Kosmos Energy Ltd. (KOS) Earnings Call Transcript & Summary
August 4, 2025
Earnings Call Speaker Segments
Jamie Buckland
executiveThanks, operator, and I appreciate all of you being with us today. Earlier this morning, we put out our earnings release for the second quarter of 2025; you can find that release along with the slide deck for today's call on the Investors section of our site. Here with me to walk through the materials are Andrew Inglis, our Chairman and CEO, and Neal Shah, our CFO. Over the course of today's presentation, we'll be making forward-looking statements relating to our estimates, plans and expectations. Factors we flag in this presentation and in our U.K. and SEC filings could cause actual results and outcomes to differ materially. For additional detail, please see our annual report stock exchange announcement and SEC filings; those documents can be accessed on our website. With that, I'll hand the call over to Andy.
Andy Inglis
executiveThanks, Jamie, and a good morning and afternoon to all of you. We appreciate you being with us today for the call on our second quarter results. I'll begin by discussing Kosmos' priorities, restating the key messages I shared last quarter, before bringing you up to date on progress throughout the portfolio. Neal will next take you through the financials and the efforts we've undertaken to improve the balance sheet's resilience, and after that I'll finish with closing remarks; then we'll open the line for Q&A. Beginning on Slide 3. As we work through the continuing volatility in commodity prices, our key priorities remain unchanged. Last quarter, I spoke about increasing production and lowering costs so that free cash flow is prioritized, while we keep strengthening our balance sheet. I'm happy to report that this quarter we've made solid progress in each of these areas. Beginning with production; in June, we announced that the Gimi floating LNG vessel had reached Commercial Operations Date, or COD, a significant milestone for the GTA project. COD is reached once LNG production has been tested over a period of 72 hours at the annual contracted rate of roughly 2.45 million tonnes per annum equivalent. The FLNG's nameplate capacity is approximately 2.7 million tonnes per annum, and we aim to reach that level during the fourth quarter of the year. The project has lifted 6.5 gross cargoes year-to-date so far. In Ghana, we're pleased that drilling and Jubilee has restarted, with the first producer well of the '25/'26 drilling program now online. Initial gross production from that well is approximately 10,000 barrels of oil per day, matching our expectations. We've also optimized the drilling program by accelerating the scheduled rig maintenance in 3Q, which lets us drill a second producer this year, replacing an injector that had been previously planned. This planned producer well should add further Jubilee production around the end of the year, ahead of four or more wells planned in 2026. I'll discuss that along with 2Q Jubilee production later in the material. In the Gulf of America, the partnership has drilled the Winterfell-4 well, with completion operations underway, and that went as expected online around the end of the quarter. We are now nearing Kosmos' record high production levels, with additional near-term growth expected as we push GTA towards the FLNG nameplate capacity and bring on more wells at Jubilee and Winterfell. Turning to costs. We focused on three areas and are making good progress across all three. First, on CapEx. CapEx in the first half of 2025 was around $170 million, down around 65% from the first half of 2024, as we come out of a heavy investment period and start to see the benefits of those investments; with a sharp focus on CapEx in 2025, we've reduced our full year CapEx forecast from around $400 million to around $350 million, with the first half actual supporting its lower forecast as we slow down some longer-term investments. Second, on OpEx. When it comes to cutting OpEx, GTA represents our biggest opening, and OpEx per BOE is dropping as output increases. In addition, we're aiming to refinance the GTA FPSO during this year's second half, and alongside the operator we're examining lower-cost operating alternatives that might push costs down even more throughout the project; and thirdly, overhead; we're still on track to hit $25 million in targeted savings before this year is out, with the complete benefit showing up in 2026 and beyond. And last, the balance sheet, where financial resilience stays our priority, centered on cash flow and paying down debt; regarding liquidity, we're acting to handle our approaching debt maturities, and as part of today's material, we announced that we've agreed indicative terms for a term loan of up to $250 million secured against our Gulf of America assets, and we expect to use the proceeds to repay our 2026 bond maturity. We're also advancing further financing activities to fund some of our longer-dated maturities; on hedging, we capitalized on stronger prices in late 2Q and early 3Q to hedge additional 2026 oil production, with 7 million barrels now hedged in 2026; our aim is to hedge roughly 50% of 2026 production before this year ends. And last, on the RBL, to reflect how GTA ramp-up costs affect leverage timing, our banks granted us a waiver on the debt cover ratio covenant through to March 2026. Neal will cover all of this in greater detail later; but in summary, we're making solid progress on our financial objectives. Moving to Slide 4, which reviews operations for the quarter. Beginning with the GTA project in Senegal and Mauritania. Second quarter net production came in at just over 7,000 barrels of oil equivalent per day, and the partnership lifted 3.5 gross LNG cargoes, as previously communicated. As noted on the previous slide, the FLNG commercial operations date was reached in late June. For Kosmos, this marks a significant operational and financial milestone, since it signals that we're finished funding the NOC's CapEx on the project. In Ghana, total net production was approximately 29,100 barrels of oil equivalent per day. Jubilee gross production of around 55,000 barrels of oil per day came in below expectations for the second quarter, driven by 9 days of planned FPSO shutdown, a stretch of riser instability after the restart, which has since been addressed, and the performance of certain wells on the eastern side of the field. I'll say more on the following slides about how the partnership is tackling these issues and the steps being taken to restore the field's full production potential. As noted on the previous slide, the first producer well of the '25/'26 program came online late last month and is performing well. Jubilee gross gas production was around 16,600 barrels of oil equivalent per day in the second quarter. At the start of June, we said we'd signed a memorandum of understanding with Ghana's government to push the licenses out to 2040. For both the project partners and the government, these extensions are a win-win, and the partners are now laying out long-term investment plans in the field so that value is maximized for all stakeholders. Together with our partners and the government, we're finalizing the documentation, and we're aiming to wrap that up in the second half of the year. During my meeting with President Mahama earlier this year, we talked about how he wants to reinvigorate Ghana's oil and gas sector by boosting investment in some of the nation's most valuable assets. The extensions on Jubilee and TEN fit squarely with that agenda. Over at TEN, gross oil output for the quarter came in at slightly below 16,000 barrels of oil per day. In the Gulf of America, net production reached approximately 19,600 barrels of oil equivalent per day, landing at the top end of guidance, thanks to strong results from the Kodiak and Odd Job fields. At Winterfell, the partnership has finished drilling the #4 well, completion work is currently underway, and the well should come online later this quarter. As for Tiberius, we keep moving the development forward alongside our 50 to 50 partner, Oxy, with FID targeted for next year.
Andy Inglis
executiveOver in Equatorial Guinea, net production came in at slightly under 8,000 barrels of oil per day, which fell short of what we had anticipated because of certain mechanical issues with subsea pumps at Ceiba. Installation of the first replacement pump is what the operator anticipates during the fourth quarter, and output should climb after that. Moving on to Slide 5. At GTA, we keep witnessing plenty of encouraging movement, since the project is now operating at full capacity. So far this year, 6.5 gross cargoes have been lifted, and the pace at which cargoes are listed keeps accelerating as output builds. Additional advancement is happening as anticipated, with production projected to climb toward the nameplate capacity of 2.7 million tonnes per annum during the fourth quarter. Output from this project ought to vary a bit in response to seasonal temperatures, with greater production anticipated across the winter months, when those air and sea temperatures occur. Our full year guidance of 20 gross cargoes captures a somewhat slower ramp-up in production than what we observed during the same quarter and the early part of the third quarter. What matters greatly is that the subsurface is delivering strong performance, which is a crucial element as we map out the expansion phases ahead. Keep in mind that roughly 25 Tcf of discovered gas in place sits at GTA. For 20 years of production at the contracted rate, Phase 1 needs only about 3 Tcf. This ranks as a world-class gas resource, offering considerable running room. A first condensate cargo is also anticipated by the partnership late in the third quarter, which represents a meaningful extra revenue stream for the project; regarding operating costs, start-up as well as commissioning costs ought to begin dropping away during the second half of the year; beyond that, we are advancing the refinancing of the FPSO lease, with completion targeted for the second half of the year. On top of that, the partners are collaborating with the operator to investigate alternative lower-cost operating models, aiming to push costs down even more. Looking ahead now that Phase 1 is fully operational, the next big chance to boost value comes through future expansion. Phase 1 plus is a low-cost brownfield expansion that draws on the infrastructure already in place from Phase 1, allowing gas production to double at a fraction of the cost by way of greater LNG production and domestic gas supplied to our host countries. In July, during an official visit to the U.S., the Presidents of Senegal and Mauritania sat down with President Trump at the White House. President Faye of Senegal told President Trump favorably about Kosmos and the critical part we played in discovering the GTA field 10 years ago. He further discussed how important U.S. investment from companies such as Kosmos is to Senegal, along with the joint opportunities that investment could generate in sectors central to the country's economic growth, including natural gas. Videos from those meetings can be found online and are worth a look. Moving to Slide 6, 2025 matters a great deal for our operations in Ghana, as drilling resumes. The time line shown on the slide illustrates the path we are following to unlock the full potential of the Jubilee field. The initial six months of 2024 brought the prior three-year drilling program to a close, and that program had relied on 4D seismic acquired back in 2017. When that campaign finished, output at Jubilee reached a peak surpassing 100,000 barrels of oil per day; during the latter six months of the year, a 12-month pause in drilling got underway, which produced a degree of natural field decline that had been anticipated, and matters were made worse by facility problems we discussed at length last year — specifically reliability, water injection and power generation. In the first half of 2025, during the planned shutdown, the partnership completed a substantial scope of facilities work on the FPSO. Although voidage replacement during the first six months of the year came in above 100%, declines in production proved greater than expected in certain wells located on the field's eastern side, among them Jubilee Southeast. Gas lift via riser was brought in on the field's eastern side, which has aided in restoring and steadying output, and there are plans to apply the same approach on the western side of the field down the road; during early 2025, we shot new 4D across the field — the first such acquisition since 2017 — to make certain the next batch of wells we drill at Jubilee represent the strongest targets, derisked with the finest data and technology available. One notable second-quarter development was the rig arriving to kick off the '25/'26 drilling campaign. In July, we placed the first new well onstream in more than a year, a producer located in the Jubilee main reservoir that initially yielded gross production of roughly 10,000 barrels of oil per day. The 2025 rig program has been fine-tuned so that a second producer well gets drilled in the Jubilee Main field after a stretch of planned rig maintenance. That second producer well should come online near the close of the year. It's exciting to watch the improved imaging from the fast-track 4D seismic data now arriving, and we intend to refine it further through ocean bottom node seismic, or OBN, which we anticipate acquiring later in the year. I'll cover more on that when we get to the next slide. Looking ahead to next year and past it, we've returned to a steadier drilling rhythm, with four wells committed for 2026, and those will begin to gain from the new seismic. Moving to Slide 7. I'd like to devote a bit of time on this slide to discussing why continuous drilling matters and how the partnership intends to apply the newest technologies to unlock Jubilee's full potential. Employing advanced seismic technology to boost resource recovery in mid-life fields is an expanding theme throughout the industry, with recent statements from a few of the majors emphasizing the notable part they foresee playing in the years ahead. The 4D narrow-azimuth seismic, or NAZ, shot during the first quarter of the year represented the first seismic taken over the field since 2017. With this fresh seismic information run through state-of-the-art processing, we're getting a clearer picture of what lies beneath the surface thanks to better imaging, and that's assisting us in pinpointing previously undrilled lobes as well as unswept oil. You can observe on the slide that the contemporary NAZ data located in the lower right corner reveals substantially sharper definition of reservoirs that already exist and delivers an enhanced grasp of how fluids have shifted across time relative to the older seismic shown in the upper right. The superior imaging from the new data additionally offers more visibility into and comprehension of deeper opportunities. Here at Kosmos, we've positioned ourselves at the forefront of pairing this contemporary seismic with fresh AI-enhanced interpretation of data and modeling of reservoirs in order to maximize recovery. As noted on the earlier slide, we intend to acquire OBN data across the field at a later point in the year, and that will strengthen the velocity model so as to further boost the NAZ processing. The velocity model additions shown in the two images on the slide illustrate how clarity has evolved and improved between 2017 and today, and our view is that additional gains remain possible with OBN data. The second point on the slide I'd like to emphasize is drilling; in the past we've spoken extensively about how necessary routine drilling on Jubilee is — an essential element of realizing the field's potential, together with strong facility uptime and continued water injection.
Andy Inglis
executiveLike I said, we've kicked off the '25/'26 drilling campaign, and the first Jubilee producer—J-72—is already producing, while we anticipate the second main field producer at Jubilee will come onstream near year-end. Once that well is finished, the rig is set to spud four Jubilee wells during 2026, aimed at well-defined main field producers backed by solid nearby well control, much like J-72. Looking ahead, we figure three to four wells annually will be required to realize the field's maximum potential across a multiyear span and keep production at elevated levels. Thanks to the license extension MOU, the partnership is now able to plan for long-term investment in Jubilee, which ought to also generate a substantial increase in 2P reserves. To sum up, Jubilee is a sizable field, and we anticipate it will grow larger via consistent drilling, aided by new imaging and reservoir management technology. Now to Slide 8. The Gulf of America's second quarter results were solid, with output at the high end of guidance, boosted by robust performance from both Odd Job and Kodiak. Over at Winterfell, the #4 well was spudded during the second quarter and should come online in late 3Q. That well ought to add a net rate to Kosmos of roughly 1,000 barrels of oil equivalent per day; regarding our development work, we, along with Oxy, keep advancing Tiberius, an outboard Wilcox discovery, developing better lower-cost development plans backed by new OBN seismic we intend to acquire later this year. FID would then be aimed for next year. Gettysburg is a discovered resource opportunity we picked up in an earlier lease sale within the Norphlet trend. To move the project forward, we brought in Shell as a 75% partner and operator, and we're collaborating with them in a joint team to advance a low-cost single well development that will be tied back to the Appomattox platform, which Shell operates. That wraps up the portfolio review, and Neal will now walk you through the financials.
Neal Shah
executiveThanks, Andy. Moving on to Slide 9, where we examine the quarter more closely. Output was up from the prior quarter thanks to GTA starting up and solid results in the Gulf of America, partially offset by weaker output at Jubilee and Equatorial Guinea. Output did land below our guidance, primarily because of the timing of the GTA ramp-up that we flagged back in June, plus weaker Jubilee volumes during the quarter; now that GTA has ramped up and the first Jubilee well came online in July, we're currently producing near record levels, as Andy noted earlier. Looking ahead through 2026, we expect production to climb each quarter, driven by additional wells at Jubilee and Winterfell, new replacement pumps going in at Ceiba, and GTA's ongoing ramp-up toward the FLNG nameplate capacity. As the slide indicates, OpEx per BOE—leaving GTA out—was higher in this quarter, largely due to the 1/10 lifting we're expecting this year, given that TEN operating costs are recorded in whichever quarter the cargo gets lifted. G&A declined, as we're starting to realize savings from certain overhead reductions. Finally, CapEx finished below budget, reflecting the timing of Gulf of America activity and lower GTA costs during the quarter. To pick up on what Andy mentioned before, our full-year CapEx outlook has been reduced, now sitting at about $350 million instead of $400 million. Looking at what we spent in the first and second quarters, it's clear we're on pace to land at that lower number, and we believe that level can be maintained through 2026. Now that spending on CapEx and NOC is tapering off while production keeps climbing, we're producing free cash flow at today's oil prices. The schedule has shifted somewhat, but our priority remains squeezing the most cash flow possible in the short term and reducing our net debt on an absolute basis. One more thing worth mentioning: quarterly working capital is tough to forecast, but we're anticipating a draw during the third quarter tied to when certain payments come due. Now on Slide 10. Andy noted during his opening comments that boosting the strength of the balance sheet ranks among the company's goals for this year, and we have lately achieved headway in a number of important areas. Regarding liquidity, we have settled on preliminary terms for a senior secured term loan with a counterparty rated investment grade, carrying a cost comparable to that of our current RBL, in an amount reaching $250 million, and we would anticipate applying it toward retiring the 2026 unsecured notes that remain outstanding; this facility would be backed by our Gulf of America assets, with final maturity falling 4 years following closing, which we expect to occur before the third quarter ends. The graphic to your right illustrates how this deal would affect our maturity schedule on a pro forma basis, under the assumption that we draw the full amount on the new facility in order to retire the 2026 notes that remain outstanding. As we move through the back half of 2025, our intention is to keep pursuing other appealing liquidity sources that could allow us to pay down certain of our more distant maturities. On the hedging side, we continue to add protection against commodity price decreases over the remainder of this year and throughout 2026. For the balance of 2025, hedges cover 5 million barrels of our oil production, with a floor set at $62 per barrel and a ceiling of $77 per barrel. We likewise capitalized on stronger pricing during late 2Q and early 3Q to layer in additional hedges for 2026. At present, 7 million barrels of oil are hedged for next year, with a $66 per barrel floor and a $75 per barrel ceiling. Turning to CapEx, on the prior slide I discussed cutting the full year guidance down to roughly $350 million, versus $400 million. The chart in the lower right illustrates a substantial decline in quarterly CapEx compared with last year, and we expect reduced CapEx levels to persist as we place priority on free cash flow. Lastly, alongside our banks, we amended how the debt cover ratio is calculated for the RBL, lifting that ratio for the upcoming 2 scheduled test dates to capture the timing effect that start-up of the GTA project has on the backward-looking leverage calculation. After that, once full year revenues from the GTA project line up more closely with operating expenses, the debt cover ratio will revert to the level originally agreed. Thus, to sum up, we stay proactive about strengthening the balance sheet, boosting liquidity, expanding hedging and trimming costs, and we'll keep the market updated as additional progress is made during the second half of this year. With that, I'll turn things back over to Andy.
Andy Inglis
executiveAppreciate that, Neal. Now moving to Slide 11 as we wrap up today's presentation. Like I mentioned at the start, our short-term priorities are boosting output, bringing down expenses, and strengthening the balance sheet's resilience, and on all three fronts we're seeing solid progress. When we look past the short term, there's considerable room to create long-term value for our shareholders via top-quality production and development possibilities throughout the portfolio. Regarding GTA, now that the first phase is running at full capacity, we're directing our attention toward cutting costs and doubling production, which will push unit costs even lower by progressing the low-cost brownfield expansion that takes advantage of the infrastructure already in place. Over in Ghana, Jubilee is a substantial mid-life field holding sizable reserves that have yet to be produced, and those can be reached through steady drilling made possible by new technology along with the license extension. In the Gulf of America, a proven basin with plenty of running room, we keep moving forward an appealing portfolio of infrastructure-led exploration and development choices in the Outboard Wilcox and Norphlet trends, drawing on Kosmos' capability. In Equatorial Guinea, our assets ought to generate cash flow as we invest selectively in production optimization. So to sum up, Kosmos holds a diverse, differentiated portfolio with a 2P reserves to production life of over 20 years, plus considerable discovered resource on top of that. Converting that discovered resource into high-value reserves and afterward into production will happen at the appropriate pace and in a capital efficient way, with cash flow and the balance sheet taking priority in the near term; we look forward to delivering on these near-term objectives, which will underpin long-term value creation for our investors. Thank you; and at this point I'd like to hand the call over to the operator so we can open the session for questions.
Charles Meade
analystAndy, I'd like to pose something regarding Jubilee. You've provided plenty of excellent specifics here, and all that technical information is great; however, if we step back and view things at a high level, you told us — you noted that during the opening six months of '24, output from the field exceeded 100,000 barrels. Then 12 months later, that figure has fallen to 55,000, or roughly 60,000 once you account for downtime. So a 40% drop across the year seems steep to me, possibly unusually steep. Yet suppose I consider it another way and think, fine, you must sink four fresh producers annually just to hold the field steady. And should those wells perform like your most recent one, perhaps that 40% yearly decrease represents the gradient you're battling each year. So I'm curious whether you'd say that's a fair perspective and what else you might contribute to that view.
Andy Inglis
executiveYeah. Appreciate it, Charles, it's genuinely a solid question. From a high-level standpoint, I believe you correctly zeroed in on our position in 2Q. The shutdown wasn't just somewhat difficult, we also faced extra problems with riser instability, which we have since resolved. So in 2Q, you need to view things within the proper frame, indeed. Yet I think it was further affected by decline that came in above what we expected, definitely among certain wells located on the field's eastern portion, especially Jubilee Southeast. So then you ask, alright, what exactly are we doing regarding that at present? I believe we covered fairly thoroughly during the prepared remarks how two factors are making an impact. First is superior data. We've — the improvement we're getting from the fast track data in the NAZ makes us quite happy, and once more, keep in mind this is fast track, a very preliminary product. To me, that improvement is enormous concerning our capacity to spot superior chances within the field, whether from undrilled lobes or unswept oil. So now you're beginning to get a far more distinct view. And I think we did struggle near the conclusion of the previous drilling campaign because of the data quality we referenced going back to 2017. Thus you now have significantly better data, plus the chance to enhance it even more by moving from NAZ to the OBN, and I believe we will achieve — witness a substantial improvement in the velocity model. So in my view, the imaging will only keep getting sharper. And then, as you correctly put it, the second aspect of this involves how we apply that enhanced data, which requires drilling regulate. And we've consistently stated that you must complete three to four wells per year in order to roughly sustain production levels. So if you kind of take that and kind of follow it forward, I believe we drilled the first one of those wells and brought it onstream last month. And we're seeing output climbing because of that. We're hoping to have a second well online around year-end. And I believe that could lift production to roughly 70,000 barrels a day. So the drilling is more than compensating for the natural decline and driving growth. And then four additional wells in '26, we believe those are probably going to produce. And if you figure each one of those adds 5,000 to 10,000 barrels a day, you can see your path with the — even with the decline that we're observing, building up toward that roughly 90,000 barrels a day. So I think that's how you get back to where we need to be; and then you can kind of repeat the process because you have quality data and you're beginning to deliver a regular consistent drilling program targeting high-quality wells. So yes, 2Q came in below expectation, and you've kind of run the numbers on that. But I think even when you were kind of — you adjust it for the one-offs that were in there and then you start to look at the performance we're seeing from some of the wells that we're drilling, you can reestablish the potential of the field; but it's going to require the two things we discussed, going to require good data. And I think I'm really pleased with what we're seeing with the NAZ, and I think the fast Track NAZ, it will only improve with the four products and then the uplift from the OBN and then back to a regular drilling program.
Charles Meade
analystUnderstood, that's really helpful, Andy. Now regarding GTA, I believe you brought up in your prepared remarks, on the slides, and in the press release that you're looking into various operating models to bring costs down. Could you give us an idea of what those could look like, or even more crucially, what the scale of the savings might be? And I'm assuming you mean in absolute terms, rather than as a step toward unit-of-production costs?
Andy Inglis
executiveYes, definitely. Well, I think it's worth keeping in mind that GTA has definitely been a big undertaking for us. Launching a large facility like this as an LNG project always involves — I'd say the initial year is invariably tough, since you're ramping up to plateau, eliminating those shutdown and commissioning expenses, and reaching a steady state. So I'd say the top priority is to achieve that result and reach that plateau. And I believe we received COD in June. I think we're maintaining those levels at present, and we're generating at the ACQ. So I'd say — but we recognize there's still further to go. Looking at each individual train and the optimization possible, there's definitely room to reach nameplate and even exceed it. So that's one piece of the effort in the latter half of the year. Another piece of the effort in the latter half of the year involves clearing out those projects, those start-up and commissioning expenses from the system and bringing them to a reduced level, which we expect to accomplish in the fourth quarter as well. And then, going forward, the discussion with the operator centers on a few items. We're examining how to refinance the FPSO in the latter half of the year. That should deliver a substantial gain for Kosmos and for the NOCs. And after that comes how to push operating costs down even further. And ultimately, Charles, that involves looking into all sorts of operating models, yes. Right now, we have an approach that relies solely on BP staff, both aboard the FPSO and at the hub, and those are the avenues for considering models used in other places that ultimately lead to a more competitive standing. So those are the next steps; I'd say there's plenty of room to cut costs. And it's not just about increasing volume. It's really about tackling the cost structure from every angle I've described.
Matt Smith
analystThanks for walking us through everything up to this point. I might just ask one fairly wide-ranging thing about CapEx. It's encouraging to see that figure declining in the 2025 guidance. What I'm really asking, I suppose, is whether that CapEx budget, now comfortably under $400 million, sitting at roughly $350 million, is a reasonable level to assume moving forward. You mentioned Tiberius FID possibly happening sometime next year, along with Phase 1 plus at GTA; so I'm curious whether you feel confident you could stay within that $350 million as you go forward. Or should we anticipate that you might have to exceed it in order to advance those projects? And maybe I'll add a second one tied to that, which is whether any momentum is showing up right now on the GTA Phase 1 plus project, whether the partnership is well aligned, or how near-term progress there might be — that's really the heart of what I'm asking, please.
Andy Inglis
executiveOkay. Thanks, Matt. When you look at that CapEx cut from $400 million down to $350 million, it's really about making each dollar count as we consider the investment flowing into the company and putting free cash flow first. So there are plenty of opportunities throughout the portfolio. That said, I'd say most of it has come from decelerating certain longer-term projects, Tiberius especially. So when you then move to the next question — can you maintain the $350 million into '26 — we haven't issued CapEx guidance yet. But if you take a step back and consider that the main call on capital in '26 is the four wells we have committed in Jubilee. There is — that represents a primary call on CapEx. In Equatorial Guinea, actually, there isn't really any meaningful CapEx call. On GTA, I'll get to that shortly. We don't think Phase 1 will be a major piece of '26; it will proceed a bit more slowly. As a result, Tiberius FID will likely arrive toward the back end of the year. So when you factor that in and consider the emphasis, particularly given the volatile oil price setting we face today, a forward figure of roughly $350 million can — not just keep the company going, but it will grow the company, as I mentioned, through the effect of the Jubilee wells without harming that future growth profile. So I'd say — to sum up, yes, roughly $350 million, probably about right. Yes, at around $350 million, the company will keep growing. And then you have the later follow-on, which falls more in the '27, '28 window, when you'd see some spending on Tiberius, some spending on Phase 1 plus, okay? Then regarding Phase 1 plus, the most important starting point there is really how the subsurface performs on Phase 1. Right now, we have 3 wells that are producing, and every one of them is doing exactly what we expected. That mattered because the partnership viewed reservoir behavior as something of a checkpoint before moving ahead. Production began right at the close of the year — 31st of December — so we now have over 7 months of output history, and we like what the data shows. On the reserve side, the capability to grow the project is clearly present. As for the partnership, everyone agrees on pursuing a brownfield expansion — one that could double volumes by expanding the FPSO through brownfield means. That vessel was built to handle roughly twice the rate it currently manages, and the extra capital required to reach that level is quite modest. So there's consensus on that front. There's also consensus that the added gas will feed both LNG and domestic gas. The government has issued a call for domestic gas. At the same time, how quickly they increase that domestic gas call is a matter we're still working through. Then there's the question of debottlenecking the Gimi to create more LNG capacity — that's the other half of the puzzle when figuring out how to utilize that additional 300 million to 400 million standard cubic feet. That's the effort underway right now. So the core question, naturally, comes down to how many wells are needed to back that incremental 350; and it's encouraging that the reservoir is delivering, since we're building a track record. Because of that, I think we have a chance to genuinely sharpen the well count. That's the work in progress today. Three items: nail down the well count — how many are required, and when must they come online to support the added volume? What's the schedule for that volume split between domestic gas and LNG, and what gain can the Gimi deliver to make it happen.
Bob Brackett
analystMaybe I could get one thing cleared up first, and after that I have a question. That clarification relates to what Charles mentioned regarding a 40% drop at the Jubilee field, which does 100,000 a day. What I take from the release is closer to three to four wells each year in order to keep output flat, and those might be divided between producers and injectors, which brings you to roughly a 15% to 20% base decline. Would that be the more accurate way to view it?
Andy Inglis
executiveThat's right, Bob. Yes. I'd say your description is correct. So when you consider the near-term program, we're going to put a heavy emphasis on producers since we think we have enough injection capacity as you increase from where we stand today up to that roughly 90,000 barrels of oil per day. So at present, extra injectors aren't really needed. That means you can kind of prioritize the program toward producers, but doing so requires the data and so on, as I went through with Charles. Once you reach that greater level, then the decline rate you referred to is the level at which the field can be managed; and so you will be — you will require injectors, because your offtake level is high. And so a combination of producers and injectors, three to four wells annually, is the correct way to look at it.
Bob Brackett
analystBob, my main question is kind of tied to that—it's about the license extension. There's an MOU in place. Could you tell us if the fiscal terms have shifted at all, or if there's any work program commitment? Or is all of that still unresolved?
Andy Inglis
executiveNo. Bob, what we've done is lay out the MOU's purpose and the scope it addresses. Honestly, it benefits both sides—the government and us. Here's what's happening: the gas price goes down, but volume goes up. So we've agreed to raise output to 130 million standard cubic feet per day, with a modest reduction in the gas price. There's also a commitment to drill as many as 20 wells. Obviously, that figure will hinge on what opportunities emerge from the NAZ as we see them; but right now, we view it as a favorable picture of the reservoir that we're forming. The fiscal terms stay the same. It falls under current legislation; those are the main points. So to us, the biggest thing is being able to invest in the field correctly so we can sustain a steady drilling program where you keep putting money into the data, because I believe we can see the improvement from the NAZ after not having shot seismic for nearly 8 years; we need to return to a routine schedule, likely every 3 years, when you shoot a NAZ—probably no need to redo OBN, but we'd revisit that once the velocity model is calibrated. So the genuine benefit here is that with a broader scope, you can invest appropriately on the front end to maintain that routine program we discussed, where the data lets you drill the best wells out there.
Alexa Petrick
analystOne thing I'd like to raise regarding GTA expenses. Our expectations were somewhat exceeded by the 3Q guidance, it seems; so I'd just like to hear what you see going into those figures. What's our view on 4Q? And is there any view on how that should be approached per BOE for 2026?
Andy Inglis
executiveSure. Neal, would you like to take that one?
Neal Shah
executiveRight; the three pieces that make up the GTA cost figures are, in a sense — yes, the FLNG toll, the FPSO lease, plus the field, basically ordinary field OpEx; and so during 2Q the FLNG toll ran somewhat higher, since we had certain bonus payments owed to Golar. On a per Mcf basis, that really gets normalized. On a recurring basis it sits at a little over $2. So the calculation is based on volume. And so it ought to stay fairly stable going into the back half of this year as well as into next year. Regarding the FPSO, that's roughly $15 million per quarter when it comes to the operating cost of that lease; and once more, I believe we're saying we're working on — we said we're working on refinancing that during the second half of this year. That remains on track. So you'll see the costs come through — the cost reduction come through once that's complete; and once more, that's roughly a little over 1/4 of the operating cost. And then the third one, as I said, is basically field OpEx, and that ought to be flat, closer to 3Q to 2Q, as we still rationalize some of those start-up and commissioning costs, and then you'll see a drop-off in that during the fourth quarter that once again, we anticipate we can hold into '25 — into '26 and then also looking at the alternative models. And so once again, I think on a per unit basis, you'll keep seeing both sides of the equation improve, both when it comes to increasing volume and costs coming down.
Alexa Petrick
analystAll right, that's useful. Then I simply wanted to ask — we understand that at this moment we're in a stretch of GTA start-up expenses while output is climbing; still, when we imagine reaching a stage with volumes that are more normalized and expenses declining, do you have any perspective on how we ought to consider a normalized free cash flow for the company?
Neal Shah
executiveYeah. Once more, my take on this hasn't really shifted, and that is to push the breakeven point for the company down into roughly the $50 to $55 per barrel kind of range. After that, again, the sensitivity — based on whichever oil price you happen to use — comes to roughly $100 million of free cash flow for each $5 sold beyond that level. So once more, I believe that's — I believe that's — once more, it won't come out neatly by quarter simply owing to when liftings occur and similar factors. Yet once more, I think approximately that pace is what we're aiming for, more or less, throughout the company on a steady basis.
Mark Wilson
analystI have a few questions, if I may. To start with GTA — when we look ahead toward Phase 1 plus, is the key item to watch for a gas sales agreement, whether that's with Senegal, with Mauritania, or with some third party? That's my first one. Then regarding Jubilee, there's been plenty of commentary and detail in the presentation, plus what I'd call some hindsight perspectives too. What I want to ask going forward, especially given this new seismic data, the processing of it, and the longer-term work still required, is whether you ought to remain the operator of that field. And is that something you're pursuing?
Andy Inglis
executiveAll right. Thanks, Mark. On your first point — yes, without a doubt. I believe I made it plain when we discussed this earlier that our aim is to collaborate with the partnership. And obviously, that partnership brings in the government, so as to identify the correct mix at this point between domestic gas and greater LNG sales, correct. So yes, certainly, one element of that entire optimization concerns how much gas they're able to take, what the anticipated ramp-up is, and consequently, how a gas sales contract would be structured. So yes, you framed it in terms of the Pacific. But as far as a deliverable goes, what we'd certainly require is, as we progress toward FID on that, we'd require clarity regarding how those gas sales would be shaped, correct. Yet once more, the government is unambiguous regarding the need. And in fact, the country's need is entirely unambiguous. An expanding economy must be capable of utilizing gas and displacing heavier — displacing pricier heavy fuel oil. And so there's a genuine economic benefit for every party involved in being able to achieve that. Thus I don't think that constitutes an obstacle, though it certainly must be tackled. As for your second point, well, we coordinate very closely with Tullow, as you're aware. In my view, it's a solid partnership. In my view, each side contributes its own particular strengths. Obviously, I think that being located — specifically, actually being located in the Gulf of America, I think the ability to capitalize on seismic, the processing, the acquisition methods and so forth is something we've managed to contribute to the partnership. And I think right now we're collaborating quite effectively with Tullow to draw on their expertise and ours in this area so as to make a difference. So the two companies see this no differently. We obviously have the rig secured. Ahead of us sit six wells. We're in agreement on which wells to choose and on what will be needed to move the field ahead. So in answer to what you asked, I think the crucial thing is that we're in agreement and that Kosmos genuinely contributes something to the effort, and plainly Tullow does as well.
Stella Cridge
analystThanks so much for all those updates. Could I ask something on the debt side? You said you're working on additional financing options. I'd love to hear about the various options that could be open to you, and how far out you're thinking when it comes to maturities — that would be great; and with the RBL, of course, there are certain requirements to handle debt a reasonable amount ahead of time. Could you speak to how confident you feel about satisfying some of those lending requirements? That would be good.
Neal Shah
executiveYes, I'll handle that. On the longer-dated maturities, again, I think when the maturity schedule was put in place previously, the aim was to leave a few maturities out there and then pay them down using cash flow the business produces; and again, recognizing that our goal isn't only to lower leverage, but to lower the absolute amount of debt, and so retiring the bonds with cash flow that gets generated makes sense; and so again, I think by its nature, that remains part of the plan, and the big variable there is really around oil prices. And so given the wobble we saw in the oil price, we felt it was prudent to take out the '26 maturity early through the refinancing. And that provides us a bit of room, together with the other proactive steps we've taken on the financing side, to clear a runway; and during that window, again, keep working in a way that maximizes cash flow for the business so we can keep bringing debt down. Beyond that, we'll keep looking at other proactive, attractive alternative sources of capital to see whether a cost of capital advantage can be gained when it comes to addressing the '27 and '28 maturities as well; they're trading at a discount, and if we can raise low-cost finance secured against our assets, there's a cost, there's a capital, there's a return to be earned there. And so the plan is to complete the Gulf facility this quarter and then keep evaluating those options. And part of that will hinge on where things trade. If they keep trading at a discount, an opportunity emerges for us to speed up net debt reduction through early retirement of those bonds; so again, I think it will be an ongoing process of evaluating that. And on your second question, regarding the RBL, again, we went through the test comfortably in March. Again, we use an RBL price deck to show that, from both existing liquidity and cash generated between now and the maturities, we have sufficient sources to cover the uses. To repeat, crude pricing has gone both directions, yet at the core we remain comfortably higher than the price decks used for our borrowing base. So we feel pretty good about the generation — the cash we can produce going forward, particularly when you add in the Gulf facility we brought in, we will have — what I expect is that we keep up solid coverage as we go through those tests routinely.
Bob Brackett
analystThis is about GTA, and you brought up a domestic gas piece. Could you remind me whether that's a pipeline going to St. Louis? Or does it involve some LNG being regasified and then, say, going to the car or something? What's the plan there?
Andy Inglis
executiveNo. I think — look, the main source, I believe, would really be pipeline gas, yes. So rather than LNG to <<inaudible>>, this would be a pipe gas answer, even though an LNG regas facility does exist in <<inaudible>>. That means you could add incremental volume through that route; but what we're examining today, Bob, I think is a more permanent solution.
Operator
operatorWith no additional questions coming in right now, I'd like to wrap up this call. I appreciate all of you for being with us today. At this point, feel free to hang up, and thank you for taking part.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Kosmos Energy Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Kosmos Energy Ltd. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Kosmos Energy Ltd. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.