Lloyds Metals and Energy Limited (LLOYDSME.NS) Q3 FY2026 Earnings Call Transcript & Summary
February 4, 2026
Earnings Call Speaker Segments
Operator
OperatorLadies and gentlemen, good day, and welcome to Lloyds Metals and Energy Limited Q3 FY '26 Earnings Conference Call hosted by Anand Rathi Share and Stock Brokers Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Parthiv Jhonsa from Anand Rathi Share and Stock Brokers Limited. Thank you, and over to you.
Parthiv Jhonsa
AttendeesThank you, Ikra. Good evening, everyone, and thank you for joining us today. We at Anand Rathi are pleased to host Lloyds Metal and Energy Limited Q3 and 9 Months FY '26 Earnings Conference Call. We have with us today from the management, Mr. Rajesh Gupta sir, Managing Director; Mr. Riyaz Shaikh, CFO; and Mr. Chintan Mehta, CIO. Without further ado, I would now like to invite Mr. Rajesh Gupta sir to initiate the proceedings for the call, which would then be followed by question-and-answer session. Thank you, and over to you, sir
Rajesh Gupta
ExecutivesGood evening, everyone, and a warm welcome to all the participants. Thank you, Parthiv and Anand Rathi for hosting this call. We truly appreciate the interest and time from all our investors, analysts and stakeholders. Let me start with the headline numbers before we go to the operative narrative, where we have got the highest -- INR 11,000 crores we have crossed in consolidated revenue, which is a very, very significant milestone for us. And as you might have seen the presentation, the EBITDA and the PAT match that. I would like to express that this current top line -- current bottom line was our top line around 2 to 3 years back, and we hope to achieve the same in the future as well. I will take a small deviation from my usual remarks today on the pellet side and start with copper. Copper, as we know, is a new gold for the new age economy. Structurally, the world is entering a phase where copper demand will remain strong for decades while supply will remain constrained. And this is where we believe our entry timing is right. The copper project in the DRC, Democratic Republic of Congo, in the Katanga area will mark a very important milestone in our history. When we expanded our operations in Gadchiroli, the region was considered difficult and impossible, and we [ ushered ] that phase in execution where we have now learned a lot. The market as well as the local communities have appreciated the efforts that we have put in, in developing the economy and therefore our business. And we generally believe that over time, the same narrative will emerge for Congo, Katanga as well as other parts of the world. For this, I would also like to take a moment to acknowledge the leader of the Congo team, [ Mr. Surya Narayan ], who is the leader and the Director of the Congo team. Projects of this nature require not just capital, but deep operational leadership, which we already have with Mr. Surya as well as other core colleagues from other parts of the operations. Now let me come back to the pellet operations. Execution continues at a breathtaking space (sic) [ pace ]. Multiple projects are progressing simultaneously, and most importantly, on schedule. The second pellet plant is now commissioned -- expected to be commissioned in Q2 FY '27 and the 1.2 million tonne wire rod mill by Q4 FY '27. While operating our pellet plant, we are seeing opportunity to unlock talent -- latent capacity. And optimizing similarly for our pellet plant #2, we will increase the capacities of both these plants by 10 million tonnes -- to 10 million tonnes from earlier 8 million tonnes. These projects will improve our value-added mix and enhance margin stability. Logistics remains one of our most critical pillars of cost leadership. Our first 85-kilometer pipeline is running smoothly and has led us to plan our second study pipeline from Hedri to Chandrapur. The key change is the introduction of a stockyard in Chandrapur to move beneficiary ore also through the pipeline route. This will give us advantage for direct access to railways near Chandrapur and also obviously a saving of INR 850 for the sale material and around further INR 250 -- that is around INR 1,250 will be for the material that will be used for the pellet plant in Chandrapur. We are by this removing the inefficiency of the mine which doesn't have a rail head. Details of this plan are covered in the presentation. Coming to operational performance. Iron ore dispatches have grown meaningfully, supported by the slurry pipeline, which is working very well, very strong operational discipline and strong execution. Pellet plants we have achieved within 3, 4 months of commissioning optimal utilization and are now looking at debottlenecking it. Our DRI plants, both of which are commissioned, and the power plants are operating at optimized levels and contributing steadily in a very difficult environment of DRI. On the demand side, both iron ore and pellets have witnessed strong demand in the domestic as well as international markets and product has been very, very well accepted. We expect the buoyancy of the market to continue, supported by infrastructure, steel demand and, of course, the economic growth in the country. Let me spend a few moments of time on the MoU with Tata Steel. We have signed a nonbinding MoU with Tata for multiple collaboration to strengthen the ecosystem in Gadchiroli area in the Eastern Coast -- Eastern belt of India, and, of course, we have also signed a shareholder agreement for BRPL pellet plant along with a conversion pellet agreement, which gives us a steady cash flow in BRPL. To summarize, we remain very buoyant on our pellet operations. Iron ore volumes are supposed -- are expected in line with the EC to grow in Q4 as well as FY '27 and value addition plans continue and FY '27 will mark our formal entry into steelmaking. And lastly, but not the least, copper will act as a strong growth engine over the medium term. Now I hand over the call to Riyazji and [ Naraidiji ], who will take you through the detailed figures.
Riyaz Shaikh
ExecutivesThank you, Rajeshji. Good evening, everyone. I'll start with a quote that we strongly relate to at Lloyd Metals. As Satya Nadella says, growth is not just about size, it's about mindset, learning and execution. This philosophy resonates very well with what we are seeing in our business today, scaling responsibly, improving structurally and executing with discipline. With that context, I will take you through the standalone financial and operating performance for quarter 3 and the 9 months ended FY '26, focusing on numbers, margins and CapEx. This has been a very strong quarter and 9-month period for us on a standalone basis. In fact, quarter 3 and 9 months FY '26 are the best we have seen so far in terms of revenue, profitability and margins. Quarter 3 FY '26 standalone, the total income came in at about INR 3,875 crores, up 129% year-on-year. EBITDA was INR 1,317 crores, which is a 137% year-on-year increase. PAT stood at INR 889 crores, up 128% year-on-year. For the 9 months FY '26 standalone, total income was INR 8,859 crores, up 59% year-on-year. EBITDA came in at INR 2,994 crores, a 74% year-on-year growth. PAT was INR 2,129 crores, up 71% year-on-year. With regards to the margins, margins have remained very healthy and stable. Quarter 3 EBITDA margin was about 34%. 9-month EBITDA margin stood at roughly 33.8%, which is almost 280 basis points higher year-on-year. This improvement is not one-off. It's structural and is coming from higher share of value-added products, especially pellets, benefit of the slurry pipeline, which has started flowing into the P&L, better utilization across mining, pellet and DRI [ operations ]. Operational highlights. On the operational side, iron ore production was 5.49 million tonnes in quarter 3 and 12.87 million tonnes for 9 months FY '26. Dispatches were largely in line, which is 4.1 million tonnes in quarter 3 and 10.1 million tonnes for the 9 months. EBITDA stood at INR 1,825 per tonne in quarter 3 and INR 1,951 per tonne for 9 months FY '26. Pellets have been a key positive this year. Pellets production was 1.14 million tonnes in quarter 3 and 1.95 million tonnes in 9 months FY '26. What's encouraging is that this run rate was achieved within just 3 to 4 months of commissioning. Realization in quarter 3 was about INR 10,289 per tonne and whereas EBITDA per tonne was roughly INR 4,535, supported by captive iron ore, slurry-based evacuation and strong demand -- domestic demand. DRI volumes were around 0.12 million tonnes in quarter 3 and 0.29 million tonnes for the 9 months. DRI expansion was commissioned during quarter 3 and operations are now stabilizing. Value-added mix. Value-added products are now forming a meaningful part of our revenue mix. For 9 months FY '26, value-added products accounted for roughly 35% of standalone revenues. This mix shift is central to improving margin stability, reducing volatility and enhancing overall return metrics. Now coming to the CapEx update on a standalone basis. Let me quickly touch upon CapEx. The standalone CapEx during 9 months FY '26 was about INR 4,236 crores. This was largely towards pellet plant 2 DRI expansion, the 1.2 million tonne steel plant at Chandrapur, the first module of the beneficiation plant. Importantly, CapEx execution is on track and within approved budgets. Touching upon the balance sheet and cash flow. Despite the high level of CapEx, the balance sheet remains comfortable. Strong EBITDA generation has supported internal accrual-led funding and controlled leverage. Working capital continues to be well managed, helped by faster dispatch cycles and healthy demand conditions. Looking ahead, the outlook looking ahead, iron ore volume should remain strong in quarter 4 FY '26. We aim to exit FY '26 with 20-plus million tonnes volume on ore. Pellet operation will continue to run at optimal utilization. DRI contribution will improve further as operations stabilize. Overall, we expect margins to remain robust, supported by a value-added mix and ongoing logistic efficiencies. To sum up, standalone performance in quarter 3 and 9 months FY '26 has been very strong. Margins are holding up well on a structural basis. CapEx execution remains disciplined. With that, I'll hand it to [ Naraidiji ] for Thriveni performance.
Unknown Executive
ExecutivesThank you, Rajeshji and Riyazji. Good evening, everyone. Trhiveni growth has always been about disciplined execution, consistency and doing the fundamentals right day in and day out. Let me take through -- take you through the Thriveni's performance for Q3 and the 9 months ending FY '26. From a financial perspective, this has been a strong and improving period for Thriveni. In Q3 FY '26, the total income stood at about INR 2,200 crores with EBITDA of roughly INR 550 crores, translating into an EBITDA margin of close to 25%. For the 9 months, revenue were around INR 5,480 crores with EBITDA of approximately INR 1,080 crores and margin of about 20%. The improvement in margin reflects better operating leverage, higher equipment utilization and continued focus on cost discipline across various projects. Operationally, our coal mining operations continue to perform exceptionally well. At PB West, we achieved the highest distinction of a 5-star rating from the Ministry of Coal, ranking #1 among more than 380 opencast mines in the country. December saw a record monthly coal production of 17.7 lakh tonnes and the in-pit crushing and conveying system commissioned earlier has already handled close to 15 lakh tonnes, significantly improving the efficiency. PB North West, our another coal block, has also commenced production and dispatches, and we expect this project to scale meaningfully over the next few quarters. Odisha remains a key growth driver for us. Several mines have seen capacity enhancements. And overall, Odisha volumes are expected to grow by nearly 40% year-on-year in FY '27. This scale-up is being driven by faster statutory clearances, improved infrastructure and focused execution at site. In Gadchiroli, which many of you are familiar with, the environmental clearance has been increased from 10 million tonnes to 55 million tonnes, including BHQ. Alongside scale, we continue to push sustainability-led initiatives such as electrification of mining equipment and LNG hybrid deployment, which are helping us optimize costs while reducing our carbon footprint. We have commenced MDO and exploration activities at Geomysore India Private Limited from January 26. This is a gold mine. This asset provides long-term visibility with a targeted EBITDA of --- contribution of around INR 60 crores in FY '27 and we see potential upside as exploration progresses. Internationally, we are rationalizing lower-margin operations in Indonesia and redeploying our equipment to higher return opportunities. Overall, Thriveni's focus remains very clear: scale responsibly, execute efficiently and protect margins through productivity and cost optimization. The pipeline for FY '27 looks very strong, and we are confident of sustaining both growth and profitability. With that, I'll hand it over to Mr. Parthiv, who can open the floor for question and answer. Thank you.
Operator
Operator[Operator Instructions] The first question is from the line of Amit Dixit from GS Financial.
Amit Dixit
AnalystsCongratulations for a very good set of numbers. A couple of questions from my side. The first one is on the MoU that we have with Tata Steel. So just wanted to understand the various facets of this MoU. While you have explained in your prepared remarks, Tata Steel also held a con call in which they explained a few things. But just wondering that in mining, when we are so strong in this region, why do we need someone else? I mean it might be Tata Steel, of course, no doubt they are experts. But what expertise we are actually looking to get from Tata Steel? And is there something that goes beyond mining, let us say, into steel where we might get some kind of consultation from them? And if there is any -- is there any scope of having a long-term iron ore supply agreement to them? I mean, just wanted to explore these points.
Rajesh Gupta
ExecutivesThe MoU with Tata has 2 parts. One is the BRPL SHA and the BRPL ownership and conversion contract, which is executed. The second future exploration of opportunities, there are 2 areas that we are looking at. One is the eastern area of the country where, for example, Tata may have some assets where we can act as a contractor, as an MDO contractor maybe, or where they may need a pipeline to a certain area where we have some expertise, which Tata has not yet developed, or maybe we have some land in Paradip, which we can try to utilize in a better way. A lot of opportunities are being looked at in the Eastern belt. In the Gadchiroli area, we are looking at whether we can bid jointly or opportunities come up with government trending system where we can get ore at a relatively better pricing, better commercials. This would not be from the existing mine. It will be for future expansions. We are always open to partnerships because that is a way to develop fast, and Tata is one of the finest companies in the country -- not one of the -- I would call them the finest company in the country. So definitely, it's an honor to be partnered with them.
Amit Dixit
AnalystsOkay. Okay. Great. The second question is essentially on the copper. So I mean, it is indicated in the presentation that there are certain mines also associated with it. First of all, Congo is not exactly the best place to work, and then mining, I know several companies who have failed because of various reasons. So what is it that we see in Congo? And are these mines yet operational or at what stage of exploration they are? You have indicated some numbers, but these numbers seem to be more for the processing side. I just wanted to understand the backward integration part of it a little bit more. And if you can also mention the grade of copper that you expect over there?
Rajesh Gupta
ExecutivesWe are looking at Democratic Republic of Congo, Katanga area. This area by itself and DRC by itself is the second largest producer of copper in the world at the moment after Chile, number one. Number two, the copper majors, Glencore, et cetera, are all based in copper in this area. There are 60 to 80 companies, small and big, operating, and the infrastructure, the systems are there in place to take care of very many things. The political stability in this country is much better, and particularly this part is the southern part of the area and it's a very economically based country and area, not politically worrying. Not zero politically worry. There will be some worries, obviously, but it is well, well sustained. The mining leases that we have are 16 or 18 leases. I'm forgetting the number right now.
Riyaz Shaikh
Executives18.
Rajesh Gupta
Executives18 leases over 100 square...
Riyaz Shaikh
Executives16.
Rajesh Gupta
ExecutivesSorry, 16 leases over 100 square kilometers. Exploration is going on. We already found copper at good depths. 1.5% to 2% copper is also available, 0.8% is also available. Oxides are available. And the 10,000 to 12,000 tonnes is a direct output of the plant that we are talking. We can -- for that -- for the cathode plant, leaching and cathode plant, we could take the ore from our own mines, which we've already started accumulating, as well as from bought out mines. At the end of the day, it would be an integrated operation of around 30,000 tonnes per annum, which may take 2, 3 years to achieve. We believe that in the next year, financial year '27, 10,000 tonnes of operations would be achieved at a fairly integrated mix of ore.
Amit Dixit
AnalystsGreat, sir. Just if I can squeeze one more. Just wanted to get the status of BHQ plant.
Rajesh Gupta
ExecutivesBHQ plant, the land is under -- land procurement is under control and the engineering is complete, the ordering is complete. We have ordered the equipment from the best possible companies in the world to take care of any exigencies. Because it's a newer technology in India, so we've not taken any chances on the technology part of it. We have worked with the Chinese and now with [indiscernible] also. And we are hopeful of getting it commissioned by December '27 or so. Latest by that time and -- yes.
Operator
Operator[Operator Instructions] The next question is from the line of Jashandeep Singh Chadha from Nomura.
Jashandeep Singh Chadha
AnalystsCongratulations, sir, on a great set of numbers. Sir, my first set of questions are around iron ore. Firstly, on your guidance, FY '26 guidance, it is close to 20 million to 22 million tonnes. If I assume that you will be doing 3 million tonnes of pellets also, that is close to 4.5 million, 5 million tonnes of iron ore, 10 million tonnes of iron ore you have still done, which means close to 6 million to 8 million tonnes of volumes you are forecasting for fourth quarter of FY '26. Lloyds has not done any time such volumes in 1 quarter. Just wanted to understand what is the confidence behind giving such guidance? And what are the challenges that the company can face in meeting those guidance? My first question is this, sir.
Rajesh Gupta
ExecutivesThe volume in this year -- in this month, that is January, is around 2.4 million tonnes -- 2.5 million tonnes, which crosses the 26 million tonne overall and definitely we'll achieve the 20, 21 million tonne target for the year. We have to appreciate one thing, that, at the moment, we have to -- the problem is not in the marketing of it. The problem is not in the mining of it. The area that we are right now focusing on solving the problems are on the logistics side. Right now, we are moving around -- on an annualized basis around 4.5 million tonnes of ore by the pipeline, and come by April, we'll be able to do 9 million tonnes. And the second plant would be -- come by June, the second, sorry, pipeline -- the pipeline would be ready to take the second pellet plant input. So 9 million tonne would move out of that. And right now, we are producing around -- transporting by truck around 70%, 60% more than the overall requirement. It is a tough job. We are very confident of achieving 21. That's why we gave a guidance of 20 million to 22 million tonnes for the year. We believe that quarter guidances and directions are lesser -- quarter guidances are lesser important for a company of our nature and our overall direction of decadal growth or at least 3-year growth is what we are -- what I'm focusing on. Operational efficiencies are looked at, at every level. And you can see that in the increase in the revenue, in the margin also. 280 basis points is a factor of whatever Riyaz said, plus a cost control system also. So everything has been factored in when we have made the guidance.
Jashandeep Singh Chadha
AnalystsUnderstood, sir. My second question is also around iron ore only. Sir, we have seen that the benchmark domestic iron ore prices have come down in this quarter. With that regard, I just wanted to understand how much the realization has been impacted for Lloyds and how much margin compression, EBITDA compression we can see in the fourth quarter? And then related to iron ore only, I just wanted to understand what is the CapEx for the slurry pipeline? And can you also -- for our analysis, can you also tell us how does it compare with the peers?
Rajesh Gupta
ExecutivesCompared to the...
Jashandeep Singh Chadha
AnalystsPeers, sir. Your peers.
Unknown Executive
ExecutivesYes. So another company.
Rajesh Gupta
ExecutivesOkay. The benchmark has come down and so has the basis of benchmark come down from 62% to 61%. So if you currently look at benchmark price of $103, it amounts to around $108, which is around $3, $4 higher than the same amount last year -- same period last year. So I think the benchmark has not really come down. It's gone up.
Jashandeep Singh Chadha
AnalystsSir, domestic -- I was talking about domestic iron ore.
Rajesh Gupta
ExecutivesDomestic iron ore, I don't know by what stretch you're saying it's come down in the -- some of my competition has increased the prices over the last 2 months, both the months. The auctions that have come out have been very strong. Steel benchmark is very strong. So at the moment, I do not see any indication of the steel industry or iron ore industry being soft in India at all, at the moment. Maybe 1 month back, 1.5 months back, it was different, but that's part of the cyclical nature of the business.
Jashandeep Singh Chadha
AnalystsAnd sir, on slurry pipeline, the CapEx and...
Operator
OperatorSorry to interrupt you, Mr. Singh. Can you rejoin the queue for more questions?
Jashandeep Singh Chadha
AnalystsMa'am, it's part of my question only I've asked you earlier.
Riyaz Shaikh
ExecutivesOn the slurry pipeline, as you might be knowing, we had planned for another 5 million tonnes of a slurry pipeline connecting the mines to the Chandrapur plant in -- the Ghughus plant in Chandrapur. Now what we are now doing is we would -- we've increased the capacity of that. We will be now making it as a 16 million tonne slurry pipeline so that we cover the entire 26 million tonnes of dispatches through a slurry pipeline. So it will be -- one will be -- one is existing, which is there as a 10 million tonne. This is a second slurry pipeline, which will be a 16 million tonne slurry pipeline, which will be taking us more to the market as well as to our Chandrapur plant. And the total cost for this -- we also, in fact, have a second phase on it, the slurry pipeline, which will be connecting to more of the markets as well as the ports. So the total cost envisaged is around INR 8,000 crores on this particular project. But we will be doing it on phase wises. So the first phase up to Chandrapur will be around INR 2,000 crores, INR 2,500 crores.
Operator
Operator[Operator Instructions] The next question is from the line of Prateek Singh from IIFL Capital.
Prateek Singh
AnalystsCongrats on a good set of numbers. And the first question, Guptaji, is largely on BHQ project. Given the fact that bulk of our volumes going ahead would be coming from BHQ, how confident are we in maintaining the fact that the cost of production of BHQ would be similar to our current cost of production given that we'll have to mine more material, there will be beneficiation cost also? I understand that we save a bit on royalty. But do you think there is any risk of operating cost overrun in BHQ going ahead?
Rajesh Gupta
ExecutivesBHQ, the royalty saving based on the existing proposals of the government as well as -- existing policies as well as future proposals of the government would -- the royalty savings would offset the cost of processing the BHQ2 ore. Please also factor in that the grade of ore from 62% to 64% would come to 66%, 67%, and that gets a very higher premium. So the cost of ore versus the selling price or the usability of ore becomes much better. The BHQ beneficiation or beneficiation of ore in general has been accepted by the government as a very, very important aspect of the national policy of steel, and therefore, we expect a lot of support on the royalty front from that. Does that answer your question?
Prateek Singh
AnalystsYes. So just going into a bit more detail here, sir. So royalty, if our current realizations are, let's say, INR 6,000 and royalty all in, let's say, 20%, so INR 1,200-odd royalty. And even if royalty on BHQ is, let's say, 0, so INR 1,200 per tonne of saving plus, let's say, some premium because of higher...
Rajesh Gupta
ExecutivesRoyalty is not 0. Royalty will be around -- from INR 1,200 will come down to around INR 200. And processing of the ore would involve some power, which is the biggest cost. We are working on getting -- greening our power also as well as other operations. And that's where -- that's why I said we are using the best technology to ensure that the systems are very, very strong and uptime and efficiency of the plant is the best. The premium that we would get on this output of product if I were to sell all the ore would be around INR 1,400 a tonne also. You have to also factor that in.
Prateek Singh
AnalystsUnderstood, sir. Understood. And the second question is largely on the slurry pipeline, 85 kilometers...
Operator
OperatorSorry to interrupt you, Mr. Singh. As we have a long queue, can you please rejoin for a follow-up question?
Prateek Singh
AnalystsYes. Sure.
Operator
OperatorThe next question is from the line of Vikas Singh from ICICI Securities.
Vikash Singh
AnalystsSir, my first question pertains to our copper mine. As you stated that it was an operational mine. So just wanted to understand, had the existing promoters was facing any difficulty in terms of producing and ramping up of the mine and that's why we have got the chance to get some stake there? And secondly, on the management bandwidth, we are doing too many things simultaneously. So just wanted to understand the management bandwidth in terms of managing and looking after the timely completion of all these projects. How should we look at it?
Rajesh Gupta
ExecutivesNumber one, on the existing promoter, they are more involved in commercial activities and general traders in the country. They have got this mine as an opportunity -- mine and the copper plant has been set up by them as well. The copper plant is running -- is set up but not running. They lost the bandwidth to run it, and that's where we come in. We have -- Mr. Prabhakaran and the erstwhile Thriveni had been looking at DRC for a long period, and that's how the opportunity comes to us of investing in that. There have been no problems. Again, I repeat there are around 70, 80 plants, including Glencore and Ivanhoe and the best companies in the world running copper mines there and copper operations. So that's not a worry that we have -- we foresee in a very serious way. In terms of operational bandwidth, we have scaled up -- first, let me give you a little bit of -- we scaled up from around INR 500 crores to INR 10,000 crores in this year, maybe INR 13,000 crores over 4 years. We have proved to the market, we have proved to ourselves, we have proved to our team, and our team has proved to us that we can take care of growth in a sustainable, sensible, economical and business-like manner. And we continue to do that, number one. Number two, as far as Congo particularly is concerned, one of the Promoter Directors would be involved full time there, apart from a very, very professional team who has been involved in mining operations, and we have hired experts on copper side also, on the copper manufacturing side also. The technicality of the leaching process and the cathode process is not a very -- is not a super technical or a super new invention, and that can be taken care of by the team that we have ensured, are already on the job at the site as we speak. I think that should -- we are confident of sustaining this growth in a very sensible way.
Vikash Singh
AnalystsNoted, sir. Sir, second question pertains to Thriveni. While the top line growth was...
Operator
OperatorMr. Singh, sorry to interrupt you. As we have a very long queue, can you please rejoin for a follow up question.
Vikash Singh
AnalystsI will rejoin.
Operator
OperatorThe next question is from the line of Vedant Sarda from Nirmal Bang Securities Private Limited.
Vedant Sarda
AnalystsCongratulations on the great set of numbers. Sir, my question is, we are hearing that government is taking various measures to ensure availability of iron ore. Like they have to bring our iron products prices at par with international markets, so we can compete and export iron goods. So can you comment on the pricing outlook going forward and how to look at this?
Rajesh Gupta
ExecutivesSee, if you look at iron ore in India, the growth is around 5%, 6%. The steel growth is around 8%, 9% even now. If you look at 5 years CAGR, it is 5%, 6% for iron ore and around 9%, 10% for iron ore (sic) [ steel ]. So there has been a continuous shrinkage of the supply -- extra supply, and therefore, exports either in the form of low-grade iron ore or in the form of pellets have reduced. So the overall supply-demand gap is very, very favorable in supply of iron ore, number one. Number two, as we go forward, over the next 5 years, around 1/3 of the capacity which is premium free will go into auction over the next 5 years and that will add to the -- not the lesser supply, but definitely to a higher cost mechanism for the industry. So we are pretty confident of our commercial part of selling iron ore. And over a period, our value-added business will be quite a lot, and we can, therefore, be well equalized in both iron ore as well as value-added products like pellets or steel as well in the future.
Operator
Operator[Operator Instructions] The next question is from the line of Harsh Shah from Seven Rivers Holding.
Harsh Shah
AnalystsA heartiest appreciation for excellent execution over the last 3 years. Sir, my first question is on the MoU with Tata Steel, given that it could end up being quite an extensive agreement eventually. So will it in any way affect or change our plans for the integrated steel plant, which would be our INR 16,000 crore CapEx plan?
Rajesh Gupta
ExecutivesOur future steel plant in Gadchiroli is being looked at internally, nothing to do with the Tata MoU. Any Tata MoU -- any Tata setup together would be for a different plant than that.
Harsh Shah
AnalystsOkay. And sir, one bookkeeping question. What would be the warrants outstanding now as of today?
Rajesh Gupta
ExecutivesWhat is the...
Harsh Shah
AnalystsOutstanding warrants as of today.
Unknown Executive
ExecutivesOutstanding warrants.
Rajesh Gupta
ExecutivesWe should be getting around INR 900 crores from it. I'll give you the number, but the value around INR 900 crores is pending, which would be coming up in the month of March. That is something - the time between 15th or 18th March that will happen. So we should be getting it.
Harsh Shah
AnalystsOkay. And sir, on the copper part, the 10,000 metric tonne capacity which we have, what would be the average realization and EBITDA margin on those?
Rajesh Gupta
ExecutivesThis is copper cathode. So the current copper price is around $11,000 -- $11,500, $12,000. And normally, there is a premium to Congo because of the transport cost. So the -- that's the approximate range. And the margins that we anticipate are approximately 30%, 32%. So that gives that INR 500 crores, INR 700 crores that we're talking about next year.
Harsh Shah
AnalystsOkay. And since we have 50% stake in this JV...
Operator
OperatorSorry to interrupt you...
Harsh Shah
AnalystsAnd it is relating to this. It is relating to this. So are we the MDO partner here or mining will be done by someone else?
Rajesh Gupta
ExecutivesMining would be by Thriveni, by a subsidiary of Thriveni in that area, yes.
Operator
OperatorThe next question is from the line of [ Hardik Gori ] from [ Abans Investment Managers ].
Unknown Analyst
AnalystsCongratulations on a great set of numbers. Firstly, on the growth outlook for our MDO business in FY '27? And secondly, what was the IPS benefit for Q3?
Rajesh Gupta
ExecutivesIPS benefits, we have been drawing the benefits from day 1 of the pellet plant production, and this year has been around INR 130 crores. The remaining outlook is around 40% increase in iron ore non-Lloyd metal. Around 60%, 70% increase in the Lloyd metal because of the BHQ increase, 15% in NTPC, that is both the Pakri Barwadih mines, around INR 60 crores EBITDA. They have come up directly with the EBITDA figure expected for the gold mine, but not...
Unknown Executive
ExecutivesGoldmines is 0.3 million tonnes.
Rajesh Gupta
Executives0.3 million tonnes output, and that would be the profitability. There will be some reduction in volumes in Indonesia and in the baryte operations. Overall, a top line growth of around 15% to 20% and a bottom line growth of around 35%, right?
Unknown Analyst
AnalystsGot it, sir. And our expected debt trajectory on a consol level?
Operator
OperatorSorry to interrupt. Please rejoin the queue for more questions.
Unknown Analyst
AnalystsAll right.
Operator
OperatorThe next question is from the line of Vinit Thakur from Plus91 AMC.
Vinit Thakur
AnalystsSir, I would like to know what would be the expected debt consol figure for the year? And what would be our peak debt?
Riyaz Shaikh
ExecutivesAs on 31st December, if I would say, the consol debt, net debt was around INR 7,100 crores. This year, we should be not more than that. And FY '28 is when I would say the peak debt. When we reach the peak debt, we should be -- on a consol basis, should be around INR 10,500 crores, INR 10,600 crores. So we are always targeting at 1:1 debt to EBITDA, and that is what we are working on. That's right.
Operator
OperatorThe next question is from the line of Shubham Harne from Purnartha Investment Advisers.
Shubham Harne
AnalystsThe question was, I think EBITDA per tonne for pellets has declined on a Q-on-Q basis. Last quarter, it was INR 5,000 per tonne. This quarter, a little less, around INR 4,000 or so. So any reason for that?
Rajesh Gupta
ExecutivesDRI is one of the most challenging businesses, like some other questioner asked earlier about the down cycle. It's most affecting the secondary steel market and that. Prices on pellets, if you're asking, has gone up.
Riyaz Shaikh
ExecutivesNo, no, no prices has...
Shubham Harne
AnalystsThe EBITDA per pellets.
Rajesh Gupta
ExecutivesIf you look at the pellet prices, the pellet pricing has gone up. Therefore, spot pricing is showing that there's a pressure on that, right, EBITDA on [ DLSI ]. So basically, it's a -- it was a cycle. The cycle has crossed the hump...
Riyaz Shaikh
ExecutivesThe pellet prices in quarter 2 was around INR 11,000, is what we had got in average realization, and it has come down to INR 10,000 in quarter 3. That is why the margins have been reduced.
Rajesh Gupta
ExecutivesThe pricing is lower because we have added more export to the mix. As the volume has picked up, we have had to add some volume of export. The EBITDA is still very strong and much stronger than the rest of the industry put together.
Operator
OperatorThe next question is from the line of [ Tanmay Choudhary ] from Ventura Securities.
Unknown Analyst
AnalystsSir, given Lloyd's ongoing CapEx pipeline, so can you just outline the expected funding mix and cash outflows over next 2 years and also the scheduled debt repayments and the [ RCFC ] payment providing CMPL not declared any dividend?
Riyaz Shaikh
ExecutivesThe debt schedule and all, we can give it to you separately. I won't be able to do that. But yes, the CapEx outlay is around INR 14,000 crores from this year and the next year. We would be around -- we intend to do around INR 6,000 crores from debt and then the balance should be from the internal accruals. That is where we are working on.
Unknown Analyst
AnalystsOkay. And sir, just last one question. In PPT, we have mentioned the realization of pellet increases because of the geographical location. So can you just throw some light on it?
Rajesh Gupta
ExecutivesSorry, can you repeat your question?
Unknown Analyst
AnalystsI'm saying in the PPT, we have mentioned the realization of pellets increases because of the geographic location. So can you just throw some light on it?
Rajesh Gupta
ExecutivesGeographically -- I mean, I cannot relate directly to the PPT question, but geographically our location is such that we can market to -- we have been very strong in marketing to the South as well as the Chandrapur area itself. So that's why our realization in pellet is around INR 4,500...
Riyaz Shaikh
ExecutivesNo, INR 10,000 crores.
Rajesh Gupta
ExecutivesAnd the EBITDA is around...
Riyaz Shaikh
ExecutivesINR 4,500 crores.
Rajesh Gupta
ExecutivesINR 4,500 crores per tonne because of the market-friendly nature as well as our costing and logistics cost. So I think that's where -- does that answer your question? Or is there something specific?
Unknown Analyst
AnalystsNo, sir. Like I'm asking about the realization.
Rajesh Gupta
ExecutivesRealization is a factor of trade versus market, and that's where we are. Being [indiscernible] located, it helps, the location helps. That's how we are better than others. That's [indiscernible].
Operator
OperatorThe next question is from the line of Karthik Srinivas from Unifi Mutual Fund.
Karthik Srinivas
AnalystsSir, I just had one question just on the policy level. Now that many mines are coming up for auction till 2030 and there is significant demand-supply gap between iron ore and steel, is there any possibility that the government has to intervene and put a cap on the auction premiums? And is there a risk that we run because the government has intervened and put this thing on the auction premiums or changed some of the policies at the policy front?
Rajesh Gupta
ExecutivesThe government, we believe, is still believing in free market and the premiums are quoted by the biggest consumers of iron ore, which are one of the biggest -- some of the biggest corporates in the country. So we have not seen any policy change or policy announcement which would indicate that there is being a cap on the premiums being put.
Operator
OperatorThe next question we have is from -- a follow-up question from Jashandeep Singh Chadha from Nomura.
Jashandeep Singh Chadha
AnalystsSir, my question was regarding Thriveni. Just wanted to understand the remarkable performance. The EBITDA has doubled quarter-on-quarter. I wanted to understand that -- the proportion of the EBITDA. So is it -- the large chunk of increase, is it coming from increased volumes from Lloyds? Or there are other major heads also because of which the EBITDA has improved? And wanted to understand how should we model the growth in EBITDA going forward till FY '28, if you can help.
Unknown Executive
ExecutivesQ3 the EBITDA has increased mainly -- up to Q2 due to rains and other local factors. The EBITDA was -- the production was lower, so the EBITDA was lower. And Q3, when the rains were not there, we came to our original strike rate and the EBITDA was normal as what we had planned. And for the next year what we are targeting -- and Q4, again, the Lloyds will be doing the full production. This year also, we are -- in Q4, we are starting one new mining lease. And next year, we are getting 3, 4 new contracts and extended capacity, so the volumes will be higher. And accordingly, we don't face -- see any challenge in EBITDA.
Jashandeep Singh Chadha
AnalystsUnderstood, sir. So just concluding that, so this appears to be the normal run rate for EBITDA and as contracts increase and volume increase, there will be growth from here on. Is my understanding right, sir?
Riyaz Shaikh
ExecutivesYes.
Operator
OperatorThe next question is from the line of [ Rushabh Dhruv ] from [ Uttam Investments.]
Unknown Analyst
AnalystsSo my question is regarding iron ore sales volume. So for this quarter, we just did around 4.1 million tonnes, right? Then why this PPT is also showing 5.39 million tonnes? What's the difference here?
Riyaz Shaikh
ExecutivesThat also includes the internal transfers. That's how. That is the dispatches from the mines.
Unknown Analyst
AnalystsOkay. So it's captive, right?
Riyaz Shaikh
ExecutivesThe sales figure is 4.1 million, which is [indiscernible].
Unknown Analyst
AnalystsThe sale is 4.1.
Operator
OperatorThe next question is from the line of Prateek Singh from IIFL Capital.
Prateek Singh
AnalystsJust wanted to get a sense as to when we had showcased the transaction with Thriveni back in December '24, we had given a sense of an EBITDA of around INR 3,500 crores in FY '27 by Thriveni. Is that something which we stand by or are on track right now as well? Or is that number a bit changed up or down?
Unknown Executive
ExecutivesIn FY '27, the EBITDA of Thriveni should be close to INR 3,000 crores.
Operator
OperatorThe next question is from the line of [ Divya Agarwal ] from [ Fincom Family Office].
Unknown Analyst
AnalystsSir, my question is on Thriveni MDO business. So in Q2 call, you guided to achieve EBITDA of around INR 2,000 crores to INR 2,200 crores for FY '26. However, if we see 9 months, the total EBITDA stands at around INR 1,100 crores. So do you still stick to your earlier guidance? Or would you like to revise it downwards?
Riyaz Shaikh
ExecutivesWe stick to the guidance.
Unknown Analyst
AnalystsDo you stick to the guidance, sir?
Riyaz Shaikh
ExecutivesYes, we stick to the guidance.
Unknown Analyst
AnalystsOkay. And on the revenue guidance as well, just wanted to know for FY '26 and '27, what would be the revenue guidance for Thriveni?
Rajesh Gupta
ExecutivesFY '20...
Unknown Analyst
Analysts'26 and'27. For the entire year FY '26 and FY '27.
Unknown Executive
ExecutivesFY '26 and FY '27?
Unknown Analyst
AnalystsRight. Right, sir.
Unknown Executive
ExecutivesYes. So FY '26, we are looking at the revenue guidance of around INR 7,500-plus crores and FY '27 revenue guidance of INR 10,000 crores plus.
Unknown Analyst
AnalystsINR 10,000-plus crores?
Riyaz Shaikh
ExecutivesYes.
Unknown Analyst
AnalystsAnd lastly, sir, just what would be the actual PAT for...
Operator
OperatorMr. Agarwal -- sorry to interrupt you, Mr. Agarwal. Please rejoin the queue for more questions.
Unknown Analyst
AnalystsSure.
Operator
OperatorWe'll take the next question from the line of Parthiv Jhonsa from Anand Rathi Share and Stock Brokers Limited.
Parthiv Jhonsa
AttendeesMy quick question is on -- again on Thriveni MDO. A couple of quarters back, you had given us the guidance for almost up to '28 and '29. I believe sir has given the EBITDA guidance of about 30% in '27. Thereafter, is it possible to give a guidance of '28 and '29, because I think it was about 32-odd percent give or take, considering you are going to do 40% higher volumes on iron ore non-Lloyds and for the other minerals as well? Is it possible to give some guidance?
Rajesh Gupta
Executives'28, '29 -- see, it's a contracting company. We are looking at contracts on a continuous basis. It will be very difficult to give a further guidance than what we have. Even the guidance that Mr. [ Naraidi ] just gave would have some surprises upwards because some contracts would come up hopefully in future.
Parthiv Jhonsa
AttendeesAbsolutely, absolutely. Yes. Okay. And sir, is it possible to repeat that number, that 40% increase in iron ore and everything? I think I missed a couple of them actually, for next year.
Rajesh Gupta
ExecutivesThe internal -- sorry, the external iron ore figure is around 40% increase in '27, FY '27. The external coal, that is NTPC contract, is around 15% growth. Correct me if I'm wrong, Mr. [ Naraidi ].
Unknown Executive
ExecutivesYes.
Rajesh Gupta
ExecutivesThere would be a reduction of around 65% in the baryte operations. There will be a reduction of around 25% in the Indonesian operations. Add to that gold and copper of the Katanga area. With that, we expect that figure that Mr. [ Naraidi ] just gave us.
Operator
OperatorLadies and gentlemen, due to time constraints, that was the last question. I would now like to hand the conference over to Mr. Parthiv Jhonsa for closing comments. Over to you.
Parthiv Jhonsa
AttendeesThank you all for joining us for the conference call today. We at Anand Rathi would like to thank the management for giving us this opportunity. This concludes this conference call. Thank you, everyone, and have a good day.
Rajesh Gupta
ExecutivesThank you.
Unknown Executive
ExecutivesThank you.
Riyaz Shaikh
ExecutivesThank you.
Operator
OperatorOn behalf of Anand Rathi Shares and Stock Brokers Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.
For developers and AI pipelines
Programmatic access to Lloyds Metals and Energy Limited earnings transcripts and 32,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.