Kosmos Energy Ltd. (KOS) Earnings Call Transcript & Summary
November 9, 2020
Earnings Call Speaker Segments
Jamie Buckland
executiveThanks, operator, and I appreciate all of you being with us today; we put out our third quarter earnings release this morning. You can find that release, along with the slide presentation for today's call, on the Investors page of our website. Here with me today to walk through the materials are Andy Inglis, our Chairman and CEO, and Neal Shah, our CFO. Over the course of today's presentation, we'll be making forward-looking statements that relate to our estimates, plans and expectations. Actual results and outcomes might differ materially because of factors we point out in this presentation and in our U.K. and SEC filings. For additional detail, please see our annual report, stock exchange announcement and SEC filings. Those documents can be found on our website. And with that, I'll hand the call over to Andy.
Andy Inglis
executiveThank you, Jamie, and greetings to everyone, whether it's morning or afternoon where you are. I'll kick off today's presentation by going over the quarter's highlights, and after that I'll hand things to Neal, who will walk through the financials. Following that, I'd like to use most of our time on this call to discuss the Tortue project — the substantial strides we've taken on it this year — as well as what we have planned next for this high-quality asset. Neal will then take you through the balance sheet, after which I'll wrap up the presentation, and then we'll move into Q&A. If you turn to Slide 2, you'll see the main points for the quarter. Kosmos turned in strong operational results during the period, producing roughly 57,000 barrels of oil equivalent per day. The result came in a bit under what we had previously told you to expect. The main reason was more storm activity than usual in the Gulf of Mexico. Even so, output from Ghana and Equatorial Guinea held firm, and both of those assets did exactly what we thought they would. Because of that, we believe we can hit full-year production of 61,000 to 62,000 barrels of oil equivalent per day, which lands close to the original guidance we gave when the year began. Over in Mauritania and Senegal, we have been collaborating tightly with BP and the NOC to get the most out of the Tortue project. I will go into more detail on that project later in the presentation. It is a world-class development, and it is moving ahead nicely at a time when a lot of other projects are being pushed back. We're still scheduled to hit first gas during the opening six months of 2023, which lines up with when the LNG market should get tighter. Phase 2's optimization, aimed at growing capacity to 5 million tonnes per annum, makes the project simpler by using Phase 1's existing infrastructure, cutting costs substantially and lifting the project's overall return. Given the possibility of better returns ahead, this isn't the right moment to lower our stake in the project. We've also set up a financing path that covers our capital obligations through first gas. And lastly, we keep making the balance sheet stronger. Back in September, we struck a deal to sell our frontier exploration portfolio to Shell, bringing in roughly $100 million of upfront cash, and those funds should be arriving soon. On top of that, we've established a 5-year Gulf of Mexico facility, giving us extra liquidity while taking the place of our Gulf of Mexico prepayment facility. Thanks to the steps we've taken over this year, we anticipate that at present oil prices, the base business will produce free cash flow moving forward. Now let's look at Slide 3. As I noted on the slide before this one, Kosmos turned in strong operational results during 3Q. Over in Ghana, net production came to approximately 28,000 barrels of oil per day, which matched our guidance. Jubilee is still doing great and running very reliably, generating roughly 88,000 barrels of oil per day in gross production during the quarter. The facility's uptime exceeded 98% in 3Q and has now surpassed 95% for the year so far. TEN's gross production of approximately 50,000 barrels of oil per day matched what we had guided. TEN's facility uptime reached 98% in 3Q, and it has been 99% year to date. Looking at the whole year, we continue to anticipate TEN cargoes being delivered out of Ghana; over in Equatorial Guinea, net production ran at roughly 11,000 barrels of oil per day, matching guidance, and we expect that to remain flat until drilling kicks off next year; we continue to expect 4.5 cargoes delivered from EG. Turning to the Gulf of Mexico, net production for the quarter was about 18,000 barrels of oil equivalent per day, which is roughly 10% below guidance, a reflection of the heightened hurricane activity. 2020 has brought one of the busiest storm seasons on record; consequently, our fields experienced 17 days of downtime in the quarter, well above the 6 days of total downtime we normally budget for a storm season. All that said, base production from our Gulf of Mexico assets looks encouraging. The Tornado-4 injection well started up in late September, and early results have been favorable; we also anticipate spudding the Kodiak completion this month and getting that well online early in 2021. Within our ILX portfolio, we expect to spud the Winterfell exploration well, formerly called Monarch, during this quarter, with results anticipated early next year. Stepping back, this past year has proven tough from an operations standpoint because of the pandemic, the Gulf of Mexico closures in May, and a more active hurricane season than usual. Yet in spite of those hurdles, we expect output for the entire year to come in between 61,000 and 62,000 barrels of oil equivalent per day, which is near the original guidance we issued back at the beginning of the year. That reflects how strong and varied our asset portfolio is, allowing Kosmos to remain durable when prices are low. I'll now hand it over to Neal, who will take you through the financial details for the quarter.
Neal Shah
executiveThank you, Andy. If you'll look at Slide 4, I'll walk through the main financial highlights from this quarter. I won't go through each individual line, since the majority of them align with the yearly guidance we've provided. Instead, I'll concentrate on the important pieces. As Andy noted, output came in at 57,000 barrels of oil equivalent per day, which fell a bit short of guidance because storm activity picked up during the period. If you set aside the effect of that heightened hurricane season, our company would have generated positive cash flow for the quarter. Realizations rose substantially — roughly double in 3Q versus 2Q — driven both by stronger oil prices and by the wide differentials from 2Q returning to normal. Right now, we're selling oil at all 3 hubs at prices that match the benchmarks. Total OpEx keeps moving downward, even if it isn't as low as we'd prefer. On a per barrel basis, 3Q came in above guidance, hit by reduced production and by elevated continuing operating costs tied to COVID, including required 2-week quarantines for staff heading offshore. For the full year, we anticipate total OpEx will be roughly 20% below 2019, which shows the steady improvement we're delivering. Base business CapEx reached $53 million during 3Q, matching what we expected. On top of that, $47 million of accrued CapEx was recorded in Mauritania and Senegal. That figure is noncash, and we anticipate the carry of our capital obligations will stretch to roughly the end of the year, with a modest payment anticipated in the fourth quarter thanks to the progress made on Tortue Phase 1. I'll pass things back to Andy now so he can update you on what's happening in Mauritania and Senegal.
Andy Inglis
executiveAppreciate that, Neal. Moving on to Slide 5. I want to begin by discussing how far the Tortue project has come during this year. Throughout the last 6 months, BP-Kosmos alongside the national oil companies of Senegal and Mauritania have put in serious effort to reshape this project — bringing down the capital cost while lifting the project's overall returns. During this same stretch, the LNG outlook has kept getting better, and it appears the project will achieve first gas at a moment when LNG prices are anticipated to firm up. That's a direct consequence of the numerous project deferrals seen in the U.S; and around the world. In its latest annual energy program, the Wood Mackenzie forum laid out the 2 charts shown on this slide. Starting from the trough in 2020, Wood Mac anticipates a far tighter LNG market across the years ahead, pushed by rising global demand along with the deferral cancellation of higher cost LNG projects. 2020 has recorded the weakest LNG supply growth since 2014, with just 5 million tonnes per annum of new liquefaction brought online this year. Since 2020 demand has remained roughly flat versus 2019, even with COVID's impact, spot LNG prices have already nearly tripled compared with the lows seen in the second quarter; on top of that, no new LNG project has reached FID in 2020. That marks the first time in almost 20 years such a thing has occurred. Consequently, Wood Mac foresees the supply-demand gap beginning to open around 2023, precisely when the Tortue project intends to deliver its first gas, which sets up a favorable backdrop for marketing the volumes tied to Phase 2; with a substantially improved project and a strengthening LNG backdrop plus a financing path now in place, our enthusiasm for this project has never been higher. Now on Slide 6, which illustrates the steady progress achieved on Phase 1 of the project throughout the quarter. As BP noted during its 3Q results call 2 weeks ago, the partnership is putting in very, very hard and very effective work on Tortue Phase I; with activity across all 4 key work streams now ramping up following lockdown periods during 2Q and 3Q. By the close of the year, Phase 1 of the project should be roughly 50% complete. With first gas still on schedule for the first half of 2023. Now to Slide 7, which presents the optimization of the Phase 2 project. This slide, which likewise draws on Wood Mac data, sets the breakeven cost of Tortue Phase 2 delivered into Asia against other LNG projects. Based on our newest cost estimate, which factors in a substantial capital reduction for the project. Tortue Phase 2 lands at the far left of the chart, with a delivered cost into Asia of just over $4 per MMBtu, competing very favorably against other expansion projects in Wood Mac's analysis. Shipping into Europe carries an even lower delivered cost, which further highlights how competitive the project is. The optimization of Phase 2 is aiming at expanding the scale of the overall development to 5 million tonnes per annum. The ideal point is where we can draw on all the key Phase 1 infrastructure. Take Phase 2, for instance — it's going to make use of unused room in the Phase 1 subsea system. We'll grow the FPSO's processing capability rather than bring in another facility. A second gas export line running from the FPSO to the hub terminal isn't needed. So in our view, Phase 2 stands as the most competitive brownfield LNG expansion anywhere in the world, since upstream capital needs are limited and should come in under $1 billion gross through first gas. Our net portion of the Phase 2 development should largely be financeable from Phase 1 cash flows. Now moving to Slide 8. As I noted, we've put a financing path in place for a self-funded project that lets Kosmos keep its present project share, and once fully built out that share can produce an expected return on remaining investment of roughly 7x. Kosmos' net capital through first gas, spanning 2021 to 2023, is projected at about $725 million, shown in the chart at the upper right of Slide 8. We're working with BP on selling the FPSO to an off — off balance sheet special purpose vehicle for the back cost paid so far, roughly $160 million net to Kosmos. BP and Kosmos are negotiating the anticipated purchase of the FPSO, and we expect to close in the first quarter of next year. The SPV will assume the FPSO's future capital obligations, meaning an additional $160 million of Kosmos' future capital obligations gets shifted to the SPV and funded by it. Kosmos also plans to refinance our national oil company loan with commercial banks during 2021, which should result in about $100 million coming back to Kosmos. Together, these 2 activities should cover Kosmos' obligations in 2021. The remaining CapEx balance of approximately $300 million owed in 2022 and 2023 should be funded through direct investment in Mauritania and Senegal. Kosmos is presently in talks to lock in this financing by mid-2021. To date, Kosmos' development CapEx on the project has come from the BP development carry, and we expect forward investment after FPSO financing to total around $400 million net to Kosmos; with Phases 1 and 2 of Tortue expected to generate $150 million to $200 million each year net to Kosmos at a $5.50 gas price, the optimized project should produce a return on investment of approximately 7x, which is why we're excited to move the optimized project forward; with that, I'll hand things back to Neal to walk through the balance sheet and liquidity.
Neal Shah
executiveMoving on to Slide 9. When we wrapped up 3Q, we reported total liquidity at approximately $650 million. After that point, our RBL redetermination was successfully finished, and under it we settled on a borrowing base totaling $1.32 billion, bringing liquidity down to slightly below $500 million. The bank's proposed forward price decks accounted for most of that decrease; during this quarter, we anticipate collecting roughly $100 million in proceeds from the Shell transaction, with the necessary approvals already secured; as a result, we look for the business to produce substantial free cash flow in the fourth quarter. Taking into account the effect of the Shell transaction, as of today we have adjusted our base business CapEx guidance for 2020 to a range of $140 million to $150 million. That figure also captures the sped-up Kodiak completion along with the launch of drilling on the Winterfell ILX prospect during 4Q; for Mauritania and Senegal in 4Q, we anticipate accrued CapEx to match the third quarter's level. In addition, during the third quarter we finalized the Gulf of Mexico facility, which refinanced the earlier prepayment facility. This facility carries a $100 million accordion feature that offers possible extra liquidity should it be needed, making certain we hold a strong financial position as the year comes to a close; with that, I'll turn things back to Andy for the wrap-up.
Andy Inglis
executiveThank you, Neal. Moving on to Slide 10, which is our last one. This year has proven difficult for the industry, and that difficulty isn't over. Still, we should take a moment to consider the way our business is positioned competitively right now. Kosmos holds a top-tier collection of premier conventional oil and gas properties, and our ESG standing is robust. Exploring and developing offshore resources, along with production, around the Atlantic Margins remains our central strategy. Three production hubs anchor our operations — one in Ghana, one in the Gulf of Mexico, and one in Equatorial Guinea — plus we have a globally significant LNG project whose initial phase should reach more than 50% completion by the time this year closes, and that project now enjoys a defined route to financing. Beyond that, optimizing the second phase takes advantage of infrastructure already in place and yields improved returns. These favorable properties feature modest decline rates, are priced against Brent or HLS benchmarks, and carry a carbon intensity overall that sits well below what the industry typically reports. Our latest TCFD report demonstrated that our business decisions and capital allocations aim to produce shareholder value in a manner compatible with a reduced-carbon future. Because these assets cost little to operate and decline slowly, they still threw off considerable free cash flow even when oil prices were weaker. Company-wide, our free cash flow breakeven sits at roughly $35 per barrel of Brent, and we anticipate producing free cash flow moving forward at present oil prices through 2021; regarding gas, the phased build-out of Tortue, with first gas expected during the first half of 2023, should create a self-financed, durable free cash flow stream that supplements the cash-generating oil properties currently in our portfolio. Turning to exploration, we keep upgrading our exploration portfolio, prioritizing returns. The deals we made in Equatorial Guinea and the Gulf of Mexico went after chances to create value by improving the current production base and by pursuing exploration tied to infrastructure. Across Kosmos, we've now assembled a pipeline of ILX prospects that we keep refining. Achieving success in exploration requires quality, which comes from having options. Practically, that means focusing on established basins where our technical knowledge runs deep, where we hold a substantial resource inventory, and where infrastructure can be utilized; last, we maintain a strong balance sheet that lets us carry out our plans. As Neal mentioned earlier, liquidity is plentiful, no debt comes due soon, and the company should produce cash while bringing leverage down. I appreciate your attention. At this point, I'll hand things over to the operator so we can begin taking questions. Operator?
Charles Meade
analystAndy, there's something I'd like to ask you about. I get that you folks probably are still hammering out the specifics around the sale leaseback. Still, I was hoping to dig a bit deeper into which aspects you feel able to discuss and which ones you don't. From my vantage point on the outside, one of the hurdles it appeared you had to work through is that project finance clearly would be a logical fit in your case, yet whether it would be a logical fit for BP, your partner, isn't so obvious. So I'm wondering, ought we to be considering this? Is it the case that BP will similarly put its interest into the SPV? Or instead, might BP serve as sponsor of this SPV, with the leverage coming off BP's balance sheet?
Andy Inglis
executiveNeal, would you like to field that one?
Neal Shah
executiveYeah. Charles, my sense is we're continuing to move through that process, though I believe BP has optionality to pursue this through a few distinct routes. They could take part on both sides of the deal, meaning they'd also gain if the deal performs well. So I'd say there are a few different paths we might land on regarding how BP ends up participating.
Charles Meade
analystOkay, understood. We'll keep an eye out for updates on that. Then I have another question, just trying to clarify what you meant by that slot in the top right corner of Page 8. If you're doing this — it stands to reason you'd arrange this financing for the FPSO, since that's the asset where a ring-fence can be placed around the tolling operation together with production, but should I read it as meaning that the remaining $300 million covers all the other components, such as the subsea, FLNG and breakwater?
Andy Inglis
executiveCharles, I'd suggest framing it this way: we are actively working and engaged with BP regarding the FPSO sale and leaseback. As Neal mentioned, the choice of how they participate is theirs, correct? That said, at this moment we are obviously sitting alongside them in the negotiations with the preferred buyer of the FPSO. As for that final $300 million, we have options regarding the — the methods by which we would actually secure it; some direct investment will be involved; and we are currently evaluating various alternatives for how to accomplish that. And clearly, our aim is to identify the most competitive route to secure that financing.
David Round
analystI have a few questions, and they both relate to Tortue and similar topics. First, regarding Phase 2, could you clarify something? You mentioned a CapEx figure that seemed considerably lower than what some market estimates suggest. So I really want to know: do you view that spending and lockdown situation as a finalized estimate, or should we still expect some fluctuation in that figure? Then, about the direct investments to fund the remainder of Phase 1, it seems you're keeping the possibility open for a smaller farmout that could potentially cover what's left of the CapEx. Do you feel there could be additional interest in acquiring a smaller stake in this project?
Andy Inglis
executiveOkay. Thank you, David. Yes. Let me handle — I'll address the Phase 2 question. Regarding the capital first, yes; so as you walk through those capital estimates, right? When you consider Tortue Phase 1 initially and the capital needed to reach first gas, our projection is a bit above $4 billion. So if you subtract the FPSO, that comes to roughly — it lands at approximately $3 billion to first gas, which aligns with the figures we've discussed. What stands out regarding Phase 2, however, is that it takes advantage of all the pre-investment made in Phase 1, correct? And as I mentioned in my comments, we're capitalizing on the spare capacity within the subsea infrastructure. Instead of installing a new facility to increase gas throughput, you can achieve it using the existing FPSO. There's no requirement for an additional gas export line running from the FPSO to the initial processing; and in fact, we selected an optimal point of 5 million tonnes per annum since it maximizes the utilization of that infrastructure. And I believe that represented the major breakthrough while collaborating with BP — to rethink how to extract the most from the subsequent phase by completely leveraging the infrastructure, and consequently, minimizing CapEx; that explains why the CapEx is so low. The CapEx required to bring in that extra 2.5 million tonnes for the upstream portion is, as I stated in my comments, a bit under $1 billion, and that reflects our present assessment. So I think as I turn to the following question about the current environment, I'd say that from a sales standpoint, yes, the present environment has proven difficult. Few companies possess the balance sheet strength right now to take part; however, incidentally, the present environment has enabled us to truly refine our approach with BP to devise the appropriate subsequent phase. I'm genuinely excited about what we've managed to put together with this project at this stage. As we note on the slide, it's the right project at the right time. And because of the preinvestment, the next phase is extremely efficient. So when you think about where we are, we basically faced a decision: either you sell a piece of the infrastructure for $320 million, or you sell a piece of the project. And clearly, for our shareholders today, the right call is not to sell the project, but rather to sell the infrastructure, yes? Looking ahead, there may be a good opportunity down the road to lock in the proper value, and at that point reducing our stake is something we'd be open to. And as you correctly point out, once the FPSO financing is secured, holding a smaller share of the project becomes appealing. That said, what we're concentrating on right now is making sure the financing path gets delivered on schedule, and we're actively involved in that as we speak. I'm also now aligned with BP. We have the correct project scale — 5 million tonnes per annum — and growing it to that level is the right move. It's extremely efficient as well, since you're drawing on all of the preinvestments. So that gives us a solid project.
David Round
analystAll right, that's quite clear. Let me just pose one very brief follow-up. Am I right in thinking this could significantly shorten the construction schedule for Phase 2 as well?
Andy Inglis
executiveActually, no, it doesn't, since there's still work that needs doing, correct? We'll have a brownfield project to add the extra gas processing capacity. So it won't necessarily contract in terms of timing across the board. That said, it does turn it into a more straightforward project. So I'd say execution risk is reduced. The schedule is likely what you'd normally anticipate, right? So we need to work with BP to finalize all that sequencing and similar matters, but it's a far easier project to carry out. As a result, execution risk is lower.
Neil Mehta
analystLet's start with the U.S. elections — how does that shape the way you're viewing your Gulf of Mexico operation? And when we assess what that business is worth, what's your thinking on the various components, especially where federal leases are concerned?
Andy Inglis
executiveRight. Appreciate it, Neil. Well, political transitions and elections aren't anything novel — not for Kosmos, not for this industry. We've been through that in every nation where we have operations. What I'd say is there seem to be a couple of truths here. First, when your asset quality is strong, you're able to keep competing no matter which government holds power. And second, in my view, it matters that your agenda aligns with the country rather than centering on whichever party happens to be in office. So, applying that to the Gulf of Mexico — the initial point I'd make is that it accounts for roughly 1/3 of what we currently produce, and within our portfolio it carries both the lowest cost and the lowest carbon intensity. That carbon intensity sits at approximately 8 kilograms per barrel — well below global averages, and also well below what alternative U.S. oil production generates. Then the second point: we've obviously made a firm commitment when it comes to the energy transition. By 2030 we aim to reach carbon neutrality across Scope 1 and Scope 2, and mitigation measures will be part of getting there. We also have several genuinely interesting projects along the Gulf Coast. These involve blue carbon, with a focus on restoring wetlands. In fact, they create carbon sinks that hold roughly 10x the carbon found in terrestrial tropical forests. So the takeaway there, I'd argue, is our belief that we can serve as part of the solution rather than stand in the way. And the cost of these projects is low. My sense is that with the portfolio and the approach we now have, we can stay highly competitive, since our assets are low cost and low carbon. Plus we've developed some inventive, inexpensive mitigation measures that let us meet our commitments. So really, nothing about our commitment on that front shifts. Now, from a leasing standpoint, there was plenty of rhetoric previously, and I'm certain there will be plenty more once the election passes. So sure — could there be a risk that no new leasing happens on federal lands or waters? In my view, that issue is still live. What matters for us is that we've assembled a hopper holding over 5 years of future drilling opportunities in the GoM. So nothing urgent to worry about at this stage. My belief is that we have a business that's competitive as it stands today. And in a way, we'll actually become even more competitive down the road, given what these assets are and how we run our operations.
Neil Mehta
analystAnd to be clear, you still possess 5 years of drilling opportunity without any need for additional federal leases, correct?
Andy Inglis
executiveThat's right. Yes; and that means drilling 4 prospects each year, yes? That is kind of more — likely more than we would actually expect.
Neil Mehta
analystAll right, that's helpful. For my second question, I want to ask about the Brent breakeven you mentioned. You referenced $35 a barrel, and that figure excludes growth CapEx. So over, say, the coming 3 years, how should we think about the price level needed to cover free cash flow along with sustaining and growth CapEx, and how does that requirement shift as time goes on? Then, this one may be for Neal. Could you walk us through the sensitivity to each $1 move in the oil price, so we can get a sense of what the free cash flow profile looks like under our oil deck?
Andy Inglis
executiveSure. That's a fair question, Neil. To me, this matters a great deal. Any free cash flow generated above $35 goes first toward reducing debt; Neal will provide the sensitivity figures on that shortly, and that represents the initial claim on capital, correct? The initial claim on cash flow. As for growth opportunities, our attention will be on a small number of ILX projects. The first of these sits within the Winterfell opportunity, and it's roughly under $10 million net to us, right? At most, I could envision needing to observe a fairly strong oil price to justify as much as $50 million in growth projects. Right now we have no shortage of competing projects for that capital. You'll see this genuinely shaping the capital allocation choice. So there's tremendous emphasis on free cash flow and using it to pay down debt. Beyond that, ILX opportunities will be quite limited. I'd say somewhere between $0 and $50 million is the range we'll be considering there.
Neal Shah
executiveRight, and to build on what was just said, Neil — yes. In the near term, at least, roughly $50 million seems like it would be the ceiling for the ILX portfolio. But as you'd expect, since we're exposed to oil prices, we're quite levered. The rough guideline we apply is that for each $5 shift in oil prices, free cash flow is affected by approximately $100 million. There are offsets of some kind, like hedging and so forth, but that's the — in a world of about $45, we can produce meaningful free cash flow from the base business.
Bob Brackett
analystI wanted to get something cleared up regarding Phase 2. If I got it right, Phase 1 ran roughly $4 billion, and around $1 billion of that was the FPSO. You're now saying Phase 2 comes in at a bit under $1 billion. Is that figure net to Kosmos, or does it represent the gross amount for the entire expansion?
Andy Inglis
executiveThat figure is growth. Let me walk you through how the numbers break down, Bob, alright? Yes, it's just a touch above $4 billion, correct. The FPSO portion of that is just a touch above $1 billion, right? Then you've got everything else — the breakwater, which carries a meaningful cost, and obviously you aren't billing that against Phase 2, correct — the breakwater, plus the pipeline running from the FPSO to the breakwater for inshore processing, which again isn't part of Phase 2. Ultimately, then, Phase 2's CapEx spend covers expanding the gas processing, a brownfield project situated on the FPSO. There's only a limited subsea build-out since that already has capacity, and beyond that you're drilling some incremental wells, right? So when you look at it that way, you get substantial capital efficiency from leveraging all the infrastructure that went into Phase 1.
Bob Brackett
analystAnd just so we're clear, that really does make sense. And with this expansion, you go from, let's say, 2.5 million tonnes per annum, and Phase 1 tacks on an additional 2.5 million tonnes, bringing it to 5. So it wasn't the 4 million tonne per annum expansion that people might have been thinking about.
Andy Inglis
executiveExactly, Bob. Yes. No, exactly, Bob. Yes. So here's what you've done, and basically, the effort we've put in over the last 6 months has been to ask, look, how do you arrive at the best project for the expansion, yes? And the clear way to accomplish that is to locate the sweet spot that lets you sort of make use of all that infrastructure you've put in. And once you do all the concept work to optimize it, between what you have in the subsea, what you have in the FPSO when it comes to a deck, you can add gas processing too. What's the constraint on the gas export pipeline, you take all of that and optimize it, this is what you get.
Bob Brackett
analystAnd timing-wise, when it comes to FID for Phase 2, how ought we to be thinking about that?
Andy Inglis
executiveYeah. Yeah. We're — once more, right now we're collaborating with BP on this; however, my expectation would be that FID happens in 2023, right?
Neal Shah
executiveSo around the time of first gas.
Andy Inglis
executiveAround the time of first gas of Phase 1, yes.
Nick Stefanou
analystNick speaking. I have a few questions about Tortue, if that's alright, and after that a follow-up regarding TEN. So for some time now, you've mentioned free cash flow of $150 million to $200 million each year for Tortue Phase 1 and 2. However, my understanding was that this was also based on the project design, which I believe was around 6 million to 7 million tonnes per annum. How is it possible to generate the same cash at 5 million tonnes per annum? That's my first question. The second thing is, could you perhaps discuss how it seems the CapEx for this project, previously $650 million, now appears somewhat higher, roughly $700 million? Could you speak a little about that? And also, whether you foresee any possibility, perhaps something like cost overruns.
Andy Inglis
executiveYes. Thank you, Nick. Yes, I'll address the second question, and then Neal will — can handle the questions regarding cash flows. Yes. Look, our thinking was roughly $650-ish million or thereabouts for Phase 1 — the capital for Phase 1. Obviously, this year has required some extra capital from us. There's simply no other way to put it, right? So you clearly had one more year of executing the project. And although we've optimized the project to lessen the effect of that, there is a cost associated with the delay. So I believe we're clear on that; and obviously, the figures we presented today represent our best estimate of that at this moment. But with the project 50% complete, yes? So execution risk has now decreased. And I think we also have a very credible time line for delivering the projects; so I don't sense that the schedule is under pressure; and as a result, you have the pressure on that capital figure. Neal?
Neal Shah
executiveYeah. So regarding free cash flow, that $150 million to $200 million figure applies to our present working interest; previously—and this may be where things get a bit mixed up—we referred to $150 million coming from a 10% share of the project under the expanded 10 million tonne scheme. The amounts look alike, but you've cut back—what we're describing now is half the project's scope at the working interest we hold today, compared with a bigger project at a smaller working interest, and the figures just happen to land in roughly the same place.
Nick Stefanou
analystAlright. Alright. Just one more quick question. Regarding TEN, output was a touch lower on a sequential basis — only slightly, though — coming in a bit above 50,000 barrels per day. So I wanted to ask: once Ntomme-09 starts up, what explains that drop? My understanding is that it came onstream during August, correct?
Andy Inglis
executiveYeah. Well, the decrease is basically tied to — well, clearly we aren't doing any drilling across the other reservoirs, correct? That means Enyenra, which contributes heavily to TEN's total output. So what you're observing is — we had a rise, and afterward some natural decline kicks in from — from Enyenra. And then — however — plus, honestly, uptime has been solid, the fields definitely keep producing well; so sure, Ntomme-09 clearly compensated for part of it, yet declines will persist given that we've run no activity during this year. We will, of course, return early next year, though nothing happened this year.
James Hosie
analystI've got a few things to ask about how Tortue will be funded. To start with, that $100 million you're seeking from the NOC — does the refinancing also shift the risk tied to those funds, or does Kosmos keep carrying it? Then, regarding the $300 million shortfall, could one path be refinancing our RBL so Tortue gets folded in — or are you looking at other ways to raise that money?
Andy Inglis
executiveYes. Neal, why don't you take those 2?
Neal Shah
executiveYeah. So regarding the NOC financing, we've had discussions with the banks about several structures concerning where that risk ultimately lands. We haven't finalized it yet — whether a backstop is needed at the end of the day, we'll settle that through the negotiations with the banks. But one thing is clear: there's appetite from the banks to support government projects in developing Africa. So there's good appetite for pursuing that. Then on the MS, the $300 million, we've kept it open for a number of reasons, since we have a couple of different options. We do have the ability to put it within the RBL today. I do think other options may be more attractive as we go down that route, and we've had discussions with a number of other interested parties. So that is an option, but it's one of the few that we're looking at.
Richard Tullis
analystFollowing up on that same topic, regarding the roughly $300 million that remains to be invested across 2021 through '23 on Tortue Phase 1, about what realized crude price would let Kosmos cover that development just from its cash flows? And is that possibility still being considered, even at, let's say, a $45 oil price?
Neal Shah
executiveYeah. So Richard, at $45, I'd say we would be able to fund it internally through cash flow; but having said that, I believe our position has been quite clear. And as Andy noted earlier, when it comes to free cash flow, our top priority is paying down the debt. And we've stated for some time that we will — our plan and expectation is to deliver a project that funds itself. The FPSO sale leaseback represents step 1 of that. And as I mentioned, there are multiple discussions underway to lock in the remaining portion. And so although funding it from free cash flow is definitely possible even in a $45 environment, right now that isn't what we intend to do.
Richard Tullis
analystAll right, that makes sense. Now, turning back to the refinancing — the one that's been planned involving loans from the national oil company — could you walk us through how that would work? Is the overall balance expected to rise by about $100 million? And what new terms should we anticipate?
Neal Shah
executiveRight. At present, we hold a loan alongside the governments in Mauritania, and BP holds one too, each covering its portion of the capital cost. What we're aiming for with this financing is to shift that interest and the associated liability over to the banks, essentially removing Kosmos from the center of it. That gives us rates that are appealing and competitive, I'd say. So we do — but the point isn't for us to earn a profit or generate any P&L from it; it's simply a straightforward transfer of the economic interest, covering both the interest component and the risk component.
Operator
operatorAt this point, we don't have any more questions. I'd like to wrap up the call now. Thank you to all of you who tuned in today. Feel free to hang up your lines now, and we appreciate your being with us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Kosmos Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Kosmos Energy Ltd. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Kosmos Energy Ltd. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.