Namib Minerals (NAMM) Earnings Call Transcript & Summary
October 1, 2026
Earnings Call Speaker Segments
Tulani Sikwila
executiveThanks, Dan, and good day to all of you. I'm glad you could join us for Namib Minerals' First Half 2026 results. I'd like to begin with a look at what Namib Minerals has accomplished since the last call, and then I'll update you on How Mine, Redwing, our development strategy, and how we're funding the plan along with our priorities for the rest of the year. Following that, I'll pass things over to Sphe, who will walk you through our financial performance in greater detail. Throughout Namib Minerals, the first half of 2026 delivered both progress and continued investment. Turning to the financials, our results benefited from a considerably more favorable gold price, and the cost and efficiency initiatives implemented throughout the company began showing clear results too. Underlying earnings saw a step change improvement. Revenue increased 40% to $50.8 million. Gross profit doubled to $27 million, representing a 53% margin; adjusted EBITDA rose 76% to $19 million. This was driven by a substantially stronger gold price, and we delivered it while production costs were lower in absolute terms compared with a year earlier. Regarding operations, How Mine produced 11,373 ounces in 2026 H1, which is 11% below the 12,741 ounces turned out in 2025 H1. The main factor was the grade coming in at 1.7 grams per tonne compared with 1.9 grams in the prior year on <<inaudible>> the same tonnage. With that first half behind us and the expanded mill contributing for only a portion of the fourth quarter, we are updating our full-year production guidance as of today. I will provide the figures and the rationale in a moment. From a strategic standpoint, 2026 H1 and the weeks that have followed have moved the company ahead. Dewatering at Redwing was completed on September 21, 2026, which was earlier than the fourth-quarter target we released in July. We had released development time lines and milestones, referred to as the Development Milestones, for Redwing's development. We're now moving up the timeline for resuming output at Redwing, and I'll get into that in a bit more detail shortly. Internally generated cash flows will pay for the restart, with the First Goal aimed at no later than January 2027. We've also maintained our disciplined funding strategy, partnering with local banks to obtain facilities for development milestones without issuing new equity. How Mine continues to serve as the operating base of Namib Minerals and the main production source across our portfolio at present. In the first half of the year, output was impacted by lower grades and a modest decline in tonnage. Throughput and recovery remained fairly steady. The mill has been the limiting factor for the mine. During the first half we put 233,000 tonnes through the mill, and that's essentially all the current plant is able to handle. With grades dropping the way they did, you can largely compensate for the lost ounces by running more tonnes. The expansion does away with that bottleneck. It takes our throughput from roughly 40,500 tonnes per month up to 55,000 tonnes per month — an increase of around 36%. Installation of the added processing capacity is more or less complete. The mill is now in position, and recommissioning checks are underway at the moment. We're expecting to commission in mid-October. That sits within the second-half schedule we laid out earlier. Even so, it has slipped past the production plan and falls short of what our initial guidance had assumed. We're expecting a ramp-up spanning six to eight weeks, so the expanded plant should be running at full rate by the end of December. For our business, this marks a significant milestone. The extra capacity will deliver a meaningful boost to throughput, and it will allow our existing cost base to be spread over larger production volumes. For 2026, our original guidance was 28,000 to 31,500 ounces. To reach even the low end of that range, we would have needed additional production during the last months of the year, when the expanded plant can run at full capacity—and full capacity won't be achieved until later in the quarter. As a result, we are cutting our full-year 2026 production guidance to 26,500 to 27,000 ounces. That range assumes commissioning in mid-October, a ramp-up period of 6 to 8 weeks, and head grades between 1.7 and 1.9 grams per tonne. Sphe will speak to what this means for our cost guidance. This revision is about timing in 2026—it is not about the asset's capacity. With the expanded facility operating at maximum capacity, How Mine is capable of achieving an annualized output exceeding 30,000 ounces at the grades currently being mined; that is the pace we anticipate carrying into 2027, and official 2027 guidance will be provided during the first quarter. As Sphe will explain thoroughly, substantial advancement has likewise occurred on the cost front through a more disciplined procurement strategy and efficiency gains throughout the operations aimed at simplifying the underlying cost structure. A significant share of How Mine's cost structure is fixed, so when output fell during the first half of the year, those expenses were spread over fewer ounces. As a result, the absolute savings we achieved have yet to appear on a per-ounce basis. Unit costs ought to improve as the expanded plant ramps up through the fourth quarter and into 2027. Now to Redwing, where we have an important update. Back in July, we published the Development Milestones as a restart pathway for Redwing, under which we stated that production would come after completion of the definitive feasibility study. Production will now be brought forward. I want to explain the reason, since this represents a change from what we communicated previously. Zimbabwe's Ministry of Mines and Mining Development recently put out a policy framework. It says foreign-owned operators must be operating above set production and capital investment thresholds by January 1, 2027. How Mine is already operating above those thresholds. Redwing and Mazowe don't meet these specifications, since they're in care and maintenance. The policy lays out a clear time line, and we've chosen to meet it. Our aim is to reach first production at Redwing in January 2027, beginning at reduced capacity and at a rate above the prescribed thresholds. Two reasons make that achievable. First, dewatering finished ahead of schedule, so we now have access to the underground workings. Next, at the time Redwing went into care and maintenance, it already had mining zones prepared for extraction, plus underground infrastructure and processing facilities in place. The first phase of restarting restores areas that were previously developed and mined. It depends on the plant we already have and isn't contingent on the feasibility study's outcome. The restart effort runs for three months, starting in October. Before we resume any mining, a comprehensive geotechnical audit of the historical mining areas will be conducted. Preliminary inspections have been positive, but the audit is the deciding checkpoint. We'll reequip those areas, refurbish the current processing plant, and onboard the workforce. I'd like to address three questions head-on. First, is the feasibility study being bypassed? It is not. Phases 2 through 5 of the Development Milestones pathway stay exactly as they were. The technical feasibility study program, which has full funding, is still expected to finish in early Q1 2027, and both the resource definition and the DFS should be completed in Q4 2027.
Tulani Sikwila
executiveTaken as a whole, those two things will establish Redwing as a large-scale operation, and no decision regarding that bigger development, or capital for it, will be made before the study concludes. The initial restart sits as a separate work stream beside the pathway rather than substituting for it. Where does the money come from? Our cash flow resources are what we are using to fund the restart. There is no plan for any new equity issuance to finance the initial start. Does 2026 guidance shift as a result? It does not. We do not expect the initial restart to make a material contribution to 2026 production. And the revised guidance I just provided covers How Mine only. Redwing's expected contribution will be included at the time we issue the 2027 guidance. In July we also reinforced the company's leadership and governance. Sphe Mchunu was appointed Chief Financial Officer while continuing as General Counsel. Since 2020 Sphe has been closely involved in Namib and its predecessor company, and took a central role in our business combination and NASDAQ listing. We were also glad to welcome Wendy Luhabe to the Board as Lead Independent Director. Wendy brings over 3 decades of board leadership plus substantial experience in development finance and in deploying capital into mining and industrial projects throughout Africa. Looking toward the rest of the year, our priorities are plain. First, commission the expanded milling plant at How successfully in mid-October and ramp it to full capacity; second, deliver the revised production guidance we have set, concentrating on raising throughput while holding to the cost discipline we have built across the operation. Third, carry out the Redwing restart programs safely behind a geotechnical audit ahead of first production in January 2027, even as the study work goes on. And fourth, continue funding the plan in a sequenced, non-dilutive way. We have a producing mine whose capacity is set to rise by more than 1/3. We have a second mine coming back into production sooner than planned, and we have funded both without dilution. With that, I will hand the call to Sphe, who will take you through our first half financial performance and outlook in more detail. Sphe?
Siphesihle McHunu
executiveThank you, Tulani, and good day to all of you. My remarks will cover revenue and production, costs and margins, adjusted EBITDA, plus the noncash items within our reported results, cash flow, the balance sheet and liquidity. Then, at the end, I'll finish with guidance. All comparisons refer to the six months that ended June 30, 2025. Revenue and production. I'll start with revenue. For the first six months of 2026, revenue reached $50.8 million, a 40% increase over the $36.4 million figure. The gold price served as the primary catalyst. Our average net realized price, calculated after royalties, climbed 48% to $4,195 per ounce, compared with $2,827 per ounce in the prior year. Volumes came in lower — 11,357 ounces sold this time against 12,226 ounces a year earlier, which works out to a 7% decline. Output totaled 11,373 ounces compared with 12,741, down 11%. Tonnes milled were 233,000 versus 236,000 tonnes, essentially unchanged. The average grade stood at 1.7 grams per tonne compared with 1.9 grams per tonne. Recovery came in at 88% versus 89%. So the benefit from the gold price outweighed by a wide margin what we lost on volume. That arithmetic lays the groundwork for what follows, since it shows how much earnings leverage this business gains from each extra ounce — and extra ounces are precisely what the mill expansion is designed to produce. Next I'll turn to costs and margins. Production costs came in at $17.9 million, a 3% decrease from $18.5 million a year earlier, even though power tariffs rose 15%. Measured against revenue, production costs dropped to 35% from 51%, and royalties climbed 70% to $3.1 million, driven by greater revenue and the elevated royalty rate in effect since January 1, 2026, applicable when gold trades above $5,000 per ounce. C1 cash cost stood at $1,576 per ounce versus $1,510 per ounce. In absolute terms, our costs declined. Yet because a substantial portion of the cost base is fixed and we sold fewer ounces, the per-ounce cost increased by 4%. For the group, all-in sustaining cost came in at $3,078 per ounce versus $2,462 per ounce — that's above our guidance range, and I'd like to walk you through what's behind it. At How Mine by itself, all-in sustaining cost was $2,534 per ounce, against $2,265 per ounce. That group number also includes corporate overhead along with the care and maintenance costs at Redwing and Mazowe, with the whole amount divided by How Mines ounces. The year-over-year increase comes from fewer ounces, higher royalties and higher corporate costs, which I'll get to. Sustaining capital was lower, at $3.5 million versus $4.4 million. Gross profit doubled, reaching $27 million from $13.5 million, which is a gross margin of 53% compared with 37%. Administrative expenses. Admin expenses came in at $13.7 million, down from $15.7 million. Since one-off items appear in both periods, I want to walk you through the underlying picture. The earlier period carried $10.2 million in transaction costs tied to our business combination and NASDAQ listing. This period, by contrast, has $3.2 million of onetime costs, and that figure includes $2.6 million in onetime restructuring costs. Strip those out and underlying admin expenses were roughly $10.5 million versus $5.5 million — so they've essentially doubled. That increase reflects the cost of operating as a NASDAQ-listed company for a full period: executive hires, directors and officers insurance, investor relations, legal and professional fees, plus $1.2 million of noncash share-based payments. The restructuring that we completed during the first half ought to lower the annualized run rate. As a result, we anticipate that administrative expenses for the second half will be lower than in the first half. Noncash or back costs. Reported earnings were impacted by two noncash items. The first is the earn-out liability. Per our Business Combination Agreement, founding shareholders could get additional shares once operational milestones are met. The fair value of that liability increased from $9.9 million at December 31 to $18.4 million at June 30, producing a loss of $8.5 million through the income statement. Second, our warrants are classified as derivative liabilities and marked to market, which created an additional loss of $2.7 million. Together, that amounts to $11.3 million. Those two liabilities shifted primarily because of our stock price, which rose from $1.01 to $1.88. A higher share price should be expected to generate additional noncash losses on these lines, whereas a lower share price would generate gains. Cash is unaffected by either, the earn-out is settled in shares, and adjusted EBITDA excludes both. Following those items, we posted an operating profit of $2.2 million versus a loss of $7.4 million, along with a profit before tax of $1.3 million. After taxation expenses of $6.1 million, the loss for the period came to $4.8 million, or $0.09 per share, compared with a loss of $11.9 million, excluding the $11.3 million in noncash fair value losses. On an after-tax basis, the business was profitable. Adjusted EBITDA. Adjusted EBITDA reached $19 million, which is a 76% rise from $10.8 million. The adjusted EBITDA margin stood at 37%, compared with 30%. You can find a reconciliation to the reported losses in our results release. Higher gold prices drove the gain, along with the gross profit expansion that followed, though higher corporate costs partly offset it. Turning to cash flow and capital investment: net cash generated from operating activities was $9.3 million, up 61% from $5.8 million, and it's important to note that we are reinvesting all of it. Net cash used in investing activities was $10.7 million versus $5.6 million, reflecting the mill expansion and production ramp-up at How Mine and the restart program at Redwing. Cash from financing brought in $1.4 million — that's $3 million in fresh borrowing, offset by $1.5 million repaid and $0.1 million in lease payments. We started the year with $1.9 million in cash and wrapped up the half at $1.8 million. Turning to the balance sheet and liquidity: as of June 30, cash stood at $1.8 million, current assets were $20.4 million, and current liabilities came to $63.3 million — leaving a working capital deficit of $42.9 million. I'd like to walk you through what makes up that figure, since the headline number overstates the near-term cash claims on the business. Of that $63.3 million, $7.5 million is the current portion of the earn-out liability, and that piece is settled in shares, not cash. About $15.9 million sits inside the Redwing and Mazowe entities, and right now those entities are under care and maintenance. Those obligations are ring-fenced to those entities, and they are not secured on How Mine. Across the group, trade and other payables totaled $37.3 million, which is $0.5 million lower than the year-end figure. Current tax was $8.9 million, excise tax was $3.6 million, and an indemnification asset of the same amount offsets it, while borrowings payable within a year were $5.6 million. We prepare our financial statements on a going concern basis. Projections from management for cash flow through June 2027, with gold-price sensitivities included, indicate the group will continue producing positive cash flow and satisfy its obligations when they come due. Those projections have been revised to reflect the updated commissioning date and production guidance, and the conclusion is unchanged. Liquidity is stronger than it was on June 30. The full $5 million Ecobank facility was drawn in July; it has a 36-month term extending to May 2029 and is repaid through monthly installments funded by gold sales.
Siphesihle McHunu
executiveOn September 29, 2026, we announced an agreement with BancABC to raise our existing facility by $6.5 million, taking it from $6.7 million to $13.2 million. At June 30, we were in compliance with all debt covenants. As of that date, we also carried $3.8 million in purchase commitments for property, plant and equipment. We can confirm that at this stage we are in compliance with all covenants under the respective finance documents. Guidance. Let me wrap up with our guidance. As Tulani mentioned, we are revising our full year 2026 production guidance to a range of 26,500 ounces to 27,000 ounces, down from 28,000 ounces to 31,500. This updated guidance range is based on the assumption that the expanded mill is commissioned in the middle of October and ramps up over a period of 6 to 8 weeks. The upper end of the range assumed a quicker ramp up and grades towards 1.9 grams per tonne. The lower end assumes a slower ramp at first with half grades. Regarding C1 cash costs, we are maintaining our range of $1,400 per ounce to $1,650 per ounce. First half C1 came in at $1,576 per ounce, and we expect improvement in the second half as volumes rise. For group all-in sustaining costs, our range was $2,400 per ounce to $2,700 per ounce, and the first half was $3,078 per ounce. Since we're going to produce fewer ounces this year than originally planned, our full-year group all-in sustaining cost expectation is now $2,650 to $2,850 per ounce. We anticipate the second half will be materially lower than the first, as restructuring savings come through and a larger ounce base absorbs the fixed costs. Guidance for 2027 production and costs, which will include Redwing's expected contribution, is expected to be provided in the first quarter of 2027. To summarize, revenue rose 40%, which means gross profit doubled. Adjusted EBITDA is 76% higher, and operating cash flow grew 61% despite fewer ounces. Production came in under plan, and we've reset guidance to account for that in the mill timing. At the mine, expenses are down in absolute dollars, while at the corporate level they are up — and we have already taken action there. On top of that, we have financed the next steps using bank debt. Our financial priorities have not changed: expand output, keep costs in check, produce cash, and deploy capital with discipline while avoiding dilution of the shareholders who own the company. With that, I will hand the call to Jonathan for Q&A.
Executive
executiveWhere does Mazowe stand with respect to the policy framework issued by the Zimbabwe Ministry of Mines?
Tulani Sikwila
executiveAt the moment, we’re focused on getting the mine to meet the required specifications. That’s what the Ministry’s directive calls for, and it lines up with how we’ve been handling Redwing.
Executive
executiveDoes the unpaid portion of the BMC purchase price rest entirely on Mr. Khumalo and the Southern Sullivan Trust as guarantors, with Minerals, Greenstone or BMC carrying no obligation to pay?
Siphesihle McHunu
executiveThat is correct. There are no payment obligations for Namib Minerals, Greenstone or BMC.
Executive
executiveDoes the aggregate development capital range we discussed earlier — roughly USD 300 million to USD 400 million for Redwing and Mazowe — still hold, and should investors think of that money as being deployed progressively across several stages instead of as one upfront requirement?
Tulani Sikwila
executiveThat range was an early aggregate indication covering both assets, and it always needed validation through a feasibility study. So the capital figure will be confirmed once the DFS is completed. On the second part of your question, yes, this was never a single upfront requirement, and the way we are developing Redwing now demonstrates that. The initial restart draws on existing development areas and existing plants, and it is funded through internally generated cash flows. The capital needed for the larger scale operation will be defined by the feasibility work. No decisions regarding that capital are being taken ahead of the study. Every stage has its own decision point and its own funding. And our approach so far has been bank debt rather than equity.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Namib Minerals transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Namib Minerals earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Namib Minerals or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.