National Aluminium Company Limited (NATIONALUM) Earnings Call Transcript & Summary

August 3, 2026

NSEI IN Materials Metals and Mining earnings 65 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to the Q1 FY '27 Earnings Call of National Aluminum Company's [indiscernible] Conference Call hosted by Systematics Group. [Operator Instructions]. I now hand the conference over to Mr. [indiscernible] Systematic Group. Thank you, And over to you.

Unknown Attendee

attendee
#2

Thank you, Sharish. Good morning, everyone. On behalf of Systematic, [indiscernible]. I would like to thank the management for giving the opportunity [indiscernible] this call. And I now hand over to Mr. Bharat Sahu, Company Secretary [indiscernible]. Over to you, sir.

Bharat Sahu

executive
#3

Good morning. Warm greetings from NALCO, [indiscernible] Ministry of Mines. Let me at [indiscernible] to introduce our personnel directors sitting in this earnings call. [indiscernible] our CMD, [indiscernible]; sitting next to him, Director Finance [indiscernible]; and sitting next to him, is Dr. [indiscernible], our Director; sitting next to me is our Director of Production, [indiscernible] and I'm Bharat sahu, the company [indiscernible]. On July evening NALCO Board considered and approved the financial reset for the fourth quarter of FY '27. NALCO already registered a robust performance in the Q1. And the one presentation is already uploaded in [indiscernible] stock exchange also on our site of the company. In the robust performance, and I will request our CMD, just to highlight some of the key financial of this one, and then we'll start taking the call the questions from our [indiscernible].

Unknown Executive

executive
#4

Good morning. At the outset, our performance for the Q1 already the presentation is loaded, but I would like to give a few highlights of the Q1 performance. Q1, our overall total income, which grew if you compare to previous year funds to from INR 3,930 crore to INR 5,400 crores, around 39% growth Q1 to Q1 and if you see CY earnings, if you see PBT grew by around 88%, EBITDA grew by around 78%. So there has been a substantial growth both in revenue collection, both in profitability of the company. If you see the highlights of the performance, physical performance also has been very good, whatever targets we have set in the beginning of the year, almost all targets we have achieved -- we have achieved best-ever production in bauxite in hydrate production and power in power generation. As far as quarter 1 progress is concerned, best quarter 1 in all these areas. Financially, if you see this quarter performance, we have done as far as our revenue generation is concerned, is the ever best quarter we have done. As far as profitability is concerned, best Q1 profitability we have achieved. And the major contributors have been, of course, our internal if fee improvement in the volumes of production, whatever targets we have taken almost we have reached to the peak of the volume in all the areas if we see refinery, if you see our metal production all the years. And we have targeted at least 5% to 10% more than the capacity utilize whatever we are going to do more than the rated capacity we have targeted this year. As far as other areas are concerned, we are also targeting to reduce our costs, increase our efficiency which is in our hand, that is increasing volumes and reducing the cost. We are also going for some value-added products for our future expansions. As far as the cantons concerned, hand is going to come this year. And also, we are targeted to spend of mental capacity for which we are going for CPR mix being it with the various milestones which we'll be discussing in the presentation. So once again, thank you, Systematic Group for organizing this conference call.

Bharat Sahu

executive
#5

[indiscernible] over to you, we can now request all our call participants to come forward with their questions.

Operator

operator
#6

[Operator Instructions]. The first question is from the line of Mr. Amit Lahoti from [indiscernible]. Please go ahead.

Unknown Analyst

analyst
#7

[indiscernible], how is the commissioning process moving there? And can we still produce 300,000 tonnes in the current system?

Unknown Executive

executive
#8

Our system refinery the current, we have -- June onwards, we have started the commissioning of view of that decommissioning activities we have started of the packages, almost around 50, more than 50 packages are there. [indiscernible] of the packages, mechanical completion already has been done, and the trial of those packages are under process. A few of the package are left out. Our target is by September end. We have to complete canal completion of all these packages. Do the integrated trial first. That is the [indiscernible] needs to be done within the packages. And after that, we start the actual production process. It will take maybe 3 to 4 months to stabilize and reach to the level of 70%. This year, our target was that we'll be producing around 2 lakh tons of alumina from this refinery. So even if we start the actual production from November, December onwards, after that also, we'll be able to achieve those kinds of figures from the system and that is around like tonnes of alumina production.

Unknown Analyst

analyst
#9

Right. So why has there been a delay? Because earlier, we were planning to start to basin from June onwards. So as you have seen around 6 months of a delay. Any reason around that?

Unknown Executive

executive
#10

We were planning to start the commissioning activity from June onwards. And after that completes it in next 3 to 4 months, of course, the mechanical completion, which was supposed to be done by June, July, maybe getting delayed by 2, 3 months. So this is a big project, big project. It is very difficult to exactly pinpoint the date of commissioning and all that, and it's a chemical process. So now our -- maybe by September end, we are targeting the mechanical compression will be there and will start. There is almost 2, 3 months delays there, not very huge delays there.

Unknown Analyst

analyst
#11

Sure. Okay. My second question is on employee cost, which has gone down below INR 1,600 crores if we annualize Q1 number of INR 395 crores. So is it part of the superannuation plan that you guided in Q3 FY '20 that you were going to affect senior people of around 20 to 50 with a cost saving of INR 70 crores to INR 80 crores. So is it same which is coming now?

Unknown Executive

executive
#12

Myself [indiscernible] Director of Finance is the right question, why our complete cost is going down. If you see the CTC of our last year to this year. Our [indiscernible] and in this quarter, it is around INR 50. There is a reduction of 3 less almost. That is because rightly, you have said that is because of [indiscernible] employees and investment of the employee at the entry level. That is the one reason. Second reason is we have made some provisions last year towards retirement benefit that is provisioned to [indiscernible] and which was on the high side, we see quarterly to provide that. And another area is we are [indiscernible] provision last year, which is at resin that ratio that can reduce our cost. And we expect that we will continue in the next 3 quarters.

Unknown Analyst

analyst
#13

Okay. So for the full year, we can still see this number around INR 1,600 crores?

Unknown Executive

executive
#14

That's right. Right. Right. In the last part of the year, in the last quarter, quarter 4, there may be some impact of very vision because [indiscernible] January 2027, [indiscernible]. So the last quarter, there may be some increase 15% additional. Otherwise, 2 quarters, second [indiscernible] the cost will be in the slide.

Operator

operator
#15

Thank you, sir. This question is from the line of Mr. Ajit [indiscernible]. Please go ahead.

Unknown Analyst

analyst
#16

My question is with respect to our alumina sales volume. So for FY '27, you have guided 25 lakh tonnes of alumina production, but anything in terms of sales volume because that number fluctuates a lot, if you can guide on the full year volumes for FY '27.

Unknown Executive

executive
#17

This financial year, last year, we sold around 4 lakh tonnes of alumina. This year, we are targeting INR 16 lakhs. Whatever 2 lakhs of Astra Alumina, we are trying to produce from this team, it will be added to our sales value. The 2 lakhs will be selling this year.

Unknown Analyst

analyst
#18

Yes, understood. And the second part is, I mean, we have seen now that the aluminum prices have come down. So going forward in Q2, do you foresee any raw material cost pressure, which will persist, because we have seen that in the earlier quarter, you have added that there is some cost inflation on [indiscernible] and other raw materials. So will it impact our margins going forward as the aluminum prices have cooled down?

Unknown Executive

executive
#19

Aluminum prices you see in the first quarter average, we got around 3,500, 3,600 700 of [indiscernible] come down to around 3,200 [indiscernible] material prices, of course, has increased. You see caustic soda prices last year average was around 43,000. In Q1, our expenditure was around 45,000 per tonne. In Q2, it will become around 49,000. Of course, plastic soda prices are going to go up by around INR 3,000 to 4,000 as compared to Q1. [indiscernible] also has gone up 53,000 watts to 44,000 watts last year, gone to 66,000 to 70,000. These are the two major areas and also price, which was 46,000 last year, it has gone up to 75,000. So this has increased our overall cost of production by around INR 15,000 to INR 16,000 per tonne of metal. So these 3 areas, [indiscernible] and HFO. These are the three areas where cost also aluminum chloride by some. So of course, around 10% to 15% increase in the topics are there. which is increasing our cost by around 15,000 to 16,000 metal prices.

Unknown Analyst

analyst
#20

So anything which can offset that means we have seen this recently [indiscernible] prices have increased [indiscernible] and then is there any scope to offset that with lower power cost or you think that the margins could take slight rate?

Unknown Executive

executive
#21

Alumina prices, what we expected in the beginning of the month, year was around $3.10 to $3.20. But of late we are getting around 370 alumina prices. That is because in Russia also Rusal and China, two of the refineries due to red mud issues, they have reduced the production. The bauxite prices in new game has increased slightly. So that's why the alumina prices, which we were expecting that it will be somewhere around $3.20. We are getting around $70. So that will offset somewhat raw material, what is increase in the raw material cost because [indiscernible] has given us an expenditure burden in Q1 of around INR 120 crores INR -- INR 230 crores and extra increase in the raw material prices. So alumina prices are the prices which we are expecting equally if we remain at the level then that will offset the input raw material costs.

Operator

operator
#22

Thank you. The next question is from the line of Pinakin from HSBC.

Pinakin Parekh

analyst
#23

Thank you for this opportunity. I have a few questions. The first is you highlighted $370 per tonne as your Alumina realization per CapEx currently. And what was the Alumina realization cost in Q1, sir?

Unknown Executive

executive
#24

Just -- can you repeat the question? Just last line.

Pinakin Parekh

analyst
#25

The alumina realized ratio in Q1?

Unknown Executive

executive
#26

Q1, our average realized was around [indiscernible] Alumina.

Pinakin Parekh

analyst
#27

And one cost of Alumina quarter of [indiscernible].

Unknown Executive

executive
#28

Little louder we are not able to [indiscernible] not clear.

Pinakin Parekh

analyst
#29

One second. Alumina cost of production, so will it be higher in quarter 2 versus quarter 1?

Unknown Executive

executive
#30

Quarter 1, our cost position if you see, you are talking about alumina or metal?

Pinakin Parekh

analyst
#31

Alumina. Alumina

Unknown Executive

executive
#32

Alumina costs normally it is between INR 21,000 to INR 42,000. Last quarter, it will be around within that well only. And the second quarter, since we have observed all the input cost increase in the first quarter and similar pattern cost, pricing be remain in the next quarter. And we don't think our cost will be increased. Whether our cost will be within that range only around 1,000 to 2,000 or term of alumina. And the weather will be getting [indiscernible] price because he has already explained that the next quarter, we are going to get incremental price of around 50 from alumina.

Pinakin Parekh

analyst
#33

Got it. My second question is, sir, you highlighted metal cost of production increase of INR 15,000 to INR 16,000 a tonne. Once that cost of production increase already fee in quarter 1? Or will that increase come in quarter 2 versus quarter 1.

Unknown Executive

executive
#34

No, it is already. It was already expected because we are knowing that raw material prices are going to go up. [indiscernible], HFO and CPC. So that was almost expected. And the similar kind of cost will continue in Q2 also.

Pinakin Parekh

analyst
#35

Okay. Similar kind of costs will continue. Got it, sir. Sir, my third question is the -- you highlighted name prices which have moved. Now how are the domestic aluminum premiums because you highlighted previously that may change with the lag. So have they increased in recent times? Or do you see the premiums increasing in the domestic sales?

Unknown Executive

executive
#36

Premium has increased. Our earlier premium was around $60. Now it has gone up to around [indiscernible] around $ 110 [indiscernible] has increased by about $50.

Pinakin Parekh

analyst
#37

Got it. And do you expect this to increase further, sir?

Unknown Executive

executive
#38

No, no. That income increase was due to that was situation in the Middle East since the situation is easing out we are expecting that it may remain a or maybe it may go [indiscernible].

Pinakin Parekh

analyst
#39

Got it. And sir, my last question is because of the war situation in the Middle East, where any of your export shipments impacted which will now normalize, either in alumina or aluminum?

Unknown Executive

executive
#40

Yes, a few of the shipments, like one shipment was earlier orders. Of course, that was before the war, it was ordered at $390 also. That has got [indiscernible] relation in that. As far as other shipments are concerned, other shipments, whatever is getting ordered, they are going no other pending shipments are there.

Operator

operator
#41

Got it. The next question is from the line of Mr. Vikash Singh from ICIC Securities.

Vikash Singh

analyst
#42

Good morning, sir, and thank you for the opportunity. Usually being a monsoon season has traditionally been weaker, especially on the coal input side. So just wanted to understand, have we have sufficient coal inventory, including the captive this time and any one-off cost escalation or any disruption we have at PDN so far?

Unknown Executive

executive
#43

As far as our core plant is confirmed in [indiscernible] that is for our smelter. There, we are having sufficient coal because that coal we are getting from our CapEx stores around 60%, 70% of coal we are getting from the captive. So their issues are not there. Of course, in our refineries, the full stock is on the lower side. All stock, we have to maintain at the level of maybe 10 to 15 days. Now it is around 2 to 3 days. That is because of the restriction given by the government, the priority of the rates there, we are heavily dependent on the rates from the railways and the priority is given to the power plant. So there are some issues out there. We are taking it very aggressively with the Indian railways and our ministry and some improvement is there. And since now the restrictions summaries will come down. So we are expecting that these stocks will also improve in the coming days. As long as the rate availability for the shipment is concerned, there is no problem so far. No, that for that shipment, our own breaks are there for the dispatching kiln alumina. For that, no issues out there. We have got our own BTAP rates. So that's no issue there.

Vikash Singh

analyst
#44

[indiscernible].

Unknown Executive

executive
#45

Mr. Singh, your voice is breaking.

Vikash Singh

analyst
#46

Is it better?

Unknown Executive

executive
#47

Yes.

Vikash Singh

analyst
#48

Yes. So sir, second question pertains to we take about our 0.5 million tonne aluminum plant. Could you give us some highlights at what stage of board approval these plans are when we will start on this and the CapEx any for this 0.5 million tonne?

Unknown Executive

executive
#49

Metal plant product development as far as of date [indiscernible] we have already got technology supplier finalized that we are going to sign technology license with them this. Maybe this month by 10 or 15. So DPR making is under process. The consultant is making that a -- our target is next 3 to 4 months, we'll be ready with the delayer and get the board approval maybe October, November for the DPR for setting up this 0.5 million tonne smelter and also 1,000 megawatt power plant. After that, maybe we'll take 8 to 9 months to order the packages. By next year, August, September, we should order all the packages and start the groundwork maybe next year, October, November, and from there, it will take 3 to 3.5 years to set up this plant. So the time lines which we have given to the ministry and our internal time line is by December 2030, we have to complete this plant along with the power plant. As far as the power plant is concerned, power plant, we have done one JV agreement with [indiscernible] for setting up this power plant has to reduce and to have the raw material security, that is the goal. NLC having the coal mines here itself in Salta districts. So the coal supply will be from there. So that will be good for this power plant. So this power plant VTR is also under process. So at the same time, both will get ordered and get commissioned by 2030 and [indiscernible] half. [indiscernible] concerned. The overall CapEx expenditure will be somewhere around INR 25,000 crores. And this will start from financial year '27 '28 and the peak will be '28, '29 and '29,'30 and '30, '31. This will be the 2, 3 years where this CapEx flow distribution will be there. This year, for that to give no major CapEx will be there. Of course, technology licenses, we have to give something maybe INR 300 crores, INR 400 crores. But the major CapEx will be coming next financial year onwards.

Vikash Singh

analyst
#50

No, that Sir, just one clarification. The shipment of the exports which we do to Russia, is it on a dollar-denominated or this will the Russian currency and whatever the dollar denominator [indiscernible] do in the export market? We booked the one at the time of shipment, right?

Unknown Executive

executive
#51

No, whatever shipment our exports are going, that is at the time of ordering when our tender is floated, we do the spot tenders and that is the dollar rate as of that is.

Vikash Singh

analyst
#52

Okay. But then the booking happens or the sales got booked at the time of shipment, right? Looking -- actually, we do the spot tender and the date of opening the core tender at that date, whatever the dollar prices are there, that is finalized.

Operator

operator
#53

The next question is from Samana Govia from [indiscernible] Securities Limited.

Unknown Analyst

analyst
#54

Sir, my first question comes on the captive coal mines. So we were targeting a 4.8 million tonne production for FY '27. So can you just elaborate on where we are in the EC process for our mine expansion?

Unknown Executive

executive
#55

Already, the mining plan approval we have done for many plan approval is to be done from the Board. This board we have done the money plan approval. And now we are applying for the ICICI. The next maybe 2, 3 months, we'll be getting the -- so already we have started the production and 400 million tonnes, we are sure we are going at the rate of 4.8 million tonnes or monthly breakup whatever we have done. The next 2, 3 months, we'll be getting easy from [indiscernible] so there are no major issues in that.

Unknown Analyst

analyst
#56

Okay. That's good to hear. And could you just give me what was our total coal production in Q1 from our captive mines?

Unknown Executive

executive
#57

Q1 was -- because initially, what happened initially 4, 5 days, in the beginning of Q1, 5 days, the production from the mines were not there, there were some technical issues. Now we have ramped the production and the subsequent quarters will be managing those whatever shortfalls were there.

Unknown Analyst

analyst
#58

Okay. Can you just repeat the number [indiscernible]?

Unknown Executive

executive
#59

11.04 lakh tonnes.

Unknown Analyst

analyst
#60

11.04. Okay. Sure. sir, my second question is the [indiscernible] mines, we have already appointed an MDO. When do we see the production to take place? Or has it already started?

Unknown Executive

executive
#61

[indiscernible] mines, actually, one, we have already ordered the MDOs. And for going to the mines and starting the production, one road is to be made 8-kilometer road for making the road recutting this to [indiscernible]. We have, along with [indiscernible] residences coming there, some activists and some residents are coming there. District authorities 2, 3 times, we have tried along with the state government, police works and all that. We are trying to mobilize the locals there along with the MDO. And I think in this month, this month itself, that is in the month of August, along with the authorities, we will be again going there or making the road once that road making will take around maybe 15, 20 days, that met we are targeting maybe September, October onwards, October onwards, we'll start the production.

Unknown Analyst

analyst
#62

Okay. Sure. That is quite helpful, sir. So one last question I had. As of the March 2026, our total employee count was roughly INR 4,880. What would the employee count be as of right now or as of Q1 end?

Unknown Executive

executive
#63

[indiscernible] for it.

Unknown Analyst

analyst
#64

Okay. So there could be another 150 to 150 to 170 employee reduction more by the year end, right?

Unknown Executive

executive
#65

[indiscernible], we'll be looking around 170 to 200 every year reduction yields in coming 3, 4 years.

Operator

operator
#66

The next question is from the line of Amit Murarka from Axis Capital. Please go ahead.

Amit Murarka

analyst
#67

You mentioned the mechanical completion of the Lumina plant in September and roughly additional 200 kt production, right? So -- but next year, then can we assume the full run rate of cost capacity?

Unknown Executive

executive
#68

Yes, next year on what we have to do. We will be going to 1 million tonne production from there and already, we are 2.2, 2.3. We are going from the existing. Maybe we'll be going to 3.1, 3.2 next year onward.

Amit Murarka

analyst
#69

Sure. Also on this local market premium for aluminum, how does [indiscernible] you enter into some contracts once the premium is fixed? Or is it goes with the spot market itself?

Unknown Executive

executive
#70

Actually, we do export tenders from export tender that is loaded on the domestic [indiscernible] in what we do that [indiscernible] on the domestic pricing, LME. Domestic pricing is based on the LME.

Amit Murarka

analyst
#71

No, no, I know I'm talking on the premium. So when you sell in the local market, the premium that you book charge customers in the local market is also based on some benchmark, let's say, MJP benchmark, something like that? Or you fix [indiscernible]

Unknown Executive

executive
#72

What we process follow is, we do on export tender. In export tender, whatever premium we do, yes, that premium is fixed for next 3 to 4 months. unless and until we do the net export tender. So suppose we did export tender last month, we got a premium of $110. So that premium will be loaded on the domestic pricing for next 3 to 4 months until we do the net [indiscernible] tender, and we discovered the premium. You were talking about the metal price or alumina.

Amit Murarka

analyst
#73

Aluminum. [indiscernible] we make local.

Unknown Executive

executive
#74

[indiscernible] is our policy, what [indiscernible] explained that these are -- we have a structured policy for facing the aluminum price. And there are other factors are also there, one factory is premium, whatever premium is discovered for tendering, export and marine, that is added to our aluminum price domestic supply.

Amit Murarka

analyst
#75

Sure, sure. Got it. And is it revised based on every tender that you every country the frequency of 10 depend 34 months, so we normally Right. Also, what is the CapEx outlook now for FY 2017 '20, if you could provide the numbers?

Unknown Executive

executive
#76

Our target INR 1,500 crores. Maybe we'll be crossing that will be somewhere ending up with around INR 26, INR 27 [indiscernible].

Amit Murarka

analyst
#77

So this year as well as next year.

Unknown Executive

executive
#78

This year, it will be -- our target is around INR 1,500 because most of the payments for [indiscernible] is done. So major capital expenditure is not there, but still we'll be doing somewhere around INR 1,500 crores to INR 1,700 crores or INR 1,800 crores. Next year onwards, it will increase because our expansion of the smelter will be there. So next year, how much we are planning? Next year, we have plan to INR 2,500 crore INR 2,500, maybe in '27, '28. After that, it will go to maybe INR 4,000 crores after net INR 6,000, INR 10,000 crores. We have done the pricing and the major expenditure will come from the smelter expansion and power plant expansion.

Amit Murarka

analyst
#79

Sure. Got it. And also captive coal, I think earlier you had mentioned about 4.6-odd million tonnes of production this year. So [indiscernible] you seem to be on track on that?

Unknown Executive

executive
#80

Yes, captive coal. Last year, we did 4 million tonnes. This year, we are targeting 4.8 million tonnes. The 20% increase is allowed for that all permissions and all that under process. And on a monthly basis, we are producing at the rate of 4.8 million tonnes and we'll be achieving that at the end of the year.

Operator

operator
#81

The next question is from Sumangal Nevatia from Kotak Securities. Please go ahead.

Sumangal Nevatia

analyst
#82

Sir, just continuing on the previous question. So one, on the CapEx, can you share 1Q, how much we spend. And then for the expansion, I just want to know, the power CapEx will happen in other JVs. So will we be contributing only to the amount of equity, which could be maybe around 20%, 30%? So just if you can explain how the power expansion CapEx will happen?

Unknown Executive

executive
#83

Our CapEx plan, what [indiscernible] explained, smelter, we are going to do EPC more. And for power plant, we have [indiscernible] with NLC and will be doing good. Okay. So contribution to total expenditure towards our CapEx up to teal be around INR 24,000 crores, INR 700 re, INR 4,000 crores on smelter and INR 6,000 crores towards contribution for this power plant megawatt per ton to get. The cost will be total cost will be around INR 12,000 crores and INR 6,000 crores from our side and INR 6,000 crores from NRC because [indiscernible]. in Power Plant, we have a detection. So if you follow that, our equity contribution will be lower. It is around INR 3,500 hours share will be balance will be financed through back through our NALCO and NLC is because [indiscernible] because this is a new JV, we will be the [indiscernible] the money will be taken from the bank. So if you see otherwise if you see our firm base, if you see our balance sheet as a bit, we have formed a of around INR 3,500 crore [indiscernible]. So every year, we are adding 2,500 after paying our dividends and all our CapEx regular. So if you see that area, we need not to get any money from the outside because we have sufficient balance. Since we have -- and to the agreement of disagreement for power plant. So the power plant will be financed by that company with any company equity participation will be 30%, 70% will be taken on that. So balanced menu, which we have will be pledging for our expensive project of smelter and other projects we are also considering that will be entirely to put it because we have suitable. So the power plant will be 70-30-ish. So that is to present proposal and we are going to go by this file.

Sumangal Nevatia

analyst
#84

Understood. Sir, for the power plant, INR 12,000 crores or 1,000 megawatt, I mean, generally, the thumb INR crore, crores per megawatt. So why is the cost so higher?

Unknown Executive

executive
#85

It is not -- sorry, one, without, I think, INR 10 crores, 1 megawatt. So it will be INR 10,000 crores to INR 11,000 crores. It is not higher because we're going to set up at 1,000 to 80 megawatts per plan.

Sumangal Nevatia

analyst
#86

Understood. And sir, what you said was the cash balance as on 1Q, net cash, INR 1,500 crores.

Unknown Executive

executive
#87

Yes. [indiscernible] June, it is INR 10,500 crores.

Sumangal Nevatia

analyst
#88

Understood. And in 1Q, how much did we spend for CapEx. This year or you are talking about [indiscernible] only in the first quarter.

Unknown Executive

executive
#89

I think 350.

Sumangal Nevatia

analyst
#90

Understood. Understood. I wanted to understand that on the previous question on sales of metal, you shared it is -- I mean the premium is decided as per the export tender. So the domestic price, just to clarify, it is the LME plus the custom duty plus whatever we get as a premium in the export are these three components there?

Unknown Executive

executive
#91

There are some handling charges and some stock charges something also added on that on that basis [indiscernible]. So put to our yield point and support to the customer on because you have a [indiscernible] the three factors there, you have rightly mentioned that it got import duty plus premium was handling cars and free qualitied customers upgrade to their location have what they will be buying from our location to the [indiscernible].

Unknown Analyst

analyst
#92

Understood. Sir, can you share what were these 3 components for 1Q?

Unknown Executive

executive
#93

And we know that the breakup of the realization our domain, you can our website, I think pricing policy is there. So that policy, we need to see whether it is a classified one or not, we can share or not.

Unknown Analyst

analyst
#94

Okay. Okay. That's fine. And sir, just one last thing. On the aluminum metal, you said INR 15,000 to INR 16,000 increase in cost. So this is 15,000 yes...

Unknown Executive

executive
#95

15,000.

Unknown Analyst

analyst
#96

Yes. So this is with respect to fourth quarter or with respect to last year as an average?

Unknown Executive

executive
#97

Last year average. Last year average was INR 156 -- 157,000 this year, average first Q1 is around 170,000.

Unknown Analyst

analyst
#98

And so for the -- as per the today's trend, 2Q should be what, sir?

Unknown Executive

executive
#99

We will slightly really increase because Citco prices and postcode in Q2 will be slightly higher, not much higher, maybe it will go to INR 172 crore or INR 170, INR 172. It depends on how much efficiency we are achieving. Understood.

Unknown Analyst

analyst
#100

And just one last question, sir. I mean when you are adding around less than 1 million tonnes of captive coal this year, what is the cost saving? What is the difference between the cost of capital coal versus what we are replacing linkage or auction coal?

Unknown Executive

executive
#101

Our cost of captive coal, which we are sourcing from our own mines, it is around [indiscernible] if we compare these costs, which have come -- there are two types of coal we are taking from the whole India. One is the [indiscernible] fuel supply agreement, another two option. [indiscernible]. Almost [indiscernible]. I mean if you see that [indiscernible]. So there is a difference of some quarters. And if you see the piece, we are not regularly getting because of the rap supply. So the auction coal is true has been our capital growth. So there is a great advantage between Octanol and our captive 1,500 almost.

Unknown Analyst

analyst
#102

Okay. And sir, last year, what is the breakup of our goal? How much was linkage and how much is the auction. Last year, if you see a [indiscernible] And they are talking about -- because of total, 7.2 million, 4 million is our own, we are taking 3.2 million from coal India. Out of 3.2 linkage and auction [indiscernible] was around 34 million from our CPP and [indiscernible] from effect. On the [indiscernible] pool, it was around 1 million. That will take up the data and let you know.

Operator

operator
#103

Thank you, the next question is from Mr. Digant Haria from [indiscernible].

Unknown Analyst

analyst
#104

Sir, just on two questions I had. One was on aluminum metal price outlook, like and because the Middle East or deployed 1 or 2 big production factories, when they come back on stream, what happens, what is your expectation of aluminum metal prices. That's number one. And number 2 is that in recycled aluminum, also, India is seeing a lot of investment like does also have any plans and can that impact our sales going forward 2, 3 years later. These are the 2 questions.

Unknown Executive

executive
#105

Metal prices, as of now, it is $3,200. So what forecasts are telling CRU and players and all that, that the remaining part of the year, that will remain somewhere around 31%, 33%. We are also expecting to somewhere in between 3 to will be the LME in the remaining part of the year because whatever smelters are supposed to come in the Middle East, that will be coming maybe by end at the Q4 of this financial year. because these metals will take some time more than 7 months, 8 months more. So supply restrictions, where the projections are there, there will be a deficit of around 0.8 million tonnes of metal in the international market. if you see the production and consumption patterns, there is a deficit of around 0.8 million tonnes. So will be there somewhere around 1 million.

Unknown Analyst

analyst
#106

Got it, sir, got it. And [indiscernible] concerned, we were talking about recycling in our [indiscernible] is concerned, recycling basically is done for the secondary produces we are making small quantity and since we are a major producer. So we don't go into a recycling because that also disturbs the quality of the metal we produce in aluminum sector, the quality of the metal is very important. The part of the Whenever the recycling is done, the quality assurance is not there. So our plans for recycling is not there. --

Operator

operator
#107

the next question is from Mr. Dinesh Kumar from [indiscernible].

Unknown Analyst

analyst
#108

So my first question is that for this quarter, did we have any LME-linked contracts for alumina? And if yes, then how do we stand for the quarters ahead o[indiscernible].

Unknown Executive

executive
#109

We could not get you, if you can repeat your question.

Unknown Analyst

analyst
#110

Yes, sir. So my question is on did we have any LME-linked contracts for alumina on 1Q for '27. And if yes, then how do we stand for the quarter?

Unknown Executive

executive
#111

Term contract in Q1, I think in the beginning, 1 or 2 shipments a obviously. But now as of now, last 2, 3 months, we have 2 months, we are not having any that we call as a term contract, which is linked to the LME that is not there because we had a few tenders in which percentage was very low. It was coming around 10% of the LME. That's why we concerned that tender because spot prices we are getting better.

Unknown Analyst

analyst
#112

So is it fair to say that for FY '21 also for the remaining of the year, we won't be having any term contracts?

Unknown Executive

executive
#113

Actually, we go for the tender, we will be doing some tender if you get better prices then only we'll go because as of now, we are getting $30, $70 and the percentage wise, if we get only 10%, 11%, so around 3,200 LME, that will come to maybe around $320. So we don't order that. So it totally depends on we'll be doing tender if you get the better prices around 12%, 13%, 14%, then only we'll book the order.

Unknown Analyst

analyst
#114

And can you, sir, also explain how we are getting this $50 of premium versus our 1Q average, which you said was around $320 per alumina and now for this quarter, you're expecting it to be 30%. So why this differential here?

Unknown Executive

executive
#115

Whatever premium I was talking, that was for metal, aluminum. Alumina may, we are not -- alumina, whatever we are selling that the spot tender fixed suppose we are doing a spot tender. And on that part tender, whatever suppose we are getting per tonne or $350 whatever, that is a fixed price for tender for shipment. But that premium I was talking was for the metal for aluminum, whatever aluminum we are selling in the domestic market. On that, we load some premium. That depends on whatever export. We do skew some export of the aluminum also. Some metal export also, we do. We do 500,000 tonnes every month. in that export tender, whatever premium we are getting that is loaded to the domestic customers.

Unknown Analyst

analyst
#116

Sure. So is it fair to say that for second quarter alumina realizes could be close to $360, $70 for [indiscernible]?

Unknown Executive

executive
#117

Yes. Already, this month, July, we have spot tenders -- spot tender also somewhere around 370 we are getting. Last spot tender, we have done 2, 3 glass that also, we got 380. So Q2 average 370, I think we'll be getting Q2. Now what we have meant the was around 3 and the next [indiscernible] will be expecting $50 work. Very short tendering or term compare [indiscernible] we are expecting that because the price per is now -- it will give us more 50 more that our annual realized.

Unknown Analyst

analyst
#118

Got you. And, sir, second question is on the box side of alumina product. So for this quarter, we spent up 3.2 tons of [indiscernible] 1 tonne of alumina, which is efficient if we compare it to the last few quarters, which was a tonnes of bauxite. So any particular reason for this improvement? And can we expect this to sustain are also?

Unknown Executive

executive
#119

It totally depends on the quality of both sides we are getting from the mines. And [indiscernible] a few new faces in there in our mind. So then the quality of oat is good. The per-ton conduction of [indiscernible] it goes down. In the coming days, because we are going to [indiscernible] we'll be getting better quality of [indiscernible]. Now or not block, it was a very old block that has almost exosted. So we are starting some new phases where the base quality will be better. So average [indiscernible] of bauxite will be getting better.

Unknown Analyst

analyst
#120

Sure, sir.

Unknown Executive

executive
#121

Just one query was there on the linkage coal and all that, our director production is there, he is going to answer that.

Unknown Executive

executive
#122

Basically for our PPP, we are aging in a [indiscernible]. Last year, we have like 47.16 lakh coal farm miles through NCL and so D&D for directors. We are taking call from through e-auction for our alumina refinery. And through linkage, we last year, we purchased 11.24 of [indiscernible] owns around 7. So approximately 40% coal of total for use in refinery, which at purchase through e-auction and balance is through linkage.

Operator

operator
#123

We have next question from [indiscernible].

Unknown Analyst

analyst
#124

I just wanted clarity on one...

Operator

operator
#125

Sir, please be a little bit louder, sir, please?

Unknown Analyst

analyst
#126

So you had mentioned about the premiums for metal is around $110 currently. Can you tell us what was it in the last time when you had done the revision? And what is the impact between the [indiscernible]?

Unknown Executive

executive
#127

That was -- last time we have done around 5, 6 months back. At that time, we got the premium was around $60 $50 somewhere around $50.

Unknown Analyst

analyst
#128

Okay. But based on what [indiscernible] has only increased. But I think in your presentation, you had mentioned something like premiums are declining or premiums are likely to reduce or risk in? Can you any the difference between the two?

Unknown Executive

executive
#129

You see the premium totally depends on the demand supply. If the demand is more supply is lesser, the premium we get better. Now last time when the tender we did -- at that time, the supply restrictions were there due to the smart situation. Since the all situations are easing out. So even the smelters in the Middle East, they are trying to increase the production in the subsequent months when this is out, the premium will [indiscernible],

Unknown Analyst

analyst
#130

just one question. Your new Alumina refinery that you're starting, what will be the difference in terms of cost of production versus your current plants because the current funds are much older cost of production in the expansion unit?

Unknown Executive

executive
#131

Correct. We have calculated for our expansion unit stream, the cost of production will not be much high because our average if you see our current cost of production of alumina. This last year, it was around INR 20,000. But this year, first quarter, we have got around INR 22,766 because of the increase in caustic soda and that is HFO. These are the 2 major contributors that have increased. In our new refineries, system refinery, the advantage we'll be getting is that is era where the cost soda consumption will be on the lower side. The cost of product consumption in our existing define, which is around 103 kg to 15 kg per tonne of alumina production. That should go up to -- go down to around maybe 85 to 90 kg per tonne of alumina conduction. And that will reduce our cost by maybe, I think by INR 1, INR 1,500 per tonne as far as the alumina cost is concerned and other areas like manpower cost and all that because that is a big unit, 1 line producing around 1 million tonnes. Now from four lines in the existing dependent from 4 lines we are producing -- so the fixed cost, that is the manpower cost will also be on the lower side. Of course, the interest is not there. The depreciation will be loaded. Some depreciation will be loaded on the cost what we have calculated the overall cost of the existing the fan and the new refinery will be almost same new family also come around INR 20,000, INR 25,000 will be the cost coming.

Operator

operator
#132

The next question is from [indiscernible].

Unknown Analyst

analyst
#133

Sir, I just have one question, just a clarification. Our current alumina capacity is 2.10 million tonnes, right?

Unknown Executive

executive
#134

Yes.

Unknown Analyst

analyst
#135

And sir, after expansion, how much is this going to become?

Unknown Executive

executive
#136

You see our current capacity is 2.1%, but last year, we produced around 2.3. So we have done on 2 excess of our capacity with spend 1 million tonne will be added. So after as mentioned, we are targeting -- the record capacity will be 3.1 million tonnes, but we'll be targeting around maybe 3.2 million or 3.3 million tonnes. And this comes up when this extra 1 million tonne capacity 1 million tonnes. This year, only 0.2 million tonnes will be added. So net year, that is '27, '28

Unknown Analyst

analyst
#137

Okay. '27, '28, we will have a full 3.1 million tonnes. So then obviously, we'll have -- as of now, we are selling what closer to 1 million, right?

Unknown Executive

executive
#138

Last year, we sold around 1.4 million, 14 lakh tons. This year, we are planning 1.6. So after this goes to the full capacity because in our smelter, we require only [indiscernible] then to be sold in open market. So next year, we'll get an extra 1 million tonnes in full that has to be sold.

Operator

operator
#139

[Operator Instructions]. We will take Mr. Rajesh Majunga from 361 Capital. Yes, [indiscernible] is back.

Unknown Analyst

analyst
#140

What is the cost of this 1 million tonne fine refinery?

Unknown Executive

executive
#141

Around INR 5,600 crores.

Unknown Analyst

analyst
#142

This is one more thing is this is all internal accrual, right?

Unknown Executive

executive
#143

Yes, it was internal accrual interest will be loaded. Depreciation will be loaded.

Operator

operator
#144

The next question is from Mr. Rajesh Majunga.

Unknown Analyst

analyst
#145

Question on the bauxite part First of all, on the existing upside mines at [indiscernible], what is the balance life of the [indiscernible] mine? And what is the result there? And putting mind what are you positioning right now? And what is the capacity to go up to next year?

Unknown Executive

executive
#146

Basically, at our personal of side, we are having a reserve of around 110 million tonnes. And in addition to that, we have acquired new mines which is also having around 100 million, 120 million tonnes. So if we take the rate up rent rate of this thing, it later around 8 million tonnes per year if we take. So we can -- we are -- we can say that the balance life of our pasta bauxite mine will be approximately 15 to 20 years.

Unknown Analyst

analyst
#147

Okay. And I understand that the potent mines, the bauxite quantity is better due to weak the cost of production for the new alumina expansion is going to be lower. Is that correct?

Unknown Executive

executive
#148

Can you repeat?

Unknown Analyst

analyst
#149

I'm saying that the quality of bauxite, if [indiscernible] is going to be incrementally positive for the cost of alumina production going forward. Is that correct?

Unknown Executive

executive
#150

Basically, the quality of bauxite at [indiscernible] mine, we will come to know after detailed exploration and all after development of mines. So at this point in that time, we cannot be 100% sure that we will be getting with that advantage.

Unknown Analyst

analyst
#151

Okay. So then what -- how are you assuming that the cost is so requirement for the new expansion will be lower based on the plan specification not on the bauxite, is it?

Unknown Executive

executive
#152

This year, we will be feeding the oxide from our existing mine to the new fit stream. And is the production of [indiscernible] mine starts, then when we will be using [indiscernible] backside. And this site, both will be mixed proportionately will be used in our [indiscernible] team as well as in [indiscernible]. So then the cost of production is likely to fall further with the [indiscernible] being operational fully. Is that correct? I think more or less, it will be same. Yes, because you see when the new mines are operated new mines operated the quality is better. And the more mines become older, we go deeper the quality is deteriorating. So this will be a new mine. So the quality will be getting better. And in our new refinery, which is coming up with the pressure dilation with the new technology where the positive soda consumption advantage will be getting due to the new technology in the refineries.

Unknown Analyst

analyst
#153

Right. And sir, I wanted to ask on the alumina realization 1 question. because we track something on the M&A between a different number from the one you get on the 370 because LME average for last quarter is [indiscernible]. So these got 3 owe complete the broad breakup of the exports are? And why is there a difference between the LME and your revaluation?

Unknown Executive

executive
#154

As far as you're talking about alumina alone. Alumina is not directly linked with the LME -- it depends on the supply demand supply of the alumina. Now earlier, we used to get from -- if you compare to LME, it was, we are getting has come down to 10% to 11%. Most of our alumina are going to the Middle East as of now also, around 60%, 70% of the alumina is going to Middle East by some growth or other -- and a few of the aluminas are also going to maybe Europe, some China some shipments are going. So actually, what is happening is the bauxite prices has gone up also slightly new gaining due to rents and all that. in Rusal, Russia and also China, two of the major refineries, they have curtailed the production of alumina because of the red mud issues there. So some supply temporary supply restrictions are there, which has cost to the increase in alumina spot prices to the level of 37 380, which we are seeing with easing out of this war situation and supply requirements in the requirement of alumina in the Middle East, which will continue to the same level.

Unknown Analyst

analyst
#155

Right. So on the long term, the alumina prices will gear towards 14%, 15% of [indiscernible] that right in some as [indiscernible] back in aluminum?

Unknown Executive

executive
#156

At 14%, 15%, maybe 12%, 12%, 11%, 12%. Because LME on the higher side, [indiscernible] around [indiscernible]. So alumina, if you see percentage wise not go more than [indiscernible].

Unknown Analyst

analyst
#157

And sir, my last question was on the net debt. Could you mention that the net debt is INR 10,000 crores now?

Unknown Executive

executive
#158

Net debt? Net cash. [indiscernible] cash results. That is a cash result. We are zero-debt company.

Unknown Analyst

analyst
#159

No, what is the net cash on the balance sheet as of the third quarter [indiscernible] net debt.

Unknown Executive

executive
#160

That is around INR 1,500 crore.

Unknown Analyst

analyst
#161

So that means that through the year, even after dividend payments will end up to the INR 15,000 crores kind of cash. Is that a correct number? And the CapEx. So the balance cash flow for FY '27?

Unknown Executive

executive
#162

Our debtor finance will explain to you every year how much we will be adding in the cash we have a balance of INR 10,500 now every year seeing our profitability and the tax, we are adding INR 2,500 plus because we are expecting R&D PAT of INR 6,000. We also we are projecting to earn us and next year onwards also. So after paying our dividend and our normal CapEx expense is around INR 1,500 crores. So the noncash item will be added to that at will be adding 3,500 plus every year. So when our CapEx funding will be there, we will have a sufficient to vegetate have, so we can easily announce our requirements through our internal appeals Okay. And that CapEx from the smelter will be approximately or INR 4,000 res, INR 5,000 crores per annum.

Unknown Executive

executive
#163

Because we have already explained that for a power plant, we have gone for a JV. So the equipment of a lesser there because that will be through debt to top ratio at 70. So 70-30. So the balance in our smelter pack will be coming through our internal accruals. So we will not go to the market for borrowing for our metal expense, seeing our treasure and our earning future potential.

Unknown Analyst

analyst
#164

And sir, the last question, if I could sneak in the capacity of the aluminum right now on the 950 pots we are operating is 4.6 lets. So is there a possibility of any downstream kind of growth there? Or is it limited to flare right? In the case of alumina, you're from 2.1 [indiscernible]

Unknown Executive

executive
#165

And so we are having capacity of 4.6 lakh tonnes. Last year, we have produced around 4.72%. And this year also, we are expecting we will be proving around 4.677 plan. we are slightly. We are operating at on debt, we are operating around 95, 99 ports.

Unknown Analyst

analyst
#166

Okay. So realistically, you can go to 4.75 kind of number purely in aluminum?

Unknown Executive

executive
#167

Yes, [indiscernible].

Operator

operator
#168

Thank you, sir. As there are no further questions from the participants, I now hand the conference over to Mr. Barak Kumar Shah from for closing comments. Please go ahead, sir.

Unknown Executive

executive
#169

Thank you, [indiscernible]. On behalf of NALCO I thank all the extreme participants who took out their valuable time and activated in this earnings call. This shows our open interest in the business activities of onco and also in the future, we expect a similar kind of operation from your side. Thank you, [indiscernible] for satiating the fourth earnings call for this Q1 [indiscernible]. I also enhance systematic group are continuously hosting this fourth earning call of Alto and quarterly basis, and we slice similar kind of cooperation in future also. Thanks. Thank you all.

Operator

operator
#170

Thank you. On behalf of NALCO Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete National Aluminium Company Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to National Aluminium Company Limited earnings transcripts and 251,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.