investment can be met by the paint business on its own. As regards the balance sheet, the gross debt position as on 30th September is 6,255 crores against 5,136 crores. The cash available as on 30th September is 1,684 crores against 1,765 crores. The net debt is 4,571 crores against 3,370 crores. The net debt — the net debt to equity is 0.63 and net debt to EBITDA is 1.95. Those are the major highlights. If you have any question — I'll now take up the questions and answers.
Ajay Kumar Saraogi
executiveThanks.
Operator
operatorThanks a lot. At this point we’ll move into the question-and-answer portion. <<operator_script>> Everyone, please hold on briefly while the question queue is put together. <<operator_script>> Our first question comes from Navin Sahadeo at ICICI Securities. You’re welcome to proceed.
Navin Sahadeo
analystGood afternoon, sir. Can you hear me okay?
Ajay Kumar Saraogi
executiveYes.
Navin Sahadeo
analystYeah. Okay. Great. Thanks for the chance to ask, and congrats on the strong numbers as well. So my first question is about volumes. First half volumes grew 19%, but how should we think about volume growth in the second half, given that Karnataka and Maharashtra are likely dealing with some water shortage-related issues, so how much exposure is there? Are you seeing any impact from that? And also in UP, with that state heading into elections, so how should we think about volume growth in the second half, please?
Ajay Kumar Saraogi
executiveNavin, first regarding Maharashtra and Karnataka — although we’re largely sold out in that region already, yes, we don’t expect any meaningful impact there. And as for whatever is happening — we’re hopeful that our annual target numbers in those regions will be achieved. On your question about UP, yes, elections are underway there, but I don’t believe they’ll take place before March. If that turns out to be the case, there could be some disruption, or otherwise. Even so, we’re confident that the guidance we provided at the start of the year — closing at 23 million tons — we remain on track, very much on track, for that number.
Navin Sahadeo
analystNo — if that isn’t the situation, then I’m actually anticipating 24 million tons. So that’s at least how it appears based on the first-half performance.
Ajay Kumar Saraogi
executiveOkay, so again, what I'm saying is that the guidance we gave was 23 million tons. It would be 23 million tons plus, so if we get 24, that's better. But right now, since next month is Diwali, a festival month, a lot of — I mean, some volumes will be affected because of Diwali. There's already some construction activity restrictions in New Delhi, due to pollution and other things. So you have to factor in all those uncertainties, as you mentioned, you know, drought and other things. So if they're bearing that — I mean, if nothing happens, we'll definitely be closer to 24 or something. But we are — as we gave guidance, 23 million, we're confident we will be there.
Navin Sahadeo
analystThanks. Sir, my second question, then, concerns cost. Your cost per Kcal came in at roughly 1.71 in Q2. Could you help us understand, at today's spot rates — with petcoke having jumped beyond $185, or somewhere between $185 and $190, and domestic coal premiums also having climbed, nearly doubling — what the cost per Kcal would be at current spot rates, and whether that will be felt in Q3, or only in Q4 or later? How should we think about that? Thank you.
Ajay Kumar Saraogi
executiveThere's going to be an effect in Q3 and also in Q4. So in Q3 we'll partly see some benefit from the inventory, but the full impact would be felt in Q4. So I think the overall impact — from 1.71 as a cost that was there at exit — we adapt to how things look, and if they continue that way the cost may rise to closer to 2 rupees. So with that 2 rupees, we may say roughly half-half should come in, which is an impact of eight — 80, 90 rupees coming in this quarter and maybe a similar amount in the subsequent — in the next quarter.
Operator
operatorThanks. Navin, anything else you’d like to ask?
Navin Sahadeo
analystNo, no. Thank you very much. Thanks a lot.
Operator
operatorAppreciate it a lot. Our following question comes from Sanjeev Singh at Motilal Oswal on the line. Go right ahead.
Sanjeev Kumar Singh
analystYes. Thanks for giving me the chance, sir. My first question concerns demand, specifically what you mentioned regarding drought and insufficient rainfall. So based on what you've seen across the past 10, 15 years, each time a situation like this has come up, what has demand been affected like, in your opinion?
Ajay Kumar Saraogi
executiveLook, I — I would — this is a tough one, but Navin brought it up. What I mean is, we truly aren't building the drought effect into our numbers. And regardless, in the areas hit by drought, our overall share is pretty small. Of our total volume share there, roughly 15% of volumes come from the South plant — that's of total volumes. So it isn't very substantial, and it will — so what I'd say is that if we do see an impact, it won't be anything significant; it'll be a marginal impact.
Sanjeev Kumar Singh
analystAlright, and then second, in the presentation you laid out the target of reaching 50 million tons of capacity by FY30. So given those growth plans, how do you see the balance sheet shaping up at the peak in terms of net debt and net debt to EBITDA? So at what level would you feel comfortable, and do you think that with the kind of profitability we have currently, you ought to stick with your plans for this sort of growth?
Ajay Kumar Saraogi
executiveLook, as we mentioned, the growth — if you consider gross debt or net debt to EBITDA, it may breach roughly 2.3, 2.35, or land somewhere between 2.25 and 2.35. That represents the peak, which will occur mostly toward the end of fiscal ’27. After that, we would see — since this is a greenfield project with a big investment — the other expansion for the 50 million journey consists entirely of brownfield expansions, where the cost will be lower. And then we would — as capacity, overall capacity, is going up, we expect better profitability. So that would — and it is perhaps from FY29 onward that we again return to our specific target. Is that — or once this is complete, we should be well within 1.5, but it will take two or three years before we start reaping the profits of the expansion.
Sanjeev Kumar Singh
analystSo my final question is about capex. What capex figure ought we to assume across the next 3 years, from FY28 through FY30? As for FY27, I believe you mentioned earlier a number of 35 billion.
Prashant Seth
executiveYes. So we're going to keep moving forward with the expansions, which means capex will land in the range of 2,500 crores yearly over the coming years.
Sanjeev Kumar Singh
analystAlright, thanks.
Ajay Kumar Saraogi
executiveSo what we're saying is, we're doing 3,500 crores in this fiscal, and then after that, with the brownfield expansions each year, it'll be in the vicinity of 2,500 crores to meet the targets.
Sanjeev Kumar Singh
analystAlright, thank you very much.
Operator
operatorThanks. <<operator_script>> The next question comes from Gaurav Nagori at Avengers Park, on the line. Go ahead, please.
Gaurav Nagori
analystYeah, thanks — appreciate the chance to ask. Sir, I’d like to get a better handle on your profitability. When I look at the EBITDA pattern you posted in the first half —
Operator
operatorGaurav, apologies for cutting in. Could you use the handset to talk?
Gaurav Nagori
analystBetter?
Operator
operatorA little bit. Please continue.
Gaurav Nagori
analystOkay, I’d like to dig a bit deeper into profitability. The EBITDA pattern for the first half comes in at roughly 900 rupees per tonne, versus 1,000 rupees last year. What I’m really trying to get at is this: if I take out the incentive per tonne for you, which usually runs somewhere between 120 rupees and 150 rupees per tonne — and given that Fujairah EBITDA margins have also risen for the year, so I’d assume yours would have risen as well — and if I also exclude the white cement and wall putty margins in the domestic market, is it fair to say that once you strip out incentives and strip out those domestic and global white cement and wall putty volumes, your EBITDA per tonne in grey cement would land at about 500 rupees per tonne? Is that understanding correct for the first half?
Ajay Kumar Saraogi
executiveI'm not sure where those figures came from. Let me clarify: on the subsidy, our cost isn't 120 rupees or 150 rupees. The reason our subsidy is what it is comes down to roughly 80 rupees a ton.
Gaurav Nagori
analystAlright.
Ajay Kumar Saraogi
executiveSo then the point we're discussing — we're splitting it using volume figures, and honestly I'm not sure what basis that's on. As I see it, whichever per-ton numbers we're looking at, those are consolidated. If we look at EBITDA margins, they come out the same for the grey business and the white business — more or less in line with the company overall.
Gaurav Nagori
analystAlright.
Ajay Kumar Saraogi
executiveI don't know, to be honest, about that 500. We've never achieved — never once has our grey cement EBITDA hit 500 rupees per ton. That has never happened for us.
Gaurav Nagori
analystRight. No — no, I get that, sir. What I’m trying to get at is this: since in the first half you’ve got that blended figure of 900 rupees, are you then saying the margins on white cement, wall putty, and grey cement are all the same?
Ajay Kumar Saraogi
executiveYeah. Sorry, I’m not able to provide profit figures for each business individually, but if you’ve been looking —
Gaurav Nagori
analystGot it.
Ajay Kumar Saraogi
executiveIf you picture a figure like 500 rupees per ton, then stating that 50% of the profit comes from the white business is your own judgment. I would prefer not to comment on that.
Gaurav Nagori
analystGot it, got it. And then, if you were permitted to say so, how much of a margin gain would you have seen — say, on fiscal volumes this year versus last year?
Ajay Kumar Saraogi
executiveThe margin gain you see is captured in EBITDA. EBITDA is what it is because margins are what they are — costs rose by more than realization did. Right. That hits EBITDA and margins directly. So that's the reason EBITDA comes in lower: the margins themselves are lower. It isn't the case that EBITDA is lower solely due to some fixed cost or anything of that sort.
Gaurav Nagori
analystAlright.
Ajay Kumar Saraogi
executiveThe reason is that margins have come down, since costs went up and we haven't managed to pass those costs through to that extent.
Gaurav Nagori
analystGot it, got it. Understood, sir. That’s all from me. Thank you.
Operator
operatorThanks. <<operator_script>> Our next question comes from Philip Mathias, who is calling in from Girija Investments. Please go ahead.
Philip Mathias
analystThanks very much, sir, for taking my question. First off, congratulations on an excellent set of numbers. I'd just like to ask, regarding the paint business, what revenue did it bring in this quarter? And earlier you'd given a guide — you'd provided guidance that in FY27 revenue from the paint business would come in somewhere around 500 crores to 550 crores, and that ’28 would be plus 150 on the ’27 base. Has that guidance changed, or — I just wanted to check on that. That's my first question.
Prashant Seth
executiveRight, on the revenue side — for this quarter we posted 116 crores, and we're holding to the guidance we gave for the full year, since we've already gotten to roughly 250 crores during the first half.
Philip Mathias
analystMy second question concerns the post-’28 expansion, where you’ve mentioned 11 MTPA brownfield at Muddapur and Panna. What’s the split? How much capacity will be added at Panna, and how much will be added at Muddapur?
Prashant Seth
executiveEach site comes in at roughly 5 million to 6 million tons.
Philip Mathias
analystAppreciate it, sir. That covers everything on my end.
Prashant Seth
executiveAlright.
Operator
operatorThanks. <<operator_script>> Our following question comes from Patanjali Srinivasan at Sundaram Mutual Fund. Kindly proceed.
Pathanjali Srinivasan
analystHello?
Prashant Seth
executiveYes, hi Pathanjali.
Pathanjali Srinivasan
analystYeah, thank you. Nice work on those numbers. I’ve got two questions. First, your execution across this half has been really strong. A lot of peers, in fact, are reporting volume growth figures that are much smaller. So would it be fair to say we picked up a decent amount of market share this quarter?
Ajay Kumar Saraogi
executiveNo. So basically, what you're seeing in the volume figures is that we've finished an expansion in Central India. The results of that expansion are pretty clear. In March of the last fiscal year, we completed a 6 million ton expansion. So those expansion volumes are there, and in — yes, we have them in other markets as well, but not to that extent. The bulk of the volumes come from Central India.
Prashant Seth
executiveHonestly, the North market posted solid overall growth this quarter. Typically, companies operating in the North have posted stronger growth figures, while the East has been a somewhat weaker market. That stems from the regional imbalance as well.
Pathanjali Srinivasan
analystBut is it fair to assume we've picked up market share, or is that—
Prashant Seth
executiveNo. North, we're right in line with the market on that.
Ajay Kumar Saraogi
executiveSo first, look — because we didn’t have additional volume in the North, we’ve held on to our market share there, and we’ve clearly picked up market share in Central India — in the Central markets.
Pathanjali Srinivasan
analystUnderstood. Now, the second point: among the figures you provide are trade share and share of premium. Trade share is growing quite strongly, and share of premium has also been climbing over roughly the past 7 or 8 quarters. So in what way does that lift our profitability? And could you also clarify where we're gaining more ground? Are we doing this better mainly in new micro markets, or is it in newer markets we're moving into? Which areas are giving us the benefit?
Ajay Kumar Saraogi
executiveThis really applies across premium products. We're aiming to raise the premium share in every market. Again, while we work on premium products, yeah, it's again basically tied to trade. So premium — when you push more premium, you maintain our — you try to gain more insight into the trade market. So yes, trade markets definitely help us achieve better profitability, and we keep working toward that. And you see, we're making a lot of — as you can see in our expenses, we're putting a lot of investment into marketing with an eye on our future expansion. That's one of the reasons we're able to share — capture the market and sell our expansion volumes at a much faster pace. So what we're — as part of expansion we keep working in the market so that whenever we come with expansion, as we're now coming up with a big expansion in the North, so in the next fiscal we have to see that we get a good market share in the North also.
Pathanjali Srinivasan
analystUnderstood. Sir, just one final question about this. Sir, since you said profitability is greater on a premium product, I'd like a general range. What additional percentage of margin would you earn on a premium product?
Ajay Kumar Saraogi
executiveRight. So with a premium product, you'd typically earn an additional profit of roughly 150 rupees on average. However — however, there's a customer segment that will take premium products if you don't manufacture and sell them. So that portion of the premium segment is also —.
Operator
operatorSorry to cut in, everyone. Sir, your audio dropped out partway through. Would you mind repeating those last few sentences for us?
Ajay Kumar Saraogi
executiveSo what I was saying is that demand in the premium market is rising too, and that means you have to keep up the pace. If you don't, then you'll — the result will be that trade loses market share.
Pathanjali Srinivasan
analystUnderstood, sir. Thanks, sir. That was extremely — extremely thorough, and honestly a fantastic collection of figures. Appreciate it. Many thanks.
Operator
operatorThanks. <<operator_script>> The next question comes from Prateek Kumar of Jefferies India. Please go ahead.
Prateek Kumar
analystGood afternoon, sir. I’ve got a question about your unit EBITDA performance. For the past few quarters, it has been lagging behind what some of the larger peers have delivered. In the past, it was in line or occasionally higher. Also, with Jaisalmer being commissioned over the next 12 months, how do you view profitability relative to your peers? So, have you kind of settled on a lower EBITDA per ton versus peers? Or how should we think about your EBITDA performance, especially compared with peers?
Ajay Kumar Saraogi
executiveNo, look, when it comes to peers, I think if you do the comparison, we'll keep ranking among the top three or four on EBITDA per ton. And even right now, based on whatever results have come out, we're there — despite the higher costs we had in the first half, if you look at the six months of working, so more or less we're there, and we're not weak. We're confident about maintaining our profitability. I even think Jaisalmer will help us hold that profitability. It shouldn't cause any dilution of profit.
Prateek Kumar
analystAlright, so we expect Jaisalmer to contribute in a comparable way, since in terms of location it’s kind of off?
Ajay Kumar Saraogi
executiveYeah. Because right now, since there’s no capacity, we can’t serve certain segments and certain markets, given that our supply is limited.
Prateek Kumar
analystAlright, another question here: could you go into more detail on why you think entering the paint segment makes sense, given that it's already oversupplied? And does this really give you a meaningful boost in cross-selling putty, so that's the reason you want to expand rather than just wanting to establish it as a standalone unit?
Ajay Kumar Saraogi
executiveLook, the first point is that we're already set to hit 500 crores with this, and once we reach that figure the current plant will be completely utilized — or possibly in the year after that. So we need to plan for new capacity by the time this plant is fully used up. This plant itself will take some time. By the time we commission the new plant, the existing one would already be fully utilized. So we need a source of supply — otherwise all the effort that's gone into building up this segment, along with putty, and meeting customer demand, will be lost. So we'd have to take a back foot. It was necessary to make sure we can keep supplying the increased demand, because next year as well, FY28, we don't have exact figures, but I think we will definitely grow another 150 crores minimum, if not more. So we're working out those details. With that, how will we meet that demand?
Prateek Kumar
analystOkay, but from a business IRR return standpoint, how are we supposed to look at this? I realize cement runs on its own, but does this business function on — like I asked before — a standalone basis when it comes to IRR?
Ajay Kumar Saraogi
executiveAnd on a standalone basis, as we've mentioned, from the paint business this year we should — I realize it takes a while — but we should post positive EBITDA in this fiscal year. And moving ahead as well, step by step as our market share grows and our market reach expands, we would certainly see EBITDA coming from the business. So for this year it ought to be EBITDA positive. For next year — it will be 3% to 5%.
Operator
operatorApologies for cutting in — the audio dropped out again on us midway through.
Ajay Kumar Saraogi
executiveWhat I said was that in the paint business this year, we should finish with a positive EBITDA, and as we expand the paint business going forward, together with putty, we would see profitability in the paint segment itself rising year on year. I mean, the increase won't be very sharp, but yes, definitely a 2% to 3% gain in profitability year on year.
Prateek Kumar
analystAbsolutely, here are the questions I have, and thanks.
Operator
operatorThanks. <<operator_script>> The next question comes from Amit Murarka at Axis Capital. His line had dropped, but he's reconnected. Please go ahead with your question.
Amit Murarka
analystYeah. Hi, thanks. So first, about the Kcal itself. Fuel cost Kcal at, I believe, 1.75 this quarter is roughly 15%, 20% below what other companies have reported. So I just wanted to get a sense of what's behind this lower fuel cost. Is it things like more domestic coal? If you could just go into that a bit more.
Prashant Seth
executiveYes, Amit, that also comes from the shift in our blend. The first factor is the automatic change once Panna line two started up, since we're now actually using Indian coal. So in practice — what I mean is — our petcoke consumption is down to just 30% to 35% at this point, while Indian coal sits at 55%. Unfortunately, we still held some stock bought at the old rate, and even though Indian coal prices are now climbing, our consumption this quarter came in at a fairly low rate. That's what produced the lower overall mean per Kcal cost. So next quarter, with Indian coal prices and petcoke prices both rising, we will definitely be above 2 rupees.
Amit Murarka
analystIs that in Q3 or by Q4 — meaning 2 rupees?
Ajay Kumar Saraogi
executiveLike we mentioned, it applies to both Q3 and Q4. So Q3 would see part of the effect, and then the rest of it, with Q4 carrying the full impact.
Amit Murarka
analystSure. Now, regarding the second question about plant utilization: the PPT mentions clinker utilization at 95%, while cement, I believe, was 67% or 70% — something along those lines is stated there. So, um,
Prashant Seth
executiveUnderstood.
Amit Murarka
analystWill this entire clinker inventory get used up during the third quarter, or will some of it carry over into Q4 as well —
Prashant Seth
executiveActually — actually, clinker inventory got used up during the quarter before this one, since we performed maintenance on the majority of our kilns. So first, we've gotten back to the average, normal level of clinker inventory, and on top of that there's a bit of extra clinker, because volumes are usually lower this quarter owing to the seasonal effect.
Amit Murarka
analystOkay, so first off — my question is this: there's a fair-sized pile of clinker inventory, as the inventory movement line item shows us too. So is all of that going to get used up, that excess inventory?
Prashant Seth
executiveNo — that's not the whole picture. As I mentioned, clinker inventory during the previous quarter came in below the usual level. So the first point is the standard clinker inventory level, and that's what will carry forward starting in Q3.
Amit Murarka
analystGot it. One final question about revenue. Could you break out grey revenue, white revenue, and paints revenue — you mentioned 116 for paints. But when everything is added together, there's still a gap of roughly 60-odd crores that shows up.
Prashant Seth
executiveAnd that's really the revenue from RMC and CC.
Amit Murarka
analystRNC, and which revenue line was that? Apologies — construction chemicals.
Prashant Seth
executiveMostly the RNC, since we began from just the prior quarter, and that figure of 60 crore is the RNC along with construction chemicals.
Amit Murarka
analystAll right. But it seems the increase mostly happened during this quarter, since earlier on the gap wasn't really that large in Q1.
Prashant Seth
executiveDuring Q1, that figure came in at 50 crores.
Amit Murarka
analystSo Q1 comes in at 50 crores, and for this quarter you're putting it at 60 crores for those —
Prashant Seth
executiveYeah, yeah.
Amit Murarka
analystAnd when it comes to those two businesses, what would that mean? Also, would any EBITDA be generated by those two businesses?
Ajay Kumar Saraogi
executiveRMC is still in a development phase. If you look at it, there’s no EBITDA at this point, because every plant — as things stand today, we currently have 23 RMC plants running. And our goal is to reach 50 plants by March 27. So roughly six months are needed for each plant to reach break-even. You see, at the start, when you set up a plant, the — and the — since it operates on a tolling model, we must guarantee a fixed cost to the tolling party no matter what, so by the time the break-even volume begins to arrive, it takes three — three months to get — three to four months to get the break-even volume.
Operator
operatorThanks. Amit Murarka will return for a follow-up question. <<operator_script>> The next question comes from Thida's line at DSP Asset Managers — please go ahead.
Sarthak Tita
analystRight — yeah. Hi there, good afternoon. Thanks for giving me the chance. I’m not sure whether this came up before, but I was hoping you could give us some color, sir, on the pricing side — how current spot prices compare with the Q2 average. Some detail on our core regions would be really helpful. Yeah.
Ajay Kumar Saraogi
executiveSo we actually began to see some pricing movement, and in—all—in the latter portion of September, which we couldn't—I mean, there had been very marginal realization in the prior—in Q2. But yes, in Q3, starting in October, or if we say from mid-September, prices overall have gone up by roughly 20 rupees per bag, trade and non-trade taken together. So that's the increase across, if it's an average product.
Sarthak Tita
analystUnderstood, sir. So is it fair to assume this would show up in the Q3 portion, if these end up carrying through at all?
Ajay Kumar Saraogi
executiveSure — if that holds up, it should turn out pretty well. It would offset a great deal of the expense growth and all of that, which is something that has been present.
Sarthak Tita
analystAll right, that makes sense — I understand. This has been quite useful. Thanks — many thanks, and best of luck.
Operator
operatorThanks. Our following question comes from Shravan Shah at Dolat Capital. The line is yours — please proceed.
Shravan Shah
analystHello, sir. Congratulations on the strong results. I have a couple of questions, sir. First, just regarding the paint business — to get a data point, what was EBITDA in Q2?
Prashant Seth
executiveFor Q2, we posted a loss of 2 crores.
Shravan Shah
analyst2 crores. And for the full year, we're looking at something in the positive —
Ajay Kumar Saraogi
executiveYes, EBITDA was positive.
Shravan Shah
analystAnd for FY28, would an EBITDA margin in the 5% to 6% range be realistic, or is that achievable given the roughly 650 crores to 700 crore of revenue we'll be generating?
Ajay Kumar Saraogi
executiveAt 700 crores, we're looking at 5% — initially, we might say yes, we'll be targeting 5%, but I'm definitely of the view that EBITDA should be 3% to 5%.
Shravan Shah
analystYeah, so for RMC, it was 60 crore this quarter. We were kind of expecting around 100 crore in revenue from Q4, so that should be a doable piece, right?
Ajay Kumar Saraogi
executiveYeah — yeah, it was higher in RMC this quarter, and then in Q4 it definitely hit 100 crores.
Shravan Shah
analystRight, got it. And sir, what was the incentive for this quarter?
Ajay Kumar Saraogi
executiveA bonus, you mean? Is that what you just mentioned — a bonus?
Shravan Shah
analystYes, sir.
Ajay Kumar Saraogi
executiveFor the quarter, that figure is 25 crores to 45 crores.
Shravan Shah
analystAlright, 45 crore — so then, that comparable run rate ought to hold in Q3 and Q4, or it would land somewhere around 50 crore, 55 crore, is that —
Ajay Kumar Saraogi
executiveRight, so it should come to roughly 50 crores, since, you see, if we aren't receiving any — you see, we — for Aligarh, many incentives aren't in place. Up in the North, we don't get them, because we're claiming the input credit, so that isn't offered. So really it's coming from just a handful of grinding units, so we — it might end up at that same figure.
Shravan Shah
analystAll right, all right. Now regarding white cement, at the consolidated level for 1H we recorded volume growth of about 4.9%. Earlier we indicated that for the full year we were expecting growth in the region of 18%. So is that figure achievable this year?
Ajay Kumar Saraogi
executiveLook, we need to examine what's actually occurred, because when we discuss things on a consolidated basis, the white cement side of the business is where Fujairah's operations are taking the hit. So yes, India operations have gone up. But we won't be in a position to offset that whole loss, since we aren't able to — whatever volume Fujairah was supplying into the Indian market, we can supply that from the India operations, but we can't supply — can't cover the shortfall for other countries. Fujairah can't export any cement or clinker to any other part of the world apart from the GCC nations. They can't ship material anywhere else, so meeting that shortage will be difficult. Other than that, it's more or less — so there may be some shortfall in the — in those numbers.
Shravan Shah
analystAlright — alright. And sir, since the clinker utilization, let's say, as Prashant sir mentioned, stands at 95%. So clearly for the second half, we definitely — with the 20% gray volume growth being there, we should be able to get close to roughly 24 million tons. But in —
Ajay Kumar Saraogi
executiveJust a minute — I’ll say that again. The guidance we’re giving is 23 million plus. I’m not making any commitment on 24 million.
Shravan Shah
analystYes — yes, I get it. I get it, sir. But that figure is being produced by the investors, sir. I’m definitely — you always —
Ajay Kumar Saraogi
executiveWe'll aim toward that figure, though plenty of other elements come into play. A 20% year-over-year increase is what we're looking at given the first-quarter base, and we still need to watch other factors. So I can't say with much certainty — we'll certainly do our best to see what's achievable, but we're not making any commitment on a volume figure of, say, 24 million tons.
Operator
operatorThanks, Shravan. I’d like to come back with one more question. <<operator_script>> The next question comes from Pinakin Parekh at HSBC. Please go ahead.
Pinakin Parekh
analystThank you very much, sir. My first question is this: could you give us some idea of where you expect absolute net debt to reach its peak? You've spoken about it at the level of the EBITDA per ton ratio, but at what point will we see that net debt figure top out?
Ajay Kumar Saraogi
executiveToday, net debt stands at roughly 4,571 crores. It might reach a peak nearer to 6,000 crores.
Pinakin Parekh
analystRight, sir. And does that figure come from the 40 million ton plan or the 50 million ton plan?
Ajay Kumar Saraogi
executiveMy view is that net debt should top out at 6,000 above that 50 million ton figure — that's the level where it peaks.
Pinakin Parekh
analystAlright, understood. Moving to the second question, sir, about cement pricing: you said there was a 20 rupees per bag increase between mid-September and mid-October. Based on what you're seeing on the ground, do you think the industry would look to push through additional price increases after Diwali, or are the hikes already in place sufficient to offset all the cost pressures that we're seeing on the ground?
Ajay Kumar Saraogi
executiveNo, actually, we still need another 10 rupees to 15 rupees in the price to cover all the cost increases. Because it isn't just fuel — packing cost remains very high, the PPC annual cost, and the packing cost that started following has gone up again. And B — the geopolitical situation is still with us. Fortunately, in between, we saw a big dent from the rupee devaluation. The rupee has been quite strong over the last few days, say the last 15, 20 days, so we don't see it, but if there is again some — when the rupee gets weaker, that will also have some impact. So I think, I mean, another 10 rupees to 15 rupees minimum is required. That gap would still be there.
Pinakin Parekh
analystUnderstood. So do you see that taking place after Diwali, or is it your sense that on the ground, it's hard to absorb those price increases?
Ajay Kumar Saraogi
executiveYeah. Look, I, I think it can happen after Diwali, because right now, with Diwali coming, people start moving in the next 10, seven, eight days to — so there will be — construction activity is going to slow down, since the laborers begin heading out. And they won't be back until around the 20th, not before that.
Pinakin Parekh
analystUnderstood. Many thanks, sir.
Operator
operatorThanks. <<operator_script>> Our next question comes from Parvez Qazi at Nuvama Wealth Management. Your line is open.
Parvez Qazi
analystGood afternoon, and congratulations on those strong sector figures. I just wanted to ask about two data points. What did our CC ratio come in at for this quarter, and how did our fuel mix look? Thank you.
Prashant Seth
executiveThe CC ratio came in at 1.5, and on the fuel side, Indian coal accounted for 55%, alternate fuels made up 13%, with petcoke making up the remainder.
Parvez Qazi
analystAbsolutely, sir. Thank you, and best wishes to you.
Operator
operatorThanks. Our next question comes from the line of Ritesh Shah at Investec Capital. Go ahead, please.
Ritesh Shah
analystHello sir, and thank you for the chance to speak. Sir, could you kindly bring us up to date on where things stand with the Mahan and West Shadole coal blocks? What's the current status, and by when could they actually start helping us on the cost curve?
Ajay Kumar Saraogi
executiveLook, on the work front, we've already begun activity on the Mahan coal whole block at the site. All the approvals are in hand, and work has commenced there. Our target is sometime in the first quarter or first half of FY29 — that's what we're aiming for, to have this Mahan mine operative in the first half of FY29. On the second mine, we're still working things out, so we're focusing first on the first Mahan, since it's the larger block, and after that we'll concentrate on — perhaps we'll be in a position, say, in another six to eight months, to give a definite schedule for the Shapur.
Ritesh Shah
analystSure. Sir, could you give us an idea of what the landed cost might be, say in FY29? That's a bit far out, but I'd just like to get a sense of it from a cost-savings perspective. My understanding is that it's a 1.2 million ton mine. Please correct me if I'm wrong.
Ajay Kumar Saraogi
executiveYeah. So our expectation is that the coal cost will come in at no more than 1.25 rupee per ton.
Ritesh Shah
analystAll right, that's encouraging. Thanks a lot. Sir, my second question concerns the fuel mix. You did give AFR, petcoke, and local coal as percentages, but is there still more room to optimize that? Or, to flip it around, are there any difficulties in sourcing local coal that would push us toward using more petcoke, or the reverse?
Ajay Kumar Saraogi
executiveNo. So, look at what happens here — it comes down to location. Our central plant will rely more on local fuel, which makes it more economical there. Imported fuel won't be economical. It's only used as a blender — some high-calorific material as a blender, limited to, say, up to 10%. Not beyond that. Now when we get to the North and South plants, it would — with Indian coal, first, it's very difficult to obtain Indian coal of that volume. We have no linkage for these plants, so securing consistent quality and the quantity needed for those operations from the open market isn't feasible. So there, you know, imported US coal or petcoke will always be present, and we'll have to mainly use that fuel at — at the north and south plants.
Operator
operatorThank you. <<operator_script>> The next question comes from Simran Kumari at Narnolia Financial Services. Please go ahead.
Simran Kumari
analystHi there, sir. Congrats on that huge win.
Operator
operatorSimran, we can’t hear you. Could you please use the handset to speak?
Simran Kumari
analystOkay, I've got my headset on. Can you hear me at this point?
Operator
operatorMa'am, we're not getting your audio clearly.
Ajay Kumar Saraogi
executiveCould you speak up a bit?
Simran Kumari
analystCan you hear me now?
Operator
operatorSure, please proceed.
Simran Kumari
analystHello? Yes — nice work on that solid status figure. Nearly everything I had asked about has already been covered. I just hoped to get a feel for where power and fuel costs are headed. Given how that power and fuel cost looks this quarter, what should we expect for 3Q and 4Q?
Ajay Kumar Saraogi
executiveAs I mentioned before, we expect power and fuel costs to rise by 80 rupees to 100 rupees per quarter.
Simran Kumari
analystAll right. Thanks very much. That’s what I was asking.
Operator
operatorThanks. The next question comes from Harsh Mittal at Emkay Global. Go ahead, please.
Harsh Mittal
analystYes. Good evening — good afternoon, sir. Thanks for giving me the chance to ask. So my question concerns realization per ton for white cement. We've noticed a fairly sharp sequential rise again this quarter, roughly 7.5%. Well, last quarter you did mention that this came from the restricted clinker — restricted material movement out of Fujairah. So do you expect additional gains in the quarters ahead, or how should we view it, sir?
Ajay Kumar Saraogi
executiveSo any increase you’re seeing, on a year-on-year basis, is due to — yes, part of the cost escalation in the white business is that white cement prices have gone up as well. But we — what I mean is, it actually went up in the first quarter itself again, though the prospect of another hike is quite difficult. So no further increase is what we expect in white cement, because again there is some — I mean, there’s a barrier — beyond a certain price point, cost pressures — customers simply aren’t willing. So it’s quite difficult. Yes. Still, we’re trying to figure out whether there’s any — whatever — how we can manage to pass along the cost increase — any additional cost increase. But as things stand right now, it’s a bit difficult.
Harsh Mittal
analystGot it, sir. So is there any guidance you can give on white — on white cement volumes, now that we've commissioned the new white cement plant this year for FY27?
Ajay Kumar Saraogi
executiveThe putty plant has now been commissioned. Whatever figure we've given as guidance, that figure will remain in place. This is meant to help us meet peak demand. And we're already running at a very high level — roughly 90% capacity utilization. Had we not brought that plant online, we wouldn't be able to grow going forward.
Operator
operatorThanks. Our next question comes from Siddharth Malhotra at Kotak Securities. Go ahead, please.
Siddharth Mehrotra
analystThanks for having me. Sir, I just want to make sure of something. We've received both the EC and CT approvals for the Bhatinda project in Punjab. Is that right?
Ajay Kumar Saraogi
executiveYes, it's below — what I mean is, the method — we're simply anticipating the formal letters very soon. All is well.
Siddharth Mehrotra
analystAll right. So those items haven't come in yet, though we anticipate getting them before long. Did I get that right?
Ajay Kumar Saraogi
executiveYes, it should be in place by some point during this month.
Siddharth Mehrotra
analystGot it. So it's a bit later than what we'd been expecting before, if I'm following you correctly, right?
Ajay Kumar Saraogi
executiveRight, but our hope is that as soon as we receive it, work will begin on location.
Siddharth Mehrotra
analystUnderstood, sir. Sir, if I may, just one brief follow-up question. In the standalone white cement volumes, we're seeing growth of 13%, 14% odd percent Y-O-Y. So could you perhaps explain just why the recovery has been so sharp? And also, is it expected to keep going?
Ajay Kumar Saraogi
executiveThat's the one serviced from India. Previously, those volumes were handled out of Fujairah last year, and at present India handles this. So that explains why the growth is there. Yes, and alongside that growth — with the market expanding, we see growth for both white cement and putty, and we've sold more material.
Siddharth Mehrotra
analystAll right, that's quite clear. So, sir, our India capacity stays unchanged at roughly 2.6 to 2.7 MTPA — for white and putty, correct?
Ajay Kumar Saraogi
executiveRegarding India, the capacity for white and putty there stands at 3.05. In the UAE, white cement capacity is 0.6. That brings the combined white cement and putty capacity to 3.65.
Operator
operatorThanks. The next question comes from Manoj Chiranjeev Kothari at Equirus Securities. Go right ahead.
Manoj Chiranjeev Kothari
analystYes. Hello sir, and thanks for the chance to ask. I was hoping to get some detail on cost pressures. You referred to roughly 80 crores to 90 crores related to fuel. So do we expect any cost inflation when it comes to packaging? And I also wanted to check whether there’s any one-off cost tied to maintenance work you’re carrying out in 2Q.
Ajay Kumar Saraogi
executiveNo, I don’t believe packaging cost has peaked yet. My view is that we shouldn’t expect packaging costs to rise any further. That said, on all these costs, if the rupee depreciates, there could be some cost impact, since that has a direct effect on the generals cost.
Manoj Chiranjeev Kothari
analystAlright. Sir, and regarding maintenance — did you incur any maintenance costs during the quarter specifically tied to it?
Ajay Kumar Saraogi
executiveNo, it’s a routine measure. It’s all plant maintenance — there’s nothing specific.
Manoj Chiranjeev Kothari
analystSir, and just one last question — sir, what utilization would we have achieved on our behalf, since we've had it commissioned for about eight months now into this period? So roughly what would utilization be at this point?
Ajay Kumar Saraogi
executiveRoughly 50% is present. Nearer to 50%.
Manoj Chiranjeev Kothari
analystAll right, that's useful. Thanks, sir.
Operator
operatorThanks. Our next question comes from Girija Ray at Nirmal Bang — please go ahead.
Girija Ray
analystHello, and thank you for taking my questions. Returning to the white business — the white cement business —
Operator
operatorGirija, we can barely hear you — it sounds muffled. Could you please talk through the handset?
Girija Ray
analystIs this okay now, clear?
Operator
operatorA bit better than that.
Girija Ray
analystCan you hear me? Yes. So to return to the question from Harsh Mittal, he was asking about the white cement business. Again, look, the situation is that sequentially, in the first quarter and the second quarter, realization has improved, and as you said, this is due to higher cost, and we can raise prices up to a certain level. Just to assume, let's say, first, the fourth quarter is always a volume-driven quarter for grey cement, and the first quarter is a price-driven quarter, that's what we believe. Likewise, can someone assume any quarter where we see volume growth in white cement, or does realization depend in a similar way?
Ajay Kumar Saraogi
executiveNo, I won't discuss the white cement. Quarter-on-quarter, the fluctuation isn't really there. This quarter — this month is definitely a strong one for white cement. It's the pre-festival peak season. We ought to see peak volumes this month. But then, again, we have a lean month in November because of the festivities, so volumes will suddenly drop again. And so — on a quarter-on-quarter basis, we — there won't be any major variation. Yes, some growth will be there, but nothing particularly significant.
Girija Ray
analystMuch appreciated, sir. Wishing you the very best.
Operator
operatorThanks. Ladies and gentlemen, because of time limits, we’ll take the final two questions. The next question comes from Navin Sahadeo at ICICI Securities. Please go ahead.
Navin Sahadeo
analystYes, thanks — thanks for the follow-up. My only question was about how we split advertising expense across the putty and white cement business versus the paints business. Because I believe last quarter we said it was break-even — that the paint business had reached break-even. This quarter shows a slight loss, though we still expect it to break even this year. It's also very encouraging to learn that future capex will come from internal accruals of this particular segment only. So I wanted to understand, at a very steady state, what margin do we expect this business to carry, and on the advertisement cost, how is that portion going?
Ajay Kumar Saraogi
executiveRegarding margins, first, we're attempting to figure out—we're working on enhancing margins, and for paint margins—we look at what competitors' margins are, and they're around 40% plus. Right now ours are lower. So across a phase—across a period of time we would—we keep working and get to figures near 35%, 38%, so that's the number we're currently aiming for. As for the advertisement portion, it's shared because this is a Maxx brand, where activities cover paint, putty, and partly white. So it's a common brand that we advertise. And more or less we've worked it out mostly as an allocation, trying to be more specific so each business receives its due apportionment of the cost. It isn't based on any top line or anything like that, but we're trying to allocate the cost so that—for paint—paint gets the fair—whatever the paint advertisement cost is, it's charged to the paint business.
Operator
operatorMuch appreciated. Given the time we have left, ladies and gentlemen, we’ll treat that as our final question. At this point, I’ll pass the conference to Mr. Vaibhav Agarwal, who will offer closing remarks.
Vaibhav Agarwal
analystYes, thank you. On behalf of Philip Capital India Private Limited, we want to express our appreciation to the Managing Director for this call, and also many thanks to the participants who are joining us. Thank you so much, sir. Nirav will now bring the call to a close.
Ajay Kumar Saraogi
executiveThank you, and thanks to all of you.
Prashant Seth
executiveThanks.
Ajay Kumar Saraogi
executiveThanks for being on the call. Appreciate it.
Operator
operatorI appreciate it. <<operator_signoff>> Thanks.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete J.K. Cement Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to J.K. Cement Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in J.K. Cement Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.