Kosmos Energy Ltd. (KOS) Earnings Call Transcript & Summary
May 9, 2023
Earnings Call Speaker Segments
Jamie Buckland
executiveThanks, operator, and I appreciate all of you being with us today. We put out our first-quarter earnings release this morning. You can find that release, along with the slide deck for today's call, on the Investors page of our website. Here with me to walk through the materials are Andy Inglis, our Chairman and CEO, and Neal Shah, our CFO. Over the course of today's presentation, we'll be making forward-looking statements about our estimates, plans and expectations. Actual results and outcomes may differ materially because of factors we describe in this presentation and in our U.K. and SEC filings. For more detail, please see our annual report, stock exchange announcement and SEC filings. All of those documents can be found on our website. With that, I'll hand the call over to Andy.
Andy Inglis
executiveThank you, Jamie, and good morning or afternoon to all of you. We appreciate you being with us today for the call on our first-quarter results. Before I pass things to Neal, who will walk you through the financials, I'll cover the progress achieved during the quarter; after that we'll take your questions. Beginning on Slide 3; a little more than 2 months have passed since the call on our fourth-quarter earnings, which moves us nearer to the expected midyear free cash flow inflection point that we discussed with our year-end results. Over that period, we moved our strategic plan forward consistently, and the first quarter marked another three months of dependable execution. In terms of output, we produced about 59,000 barrels of oil equivalent per day net on average across the quarter, which matched our guidance. As fresh wells begin producing, mainly at Jubilee, we anticipate that production will climb during the third and fourth quarters. Our development project — which we expect will boost the company's overall production by roughly 50% between now and 2024 — kept advancing well. At Jubilee Southeast, our goal is to achieve first oil next month. For Tortue Phase 1, we are aiming for first gas at the close of the fourth quarter. Regarding Winterfell, our goal is to achieve first oil by the close of Q1 in the coming year. Even as we concentrate on bringing these short-term development efforts to completion, we are simultaneously advancing the expansion opportunities that lie further ahead. In the Gulf of Mexico, we intend to spud the Tiberius infrastructure at exploration or ILX well during the upcoming quarter. Together with our allies in Mauritania and Senegal, we are making headway on Tortue's second phase. The LNG concept has been chosen, and the initiative is now entering pre-FEED. Additionally, in other areas of Mauritania and Senegal, we keep refining the development plan for the BirAllah and Yakaar-Teranga finds as we push forward our next gas project. Now, let's move to Slide 4. On this slide, we're reviewing how things went at our three production hubs over the quarter, along with what's coming up next. Net production came in at roughly 59,000 barrels of oil equivalent per day, which matched what we told you to expect for 1Q, and our full-year number stays the same — 65,000 to 69,000 barrels of oil equivalent per day net. Turning to Ghana: Jubilee's gross oil output averaged about 72,000 barrels per day, a decline versus the fourth quarter that came mostly from lower water injection, which we did mainly to keep reservoir pressure in check while drilling at Jubilee Southeast. Since we brought water injection back to normal levels in February, production has held steady. We expect five wells altogether—four that produce and one for injection—to come online between the close of Q2 and the close of Q3. Over the months ahead, those wells ought to deliver a significant boost to Jubilee output. I'll get into that further on the following slide. At TEN, oil production on a gross basis came in at an average of slightly more than 20,000 barrels each day. In Q2, the operator handed the Ministry of Energy a draft development plan covering a set of extra, high-graded wells at TEN. This plan features one combined associated gas sales agreement that takes in every upcoming gas sale across both Jubilee and TEN; the goal of this set of activities is to keep TEN oil output near where it stands today while also lifting gas exports. Getting more domestic gas is something the government regards as a priority, and we're eager to push forward this proposed oil and gas development at TEN. Turning to Equatorial Guinea, gross oil output came in at an average of slightly above 27,000 barrels per day for the quarter, matching what we expected. The 3-well infill drilling campaign should kick off in the fourth quarter, with the first well coming online near the end of the year. The Akeng Deep ILX should wrap up around the end of Q1 next year, once the infill drilling program is finished. Moving to the Gulf of Mexico, our net production was about 16,000 barrels of oil equivalent per day, which lines up with what we guided. At Kodiak, we've locked in the vessel for the Kodiak 3-well workover, and that work is set to begin in Q4. The Odd Job subsea pump project continues to move forward nicely and remains on schedule to come online in mid-2024. As I mentioned on the slide earlier, we're still on track to spud the Tiberius ILX well in the next quarter — a high-graded prospect sitting in the outer Wilcox trend — and over at Winterfell, we've already ordered more long-lead items. We expect the export and host platform agreements to be executed around midyear. Drilling should begin in 3Q as planned, with first oil targeted for the end of the first quarter of next year. In addition, at the most recent Gulf of Mexico lease sale, Kosmos, bidding jointly with a Winterfell operator, emerged as the apparent high bidder on a block adjacent to Winterfell, which might expand the resource from this hub past the 2 phases presently planned. Now to Slide 5, which gives more detail on Jubilee, the field expected to fuel our near-term production growth this year; our full-year results in late February covered the substantial upside potential at Jubilee across the years ahead. This field is sizable and continues to expand. The resource in place is thought to be over 2 billion barrels, and recoverable volumes are estimated at more than 1 billion barrels equivalent. Since production began in late 2010, under 40% of those recoverable barrels have been extracted, leaving room to stretch out the plateau of this high-margin output. Over the course of the year, we expect output to rise both from the main field and through the new Jubilee Southeast infrastructure as additional wells are brought on; inside the main field, the partnership plans to bring on 2 producer wells and 1 water injection well during this year, and the first producer should come online before long. The remaining producer and the injector ought to be online in the third quarter. At Jubilee Southeast, first production should begin in June. Two producer wells plus one injector have been drilled, and those producers should come online late in 2Q and early in 3Q, respectively, while the water injector is set to start up in early 2024. Expected effects of these new wells entering service appear in the chart at right: gross production should climb by more than 50% between the first quarter and the fourth quarter, reaching over 110,000 barrels of oil per day. The partnership has pinpointed over 30 chances to drill and develop, and it aims to hold gross output at more than 100,000 barrels of oil each day until the decade wraps up. Following the OXY deal that closed near the end of 2021, Kosmos increased its stake in Jubilee from 24% to about 39%. Within just 14 months, that money has been recouped. Looking ahead, the real benefits from this transaction still lie in front of us, as we chase greater production and try to keep the flatter. On the right-hand chart, we've additionally flagged the likely timing for Jubilee cargo liftings, which Neal will cover in a moment. Because of the ramp-up during the third quarter, Jubilee's cargo lifting schedule tilts heavily toward the second half of the year, with just 2 Jubilee cargoes anticipated in the second quarter. To sum up, this is an exciting period for our core assets at Jubilee.
Andy Inglis
executiveOutput from those newly drilled wells marks the opening move toward the production and cash flow upturn we've been expecting. On Slide 6, you'll see the initial stage of Tortue, where all 4 main work streams moved ahead nicely this quarter. Starting with the subsea side: drilling, completion, and flowback on the wells are done, so they're ready to produce. The Amazon is currently installing the deepwater pipeline, after which come the infield flow lines and placement of subsea structures. Getting the subsea scope done on schedule is the critical path now for the first half, finishing before year-end. On the FPSO, pre-commissioning activities moved forward ahead of its planned start in Singapore. Arrival at the field location is anticipated near the close of the second quarter. The hub terminal build is finished, with transfer to operations slated for the end of this quarter. Last, work on constructing and mechanically completing the floating LNG unit is wrapping up, and commissioning is currently in progress. Departure from the shipyard should happen around midyear. Right now the operator's attention is on bringing these work streams together and steering the critical path via subsea so that first gas lands by year-end. Now Slide 7, covering the gas and LNG upside we see coming through the portfolio. Even though the team's full attention is on delivering Tortue Phase 1 during this year, we've moved the following gas development phase forward too. Within the Mauritania and Senegal basin, our partnership identified and de-risked roughly 8 Tcf in place of low-cost gas resources throughout our acreage. That works out to about 15 Tcf of recoverable gas net to Kosmos, or beyond 2 billion barrels of oil equivalent — more than 4x the 2P reserves we hold today. Deals struck recently in the sector underscore how valuable strategic, world-scale gas assets are. Our deep resource position spanning Tortue, BirAllah, and Yakaar-Teranga genuinely sets the company apart. It's a portfolio we consider unmatched among independent E&P firms. As you might have noticed in the late April press release, we just reinforced the company's Board of Directors. The new directors carry international operations and LNG expertise that will benefit the company as we pursue our strategic goals and capture maximum value from our gas resources. Turning to the specific future growth opportunities on this slide: for Tortue Phase 2, we announced the gravity-based structure development concept not long ago, an important milestone toward moving the project into pre-FEED. On BirAllah, after the new PSC was agreed with Mauritania's government late last year, we're collaborating with partners on optimizing the project and advancing the concept. And for Yakaar-Teranga, we're pushing the domestic gas plan forward alongside our partners and Senegal's government, with LNG export potential to follow. To wrap up, we keep pushing forward our distinctive set of opportunities in Mauritania and Senegal, moving ahead on several possibilities that let us selectively deliver upcoming gas and LNG expansion throughout the basin; that wraps up the portfolio review. At this point I'll pass things to Neal, who will discuss the quarter's financial highlights.
Neal Shah
executiveAppreciate that, Andy, and greetings to all of you this morning and afternoon. If we move to Slide 8. Our performance during the initial three months of the year matched what we had anticipated, with output level compared to Q4 of last year and expenses aligning with our guidance. Pricing we actually received declined from one quarter to the next because commodity prices were weaker throughout 1Q. Lower OpEx from quarter to quarter made up for that. The drop in first quarter OpEx stemmed mainly from a shift in the sales mix within Ghana, since no 10 listing occurred this quarter like it had during the fourth quarter. CapEx matched our guidance, with roughly 50% tied to Mauritania and Senegal. As we mentioned when reporting fourth quarter results, CapEx will likely lean more heavily toward the first half of the year while we advance Tortue Phase 1 and finish up the Jubilee Southeast development, and consequently ought to begin declining during the back half of the year. Free cash flow, marginally negative during the first quarter, ought to begin climbing in the latter half of the year as we hit that turning point of greater output and reduced CapEx. As Andy mentioned previously regarding the Jubilee slide, we anticipate just 2 cargoes from Ghana during the second quarter, resulting in an underlift position and an anticipated cash outflow in 2Q; so with that, I'll pass things back to Andy.
Andy Inglis
executiveAppreciate that, Neal. Now if you’ll look at Slide 9, we’ll wrap up what we’ve covered today. There’s a lot going on for Kosmos in 2023, with several catalysts, and we’ve already hit important milestones during the first quarter. The next significant one involves output growth at Jubilee as the new producer begins operating in the main field, and after that, Jubilee Southeast should start up next month. Then we anticipate selling the FLNG vessel away from the Singapore shipyard and the FPSO arriving at the location, both near the midpoint of the year. Drilling at Tiberius and Winterfell is slated to begin in the third quarter. About that same period, hook-up work on Tortue is expected to get underway, aiming for first gas by the close of the year and first LNG during early 2024. Thanks. At this point, I’ll hand things to the operator so we can begin taking questions.
Nicolette Slusser
analystNicolette Slusser here, filling in for Neil Mehta. Our opening question concerns what free cash flow will look like across the year. I realize it leans somewhat toward the back half. Still, as I understand it, during the prior quarter's call you said that with oil where it currently sits, the anticipated band for the year would land somewhere between $100 million and $200 million. Ought we to expect any revision to that band, and do you have a sense of where we might end up under the present strip?
Andy Inglis
executiveLet me hand things over to Neal.
Neal Shah
executiveRight. If we set the guidance for Q4, we land in the low to mid $80 range, compared with the mid-70s at present. So at today’s oil prices, 100 to 200 million is nearer to flat. That lines up with the usual fluctuation we’ve observed in oil price, where $5 equals about $100 million in free cash flow. So I believe that relationship still stands.
Nicolette Slusser
analystThat's really useful. Now, my second question relates to 2 Phase I. I wanted to ask whether you might share any new information or status regarding the arbitration and how that contract is structured.
Andy Inglis
executiveSure, I can address that. There isn't anything new to report. During our discussion at 4Q, we reached an agreement to proceed with arbitration so that both BP and ourselves would share the same reading of the contract. That process is now underway, and we expected everything to wrap up before the window opens to sell the cargoes, which comes following the commissioning phase once Tortue Phase 1 has started up. So it's all proceeding as planned and simply being dealt with in the ordinary course of business.
Alex Smith
analystI wanted to ask something quickly regarding Ghana, especially Jubilee. It seems your guidance has shifted a bit, now pointing to $110 million gross production, coming from both you and your operator. What is behind this? Did the wells get drilled faster than anticipated? Or is it simply that you have greater confidence in the base Jubilee, with the Southeast being an additional layer? I would just like to get your perspective on this, please?
Andy Inglis
executiveYes. No, thank you, Alex. In truth, I don't see much of a gap there. Reaching $110 million by the fourth quarter, I believe, aligns with what the operator has guided. So all in all, we are on schedule to deliver what we committed to. We obviously understand the wells much better at this point, along with how each one performs, since we have drilled and completed them. So now we are going through startup. The initial well in the main field will come online before long, and once the Jubilee Southeast infrastructure is finished, we have 1 well beginning at the close of the second quarter, a third during the third quarter, and after that a producing injector in the main field. So the path toward that 110,000 is well defined, the work program is proceeding as planned, and the well rates we are aiming for match up well and are marginally above what we estimated before drilling.
Matt Smith
analystI’ve got a few, so maybe I’ll take them one by one. The first one is about Jubilee. I noticed the lower water pressure you experienced during January and February. I was just wondering whether you can give us a March figure or something more recent for production, just so we can understand how we’re going into 2Q, or whatever happens before those new wells start up.
Andy Inglis
executiveYeah. No. Thanks, Matt. Yeah, I think we obviously saw the decline from 4Q to the 1Q rate, and that was really tied to under-injection while we finished drilling at Jubilee Southeast. We’re now catching up, so we’re level with the rate we hit in the quarter. Production is basically unchanged at about 70,000 barrels a day. After that, we begin the ramp-up as the new wells come online. And I think, looking at that, as I mentioned in response to Alex’s earlier question, we have a defined set of activities to finish on the infrastructure build-out, and those are proceeding as planned. On the wells, we’ve seen strong results from them, in both the main field and Jubilee Southeast, so we’re now beginning that gradual increase. And then, as we said in my remarks, this is a large field that keeps getting larger. We now have a genuine goal of holding the plateau above 100,000 barrels a day. We see a lot of opportunity in the infill program we have; so I think at this point it’s really about reaching that plateau and then sustaining it through a program driven by quality. And obviously, we’ve been highly efficient with drilling in this stage of the main field and Jubilee Southeast.
Matt Smith
analystGreat, thanks for that detail. My follow-up is about Tortue, and I noticed what was said regarding Phase 1, specifically that subsea equipment sits on the critical path. What I'd like to know is whether this is something that has started to worry you more over the past quarter, or whether it's simply the way the critical path has naturally evolved, given that the FPSO was likely the key item before and may no longer be sitting at the front. I'm essentially trying to gauge whether you believe the risk profile has shifted at all.
Andy Inglis
executiveYes, thanks Matt, that's a fair question. With a project of this scale, where you're bringing together the main work streams, the attention naturally lands on whatever item has moved onto the critical path. I'd say the operator has managed things well in making sure the terminal was completed on schedule. Beyond that, the large in-country scope of work is obviously significant. There are clearly risks tied to that, especially through the COVID period, though we're happy with how things are progressing at this point. As I mentioned earlier, handover to operations happens at the close of the quarter, and that represents a major milestone that takes risk out of that portion of the activity set. The FPSO, as you noted, was obviously a concern. I believe the construction work is now finished, the vessels have left the shipyard, and it's currently en route to the field, with arrival expected around the middle of the year. A great deal of effort has gone into the time it spent in Singapore to build a solid grasp of the work scope involved in the critical pre-commissioning activities needed for first gas to happen. I'd say our understanding of that has improved considerably over the period it was in Singapore, and that once again pushes it further down the list of critical path items. So the pressure has clearly shifted to the subsea scope. On that front, the shallow water portion has already been carried out. What remains is really the deepwater segment of the subsea installation — the Amazon vest, which handles the deepwater pipeline, followed by installing the subsea structures and the infill flow line. So it's really a gradual migration of the activity set toward the part of the project that now determines whether we reach first gas.
Charles Meade
analystAndy, thanks for what you said in response to the earlier question. I found it quite useful — you provided a great deal of added granularity there. To start, I'd like to ask about the Jubilee Southeast development, and simply to follow up on what you folks told us during the prior quarter regarding certain extra pay zones that your drilling had come across. What I'd like to know is what effort you've put in, and in what way do those extra zones play into the development and the plateau you're describing, whether over the near term or further out?
Andy Inglis
executiveYeah. No, that's a solid question, Charles. What it really comes down to, I'd say, is a handful of factors. At Jubilee, there's a set of opportunities we've mapped out using 4D across the main field. We've completed one cycle of that — the first second cycle — and there's an additional cycle scheduled for next year. So with the main field, you're creating that wellbore to capture opportunity. The situation with Jubilee Southeast, however, is that this is virgin reservoir, so it arrives at a reduced GOR in essence. Because of that, the added output from those wells matters a great deal, since we're genuinely gas-constrained at the facility. So the capacity to selectively bring the Jubilee Southeast wells on sooner, possibly in front of certain main field wells, is what helps hold the plateau and in fact prolong it. So that chance, I'd argue, is why Jubilee Southeast has increased in relative size compared with the opportunity set in the main field. Yet once more, returning to what I said earlier: on the whole, there's consequently plenty of opportunity, so to speak, within the main field, from unswept regions picked up by 4D, plus in the undeveloped portion of Jubilee Southeast where further Patons are being added, and that's what gives us assurance regarding the eventual duration of the plateau. So it's a fascinating moment in Jubilee's development. Right now we're in a ramp-up stage. After that, I believe the genuine opportunity stems from our ability to high-grade that set of activities and thereby prolong the plateau. So in the end, what I'd say is that it concerns how long the plateau lasts, and that's due to the unswept regions you see in the main field, along with — as you correctly note — extra horizons in Jubilee Southeast. And once more, those tend to arrive with a somewhat greater initial production rate owing to the reduced GOR.
Charles Meade
analystYeah, that's a perfect illustration of how large fields tend to expand. Then, regarding the EG infill program, might you align what we should anticipate in terms of the flow rates from those wells, whether any exploration risk exists, the schedule, and how all of that could translate into what it means for EG cargoes, maybe during '24?
Andy Inglis
executiveYeah. Once more, that's a solid question. Once more, you pull back from the specifics. What drew us to the chance in Equatorial Guinea was the capacity to — the infrastructure already there at Ceiba and Okume, not completely utilized, the capacity, as a result, to introduce fresh production sources where — there's essentially been no drilling work throughout the past 10 years. As a result, a chance existed for infill drilling, and that's what we're aiming at. We possess refreshed seismic. So I believe you ought to view these as genuine development wells. And I believe if you consider that, Charles, across the medium term, say, it maintains output, slight expansion, yet I believe it maintains output. I believe the major surge arrives with the <<inaudible>> well, where we're drilling a substantial prospect that can be tied back into the infrastructure. That's the point where you'd witness an increase in output. So the well gets drilled roughly at the close of Q1 next year, and then tieback possibilities likely within that 18-month window, yes. So I believe we foresee upcoming expansion in Equatorial Guinea from that ILX program, though it's likely 25 and beyond.
Ashley Kelty
analystLet me ask something brief regarding Tortue. In the past, you mentioned wanting to forward sell a portion of your LNG. Could you tell us where things stand on whether that's been accomplished? And if it has, what sort of pricing were you considering?
Andy Inglis
executiveActually, no — perhaps we didn't communicate this well, but my understanding is that forward selling from Phase 1 was never truly our plan. There's a sales contract in place, which we've talked about with BP. Right now we're working through the question of how cargoes would be handled beyond that agreement; that gives us a chance tied to those diversions. Still, that represents the main upside here, and so far — currently we're in discussions with a number of parties, but no contractual terms have been established yet for it.
Mark Wilson
analystI want to go back to Andy regarding his response about the subsea critical path. The reason is that the FPSO should show up near the middle of the year, and the FLNG vessel is departing Singapore near the middle of the year too. Is the reason it's the critical path that those vessels will reach the location prior to completion of the deepwater pipeline? Is that how you see it?
Andy Inglis
executiveWhat I'm telling you, Mike, is that you're bringing every work scope together. Obviously, something can be delayed, something can move ahead; however, based on how we view it right now, the main work scope that determines completion isn't tied to the FPSO; it isn't tied to the hub terminal; and at present, we don't think it runs through the FLNG vessel. Therefore, getting the offshore work done on time — the subsea work within the deepwater section — is what constitutes the critical path all the way to first gas.
Mark Wilson
analystOkay; but that's proceeding as per plan.
Andy Inglis
executiveSorry?
Mark Wilson
analystStill, that subsea route is moving along according to schedule.
Andy Inglis
executiveRight. Obviously, when we consider how that began, the Amazon vessel kicked off somewhat behind what we had expected. It reached the site somewhat behind schedule. Yet at this point that scope of work is underway; and like I mentioned, the goal is to make sure everything is finished and allows for the first gas day.
Mark Wilson
analystGreat. Okay, and then second, regarding Jubilee and keeping that 100,000-plus plateau going toward the end of the decade — you brought up the 10 gas volumes being part of the gas sales agreement. Could you discuss how gas volumes interact with the oil production battle that's expected to be sustained?
Andy Inglis
executiveYes. On Jubilee specifically, we're at a point today where we're exporting roughly 100,000 million standard cubic feet from Jubilee. That's a credible export level, where we're achieving the right balance between the gas export voidage replacement with gas and with water. So ultimately, I don't think that gas — the oral rate is being affected by the gas export rate on Jubilee.
Neal Shah
executiveMark, one more point from my side: absolutely, the gas tied to 10 would come on top of what we already sell out of Jubilee. Jubilee operates independently, so the 10 GSA plus the arrangement we're aiming to finalize with the government would represent extra gas, and it wouldn't have any effect on Jubilee output.
Mark Wilson
analystUnderstood. And Neal, just one final item on your end. You said, I believe, that you're expecting a modest cash outflow during Q2. Could you update us on the current status of those exploration bonus payments coming from Shell?
Neal Shah
executiveSure. At this point, we aren't anticipating any payments from Shell. That $50 million came in as a lump sum during the fourth quarter of last year. Should they propose another development plan, whether tied to one of the discoveries we made, then an additional payment might potentially materialize. However, right now, none of that is being planned for or factored into the forecast.
Operator
operatorAnd with no more questions coming in right now, I'd like to wrap up this call. Thank you to all of you who tuned in today. At this point you're welcome to hang up, and we appreciate your taking part.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Kosmos Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Kosmos Energy Ltd. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Kosmos Energy Ltd. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.