Mineral Resources Limited (MIN) Earnings Call Transcript & Summary
October 23, 2026
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone joining, and we’re glad to have you on Mineral Resources’ call about the September 2026 Exploration and Mining Activity Report, which was released today. Speaking today will be Mal Bundey, Independent Non-Executive Chair; Mark Wilson, Chief Financial Officer; Darren Killeen, Chief Operating Officer; and Chris Chong, General Manager, Investor Relations. Just a few housekeeping points before we begin. <<operator_script>> This call is being recorded, and a written transcript will be uploaded to the MinRes website later today. I’ll now pass things over to the MinRes team.
Mark Wilson
executiveThanks, David, and good morning, everyone. Thanks for joining us. I'm Mark Wilson, the CFO of Mineral Resources. With me today are Mal Bundey, our Chair; Darren Killeen, Chief Operating Officer; and Chris Chong, General Manager, Investor Relations. I'll begin this morning with a few opening comments on the quarter before we go to questions. The September quarter once again showed how strong our diversified business model is. We recorded quarterly mining services volumes of 103 million tonnes, a record. We hit record production at both Onslow Iron and the Pilbara Hub, and we delivered record lithium sales. The cost control shown by our teams on site during the quarter was outstanding. Our focus stays on what we can control: operational delivery, cost discipline and a strong balance sheet, allocating capital only where the returns justify it. On governance, in September, ASIC advised that its investigation had concluded and that it will take no enforcement action. We're pleased to have that matter closed, noting it does not change our focus on governance, which remains a priority. Turning to the balance sheet, which continues to strengthen despite softer iron ore and lithium prices. Liquidity improved to $2.5 billion at 30 September, comprising $1.7 billion of cash and a fully undrawn $800 million revolving credit facility.
Mark Wilson
executiveFitch raised our credit rating in September to BB, and the outlook is stable. During the quarter, net debt came down to roughly $4.1 billion, which mainly reflected a $170 million rise in cash. That cash increase came after we spent $310 million on capital expenditure and paid the FY '26 full year dividend of $160 million. In the quarter, FX movements on our U.S. dollar liabilities, other working capital movements and net interest paid were minimal. We continue to anticipate that the POSCO lithium transaction will complete in the first half of FY '27, subject to conditions precedent. Before we move to operations, just a quick note on diesel. Once again, we had no disruption to fuel supply. For the quarter, average diesel prices were consistent with $1.25 per liter in our cost guidance. Prices, though, climbed to about $1.60 per liter in September. And with a 1-month pricing lag, we expect that increase to flow through to FOB costs starting in October. On a run rate basis, just to give you some guidance, that $0.35 increase works out to about $1 per tonne at Onslow Iron, $2 per tonne at the Pilbara Hub and roughly $20 per tonne SC6 at our lithium sites.
Mark Wilson
executiveEven if diesel prices remain where they are, we still anticipate that FY '27 FOB cost will stay inside guidance at each operation, with Mt Marion sitting at the top of its range. I'll cover that in more detail shortly. Just to remind you, diesel prices do not impact Mining Services margins, since fuel cost is typically passed through to the client or supplied by them. Now to Mining Services. Quarterly production volumes rose 10% versus the previous quarter, reaching a record 103 million tonnes. That was driven by the ramp-up of Bald Hill and the Pilbara Hub, along with higher strip activity at Mt Marion. We also started a new external ore sorting contract, renewed 2 existing crushing contracts and wrapped up 2 contracts during the quarter, and we remain on track for FY '27 guidance of between 370 million and 390 million tonnes. In the Iron Ore division, Onslow Iron produced a record 10.3 million tonnes in the quarter, up 17% on the prior quarter on a 100% basis. Shipments from Onslow Iron came in at 9.2 million tonnes on a 100% basis, which works out to an annualized run rate of approximately 36.9 million tonnes. Attributable shipments were 5 million tonnes, or 54% of the total, against a 57% equity share, and that simply reflects shipment timing.
Mark Wilson
executiveAt Onslow Iron, we remain on track with guidance, even after some unusual weather and a 7-day hit from maintenance on the port's load circuit earlier in the period. After that circuit came back online, September became the project's biggest export month ever, at 3.49 million tonnes, beating the prior record from June. Our 7th transhipper entered service in August, and with 7 transhippers in the fleet today, 1 vessel can cycle through planned maintenance while 6 keep operating, which delivers the flexibility and redundancy we were aiming for. The initial stage of dredging at the Port of Ashburton is finished. Activity there picks up again in mid-November, with completion anticipated by the close of the December quarter. We foresee only a minimal effect on volumes. Realizations for the quarter came in strong at 86% of the Platts 61% index, and FOB cost stood at $53 per tonne, under the bottom of our $54 to $58 per tonne guidance range. Once more, we're holding FY '27 FOB cost guidance in spite of today's elevated diesel prices. Over at the Pilbara Hub, output reached 3.2 million tonnes. That represents a 55% increase over the previous quarter, and we shipped 2.9 million tonnes. Lamb Creek has moved smoothly from commissioning into full operations, with all major construction now finished.
Mark Wilson
executiveI’d like to highlight that Lamb Creek really showcases what our in-house engineering and construction teams can do when it comes to delivering quickly. We only broke ground there in December '25. Realizations for the quarter came in at 84% of the Platts 61% index, helped by a higher lump weighting. FOB costs stood at $75 per tonne, consistent with our guidance range of $74 to $79 per tonne. Turning to lithium, we achieved record sales of 170,000 tonnes SC6, an increase of 8%. The average realized price was USD 1,873 per tonne SC6. That represents a 23% decline, driven by the steep drop in lithium prices during September. To put that in context, since most of MinRes' lithium sales occur on the spot market, our realized prices tend to move ahead of the lagging indices. What that means is realizations decline sooner than the indices do in a falling market such as September, and we've generally outperformed the indices when prices are climbing. On top of that, average realized prices would have come in 2% higher if not for prior period adjustments. Keeping a tight grip on costs remains a priority, as you've observed across every one of our sites as we steer through market conditions across the cycle. At Wodgina, sales reached 90,000 tonnes SC6 and all 3 trains ran continuously. That drove a 9% increase in production.
Mark Wilson
executiveStage 3 ore came online during the quarter, and recoveries rose to 70%. We anticipate a steadier supply of clean ore in the second half. FOB cost declined to $674 per tonne SC6, landing within guidance. At Mt Marion, this year is one of transition, with volumes easing as we open the Northern pits. FOB costs are expected to be higher, reflecting reduced volumes and recoveries. Stripping will run at elevated levels this year before the strip ratio falls in FY '28 once underground feed is incorporated. Construction of the flotation plant is underway, and earthworks remain on schedule. Macmahon mobilized to site in July as well, and blasting of the underground decline has begun. During the quarter, opening the Northern pits pushed the strip ratio up. We also saw a larger share of lower-grade contact ore, which brought recoveries down to 52%. Sales came to 58,000 dry metric tonnes on an SC6 equivalent basis. FOB cost was $1,029 per tonne SC6, slightly above the top of our full year guidance range of $960 to $1,020. Given the Q1 result, we expect FY '27 FOB cost to land at the upper end of guidance, as recoveries should improve marginally. At Bald Hill, ramp-up continued through the quarter, and we remain on track for nameplate of 140,000 tonnes SC6 this quarter.
Mark Wilson
executiveAt $1,498 per tonne SC6, our FOB cost reflects a quarter of low-volume ramp-up, and for the full year we expect to land inside the guidance range of $1,000 — sorry, $1,150 to $1,250. To close, FY '27 got off to a strong start, building on how we performed operationally in FY '26. Records were delivered across mining services volumes, iron ore production and lithium sales. Guidance for FY '27 stays in place for every division. Liquidity has risen and net debt has fallen. This quarter demonstrated the resilience of our diversified model, with mining services as its foundation. Given our strong liquidity and leverage positions, we're well placed to capitalize on the large pipeline of opportunities ahead of us. With that, I'll pass it back to Lumi to facilitate questions. Thanks.
Operator
operator<<operator_script>> Our initial question this session is from Matthew Frydman of MST Financial.
Matthew Frydman
analystCould I get some detail on the Mining Services division? Clearly, it's been a robust opening to the year, with volumes running at an annualized pace above 400 million tonnes. I'm curious whether anything specific shifts across the rest of the year that would, I suppose, pull results back within that guidance range. You mentioned that 2 contracts wrapped up in the quarter. Are those significant enough on their own to bring things back into the range? Or, if conditions largely hold steady, should we take it that you're heading toward the upper end of that guidance range — or possibly beyond it, considering potential contract wins and so forth?
Darren Killeen
executiveAppreciate the question, Matt. This is Darren. Look, Mining Services gained from extra mining work at Mt Marion, Pilbara and Bald Hill during the quarter. So we do anticipate lower volumes in the second half. That said, we also expect to keep our guidance in place. So mining activity does decline. We have some seasonality at Onslow that we're factoring into our forecast going forward. So look, we're holding guidance. I wouldn't suggest taking our first quarter results and multiplying them by 4.
Matthew Frydman
analystThen perhaps a comparable question regarding Onslow. Clearly, September was a really robust month — 42 million tonnes per annum annualized from that month by itself following the maintenance. So again, does that serve as evidence of the creep occurring through the system, given that 7 transhippers are now online, and possibly some improvement work was completed at the port over that maintenance window? Yes — how embedded is a run rate like that? Or does it simply reflect sprint capacity at one particular moment during September?
Darren Killeen
executiveThings are going well on the minerals side. As Mark mentioned, we have 7 transhippers, and 6 of them are running at all times. That gives us the flexibility we've been talking about. September brought record shipments, and today we've had some weather that's unusual for the season up there, plus a bit of port maintenance, as we noted. So look, our focus is on getting those assets working hard up to 40 million tonnes per annum. We're heading into cyclone season. That seasonal weather is ahead of us. So look, once again, we're keeping guidance unchanged there, Matt.
Operator
operatorRahul Anand from Morgan Stanley has the next question.
Rahul Anand
analystI have two. I'll likely begin with the Pilbara Hub and then move on to Wodgina. Regarding the Pilbara Hub, I notice you had a greater lump proportion in sales during this period compared with '25, which is your guidance, and that clearly produced a stronger pricing outcome — or rather one in line with Onslow. So my question is, first, why was the fines product realization considerably weaker than Onslow? The second part concerns the profitability of this business. Clearly, in today's market with elevated freight rates, on a cash basis the business is losing money, but you are evidently adding tonnes in the mining services business. And depending on how you allocate sustaining capital, I'm confident you're working through that. You're delivering a result for the business. I just want to grasp where that breakpoint lies. And do you have a view you could share with us on how we ought to think about these volumes? That's the first one. I'll return with an easier one on Wodgina afterward.
Darren Killeen
executiveAppreciate that question, Rahul. Yeah, you've got it exactly right. At current spot pricing for the Pilbara Hub, we're seeing solid support from where we sit on the cost curve. Lamb Creek came online in 9 months. We have lower costs and a higher lump proportion. Correct — Mining Services adds volumes of roughly 55 million tonnes per annum on top of that. There's meaningful strategic value, or option value, in the Central Pilbara that we're advancing. And I'd say that's precisely where our attention sits when it comes to maximizing long-term returns. For the remainder of the financial year, we're expecting 35% on lump returns. That's ahead of what we'd anticipated. So 35% is where lump stands right now.
Rahul Anand
analystAlright, let me turn to Wodgina. On recovery, 70% is a pretty solid outcome. And clearly, cleaner ore feed hasn’t come through yet. Once ore quality gets better, how should we view that recovery? Is there some upside to be had? Or have you already had access to improved ore? What exactly is behind that result?
Darren Killeen
executiveThanks for asking that. So, we've discussed the clean ore feed for a while now, and it's beginning to go into the 3 plants. That means 3 trains are running steadily. Clean ore feed is going to keep going through the second half of FY '26. Wodgina is a world-class asset. Its performance is going to keep getting better. Recoveries stand at 70%, and the team is definitely working on that and on improving it further. We just have to keep an eye on it, and once we know more, you'll hear from us. As we've said before, we're examining expansion options that carry low risk and high return. Wodgina is a great asset.
Operator
operatorOur following question is from Kate McCutcheon at Bank of America.
Kate McCutcheon
analystRegarding Bald Hill, you apparently chose to bring that operation back online with pricing around the mid-$2000 mark rather than, say, $1,600 as we see today. What options are available for you to use there? I understand that you're bringing the operation back up. I understand the approach has involved selling at spot, but wouldn't it be sensible to secure a portion of offtake on the other one? Which elements are flexible?
Darren Killeen
executiveAppreciate the question, Kate. This is Darren here. Well, you're correct that at today's prices, it's marginal. Our attention is on costs. We're on schedule to hit nameplate out there in Q2. At Bald Hill, we'll be ramping up during the first quarter. Bald Hill added 25 million tonnes per annum to Mining Services, which is also in there, comparable to the Pilbara Hub story. And well, we're looking into expansion options that we mentioned before. So we don't -- we see it over the medium term, rather than the short term. Right now, it's completing ramp up, and we're operating at a steady state.
Kate McCutcheon
analystAnd then perhaps building on what you said about the Bald Hill expansion option. So, Mark, during your opening remarks you mentioned a big pipeline of opportunities ahead. If you had to rank them, what are the main ones you have in mind here — organic options or inorganic?
Mark Wilson
executiveKate, when we look at what’s available to us, we consider it in 3 ways. As we’ve said before, our attention is on those internal brownfield expansion opportunities we’re advancing across the portfolio. You’re aware of the Marion opportunities we’re working through with underground and float. We’ve also discussed the Wodgina options at length. Darren just mentioned the Bald Hill expansion. We see every kind of optionality in the Central Pilbara region, given the supply chain we’ve operated there for a long time and the operating experience and skills we have in that area. And as Darren said, we’re stretching or sweating the tonnes at Onslow toward 40 million tonnes per annum. So we view that brownfields growth as a priority, low risk, high return. We also see other opportunities in the domestic Australian market. We’re still working through a range of those with clients and prospective clients. And we’ve previously talked about offshore options. So those are the 3 rings we think about. But right now, our primary focus is simply delivering on those internal brownfield expansions.
Operator
operatorOur following question is from James Redfern at RBC.
James Redfern
analystThanks, just a handful of questions if I may. To start with, on the FY '26 results conference call, there was mention of possible pop-up chances through a joint venture involving a shovel-ready project. I was hoping you could bring us up to date on that — specifically, where things stand for MinRes regarding that potential transaction, I suppose?
Darren Killeen
executiveYes. Appreciate the question, James. So, as we said before — and Mark just walked through our strategy — we're looking at quite a few projects, James. Copper is a commodity we're keen on. Above all, we favour it here in Australia, though we are also reviewing opportunities offshore. None of those has been finalised. We evaluate them against whether they meet the capital allocation framework and whether we can apply the MinRes model — if so, we'd consider it. But right now, plenty of assessment is still underway.
James Redfern
analystOperationally, you turned in a solid quarter, which is great. That said, weaker lithium prices clearly weighed on results, and since you sell at spot, the price right now sits near USD 1,300 a tonne. So how should we think about pricing for the December quarter? Obviously, those levels are considerably below what we saw in the September quarter. I'm just curious what your take is — what's your view on spot prices at the moment?
Mark Wilson
executiveJames, this is Mark. On lithium pricing, our attention over the longer term remains on what the market’s fundamentals show. We continue to anticipate demand growth arriving in periods ahead. CATL released its own projection of a 20% to 30% demand rise for next year. We observe inventories coming down. So the fundamentals, in our view, are present. The market contains considerable noise. Numerous rumors frequently push the price around. We look beyond all that. Our focus stays on what we can control, namely costs and volume.
Operator
operatorLyndon Fagan with JPMorgan is up next with a question.
Lyndon Fagan
analystI'm curious — does the softness we're seeing in the lithium market right now make you any less excited about the lithium expansions?
Mark Wilson
executiveWhen it comes to expansion, we're simply carrying on with the work at each of the assets. At Marion, we're committed and already underway, and that's going to produce a great result for that site. It will push our volumes higher and bring our costs lower, and we'll transition to a single product, SC5. So continuing those expansion activities at Marion delivers a whole range of benefits for us. Wodgina is simply a world-class asset, and we'll keep working with the JV partner there to figure out what those alternatives look like. Just keep in mind that when we consider raising volume at sites, that has the ability to bring costs down. That's really what we want to see across our operations.
Lyndon Fagan
analystThere's one more thing I have to ask about, I just can't resist. So, is CMRG looming in the background for you folks? Or by now have you gotten out of that rack?
Mark Wilson
executiveYes. We have no direct involvement or relationship with CMRG. As far as Onslow goes, most of our volumes have been committed by Baowu as the JV partner for its own mills. In our iron ore business, we only carry small volumes that get traded on the open market. So relative to production coming out of Australia, we're quite small.
Operator
operatorOur following question is from Glyn Lawcock at Barrenjoey.
Glyn Lawcock
analystI just want to get some clarity on the dredging at Onslow. Does that involve only the berth pocket that was already there? Or does it cover the channel? Or are you creating a larger berth pocket, so that a second transhipper can come in while one is still in place?
Darren Killeen
executiveYeah, Darren here, Glyn. Yes, this is something already in place. It sits within the existing channel, and basically it amounts to maintenance dredging. If you'd like to frame it that way, it occurs on a periodic basis. So yes, it's the current pocket, not work tied to expansion.
Glyn Lawcock
analystAll right. Since there wasn't the option to perhaps enlarge the pocket and bring in a transhipper while one is already on-site, is that something being considered at all, just to help a bit — to push slightly more volume through the port?
Darren Killeen
executiveSure — of course, there are several studies examining what Onslow might look like down the road. As we've mentioned before, that's one of them. Right now, though, our attention is on getting the most out of that asset. None of those efforts are moving forward at this point.
Glyn Lawcock
analystOkay, that’s clear. Then about the sell-down to POSCO — I mean, it has really been dragging. Is this still — like — what exactly are we waiting on at this point? Is it just one remaining item? And is it POSCO that hasn’t turned in the paperwork? I’m just trying to get a handle on why this is taking so long.
Mark Wilson
executiveGlyn, this is Mark. A couple of items are still open. Several CPs remain to be worked through, and that includes certain third-party consents. So those simply need to be wrapped up. Even so, as I mentioned, we anticipate that during this half.
Operator
operatorOur following question is from Ben Lyons at Jarden Securities.
Ben Lyons
analystMark, I'd like to start with you, and I want to dig a bit deeper into the cash flow and how capital was allocated. We still have $4.1 billion of net debt while commodity prices are declining, and I noticed cash rose only around $170 million in the quarter, which got a boost from land sales of roughly $50 million and $32 million in proceeds from the carry loan. Of course, the dividend went out and $300 million of CapEx went out, but there were no working capital movements and no coupons on your debt facilities either. So what interests me is the somewhat weak cash that was added to the balance sheet despite the strong operating performance, and whether anything else lumpy was in there that explains it. And second, are those unsuccessful Pilbara gas carbon -- gas wells included in the CapEx or in the expense?
Mark Wilson
executiveBen, on the cash and the balance sheet, look, we feel really good about where we stand. Over the past 12-plus months, we've demonstrated our capacity to bring down debt. I'd note that one of the ratings agencies recently upgraded us, reflecting their take on how we're managing the balance sheet. On leverage, we're comfortably under our target. Liquidity stands at $2.5 billion. We're producing cash. Our earliest maturity is October '28. I think the 2 refis we completed last year, or across the last 12 months, show the backing we get from our debt partners. So I'm at ease with where we are. I'm at ease with where we are.
Ben Lyons
analystTo confirm, there wasn't anything else unusually lumpy during the quarter that we should factor in, and regarding the gas wells, did they fall under CapEx or under expenses?
Mark Wilson
executiveRight. So at this point those have stayed within CapEx, though we'll take another look once we reach the balance state.
Ben Lyons
analystSure, neither one worked out. Turning to Wodgina and the expansion projects in that area — from what I recall, you were looking at extra grinding capacity, possibly putting in a ball mill at the front end. And the other one was a possible fourth concentrator. So I'm just curious whether you could give us a bit more detail on the projects the studies are evaluating right now, and whether that's captured in the fiscal '27 CapEx guidance as it stands?
Darren Killeen
executiveBen, Darren here. Thanks for asking. Look, you're exactly right about those 2 upgrades you mentioned. So they remain underway, with completion targeted for Q3. We've said before that these upgrades aren't mutually exclusive. We have the option to pursue both or take them one at a time, based on what the market tells us, what — we haven't yet talked with our JV partners about how this would look and when we'd act and make calls on them. But Q3 is the point when we'll have sufficient information to make that evaluation.
Operator
operatorOur following question is from Mitch Ryan at Jefferies.
Mitch Ryan
analystCould you remind us what the carrying value is for the Perth Basin JV? And with Hancock having pulled out of it, are there any implications we ought to be considering?
Mark Wilson
executiveRight, there’s essentially no value and no carrying value attached to the Perth Basin JV. Hancock’s decision doesn’t really carry any implications for us.
Mitch Ryan
analystMy second question concerns the expenses tied to transhipper maintenance. What treatment will those receive? Could you quantify them in some way? Are they material in any respect?
Mark Wilson
executiveRight. It doesn’t matter in any respect. That cost is built into the Mining Services margins. We expense it, and everything is reflected in how we plan for our Mining Services operations.
Operator
operator<<operator_script>> Our following question this afternoon is from Lachlan Shaw at UBS.
Lachlan Shaw
analystI've got two questions. First, I'd like to dig a bit deeper into the growth you're seeing in Mining Services tied to copper. What I'm curious about is how you weigh the trade-offs between, say, a lower-risk incremental path — picking up a handful of contracts in CSI — versus something more structural, like taking equity in an asset and pairing that with contracts that could potentially run for the life of the mine. How do you think through that balance? Second, on jurisdictions — clearly your culture is a defining feature of who you are — but with new jurisdictions, I'm interested in how you're thinking about those and the chance to replicate that successful culture in some of these new jurisdictions. I'll come back to the second question.
Darren Killeen
executiveWell, Lachlan, on your first question — our capital allocation framework, which we've already laid out, basically establishes the return levels we require, and so on. We've said before that South America is a region we favor. So when it comes to jurisdiction, South America appeals to us, and Chile appeals to us. But the work still has to be done — all the things you'd expect when operating in that country and those regions. So the capital allocation framework will determine whether we pursue an Australian project onshore, and onshore sits first and foremost in our strategy. And if it's offshore, then we apply discounts for factors like jurisdiction, like whether it's copper, whether it's iron ore. There's a whole set of criteria we've established to ask, well, is it right for us? And can we deploy the MinRes model, and can we win.
Lachlan Shaw
analystThanks, Darren. This is my second question. So, on Onslow specifically, it’s obviously quite encouraging to see the September run rate. But as you look toward pushing to 40 million tonnes per annum and perhaps past that, could you remind us of the largest opportunities you see ahead? Is it autonomous trucks? Is it additional debottlenecking at the port? And how should we think about the timing of those — of that kind of potential pathway?
Darren Killeen
executiveSee, the run rates we're getting — we regularly reach that 40 million tonnes per annum mark. It really comes down to consistency, right? So weather is largely something we can't control, but we have plenty of historical data that informs what we do. So, understanding the seasonality, TSV — the system is built so that the ship loader is the bottleneck, right? So we've done a lot of work on the ship loader: how do we boost throughput through the ship loaders via the reclaimer, and how do we make the most of our TSV? So those 7 TSVs give us the sprint capacity we've been after. It lets us carry out maintenance on the cycle times we've been seeking. So, focusing on sweating those assets to 40 million tonnes per annum really comes down to how we use the transhippers and how we handle the sea states.
Operator
operatorMatthew Frydman of MST Financial has the next question.
Matthew Frydman
analystThanks for giving me the chance to ask a few more questions. I mainly wanted to pick up on some of the earlier questions about the potential for additional lithium volume expansion. And Mark, of course, you talked about the medium- to long-term fundamental outlook for the lithium market. And of course, you're aiming to move the expansion work forward at Wodgina, specifically the detailed design work, during this quarter. So I'm wondering how you, internally and together with your JV partners, including POSCO, evaluate market conditions and pricing before you commit to adding that extra volume? I'd suggest that your capital intensity is likely lower compared with some of the other expansion projects out there in the market. So perhaps the price required to generate attractive returns is arguably lower than it is for some peers. But yes, are there any kinds of thresholds regarding what you need to see in the market when you're assessing the timing of investing in further expansion? Do you have a sort of floor price in your analysis regarding what you need to see in order to clear your hurdle rate?
Matthew Frydman
analystAnd I suppose, when it comes to the timing of committing to further expansions, do your JV partners view the market the same way?
Mark Wilson
executiveAppreciate you sending in 25 questions. I'll do my best to keep half of them in mind.
Matthew Frydman
analystSorry about that.
Mark Wilson
executiveNo, no, everything's fine. Actually, you've pointed to one of the key elements in your question — namely that, compared with others, our capital intensity is considerably lower when we examine these opportunities. That's among the major benefits of our model. It stems from decades spent operating in Western Australia carrying out what we do. And something else it provides is a strong degree of confidence when we set about the work. So when we undertake the work, we hold a strong degree of confidence that it will be delivered at the price we report, since we self-perform. That therefore gives us a strong degree of confidence when we run our analysis. As it happens, the kinds of opportunities we are reviewing all generate, or are all projected to generate, very high returns even under conservative commodity prices. It won't surprise you that we assess across a range of scenarios. We do that internally. We generally adopt a conservative stance on commodity prices, especially for something like lithium, where volatility has been somewhat greater. So we try to reason through matters of that kind.
Mark Wilson
executiveHopefully that provides some sense of the situation. Still, as you noted, these are JVs, and our task is simply to continue collaborating with our joint venture partners; should we decide to move forward, we will inform the market at the appropriate time.
Matthew Frydman
analystAppreciate it, Mark. That probably took care of the bulk of those 25 questions, so thank you.
Operator
operatorGlyn Lawcock with Barrenjoey has the next question.
Glyn Lawcock
analystMark, I'd like to dig into the copper opportunity a bit further. Do you view this as a fee-for-service arrangement, maybe on the design and build side? Or do you see yourselves having to commit your balance sheet to this project? And if that's the case, how much would you be comfortable spending, given the present debt level on the balance sheet — POSCO will obviously be coming in soon, but also the current pricing environment? I'm just trying to get a sense of how you're approaching it. Is it fee-for-service, or will you actually need to put your balance sheet in and get equity back?
Darren Killeen
executiveGlyn, Darren here. So look, typically if we're going to do this, what we want is to take equity and earn in. As you've witnessed through the years, the ways we've accomplished that are numerous — there are plenty of approaches we've used. Mining Services has to be a central component of it. Build and operate also needs to be a central component. And — I keep saying this — we have to unleash the model, correct? MinRes therefore must be in a position to win, and winning means delivering Mining Services volumes, delivering the Mining Services model, and drawing on the unique skill set we possess to earn our way into these projects, using that MinRes currency so we can deliver the returns we're after. So I'm probably not truly answering your question, but we have to unleash the model, and Mining Services needs to stay at the front of all those conversations.
Mark Wilson
executiveGlyn, this is Mark. I’ll jump in here — beyond what Darren just mentioned, I think the capabilities our business holds give us considerable room to maneuver in how we go after any opportunity. Ideally, we’d partner with parties where we can offer our build-and-operate design and engineering solutions. At the core, we have to aim for an after-tax IRR of at least 20%. But, you know...
Glyn Lawcock
analystI suppose...
Mark Wilson
executiveWhat I'm laying out in that answer, Glyn, reflects how we operate as a rule. I'm not referring to any particular opportunity in this case.
Glyn Lawcock
analystThat makes complete sense. And I suppose whatever chance might present itself, since it sounds as though you'd commit your balance sheet to it. All of that would come on top of the '27 CapEx guide and, quite obviously, in all likelihood carry over into '28.
Mark Wilson
executiveYes. Look, our guidance for '27 doesn't include any investment of that kind. If we did move ahead with an opportunity like that, you can assume there would be CapEx spread out over a period of time. It wouldn't necessarily be a lump sum upfront. But again, I'm being very speculative here.
Glyn Lawcock
analystIs there any sense, though, of what the ceiling might be — what that opportunity could end up costing us?
Mark Wilson
executiveI won't attach any figure to something like that, Glyn. When the moment comes, we'll evaluate it against how our balance sheet looks then and where the business stands.
Operator
operatorThat wraps up all the questions we have, so today's call ends here. If anything else comes up, feel free to contact the MinRes team with your follow-up questions. You can go ahead and disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Mineral Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Mineral Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Mineral Resources Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.