MGX Resources Limited (MGX) Earnings Call Transcript & Summary

April 22, 2021

Australian Securities Exchange AU Materials Metals and Mining earnings 17 min

Earnings Call Speaker Segments

Operator

operator
#1

Thanks for being on today's call about the release of Mount Gibson Iron's March Quarter Activities Report. Leading the discussion will be Mount Gibson's Chief Executive Officer, Peter Kerr, and with him are Chief Financial Officer, Gill Dobson, plus External Relations Manager, John Phaceas. Mr. Kerr is going to give a short overview, and after that you'll have a chance to ask questions. Because of time limits, only institutional participants will be invited to ask questions at that point. A recording of the call will be made available on Mount Gibson's website shortly after today's teleconference wraps up. Please go ahead, Peter. Thank you.

Peter Kerr

executive
#2

Thanks, Bethany, and good morning everyone. Appreciate you being here as we go through Mount Gibson's report for the March quarter. As always, I'll run through a quick overview, then hand things back to Bethany at the end for whatever questions you might have. During the March quarter, our activity centred on the overburden stripping program investment at Koolan Island along with development of the Shine Iron Ore mine in the Mid-West. At Koolan Island, even with record wet season rains, we moved the overburden stripping program forward in the Main Pit fairly well. And that work is still on track for substantial completion in the second half of this calendar year. This program matters greatly to our business, as everyone knows, since it will position the mine to cut costs and lift sales and cash flows considerably for the rest of its life. We also completed the ground support plan for the Main Pit's upper western end footwall and kicked off the crushing plant upgrade. At Shine, progress was very good, and we remain on track to begin initial shipments early in the September quarter. On overall iron ore sales, we shipped slightly more than 230,000 tonnes from Koolan Island, with one extra late quarter shipment in fact pushed into April because of a shipping delay.

Peter Kerr

executive
#3

For the nine months ending at quarter close, group sales came to 2.5 million tonnes in total, which includes 1.3 million tonnes sold from Koolan. That aligns with the guidance we've given for Koolan Island this financial year of roughly 1.8 million tonnes, and for group sales in a range of 2.8 million tonnes to 3.3 million tonnes. Sales revenue was AUD 30 million FOB — we report everything on an FOB basis — which reflects lower sales volumes and grade specifications while the overburden stripping investment is carried out at Koolan. Also worth remembering that sales from the Mid-West operation at our Extension Hill mine site wrapped up successfully in late December. Year-to-date sales revenue for the nine months comes to $269 million FOB. Given the Koolan Island stripping phase and the inventory build, the group's unit cash costs — which capture everything apart from capitalized stripping and capital project investments — averaged AUD 135 FOB per tonne sold, clearly a reflection of that lower sales volume. Cash and investment reserves fell by $24 million during the quarter, standing at AUD 412 million as of 31 March, and the company carries no borrowings. That cash movement reflected a net investment of $34 million at Koolan Island; Shine development costs of $11 million; closure and rehabilitation spend at Extension Hill of $4 million; the Mid-West rail refund, which keeps accruing and coming to us, of $2 million; interest and other income of $2 million; and corporate and admin costs of $4 million.

Peter Kerr

executive
#4

On top of that, we saw a $25 million inflow into working capital that was positive, purely down to the timing of when receipts and payments landed. So let me now go into Koolan Island operations in a little more depth. On mining and production, as we said, the priority is finishing the overburden stripping phase so the site is positioned for materially higher ore sales and for lower costs beginning later this year. We're still on track to hit that goal, even though material movement took a hit during the quarter from heavy rainfall and the lightning interruptions that came with it. In the March quarter we got more than 1 meter of rain, which clearly is quite extensive. And from the beginning of this wet season up in the Kimberly, we've now received in excess of 1.8 meters of rain, which makes it the heaviest wet season since 2007, i.e., under Mount Gibson ownership. Total material movement came to 4.4 million tonnes. Ore production was affected less, coming in at 260,000 tonnes, since output was drawn mainly from the upper western end of the Main Pit, an area less susceptible to wet weather interruptions, though its quality is more variable. On a positive note, waste stripping rates have picked up over recent weeks as conditions have improved, and we anticipate additional gains as the dry season arrives.

Peter Kerr

executive
#5

We've now completed the geotechnical ground support plan for the upper footwall at Main Pit, which lets us safely reach the high-grade ore zone in the western floor of Main Pit later this year. To date, specialist contractors have been brought on board, and they were mobilized to site this month. That program should cost roughly $15 million across the coming 6 months. It will gradually open up safe mining access to the higher-grade western floor of Main Pit. For the near term, medium-grade ore will keep coming from the upper western and eastern ends of Main Pit. The first phase of the crusher upgrade project — estimated to cost us $20 million — is moving along well, with the upgrade design intended to ensure efficient processing of substantially larger volumes of high-grade ore starting later this year. The work is being phased so that we maintain crushing capacity as needed over the months ahead, until the new circuits are commissioned in the September quarter. Now, from a cash flow — sorry, from a cash flow standpoint, Koolan produced operating cash flow of $7 million in the quarter, before capitalized advanced waste stripping investment of $35 million and the other capital projects, mainly the crusher upgrade at $6 million.

Peter Kerr

executive
#6

Site cash costs, which reflect sales and don't capture that shipment deferred at month end, came in at AUD 102 FOB per tonne sold — and that's prior to the waste stripping and capital upgrade projects. As I said, unit costs were clearly distorted by that delayed shipment. Guidance for Koolan cash costs for the year stays at AUD 70 to AUD 75 per tonne sold. Now to our Mid-West operations. We've been focused on developing the Shine Iron Ore Project, situated 85 kilometers north of the Extension Hill mine site, which is now closed. Shine's production is targeted at 1.5 million tonnes per annum across an initial 2-year period. And a further 2 years is possible should conditions stay supportive. Shine's cash costs are expected to average AUD 65 to AUD 70 per tonne FOB before royalties, with the average iron grade at roughly 59% Fe. We'll have both fines and lump products. The site team has progressed very well so far. Work has sped up over the last couple of months. And we're on target to begin sales early in the September quarter. Construction activities at the site are well advanced, and mining got underway during March, ahead of our schedule.

Peter Kerr

executive
#7

Thus far, we have expended roughly AUD 12 million against a projected capital cost of between AUD 17 million and AUD 20 million. Out of that AUD 12 million figure, AUD 11 million was used in the March quarter. Clearly, that is the period when things ramped up. Around $15 million will go toward preproduction and inventory build during this June quarter. During the past week, we began extracting the first ore from the top of the deposit. Alongside the on-site activity, we are continuing to advance the main commercial agreements, which includes possible alternatives to the baseline transport approach — hauling ore by road to our current storage operations at Geraldton Port. As you may remember, for many years we have made our living in the Mid-West hauling by truck and utilizing rail into the Geraldton Port facilities. In the meantime, rehabilitation at the closed Extension Hill site is moving forward consistent with the closure plan, and shifting of staff and machinery to Shine has been carried out where appropriate. We anticipate that a fair share of the current $9 million closure provision — the provision as at 31 December — will be drawn upon across the coming 12 months. Although the bulk of sales in the quarter were booked in the Mid-West business, we did accrue $2 million related to the ongoing rail refund credit I referred to earlier.

Peter Kerr

executive
#8

On the pricing side, I’d like to make a few remarks, and clearly pricing is still remarkably robust. For the quarter, the Platts 62 CFR Index fines averaged USD 167 per dry metric tonne, compared with USD 134 during the previous quarter. Koolan medium-grade fines—and we are of course selling lower-grade material while the overburden program is carried out—recorded an average realized price of USD 106 FOB after penalties. That mirrors the lower 60% average grade for the quarter, which stems from the stripping program, as I noted. Even with shipment volumes currently lower, these iron ore prices still provide a substantial benefit by reducing the net investment we need in order to finish—or rather, to fully complete—the Koolan Island overburden stripping program, and they also point to a considerably stronger economic result for us at Shine. Turning to guidance: for the 2021 financial year, group ore sales remain at 2.8 million tonnes to 3.3 million tonnes. Koolan Island, as mentioned, is expected to contribute roughly 1.8 million tonnes of fine products. Group cash cost guidance for the financial year is unchanged at AUD 65 to AUD 70 per tonne FOB.

Peter Kerr

executive
#9

And that comes on top of what we're investing at Shine to develop that project. Plus the overburden stripping and capital improvement work at Koolan Island. And finally, mainly the crusher upgrade. At the Koolan Island site, cash costs should average between AUD 70 and AUD 75 per tonne sold FOB, not counting the capital investments I just referred to. So to wrap up, although the quarter brought a fair number of challenges, especially the heavy wet season in the Kimberly region, we moved forward with the scheduled overburden and capital upgrade programs, and we are now advancing quickly on developing the Shine project out in the Mid-West. That progress has kept us positioned for significantly better financial performance in the second half of this calendar year. And that is clearly a real focus, since our first-half investments make it possible to achieve stronger sales and cash flows. So with that, Bethany, I'll turn it back to you for any questions anyone may have.

Operator

operator
#10

The operator has just given the instructions, and the first person to ask a question is Paul McTaggart of Citigroup.

Paul McTaggart

analyst
#11

We’d like to understand a little more about the $15 million you have to spend on the footwall work. What I’m really trying to gauge is how confident you are that this will be only $15 million? And will there be any effects or interruptions to mining from that work during this period, because it’s at Shine, and obviously we have this window while iron ore prices are very high. So maybe you could give us a sense of exactly what will happen there?

Peter Kerr

executive
#12

Absolutely, Paul. As you're aware, the footwall project we're undertaking relates entirely to safety and to securing the future of operations in that section of the pit. It came about following the rockfall in the upper portion of that footwall during late October and early November of last year. We've prepared estimates, and naturally we developed them together with a specialist contractor who is now onsite, covering what we believe that work will involve based on the design of where bolting must be placed along that footwall. Precise estimation is therefore difficult, because as we proceed and gain familiarity with that Baltic program — something we've carried out for many years from the pit floor base — well, there's nothing novel about how the work is performed, though work higher up on the pit floor could take some time before we become efficient at it. The contractor we're using is a very good one, handling this across a whole range of applications, mining included. So that's our best estimate at present. Naturally, should we be able to — apologies, should it take longer, then it will cost more.

Peter Kerr

executive
#13

Whether it gets a lot more expensive is still uncertain, in our view. What matters most to us is progressing through that program across the priority zones on the footwall. That way, working in phases, we're able to reach the ground beneath those western end levels.

Operator

operator
#14

Moving on, we have Jon Scholtz from Macquarie with the next question.

Jon Scholtz

analyst
#15

When it comes to the satellite alternatives near Koolan Island, could you share a little more detail on that and explain what would work as we go in there regarding the satellite elements?

Peter Kerr

executive
#16

Okay, Jon — as you're aware, a few deposits have been mined by us before, and there are 1 or 2 where we're assessing whether we can get back into them. Acacia East is one of them. If that works out, we'd be in a position to blend that material together with material coming out of the Main Pit, which is exactly what we did many years back. When it comes to satellite deposits that haven't been mined yet, one stands out — Mangrove, located along strike to the east of the Main Pit. Over the last few months we've been working alongside the traditional owners on heritage clearance and ground clearance for that area. It's been cleared before, but we've gone with a fairly robust approach together with the traditional owners to confirm there are no issues, and that seems to be the situation. So drilling is planned there for this dry season. On top of that, there are further deposits, and one of them — Coral Trout — is where we're doing the same thing with the traditional owners, pursuing the heritage clearance process so that we can drill there as well. Historic drilling does exist at both of those areas.

Peter Kerr

executive
#17

We do have some understanding of the mineralization, though from a mine planning standpoint, we would need to add another program this year.

Jon Scholtz

analyst
#18

Great. And regarding Shine specifically, I just want to clarify: does the rail refund get affected at all by what's happening with Shine's development, or does it come out of Shine? Or are those two entirely separate?

Peter Kerr

executive
#19

Totally distinct, Jon. The rail refund ties back to the arrangements we had previously at Extension Hill, and Shine doesn't affect them.

Operator

operator
#20

<<operator_script>> Thank you. Peter, at this point it appears there are no additional questions. I'll return the call to you now. Thank you.

Peter Kerr

executive
#21

Okay, thanks, Bethany. And I appreciate everyone joining us today. Should anybody have further questions, well, you're aware of how to get in touch with us here at Mount Gibson. Take care, and thanks again.

Operator

operator
#22

Since the person hosting this session has now wrapped things up, you’re welcome to exit by ending your phone connection. We appreciate your participation.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete MGX Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to MGX Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in MGX Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.