Minerals 260 Limited (MI6) Earnings Call Transcript & Summary

October 27, 2026

ASX AU Materials Metals and Mining earnings

Earnings Call Speaker Segments

Nicholas Read

unknown
#1

Appreciate you all holding, and welcome to the Minerals 260 September 2026 quarterly webcast. Nicholas Read here, from Read Corporate, and I'm really pleased to bring in Minerals 260's Managing Director, Luke McFadyen, to lead today's call. During the webcast, Mr. McFadyen will give a short overview of the September quarter, and after that we'll open things up for online questions. Should you wish to ask something, just click the live Q&A tab on the right-hand side of the webcast screen. Just a note that a recording of this webcast will be posted at the same link later today, and it will also be available via Minerals 260's website and social channels. I'll now pass things to Luke, who will take us through the quarterly highlights before we move to questions. Luke, over to you.

Luke McFadyen

unknown
#2

Good afternoon, everyone, and thank you for tuning in to Minerals 260's inaugural webcast covering the September 2026 quarter. As Nick mentioned, my name is Luke McFadyen, and I serve as CEO and Managing Director at Minerals 260. I'll walk you through this quarter's highlights, covering both the company overall and the Bullabulling Project specifically, and afterward I'll field questions submitted shortly before this call began, followed by questions coming in live during the call. This quarter marked another pivotal period for Minerals 260, since it was our first as a member of the ASX 200, and we kept advancing DFS early construction work on the village and water, staying on schedule to deliver the DFS and FID for the village early in the new year. We brought in a further AUD 420 million of funding via another outstanding agreement with Franco-Nevada, and a AUD 250 million equity raise completed our inaugural grade control program, carried our exploration forward, and grew our tenement package by close to another 300 sq km. We ended the quarter with a pro forma cash balance of roughly AUD 600 million. That leaves us exceptionally well-funded to keep progressing and de-risking development at Bullabulling ahead of FID, which remains on track for the first quarter of calendar year next year.

Luke McFadyen

unknown
#3

Turning to funding, we achieved significant progress on that front, and it positions us very well to keep carrying out the pre-FID expenditure as set out in the PFS. First, we closed an additional AUD 200 million strategic financing package with Franco-Nevada. This consisted of AUD 170 million in additional royalty financing and a AUD 30 million equity investment. For anyone unfamiliar with them, Franco-Nevada ranks among the most highly regarded names in precious metals finance, and in our view this represents a solid vote of confidence in Bullabulling, reflecting the thorough due diligence Franco-Nevada carried out on the PFS as well as the new resource. Following that, we brought in AUD 250 million via a two-tranche equity placement. Existing institutional holders, Franco-Nevada among them, gave us robust backing, and we were glad to add several new domestic and international institutions to the register. Taken together, these two steps leave the company strongly placed as we work toward completing the rest of the funding needed to reach first production, which we anticipate will be done through conventional project finance. It is also worth pointing out how we have drawn on Bullabulling's distinctive characteristics — a long life, large scale and high margin project — to pursue a financing approach that very few others could pull off, one that lowers the cost of capital and delivers not just greater asset value but also builds and protects shareholder value over the long term.

Luke McFadyen

unknown
#4

For Bullabulling in particular, we picked up a bit more than 350 sq km by way of additional tenement acquisitions, and that keeps giving us optionality across exploration, infrastructure and water. The project footprint now spans 1,500 squares, versus the 130 squares we acquired in April 2025. As everyone knows, resources and mineralization don't end at tenement boundaries, so at this point we're unconstrained to both the north and the south, which offers strong optionality for future resource growth. On the approvals side, we're still making really solid progress. Our expanded mining lease came through during the quarter, and together with the other mining leases already in place, it now covers the whole mining and processing area set out in the PFS. The remaining approvals, as we discussed in our quarterly report, stay on the WA State pathway and are being assessed. All the documents are in place. Engagement has been very positive, and we expect the required approvals to arrive in time to support FID early next year. On early works, as a lot of you are aware, we secured initial approvals last quarter to start construction on site for both the village and the water infrastructure. Village construction is tracking to plan, and to such a degree that the board recently gave the go-ahead for manufacturing and installing another 200 rooms, lifting capacity to 600, which is sized for our longer-term production case.

Luke McFadyen

unknown
#5

The village should be up and running completely by Q1 of next year, which lines up with when major construction work is set to begin. We felt a great deal of pride when we received approval to call the village Champions Rest, honoring a well-known family in the Marlinyu Ghoorlie Native Title group. Inside Champions Rest, there's a section known as Brian's Garden — named for an elder, Brian Champion — where native plants will be grown, acknowledging how strongly the group is tied to this land. This is something we're absolutely delighted about, and our ties with the Marlinyu Ghoorlie are strong. Water infrastructure is also moving forward. Across the project, 22 bores have gone in. Test pumping is taking place, and water exploration is continuing following positive results. Purchase orders for long lead items are set to be issued this quarter, further reducing schedule and capital cost risk. As for the DFS, the technical studies feeding into it keep backing up the PFS and are even enhancing it in certain areas. Our inaugural grade control program of 26,000 m has been finished, and gold grades overall matched the drilling and the data underpinning the 6.2 million ounce resource. A second grade control program is due to get underway soon as well.

Luke McFadyen

unknown
#6

Additional findings from this quarter keep validating the mineralization contained in the resource plus extensions outside it, and we're still seeking to upgrade inferred resources into indicated. Regarding geotech, the DFS test work has finished, and we anticipate it will back steeper pit wall angles within fresh rock for the DFS itself. On the metallurgy and processing side, testing finished so far keeps backing the comminution and recovery assumptions used in the PFS. In summary, we're very well-funded, with roughly AUD 600 million in pro forma cash, and Franco-Nevada is a long-term strategic partner that will hold more than 5% of our capital following the recent equity raise. Our confidence in the resource keeps building as that initial round of grade control drilling validated the resource, and a second grade control program is set to begin shortly too. Early works on both the village and water keep advancing according to plan, and we're on track to place long lead item orders this quarter. Continuing technical work keeps de-risking the project, and we remain on track to deliver the DFS in the first quarter of next calendar year. Thanks very much, and now we'll move to questions.

Nicholas Read

unknown
#7

Much appreciated, Luke. We're moving on to the online Q&A portion now. A quick note for all of you listening in: if you'd like to send us a question, please use the live Q&A tab located on the right side of your screen. A number of questions came in by email beforehand, so those will be addressed first, and where questions are similar we'll try to merge them so we use our time efficiently. Luke, here's the first one. An investor notes that recently you've spoken in more upbeat terms about the expansion case goal of 200,000 oz per annum. What is behind that confidence, and what has shifted since the PFS?

Luke McFadyen

unknown
#8

Okay, Nicholas, the main point is really the resource. For the PFS, we relied on the 4.5 million ounce resource. With the DFS, that figure becomes 6.2 million ounces. And inside that, the indicated portion goes from 3 million up to 4.4 million, and that will back a reserve upgrade alongside the DFS early next year. So the resource base is considerably bigger, which hands us more optionality and more opportunity when it comes to the expansion itself.

Nicholas Read

unknown
#9

Much appreciated, Luke. We have another question now. A few of your Goldfields peers have flagged grid power problems in their latest quarterly reports. What steps will you take to shield the project from comparable troubles while it's being built and afterward, once it's producing?

Luke McFadyen

unknown
#10

Well, look, none of this is new. Grid stability in that region has been widely known for several years now, and we've picked up lessons from the others drawing on that grid power. Our power setup is going to be off-grid—an off-grid hybrid combining diesel generation, solar, battery, and wind. We'll construct it independently of the grid, and that takes away essentially all the risk to us from anything occurring on the grid itself.

Nicholas Read

unknown
#11

Great, thank you Luke. Moving on to the next question. Minerals 260 put out an exploration update earlier this month. How do you plan to factor the recent drilling into the DFS and the mine plan, particularly the high-grade trends you've been identifying?

Luke McFadyen

unknown
#12

So yes, the drilling keeps backing up and building out our resource as well as our future reserve. Whatever feeds into a future resource is going to come out once the DFS is done. The DFS resource stands at 6.2 million. A fresh reserve will be generated from that resource, and all of today's work is aimed at the resources and reserves that come later.

Nicholas Read

unknown
#13

Thanks, Luke. Moving on to the next question. CapEx inflation is a hot topic right now in the resources sector. What are you observing on that front as between the PFS and the DFS?

Luke McFadyen

unknown
#14

Well, I think it's worth keeping in mind that many of the prices in the PFS were shaped by market tenders. What we've managed to do is keep supporting that tender process and those prices in our DFS. We haven't observed any significant shift. As I said in my introduction, by ordering long lead items — a considerable capital cost — we'll further de-risk the capital estimate as we secure those prices before next year. We have an investment of AUD 70 million to AUD 80 million in the village, and it's a fixed price. That capital cost won't be changing. We're very aware of inflationary pressures throughout the environment. But right now we're actually seeing something broadly consistent with the PFS, so no material movement.

Nicholas Read

unknown
#15

Thanks, Luke. We have a handful of questions on funding, and I’ll kind of merge them together, around how you’re viewing your funding from this point on. You’ve said funding will probably come from traditional sources — the remaining portion via conventional project finance. How have the banks been engaging since the Franco royalty and equity raise? Could you give us a sense of where that process currently stands?

Luke McFadyen

unknown
#16

Yeah, look, it's been favorable. I think after the equity raise and the additional investment from Franco-Nevada, outside funding sources only keep gaining more confidence, since a company like Franco-Nevada that has placed AUD 420 million into the business over the last six months, with two thorough due diligence processes, is key. It only brings internal and external confidence regarding what we're doing. We expect that process to wrap up in support of our FID process or FID timing in the early calendar year next year.

Nicholas Read

unknown
#17

Great, thank you, Luke. We have a question here specifically about the SPP that wrapped up not long ago. Your target was AUD 30 million. Could you walk us through how that turned out and share your thinking on those results?

Luke McFadyen

unknown
#18

Look, we've consistently been a business that values and appreciates its retail investor base. That group accounts for 20%-30% of the register on its own. When we did the placement, we made the SPP available as part of the identical arrangement with the institutions. We feel it's simply fair to show respect to those shareholders. The gold price fluctuates sufficiently that it pushes the offer price higher than spot. Given how the offer price compared with the share price, the result was entirely unsurprising. We put that offer forward to keep things fair and equal for everybody, and that isn't how it turned out. What matters to us is that AUD 30 million is, relative to the overall funding cost, immaterial. It causes no harm to our strategy. It has no bearing on how we approach funding the business. Naturally, you always hope it will succeed, but here it didn't, and yeah, we move on quite fast.

Nicholas Read

unknown
#19

Thanks, Luke. We have a question about diesel. It asks whether the all-in sustaining costs, or AISC, in the PFS appear reasonable at AUD 2,500 an ounce. Recent quarterly reports from peers have revealed elevated diesel prices, especially, driving costs higher. How are you factoring diesel prices into the DFS?

Luke McFadyen

unknown
#20

For the PFS, we relied on a market price along with the forward curve. Once more, we had live tender responses covering the diesel price over the short term, and for the longer term we applied the forward curve. The rationale behind that choice is that if we genuinely wanted to hedge diesel, we have the ability to do so, and the forward curve is what we'd use for it. We'll apply that same approach in the DFS too. Whatever the forward curve turns out to be, that's what will be reflected in the DFS. We aren't shielded from any of the costs working their way through the industry. I'd say it's a good thing today that we aren't producing, since not purchasing diesel at scale over the next two years represents meaningful risk mitigation. That said, naturally, should the forward curve prove wrong two years from now, then yes, something would be different. Right now, the forward curve is the best indicator available, and as I mentioned, if we truly wanted to, we could purchase the diesel at that price today.

Nicholas Read

unknown
#21

Great, thank you Luke. My question is about approvals. Getting approvals is essential for reaching FID and moving into construction. The question is this: "I understand that all of them have now been submitted through the WA State pathway, but what makes you confident they'll be granted on a timely basis?"

Luke McFadyen

unknown
#22

Sure, that's a fair question, and it's clearly a hot topic across the industry right now, especially with what others are doing. Just as a reminder for everybody listening, this project was up and running during the 1990s for a few years. Since then, across its whole history, it has consistently received approval to proceed. Earlier this year we were granted what's known as an MDCP and works approval, which supports building the village. After that, our mining lease was expanded and granted during the last quarter. Where the remaining approvals needed for the major construction phase are concerned, engagement has been entirely positive. We've therefore had multiple rounds of consultation with the department. The historical mining area, the existing mining lease, and the engagement with traditional owners all combine to leave us very confident. The exact day they arrive, naturally, is never certain. The guidance we've received regarding FID is sensible and reasonable. That said, we've found the engagement with the department and the government encouraging so far. So that's the source of the confidence we have.

Nicholas Read

unknown
#23

Thanks a lot, Luke. We're making progress. There are only a handful of questions left now. First off, does the company intend to pick up any additional tenements in that area?

Luke McFadyen

unknown
#24

No, I think we're in a pretty solid spot. With 1,500 squares, the geologists have plenty to keep them occupied. Our teams are out today searching for targets across those new tenements. From a gold mineralization standpoint, a water standpoint, or a project footprint standpoint, I don't feel we need additional tenements. What we've picked up today has been highly strategic and very important — that's clearly why we've done those first — but I don't see anything else coming forward down the road.

Nicholas Read

unknown
#25

Luke, we have a question here. All right, let's take a look. Just going through these. I believe the tenements have been addressed. Okay. The question asks: given that your recent expansion of tenure is clearly a positive for the potential to grow the resources, does that provide any further advantages or flexibility when it comes to infrastructure, such as power or extra water access? I think that pertains to the tenements there.

Luke McFadyen

unknown
#26

Yeah, that’s a view we’ve held from the start. We’ve consistently evaluated tenement purchases with two things in mind: first mineralization, next water, and afterward infrastructure flexibility for both the 5 million ton scenario and the 7.5 million ton scenario. That’s the way we’ve always approached it. That’s the reason we’ve been intentional about expanding our tenements north, south, and east. Obviously, our ore body dips to the west. Tenements on the western side hold less appeal for us compared with, say, tenements to the east, north, and south.

Nicholas Read

unknown
#27

Great, thank you very much. All right, moving on to the next question. Do any changes need to be made to MDCP 2 and the works approval in order to run Bullabulling at 7.5 million tons per annum?

Luke McFadyen

unknown
#28

No. The permits we’re going to receive for the first build already cover the expansion scenario. That includes the waste dump footprint, the tailings dam, and the village—which, as you know, we’ve just grown to 600 rooms. Every one of those is tied to the longer-term expansion case. No, nothing else will be needed in terms of approvals beyond that.

Nicholas Read

unknown
#29

Alright, Luke, let's take one more question. This one's fairly detailed and concerns water. There are 22 water bores, along with test pumping results up to now. During a recent site visit, we observed some solid flow, which gives us confidence. How confident are you in the yield and the water quality, for both the base case and the possible expanded case?

Luke McFadyen

unknown
#30

Right, so we keep on with exploring, putting in bores, and after that testing those bores. What we've observed so far has come in above what we first expected, on both the north and south sides of the project itself. Quite recently we widened the water exploration effort to back the expansion case. So yes, we'll keep de-risking water right through the coming year. But thus far it's looking good. It has gone beyond our expectations.

Nicholas Read

unknown
#31

Great, Luke. I’m working my way down the list here. I believe we’ve handled essentially all of it. It seems every one of those questions has been addressed, so let me return things to you at this point. We’ll bring the Q&A portion to a close and maybe share just a couple of final remarks.

Luke McFadyen

unknown
#32

Thanks, Nicholas. And thank you to everybody who joined us for our very first webcast — we appreciate you spending the time with us. As a closing note, we're making rapid progress at the Bullabulling Project. Final investment decision isn't many months off at this point. On the funding side, things are firmly under control, and the final piece of the puzzle will arrive in time for FID. Approvals are proceeding according to plan. Construction work is on track. We look forward to bringing you an update following another busy quarter, in a couple of months' time. Many thanks.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Minerals 260 Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Minerals 260 Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Minerals 260 Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.