K92 Mining Inc. (KNT) Earnings Call Transcript & Summary

August 10, 2023

Toronto Stock Exchange CA Materials Metals and Mining earnings 52 min

Earnings Call Speaker Segments

Operator

operator
#1

Thank you for holding. Speaking is the conference operator. We welcome you to the conference call on financial results for the second quarter of 2023. Please note that everyone joining is in listen-only mode, and this call is being recorded. <<operator_script>> At this point, I'd like to hand the conference over to the President, David Medilek. You may proceed.

David Medilek

executive
#2

Thanks, operator, and I appreciate everyone joining us for K92 Mining's conference call on our Second Quarter 2023 results. We hope things are going well for all of you and your families. Along with me on the line are John Lewins, our Chief Executive Officer and Director, and Justin Blanchet, our Chief Financial Officer. I also want to remind everybody that following management's remarks, we'll move into a Q&A session. Since forward-looking statements will be made during this call, we ask you to review the cautionary notes and risk disclosure found in our MD&A as well as on Slide 2 of the webcast presentation. Please also keep in mind that any dollar figures discussed on this conference call are denominated in United States dollars unless we say otherwise. At this point, I'll hand things over to John for an overview.

John Lewins

executive
#3

Thanks, David, and welcome, everybody. During Q2, K92 posted robust operational results, lifting gold-equivalent output 43% versus the first quarter and 18% compared with Q2 2022. For the quarter, cash costs and all-in sustaining costs came in well below the range we guide to annually. Our cash position strengthened markedly over the quarter, even following capital and exploration spending that was close to record levels. We likewise advanced a number of growth efforts substantially, among them finishing the Stage 2A plant expansion; uncovering a high-grade zone — the J2 vein at Judd South — which may delineate still another productive vein across the Kora South, Judd and Judd South vein systems; and, after quarter end, our Board of Directors sanctioned awarding the Stage 3 expansion process plant lump sum EPC contract, which takes a great deal of risk out of most of the growth capital for the expansion. We're eager to walk through all of this in greater depth as the presentation proceeds. The company's performance, as highlighted in the 2022 sustainability report released in late July, makes us very proud. That report lays out our principal sustainability initiatives and shows our dedication to socially responsible mining. K92 employs roughly 1,500 people, with a strong emphasis on hiring locally — about 94% of our workforce comes from Papua New Guinea, and most are from our nearby communities, with a clear major emphasis on training and development.

John Lewins

executive
#4

K92's environmental impact is modest, thanks to a conventional tailings impoundment, zero cyanide use, and a low greenhouse gas emissions profile. Right now we're concentrating on a number of long-term social and economic development efforts in Papua New Guinea — through joint ventures, education, infrastructure, service programs, agricultural programs, and investment in female empowerment programs, among many other things. ISS has acknowledged K92 as having corporate governance that leads its peers, and we rank as the second largest corporate tax payer in Papua New Guinea's mining industry. We'd encourage you to read the report, which you can find on our website. Although that report addresses the 2022 fiscal year, we are deeply saddened to report two tragic incidents that led to multiple fatalities during the quarter. Those were previously disclosed through a press release. The health and safety of our workforce has always been our top priority and will remain so, and we're committed to providing additional disclosures about these incidents and the steps we've taken to strengthen our safety culture in our 2023 sustainability report. In June, K92 was very pleased to announce our 2030 greenhouse gas emissions target: cutting our scope one and two emissions by 25% on a business as usual basis. K92 already stands among the lower emission gold mines worldwide, and we're committed to further enhancing our energy and GHG emission platform.

John Lewins

executive
#5

We think we're in a strong position, with a clear route to hitting that target by improving access to hydropower from the local grid alongside other reduction efforts. I want to note that we've already acted this year to improve our greenhouse gas emissions, with a dedicated power line now finished from the Ramoo substations beside. That line was put in to boost the reliability of hydroelectric power from the distribution grid, allowing us to cut back on standby diesel gensets. Together with PNG, we're evaluating additional opportunities to make the most of hydropower. Turning to operational performance: in the quarter, the Kainantu mine generated 30,794 ounces of gold equivalent, 112,471 tons processed at a head grade of 9.2 grams per ton gold equivalent; versus Q1 2023 and Q2 2022, production rose by 43% and 18% respectively, and long hole stoping in the quarter met design. Cash costs came in at $597 an ounce and all-in sustaining cost at $975 an ounce, notably below the annual guidance range of $622 to $684 for cash costs and $1,180 to $1,300 for all-in sustaining cost. On our key operational quarterly physicals, Kainantu came in within 5% to 10% of our record ore tons processed, total material mined and developed — and that was despite the effects of the safety incidents in the case of processing tons, plus the work tied to Stage 2 mine commissioning.

John Lewins

executive
#6

Like we mentioned on earlier calls, getting our development rates higher is still a key priority for us, since we're making up for development delays caused by the COVID-19 pandemic. And I'm happy to say that a new jumbo came on site in July. One big highlight in Q2 was how the process front performed, with recoveries rising substantially once we finished commissioning the new rougher flotation cells, which have doubled rougher flotation capacity — that came as the last piece of the Stage 2A plant expansion, finished in May. During the second quarter, recoveries for both gold and copper were the best we've seen since Q4 2021, and in June gold recoveries hit the integrated development plan parameters of 93%. With that initial commissioning now behind us, optimization work aimed at lifting recovery further is in progress. I'll now hand the call to our Chief Financial Officer, Justin Blanchet, to go over our financial results for the second quarter. Thank you, Justin.

Justin Blanchet

executive
#7

Thanks, John, and hi everyone. In the second quarter of 2023, we brought in $51.8 million in revenue, which was up 39% versus the prior year. We moved 28,141 gold ounces at an average selling price of $1,883, versus 23,674 gold ounces at an average selling price of $1,783 a year earlier. As of June 30th 2023, inventory held 2,398 gold ounces, covering both concentrate and doré a, which was a decline of 895 gold ounces relative to March 31st because of the timing of sales. During Q2 2023, cash flow from operating activities before changes in working capital came to $16.2 million, versus $10.5 million in the same period a year prior. At June 30th 2023, cash and cash equivalents stood at $95.6 million. As of June 30th, K92 posted one of its strongest working capital balances on record at a $112.5 million, even after spending $22 million on property plant and equipment during the quarter. There is no debt on the company's balance sheet. The rise in cash and cash equivalents relative to March 31st stems mainly from higher production and total metals sold, while we still spent $15.9 million on expansion capital. In Q 2023, cost of sales was $29.2 million, versus $23.2 million in the prior year, or $21.8 million versus $18.5 million when non-cash items are excluded.

Justin Blanchet

executive
#8

Even though cost of sales went up overall, we still got better economies of scale and a lower unit cost per ton of ore produced, thanks to the successful ramp up of the stage 2 expansion, with ore and waste tons mined rising 17% to 266,613 from 227,673 in Q2 2022. As John mentioned, in the second quarter, the Kainantu Gold operations produced 27,405 ounces of gold, 1,526,547 pounds of copper and 34,001 silver ounces, or 30,794 ounces of gold equivalent. We sold 28,141 ounces of gold, 1,657,115 pounds of copper and 36,253 ounces of silver. We incurred a cash cost of $597 and an all-in sustaining cost of $975 per ounce of gold, which was significantly below our realized gold selling price of $1,883 per ounce. Our Q2 2023 cash cost per ounce of gold decreased to $597 from $617 in Q2 2022. The decrease in cash cost was primarily due to the increase in production as compared to prior year. Our Q2 ounce ascending cost per ounce of gold increased to $975 from $893 in Q2 2022. The increase in cost per ounce can be attributed to spending $8.3 million on sustaining capital as compared to $4.9 million in the same period prior year.

Justin Blanchet

executive
#9

Higher sustaining capital largely reflects equipment replacements made this quarter. At this point I'll hand the call over to John, who will carry on with the remainder of the presentation.

John Lewins

executive
#10

Thank you, Justin. To start the exploration growth portion, we're going to show a brief video of the Stage 2A plant expansion that was completed in May — it begins at the crushers and flies toward the mill, the flotation circuit, the gravity circuit, and the press buildings. As mentioned before, the last piece of that work — doubling the wrapper flotation capacity — went into commission in May 2023. Since commissioning, plant performance on recovery and throughput has been strong, and we keep optimizing the plant so it reaches its ultimate recovery and throughput potential, whatever that ultimately turns out to be. I'd also like to pause and recognize the team on-site who delivered both the Stage 2 and Stage 2A plant expansions. From the end of 2019 through today, this team has more than tripled the throughput rate, and a great deal of that expansion work got done during the pandemic. Turning to the growth pipeline for the Kainantu mine strategy, Stage 2A, as noted earlier, is now complete. On Stage 3, we have made considerable progress across multiple areas of the expansion. On July 24th, the Board of Directors authorized awarding the engineering procurement construction lump sum contract for the Stage 3 expansion process plant to GRR Engineering Services.

John Lewins

executive
#11

The contract award is valued at $81 million U.S. dollars, structured as a lump sum fixed price arrangement. At the same time, we announced that long lead items for the main process plant have now been ordered. For the Stage 3A expansion process plant, roughly 94% of the total capital cost has been fixed. Based on the integrated development plan, that accounts for more than half of the total growth capital cost of the stage three expansion, and it substantially reduces the risk of potential increases in growth capital costs for the expansion. As previously announced, commissioning of the process plant is targeted for the end of Q1 2025, and the forecast cost sits within 10% of the Kainantu integrated development DFSMPA case. As noted earlier, increases in growth capital cost have been substantially derisked. We are extremely pleased with this outcome. The Stage 3A expansion has also made novel progress across multiple other areas. As the picture on the right shows, the attaining lift 1C is well underway and approximately 60% complete, with completion targeted for the end of 2023. Our accommodation facilities continue to expand, with capacity due to exceed 1,500 by the end of 2023, which is the capacity required for the Stage 3 operations. Front-end engineering design for the Paste Fill plant is proceeding, and we expect to award the final contract in Q4, and the process continues to advance across various on the ground surface infrastructure packages, including vertical development power and transportation.

John Lewins

executive
#12

Regarding treatment, by the end of July the twin incline has been reduced by 2,539 meters and stands more than 80% finished. During Q4, we intend to begin extracting the lower section of the core resource from the twin incline earlier than planned, which will progressively deliver a substantial increase to our operational flexibility in 2024 as we create the new mining front at depth. The twin incline additionally offers a highly practical platform for drilling and exploration. As I believe many of you know, the twin incline is built to handle as much as 5 million ton per annum with conveyors, which is several times greater than the throughput of the Stage 3 and stage 4 expansions. We chose this only because we do not yet know how large the system is and will become, and how many expansion stages potentially lie ahead of us. Given what exploration has shown us, it is fair to say we are glad that we oversized the twin inclines. On near mine drilling, we are presently drilling Kora, Kora Deeps, Kora South, Judd South targets either from underground or at surface targets, including Maniape, and Arakompa and Karempe carry very high potential and we anticipate starting to secure in due course.

John Lewins

executive
#13

Turning to the long portion of Kora, the Kora South Vein system, I want to highlight three main things. First, since the previous estimate, quite a lot of drilling has taken place beyond the resource, as shown by the various annotated points, and that area now spans non-drill straight lengths reaching as much as 2.65 kilometers. Second, sideways drilling has uncovered by latent zones — two zones interpreted today, marked with the blue lines and the double arrows you can see there — which have delivered record intersections, among them 27.9 meters at 10.5 grams per tonne gold equivalent and 50 meters of 5.2 grams per tonne gold equivalent. These zones look to have limited straight length with meaningful potential, vertically, and our understanding keeps progressing as we carry out our drill program in this area. Third, we see underground drilling entering an exciting phase, with both Kora Deeps and Kora South now underway at the depths highlighted by the two blue ellipses visible for the site and depths. Along with drilling Kora South from the surface too, using the third ellipse, all of these are high-potential areas. Now, looking at the long section of Judd, the Judd South vein system, there are four key points I think I'd like to make here.

John Lewins

executive
#14

To start, we have broadened quite a bit how much drilling has been done across the Judd resource, achieving a very impressive success rate along with several high-grade results. Next, Judd, similar to Kora, possesses a latent zone — with two zones currently interpreted — and again, looking into the <<inaudible>>. Third, during the third quarter we reported the discovery of a high-grade zone along the flanks in a second vein at Judd J2, returning 2.4 meters at 345 grams per tonne, which I will cover on the following slide. And finally, as with Kora, we foresee an exciting stretch for underground drilling at both Judd Deeps and Judd South. On May 25th, we reported six two drill holes from Kora and Kora South. The result stood out thanks to the discovery of the high-grade zone at the J2 vein on the South side, aligned with the ellipse shown here. That included, as I noted earlier, 2.4 meters and 345.36 grams per tonne gold equivalent. Additional high-grade intersections included KUDD0045, which returned 11.2 meters or 12.69 grams per tonne gold equivalent, and KUDD0043, which returned 3.8 and 10.19 grams per tonne gold equivalent. Importantly, the J2 vein is absent from the current resource estimate, is opening in multiple directions, and has achieved a hit rate to-date of 46% of intersections exceeding 5 grams per tonne gold equivalent.

John Lewins

executive
#15

At the K1 vein, the highlights start with surface drilling KODD0036, which returned five meters at 161 grams per tonne gold equivalent, targeting a sizable under-drilled area between the Judd resource estimate and surface within ML150, and KUDD0040, which cut our latent zone, returning 22 meters at 5 grams per tonne gold equivalent, along with a broader intersection that included a substantial 57.8 meters at 2.73. As the long section shows, J1 is opening up in several directions and has produced strong hit rates so far. Drilling has expanded across multiple zones of known high-grade mineralization at Kora and Kora South, with highlights at the K1 vein that include KNDD0485, recording 5.94 meters at 15.96 grams per tonne gold equivalent, and KNDD0545, recording 7.98 meters at 12.14 grams per tonne gold equivalent. K2 vein highlights included KNDD0535, 10.3 meters at 12 grams per tonne gold equivalent, and KNDD0525, recording 5.65 meters at 9.08 grams per tonne gold equivalent. On post exploration, we continue to make progress at A143, recording multiple porphyry vectors from drilling, and we look forward to updating the market in due course. With that, operator, we’d like to begin the Q&A session. Thank you.

Operator

operator
#16

Thanks. <<operator_script>> Our first question is from Ovais Habib at Scotiabank. You have the floor.

Ovais Habib

analyst
#17

Thanks, operator. Hi, Jordan, and hello to the K92 team. I have a couple of questions to kick things off. First, sustaining capital came in roughly 26% below Q1. I believe you were aiming to speed up development as we move into the second half. Do you have the equipment and the people in place to spend the development budget set aside for this year? Or do you expect some of it to spill over into 2024?

John Lewins

executive
#18

Alright. Thank you, Ovais. Now, regarding capital, it fluctuates a bit from quarter to quarter. As for equipment, yes, we already possess the machinery that was required by this stage of the year. And actually, I believe that after the quarter ended, one more transformer showed up at the site. So a couple of units have come in at long hole drill. An extra jumbo plus an additional loader charge up machine, along with plenty of other gear, have arrived on site. We are certainly increasing our workforce. And in fact, come year-end, CAT, for example, will be running at the capacity needed for Stage 3. So we're actually ahead on some of our capital — we are in fact spending and on some of the expansion work we're carrying out. But right now, we have the personnel on the equipment required to hit the figures for sustaining capital.

Ovais Habib

analyst
#19

Perfect. Appreciate the detail. Then, just on Q4 — my understanding is that it's only the Kora zone you plan to mine in Q4, and that isn't in the budget. Could you give any sense of how many tons or what grade we should expect there? And as we head into 2024 as well?

John Lewins

executive
#20

To be honest, I’d say not right now. We aren’t anticipating a large tonnage, since there will be only limited development work on ore. So we don’t anticipate recovering much tonnage from that area. But clearly, in the south, there will be no stoping down on the 911 recent developments along strike on Kora.

Ovais Habib

analyst
#21

All right, thank you for that. Perhaps I'll stop at that point. And — and I appreciate your taking my — incidentally, I'm eager to visit the site next week as well.

John Lewins

executive
#22

Yeah, well, I'm here to make sure those — get made and everything like that.

Operator

operator
#23

Our following question is from Alex Terentiew at Stifel. You have the floor.

Alex Terentiew

analyst
#24

Morning, everyone. I’ve got a couple of questions. The first is somewhat tied to what Ovais asked. With Barrack and the group program showing some progress and essentially aiming to restart it, has that altered the labor or cost situation at all in the country, or for your projects in any way, over the past, I suppose, couple of months?

John Lewins

executive
#25

Thanks, Alex. That's a reasonable question. Clearly, we gained from the sole other underground mine occurrence. I think it's fair to say we have, we do have some individuals that we have — I mean skilled individuals, unskilled underground individuals who are arriving from everywhere. And we certainly anticipate moving those individuals back to power, purely because they're coming down from the SEM bus or we fly them down from there. We don't view it as a significant problem for us, purely because we did operate with ourselves in the past and we've actually placed a fair amount of emphasis on actually building up the skills of our local individuals, and that's deliberate — if the individuals from here in our communities, then they will tend to remain with the mine, they will not be seeking to head up to up to Kora. And I think from an operating standpoint. But we provide what I would describe as a superior operating environment compared with what we have at the top. So, we know we want to have one or two shortages, individuals departing with little modest, but I mean, on the whole we're ramping up numbers and seeking to get ahead of the curve in terms of — in terms of the numbers and then ultimately, in terms of experts in key things like <<inaudible>> and jumbo operators and the like?

John Lewins

executive
#26

Recruiting those individuals hasn't presented us with any major problems so far.

Alex Terentiew

analyst
#27

All right, thanks. And I suppose, clearly, since you folks are already well along and at stage 3, you probably have, I'd imagine, somewhat of an edge when it comes to retaining those people. But great — so my second question: it's great to see the exploration budget rise this quarter. I know you mentioned quite a few targets. And I guess what I'm asking is, have you, I guess, formally updated your exploration budget for this year? I mean, your prior guidance was $13 million to $16 million, and obviously you have plenty of targets where you could deploy capital to move them forward. So which areas are you, I guess, really concentrating on the most? And when might we — when do you expect the next resource update to be released?

John Lewins

executive
#28

All right, so from an underground standpoint, the main focus has been Judd inside the mining lease. Then Judd south, starting near surface and partly from underground. After that, Kora — wrapping up a few of the zones up north, a few zones inside the mining lease, and then Kora to the south, both from surface and underground. Sorry — and Judd from surface as well, to make that clear, within the mining lease. Those are the targets where our main effort is on growing the resource, and we're targeting October for the release of a new MMO result estimate. Another area we're drilling at the moment is A1. We have one rig running there, and depending on how things close out with some of the surface drilling at Judd Kora, we'd be looking to move a rig over to Arakompa, Maniape. And Alex, as you may remember, those are two historical resources — Arakompa at roughly 800,000 ounces, Maniape slightly below 580,000 ounces, 560 I believe it actually was. And they haven't seen drilling in 20-odd years, only a couple of kilometers from Kora. In fact they sit closer to the plant than Kora does, and it's certainly something we're quite excited to get started drilling — we consider, say, Arakompa at 1,00,000 ounces and 9 grams a tonne, down at 300 meters, and it hasn't been drilled in over 20-odd years.

John Lewins

executive
#29

That's the type of opportunity that PNG, and especially the Kanto region, presents to us, and I suppose it explains why Kora and Judd, along with the surrounding areas, have always had us enthusiastic about their exploration potential.

Alex Terentiew

analyst
#30

All right, that's great. Yeah, I suppose having that many targets is a nice problem to have, and figuring out where to drill next.

John Lewins

executive
#31

Yes. That means your exploration strategy ends up broader than it would typically be.

Alex Terentiew

analyst
#32

All right, sounds good — thanks a lot.

Operator

operator
#33

Ralph Profiti from Eight Capital has the next question. Go right ahead.

Ralph Profiti

analyst
#34

Appreciate it, operator. Morning, John. I'd like to return to the first item, or rather Kora Deeps, which is set to come into play in Q4. I'm just curious — if we consider Q4 and the early portion of 2024, how does the veining actually work regarding what will be targeted at the outset, and then second, on the mining method and your thinking around the deeper areas, with Volga ultimately transitioning into long hole?

John Lewins

executive
#35

Right now we're in the middle of putting together the detailed mine plan and the budget for 2024. So I can't share much detail with you, simply because that's what we're busy with.

Operator

operator
#36

Apologies — this is the operator speaking. John Lewins, your line has dropped. Kindly hold while we reconnect you.

John Lewins

executive
#37

My apologies—is this coming through? Hi there.

Ralph Profiti

analyst
#38

Yes, John, I can hear you.

John Lewins

executive
#39

Let's return to that. All right, apologies for that. My apologies for that. But the current operating level of 1200 — which is actually moving from 1,130 up to 1,280 — will really be the main area of focus for the balance of this year and next year, and that combines Judd K1 and K2. As we said, we'll be aiming to get into that 900 area primarily with Kora, and it will just be development in the markets stopping until, I would think, Q2 next year at the earliest. And there's also the potential to call out some Judd from that as well relatively early. In fact, we've gone through Judd in some of our developments for our — the first or waste pass it. We are putting in which we develop to the West. So, going out some funds from Judd, kind of 900-ish, is also a potential. When it comes to our mining method, it will continue with the Volca until 2025, when we commission the phase 2.

Ralph Profiti

analyst
#40

Understood. Appreciate it, John. For my follow-up, when you consider the mining zones lined up for the back half of the year and how those tie into ore throughput, do you feel assured that no site-specific geotechnical difficulties are cropping up, that those have been dealt with, and that the development work on the schedule is running ahead of the mining levels — basically, that you're in a spot where you're comfortable and confident?

John Lewins

executive
#41

Honestly, I'd say we feel quite good about our current position regarding access to the mining areas and with respect to geotechnical matters in underground mining. There will always be some geotechnical problem in a localized spot. We believe we have a solid grasp of what we're facing in those areas and the capability to handle any interaction with them, but in any underground mine — and we're not at that point yet with any underground mine — you do encounter localized geotechnical zones and problems. And it's a continuous matter, managing that on an ongoing basis. In our own case, we make heavy use of shotcrete within our support system, along with bolting and meshing that is fairly comprehensive. But those are items we keep examining and assessing, and certainly one of the projects underway, for example, is an evaluation of how we can mine the Guy Solomon and capture additional ounces that are currently in the rest of the PA.

Ralph Profiti

analyst
#42

Great. That’s good to hear. I appreciate the added detail, John. Thanks.

John Lewins

executive
#43

Appreciate it, Ralph.

Operator

operator
#44

Arun Lamba from TD Securities has the next question. You may proceed.

Arun Lamba

analyst
#45

Hey, John. Just a quick one — as usual, I'm asking more of an accounting-type question. Could you remind me how we ought to think about the revenue coming in, specifically when we look at the loss on receivables at fair value? Revenue landed a bit lower according to your reporting. Can you remind us how we should be thinking about that going forward?

Operator

operator
#46

Apologies for cutting in — operator here. John, we’ve got your line open. John, your line is open. Go ahead whenever you’re ready. <<operator_script>>

John Lewins

executive
#47

Arun, we got cut off there. Are you able to hear me now?

Arun Lamba

analyst
#48

Okay, John, you're coming through clearly now.

John Lewins

executive
#49

My apologies for that. Were the questions answered by David?

Arun Lamba

analyst
#50

I didn’t catch that, but I’ll ask you again quickly just in case you didn’t hear it. So obviously there’s an adjustment coming in there. There was also an adjustment coming in from 31st March to June, which I think was also down around 5%. So adjustments came in from both of those. And then from our provisional invoicing to our final invoicing, in terms of moisture content and assays, I think we had a couple of percentage points of adjustment there. That tends to be around about where we get—obviously, gold varies from quarter-to-quarter and copper varies from quarter-to-quarter. No, that’s perfect. Thanks, John. And then just one quick one for me. Just thinking on the bull case of this expansion on the PA, the mill, both mills, we do probably 1.7 million tons per annum. Assuming the mill can do a little bit above design, will you guys have the infrastructure in place, ramp, et cetera? And will the mine be able to support potentially if the mill can do 1.8 million, 1.9 million tons per annum, in kind of a bull case scenario?

John Lewins

executive
#51

That is a fair question. Well, clearly, we noted right from the start that the twin incline was built with the express purpose of accommodating Stage 3, Stage 4, Stage 5, and possibly Stage 6. So yes, absolutely, infrastructure in that sense — ventilation, power, and so forth — all of that supports it. On the matter of tonnage and achieving your tons per vertical meter, and so on, we would definitely be looking ahead, and we believe a meaningful boost to the resource due in October would clearly signal that we could sustain getting 10%, 20% additional tonnage on an annualized basis. And yes, exactly as you point out. Well, at present, we already observe that the plant we have can readily deliver 5% to 10% beyond, perhaps, the nameplate capacity of 500,000 that we hold. And if you examine standard silver plant design, mills are, obviously, your — typically where you debottleneck, and generally with a new plant like ours, you design at the 85% bond index — put differently, you are permitting yourself to achieve your nominal hourly throughput even where your hardness runs substantially higher than the ore body average.

John Lewins

executive
#52

And because of that, the capacity you actually install usually ends up exceeding what isn't capacity — that nameplate figure. It's a method involving metal, or simply a way for them to appear better, and on that front they can use every bit of assistance available.

Arun Lamba

analyst
#53

Perfect. That covers everything from my side. Many thanks, John.

John Lewins

executive
#54

Much appreciated.

Operator

operator
#55

Don DeMarco from National Bank Financial has the next question. Go right ahead.

Don DeMarco

analyst
#56

Thanks, operator, and good morning, John and team. I have a few questions. First, it's great to see such a strong rebound lower in all-in sustaining costs. The higher grades clearly helped, but looking at it now, year-to-date AISC is around 11.80 versus the guidance range — that puts it right at the bottom of the guidance range, and we're heading into what could be a stronger back half of the year. Could you comment on where you see AISC headed over the last couple of quarters? Sustaining CapEx year-to-date is $20 million. Do you expect sustaining CapEx to increase? I think you touched on this a little bit. Maybe you could expand on the outlook for sustaining CapEx and AISC at year-end and over the next couple of quarters?

John Lewins

executive
#57

Broadly speaking, yes — we'd say we anticipate increased sustaining capital during this year's second half, given that extra rig arriving and our aim of achieving greater development meters. That clearly ranks among the factors pushing all-in sustaining costs, though several further factors also feed into it. So yes, we do expect greater spending and a larger all-in sustaining cost figure across the latter six months, and we remain firmly of the view that it will land within the guidance range, in line with guidance.

Don DeMarco

analyst
#58

All right, thank you for that. Turning perhaps to the mine development meters: last year we observed the pace rising quarter over quarter. This year it has eased somewhat. Over the coming few quarters, what number of meters per quarter ought we to expect?

John Lewins

executive
#59

Alright. Well, we did lose some meters toward the close of last quarter and into the start of this one, clearly, because of our safety incident. So we're somewhat below where we'd hoped to land for the quarter. Broadly, we're targeting 2,200 to 2,400 per quarter, and definitely above 2,400 for the final quarter.

Don DeMarco

analyst
#60

All right, thanks for that. It's encouraging to see the deposit free cash flow in Q2. Congratulations on the cash balance moving up. Given that, maybe the RCF remains a somewhat lower priority item, but could you give us an update on the timing of the RCF or any discussions currently underway?

John Lewins

executive
#61

Completion of that is anticipated during the current quarter.

Don DeMarco

analyst
#62

Great, all right. Thanks a lot. And yes, I’m looking forward to catching up next week — best of luck with Q3.

John Lewins

executive
#63

Appreciate that, Don.

Operator

operator
#64

Since nobody has any more questions, that brings the Q&A portion to an end. I'll now hand things back to John Lewins, who may have some closing comments.

John Lewins

executive
#65

Okay, thanks, operator, and thank you all for being with us. I want to apologize for the minor technical difficulties we're having while coming to you from Kainantu. I'd say it's fair to note that, looking at the second-quarter figures, we're quite pleased with how the final numbers came out on production, on costs, and on other measures. As a company, though, we have just been through what I believe was the hardest quarter we have ever experienced, given our safety incidents. That is something we as a company will work extremely hard on so that nothing of this kind ever happens again. Once more, for the whole team, Kainantu has truly been something extraordinary — unfortunately, in the wrong way for a company. Even so, we have refocused on safety and on our operations. We will certainly keep our attention there going forward. So I would like first to acknowledge the loss of our teammates. And second, to recognize the efforts of all our people here at Kainantu, along with the successes this company has delivered over the past few years and across the recent quarters, and their continued dedication to the company.

John Lewins

executive
#66

Thanks for that. I'm also looking forward to meeting some of the folks on this call in person at the site next week. Many thanks.

Operator

operator
#67

That brings us to the end of today's conference call. You can now disconnect your lines. Thanks for joining us, and have a pleasant day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete K92 Mining Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to K92 Mining Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in K92 Mining Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.