MGX Resources Limited (MGX) Earnings Call Transcript & Summary

April 22, 2020

Australian Securities Exchange AU Materials Metals and Mining earnings 23 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone being on today’s teleconference as Mount Gibson Iron releases its quarterly activities report covering the March quarter 2020. Leading the discussion will be Mount Gibson’s Chief Executive Officer, Peter Kerr, and he is joined by Financial Officer, Gill Dobson; Chief Operating Officer, Mark Mitchell; and External Relations Manager, John Phaceas. Mr. Kerr will give a brief overview, and afterward there will be a chance to ask questions. Because of time constraints, at that point only institutional participants will be invited to ask questions. A recording of the call will also be made available through Mount Gibson’s website shortly after today’s teleconference ends. Please go ahead, Peter.

Peter Kerr

executive
#2

Thanks, Brie. Morning, everyone, and thank you for joining us to go over Mount Gibson's activities report for the March quarter. As we always do, I'll begin with a few comments, and after that we'll move straight into Q&A. To start things off, our operations did reasonably well during the quarter, though we encountered delays caused by heavy rainfall at Koolan, along with travel and operating restrictions tied to the COVID-19 virus, and we'll get into those a little more. Total ore sales came to 1 million tonnes, down on the prior quarter, mainly because ore extraction rates at Koolan Island were lower. Koolan sales reached 439,000 wet tonnes of high-grade fines. The average grade sold was 65.6% iron, which stays well in line with the ore reserve. Sales from the Mid-West operations came to 587,000 wet metric tonnes of low-grade material. For the 9-month year-to-date period through the end of March, total sales were 3.8 million tonnes. With iron ore prices holding up and the Australian dollar weaker, sales revenue for the quarter came to roughly AUD 82 million FOB. We report all revenue and costs on an FOB basis out of the relevant ports.

Peter Kerr

executive
#3

For the quarter, gross cash flow totaled AUD 19 million before a few items. The first of those is $16 million of capitalized waste stripping at Koolan. We treat that capitalized waste stripping as part of normal operating expenditure, and it gets captured in our unit cash costs. Beyond that, we also incurred $5 million of initial construction spending on the new Koolan airstrip, along with some favorable working capital movements. Consequently, the group's cash and investment reserves rose slightly, up $4 million to $402 million by quarter end. And clearly, our balance sheet remains strong, with no borrowings. Now, a bit more detail on Koolan. As we reported earlier, the operation was affected during the quarter by several severe wet weather events tied to cyclones. And although we plan for the wet season, anticipate these events, and have pumping systems installed, we could not prevent every delay tied to dewatering and catch-up mining work in the Main Pit. Heavy rainfall events cause large volumes of water to flow rapidly into the narrow base of that pit, and removing it and getting mining activities back on track takes time.

Peter Kerr

executive
#4

So — apologies — this meant lower ore extraction and fewer shipments over the quarter. And then, clearly, in March we also dealt with the negative effects of the COVID-19-related shifts. So although we managed to keep total tonnes mined at Koolan in the March quarter within 10% of December quarter levels, our unit cash costs per tonne sold — a straightforward measure, just summing all operating costs and dividing by whatever volume we sell — rose temporarily, which mirrors the island's high fixed cost base, the waste stripping requirement sitting at elevated levels during the first 2 years of mine life, and the smaller shipment volume we achieved. Mining performance has carried on more consistently into April, and ore production is getting better. Although we have withdrawn annual guidance — because of recent performance as well as the COVID-19 regulatory uncertainties we face — we do expect Koolan's sales and costs in the June quarter to improve on the March quarter. From a geotechnical standpoint, the mine keeps performing to plan. The seawall is functioning as designed, along with normal operational geotech work on the footwall, and that work includes depressurization drilling, cable bolting, shot-creting and meshing — all of these continue to advance well.

Peter Kerr

executive
#5

On the COVID-19 front, I wanted to give you a sense of the kinds of actions we're taking and already have taken, especially since this has clearly been a major problem for the resources industry throughout Australia over the last 2 months. Some of you know that the Kimberley region — which takes in Koolan along with the towns of Broome and Derby — became, in March, subject not just to travel restrictions from the West Australian government but also to some tough federal government biosecurity protections, and only a few regions around Australia carry these additional protections. Consequently, we had to negotiate with the regulators — notably the WA government and the police — and to arrange and agree on a set of detailed changes to travel and operations so that Koolan would stay safe and be cleared to keep operating. Among the measures we've put in place are screening and documentation before travel; social distancing, as you'd expect, while travelling and at the site; better cleaning and personal hygiene practices, as has happened throughout the country; and longer rosters to cut down on travel movements. In fact, we've moved most of the site workforce from a 2 weeks on, 1 week off roster to a temporary 4 weeks on and 2 weeks off roster, and we've also relocated a number of personnel from interstate.

Peter Kerr

executive
#6

And we've now swapped out the commercial flights we were using between Perth and Broome, replacing them with a dedicated jet charter service linking those 2 towns, running twice per week. So quite a few significant changes have taken place within a very short period. Since mid-March, site manning levels have come down as well, and certain nonessential work has been deferred. For obvious reasons, we've also stopped hiring personnel from interstate. So we're thankful that a number of our interstate resident workers have decided to relocate to WA for the time being so they can keep working on Koolan Island. So on top of all that, a special focus has also been needed on-site to minimize contact between our personnel flying in from Perth and locally resident personnel. And that involves a number of changes aimed simply at trying to increase separation and lower the risk of any transmission should the virus arrive in the Kimberley. When it comes to the Koolan airstrip, construction is progressing well, and we spent the first $5 million of the expected $20 million capital cost during the quarter and remain on track to begin flights onto that airstrip around October.

Peter Kerr

executive
#7

So this is a brand-new 2.1-kilometer airstrip, and what it does is let us fly our Perth-based FIFO employees straight to the site aboard commercial jet aircraft — which is something we have never been in a position to do before. There will be considerable advantages when it comes to safety, well-being and productivity, particularly by cutting the typical transport time for our people. And on top of that, from both a productivity standpoint and a cost standpoint, it delivers gains across the life of the mine. Clearly, the airstrip is now viewed as a central element of our COVID-19 management plan, above all since it lets us avoid moving our Perth-based personnel through Broome. So because of that, we are chasing a few opportunities in an effort to speed this project up. Over in the Mid-West, we posted another positive quarter, and we will continue delivering low-grade material through the June quarter and potentially into the early part of next financial year. We shipped slightly less than 0.6 million wet metric tonnes of material during the quarter, and the cash cost came in at AUD 41 per tonne sold FOB, which matched the plan. So ever since we launched the low-grade program in June last year, we have sold 2.2 million tonnes to date, which is more than twice our initial target, and we are still looking into further sales that would carry us into next financial year.

Peter Kerr

executive
#8

Right now we're simply evaluating the extension program for that. During the quarter, the business brought in cash flow of — this is the Mid-West operation — AUD 5 million, made up of AUD 3 million generated by operations plus AUD 2 million in continuing refunds of historic rail charges. Still, how that operation has performed speaks well of our compact Mid-West team and the contractors working with them. And as with every other operation, that team has likewise adapted to the COVID-19 management requirements and travel restrictions that were necessary. It has been run with only limited effects on the business, and clearly this is something we keep monitoring closely. Turning to unit cash costs, and building on what I've already said, our all-in group cash costs came in higher, clearly, at AUD 80 FOB during the quarter, which was up from AUD 69 in the December quarter. And year-to-date, across the 9-month period, those cash costs stand at AUD 71. That AUD 71 is in fact consistent with the guidance we have since withdrawn, though obviously it reflects a somewhat different mix. We had initially anticipated somewhat more Koolan production and had not anticipated the extent to which we've been able to extend in the Mid-West business.

Peter Kerr

executive
#9

However, looking at the net outcome for that cash cost, the figure stems from temporarily elevated expenses at Koolan, coming in at AUD 127 per tonne FOB sold, and that figure encompasses the entire waste stripping investment. So this mirrors the continued heightened waste movement as we progress through the coming 12 to 18 months, along with wet season disruptions and, most significantly, our lower shipment tonnages as a result. Turning to realized prices, we gained from stronger realized prices during the period. The Platts 62% Fe CFR benchmark index — that's the delivered price in China — held flat versus the prior quarter at USD 89 a tonne. Meanwhile, the 65% Index, which matters for us at Koolan Island, in fact rose compared with the previous quarter, when it stood at $98, and it averaged $104 in the March quarter as the premium for high-grade material grew. That high-grade premium presently stands at roughly 12% today. Demand out of China seems to be holding up strongly, and I'd say that has been well underpinned by production and supply troubles elsewhere in Brazil, Canada and South Africa, where those nations have experienced their own wet season and wet weather effects, plus COVID-19 shutdowns.

Peter Kerr

executive
#10

Freight costs for our shipments declined as well during the March quarter. For Panamax vessels carrying ore from Koolan Island to China, the rate dropped to roughly $8 to $9 per tonne shipped so far this year, compared with USD 10 to USD 12 a tonne shipped last year. Consequently, on a provisional basis, we achieved an average price of USD 86 per dry metric tonne FOB on the Koolan high-grade fines we sold, which rose from USD 73 a tonne during the December quarter. Sales of low-grade material from the Mid-West likewise fetched somewhat better average prices — USD 37 per tonne FOB for lump and USD 27 per tonne FOB for fines. A weaker Australian dollar also worked in our favor; it averaged just under USD 0.66 across the quarter versus USD 0.68 in the December quarter. To put that in context, our average realized price for Koolan high-grade fines came to approximately USD 130 per dry metric tonne FOB during the quarter. In closing, although the March period brought a number of challenges — some tied to delays from weather and others to the effects of COVID-19 — we remain in a stable and financially strong position to deliver on our long-term objectives.

Peter Kerr

executive
#11

That covers, in brief, what we did during the quarter. So, Brie, I'll turn it back over to you now for whatever questions might be out there. <<inaudible>> Brie, sorry—are you able to hear me?

Operator

operator
#12

Thank you very much, Peter. Good morning to all of you. This is Brie speaking from Express Virtual Meetings, and I'll be handling the question-and-answer portion of today's call. <<operator_script>> To begin, we have Hayden Bairstow with Macquarie.

Hayden Bairstow

analyst
#13

Perhaps just a few. First, on Koolan: you've clearly laid out the whole life-of-mine guidance and all of that. But could you give us a sense of when stripping really begins to taper off? Because obviously, once that happens, the cash generation is enormous. I just want an idea — given the delays you've had and everything else — of what sort of quarter it looks like when we start to see that decline. From memory, there was actually a step-up from here; it was high stripping for the next few quarters. I just want a sense of when that starts to tail off. And then at Extension Hill, how long can we keep producing roughly 0.5 million tonnes a quarter of this material?

Peter Kerr

executive
#14

Appreciate the questions. All right. So regarding the first one, Hayden, the key one for Koolan — you've got it exactly right: the life of mine plan stripping requirement does indeed increase, and ore comes down somewhat in year two. So we're essentially moving into that second year at this point. What has happened, though, is that the ore quantities we'd aimed to extract during year one fell a bit short, so that will carry over into year two. The life of mine plans we're currently working on — and those are being optimized continuously — show we've essentially got another 12 to 18 months of elevated stripping requirements. Near the end of that 18-month stretch, it may decline somewhat, but that's roughly the timeframe, and it matches precisely the life of mine plan we released a while back. On Extension Hill, that question never goes away. We're in fact still evaluating options for material sitting on the edges of the Extension Hill pit, as well as historical stockpiled subgrade material located next to the Iron Hill deposit that we mined a year or 2 ago. So there's a real possibility we could have another 3 to 6 months beyond 30 June.

Peter Kerr

executive
#15

Making a truly dependable forecast is hard, since our sales come in batches booked 2 or 3 months in advance at fixed prices. We also want to avoid landing in a spot where our price drifts far away from whatever the market price turns out to be. That approach appears to have served quite a few of our customers well. So that's the plan as it stands, and there isn't much more we can add, because at this point we aren't entirely certain.

Hayden Bairstow

analyst
#16

Yeah. Okay. And returning to Koolan for a moment. I mean, the stripping runs over 18 months, but the profile isn't flat either, right? It's kind of — it dips a bit more, then it eases off next year?

Peter Kerr

executive
#17

Correct. So there is a fair amount of waste in the 2021 financial year, particularly during the first half. In the second half, we're focused on optimizing that, but it aligns exactly with the mine plan we had. So our thinking is that the 12 months in front of us now do need a fair bit of waste movement, and that's what we want to try to synchronize with as smooth an ore delivery as we can provide now. We will provide an update on guidance for that, not right now, but once we've completed that work early in the new year, as we typically do.

Hayden Bairstow

analyst
#18

All right. Last thing—regarding the lump, will that begin arriving once these big strip is finished? Do you get a small amount of lump out there, or not?

Peter Kerr

executive
#19

Sure, we’re hopeful. The lump, I think, is going to depend on — there are some areas along strike of the Main Pit that are a bit lower grade and where the material is harder, and there are also satellite deposits we’re aiming to access. That could add some feed into lump product. So right now, the small amount of lump coming out is effectively being crushed to handle fines — it’s crushed down to fines. So our fines product has a good sizing distribution within it, but we’re watching for when that lump will come. At this point, though, it isn’t certain which month or quarter it will fall in. It’s something that’s in our plan.

Operator

operator
#20

Moving on, Paul McTaggart of Citigroup is our next participant.

Paul McTaggart

analyst
#21

I'd like to circle back on something: how did these extra federal government security requirements at Koolan come into play? What's behind them? Is biodiversity the specific factor? Which items need to be examined, and what's driving that?

Peter Kerr

executive
#22

That isn't something unique to Koolan, Paul. In fact, the Kimberley region in WA was one of roughly 4 regions across the country flagged in March as biosecurity sensitive. So since we fly personnel through Broome, the state government effectively raised the shutters right away, and we had to supply a great deal of information about the steps we take to make sure our people transiting through Broome — and our people working on Koolan Island — effectively stay separate from, or keep their contact with, Kimberley residents to a minimum. Meanwhile, the state government here announced some fairly strict protections for a number of remote Aboriginal communities in the Kimberley. So there are in fact quite a few restrictions: in 2 of those communities, people aren't permitted to enter, or even if they reside there and leave, there are limits at certain times on their coming back. So it's simply an extra set of rules layered on top of the travel restrictions within Western Australia's regions that the WA government has brought in.

Paul McTaggart

analyst
#23

And all of that being said, those restrictions clearly increase costs — you know, trying to operate specific managed flights, et cetera. Could you give us some sense of how much that may have added to your cost structure?

Peter Kerr

executive
#24

Sure, it’s going to have some effect. One reason we pulled the guidance is that it’s really difficult to pin down, since right now the rules keep shifting for us and our practices are being refined every few days. That said, I wouldn’t point to a single large, clearly identified cost hit. It’s a broad set of things. For example, instead of flying people up to Broome on commercial airline flights — those flights actually stopped, and now only 1 or 2 are being reinstated. But on the flights we do use now, people have to be spread out on the plane. So rather than 5 people in a row of seats, you get 2 or 3. That means the unit cost of transport goes up. The other thing happening is that we’re trying to separate our teams on the site, change a number of practices around meal times, all those kinds of things you’d expect. So those sorts of changes affect productivity more than they directly raise costs. But obviously, the productivity shift matters for us because a large cost on the island is fixed. So if we’re moving fewer tonnes or selling fewer tonnes, then it gets spread across those areas.

Peter Kerr

executive
#25

I realize that's a lengthy, wordy response, but at this moment I can't give you a specific percentage. We're putting in that effort to try to keep the change as small as possible. In the end it may not amount to much, but we want to be sure we've planned it out properly. These changes came together very fast, within just a few weeks. So when that occurs, you just take steps to make sure we can keep operating, and then handle refining the costs afterward.

Operator

operator
#26

That seems to be all, Peter.

Peter Kerr

executive
#27

Okay. All right. Well, thank you, Brie. Thanks, everyone. Thanks, Hayden and Paul. And should any of you have questions, please reach out to either John Phaceas or me. The details are in the quarterly report, and we'll talk to you next time. Thanks.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete MGX Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to MGX Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in MGX Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.