MGX Resources Limited (MGX) Earnings Call Transcript & Summary
April 26, 2022
Earnings Call Speaker Segments
Operator
operatorThanks for being on today’s teleconference as we present Mount Gibson Iron’s activities report for the March quarter. Peter Kerr, Mount Gibson’s Chief Executive Officer, will lead the discussion, and he’s joined by Gill Dobson, Chief Financial Officer, and John Phaceas, External Relations Manager. Mr. Kerr will give a brief overview, and after that there will be a chance to ask questions. Because of time limits, only institutional participants will be invited to ask a question at that point. A recording of the call will also be made available on the Mount Gibson website shortly after today’s teleconference ends. Please go ahead, Peter.
Peter Kerr
executiveThanks, Erika, and good morning everyone, and thank you for joining us to go over Mount Gibson's March quarter report. As always, I'll provide a short overview, then hand it back to Erika for questions. The March quarter marked the last period of net investment at Koolan Island, since the major overburden stripping program is close to finishing. That activity, as we all know, has been the main drain on our cash reserves over the last year. We're now seeing rising production rates of high-grade ore, and the stripping ratio of waste to ore has fallen substantially. Together, these 2 factors are essential for us to generate substantial cash flows over the next 5 years. Attention at Koolan Island now centers on lifting high-grade ore output from the main pit ore zones as overburden stripping requirements keep declining. Total material movement for the quarter came to 3.7 million wet metric tonnes, 15% below the prior quarter, reflecting the usual wet season adjustments and the lower stripping ratio, while ore production doubled to 325,000 tonnes. Ore extraction rates have climbed steadily since we regained mining access to the initial high-grade ore zones in the main pit in February, and waste material movement has decreased correspondingly.
Peter Kerr
executiveBeyond that, ground support is being carried out on the upper Western footwall, involving drilling, bolting and grounding work that was pushed forward so mining could safely continue on pit 4 beneath every completed section. As the quarterly report mentions, drilling and bolting for ground support is now finished across roughly 70% of the upper Western footwall zones slated for this work, covering the Western 1 kilometer of the 2-kilometer long main pit. Completion of the remaining Western footwall work is planned for the September quarter, consistent with the mine plan for the underlying mine zones in the pit floor. The waste to ore stripping ratio is coming down as planned. You may remember it stood at 17:1 during the December half year. In the March quarter, it was slightly above 10:1. Another decline is taking place this quarter, so the average strip ratio should come in at about 5:1 for the June half year period. Substantially higher ore production will drive this improvement in the June quarter, with Koolan Island sales still targeted at 1.5 million wet metric tonnes for the '21/'22 financial year.
Peter Kerr
executiveFor the first 9 months, sales came to 0.64 million wet metric tonnes in total, which of course means shipments are going to be very heavily concentrated in this June quarter we're in now. From the midpoint of this year onward, we're looking for the stripping ratio to come in at roughly 1.5 tonnes of waste per tonne of ore across the next 5 years of operations at Koolan Island. When we get to the '22, '23 financial year, our expectation is a strip ratio averaging about 2:1, with roughly 3.5:1 during the first half of that year and then dropping to 1:1 in the second half, based on our mine plans as they stand at this point. As I mentioned, ore production in the March quarter came to 325,000 wet metric tonnes, twice the ore tonnage that was extracted in the quarter before, when we were right in the middle of the overburden stripping program. Total sales were 238,000 wet metric tonnes, and they're on the rise now. The grade on those ore sales climbed significantly as well, moving from below 58% FE in the previous half year up to 62.8% FE in the March quarter, as we blended certain stocks of medium-grade material together with newly mined high-grade ore from the main pit. Around the middle of this year, sales grade should rise to the ore reserve grade of 65% FE.
Peter Kerr
executiveOn the island's other activities, the crusher upgrade wrapped up in December, and commissioning work is progressing nicely as ore throughput rises. Tropical Cyclone Anika disrupted what we were doing in late February and early March, largely because some site personnel had to be evacuated temporarily for several days. Rainfall across this wet season came to 1.2 meters, and we ran into plenty of rate and lighting delays, though conditions were not quite as severe as the prior wet season, when rainfall reached 1.85 meters. The seawall, meanwhile, keeps performing in line with design, as expected. Unit mining, logistics and administration costs, including every transport charge, came to $12.07 per tonne of ore and waste moved — that is per total material moved for the quarter — versus $10.89 in the quarter before, which reflects lower total material movement along with the wet season's impact and some COVID interruptions. Productivity and commercial initiatives aimed at bringing these costs down are in progress. Clearly, unit cash cost per tonne of ore shipped should fall significantly as total mining expenditure comes down and ore shipment volumes go up. On cash flow, net investment for the quarter was lower than before, at $38 million compared with the prior quarter.
Peter Kerr
executiveThat covered more than $29 million in overburden stripping investment, plus other capital investments — among them the $5 million upper footwall ground support program I mentioned earlier. We expect operating cash flows to turn positive in the June quarter and to keep improving after that, as total material movement comes down and high-grade ore shipment volumes go up. Now, on COVID, I wanted to offer a few remarks about the current and potential effects. To this point we have not been immune to the workforce effects of Covid, though fortunately we have so far avoided major disruptions. As with other miners in WA, we have strengthened our screening, testing and transmission mitigation measures. And I acknowledge the positive response from our employees and contractor workforce. That said, possible COVID effects on our workforce pose a risk to near-term operational productivity, especially since community transmission in WA is now at record levels. In recent weeks, Koolan Island has seen COVID-related absenteeism ranging from 6% to 10%. That comes either from people unable to work because they have contracted COVID or because they are close contacts of someone with COVID and must isolate under the WA rules.
Peter Kerr
executiveNow, turning to another part of the company in the Midwest: the Shine site is still being kept in a low-cost care and maintenance mode, and we are watching market conditions in case a restart becomes possible. That said, right now, discounts on medium-grade product, along with elevated freight rates out of Geraldton Port, continue to stand in the way of restarting the operation in the near term. Mac Gibson has also fielded several inquiries about its Midwest infrastructure — specifically rail sidings and storage sheds at Geraldton Port — and we are already collecting some revenue from third parties under certain initial arrangements we have put together. Talks are ongoing about additional interim arrangements to use spare capacity within those infrastructure assets. On the exploration side, as noted before, we have also begun work on our expanded footprint around the former Tallering Peak mine and the areas north of it, roughly 150 kilometers northeast of Geraldton, and we view this area as having attractive prospectivity for base metals mineralization. During the March quarter, detailed field mapping and lag sampling were carried out at 2 key prospects, with assay results from those samples anticipated over the coming weeks. Interpretation of aerial electromagnetic survey data collected over prospective areas in December is also close to being finished, with the aim of conducting some drilling around the middle of this year.
Peter Kerr
executiveTo wrap up, regarding realized pricing and cash flow during the quarter: our sales revenue came to $26 million FOB — and as we report, every figure we give is on an FOB basis. Koolan Island fines achieved an average price, after penalties and shipping freight costs, of USD 81 per tonne FOB. Freight from Koolan to China averaged roughly USD 19 per tonne during the quarter. At today's prices, a Koolan Island fine shipment grading about 63% iron — which is what we've been selling lately — carries a value of approximately AUD 11 million FOB before royalties. The company's cash and investment balance stood at $92 million at quarter's end, and the change across the quarter reflected a net investment at Koolan of $38 million, interest and other income of $4 million, net corporate exploration and minor rehabilitation costs of $4 million, plus working capital movements of 12. So in summary, we're beginning to see the positive changes we anticipated at Koolan Island, where growing high-grade ore output and declining waste-to-ore strip ratios will produce substantial positive cash flow across the rest of the operation's 5-year mine life. That is strategically advantageous for us, given the growing importance of high-grade iron ore feedstocks — notwithstanding the iron ore price drop overnight, which at this stage we hope is temporary, given that it's a COVID-linked issue for Chinese economics.
Peter Kerr
executiveYet this matters to us when it comes to grade, in terms of raising steel mill productivity and cutting the carbon intensity of steel production. Ores of high grade keep commanding a healthy premium over those of lower grade, and we expect that situation to persist over the medium and longer term. So with that, Erica, I'll hand it back to you for any questions anyone might have.
Operator
operator<<operator_script>> At this moment, it appears no questions have come in. We're glad to wait roughly another minute. <<operator_script>>
Peter Kerr
executiveErica, if nobody has anything else to raise, we're glad to wrap up here, since the analysts, investors, and shareholders who track us can simply call us, and we'll be able to answer whatever questions may arise later on.
Operator
operatorSure thing, Peter — that's not a problem at all. With that, I'll go ahead and bring the Q&A portion to a close at this point.
Peter Kerr
executiveExcellent. Very well then. Appreciate everyone, and enjoy the rest of your day.
Operator
operatorThank you. That brings today's teleconference to a close. We appreciate your participation and hope the remainder of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete MGX Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to MGX Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in MGX Resources Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.