Kosmos Energy Ltd. (KOS) Earnings Call Transcript & Summary

November 6, 2023

New York Stock Exchange US Energy Oil, Gas and Consumable Fuels earnings 54 min

Earnings Call Speaker Segments

Jamie Buckland

executive
#1

Thanks, operator, and I appreciate all of you being with us today. We put out our results for the third quarter this morning; you can find that release along with the slide deck accompanying today's call on the investors page of our website. Here with me to walk through the material are Andy Inglis, our Chairman and CEO, and Neal Shah, our CFO. Throughout today's presentation, we'll be making forward-looking statements relating to our estimates, plans, and expectations. Actual results and outcomes may differ materially, because of factors we point out in this presentation and in our UK and SEC filings. For more details, please refer to our annual report, stock exchange announcement, and SEC filings. Those documents can be found on our website. With that, I'll hand the call over to Andy.

Andrew Inglis

executive
#2

Appreciate that, Jamie, and a good morning or afternoon to all of you. Thanks for being with us for our third quarter results call. Since we last spoke, we've kept making solid headway against our strategic objectives, with a number of significant recent developments. I'll cover those in greater depth in today's material, along with an update on the quarter. After that, I'll pass things to Neal, who will walk you through the financials, and then we'll wrap up the presentation and open the line for Q&A. Moving to slide three, Kosmos operates under a straightforward, steady approach: we provide the energy needed in the present, simultaneously striving to cut the carbon intensity of what we hold and to supply cleaner energy that will be required in the future. Achieving that means executing a set of distinctive initiatives focused on advantaged, low-cost, lower-carbon oil along with advantaged, low-cost, lower-carbon gas. The progress we've achieved is shown on this slide. Starting with output growth, we established an objective of expanding production during the latter six months of 2022 by roughly 50% compared with the same period in 2024, driven by three primary development ventures: Jubilee Southeast, Tortue Phase 1, and Winterfell. During Q3, we achieved a major step by starting up Jubilee Southeast, the first of our development projects to come onstream. That lifted Jubilee's gross output to roughly 100,000 barrels of oil per day — an increase of nearly 50% compared with what we saw in the opening six months of the year. I'll cover more on Jubilee in the upcoming slides, though overall we're happy with the progress. Further gains are anticipated in the coming months. Turning to the second point, both of our other developments are continuing to advance. Regarding Winterfell, the partners just finished drilling the initial production well, marking a key project milestone. As for Tortue, the hub terminal has been finished and transferred to operations, plus we've signed a new contract for the subsea work scope, which had been sitting on the critical path before. Third, over the past few weeks, we've expanded the set of attractive, high-quality opportunities we hold in oil and gas. Back in October, we shared news of a discovery at the Tiberius well, located in the Gulf of Mexico, and as of today, we've announced that we took over as operator and raised our working interest in the Yakaar Teranga Fields in Senegal — projects of global scale — pending the usual government sign-offs. Both of these ventures have us enthusiastic, since we anticipate they will drive the next phase of value growth for KOSMOS after 2024. We'll go into more detail on each of them later in this presentation. The chart appearing on the right side of the slide is one we've presented previously, now refreshed to reflect these developments. This demonstrates how we're advancing toward the strategic goals we've set for the longer term. During the third quarter, we achieved our first notable increase in output, as production climbed 17% compared with the second quarter, and there's room for additional gains from Jubilee, followed by the scheduled launch of Tortue Phase 1 and Winterfell during 2024. Once those developments begin operating, we expect this growth to drive a considerable improvement in pre-cash flow, which ought to enable the Company to reduce debt even more and, ultimately, fund returns to shareholders at the moment leverage falls beneath the target threshold we've established. Looking ahead, we have a large, high-quality set of growth projects, some operated by us and some not, covering quick-turnaround oil as well as longer-term gas. Those assets will continue to distinguish KOSMOS from rivals in future years. We plan to strike a balance between the pace at which we advance and the ownership stakes we acquire in these forthcoming developments, allowing us to steer our expansion and generate solid pre-cash flow. Turning to slide 4, which takes a closer look at what we achieved operationally this quarter. Our net output came in at approximately 68,000 barrels of oil equivalent each day, in line with guidance, and was up roughly 17% versus the previous quarter, thanks to the Jubilee South East coming online. On a gross basis, Jubilee averaged approximately 96,000 barrels of oil per day across the quarter, up more than 30% from the quarter before, as three producer wells were brought online spanning Jubilee South East and the main field. Although our production wells performed well, delays occurred in delivering the required water injection, and that has created a knock-on effect on production in the near term, which I will address in greater detail; at TEN, quarterly output of about 15,000 barrels of oil per day came in as expected and was below the prior quarter because of a planned two-week shutdown. During FPSO maintenance work, we altered the gas train, and the redirected gas is now being re-injected at the Entome field to help sustain reservoir pressure and hold production steady. That has delivered roughly a 75% cut in flaring, a significant advance toward our aim of ending routine flaring by 2026. The revised TEN plan of development, together with the combined TEN and Jubilee gas sales agreement, has been handed to the Ministry of Energy for approval. Meanwhile, we have prolonged the Jubilee gas sales agreement until the end of November at $2.90 per MMBtu. Moving to all Guinea, gross production came to an average of about 25,400 barrels per day in the quarter, as expected. We're set to kick off the infill drain campaign this quarter, and the rig is already in the country. Ahead of those three infill wells we've got planned, that rig is going to handle a pair of work-overs at Sabre field, and that should give our year-end production rate a boost before the new wells begin coming on stream around the end of Q1. Management expects the work-over plus infill program to add about 10,000 barrels of oil per day to gross production. Once the infill campaign wraps up, the Akeng Deep infrastructure-led exploration well is still tracking toward a spud in early Q2 2024. On the Gulf of Mexico side, we averaged roughly 15,700 barrels of oil equivalent each day on a net basis, which came in above our guidance because storms were less frequent than we had expected. When it comes to all of our operations, the subsea pump project continues to progress nicely and is slated to start up sometime in 2024. At Kodiak, volumes are tracking right in line with our forecast, and a work-over planned for the midpoint of 2024 will provide support; as for Winterfell, things are moving along well with our partner. The rig arrives in the third quarter, and the first of three wells has now been completed successfully — an important milestone for that development. First oil is still expected by the end of the first quarter of 2024, keeping us on schedule. After the quarter ended, we disclosed the Tiberius well discovery in Keighley Canyon, and I'll cover that in greater depth later on in this presentation. Moving to slide five, bringing the Jubilee Southeast development into service has produced a significant increase in output at Jubilee. During the quarter, three producers came into operation, lifting gross output to roughly 100,000 barrels of oil per day — a mark we hadn't reached in quite a few years. As I said before, water injection rates during 3Q came in below what we had planned. Part of that is due to the water injection pumps running less often, and part is because two water injection wells took longer than expected to start up — they originally were supposed to kick off in 3Q. After the quarter ended, we did get both of those water injection wells up and running, and now we're ramping up water injections to maintain these larger production volumes.

Andrew Inglis

executive
#3

Before now, our arrangement assumed we'd contract out the Ghana drilling rig sometime in Q4. The idea was that this would allow us enough time to assess the initial three Jubilee wells and improve the selection of the wells that followed. However, given our strong performance in picking wells and executing the drilling, we've decided to move an extra producer and water injector forward into the fourth quarter, pulling them out of 2024. This should help sustain Jubilee output growth as we move through 2024, and we expect both wells to begin producing early next year. By accelerating this work, Kosmos's 2023 CapEx net figure goes up by about $30 million. That said, the returns we anticipate remain quite strong, and the payback period is short. Since injection volumes of water have come down, the operator's current projection for Jubilee's 2023 gross output is roughly 85,000 barrels of oil per day, a decrease from the 90,000 figure it had previously used. This downgrade is the reason our full-year production guidance is lower, and it should result in Jubilee shipping one less cargo during 2023 than we had earlier anticipated; this is entirely a question of timing, our outlook for 2024 output is unchanged, and we expect the 2023 gap to be recovered next year. Launching a new project and getting the whole field to perform at its best never comes without obstacles, yet we remain enthusiastic about what Jubilee could achieve down the road and keep collaborating effectively with the operator to drive the highest possible cash flow from that field. Now, on slide 6, here's a page we've relied on across the years to update everyone on where things stand with the main work-streams tied to the Tortue LNG project. As for the hub terminal, building work has wrapped up and the transfer over to operations is now done. We also achieved meaningful headway this quarter on the subsea portion of the scope, which until then had sat on the critical path toward first gas. Following the problems that arose around the performance of the earlier pipeline vessel, the subsea work has been awarded under a new contract. The deepwater pipeline and infill flow lines will now be completed by All Seas and Saipem, who have been engaged for that work, which should get underway at the start of December and wrap up during 2024's first quarter. As for the FLNG, the vessel should set sail before this quarter ends and reach its destination at the beginning of next year. Right now, the partnership is exploring options with Golar aimed at speeding up commissioning work on that vessel. When it comes to achieving first gas from phase 1 of Tortue, the critical path is now tied to the FPSO's arrival, hook-up and commissioning. According to what BP, the operator, indicated in its third-quarter results released last week, whether gas gets delivered during the opening quarter of 2024 hinges on how well this workstream is carried out, and there's a chance it could drift into the following quarter. If you look at Slide 7, in addition to those main projects, our attention has gone toward identifying what the Company's upcoming wave of growth projects should be, aiming at premium, advantaged oil and gas ventures where we would hold operating control. KOSMOS announced today that its interest in the proposed operatorship of the Yakaar Teranga field in Senegal has been increased, subject to the customary government approvals. Yakaar Teranga ranks as a world-scale gas resource, holding roughly 25 trillion cubic feet of gas in place, and back in 2017 it stood as the biggest discovery anywhere on the planet; this is advantaged gas carrying negative CO2, sitting about 75 kilometres away from the Dakar Peninsula, which makes a low-cost development possible. KOSMOS's working interest in Yakaar Teranga is set to rise to 90%, while Petrosen keeps the other 10%. What we want is for Petrosen to take part as an equal partner across the entire value chain, holding a bigger working interest. On this earnings call, we want to update you on how KOSMOS is working alongside Petrosen and the Senegalese government. Together we're pursuing a novel way of developing resources. The idea is to first make sure Senegal's rapidly expanding local market gets gas at competitive prices, and then add a floating LNG unit so we can also serve buyers abroad. Petrosen's Director-General appeared in today's press release, calling Yakaar Teranga a strategic initiative and expressing support for the Plan Senegal et Merchant, which is designed to bring the nation affordable, plentiful, and greener energy. Going forward, KOSMOS and Petrosen plan to look at ways to form partnerships, with the aim of assembling a cohesive team that brings the necessary upstream and midstream capabilities, plus the ability to secure inexpensive financing and reach global LNG markets. Turning to slide 8, KOSMOS announced last month that it had made a successful find at the Tiberius well, an exploration effort tied to existing infrastructure in the Gulf of Mexico. At that site, KOSMOS is the operator and, alongside Oxy and Equinor, owns a 33.34% stake. Tiberius sits within the outboard Wilcox trend as a four-way structural trap, and it was drilled with seismic data gathered by the partnership using ocean bottom nodes. Thanks to this up-to-date seismic method, the prospect comes through in a sharper image, which aids in fine-tuning the well's location and in lowering risk for the development program ahead. Shown in the slide is the Tiberius exploration well, which was drilled at the top of the structure in the central fog block, while additional upside exists in the neighboring fog blocks. Things like OBN seismic are a real breakthrough for this business, giving us a far clearer picture of what's below the surface ahead of drilling. That well encountered a net oil column of roughly 250 feet, and we were able to carry out a broad logging program, bringing back numerous fluid samples along with sidewall cores. Early review suggests fluid quality in line with other discoveries close by within the Wilcox trend. Those fluid samples and cores have now been sent to the lab, where analysis will sharpen our grasp of permeability and viscosity — two factors essential to verifying well flow rates down the road in a development. Right now, together with our partners, we're putting together a plan for staged development, with the goal of first output in about two years' time. The host platform we'd prefer is Lucius, which Oxy operates, located six miles northwest of where we made the discovery, and before we drilled, we had already locked down the main commercial terms for the production handling agreement. Tiberius coming through the way it did validates how solid our foundation is and how we go about exploration — infrastructure-first, chasing oil targets that are cheap, emit less carbon, and move fast — and those sit next to a big pipeline of longer-dated, lower-carbon gas opportunities in West Africa. With that, I'll hand it over to Neal, who'll take you through the numbers.

Neal Shah

executive
#4

Appreciate that, Andy. If you go to Slide 9, output for the quarter came in right on guidance. The Gulf of Mexico did a bit better than we'd expected, which made up for weaker production at Jubilee than anticipated, as Andy discussed earlier. OpEx matched guidance and rose versus the prior quarter because of the 110 cargo we have this year landing in Q3. Keep in mind that TEN OpEx, which runs above the other assets in the portfolio, gets recognized when we have the listing. The guidance slide in the appendix indicates OpEx dropping to normalized levels in Q4. CapEx sits at the top end of our range, which did encompass the extensive success case evaluation program tied to Tiberius that Andy referenced on the prior slide. Moving to Slide 10, in Q3 we experienced ongoing strengthening of our financial position, with leverage declining thanks to both higher EBITDAX and lower net debt. We paid off the Gulf of Mexico loan during the quarter, a key step toward simplifying the capital structure. After the GoM term loan pay-down and the October RBL amendment, Kosmos faces no scheduled debt maturities before 2025. We've discussed hitting a cash flow inflection point as production grows and capital declines with our growth products being delivered. Our near-term priority for any cash we generate is paying down debt to move leverage toward our long-term target of under 1.5 times at mid-cycle oil price. Since our floating debt is now costlier than our fixed debt, we're prioritizing the RBL, which lets us maintain and grow available liquidity over time. We expect we still have a couple of quarters of elevated CapEx ahead while we finish Tortue and Winterfell, and after that, we anticipate debt reduction speeding up as free cash flow increases meaningfully in the second half of next year. We keep making solid progress on our hedging targets for next year. Consistent with past practice, we aim to hedge roughly 50% of the following year's production, which enables us to fund the capital plan for the year. Through collar structures, we presently have about one-third of next year's production hedged at an average floor of $69 per barrel with an average ceiling of roughly $94 per barrel. Looking ahead to our 4Q guidance, which appears in the appendix, there are a few points I wanted to highlight. Full year '23 production guidance is now anticipated to be about 63,000 barrels of oil equivalent per day because of the delayed start-up of Jubilee Southeast and lower water injection levels. We lifted full year GoM production guidance due to the back of storms, but 4Q GoM production is below the third quarter because of both planned and unplanned downtime, which should be largely finished this month. Additionally, our projection for full-year capital expenditures is now approximately $800 million, which accounts for the faster pace of drilling at Jubilee during Q4 and more work at Tiberius after that favorable well outcome. We continue to anticipate a reduction in CapEx as we move into '24, especially during the latter six months, once we wrap up the capital outlay on our three main projects. So with that, I'll pass things over to Andy to wrap up the presentation for today.

Andrew Inglis

executive
#5

Appreciate it, Neal. Now moving to Slide 11 as we wrap up today's presentation. At the outset of today's presentation, I discussed how crucial it is to have a strategy that is both clear and consistent. In 2023 thus far, Kosmos has hit a number of significant milestones in executing that strategy, and that positions us well for delivering even more in 2024. While I won't go through each bullet on the slide in detail, I do want to highlight several key themes. Kosmos offers a growth story that sets us apart, and we've begun to bring that to life with the Jubilee Southeast project coming on stream in Ghana, with additional growth anticipated during 2024. We keep advancing our remaining development projects at Tortue and Winterfell, and these should generate another substantial increase in production in 2024, with Tortue bringing even more diversification to the portfolio, both in terms of geography and by adding a new LNG revenue stream that will last for many decades once it comes online. We're also broadening our medium- to long-term growth pipeline with operated, high-quality investment opportunities spanning both advantaged oil and gas via Tiberius and Yakaar Teranga; and lastly, as we generate greater free cash flow, debt reduction will be our priority until we hit our target leverage level, and that's the point at which we intend to consider shareholder returns. Everyone on the Kosmos management team is enthusiastic about the future opportunities ahead of us and motivated to build additional value for our shareholders. Thank you. At this time, I'd like to hand the call over to the operator so we can begin the question session.

Matt Smith

analyst
#6

Hello everyone, thank you so much. I have a few questions, if that's alright. The first concerns Tortue CapEx. During the previous earnings call, we mentioned there's some uncertainty regarding the phasing, and I believe also the size of extra CapEx that would come from the new subsea contractor. If I recall correctly, you didn't mention that as a factor behind the higher 2023 guidance. So, should I assume there could be some CapEx pushed into 2024 because of this change? That's my first question. Secondly, if I may, regarding Tiberius, I realize more analysis is needed, but could you remind us of the pre-drill resource estimate you had for it, and where you think it may have landed relative to that, if you're open to saying; and then finally, a third one if that's fine, which is whether there's anything you can share about Tortue Phase two right now. And I guess what some investors might wonder is whether we should infer anything from BP leaving Senegal regarding their level of enthusiasm for the expansion at Tortue? Please.

Andrew Inglis

executive
#7

Yes. Thanks, Matt. Let's divide this into three questions. I'll have Neal address the Tortue CapEx. I'll take Tiberius and then discuss Phase Tortue.

Neal Shah

executive
#8

Yeah. So Matt, regarding the Tortue CapEx, right. During the prior quarter we noted a rephasing would occur because of the subsea work, though our general outlook for '23 remains the same. A portion of that CapEx ties to the subsea, which had been intended for roughly Q2 and Q3, got moved to Q4, and in the end, part of it slid into '24. As a result, '23 is about unchanged. Compared with our initial plan, there's extra capital — likely on the order of $100 million net for Tortue during the '24 period.

Andrew Inglis

executive
#9

Alright, Matt — regarding Tiberius, that first exploration well has us genuinely excited. During the presentation, we mentioned that our target was the central fault block, and our belief is that within that central fold block, we took roughly one-third of the pre-drill potential and moved it off the risk table. When it comes to developing it, we ran quite a thorough logging program, and that accounted for part of the extra CapEx we incurred during '23. So my sense is we now hold a very solid collection of sidewalk cores along with fluid samples, and those give us confidence that we can press forward rapidly toward development. Naturally, all of that lab analysis has come back to us. Meanwhile, we have already launched the planning work on the tieback to Lucius. In fact, I believe it was within seven days of announcing the discovery that the team had bid documents out the door for constructing the subsea layout. So I'm genuinely happy with how quickly things are advancing, and with the fact that this initial fault block represents a meaningful production increase for Kosmos. We expect it to come online in about 24 months. So once more, solid headway. And my understanding is the subsea architects will be laid out. To begin with, there will be one flow line. But then perhaps two, perhaps three more wells get added from those other fall blocks we highlighted in the presentation; regarding Tortue Phase 2, I'd say take a step back and consider how it connects with Yakaar Teranga — and I'm certain there will be additional questions about Yakaar Teranga. Still, at Kosmos we hold a highly distinctive growth portfolio of advantaged low-cost gas sitting next to Europe. What we're aiming for now is to stage that development so that we can both expand and give capital back to our shareholders. Obviously, finishing Tortue Phase 1 is the opening move, and we've provided the forward time line for it; now that Yakaar Teranga is under our control, my thinking is we can position that as the following building block in the sequence; and I would imagine Tortue Phase two could sit behind that. So we now have a phased set of developments where you're building out somewhere around 2.5 million tonnes of LNG, yet doing it in a manner where an operated project gives you control and where you're constraining the capital outlay so your capital profile stays credible and manageable; so we're happy with how the future is shaping up, and we regard this as a key source of value growth for shareholders.

Charles Meade

analyst
#10

Morning, Andy, Neal, and everyone else on the Kosmos side. Andy, maybe I can jump in right about where you stopped. You mentioned you were certain there'd be additional questions regarding Yakaar Teranga, and that's exactly what I want to ask about. I think this breaks into two pieces. First, could you provide the broader picture of where Yakaar Teranga stands and how you decided to move forward with Tortue ahead of Yakaar Teranga? And where does Yakaar Teranga fit, in your thinking, as far as whether it ranks second behind Tortue? Then, along those lines, I realize various companies hold various priorities and various perspectives. Charles, you're asking how we'd make the case for what Yakaar Teranga brings to Kosmos when folks point at BP and wonder — if BP just up and left it behind, what makes it worth anything?

Andrew Inglis

executive
#11

Yeah. Appreciate that, Charles. Those are fair questions, as you say. Maybe I'll start from the tail end and move forward from there. What we have in Yakaar Teranga is a gas resource that stands apart. The CO2 level in it is minimal. It's located close to the coast — 75 kilometers out from the Dakar Peninsula. And whether you look at it from the standpoint of the domestic market or the LNG market, there's significant demand pulling for it. Senegal needs something to take the place of heavy fuel oil for generating power. Senegal stands out as one of the nearest new LNG supply options for Europe. So the question becomes, how does that align with what different companies are doing? My sense is that we've reached a stage in the energy transition's life cycle where each company is making its own wager. Nothing illustrated that more plainly than the pair of major announcements made in the U.S. within the past two weeks. That strategic backdrop, I'd argue, shapes how people evaluate different investment opportunities. As I mentioned, Kosmos views this gas as distinctive, and I think that description fits well. So, what does "well described" mean in this context? At Tortue, we drilled four wells for exploration and appraisal, plus a DST, which let us calibrate the seismic data — and that resulted in four development wells that succeeded. That's an enormous volume of subsurface information, and it maps directly onto Yakaar Teranga, where three exploration and appraisal wells exist. Because of this, our belief is that the subsurface has been well described, and we're confident it can support a highly commercial project. We also think the development solution is low-cost, thanks to where it sits geographically, near the Dakar Peninsula. Now, my sense is that BP sees things differently. And ultimately, I don't think that's the case — I think they've been influenced. In the end, it comes down a lot to the strategic situation—specifically where they're putting their capital and whether they can picture a commercial path forward. So from my perspective, this is a very solid opportunity for the company. We assumed our share, which started out at 90%. Our goal is for Petrosen to keep increasing its position until it's a full equal with us and anyone else who comes in. That means we'd anticipate stakes in the range of 25% up to maybe 33%. As things stand, there's still plenty of work to do: we need to fully develop the concept we laid out in the materials, and we also have to bring in a partner and lock down the financing. Once all that's in place, though, it's a tremendously commercial prospect, yet it must be pursued cheaply while making full use of every bit of subsurface expertise. That, then, is basically what sets it apart. Still, what I see is an enormous chance for the business. And as you're aware, this isn't unheard of. You know the Gulf of Mexico well. Think back to something along the lines of Shenandoah. Two big players walked away from it, if I recall. A smaller player holds it today and is currently running a highly competitive large-scale project. So such situations are common among industry presidents. And in my view, the energy transition has only sharpened those distinctions, which means the chance is even bigger.

Charles Meade

analyst
#12

That's useful detail, Andy. And going back to what you said in your prepared remarks, you mentioned the 2 extra wells that will be drilled at Jubilee and Jubilee Southeast, and I just — I want to confirm I got it right; so you were planning to farm out the rig, but then you chose to go with these 2 wells. One sits in Jubilee, if I have it correct, one sits in Jubilee, one sits in Jubilee Southeast, does that result in a higher plateau, or is it just — or were these wells simply kind of more about lowering the volatility around that plateau in case you get more of this water injection. Could you sort of lay it out for us what the...

Andrew Inglis

executive
#13

Yes. It's really just about pulling activity forward from '24 into '23, which lets us actually build toward the facility limit more quickly. So that extra water injection well matters because it lets us tackle some of the water injection problems we've been having; and then the second well is a producer, which would start up in '24; and then we have a continuing drilling program on Jubilee that would grow with additional producers. So at the end of the day now, it's about building to the facilities limit in terms of well capacity, probably building a bit past what the facility limits are; so we have some degree of well capacity held back and then keeping the field at that level. So we've moved some capital forward from '24 into '23 to let us build toward that facility limit more quickly.

Bob Brackett

analyst
#14

Bob, thanks—always appreciate the questions.

Andrew Inglis

executive
#15

Yes, the porosity came in exactly where we thought it would. As you know well, the next thing is to put in the work to actually verify permeability instead of just inferring it from porosity, and then to complete the fluid data, including the viscosity piece and all of that; after that we can fine-tune how we complete the well. So yes, all of it matches our expectations. It lines up with analogs from nearby fields, so things look encouraging so far, and like I said, we're proceeding with a highly economical plan to develop this, tied back to Lucius. Neal, why don't you speak to the capital side of that.

Neal Shah

executive
#16

Correct, Bob. There's very little infrastructure that needs to be put in place, so the tieback program ought to be highly cost-effective. Our vision when developing it followed the same approach we took with Winterfell and other projects — staged, phased development, starting with a single-well EPS where we install a complete facility line, then expanding the development as we gather additional information from the well and the reservoir. So I believe we've previously discussed S&D generally sitting somewhere around $10 to $15. Yes, this one would land right in that bracket.

Neil Mehta

analyst
#17

Morning, everyone, and thanks for the update today. My first question concerns capital spending. Could you walk us from the prior CapEx guidance to the present figure? And what portion stemmed from projects as opposed to inflation; then, when considering 2024, though you lack complete figures, in what manner should we think about the fair approach that we — insofar as you can share that?

Andrew Inglis

executive
#18

Yes. Great. Neal will take that one. Neal?

Neal Shah

executive
#19

Yeah, so for 2023, the two largest items, I'd say, centered on the Tortue ramp-up that Andy mentioned — that accounted for $30 million — and roughly $20 million of it came from the extra drilling, meaning the additional two wells, or 1.5 wells, at Jubilee in Ghana. That's $30 million there, and then the $20 million was really further drilling at Tiberius following the success plus those extensive logging campaigns. So that essentially carried us from — we had been leaning toward the upper bound of the range, and that pushed us from 750 to 800; so that's the acceleration of what we term value-adding activity into 2023. Looking ahead, I believe we've discussed a normalized CapEx, correct, after our three major projects, of let's say 300 to 350 for maintenance and 200 to 250 for growth, which lands you at approximately 550 in steady-state CapEx for the company. 2024 is somewhat of a transition year, since we still have Tortue and Winterfell completion, the remaining CapEx tied to those, plus the steady-state CapEx. So once more, we haven't provided 2024 guidance yet; that will come in February. But my expectation is that 2024 will land between the two, where we are this year and then the steady-state level, as we wrap up those two key projects.

Neil Mehta

analyst
#20

My follow-up concerns Phase I. Could you provide additional detail on that work stream you mentioned, the one that might move into the second quarter? Right now, though, you remain on schedule for first gas during the first quarter. Can you take us into the field and give us more specifics, so we understand exactly what you mean?

Andrew Inglis

executive
#21

Yes, sure, Neal. If you walk through the main work streams: we discussed the hub terminals being complete and handed over to operations. That marked a major milestone during the quarter. Then there's the FLNG vessel, which will clearly be more at the hub terminal; it departs Singapore during this quarter and reaches site at the start of next year. So it's not really on the critical path. The quarter's major breakthrough involved completing all the subsea architecture and re-contracting with dual-seas and side-pen. That work begins early next month, with a clear program to finish in the first quarter. So I feel good about that. The piece — the problem we're dealing with right now — concerns only the FPSO. It's actually something external to the vessel. The vessel has fair leads on it. The fairleads are used for permanently anchoring the vessel at location; they have sea fastenings during the voyage across to the East Coast of Africa. Those sea fastening castings got damaged. The boats currently sit offshore at Durbin, and we're seeking access to Durbin's port so that work addressing the fair lead issue can take place. So that's where a bit of uncertainty about timing exists. So it's not a major problem, but it's — it is a very singular problem we're working. That said, work continues on the FPSO itself and all the topside, so we can proceed with pre-commissioning work; so once it arrives on site, that work stream is shortened; so look, as with all big projects, it comes down to integrating the pieces, we're clearly getting close, and I actually felt good about the progress made in 3Q; and we now have significant milestones to hit over the rest of this quarter and into the first quarter of next year. And the one we're obviously intensely focused on with the operator is ensuring we get the FPSO on location so that we can deliver first gas. So that's the color behind the update.

Mark Wilson

analyst
#22

All right. Thank you, gentlemen. And I appreciate the details regarding the FPSO. That was actually something I intended to inquire about, so it's now clear. Moving on to Yakar Taranga. In today's press release, you laid out a highly detailed development plan: 550 million cubic feet per day, involving piped gas, supply for domestic use, and exports through FLNG. Andy, I believe you referenced an FLNG vessel comparable in size to Tortue, and that's precisely what I'd like to verify — how would that gas be divided? What volume does Senegal need for its own market, and consequently, what quantity remains available for export? You also brought up adding a partner. Am I right in thinking that is an absolute prerequisite to proceed? And what final percentage interest do you picture holding in a project like this?

Andrew Inglis

executive
#23

All right. Yes, those are good questions, Mark. I believe I touched on some of this earlier, but to reiterate, it is a thoroughly detailed development plan. I hope this gives you the impression that we have — clearly we've collaborated closely with Petrosen on putting that together, and it's a plan that is unquestionably competitive and commercially appealing, while also satisfying the nation's own objectives for growth, which centered on supplying gas domestically and then being able to generate extra income via LNG exports. Looking at how it breaks down, roughly 130 million standard cubic feet per day goes to domestic gas, and with that, at first there likely won't be sufficient power capacity to absorb all of it, though that will expand over time. Then — once at a steady state, we'd be contemplating an LNG project of approximately 2.5 million to three million tonnes, yes, which brings you to a gas supply between 400 million and 500 million standard cubic feet, yes. That provides a picture of the plan and, as a result, how many wells will be needed; the well potential closely resembles GTA. And I think, connecting back to your question, the reason why is deeply not involved — this is a plan we put together jointly with Petrosen; and in the end, BP's choice not to take part has enabled us to proceed with it; so as they withdraw, their attention goes to completing Phase 1 of GTA; and that opens the door for us to pursue this. So I think the plan is clear. Regarding ownership percentages, we generally hold 25% to 33% in our existing projects, and I'd expect the same here. The aim is for Petrosen to rise to a share equal to that of any other parties joining. If there are two, perhaps we hold 25% and they hold 25%. If only one party joins, perhaps we end up at a third, a third, a third. So that's roughly the structure. So reaching that point means there’s effort required right now on our side to draw in the partner that acts as a prerequisite for us as well as for Petrosen, and to lock down the funding required so Petrosen can proceed. Plenty remains to be done there, yet this is a venture that, in my view, enjoys complete backing from the government, comes with an extremely well-defined plan for development, and offers a highly competitive cost structure; at this stage, the task is to turn all of that into reality.

Mark Wilson

analyst
#24

All right, and regarding that development idea, can we dig into it a bit more? Take Tortue, for example — an enormous breakwater is under construction there, and much of Phase I was designed so that a subsequent Phase 2 FLNG could be tacked on. Could you walk us through how Yakaar Teranga differs, perhaps in terms of where it sits offshore, which might make an international phase simpler or faster?

Andrew Inglis

executive
#25

Yeah. No, once more, that's helpful context, Mark. Yeah. We — I guess the best way to put it is that a breakwater isn't something we see ourselves constructing. Our thinking is that there's a design allowing an FLNG vessel to sit at that site, with metocean conditions that differ, meaning you avoid the hefty expense of putting up a breakwater. So I'd say it comes down to innovating on the demand solution we've discussed, and we feel we've put in considerable work. Considerable work has been done by us so that we can move our concept forward.

Mark Wilson

analyst
#26

All right, that sounds excellent. My apologies — I have one final item. I simply want to verify something. At Jubilee, there is now another producer-injector pair coming before the year is out, yet the intention remains for that rig to keep working through 2024 on a program of three to four wells each year, which I believe the operator has mentioned previously.

Andrew Inglis

executive
#27

Correct. No, no, that's accurate, Mark — as a concept, that is what's proposed. Roughly half a rig year on Jubilee during '24, I'd estimate; and once more, I believe it was Charles' question regarding the aim of building well capacity so that we hold a kind of reserve capacity past the facilities limit. Alongside dependable water injection, you then gain the capability to more or less maintain the plateau at that level. And then obviously, you subsequently add more wells once that well capacity gets tested. But we're now on a solid path to keep pressing ahead with Jubilee as those wells are added and essentially support the new wells with dependable water injection. So the growth at Jubilee is properly captured when it comes to the forward activity set.

Stella Cridge

analyst
#28

Hello everyone. Good afternoon. Thanks so much for the updates. I have three questions, if I may. First, a small clarification regarding Yakaar Teranga. Is any consideration actually owed to BP for that extra stick — that's question one. Second, about the TEN gas development. I noticed a figure in the press regarding a possible cost. I was wondering whether you could speak to that directly — what CapEx do you foresee there, and how would the Cosmos share be funded? And lastly, is there anything new on the Ghana tax matter? So that's three items.

Andrew Inglis

executive
#29

Okay. Let me take those in reverse order, roughly. Regarding Kosmos, there is no continuing discussion between us and the GRA — the Ghanaian Tax Authority — concerning any tax matters. On TEN, the — I believe the newspaper piece mentioned a $1.3 billion development, which would encompass the entire next phase of the TEN POD. Our portion would be 20% of that; and obviously, that expenditure would be forward spend across potentially '24, '25, and so on. So — however, we're still awaiting movement from the Government of Ghana when it comes to that spend; thus we don't have any firm timing as yet; and then regarding Yakaar Terganga, no consideration was paid to BP.

Stella Cridge

analyst
#30

That's excellent. So you said there isn't any continuing conversation with the government. Does that mean the tax claim no longer exists, or does the claim remain, but there simply haven't been any talks about it?

Andrew Inglis

executive
#31

We don't have a tax plan.

Stella Cridge

analyst
#32

All right, understood. Did anything specific cause that to be removed, so...

Andrew Inglis

executive
#33

I don't believe so — no — when it comes to how much we sold compared with other entities, at no point was there a tax claim filed against...

Neal Shah

executive
#34

Never a dispute.

Andrew Inglis

executive
#35

Never a dispute.

Neal Shah

executive
#36

No two partnerships look the same, and we have never been involved in a formal dispute with the GRA. Naturally, we do hold continuing conversations with them, yet there are no claims we are currently working through.

Operator

operator
#37

That wraps up the question portion. At this point, I'd like to end the call. We appreciate all of you being with us today. You're welcome to hang up now, and thanks for taking part.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Kosmos Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Kosmos Energy Ltd. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Kosmos Energy Ltd. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.