J. Kumar Infraprojects Limited (JKIL) Earnings Call Transcript & Summary

February 12, 2020

National Stock Exchange of India IN Industrials Construction and Engineering earnings 42 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day. And welcome to the J. Kumar Infraprojects Q3 and 9 Months FY '20 Earnings Conference Call, hosted by Anand Rathi Share & Stock Brokers. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Rachit Kamath from Anand Rathi Share & Stock Brokers. Thank you, and over to you.

Rachit Kamath

analyst
#2

Thank you, Stephen. Good day, and welcome to all the participants to J. Kumar Infraprojects Q3 and 9-month FY '20 Earnings Conference Call. Today, we will start with a brief update from the management for the past quarter and then proceed to a Q&A session. From the management, we have Mr. Kamalji Gupta, Managing Director; Mr. Nalinji Gupta, Managing Director; Mr. Arvind Gupta, Chief Financial Officer. Without further ado, I now hand over the call to the management. Thank you, and over to you, sir.

Unknown Executive

executive
#3

Thank you, everyone, and a warm welcome to everyone on this con call of J. Kumar for Q3. Along with me, I have Mr. Arvind Gupta, CFO; and our Investor Relations team. I hope everyone has an opportunity to look at our results. The presentation and press release have been uploaded on the stock exchanges and our company's website. Before I take you through the operational and financial performances, I would like to highlight a few points. We are very happy to maintain consistent growth momentum in revenue and profitability despite changing environment. We are delighted to report yet another remarkable quarter as we clocked 16% year-on-year growth in our revenue operations and 26% in PAT. Our careful project selection criteria, strong bidding and estimation capabilities, efficient project planning and management coupled with asset ownership and -- are our key to success. Our robust and well-diversified order book gives us confidence to deliver our growth targets in the foreseeable future. With our expertise and track record -- of our track record, we are hopeful to -- of being awarded more such Urban Infra Projects across the country. The recent budget had laid emphasis on our urban infrastructure and increased budgetary allocation, which should help our organization. Now allow me to give you an overview of our operational performances during the quarter. With regards to order book, our total order book as on 31st December 2019, stands at INR 12,433 crores, wherein metro accounts were approximately 55% followed by flyover and bridges, which accounts to around 31% of our order book. Our stand-alone financial performances for Q3 and 9-month ended FY '20 is as follows: revenue from operations for Q3 FY '20 grew up by 16% to INR 793 crores as compared to INR 686 crores in FY '19 Q3. Revenue from operations for 9-month ended FY '20 has grown up by 15% to INR 2,093 crores as compared to INR 1,819 crore in 9 months ended FY '19. And the EBITDA has also grown up by around 6% to INR 118 crore as compared to INR 111 crore in Q3 FY '19. EBITDA for 9-month FY '20 has grown up by 11% to INR 337 crore as compared to INR 302 crores in 9-month ended FY '19. The PBT has also grown up by 10% in the Q3 of FY '20 to INR 74 crores as compared to INR 67 crore in Q3 FY '19. The PBT for 9-month ended FY '20 has grown up by 7% to INR 193 crore as compared to INR 181 crore in 9-month FY '19. The PAT for Q3 FY '20 has grown up 26% to INR 56 crore as compared to INR 44 crore in Q3 FY '19. The EPS, which is not annualized though, for Q3 FY '20 stood at INR 7.36 per equity share as compared to INR 5.84 per equity share for Q3 FY '19. PAT for 9 months has grown up by 27% to INR 153 crore as compared to INR 120 crore in 9-month FY '19. EPS, again, not annualized, for 9-month FY '20 stands at INR 20.16 per equity share as compared to INR 15.83 per equity share for 9-month FY '19. With this, now I leave the floor open for questions. Thank you very much.

Operator

operator
#4

[Operator Instructions] The first question is from the line of Shravan Shah from Dolat Capital.

Shravan Shah

analyst
#5

Sir, in 9 months, we have done good in terms of the execution, INR 2,092 crore. So we guided for FY '20 INR 3,200 crore revenue and for FY '21 INR 3,600 crore. So I just wanted to know, are we able to do INR 1,100 crore revenue in the last quarter of this year? And is there any change in the guidance for this year and next year for revenue?

Unknown Executive

executive
#6

Shravan, we expect that we'll surely be able to maintain the guidance given by us for the current and the next year as we are quite on toes. And if you look at the top line that we did for the Q4 of last year also, which was around INR 900 crores, so we are sure that we should be able to match up the guidance given by us.

Shravan Shah

analyst
#7

Yes. Sir, primarily because why I'm asking is because I just wanted to understand 2, 3 projects, particularly Dwarka I, where -- Package 1 where we have already received the appointed date, where in this quarter, there was no revenue. Secondly, on Line 9 Mira Bhayandar, I think there is no revenue in this quarter; and Line 4A Gaimukh, there is also no revenue in this quarter. So I just wanted to know how much of revenue are we factoring in the fourth quarter for these 3 projects: Dwarka Package 1, Line 9 and Line 4A?

Unknown Executive

executive
#8

Well, for Line 9 and Line 4A, the orders have been received in the month of September 2019. So it's only 3 months now. And in 3 months, there are a lot of -- means, even the agreements got signed only in the month of October. So once -- the initial 6 months are always the time where we have to do a lot of preparatory works right from documentations, design basis report submissions, all your quality assurance plan, safety plan, and there are a lot of documentational work and site survey work, wherein we have to -- we do a lot of physical work in terms of making the alignment survey, soil investigation works, barricading, taking traffic permissions. So all these things don't count into the revenue part of it. So -- but for sure, in the Q4, we'll have a contribution coming in from Line 9, Line 4A as well as Dwarka Expressway. And the exact numbers can't be given because it's just part of the work, so I think you'll appreciate that.

Shravan Shah

analyst
#9

Yes, yes. No issues. Because I actually see a lot of -- as you are rightly saying, a lot of preparatory work, particularly in Mira Bhayandar, but there is no revenue, so that's what particularly I asked because I saw continuously there are -- work is going on. So that's what I wanted to ask. Secondly...

Unknown Executive

executive
#10

You'll start seeing it in this quarter.

Shravan Shah

analyst
#11

Okay. And sir, on Package 2, Dwarka, when -- because last time, we were expecting 15 December appointed date. So now what is the status when the appointed date will be there?

Unknown Executive

executive
#12

As we had mentioned that we have told them that we need a clear site, for which within a month's time from now, we should -- we have told you even last time around Feb is what we are expecting. So within the next 30 days' time, we should get the start date from -- for Package 1 as well. Package 2, we have already got.

Shravan Shah

analyst
#13

Okay. And sir, on the -- last time, we said we bidded for INR 1,000 crore Worli-Sewri. So what is the status? And what kind of -- also you have mentioned, in terms of the Mumbai Metro Line 10, 11, 12 and, also, which are on the DPR stages and also Delhi Metro Phase 4. So what kind of a tendering we can see? What kind of opportunities are there in next 6 months?

Unknown Executive

executive
#14

Yes. So Shravan, with regards to Worli-Sewri, we have learned that we are the lowest bidder. But we have not been informed anything, so we cannot comment much on that. But it's on the positive side. So there is nothing to worry about it. And with regards to Package 10, 11, 12 for the metro lines that you are talking about, the DPR is in progress. And once they get a nod from the government, they will float these tenders in a short span of 4 to 6 months' time. This is what we are expecting.

Shravan Shah

analyst
#15

And Delhi Metro, how much tendering we can see in next 6 months?

Unknown Executive

executive
#16

We are expecting close to like around INR 20,000 crores of underground metro works that will be coming up very shortly in Delhi Metro for the Phase 4, as well as also in Delhi, NCRTC has started tendering for underground projects and currently a INR 1,600-crore project is already into bidding stage, as well as Gujarat has come up with new tenders, Ahmedabad Metro, wherein they have floated tenders for Gandhinagar Metro, which is around close to INR 2,000 crores for the civil jobs as well as Surat Metro is about to be bidded. At the same time, there are a lot of other projects from -- means for this, what you call, I mean to say, the GMLR project, which is a tunnel from Goregaon to Mulund. So that tendering is around INR 5,000 crores. So there are a lot of opportunities. In short, if you talk about Maharashtra alone or if you talk as a pan India basis, there's a lot of opportunities that is there for all the infra companies. And I think this is the time where people can really think of working in a comfortable scenario.

Shravan Shah

analyst
#17

Yes. That's good to hear. So considering all this, now how much more -- if I include this Worli-Sewri INR 1,000 crore, apart from that, how much more are we expecting in terms of this year and the next year order inflow?

Unknown Executive

executive
#18

See, as you would appreciate that we are already in the middle of February. So there is nothing big in terms of order book that we can expect in this quarter, some couple of crores here and there, it's okay. But as such, whatever tendering process will happen, the order book should flow in only in the next -- Q1 of next year.

Shravan Shah

analyst
#19

Okay. So for the full year, how much are we planning to add in the next year?

Unknown Executive

executive
#20

Sorry, come again?

Shravan Shah

analyst
#21

For full year FY '21 next year, sir, how much more fresh orders are we planning to add?

Unknown Executive

executive
#22

See, for the next quarter -- I mean, for the next year, we are expecting order book grabbing of around INR 5,000 crores. With the whole year, we should expect at least INR 5,000 crores orders to flow in. This is what is our internal target.

Shravan Shah

analyst
#23

Yes. And lastly, sir, on some balance sheet numbers, what is the gross debt, cash, inventory, debtors and payable?

Unknown Executive

executive
#24

The gross debt is INR 703 crore. Hello?

Shravan Shah

analyst
#25

Yes, yes. Yes, sir. Go ahead.

Unknown Executive

executive
#26

Gross debt is INR 703 crore, inventory is INR 821 crore and FDR -- the INR 387 crore is FDR.

Shravan Shah

analyst
#27

Okay. So -- and including FDR, what is the total cash?

Unknown Executive

executive
#28

This is totally INR 420 crores.

Shravan Shah

analyst
#29

INR 420 crores. And sir, what is the debtors and payables?

Unknown Executive

executive
#30

Debtors is INR 782 crore and creditors is INR 300 crores.

Operator

operator
#31

The next question is from the line of Aniket Kulkarni, an individual investor.

Unknown Attendee

attendee
#32

Hello?

Unknown Executive

executive
#33

Yes, Aniket.

Unknown Attendee

attendee
#34

Sir, I need to know about the Delhi-Meerut RRTS project. So are we bidding for that project?

Unknown Executive

executive
#35

Yes, it is not NRCS, it is NCRTC. And for that, we will -- we are surely looking forward to bidding for that project.

Unknown Attendee

attendee
#36

Sir, and what's the opportunity size in that project?

Unknown Executive

executive
#37

Opportunity in the sense?

Unknown Attendee

attendee
#38

I mean how much order inflow can we expect from that project?

Unknown Executive

executive
#39

It's a project of around INR 1,600 crores, that's what I mentioned.

Unknown Attendee

attendee
#40

Okay, sir. Sir, and I just missed the order book guidance for next year. So can you please repeat?

Unknown Executive

executive
#41

Well, we are expecting around INR 13,000 crores to INR 15,000 crores somewhere is what we are looking at.

Unknown Attendee

attendee
#42

So the total order book will be around INR 15,000 crores by next year?

Unknown Executive

executive
#43

Yes, INR 13,000 crores to INR 15,000 crores, anywhere between that because we will be having around an execution of close to INR 1,200 crores in the current quarter -- in coming quarter. So we expect to stay anywhere between INR 12,000 crores to INR 15,000 crores.

Unknown Attendee

attendee
#44

Sir, and just looking at your presentation, why has the EBITDA margin dropped by 1.35%? Any specific reason for that?

Unknown Executive

executive
#45

See, EBITDA margin, if you see on a year -- on a 9-month basis, you will see that we are already around 16%. So every -- in a work of infrastructure work that we are carrying out, it totally -- every quarter cannot be the same. But what is more important to be seen is on a year-on-year basis, what margin you're making because the nature of work is such that there are certain times where the margins get fluctuated here and there. But as a project and as a -- on a year-on-year basis, if you see, the margins are well maintained at 16%, and we are sure to maintain that.

Unknown Attendee

attendee
#46

Sir, and what's the status of CIDCO Coastal Road Project and NBCC project? So are they going on?

Unknown Executive

executive
#47

Yes, yes. They have been -- the CIDCO work has already been awarded to us. And -- means, again, it is on the preparatory stage because it's been recently awarded.

Unknown Attendee

attendee
#48

So have we received the appointment date for CIDCO project?

Unknown Executive

executive
#49

[Foreign Language] Yes, CIDCO, we have already declared.

Operator

operator
#50

The next question is from the line of Shubham Jeswani from Mittal Analytics.

Yogansh Jeswani;Mittal Analytics;Senior Research Analyst

analyst
#51

Sir, Yogansh here from Mittal Analytics. Sir, a quick question on your order book. So you have a fairly good order book and you anticipate some more orders coming in. So can you also throw some light on how are we planning to fund these orders? Do we see debt going up further? Or -- and do we have any debt equity in mind that we would like to maintain?

Unknown Executive

executive
#52

Well, we are not looking at any major change in debt ratios because as of now, our gross debt is INR 703 crores, which is just 8.39% debt-equity ratio, which I guess you -- everyone will appreciate that it's much better than the peers. And with the internal cash accruals of the project and with the mobilization advances which are available to us, we are quite confident that we'll be able to -- there will be no major increase in the debt.

Yogansh Jeswani;Mittal Analytics;Senior Research Analyst

analyst
#53

Okay. Understood, sir. That's great. Secondly, sir, if you could also just broadly highlight the execution time line that you will have for this INR 12,000-crore, INR 13,000-crore order book, so what kind of annual run rate do you see going forward, say, in FY '21, how much are you expecting?

Unknown Executive

executive
#54

On an average, it's just between 3 to 4 years because certain projects are like from 30 months to 50 months -- 48 months. So like Metro Line 9 is having a completion period of 48 months, having a combination of elevated and underground works. So on an average, 3 to 3.5 years is what we expect for these projects.

Yogansh Jeswani;Mittal Analytics;Senior Research Analyst

analyst
#55

Okay. And sir, lastly, a couple of months back, there were some news articles when the new Maharashtra government was formed that the orders were again reviewed and there was a lot of disturbance on these orders. So are we seeing any kind of impact on business or any issues or any tussle with -- on some projects or something?

Unknown Executive

executive
#56

Yogansh, I think you will appreciate that immediately 2 days after that statement was being made by the Honorable Chief Minister, it was already being clarified by the next day that they just wanted to have a check on the awarding and whatever things were in there for the process. But in terms of award of the contracts, in terms of execution and getting payments, everything is smooth, and we have been receiving payments very regularly. And we don't see any impact as such on the change -- due to the changing political scenario.

Operator

operator
#57

The next question is from the line of Jiten Rushi from BOB Capital Markets.

Jiten Rushi

analyst
#58

Sir, I wanted to understand on the recently canceled orders in Mumbai Metro. We have seen some cancellation happening in Mumbai Metro because of the delayed execution. So what would be the next step? Will it come as a fresh bid? Or how it is going to happen, sir?

Unknown Executive

executive
#59

The tenders are already available online, and it's been -- it's on bidding now. So Line 7 contract has been, which was CA-01, that particular contract has been canceled, and it's already been put for bidding, and the submission is on 25th of -- 24th of February.

Jiten Rushi

analyst
#60

Okay. So there are 3 contracts in total, which were canceled, if I...

Unknown Executive

executive
#61

That is right. That was CA-01. And in Line 2B, there were 2 contracts: one of INR 1,000 crore and the another of nearly INR 500 crores. So all 3 tenders have been put for bidding, out of which Line 7 CA-01, which is the most priority work for them, that has already been put on bidding. And that's to be submitted by 24th of this month.

Jiten Rushi

analyst
#62

So this could be for the balance work. So what is the cost...

Unknown Executive

executive
#63

It's around 300, 150 and -- around INR 275 crores.

Jiten Rushi

analyst
#64

Balance work is INR 275 crores. Okay, okay. And sir, can you just tell me what is the order inflow so far in this year in terms of value and segmental breakup?

Unknown Executive

executive
#65

INR 4,289 crores, say, INR 4,300 crores is the order inflow in the 9-month ended FY '20.

Jiten Rushi

analyst
#66

And sir, 9 months revenue from metro and nonmetro in [ 3 ] and this quarter, if at all, it is possible to get a breakup?

Unknown Executive

executive
#67

In terms of revenue?

Jiten Rushi

analyst
#68

Yes, sir.

Unknown Executive

executive
#69

Okay. So around 73% of the revenue comes in from metro line and -- from the metro projects and around 27% from the others.

Jiten Rushi

analyst
#70

Okay. This is for the 9 months, right?

Unknown Executive

executive
#71

9 months. That's right.

Jiten Rushi

analyst
#72

And sir, what -- can you just highlight on the status of the Mumbai Metro 3 underground project? How much work has been completed? And at what stage are we at?

Unknown Executive

executive
#73

So around 50% of Line 3 project is completed and around 75% Metro Line 2 is completed and Metro Line 7 to the tune of around 90% has already been completed.

Jiten Rushi

analyst
#74

Okay. So now at least these are in the -- so Metro Line 3, we can -- can we expect it to complete by end of next financial year? What is the target?

Unknown Executive

executive
#75

Well, I think it would take around 1.5 -- 18 months at least from now because all the problematic situations which are there when you start the work has already been sorted because there are a lot of utility shifting and some unexpected issues, which were not expected or which are not known to even the government bodies, so that things have already been sorted. And now what -- the excavation works are completed and RCC has started, the structural work for the main structure. And also, the tunnelings are being completed in quite a good areas. So I think 1.5 years is at least what you should expect. One year is too short to complete it.

Jiten Rushi

analyst
#76

Okay. And sir, just finally, on the bank limits, nonfund and fund limit and utilization levels?

Unknown Executive

executive
#77

Yes. So we have a sanctioned limit of around INR 4,430 crores, out of which 78% is only utilized till now. That's around INR 3,500 crores approximately.

Jiten Rushi

analyst
#78

Sir, this is the total limit, but can you give me the breakup between nonfund and fund?

Unknown Executive

executive
#79

So fund-based limit, we have INR 700 crores, wherein only INR 500 crores has been utilized, that is 72%. And for term loan, it is INR 263 crores, out of which only INR 194 crores has been utilized, which is another 74%. So major fund -- limit is nonfund based, which is INR 3,450 crores, out of which INR 2,800 crores is what has been utilized.

Jiten Rushi

analyst
#80

Okay. And sir, what is your view on the bidding currently? Because now we've seen a lot of dull ordering happening in the last 18 months, and now the bidding has been aggressive from most of the bidders. So do you see any competition in terms of aggressive bidding and -- which can impact the margins going forward? Or we are happy with what we are getting right now?

Unknown Executive

executive
#81

See, well, I would say that there has been aggressive bidding in certain areas, but if you look at the job opportunities which is available pan India in terms of Chennai Metro has come up with huge number of projects, Delhi has come up with new metro projects, NCRTC projects, National Highway has come up with extension of Dwarka line, there is so many road works, flyovers, structures, MCGM, MMRDA, MSRDC. So there are N number of works which are available. So you can find, means, hard competition in certain areas like Delhi, where there were no contracts for a long time. From last 3 to 4 years, there were no major contracts that had come up. So that's the reason in Delhi, for the elevated projects, there were some sort of aggression by the bidders. But if you look at Maharashtra, Gujarat, I think NH projects, there are so much work is available, I find that there are no proper or enough bidders to take up such projects.

Jiten Rushi

analyst
#82

Okay. And sir, what is the pipeline from Chennai Metro in terms of packages and value?

Unknown Executive

executive
#83

So Chennai is close to around 5,000-crore-odd jobs has been floated by them.

Jiten Rushi

analyst
#84

And how many packages it would be?

Unknown Executive

executive
#85

It's around 3 -- 2 or 3 packages.

Jiten Rushi

analyst
#86

Elevated?

Unknown Executive

executive
#87

Yes. So it's like there are 2 packages of around INR 2,000 crores, INR 2,500 crores, which is for the underground metro, which they have already floated.

Jiten Rushi

analyst
#88

This is undergone metro, okay, not elevated. Okay.

Unknown Executive

executive
#89

Yes.

Operator

operator
#90

The next question is from the line of [ Darshan Manik from Lark Consultancy. ]

Unknown Analyst

analyst
#91

Yes. Just if you can provide details about the Mulund-Goregaon project, where the bidding stages and when the tender result can be out?

Unknown Executive

executive
#92

Well, for Goregaon-Mulund link road, it's a tunneling job, which is around 13-meter dia and the work is from MCGM and the tendering process in terms of RFQ started, and I think somewhere in the month of March is what the RFQ, that is the request for qualification, would be submitted. And within the next 2 to 3 months, we should be having the financial bids submitted.

Unknown Analyst

analyst
#93

And the project duration will be for around 2 years, if I'm not wrong?

Unknown Executive

executive
#94

No, no, no. It's a tunneling job. So for sure, it would be something close to like 3.5 to 4 years.

Operator

operator
#95

[Operator Instructions] The next question is from the line of Alok Deora from Yes Securities.

Alok Deora

analyst
#96

Just one question. This MM 7 on the bids, which are -- a tender, which has been floated, are we looking to bid for that? And also, the delay because of the change in contractor, does that impact the existing work, which we are doing?

Unknown Executive

executive
#97

Well, Alok, firstly, yes, we are surely going to bid for this Line 7 balance work as it falls within our same alignment and establishment. So we'll surely try to go for it. And with regards to impact on the existing work, it is no way related because all the projects are individual and any completion or noncompletion does not affect the execution of the said project, though it will have an implication surely as an overall completion of the line for MMRDA, but with regards to the contractor's point of view, there is no implication.

Alok Deora

analyst
#98

Right. So when do we see this project actually getting completed as in our part getting finished?

Unknown Executive

executive
#99

Well, from J. Kumar's part, in the next month, that's by end of March, J. Kumar is the only contractor I'm very proud to say that is that we will be completing our entire project because 90% of the project is already completed by us. And the entire launching activity for Line 7, which is from Goregaon to Kandivali, that stretch will be completed by us by next 20 days' time.

Alok Deora

analyst
#100

Okay. And NCC slightly behind schedule is it?

Unknown Executive

executive
#101

Yes. Well, I wouldn't like to really comment on such things, but there are a lot of issues even for land or the method of construction and various other issues. So they would take some while though. But still by -- before -- around May, all the projects should be completed. Even for this new project of Line 7 balance work, the time line given is only for 6 months. And fortunately, this line -- this package CA-01 falls at the fag end of the line. So because of that, the lines can be made operational even without commissioning this station. So -- but still 6 months time line has been given and by -- this tender being a very highly important project of the whole line, this will be awarded very quickly. And -- so say, from around August is the date of completion, so practically, the entire work should be operational in the month of December or January, we should be able to use the Line 7.

Alok Deora

analyst
#102

Right. Just one last thing. The Simplex work, which is now gone for rebidding, so what's the value for that, I missed that number, actually?

Unknown Executive

executive
#103

INR 275 crores.

Alok Deora

analyst
#104

Okay, okay. So basically, it was around INR 350-odd crore and till now INR 275 crores is pending, is it?

Unknown Executive

executive
#105

It's not exactly like that. It's around -- works to the tune of around INR 200 crores or something was spending, but because of the price escalation that's been happening over that, which he was getting, so that needs to be added as well as there are some changes, which has been -- which we have proposed to the government to speed up the job because at this situation, where there is a change of contractor and the difficult areas, which has been led by him, would take some while, so because of that, there are some change in methodology. So the cost has gone up.

Alok Deora

analyst
#106

Okay. Just one last question. So that stretched -- the work has completely stopped as of now?

Unknown Executive

executive
#107

Yes, of course, it is stopped.

Operator

operator
#108

[Operator Instructions] The next question is from the line of Shravan Shah from Dolat Capital.

Shravan Shah

analyst
#109

Sir, how much mobilization advance is outstanding as on today? So how much have you taken? And how much more can be taken in the fourth quarter?

Unknown Executive

executive
#110

You can take around -- INR 550 crores more advance can be taken by us, which is mainly for Dwarka and MM Line 9 and project 4A, 6. And outstanding advance, mobilization advance as of now is around INR 486 crores.

Shravan Shah

analyst
#111

INR 486 crores. Okay. And sir, I just wanted one thing, in terms of the employee cost though -- why it fluctuates, particularly in the third quarter? Is that all the appraisals happens in this quarter because even the last year also and this year from second quarter to this quarter, from INR 69 crore to INR 84 crore, and in the fourth quarter, it comes down. So what is the -- why it happens?

Unknown Executive

executive
#112

See, there is no major change as such, if you look at the employee cost, which is like 8.9%, which was there as a -- on a year-basis figure. And as of now, for 9 month, it is around 10.1%. So 1%, there has been a change because of recruitment of some senior level employees by the organization as we are -- the size of the company is growing, so we need some good peoples to be associated at senior level. So that's the reason why you can see the slight increase.

Shravan Shah

analyst
#113

Okay. So -- because even till last time also, from the second quarter to third quarter, the employee cost rises and in the fourth quarter, it comes down. So INR 10 crore, INR 15 crore it increases and then it comes down in the fourth quarter. So will it be the same case...

Unknown Executive

executive
#114

If you look at the Q2 figure -- if you look at the Q2 percentage, it was 10.9%, whereas in Q3, it has come down to 10.6%. So it is -- if you see with the Q4 figure coming up, you'll further find it to be reducing. So that's basically related to your top line because the fixed cost remains the same.

Operator

operator
#115

[Operator Instructions] The next question is from the line of Rachit Kamath from Anand Rathi Share & Stock Brokers.

Rachit Kamath

analyst
#116

Sir, I just wanted to understand project-wise revenues that we are targeting in the next year for FY '21? If you can give...

Unknown Executive

executive
#117

You're talking for FY '21?

Rachit Kamath

analyst
#118

Yes.

Unknown Executive

executive
#119

For FY '21, we can just mention that approximately around INR 2,500 crores is what we are expecting from metro works and nearly around INR 1,000 crores is what should come in from other projects.

Rachit Kamath

analyst
#120

Okay. And sir, for Q4, you are targeting around INR 1,200 crore a quarter. So how -- from where are we planning to source this from?

Unknown Executive

executive
#121

See, as we have mentioned that around 70% will be all from metro works because historically if you see the 9 months figures as well as the FY '19 figures, around 70% is coming in from the metro works and around 25% to 30% is from others. So Bombay Metro (sic) [ Mumbai Metro ] is major projects where we have been working. And as on now, around 93% of the revenue has come up from Maharashtra for Q3. So this is the main area from where we are expecting this top line.

Rachit Kamath

analyst
#122

Okay. Sure, sir. Sir, one last question is regarding the debt figure. So we are planning to close our debt somewhere around INR 700 crores for this year, if I'm not mistaken, INR 700 crores to INR 720 crores?

Unknown Executive

executive
#123

Yes. The gross debt will be around INR 700 crores approx.

Rachit Kamath

analyst
#124

INR 700 crores. Sir, one question on mobilization advances, you just said that we have -- we can access only INR 550 crores more of mobilization advances, if I am not mistaken?

Unknown Executive

executive
#125

Can you come back once again with your question?

Rachit Kamath

analyst
#126

Sir, you said we can draw only additional INR 550 crores of mobilization advances. Is that correct?

Unknown Executive

executive
#127

Yes. We are entitled for additional INR 550 crores, which we'll pick up as and when it is required for the project. So in 6 months' time to 1-year span, anywhere we'll pick up this money.

Rachit Kamath

analyst
#128

No. So my question was, shouldn't we be entitled to a bit higher amount because we -- in Q2 itself, we had around INR 3,000-plus crores, INR 4,000 crores kind of -- INR 3,000 crores kind of an inflow? So I just was wondering...

Unknown Executive

executive
#129

See, the order book, totally, which came in was around INR 4,500 crores approximately for Q3 -- Q2 for the 9 months, and out of which everywhere, there are not -- all the projects are not with interest-free amount. So we are basically trying to focus on the projects where we get interest-free mobilization advances. So that's how we are trying to tell you a figure, which would be around INR 550 crores, which will, of course, include Dwarka Expressway, which is interest-bearing. So this is an approximate advance what we are entitled for.

Rachit Kamath

analyst
#130

Sure, sure. I understand, sir. Sir, this last question is on the Simplex project. Given the fact that we are already going to complete our Line 7 project and this is an adjoining package, if I'm not mistaken, how well placed are we? Or has the authority come to us regarding this project?

Unknown Executive

executive
#131

See, it is basically for such a type of work, where the tender has been split into 2 portions of INR 150 crores for viaduct and around INR 125 crores-odd for the stations. So for such type of works, of course, we stand at better chance because we are well established.

Operator

operator
#132

The next question is from the line of Jiten Rushi from BOB Capital Markets.

Jiten Rushi

analyst
#133

Sir, I just wanted to know the Gross Block as on December and the CapEx for 9 months and full year targeted CapEx for FY '20 and then FY '21 CapEx target?

Unknown Executive

executive
#134

As of 9 months, we have made a CapEx of around INR 82 crores, and we're expecting add-on of around INR 20 crores more for this year, as we are getting in a straddle carrier mainly, which is for the launching activities as well as some transit mixers, batching plant sort of things. So INR 20 crore is additional what we are expecting, taking the CapEx for this year to around INR 100 crores, followed by FY '21, we expect a CapEx of around INR 30 crores to INR 40 crores maximum.

Jiten Rushi

analyst
#135

Okay. And what is the Gross Block size as on date -- as on December?

Unknown Executive

executive
#136

I'm sorry, come back?

Jiten Rushi

analyst
#137

Gross Block size as on December?

Unknown Executive

executive
#138

Gross Block is INR 780 crores.

Operator

operator
#139

[Operator Instructions] The next question is from the line of [ Mohit Bansal from Ajinkya Investment. ]

Unknown Analyst

analyst
#140

Sir, what I have gathered from the con call is that we have sufficient bank lines to carry on the projects for the next -- our projection for the next year, and we also are getting advances, I just wanted to understand, sir, we are going to generate sufficient cash flows, what would be the best use of those cash flows going forward according to the management?

Unknown Executive

executive
#141

See, historically, we have been using the internal cash accruals for working capital as well as for the CapEx requirements. So -- and that's the reason, like, in the past couple of years, we have not made any fundraising or anything, and we don't look forward to raising any external funds for the next couple of years. So the internal cash accruals are basically utilized for this working capital and CapEx.

Unknown Analyst

analyst
#142

Okay. But as we can see, sir, that, we are generating because we are at a level where we are generating cash flows, which are pretty much higher than the past. So is there a view where we can probably look at -- because 3 SEBI clean chit, there were in the con call discussions regarding a buyback. Just wanted to understand your views on that, sir?

Unknown Executive

executive
#143

We have already done a buyback of nearly around 1% in this year -- from the promoters. Okay. From the promoter side, we have done 1%. And basically, the cash flow -- the requirement of raising money for the -- as there are new orders coming up and the company is growing and the size -- if you look at the order book and if you look at the nature of work, so for this metro works in terms of the requirement of CapEx, in terms of working capital, if you see FY '19 to FY '20, there has not been any increase in the debts. So that's basically because of the internal and positive cash flows that we have been able to sustain the same debt levels.

Unknown Analyst

analyst
#144

Yes. I mean that's prudent, sir. And...

Unknown Executive

executive
#145

We will be trying to reduce the debt with this extra money.

Operator

operator
#146

The next question is from the line of Rachit Kamath from Anand Rathi Share & Stock Brokers.

Rachit Kamath

analyst
#147

Yes. Sir, one question. It's one of the previous questions, I just wanted to understand what's our status on the NBCC order?

Unknown Executive

executive
#148

NBCC?

Rachit Kamath

analyst
#149

Yes, sir.

Unknown Executive

executive
#150

So that's not been awarded to us yet. And we have already -- means, it is likely to get canceled.

Rachit Kamath

analyst
#151

Okay. So we have it in -- okay, okay. Sure, sure. And sir, are there any other slow-moving orders in the order backlog or the whole backlog is moving?

Unknown Executive

executive
#152

No, that's the only order of NBCC. Otherwise, as we had mentioned, all the works -- the newly awarded works, which were mainly for Metro Line 9, Metro Line 4, Dwarka Expressway, everything is well under the pipeline and works have started at mostly all the projects.

Operator

operator
#153

[Operator Instructions] As there are no further questions, I now hand the conference over to Mr. Rachit Kamath for closing comments.

Rachit Kamath

analyst
#154

Thank you, Stephen. We thank the management for giving us this opportunity to host the Q3 and 9-month FY '20 earnings conference call. And wish them the best of luck for the next quarter. Over to you, sir.

Unknown Executive

executive
#155

Thank you, everyone, for joining on the con call. We hope we have been able to answer your queries. For any further information, we request you to kindly get in touch with our investor team, and have a good evening, everyone. Thank you very much once again for joining the call.

Operator

operator
#156

Thank you. Ladies and gentlemen, on behalf of Anand Rathi Share & Stock Brokers, that concludes this conference. Thank you for joining us. And you may now disconnect your lines.

Unknown Executive

executive
#157

Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete J. Kumar Infraprojects Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to J. Kumar Infraprojects Limited earnings transcripts and 251,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.