Lloyds Metals and Energy Limited (512455) Earnings Call Transcript & Summary

October 25, 2024

BSE Limited IN Materials Metals and Mining earnings 42 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Q2 FY’25 earnings call of Lloyds Metals and Energy Limited, hosted by Equirus Securities. Just a reminder that every participant line will be in listen-only mode, and once the presentation wraps up, you’ll have a chance to ask questions. <<operator_script>>. Kindly note that this conference is being recorded. I’ll now hand things over to Mr. Siddharth Gadekar. Thank you, and over to you, Mr. Gadekar.

Siddharth Gadekar

analyst
#2

Good morning, everyone, and thanks for being with us today. Equirus is glad to host the 2Q FY’25 earnings conference call for Lloyd Metals and Energy. Joining us are Mr. Rajesh Gupta, Managing Director, and Mr. Riyaz Shaikh, our CFO. At this point, I’d like to hand things over to Mr. Rajesh Gupta to kick off the proceedings for the results call. Thank you.

Rajesh Gupta

executive
#3

Good morning, everyone—investors, analysts, and all those joining us on this call. We're grateful for the support and interest you continue to show in Lloyds Metals, and a special thank-you goes to Siddharth and the Equirus team for hosting today's call. We appreciate the chance to share with all of you our progress, our insights, and where the company stands in its process. I'm happy to say that our Q2 and H1 FY’25 results have been very satisfying and robust, showing strong performance across both operations and financial metrics, and they continue our aim of building a steel business that is cyclical-proof. On iron ore volume, we reached 5.37 million tons during the first half, and in sponge iron production we also did better at both plants, since two plants are now running compared with the prior year, substantially. The domestic iron ore market is still buoyant. There is some headwind, yet prices have stayed stable at around $100 for the 62% grade internationally. And in the Indian market, for the first time in many months, we've seen the price rise twice in the market itself. Beyond that, demand for high quality ore is considerable, which very positively shapes our outlook for the iron ore business.

Rajesh Gupta

executive
#4

On the project side, there's news we're glad to share: the 85 kilometer slurry pipeline has been laid successfully, finished in record time — likely among the quickest spans at roughly eight to nine months from when the project began. That pipeline is now waiting on the first pellet plant to be finished, and that plant will be done during this financial year in Konsari. The DRI plant in Ghugus is likewise moving along well, and upcoming projects — the second pellet plant plus the 1.2 wire rod mill in Konsari and Ghugus — are progressing too, comfortably inside schedule. As for the mine expansion, approvals have come through stage by stage, and during this fiscal year we expect to make the mine expansion announcement as well, in line with our original projections. With that, I'll pass the call to Riyaz, our CFO, who will take you through the quarterly numbers. Over to you, Riyaz.

Riyaz Shaikh

executive
#5

Thank you, Rajesh ji. Good morning to everyone participating in this earnings call. We appreciate your joining us today. Here's a brief overview of how our revenue performed in H1 FY’25. Revenue for H1 FY’25 increased 26% year-on-year, supported by greater sponge iron and iron ore volumes. Where iron ore is concerned, volumes as well as realization posted encouraging growth year-on-year. Sponge production likewise saw higher volumes and realizations year-on-year. The company received close to INR72 crores as IPS benefits from previous years, which contributed to overall performance, and for reporting purposes this forms part of our income — other income. Turning to EBITDA, EBITDA tracked revenue performance, rising 37% year-on-year in H1 FY’25. This robust performance was backed by high margins from both iron ore and sponge. On capital expenditure, we incurred capex of INR1,690 crores in FY’24 and INR1,714 crores in H1 FY’25. Now — now we'll also give you a brief snapshot on per ton metrics. Iron ore realization for quarter two FY’25, iron — the iron ore realization stood at INR5,516 per ton, up 19% year-on-year. And for H1 FY’25, it came to INR5,638, up 11% year-on-year. EBITDA per ton for quarter two FY’25 was INR1,668, up 17% year-on-year, and for H1 FY’25 it was INR1,782, up 21% year-on-year.

Riyaz Shaikh

executive
#6

For the DRI segment, the volumes were the following. Q2 FY’25 came in at 84,552 tons, while H1 FY’25 stood at 1,60,974 tons. Realizations held steady on both a year-on-year and a quarter-on-quarter basis. On the power segment, power put in a stable showing, with sales up 38% year-on-year in quarter two FY’25. Volumes for H1 FY’25 were also 4% higher year-on-year. Now for capex and project updates. As Rajesh ji mentioned, every one of our projects is moving ahead at breathtaking speed. A number of projects are running ahead of schedule, though we will keep our capex design as previously guided. The fundraising the company carried out has helped all the projects move quickly. Taking my cue from Rajesh ji, we expect a much better H2 FY’25. Thank you. That is everything from my end. Thank you for — thank you all for making the time to join this call. I look forward to your insights and questions during this call. Thank you. I'll hand it over to you, Siddharth.

Operator

operator
#7

Many thanks. At this point we'll open things up for questions. <<operator_script>> Everyone, please hold on briefly while we put the question queue together. Our first questioner is Parthiv Shah, calling from TS Builders Private Limited. The line is yours.

Parthiv Shah

analyst
#8

Thank you, sir, for taking my question after me. First off, congratulations on a really resilient set of numbers. Sir, I'd like to understand what the average iron ore prices were during the quarter, and also what the exit iron ore prices were?

Riyaz Shaikh

executive
#9

This quarter, the typical iron ore price came in at INR5,516 per ton.

Parthiv Shah

analyst
#10

And what would that be?

Riyaz Shaikh

executive
#11

For the half year, that comes to INR5,638.

Parthiv Shah

analyst
#12

Sir, did you raise the ore prices for the October deliveries?

Riyaz Shaikh

executive
#13

I’m not able to hear you properly.

Parthiv Shah

analyst
#14

Pardon me, but did you raise ore prices for October shipments? And sir, could you also give us a number, since NMDC has implemented 2 price increases during October?

Rajesh Gupta

executive
#15

Right, so we move with whatever the market is doing, and we've raised prices as well. Ours tend to be steadier — either increases or decreases happen more regularly. This year — or actually this month, as I said before — after many months, NMDC announced a price increase of 2 times, and we've matched it, coming in a little bit better than that.

Parthiv Shah

analyst
#16

And, sir, regarding your production volume guidance for ’24 — what are the estimates for FY’24?

Rajesh Gupta

executive
#17

For FY '24-'25, we're looking at roughly 13 million to 14 million tons, assuming the expansion is completed around February — mid-February, give or take.

Parthiv Shah

analyst
#18

Alright. And sir, just one final question. On earlier calls, you noted that once iron ore mining output rises, operating leverage tends to kick in, which would bring your costs down. Could you shed some light on where your cost per ton stands following this increased — increased mining?

Rajesh Gupta

executive
#19

Once enhanced mining is in place, the MDO cost ought to drop, settling somewhere around INR150 to INR200 per ton. Then, when beneficiation kicks in, that adds another INR152, and after that, volumes rise very substantially — that's the first point. Second, the slurry pipeline expense, once it's up and running — and it will come online together with the current plant — ought to cut our transport cost by roughly INR600 per ton as well.

Parthiv Shah

analyst
#20

That's great, sir. Thank you. Many thanks, sir, for taking my questions. Wishing you all the best.

Rajesh Gupta

executive
#21

I really appreciate it.

Operator

operator
#22

Thanks. Our next question comes from Vikash Singh at Phillip Capital. Vikash, please go ahead.

Vikash Singh

analyst
#23

Morning, sir — thanks for the chance to ask. Sir, I’m just trying to get a handle on what I’m seeing: sponge iron EBIT has risen quarter over quarter, even though we understand prices were somewhat weaker for most players in the Chattisgarh region. So — is there something extra in this sponge iron that we’re not seeing at the moment?

Rajesh Gupta

executive
#24

We received approval this year for the prior year's IPS industrial promotion scheme, and we recorded that as other income of roughly INR72 crores. So that's a one-time income that gets added to the bottom line?

Vikash Singh

analyst
#25

Got it, sir. About pellet trading — we launched that and it produced marginal losses this quarter. I just wanted to understand: if we're able to sell iron ore, why is this pellet trading taking place here at this point? Or —

Rajesh Gupta

executive
#26

We began trading pellets for three or four directional reasons. The main one is that this will serve as our seed marketing push for the higher-grade pellets, so we'll be entering the market very soon, which lets us export with stronger market knowledge once we're fully commercial. This quarter, as many people are aware, pellet margins, particularly on the export side, were very low. As a result, we've had little to no export, and the margin loss you're seeing is essentially a carryover from earlier quarters, some figures that were balanced, and some admission costs.

Vikash Singh

analyst
#27

Got it, sir. Sir, just one final question. What amount of capex have we already spent during the first half, and what capex remains for the second half that we are guiding, and also for FY’26?

Riyaz Shaikh

executive
#28

During the first half we posted roughly INR1,700 crores, and in the second half of this same financial year we ought to deliver a comparable figure.

Vikash Singh

analyst
#29

Got it, sir. And one last thing — if you could give us a sense of where the low-grade iron ore beneficiation project stands at the moment, when we expect to get started, and what the cost differential looks like in terms of the extra cost we had to incur for beneficiating iron ore?

Rajesh Gupta

executive
#30

On the beneficiation plant, a pilot plant has been started, and it was commissioned at the end of March 2024. That pilot plant is delivering very good results for us. The results we are getting are a little better than what had originally been expected. Through the beneficiation route, we are achieving 68% output. We have produced some quantities, and now we are going to carry out testing of these quantities through to pellet making as well as steel-making, so that we can understand the full benefit of the ore and/or whether any correction needs to be made in downstream production activities — that is number one. Number two, from the project angle, with the beneficiation pilot plant completed, the project's flow sheet is now final, and digital engineering is underway together with our Chinese contractor, Sinosteel. At the same time, the permissions needed for the forest land, etc., are being processed, and we remain on track for — as projected — the first plant to be ready by the end of ’27-’28. So we are very much in line within that.

Vikash Singh

analyst
#31

Got it, sir. Sir, regarding the extra cost you'd have to incur compared with the premium for 67% Fe grade — what does that premium stand at right now, and what additional cost are we expecting?

Rajesh Gupta

executive
#32

Beneficiation would run about INR800 to INR700 per ton, yet that gets more than outweighed by two things. First, this material would travel through a slurry pipeline to our steel plant or pellet plant facilities. Second, the royalty would drop since we are performing this beneficiation outside the mine area, and the royalty will be paid on lower-grade material. So we think the cost would be well under control versus the current situation, even with a higher-grade. On the premium for the higher-grade, pelletization, the market is offering a premium of roughly USD40 to USD50 internationally. And in steelmaking, we expect around a similar benefit — not similar, perhaps somewhat lesser benefits in steel making, we expect around a similar benefit. So overall it is a win-win situation.

Vikash Singh

analyst
#33

Yeah, it’s still far higher than what you’re actually spending.

Rajesh Gupta

executive
#34

Yes.

Vikash Singh

analyst
#35

Those are all the points I had, sir. I appreciate your taking my question, and I wish you the best going forward.

Rajesh Gupta

executive
#36

I appreciate that.

Operator

operator
#37

Thanks. <<operator_script>> Our following question comes from Nishant Bagrecha at Incred Finance. Your line is open — please proceed.

Nishant Bagrecha

analyst
#38

Yes, thanks for the chance to speak, sir, and I hope you can hear me clearly. I have a couple of questions about capex and also about your iron ore. So, sir, my first question is this: could you give us some highlights on the capex side and share the timelines for commissioning each plant over the next two to three years?

Riyaz Shaikh

executive
#39

On capex, as I said earlier for this first half, we've spent INR1,700 crores. That was well supported by the fundraise we also completed. So the projects are all progressing on time. We plan to do roughly INR35 crores — INR3,400 crores, INR3,500 crores of capex this year, and then over the following two years almost — not quite double what we're doing here. So we should — and that's how the capex plans stand. All our projects are running well — all our projects are running far, far ahead. As of today — as we said, but we just keep sticking with the same dates we've already stated. So on the capex side, all projects are nearly one, one and a half years ahead of schedule. That's what we're going with. So we should be finishing things very, very soon, but we should be coming out with things.

Nishant Bagrecha

analyst
#40

Okay. Sir, and like the pellet, like the first pellet —

Rajesh Gupta

executive
#41

Let me share a quick status update on the project, if I may. First, there's the 25 million ton dispatch from the mine, whether DSO or beneficiated. That's something we're hoping to wrap up by February 2025. As for beneficiation, as I said before, the original plan was to have it done by the end of financial year '27-'28. We're hoping to finish roughly six months ahead of that across all 3 phases. On the iron side — the iron ore grinding plant and the pipeline — as I mentioned earlier, the pipeline is already done. The 10 million ton grinding unit should be finished by March '25. For the pellet plant, the first one will be done by March '25 and the second by March '26. Our original guidance had this at about six months to a year later than that. Now, for the integrated steel plant, its first phase is the DRI plant. We're hoping to have that done by March '25 as well, along with part of the captive power plant in March '25 — one small portion in January '25. And the 1.2 million ton steel plant, including the BF, blast furnace, coke oven, and wire rod mill, should be done by September '26.

Nishant Bagrecha

analyst
#42

All right, thanks. And sir —

Rajesh Gupta

executive
#43

These figures are what we're projecting internally. What we presented to our Board — the initial forecast given to the Board was slightly higher than this, as we've said.

Nishant Bagrecha

analyst
#44

Alright, and I just wanted a bit more clarity regarding capex — we’ve discussed roughly INR32,000 crores of capex across the coming five to six years. So after the fundraise, is it fair to assume that all of that capex would be covered through internal accrual?

Riyaz Shaikh

executive
#45

Yes. As of today, we've all decided it should be — it should be — and it would be entirely — without debt. That's what we have — we should keep going. We had — we had a fundraise of peaking plus warrants. Warrants are still around 35%, which is what we got, and it will be getting 65% more. So we have — so this would be funding for the projects, nothing else. It would be without — we still maintain, it would be without debt.

Nishant Bagrecha

analyst
#46

Okay. Okay. And sir, just one more thing — what would it cost us to beneficiate this iron ore? Could you give us some idea of the all-inclusive cost for iron ore, covering mining, beneficiation, and royalty charges?

Rajesh Gupta

executive
#47

The total bundled cost for beneficiation, royalty, and transportation to wherever it gets consumed — whether that's a pellet facility or a steel plant — should stay roughly at today's level. All right, roughly INR2,500 to INR2,800 up to INR3,000.

Nishant Bagrecha

analyst
#48

Alright. Alright, certainly. Thanks, sir.

Operator

operator
#49

Thank you. Our following question comes from Rajesh Ravi, who is on the line from HDFC Securities. Kindly proceed.

Rajesh Ravi

analyst
#50

Hello, sir, good afternoon. Yes, for the bulk of the question, you're asking for the specifics on the timeline. I just wanted to confirm: this INR3,500 crores of capex would fall in FY'25, and then INR7,000 crores each in FY'26 and FY'27?

Rajesh Gupta

executive
#51

Correct.

Rajesh Ravi

analyst
#52

All right. So on your timeline, the bulk of this project should wrap up by FY ’26, and the BHQ beneficiation line you brought up would also finish by the end of FY’26 or early in FY’27. As for BHQ, its final phase is set to be done by September 2028.

Rajesh Gupta

executive
#53

Regarding ’28.

Rajesh Ravi

analyst
#54

Alright. Alright. So —

Rajesh Gupta

executive
#55

Apologies — that should have been September 2027.

Rajesh Ravi

analyst
#56

All right. So it will be finished in FY’28. So —

Rajesh Gupta

executive
#57

This is a 3 million ton steel plant. Work on acquiring the land has begun, and right now the project is being fully studied. That INR16,000 crores project — apart from land — would be invested once some of the major investments are completed.

Rajesh Ravi

analyst
#58

Right. So beyond this INR14,000 crores — 17,000 — INR18,000 crores, which you'd be spending across three years, this is a third leg, you know, and the remaining INR16,000 crores, INR17,000 crores is what you would be outlining for —

Rajesh Gupta

executive
#59

That encompasses that.

Rajesh Ravi

analyst
#60

Pardon me?

Rajesh Gupta

executive
#61

To begin with, if you'd like to separate things out, we have the DRI plant, the pellet plants at roughly that level, plus the pipeline and beneficiation, together around INR16,000 crores, and a 3 million ton steel plant at approximately INR16,000 crores — these are broad figures I'm giving you. So that INR16,000 crores of investment, aside from land and technology build-up, would get underway once most of those other projects are finished.

Rajesh Ravi

analyst
#62

All right, got it. Thank you very much, sir. I’ll rejoin the queue and come back. Thanks.

Operator

operator
#63

Thanks. Our next question comes from Manish Sehgal, an Individual Investor. Your line is open.

Manish Sehgal

analyst
#64

Hello, sir. I’d like a brief clarification about our relationship with Sunflag, since we have roughly INR6 crore shares sitting there, which could potentially be a supply overhang. Also, there was some oversupply agreement — could you clarify that a bit with them?

Riyaz Shaikh

executive
#65

As everyone is aware, Sunflag was an arbitration matter through which we had issued those OFCDs to them, and those were subsequently converted into equity shares. That amounts to roughly INR6 crores of equity shares, which they hold. And further, under that same order, we signed an ore purchase agreement in which we supply them nearly — their requirement comes to about 1 million tons per annum. So on a cost-plus basis, we have been carrying that out according to the arbitration order we hold. And it is entirely — those shares sit within, they constitute part of the public holding. and

Manish Sehgal

analyst
#66

Thanks. At least on the original list, the warrants were also issued to them. But in the end, of course, I think it didn’t come to fruition.

Riyaz Shaikh

executive
#67

Yeah, they weren't able to <<inaudible>> for it.

Manish Sehgal

analyst
#68

Right. So I guess my question is, is there any longer-term thinking regarding the relationship with that company as well, or does it just sit outside — being set outside?

Rajesh Gupta

executive
#69

When it comes to the long-term relationship, that is confined to iron ore supply, and for that we hold a long-term supply agreement with them.

Manish Sehgal

analyst
#70

All right, so that supply is able to enter the market in an effective way.

Rajesh Gupta

executive
#71

As far as the supply of iron ore goes.

Manish Sehgal

analyst
#72

No, no — I'm only saying the stock —

Rajesh Gupta

executive
#73

Regarding the share supply, that falls under the public shareholding, and the company isn't in a position to comment on it.

Manish Sehgal

analyst
#74

All right. Wonderful. Thanks. That’s all. Appreciate it.

Operator

operator
#75

Thanks. <<operator_script>> Our following question comes from Siddharth Gadekar at Equirus Securities Private Limited. You may proceed.

Siddharth Gadekar

analyst
#76

Hello, sir. Sir, could you put a number on the price increases we've implemented as of October 1st?

Rajesh Gupta

executive
#77

We've implemented one price increase of INR425, and the second comes in at roughly INR380 or INR400 in the fine sector. As for the lump sector, the first was INR425, that same figure. The second, I believe, is INR500 — I can't recall the second one off the top of my head at this moment. Close to INR500 crores.

Riyaz Shaikh

executive
#78

Just about INR500.

Rajesh Gupta

executive
#79

Yeah.

Siddharth Gadekar

analyst
#80

So on a broad basis, leaving aside the royalty — the extra royalty we might pay on that higher realization — basically all of it ought to drop through to our EBITDA in Q3 and Q4, assuming prices hold at their current levels, correct?

Rajesh Gupta

executive
#81

So apart from that royalty, everything else ought to drop straight through to the bottom line.

Siddharth Gadekar

analyst
#82

Alright. Sir, moving on to the second point about the IPS figure — you mentioned INR72 crores received for this year. How should we think about that going forward across the next 2, 3 years?

Rajesh Gupta

executive
#83

My sense is that this figure is pretty much the final number for the overhang left over from the earlier investment. Going forward, as soon as the pellet plant is up and running, we'll then kick off our new series of the IPS for Gadchiroli at 150%, and that would begin after the pellet plant and would likewise apply to the DRI plant in Gadchiroli. And in the same way for the DRI plant, the new plant, once we get going, after that the income would begin accruing.

Siddharth Gadekar

analyst
#84

So we should expect those benefits to begin coming through starting in FY’26 and not before?

Riyaz Shaikh

executive
#85

Right, right — once those projects are finished in FY’25 and we begin operating them in FY’25–’26, we should be in good shape.

Siddharth Gadekar

analyst
#86

Second, sir, regarding the slurry pipeline that's already been commissioned, when do we expect to actually begin using it?

Rajesh Gupta

executive
#87

We would — the iron ore grinding unit is being prepared, along with the pellet plant. Even once that grinding unit is running, we can begin delivering ground material over to the pellet plant site and attempt to ship a portion of the ground material out to certain customers. That said, the delay is more — is anticipated to land at roughly the same point as the pellet plant, around March ’25.

Siddharth Gadekar

analyst
#88

So the transportation cost at the pellet plant would come to roughly INR50. Is that a reasonable way to look at it?

Rajesh Gupta

executive
#89

Regarding the pellet plant?

Siddharth Gadekar

analyst
#90

Right.

Rajesh Gupta

executive
#91

Yeah, yes — roughly INR50.

Siddharth Gadekar

analyst
#92

All right, that’s all from me, sir. Thanks.

Operator

operator
#93

Thanks. Our next question comes from Ashutosh Somani with JM Financial. Please go ahead.

Ashutosh Somani

analyst
#94

Thank you for the question. Could you take a bit of time to discuss how you see domestic pricing going forward, both near term and longer term? On the near-term side, what are your customers telling you, and how much room do you see for additional price increases? And looking further out, with mines expiring in 2030, how do you view the pricing outlook there?

Rajesh Gupta

executive
#95

Thank you very much, Ashutosh ji, for that very good question. To address some of these points, we have commissioned BigMint and Questro <<inaudible>> to carry out a detailed market study. In the preliminary discussion, a few surprises have come up. For instance, I didn't know that many of the sale steel authority pipe mines are also expiring in 2030, at the same time as some of the other mines. So, continuing with the long-term picture, the steel market is expected to reach 300 million tons by 2030, '32, '33, with growth of roughly 7%, 8% per annum over the next four years or even more. Given how iron ore mining has increased over the past few years, we do not see it keeping pace. So we see a mismatch. Other beneficiation projects that are being considered will cover part of this mismatch, but we don't know the extent of that. That is the study BigMint would try to cover for us — in the next two, three months, we'll have that detailed report with us. On the short-term side, steel plant capacity in the country has been added by around 8% in the last quarter, with two mega blast furnaces commissioned, apart from many other units being added.

Rajesh Gupta

executive
#96

No mine announcements have come up, so that's likely one factor behind this mismatch and the price rise. India's market is still at a steep discount compared with international prices, and that stays part of the overall picture we take into account.

Ashutosh Somani

analyst
#97

Alright, that clears up what I asked, sir. Thanks.

Operator

operator
#98

Thanks. Our following question comes from Aryan Sharma at B&K Securities Limited. You have the floor.

Aryan Sharma

analyst
#99

Hello, sir, good afternoon. I just need one clarification. I realize you've already touched on this, but would you mind giving us a more detailed breakdown of your future costs — for instance, how much is earmarked for the beneficiation pipeline or the steel plant, and so on? Could you share some specifics on that?

Rajesh Gupta

executive
#100

That seems like it would be pretty detailed. Could we ask you to reach out to our investor relations team, and they'd be happy to bring you up to date on that?

Aryan Sharma

analyst
#101

Absolutely, sir, absolutely. That’s not an issue at all.

Rajesh Gupta

executive
#102

Thanks.

Operator

operator
#103

Is that what you were asking, Mr. Aryan?

Aryan Sharma

analyst
#104

Yeah, absolutely, definitely.

Operator

operator
#105

Thanks. We'll take the next question from Deep Mehta at Bank of India Mutual Fund. The line is yours — please go ahead.

Deep Mehta

analyst
#106

Hello, sir. Thanks for the chance to speak. I just need one clarification. We're going to receive our EC limits for expanding our mining capacity by the end of this year, is that right? Then

Riyaz Shaikh

executive
#107

As we wrap up this financial year.

Deep Mehta

analyst
#108

Right, so that wraps up the financial part — and then how long will it take to get production ramped up to the rated capacity?

Rajesh Gupta

executive
#109

Let me give some clarity on the EC. The mining plan has been approved, and the TOR has been approved as well. The public hearing will now take place after this Maharashtra elections. Following that, the EC would be issued by the Central Government, MOEA. So that's the process — what's done and what remains. We expect the timeline to land around February 15, 20-something. We have already processed up to 2 million, 2.5 million tons per month as well, so we hope the 25 million ton DSO sales on a monthly basis could happen more or less immediately, in line with the EC clearance. Our MBO Thriveni has already begun implementing machinery on this basis.

Deep Mehta

analyst
#110

So would it be fair to think that in FY’26, we might get to 20 million tons, or around that?

Riyaz Shaikh

executive
#111

25 million.

Rajesh Gupta

executive
#112

A more accurate figure would be 25 million.

Deep Mehta

analyst
#113

Understood, sir. The pellet plant will begin operations as well, correct? So how much will be sold to outside parties, and — . Yeah. Okay, sir. And the pellet plant ought to commence by — at the beginning of the next financial year, correct?

Rajesh Gupta

executive
#114

The first pellet plant, along with the initial DRI plant capacity enhancement, ought to be completed by the end of March ’25.

Riyaz Shaikh

executive
#115

The next financial year is when operations ought to begin.

Deep Mehta

analyst
#116

Understood, sir, that's completely clear. Nothing further from my side. Thanks.

Operator

operator
#117

Thanks. Our next question comes from Vikas Shah at RNM Capital Advisors. Vikas, please go ahead.

Vikas Shah

analyst
#118

Yes, sir. Thanks for the chance to speak, and congratulations on the strong results. So my first question concerns our pilot beneficiation plant — what yield have we achieved there? And is it fair to assume that yield will get better once beneficiation is carried out at a larger scale?

Rajesh Gupta

executive
#119

We ended up with a yield of roughly 38%. We had originally expected 35%, so 38% represents a modest gain over that. In my view, 38% is an optimal number — a bigger plant involves too many variables — so I'd say 38% will stay our internal assumption at —

Vikas Shah

analyst
#120

Okay. So when we discussed that 45 million tons of beneficiation, which would yield us approximately 15 million tons of saleable iron ore — could that figure go even higher as well?

Rajesh Gupta

executive
#121

It’ll be somewhat greater, though once again — we need to recognize that this marks the first instance of this plant being built in India. So we’re being extremely cautious when we announce the numbers, and — even so, the pilot plant is coming in at 38%.

Vikas Shah

analyst
#122

And then a final question from me. In any given month, how much mining have you actually carried out? I'm just trying to get a sense of how quickly the mine can be ramped up.

Rajesh Gupta

executive
#123

Pardon me, could you repeat that? I didn't catch your question.

Vikas Shah

analyst
#124

Sir, my question is this: what's the highest monthly mining figure we've ever achieved? I'm just trying to get a sense of how quickly we're able to ramp up the mines.

Rajesh Gupta

executive
#125

I believe roughly 2.2 million tons were completed near the start of this financial year.

Vikas Shah

analyst
#126

Right, sir. Got it. Thanks a lot for taking the question.

Rajesh Gupta

executive
#127

And there's another factor we need to keep in mind, which is the movement of logistics. That turns into a bottleneck. With a pipeline of 10 million tons coming online at the same time, that bottleneck gets reduced dramatically.

Vikas Shah

analyst
#128

Right. Right. Okay, sir. Thanks a lot for taking the question. Thank you.

Operator

operator
#129

Thanks. Our next question comes from Shrey Gandhi at CR Kothari Stock Broking. Go ahead, please. G

Shrey Gandhi

analyst
#130

Good afternoon, sir, and thanks for taking my question. I have just one small thing I'd like to ask about. Looking through the quarterly results, I noticed that mining revenue is down by nearly INR800 crores compared with the prior quarter. So could you shed a bit of light on that for us, and what should we expect in the coming —

Riyaz Shaikh

executive
#131

Could you speak up a bit? We can't hear you properly.

Shrey Gandhi

analyst
#132

Okay, can you hear me at this point?

Rajesh Gupta

executive
#133

Yeah.

Riyaz Shaikh

executive
#134

Correct.

Shrey Gandhi

analyst
#135

Mining revenue is down by nearly INR800 crores in quarter two versus the prior quarter. Could you shed some light on that, and what should we expect going forward?

Rajesh Gupta

executive
#136

Guidance for quarter two is always going to come in lower in any given year, since you have the rains, the monsoons, and demand and so on. Taking all of that together, it will always be a bit below quarter one or quarter four. That's just the nature of the animal.

Riyaz Shaikh

executive
#137

It's a seasonally weaker quarter, so. The second quarter always sees a similar type of quarter.

Rajesh Gupta

executive
#138

Still, this quarter improved relative to the same quarter a year earlier. And this half came in stronger than the comparable half last year.

Shrey Gandhi

analyst
#139

Right. So for the upcoming quarter, should we anticipate a comparable figure, or perhaps something above what we saw in quarter one?

Rajesh Gupta

executive
#140

As we said before, we would be having our — if you're talking about mining, those numbers will keep going on that same basis until we get the, and the total guidance would be roughly 13 million, 14 million tons for the year in mining, and for our DRI plant, around 330,000 tons a year will be the overall guidance.

Shrey Gandhi

analyst
#141

Alright. Thanks, and congratulations on those great numbers.

Rajesh Gupta

executive
#142

Thanks.

Operator

operator
#143

Thanks. Our next question comes from Bharat Bagrecha, an Individual Investor, on the line. Go right ahead.

Bharat Bagrecha

analyst
#144

Yeah, can you hear me, sir?

Rajesh Gupta

executive
#145

Yes, sir.

Bharat Bagrecha

analyst
#146

Yeah. If EC clearance comes through by year-end or in 2025, as you mentioned, could we see any incremental volume?

Rajesh Gupta

executive
#147

So the incremental volume — at the moment it's 10 million tons, going to 13 million tons — so that means 3 million tons would be the incremental volume over the last month and a half to two months.

Bharat Bagrecha

analyst
#148

Given that prices are higher today, how can we boost profitability at current levels?

Rajesh Gupta

executive
#149

Could you say that again?

Bharat Bagrecha

analyst
#150

Because the number of prices is higher today?

Rajesh Gupta

executive
#151

The beginning of your question isn’t coming through for us. It seems like there may be an issue with your line.

Bharat Bagrecha

analyst
#152

What does profitability look like at today’s iron ore price levels?

Rajesh Gupta

executive
#153

I’d let the very capable analysts handle that analysis. The group has close to 100 people, so I’m confident plenty of them will be working through a great deal of that analysis.

Bharat Bagrecha

analyst
#154

Thanks.

Operator

operator
#155

Thanks. <<operator_script>> Our following question comes from Amit Agicha with HG Hawa and Company. Go ahead, please.

Amit Agicha

analyst
#156

Good afternoon, sir, and thanks for the chance to speak. Can you hear me clearly and is the sound good enough?

Riyaz Shaikh

executive
#157

Correct.

Rajesh Gupta

executive
#158

Yeah, yeah.

Amit Agicha

analyst
#159

Could you go into more detail about the ways the slurry pipeline helps lower the carbon footprint and improve operational efficiency?

Rajesh Gupta

executive
#160

As far as carbon efficiency goes, we spend roughly — well, I don't have those numbers on hand, but we —

Amit Agicha

analyst
#161

Could we get those numbers?

Rajesh Gupta

executive
#162

We don’t have that number. Truck movement runs on diesel, and this comes through pumped power, while the slurry brings it down. I’ll look into that. That’s a really interesting question. Our figures are in rupees, not in carbon footprint. We will assess that. Beyond that, another thing we’re doing to cut carbon footprint is pelletization. We are working — we’re going to work with LNG, not with oil. So that will lower that carbon footprint in a very big way. Local transport to the siding and to nearby customers would run on LNG trucks. That’s as far as transport goes. Inside the mine, much of the equipment by the year 2025 would run on electrical equipment, again cutting carbon footprint dramatically. So all of that together brings the footprint down. By the next quarter, I think we’d be able to give a more precise — not precise, but more elaborate answer to your question, my friend.

Amit Agicha

analyst
#163

Thanks a lot — that was really useful. And for the final question: do you have any plans for diversification, or investments in technology, that are meant to improve operational efficiency?

Rajesh Gupta

executive
#164

That covers it. As part of the plans we're pursuing, we keep working continuously on becoming more efficient, strengthening marketability, bringing costs down, and similar areas. So that process is ongoing. Beyond that, there isn't any particular item we're focused on at the moment. Regarding the steel plant we've been discussing — the 3 million ton steel plant — we're evaluating the newest technologies available in the blast furnace route and so on, so we can be sure those technologies are thoroughly current. As a result, whichever plants we purchase are state-of-the-art and up-to-date facilities.

Amit Agicha

analyst
#165

Thanks a lot. That really was quite useful. Thanks, and I wish you the very best.

Rajesh Gupta

executive
#166

Thank you, sir.

Operator

operator
#167

Thanks. Since nobody has any more questions, we'd like to pass the conference over to the management team at Lloyds Metal and Energy Limited so they can offer their closing remarks.

Rajesh Gupta

executive
#168

I want to express my appreciation to everyone for joining in so actively and for the really engaging questions. Happy Diwali to each of you, and I wish you all a joyful and prosperous New Year for investing. Thank you.

Operator

operator
#169

<<operator_signoff>>.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Lloyds Metals and Energy Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Lloyds Metals and Energy Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Lloyds Metals and Energy Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.