executiveHello everyone, and thanks for joining us for Metallus's call on the second quarter of 2024. This is Jennifer Beeman speaking — I handle Communications and Investor Relations here at Metallus. With me on the line are Mike Williams, our President and Chief Executive Officer; Kris Westbrooks, Executive Vice President and Chief Financial Officer; and Kevin Raketich, Executive Vice President and Chief Commercial Officer. A copy of the press release we put out yesterday evening ought to be in your hands by now. On this call today, we might share forward-looking statements, as the SEC defines them. Because of many different factors — which we lay out in more detail in last night's release — what actually happens could end up materially different from what we project or imply. Take a look at our SEC filings, among them our latest Form 10-K and Form 10-Q, plus the factor list contained in our earnings release; all of these can be found on Metallus's website. If we mention non-GAAP financial information, you'll find further specifics and reconciliations to the comparable GAAP figure in that same release; so with that said, let me hand things over to Mike. Mike?
Michael Williams
executiveHello, everyone, and thanks for being with us today. In Q2, we concentrated on the areas within our power to lessen the effects of difficult market conditions. Demand from the aerospace and defense sector stayed robust, and our automotive volumes held firm. Regrettably, the weakness in industrial and energy markets that we observed during Q1 carried over into Q2. This softness stems from deteriorating worldwide economic circumstances, high levels of imported product, inventory situations at customers and within the supply chain, plus uncertainty surrounding scrap prices. Even with certain end markets working against us, we continue to dedicate ourselves to handling what we can influence — matching production to demand, prudently overseeing working capital and expenses, and putting money into our facilities and workforce to support future expansion. Throughout the quarter, we stayed profitable and generated positive operating cash flow, which speaks to the strength of our business model and our careful financial stewardship. I believe that as market conditions shift, we are ideally situated to capitalize on recovering demand and expect better profitability ahead. At Metallus, safety isn't merely a priority — it's a fundamental value; we hold the view that a workplace that is safe is also one that is productive and successful. We've put in place a thorough safety plan and established bold targets aimed at protecting the health and welfare of our employees, contractors, and visitors. We've achieved meaningful headway in carrying out that safety plan, which encompasses improving our safety procedures and systems, along with our physical surroundings, our cultural atmosphere, and our safety competencies, with a heavy emphasis on preventing serious injuries and fatalities. Over the back half of this year, we'll keep implementing our safety plan, concentrating on thorough pre-job safety planning and inspections, advancing our programs for preventing serious injuries and fatalities, persisting with investments in physical equipment and equipment guarding improvements, and pursuing focused injury reduction approaches tied to hand injuries and ergonomics. Our safety plan is producing favorable results, as we're seeing encouraging signs in employee engagement, hazard identification, and incident prevention. So far, we've committed $4.5 million to safety programs. As a reminder, we projected roughly $7 million in total safety spending for the year. Shifting to our end markets — as I noted before, demand in our industrial and energy sectors is still weak. For instance, we think investments in agricultural machinery are being pushed back because of elevated prices and interest rates. Inventory levels in industrial distribution are still high owing to weaker end-customer demand, short lead times, and uncertainty about scrap prices. Finally, rail and mining markets are anticipated to stay sluggish through the year. Regarding our automotive results, we recorded a 2% sequential rise in shipments. While periodic disruptions in the automotive supply chain have occurred and continue to occur, demand has proven resilient. We take pride in supplying our automotive customers with premium bar and tube products, along with manufactured components for internal combustion, hybrid, and electric vehicles. The aerospace and defense sector stayed robust during Q2, even though we had originally anticipated a sequential drop because of how customer orders were timed. That expected decrease, though, has been pushed back by 1 quarter, and at this point we anticipate that shipments in this end market during Q3 will come in below what we saw in Q2. Previously, I brought up how imports have hurt our business. For some context, from 2020 until the middle of 2022, SBQ imports made up around 10% of the market, yet that figure climbed to roughly 17% starting in Q4 of 2023 all the way through the first half of this year. In the same way, we keep facing pressure from a high volume of tubing imports. Now, regarding our capital investments, we are achieving meaningful progress by putting money into assets that fuel growth while also boosting product quality, asset reliability, customer service, and cost structure. At the beginning of this week, we held a groundbreaking ceremony at our Faircrest steelmaking plant to mark construction of a bloom reheat furnace. A large number of local, state, and federal officials came to the event, among them Ohio's Lieutenant Governor, Jon Husted. We were announced as the recipient of $3.5 million in grants from JobsOhio to back the planned expansion of our steelmaking facilities. The purpose of these grants is to help with training, update equipment, and strengthen skills for implementing cutting-edge steelmaking technologies. Installing a continuous bloom reheat furnace will allow us to satisfy rising demand from both current and new customers; we appreciate the support we've received from the community, the State of Ohio, and our federal government, which will let us improve and optimize our assets, boost our capacity for high-quality defense products, and back key training efforts centered on safety and technology via a workforce development grant. As a reminder, back in February, we disclosed an agreement worth up to $99 million in funding from the United States Army to support our national defense efforts. As a reminder, we anticipate the bloom reheat furnace will be up and running in late 2025. Over the quarter, we put $14 million into capital expenditures, making additional headway on installing an automated grinding line, in-line saw technology, and new camera inspection technologies. These efforts fit within our wider plan to realize substantial cost reductions, produce free cash flow, and lift our profitability. Although there are certain difficulties in the present demand environment, we stay confident about our strategic imperatives and our capacity to handle market volatility. We are dedicated to fueling growth, improving profitability, and delivering value to our shareholders. At this point, I'll hand the call over to Kris Westbrooks, who will share more specifics about our financial performance.
Kris Westbrooks
executiveThanks, Mike. Good morning, everyone, and I appreciate you being on the call for Metallus' Q2 2024 earnings discussion. During this quarter, we kept steering through tough market circumstances, which showed how durable our business model is and how strong our team is. Looking at the finances, net sales for the second quarter came to $294.7 million, which is 8% lower than the prior quarter. This drop in net sales mostly came from reduced shipments, a less favorable price mix, and a 12% market-driven fall in average raw material surcharge revenue per ton because scrap prices were lower. Net income for Q2 was $4.6 million, or $0.10 per diluted share. Looking at the first quarter right before this one, net sales came to $321.6 million, and net income was $24 million, which works out to $0.52 per diluted share. If we go back to the second quarter of last year, net sales reached $356.6 million, with net income of $28.9 million, or $0.62 per diluted share. Turning to adjusted figures, net income for the second quarter of 2024 was $6.7 million, equal to $0.15 per diluted share. As a point of comparison, adjusted net income during the first quarter was $26.1 million, or $0.56 per diluted share. And in last year's second quarter, adjusted net income totaled $27.6 million, or $0.60 per diluted share. For the second quarter of 2024, Adjusted EBITDA was $19.9 million. That sequential decline was driven primarily by reduced melt utilization, since we aligned production with demand. The quarter-over-quarter decrease in Adjusted EBITDA also reflected somewhat softer shipments, a weaker price mix, and a market-related softening in the raw material scrap surcharge environment. Turning now to the details of our second quarter financial results: shipments for the quarter totaled 150,100 tons, which was 5,100 tons, or 3%, below the first quarter. Within the industrial end market, quarterly shipments were 56,400 tons, down 4,400 tons, or 7%, on a sequential basis. Distribution clients held off building up stock, which kept industrial shipments soft. They're wary because of quick turnaround times, where interest rates sit right now, and fluctuating scrap prices. On the automotive side, we moved 67,800 tons during Q2 — a 2% gain over Q1, reflecting consistent demand from customers. Over in aerospace and defense, which we call A&D, volume for the quarter came to 16,400 tons, roughly flat versus Q1, since demand there stayed robust. Our forecast had called for A&D tonnage to drop between Q1 and Q2, given how customer orders were timed. But that anticipated dip got delayed by a quarter, so now we expect A&D shipments in Q3 to come in lower than Q2 on a sequential basis. For the fourth quarter, we're looking at A&D shipments going up compared with the third, and that momentum should carry through into 2025. If you look back at the same period last year, our A&D shipments were twice as high in Q2 2024. On the energy side, demand stayed weak — we moved 9,500 tons during the quarter, which is 1,900 tons less than the previous quarter. Switching over to manufacturing: production was matched to demand as planned, and that hurt our cost leverage this quarter. In May, we lost about a week of operations to bring new technology online at our electric arc furnace, and the goal there is better reliability of assets along with improved safety results. Moving on to June: our electricity provider required upgrades to its infrastructure, which forced the melt shop to halt operations for roughly seven days. As a result of that situation, along with our ongoing practice of matching output to demand, the melt utilization rate for the second quarter registered 53%. By comparison, that figure stood at 72% during the first quarter and 75% in the equivalent period last year. Even so, with output reduced, our manufacturing team is keeping a close watch on variable costs. I'll now turn to pensions. In Q2, we put $5.9 million into the bargaining pension plan as required contributions — that figure covered the earlier first-quarter required contributions as well — and we've got planned required contributions of $3 million for Q3 and $5 million for Q4. For the full year, we're looking at roughly $43 million in required pension contributions. That's $2 million under what we previously guided. Now on the salary pension plan: during Q2, we finished moving $121 million of its liabilities over to a highly rated insurance company. During the prior quarter's discussion, I noted that annuitizing this salary pension — plus a comparable bargaining pension annuitization worth $256 million completed in 2022 — marks meaningful progress in bolstering our balance sheet and reducing risk tied to our legacy pension plans. By the close of June, roughly $550 million in pension obligations remained with the company, a substantial drop from the $1.3 billion in total pension liabilities we carried at the end of 2021. Turning now to cash flow and liquidity: operating cash flow for the second quarter came in at $8.3 million, powered by profitability and reduced working capital, though required pension contributions partly offset that gain. During Q2, our capital expenditures came to $14.1 million. For the entire year, we're now projecting CapEx of roughly $55 million — that's $5 million less than what we previously told you. Keep in mind, this 2024 CapEx figure excludes any investments funded by the government. Just to remind everyone, back in February, we signed an agreement with the U.S. Army worth as much as $99.75 million, which supports the Army's goal of increasing munitions output. More specifically, that money is largely intended to cover the cost of a new bloom reheat furnace at our Faircrest site. Mike noted earlier this week that we've officially broken ground on that project. Our aim is to have it up and running by late 2025. With our new bloom reheat furnace, we anticipate being able to produce more high-quality bar-based goods, which should underpin roughly $60 million in extra defense product sales each year. The government sent us an initial $10 million payment in the second quarter. Then, in July, another $20 million came in. As we hit milestones that both sides agree on over the course of the project, more funding should follow. Project spending through the end of June has been quite limited. We look forward to providing more updates on this significant growth effort in the quarters ahead. Now let's turn to our efforts to deliver value back to shareholders. Thanks to progress we made on share buyback initiatives that were described during the prior quarter, in May our board gave the go-ahead for an additional $100 million program to repurchase common shares. During Q2, 440,000 shares were repurchased for $9.6 million. Through July 31, 2024, buybacks total 836,000 shares, costing $17.9 million; in total, $122.5 million is still open for repurchasing under the approved program as of July 31st; going forward, we intend to exhaust that authorization, supported by continued strength in our balance sheet and our ability to generate cash flow. At the close of the second quarter, cash and cash equivalents stood at $272.8 million, and total liquidity was $512.1 million. We believe the company's solid balance sheet, together with anticipated through-cycle profitability and positive operating cash flow, will give us the chance to keep carrying out our capital allocation strategy. That means putting money into profitable growth, keeping a strong balance sheet, and giving capital back to shareholders via ongoing share repurchases. Now let's discuss the outlook. We expect third quarter shipments to come in below the second quarter. Looking at end markets, automotive shipments should stay fairly stable, but industrial and energy demand are still weak. Although long-term aerospace and defense demand should stay robust, we foresee a sequential drop in third quarter A&D shipments due to the timing of customer orders. In Q3, we expect the base price per ton to stay about the same, though the mix of products will probably be worse than it was in Q2, since A&D shipments will be lower. Operationally, we've scheduled annual shutdown maintenance for the back half of the year, and it should cost about $13 million in total, split roughly evenly between Q3 and Q4. Additionally, the melt utilization rate in Q3 ought to increase from the prior quarter, as we continue to match production with demand. Given that lead times now extend from late Q3 into early Q4, and melt shop shutdown maintenance is planned for October, a significant share of Q3 melt production will be used for Q4 shipments. Considering everything we've discussed, we anticipate that Adjusted EBITDA for the third quarter will come in lower than what we saw in the second quarter. In closing, we want to express our appreciation to our team members for the way they work together day in and day out, all while keeping their attention on completing every single day without an incident or injury; in a challenging market, we remain dedicated to managing the things within our control, even as we continue putting money into the future and giving capital back to shareholders. Thanks to our team's diligent efforts on our strategic imperatives, we're well positioned to gain once demand picks back up, and we anticipate significant improvements in profitability down the road. We appreciate your interest in Metallus. At this point, we'd like to turn the call over to your questions.
John Franzreb
analystMorning, everybody, and I appreciate you taking my questions. I want to focus on Q2 for a moment. Looking back at it, what stood out most as surprises, and what were the positives and negatives on the revenue line and on costs, compared with what you expected roughly 3 months ago?
Michael Williams
executiveMorning to you, John. On the revenue side, I'd say the largest surprise for us was how little demand showed up, especially out of the spot market. If you remember, we entered 2024 with a contractual mix of about 60%-65%, with the rest being spot. Our thinking is that elevated interest rates and uncertainty in the economy are pressing on people, and they simply aren't purchasing at those levels — not just in terms of order quantities, but in overall buying, which is much lower, and they're truly running on a hand-in-mouth basis. So as far as volume goes, that played a major role in Q2 versus what we had anticipated as we headed into Q2. The second item is really the customer mix, which impacted base pricing, since those spot customers typically pay a higher base price per ton than our contractual customers do. And the absence of demand from those spot customers affects our ASP, our average selling price. From a revenue perspective, I'd point to those 2 things. On top of that, our electrical supplier came in wanting to upgrade the distribution facility that serves our Faircrest steel plant, and given the order demand pattern, we agreed to let them complete all the upgrades to cut voltage loss and boost reliability for our long-term benefit; that cost us a week of operations, which weighed heavily on our leverage, our fixed cost leverage.
Kris Westbrooks
executiveMike, if I could add one thing-
Michael Williams
executiveOf course.
Kris Westbrooks
executiveWithin the automotive sector, a few of our customers dealt with downtime over the quarter, and that wasn't planned on their end, so it had an effect; roughly 5,000 tons was what we had anticipated shipping in Q2, and at this point they've resumed operations, though that lack of certainty caused a certain amount of disruption.
John Franzreb
analystOkay. So the electrical upgrade caused unplanned downtime during the quarter, and regarding the auto downtime, should we expect that to be made up in Q3? Is that right? Could you just take me through those two negatives and positives?
Michael Williams
executiveWell, actually, actually, yes, those customers who were hit by their unplanned downtime, that will be recovered in the third quarter. But unfortunately, we have been told-
John Franzreb
analystAlright.
Michael Williams
executive... from at least 2 big OEMs. One of them is working to streamline inventory across its supply chain, and because of that, the demand coming from that OEM will drop. As for the other, there are separate problems — word came to us that its plant will be shut down for a period nobody has specified, so that fixes can be made to several issues. Q3 is when that will hit us. On top of that, our expectation isn't there when it comes to a number of our big defense customers. You know, we'd said we figured it would take place in Q2, but our belief now is that Q3 is when it will take place — they had placed advanced orders and ramped up to get new equipment commissioned. Every bit of supply they require, they already have, so until that equipment is fully commissioned later this year, a repeat of those orders isn't something we expect.
John Franzreb
analystAll right, thanks. You've actually touched on another thing I was going to ask regarding A&D. How big is the decline you're anticipating for the third quarter, and does it snap back to the present sales figure during the fourth quarter? What's the right way for us to view this moving forward?
Michael Williams
executiveYes, my expectation is that it returns to where it stood in the prior year.
John Franzreb
analystAll right.
Michael Williams
executiveWhen comparing the second quarter of the prior year with the second quarter of this one, it will fall back to those earlier levels. That is what we anticipate.
John Franzreb
analystAlright, so what's the-
Michael Williams
executiveHonestly, John, it just changes from one day to the next.
John Franzreb
analystAll right, so what sort of decline should we be anticipating for Q3?
Kris Westbrooks
executiveYes, John, Q3 is going to see a pretty substantial decrease, simply because of how strongly positioned they happen to be at this moment.
Michael Williams
executiveYeah.
Kris Westbrooks
executiveAnd that's-
John Franzreb
analystRight
Kris Westbrooks
executive... what's gonna drive that price mix.
Michael Williams
executiveWhen you compare the second quarter of 2023 with the second quarter of 2024, we're probably around 10,000 tons higher on a quarter-over-quarter basis. That's in line with what we anticipate, though it could potentially decline in Q3.
John Franzreb
analystAlright, alright. Fine, I'd say I've taken up more than my share of this call. I'll rejoin the line. Appreciate you answering my questions.
Michael Williams
executiveSure thing, John, thank you.
Dave Storms
analystGood morning, and thanks for fielding my questions. I just wanted to understand whether the current weakness in the market opens up a chance for you to reduce expenses even more, and what other levers might be available to pull?
Michael Williams
executiveYes, so, listen, our approach to managing the finances is extremely disciplined. As you know, we've already brought down — this is included in the earnings release — a portion of the CapEx for this year; and we're doing everything possible to streamline our expenses given the demand we're seeing right now. That said, our true emphasis is on executing and speeding up the strategic imperatives tied to our main strategic investments in the automated grinding line, the installation of in-line saws, and bringing in the new camera technology so we can achieve better yields, improved quality, and reduced cost. That's where our attention is. We're also seizing the chance to expand employee training, cross-training so they become multi-crafted, capable of operating several pieces of equipment, and more flexible in moving across the plants to run equipment, which lets us optimize our workforce. So those are items within our control, and they're what we're concentrating on.
Dave Storms
analystGot it. That helps a lot. Thanks. You brought up CapEx in there. I realize your CapEx guidance has been lowered. Is there a particular program or initiative you're pulling out of the plan? And when it comes to CapEx, what portion goes to maintenance, what portion goes to hardware purchases, and what portion goes to IT and automation efforts?
Michael Williams
executiveWell, the IT transformation project we're working on isn't impacted by this; there are two parts to it. Dave, part of it involves maintenance we're pushing off, but the bulk consists of specific projects that have simply turned into a lesser priority right now, since we're concentrating on the larger value-generating projects so we can get them done while we have the opportunity to speed them up, given that demand isn't at the elevated level we'd normally anticipate.
Dave Storms
analystGot it. And could I squeeze in just one additional question?
Michael Williams
executiveOf course.
Dave Storms
analystYou said a milestone has been hit on Bloom. That was made public in February. So is this roughly the normal cadence — every 2 quarters, say? How are we meant to think about these?
Michael Williams
executiveIn the deal we have with the Department of Defense and the U.S. Army, particular milestones exist that must be satisfied before funding comes through, moving forward stage by stage as the project proceeds. A number of them have therefore been achieved so we could get that money. Most recently, we held the groundbreaking ceremony — literally sticking a few shovels into the earth and kicking off the excavation work for the foundations, the new building, and all that goes into raising the new facility.
Dave Storms
analystGot it. Thanks for answering my questions, and best of luck during Q3.
Michael Williams
executiveOkay, thanks.
Phil Gibbs
analystHey, good morning.
Michael Williams
executiveGood morning.
Phil Gibbs
analystThat sequential rise in absolute costs during Q2, I think, caught us a little off guard. You all referenced the 2 outages in the quarter, 1 in May and 1 in June, yet you also have planned outages coming in Q3. So does that effectively cancel out that sequential increase, or the sequential increase that would happen, since you already dealt with some downtime in Q2?
Michael Williams
executiveWell, the first extended downtime involved us installing technology on our EAF for safety, reliability, and better quality. And, you know, that project would normally have been done around October, early November. But given the absence of demand, we had the chance, and since it's such a beneficial upgrade for our EAF, our efficiencies, and our costs, we chose to do it in Q2. The other extended downtime, Phil, came about because the electrical company reached out to us, and we would have done this around October as well, okay? They came to us; they had reliability problems that we've dealt with over the last couple of years. They were able to completely upgrade their entire delivery system into our Faircrest facility. At the same time, they were also seeing significant voltage loss on that equipment. So actually, it was a win-win for both companies, and we just decided to move forward with it because of pretty much no spot demand. But that doesn't alter when our outage in October, early November is going to happen, because that was all part of it, running in parallel with what we're doing during that period. And there were other projects with longer execution times in the planning schedules. So they were all going to be folded into the overall long lead time planning schedule for the October outage. Does that make sense to you?
Phil Gibbs
analystNo, that's logical. What I'm really getting at is the normal upkeep. I believe your figure was $13 million, divided evenly across Q3 and Q4, yet in Q2 there were items that — I wouldn't call them one-off, exactly — but they were less typical; so can we simply tack on the portion of that $13 million belonging to Q3? Or do we need to factor in that Q2 included somewhat higher costs — that's essentially what I'm asking.
Michael Williams
executiveYes, some elevated cost came with the first project I mentioned. As for the second one, the electrical providers, our costs were minimal aside from the fixed cost leverage impact from those seven days of downtime.
Kris Westbrooks
executiveBuilding on what was just said, Phil.
Phil Gibbs
analystAll right.
Kris Westbrooks
executiveOur melt came in roughly 60,000 tons below where it stood in Q1 compared with Q2, and that, as you can imagine, represented quite a significant step down when viewed through the lens of cost leverage.
Phil Gibbs
analystAll right, and after that, for Q3, you're indicating that melt rates are being raised so you can satisfy demand during Q3 and Q4; so given that, ought we to anticipate inventory building up in Q3?
Michael Williams
executiveYes. Once more, melt rates will rise since the electrical outage won't take place; and, as you know, later in this quarter, well, quite soon, we'll begin melting for Q4 orders.
Phil Gibbs
analystAll right.
Michael Williams
executiveTherefore, an increase in melt utilization is what we anticipate.
Phil Gibbs
analystThen the final item I've got concerns the bloom caster. Pardon me — the bloomer. From what you said, it sounds like roughly $30 million has already come in from the government through July, assuming I caught your comments right. The $55 million in CapEx doesn't cover whatever spending might happen this year; and since equipment lead times are what they are, it doesn't sound like much, if anything, gets spent this year. So essentially, we ought to expect that next year's CapEx figure, on a gross basis, will show this investment, plus some money received from the government this year, plus some received from the government next year? Is that how you're thinking about it?
Michael Williams
executiveYes. Given the milestone array agreements in place, we anticipate some further payments arriving later this year. Down payments will need to be made for ordering a number of the equipment. But yes, cash coming in is going to exceed cash going out, and then all of that cash outflow will begin showing up next year.
Phil Gibbs
analystAlright, that's clear. That's totally logical. Thanks.
Michael Williams
executiveThanks, Phil.
John Franzreb
analystYeah, sorry if I didn't catch this — what was the effect on melt utilization during the quarter from the electrical upgrade downtime?
Michael Williams
executiveCan you give us a breakdown on that?
Kris Westbrooks
executiveYeah; it was between 7 days — 10 days, so, you know, 7%-10%, honestly.
Michael Williams
executiveYeah.
Kris Westbrooks
executiveIt's 1% a day, essentially.
John Franzreb
analystOkay.
Kris Westbrooks
executiveAt least from my standpoint.
John Franzreb
analystChris, assuming I caught what you said correctly, I believe the phrase you used was that you'd exhaust the authorization for shares. As we build out our models for the rest of the year, just how aggressive ought we to be when thinking about buybacks?
Kris Westbrooks
executiveFlexibility is something we'll hold onto in that area. Our commitment is to use it up completely — though not within some particular, say, period of time. What we'll keep doing is proceed as pricing permits, and when prices are lower, you acquire somewhat more. So going forward, expect us to keep giving updates each quarter.
John Franzreb
analystFine, and thanks for allowing me to ask these additional questions.
Kris Westbrooks
executiveYou're welcome.
Michael Williams
executiveAppreciate it, John.
Jennifer Beeman
executiveExcellent. Thank you all for being with us today — that wraps up our call.
Operator
operatorThank you all for joining. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Metallus Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Metallus Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Metallus Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.