executiveGood morning, everyone, and welcome to National Grid's Half Year Results Presentation. I'm Nick Ashworth, Head of Investor Relations, and it's wonderful to see so many of you joining us today. First off, I'd like to point you toward the cautionary statement located at the front of the pack. As always, John and Andy will take part in a Q&A following the presentation, so please dial into the conference call if you'd like to ask a question. All of today's materials can be found on our website. And naturally, should you have any additional questions after the call, please don't hesitate to get in touch with me or a member of the IR team. With that said, I'd now like to turn things over to our CEO, John Pettigrew. John?
John Pettigrew
executiveThanks, Nick. Good morning, everyone, and welcome to the call. As always, Andy Agg, our CFO, is here with me. After each of us has presented, we'll be glad to take your questions. The past 6 months have been busy ones for National Grid, with steady progress on both the financial side and in delivering our strategic priorities. For governments worldwide, the energy transition is still a fundamental priority, and it sits at the heart of National Grid's strategy. Yet the latest headlines make clear that awareness is growing around the practical difficulties involved in delivering it. How decarbonization goals get met could carry real consequences for affordability, reliability and security of energy. So we have kept engaging proactively with governments and regulators, pressing for speedier reform progress so that a stable, predictable and investable environment exists to deliver net 0, and I'm pleased with how much we achieved in the first half. 6 months ago, we settled on 5 priority areas for policy reform in the U.K., and progress on each has been positive. In Electricity Transmission, we're increasing our investment, with the 17 major projects awarded to us under the accelerated strategic transmission investment, or ASD, framework now part of our license.
John Pettigrew
executiveAlso, in September, the Prime Minister gave a speech about how the government plans to handle net-zero. While that speech pushed back near-term bans on combustion engines and gas boilers, it did back a lot of the policies we have been pushing for. That includes a strategic special energy plan that provides certainty about what must be built, where, and when, fast-track planning processes for nationally significant projects, and a new connector move approach to grid connections. We have seen meaningful progress in the U.S. as well, where we submitted proposals in Massachusetts for the investments required to support the Stage 2050 decarbonization goals. We got approval to move ahead with our Propel New York Energy Transmission project alongside New York Transco, which will help offshore wind coming into the state. There has also been a step forward on the Twin States Clean Energy Link project, which will link Canadian hydropower to New England, after the Department of Energy chose it for federal funding. And last month, our community offshore wind joint venture succeeded in the latest New York offshore wind solicitation, receiving a provisional offtake award of 1.3 gigawatts. So clearly, the last 6 months demonstrate that we are now solidly in a new phase of capital delivery for the energy transition.
John Pettigrew
executiveSo because of that, we've now revised the five-year financial framework as of today. From April 2021 through March 2026, our expectation is to put in roughly GBP 42 billion, which is higher than the GBP 40 billion we previously guided to, and that raises how much we're investing in decarbonizing energy systems. Within the ranges we already have, this will give a modest lift to both asset growth and underlying earnings per share growth. And as we move into this exciting new phase of heavy capital delivery, we'll keep doing our part to ease the affordability strain felt across our customer base, since we have now beaten our GBP 400 million cost efficiency goal 6 months ahead of schedule. So moving on to how we performed financially. On an underlying basis — meaning we exclude timing impacts and exceptional items — operating profit from continuing operations came to GBP 1.8 billion in the first half, a 14% decline versus the prior year at constant currency. The underlying business did well in the first half, with the prior year boosted by several one-offs as we closed out transactions. Underlying earnings per share came in broadly in line with expectations at GBP 23.8, and our full year guidance is unchanged. A record GBP 3.5 billion of investment was delivered by our regulated businesses, a 10% increase year-on-year at constant currency.
John Pettigrew
executiveCapital expenditure for the operations we're continuing with came to GBP 3.9 billion. Consistent with our policy, the Board has declared an interim dividend of 19.4p per share, which represents 35% of last year's full year dividend. Now I'll move on to how we performed on reliability and safety. Starting with reliability, and that has stayed strong across our networks in the U.K. and the U.S. In the U.K., lots of you will have come across the winter outlook report that the electricity system operator published at the end of September. The ESO has forecast an electricity capacity margin of 7.4% this year, a touch above last year's figure and broadly in line with recent winters. That said, the ISO expects a handful of days when we'll need to use tools like system notices. And after its successful pilot last year, there's the demand flexibility service, which gives customers an incentive to cut consumption when margins are tight. We're confident about delivering our usual high standard of reliability across our networks over the months ahead, and we remain vigilant as we go through winter in both the U.K. and the U.S. Turning to safety. Our lost time injury frequency rate came in at 0.09, versus 0.11 last year and against a group target of 0.1.
John Pettigrew
executiveBut sadly, a colleague in our U.K. electricity distribution business died in August after a fall from height at a site in Ludlow. As you would expect, that loss has been felt very deeply throughout the group, and as a leadership team we are determined to ensure the lessons from this tragedy are shared right across the organization. Turning now to how the group has been operating, beginning with U.K. electricity distribution. We have made a good start under the new ED2 price control, with capital investment of GBP 608 million in the first half, 4% higher than the prior period, mainly reflecting increased spend on new customer connections, including the Hinkley Point nuclear connection. In July, we held our first investor event since acquiring WPD, at which we set out our plans for delivering the RIIO-ED2 price control, including a 30% step-up in annual investment from ED1 to ED2 -- or we intend to achieve our target of 100 to 125 basis points of outperformance, with a focus on totex efficiency. And there is our progress in integrating electricity distribution into the group, including identifying GBP 100 million in synergies to be delivered over the next 3 years. In the first half, we also enabled more than 40,000 domestic connections of low-carbon technologies such as solar panels, EV charge points, batteries and heat pumps.
John Pettigrew
executiveAlso, with demand for hookups to our grid rising so sharply, we laid out an action plan back in September that frees up 10 gigawatts of additional network capacity, speeding the hookup of renewable generation assets. Now turning to U.K. Electricity Transmission. Capital investment hit a record GBP 800 billion during the first half, up 27% compared with the prior year. That bigger spend covers close to 3 gigawatts of fresh connections made in the period, among them the biggest offshore wind farm anywhere, DogaBank in Yorkshire, plus the Lark green solar project close to Bristol — the first project of its type linked straight into the U.K. transmission network. We likewise hit 2 key milestones during the first half: finishing the tunnel boring on our London power tunnels — that project, which will future-proof the grid against rising electricity demand in the capital, stays on schedule to finish in 2026 — and completing all 116 tea pylons on our Hinkley Connection project, which will supply low carbon energy to 6 million homes and businesses. We have made major headway as well in building up our new strategic infrastructure organization, a business unit set to deliver our Asti projects, with 320 people now working inside the division.
John Pettigrew
executiveAs that map illustrates, we're carrying on with the detailed engineering effort on the 12 onshore and 5 offshore projects we've so far committed to move forward with Ofgem, and which now sit within our electricity transmission license. Specifically, during the period we picked the preferred suppliers for HVDC cable and converter stations on Eastern Greenlink 1 and 2, and we secured all planning consents on the English side of those links. We've kicked off engagement with the global supply chain aimed at choosing enterprise partners for 9 of the 12 onshore projects within Asti, and consenting has moved along well on the Orkard Green and Branford to Twinsted lines. As engineering works keep advancing, the investment profile will grow clearer, and we expect roughly GBP 3 billion of CapEx on these projects as part of our financial frame to 2026; including inflation, our present CapEx estimate sits in the mid- to high teens across the 17 projects. In New York, capital investment of GBP 1.3 billion came in 5% higher at constant currency. That reflected continued work on the FERC-regulated SmartPath Connect project, where we're rebuilding 110 miles of transmission lines in Upstate New York so larger scale renewable generation can connect, plus higher levels of leak-prone pipe replacement, with 148 miles replaced in the first half, which keeps cutting methane emissions from our network.
John Pettigrew
executiveWe've kept making headway as well on the new transmission projects that were given the green light last year under the Climate Leadership and Community Protection Act. All told, roughly $2.9 billion will go into those projects, which will allow additional renewable generation capacity within the state. And regulatory progress has been strong too. In early September, the Public Services Commission staff filed their response to our rate case for our downstate gas companies, KEDNY and KEDLI. We're glad to see wide backing from the staff for what we submitted, including the requirement for more investment, and we expect to get to a joint proposal early next year on new rates taking effect from April. Turning to our New England operations, where the regulatory stretch has been busy as well. In September, we filed our electric sector modernization plan, laying out a road map for our network to support hitting the Stage 2050 net 0 target. In that plan, we set out the essential investments our network needs over the decades ahead, among them a proposed investment of about $2 billion across the next 5 years. Also in September, the regulator signed off on annual rate adjustments of $67 million for Massachusetts Electric and $57 million for Massachusetts Gas. Those new rates took effect at the start of October.
John Pettigrew
executiveDuring the first half, our capital investment came to GBP 789 million. That figure was up 9% versus the same period a year earlier, on a constant-currency basis and leaving out the Rhode Island business that we divested last year. The increase reflected heavier spending on electric distribution, tied to a greater number of customer connection requests, along with additional investment in grid modernization. Within the first half, we finished upgrades at the Tsp substation through the FERC 1000 process, which is competitively awarded. Those upgrades represent a cost-effective way to maintain grid reliability as roughly 2 gigawatts of fossil fuel generation in the Greater Boston area is expected to retire next year. Turning lastly to National Grid Ventures, capital investment there amounted to GBP 326 million, including ongoing spending on the Phase I expansion of our Eslegreen LNG facility and on our Viking Link interconnector, where the final cable sections have now been laid and joined. First-half investment was GBP 205 million below the prior period at constant currency, reflecting the completion last year of the selling converter station rebuild. Construction work on our vacant linked to Denmark is now close to finished. The project is entering commissioning. We anticipate the 1.4-gigawatt interconnected being online by the end of December, which would lift the operating capacity of our interconnector portfolio to 7.8 gigawatts.
John Pettigrew
executiveIn October, National Grid Renewables began operating the Yellow Bud solar project in Ohio, which has 274 megawatts of capacity. That brings total renewable operating capacity to 1.3 gigawatts, with another 800 megawatts currently under construction. So, with that summary of operational performance for the first half, I'll now pass things to Andy, who will walk you through the financials before I return to discuss our priorities for the remainder of the year. Andy?
Andrew Agg
executiveThanks, John, and good morning, everyone. I want to point out that, as we always do, our underlying results are shown excluding timing and exceptional items, and the door figures are given at constant exchange rates and less specified. Our 40% remaining stake in U.K. Gas Transmission, now National Gas, is still reported as a discontinued operation after we agreed to sell a further 20% interest to the Macquarie-led consortium, along with the option for them to buy the remaining interest. Because of that, every bit of earnings from this business has been left out of the continuing group's underlying earnings. Now, onto our half year performance. We're happy with the operating and financial results we delivered, with underlying operating profit on a continuing basis of GBP 1.8 billion, which is in line with expectations. The prior period benefited from certain one-off items, specifically St William Property sales, 2 months contribution from NECO, our Rhode Island business that was sold to PPL, and insurance proceeds received at our IP-1 interconnector following the fire in September 2021. Together, these 3 items came to over GBP 320 million and were the main reasons for the weaker year-over-year performance. The key drivers of operating profit this period were higher revenues across our regulated businesses thanks to indexation in the U.K.
Andrew Agg
executiveWe also saw rate increases throughout our U.S. operations. At our NSL interconnectors Norway, we received an upward cap adjustment stemming from its post-construction review, plus there was no repeat of last year's Western Link settlement. Beyond that, during the half we delivered an additional GBP 53 million in efficiency savings, which brings the cumulative total to GBP 426 million — surpassing our GBP 400 million goal 6 months ahead of schedule. We'll keep pushing on efficiencies and anticipate comparable results in the second half as this program wraps up. Since net interest charges stayed broadly unchanged, underlying earnings per share tracked operating profit, and at 23.8P per share it came in 27% below the prior year. Although in the prior year underlying EPS leaned more heavily toward the first half than is typical, we expect this year to return to our long-term pattern, in which roughly just under 2/3 of earnings land in the second half. Moving on to our capital program, we're continuing to see solid progress there. Investment in our regulated networks reached GBP 3.5 billion — another record figure and a 10% rise year-over-year. In total, capital investment from continuing operations came to GBP 3.9 billion. The growth reflects greater connection spending as well as early-stage investments tied to our new Asti projects in our U.K.
Andrew Agg
executiveTurning to the electricity transmission business — grid modernization efforts in Massachusetts and a step-up in what we're investing in the SmartPath Connect transmission project up in Upstate New York. Consistent with our policy, the Board has declared an interim dividend of 19.4p per share, which represents 35% of last year's total. Scrip uptake in the summer on the full year dividend came in at 4%, and we will again be offering the scrip option at the half year. Now let me walk you through how each of our business segments performed. I'll start with U.K. electricity distribution. Underlying operating profit came to GBP 563 million, which is down GBP 16 million versus the prior year. Revenues got a benefit from indexation of the RAV. That said, this was more than offset by lower incentive revenues, as we expected at the start of the new ED2 period, and by profit from the sale of its smart metering business in the prior period. As we laid out at our investor event in July, we expect to deliver operational outperformance of 100 to 125 basis points across the ED2 price control. That will largely be driven through totex efficiencies, strengthened by synergies following the acquisition. To date, we've delivered GBP 18 million of our GBP 100 million 3-year group synergy target, so far mainly procurement enabled, for example, through the adoption of lower-cost cabling designs taken from transmission.
Andrew Agg
executiveFor the half year, capital investment rose to GBP 608 million, which is GBP 24 million more than the prior period, mainly due to greater spending on asset replacement and connections. That figure includes GBP 65 million for the Hinkley Point Electricity Distribution Connection Link, and that project is still on track for completion in 2024. Turning to U.K. electricity transmission, underlying operating profit there came in at GBP 656 million, an increase of GBP 92 million versus the prior period. The strong first half performance reflected higher allowed revenues thanks to indexation, along with the absence this time of the GBP 69 million returned in the prior period in relation to Western Link. Capital investment was GBP 800 million, which is 27% higher than the prior period. Part of that comes from work on our RIIO-T2 projects, including system resilience, asset health and new connections work, as well as significant progress on our major capital projects. We've also seen a step-up in investment in our Asti projects during the half, notably driven by our offshore projects, Eastern Green link 1 and 2, where we've signed joint venture agreements with Scottish Power and SSE and selected the preferred suppliers for HVDC cable and converter stations. For our onshore Asti projects, we've launched our great grid upgrade partnership tender to source enterprise delivery partners and secure the supply chain that will help deliver these projects.
Andrew Agg
executiveOur intention is to award contracts during 2024. That said, because we must keep pace with our Yorkshire Green project, contracts for overhead lines and substation work are already signed. Last, in the U.K., the electricity system operator recorded underlying operating profit that fell by GBP 18 million in the period, landing at GBP 34 million. After the Energy Act to 2023 passed at the end of October, the business has been classified as held for sale. Turning now to the U.S., where New York's underlying operating profit came in at GBP 119 million, which is GBP 76 million below the prior year. Greater net revenue, driven by rate increases and ongoing delivery of its cost efficiency program, was more than offset by increased depreciation stemming from rising investment levels, higher recoverable bad debts following the end of the state's bill relief program, and a pension buyout gain that occurred in the prior period. Capital investment totaled GBP 1.3 billion. That figure was GBP 62 million above the prior year, assisted by a step up in investments in the $550 million SmartPath Connect transmission project in Upstate New York and by greater investments in our gas distribution networks as we keep making progress on our leaf replacement program.
Andrew Agg
executiveThat said, the earlier period had noncash lease additions in it, among them the Voni Marci transmission line lease; if you set that effect aside, capital investment rose by close to GBP 200 million. Now on to New England. Underlying operating profit came in at GBP 218 million, which is GBP 33 million below the earlier period once Rhode Island's contribution is excluded. Increased rates for Massachusetts gas, pushed through its capital tracker, and for Massachusetts Electric, delivered via its yearly performance-based rate mechanism, were cancelled out by greater recoverable storm costs and greater recoverable bad debts after commodity prices rose. Capital investment reached GBP 789 million, GBP 64 million above the prior year, again leaving out Rhode Island's effect. The drivers were grid modernization spending on our electricity distribution networks plus more asset condition work throughout our New England Power transmission assets. Switching to National Grid Ventures. Performance stayed solid, with underlying operating profit of GBP 278 million, joint ventures included. Support came from strong interconnect results, particularly at our NSL Interconnector, and from good results at the Isle of Grain LNG facility. The GBP 51 million drop versus the prior year is mainly down to insurance proceeds received in that earlier year, along with a shift in the phasing of onshore renewables projects, where a larger share of sales into our joint venture is now expected in the second half.
Andrew Agg
executiveCapital investment for National Grid Ventures came to GBP 326 million. That was supported by ongoing progress at Viking Limpo Denmark, since we're close to finishing our SIC interconnector, and by spending on our Grain LNG expansion project, where construction of the new tanks is almost done. Investment ran GBP 205 million lower, because the prior year carried most of the IFI converter station rebuild spend along with peak investment at Viking and the Isle of Grain. Our other activities posted an operating loss of GBP 13 million, compared with a GBP 145 million profit in the prior period. The main reason is that property sales closed last year, largely through the St William transaction. Capital investment was GBP 13 million. Now to finance costs and tax. Net finance costs were GBP 711 million, a decrease of GBP 10 million. Reduced inflation on index-linked debt and lower bridge financing costs were partly offset by the effect of higher interest rates. The underlying effective tax rate before joint ventures stood at 24.7%, which is 500 basis points above the prior year, reflecting the rise in the U.K. corporate tax rate from 19% to 25% and the shift in profit mix given higher property sales in the prior year.
Andrew Agg
executiveLooking at the full year, the underlying effective tax rate—leaving out the joint venture share of post-tax profits—should come in at roughly 26%. Underlying earnings came to GBP 875 million, with EPS of 23.8. Turning to cash flow: cash generated from continuing operations reached GBP 3.1 billion, a 30% rise versus the prior year. The main driver here is favorable U.K. timing at the electricity system operator, partly offset by lower underlying operating profit than a year earlier. Net cash outflow for the period was GBP 2.6 billion, a reduction versus the prior year, since higher cash flows from operations were only partly offset by larger cash dividend payments given lower scrip uptake. Consequently, net debt rose by GBP 2.9 billion to GBP 43.9 billion relative to the prior year-end. For the full year, we expect net debt to grow by just over GBP 0.5 billion from the September level at a USD 1.2 exchange rate, including the GBP 700 million of proceeds we expect to receive from selling 20% in national gas to the Macquarie-led consortium. As we announced this morning, we have updated our 5-year financial frame, with group capital investment for the 2021 to 2026 period now expected to be around GBP 42 billion, up from our previous guidance of up to GBP 40 billion.
Andrew Agg
executiveWe think this higher level of investment will provide a modest boost to asset and EPS growth. Our commitment to a strong investment-grade credit rating stands, and we expect to achieve that growth while staying within our group gearing guidance, with regulatory gearing holding in the low 70% range during the period. The additional investment comes from our ASTI projects, where we now anticipate spending roughly GBP 3 billion, compared with our earlier guidance of GBP 1 billion, and that takes investment in electricity transmission to approximately GBP 11 billion, versus GBP 9 billion before. The ASTI uplift stems mainly from the progress achieved on 4 projects: Eastern Green, Link 1 and 2, YorkshirGreen and Branford to Twinster, and with 17 ASTI projects now in our license, as detailed engineering work advances, clarity on the scope of these investments is improving. On that basis, our present best estimate for total investment across these projects falls in the mid- to high teens billions of pounds range. Lastly, as is customary, in addition to refreshing our 5-year financial framework through 2026, we have refreshed our more granular guidance for this full year, which now reflects the electricity system operator being held for sale.
Andrew Agg
executiveIf we set aside the accounting gain from no longer recording depreciation on the ESO, our guidance for underlying EPS in FY '24 overall is unchanged from what we laid out in May. With that said, I'll turn things back over to John.
John Pettigrew
executiveThank you, Andy. To wrap up, I'd like to take a few minutes to go over what we're focused on for the second half of this year, beginning with the U.K. As I said earlier, the progress coming from government and Ofgem is encouraging to me, responding to our request for more urgency, in both action and mindset. The Energy Act is law now and will create a new future system operator, bring in onshore competition for networks, and put a net zero duty in place for Ofgem. We've also seen consultations on national policy statements on community benefits on the nationally significant infrastructure projects process and on market reform. And Nick Winser, the Electricity Networks Commissioner, has laid out his recommendations for fundamental reforms to the planning system and the creation of a strategic special energy plan endorsed by the Prime Minister and his net zero speech. We have an exciting few months in front of us. We've made good progress in the first half, and we'll keep pushing for more in the months ahead as we look to see consultations and announcements from government turned into real decisions and policy reform. The need for change is nowhere more apparent than in the connections process, and the forthcoming connections action plan from government and Ofgem is a critical opportunity to move away from the current first-come-first-serve approach to a connector move model and stop so-called Zombie projects from block in the queue.
John Pettigrew
executiveAt the same time, we're developing new answers in electricity transmission to tackle this problem. That involves changing how we work with DNOs and how we handle storage. These adjustments are going to free up 40 gigawatts of network capacity for projects that are ready to connect. We'll explore the connections topic in our next grid guide 2 series for investors in early 2024. Beyond connections, one more key area where we're engaging with stakeholders is advancing planning reforms over the months ahead; we anticipate refreshed national policy statements from government will offer greater clarity and authority regarding the need for and urgency of infrastructure projects, so they can be delivered on time. As part of that, we're continuing to back the development of a strategic special energy plan, along with a centralized strategic network plan, which will establish what needs building and where, in support of a more efficient system over the long term. Within our U.K. Electricity Transmission business, we're focused on pushing forward the 17 ASTI projects while we keep working with government and Ofgem on the policy changes required to deliver them. Last month, Ofgem published its future of system network regulation framework decision, which lays out how they see the framework evolving.
John Pettigrew
executiveWe'll keep working with Ofgem as they get ready to publish their sector-specific methodology consultation at the end of this calendar year. That consultation will serve as the foundation for putting together our RIIO T3 business plans, which we'll submit during 2024. Taken together, these things will give us added confidence and clarity regarding how investment will be shaped over the second half of the decade. Shifting away from regulation, another major priority for us in the second half is delivering our new contractual model for how we work with the supply chain. We have now kicked off the procurement process for our enterprise partnership model, and in the months ahead, we'll be choosing our strategic partners so that we have the supply chain ready to deliver these projects within the time frames required. And in electricity distribution, our focus is on wrapping up a strong first year of delivery under RIIO-ED2 as we ramp up our investment. Although the U.K. government has recently pushed back the ban on sales of combustion engine cars and gas boilers to 2035, our expected asset growth is unaffected, since more than 95% of our investment is already agreed within our baseline allowances. Turning next to our key priorities in the U.S.
John Pettigrew
executiveWe will keep building regulatory momentum in the jurisdictions where we operate. In New York, while we finalize settlement negotiations regarding KEDNY and KEDLI, we are also still on schedule to submit a new rate case for our Niagara Mohawk electric and gas business next summer. We also have a busy regulatory agenda in Massachusetts, where we filed our electric sector modernization plans. In those plans, we set out the investment needed to help the state meet its targets under the 2050 Clean Energy and Climate Plan. Our proposal covers upgrades that will improve how resilient network infrastructure is, greater digitization of the grid, and new customer programs aimed at encouraging energy efficiency and the adoption of clean energy solutions. We are now engaging with stakeholders ahead of making a formal filing in January next year. We are also finalizing the next rate filing for the Massachusetts Electric business, which will be submitted later this month. On the policy side, we continue to advocate for reforms that support the clean energy vision. That includes advancing a new clean heat standard with lawmakers in Massachusetts, which allows more renewable natural gas to be blended into our distribution networks. We hope to see similar legislation introduced in New York early next year. And across our U.S.
John Pettigrew
executiveOn the operations side, our attention is on carrying out our capital program efficiently. We'll keep advancing the big transmission projects we have in New York, and beyond the $550 million Smart Path Connect project that I brought up earlier, work has started on our $800 million CLCPA Phase 1 projects. That covers rebuilding 170 miles of transmission lines, upgrading 16 existing substations, constructing 2 new ones, and installing new technologies such as dynamic line ratings. We're also moving ahead with developing our CLCPA Phase II projects, which take in another 400 miles of transmission line rebuilds, along with 5 new substations and 11 substation upgrades. These efforts will assist New York in reaching its target of 70% renewable electricity by 2030 while improving how reliable and resilient the transmission network is. As I noted earlier, the Twin States Energy Link project was chosen in October to advance to the next stage. In the months ahead, we'll be working alongside the Department of Energy to move forward the 1.2 gigawatt capacity project, which, should it be built, would bring clean power from Canada into the region and could generate meaningful savings for customers. And at National Grid Ventures, we're carrying on negotiations with NYSERDA regarding the provisional offtake award of 1.3 gigawatts for our community offshore wind joint venture with RWE.
John Pettigrew
executiveWe also anticipate moving our bid forward into the New Jersey offtake solicitations during the first half of the next calendar year. So a busy period lies ahead of us. But before I wrap up, I want to take a moment to discuss our role as a responsible business. As I've mentioned previously, at National Grid, we undertake -- we recognize the important part we play in enabling both net zero and making sure the benefits of that transition are shared by everyone and that nobody is left behind. That responsibility sits at the heart of our core strategy and is foundational to everything we do. In 2020, we set this out through our first business responsible charter. Since that time, our business has changed considerably with the repositioning of our portfolio. And so in September, we released a refreshed charter. One of the elements of the update I'm proudest of is that, as a group, our near-term emissions reduction targets are now aligned with the 1.5-degree pathway, as verified by the science-based target initiative, or SBTi. With this, we aim to cut Scope 1 and 2 emissions by 60% by 2030 against a 2018/'19 baseline while lowering Scope 3 emissions by 37.5% by 2034. More detail on our updated responsible business charter and a replay of the recent ESG investor webcast can be found on our website.
John Pettigrew
executiveTo sum up, the first half has been a busy period, with solid results financially and operationally. To my mind, one thing is obvious: the opportunity in front of us is enormous. Considerable progress has been made, and we now understand clearly not only how big the challenges ahead are but also the way to get past them. The momentum behind policy reform that we have witnessed on both sides of the Atlantic leaves me optimistic, though what we need now is for announcements and consultations to turn into decisions and actions. Here at National Grid, we are beginning an exciting new phase of substantial capital delivery. We are delivering the energy transition today, and we stand ready to seize tomorrow's opportunities. So I will stop there, and Andy and I will gladly take your questions.
Operator
operatorThe operator has given their instructions.
John Pettigrew
executiveAll right, let's go ahead and begin the Q&A portion. Pavan with JPMorgan, please go first with your question, and then Dominic from Barclays, you'll take the second one. So Pavan, go ahead and kick us off.
Pavan Mahbubani
analystI have three, please. First, you've raised the CapEx guidance by $2 billion, and you mention modest enhancements to asset growth and EPS CAGR within the existing ranges. Could you give us a bit more of a steer, particularly on EPS? I recall that back in May, you were talking about being toward the lower end of the range because of changes in capital allowances. Is it fair to assume that a decent base case now is toward the middle of the range for EPS? Second question, following on from that: if we were to then adjust for the capital allowance impact on your EPS, again, is it a fair assessment that today's announcement should actually be seen, on a like-for-like basis, as coming on top of the 6% to 8% EPS range, or above the top of that range as you set it before the capital allowance position changed? And then my final question is on New York rate filings. I noted in your statement this morning that the New York PSC has responded to your rate filing with a 9.1% allowed ROE versus your 9.8% request. Do you expect an improvement on this front, or should 9.1% be our base case going forward?
John Pettigrew
executiveThanks, Pavan. I'll handle the first and third questions, and Andy can take the second. On the CapEx forecast upgrade — you're correct. We had previously discussed GBP 40 billion for the 2021 to 2026 period, and as of today we've raised that figure to GBP 42 billion. To give you some context on why: over the last 6 months, we've put in a tremendous amount of effort on the early projects tied to ASTI — 4 of them in particular — with extensive engineering work, much greater clarity on scope, and engagement with the supply chain as well. On the back of that work, we now have a clearer picture, and since we always aim to be as transparent as we can, we've moved the number up to the 42%. And as you noted in the statement, we've indicated that this will modestly enhance both asset growth and EPS. In May, Andy mentioned that, given the capital allowance change, we'd been sitting in the lower part of the 6% to 8% range. So yes, on the basis that this is a modest increase, it should move us toward the middle of that range.
John Pettigrew
executiveOn the New York rate filing, I honestly have to say I'm very pleased. The team put in an enormous amount of effort engaging with the PSC ahead of our filings, so nothing caught us off guard when we filed. The initial response showed clear acknowledgment of the investment that's needed, and equally clear acknowledgment of several of the programs we proposed for vulnerable customers. We came in at 9.8% at the outset, and the PSC staff's initial response was 9.1%. We're in that process now, so we're looking at whether a settlement and negotiation can be worked out over the coming several months. My hope is that we'll land somewhere in the middle between the two sides, but we'll see how far we get. Their starting point is 9.1, and our rate case filing was 9.8. So we'll see where things land over the next few months. Andy, would you like to take the second one?
Andrew Agg
executiveYeah, of course. Thanks, Pavan. So, just to add to what John said about the updated guidance this morning, which brings us closer back toward the middle of the range — you're absolutely right. If it weren't for the capital allowances impact to the 6 to 7, we would now be looking at EPS CAGRs above the top of the 6% to 8%, absolutely.
John Pettigrew
executiveLet's go to Dominic, and after that we'll hear from Deepa Venkateswaran at Bernstein.
Dominic Nash
analystIs this coming through? I have 2 questions. The first one likely consists of 2 parts. First, you raised CapEx, or your investment, to GBP 42 billion through the end of 2026. What that essentially means is your run rate rises, I believe, from EUR 8 billion this year to roughly EUR 10 billion across the next 2 years. Yet you devoted a good deal of the presentation to noting that ASTI is just EUR 3 billion, maybe in 2026, and we have another one, likely roughly another GBP 15 billion still to come, but a further framework could potentially arrive at the start of 2024, and in the U.S. CapEx clearly appears set to rise. So my first question on that is: what do you actually see as the potential run rate for the ASTI spend and the new one beyond the 17 projects we will reach, and over what kind of time frame will that GBP 15 billion be spent? Second, 2026 will be there in the bar and led, and I think we are only looking about 2 years ahead.
Dominic Nash
analystAt what point do you expect you'll be able to return to us with a picture of how your investment and balance sheet management will look? How soon will you have clarity, so that we can sort of see auto 2030 and beyond? And then the third question is on the ESO. I see it's now an asset held for sale. Could you give us some kind of guidance on the timeline, on how the price is going to be set, and on what happens if the guess comes in at a level that isn't satisfactory for you?
John Pettigrew
executiveAlright, Dominic. I’ll address those questions. Regarding how we view capital investment past 2026, it’s actually comparable to my comments in May. I believe we’ve made solid progress during the last 6 months. The way I’d frame it—and I do frame it this way to my team—is that the mists are beginning to lift. You saw evidence of that today through our near-term upgrade, thanks to projects we’ve been developing that moved us from 40% to 42%. But over the coming period, we do need somewhat more clarity on precisely what CapEx we’re being asked to deliver across the longer term. Some uncertainty remains there. Second, and probably most important, what the profile of that CapEx will be. Clearly, we’re awaiting the outcome of items such as the Nick Winser review and where the government will land on certain policy decisions like community benefits and so forth. That will shape what that CapEx profile looks like. And finally, naturally, we’re waiting to see what the regulatory framework will be regarding incentives for delivery.
John Pettigrew
executiveAs soon as we achieve that clarity and transparency, we’ll be in a position to tell the market what the CapEx profile looks like past 2026. On timing, for the items within our control, we will definitely bring the market up to date once we have improved information, and that is precisely what we did today with the $42 billion update. However, some elements sit outside our control. Still, we have a reasonably broad sense of what we expect to see. So in the period ahead, we are hoping for a response from the government regarding the Nick Winser review on streamlining the planning process and the national policy statements. A sector-specific consultation is due to come out in December. How much information it contains will shape what it gives us for the regulatory framework. You have the ESO publishing its next centralized network plan, with the investment it receives beyond 2030 through to 2035, hopefully in the first quarter of next year. So if those developments land within the time frames currently being indicated, the fog will keep lifting and we’ll be able to offer some transparency. But those matters are not actually mine to give in terms of control.
John Pettigrew
executiveThe answer is that once we have that transparency, we'll share it with you. Regarding the ESO, let me begin by saying we're rather pleased that the energy bill has passed. In fact, the government needed that energy bill in order to be able to purchase the system operator from National Grid. As you know, we've consistently supported the idea that given the role the ESO has been asked to fulfill, separating it from National Grid is the right thing to do. Over the past 12 months, we've been quietly busy in the background getting ready for that separation, which could potentially happen in the summer of next year. We're carrying out a lot of the IT separation work that you would expect us to be doing, and now that the energy bill has gone through, we're in a position to engage with the government on the commercial aspects of it. They've recently appointed their advisers, and we're just beginning those conversations now. So we'll keep the market updated as this progresses, but we've only just started those discussions. Okay. So if we could -- we'll take the question from Deepa next and then James from Deutsche Bank.
Deepa Venkateswaran
analystI've got two questions. The first concerns the community energy project for offshore wind that you won together with RWE. Could you describe what return expectations you'd have for taking FID on that project? I realize FID isn't until roughly 2027, but it would help if you put your return expectation into context against, say, the 10% FERC allowed returns on transmission projects. And then, in the same manner, could you also speak to some of the difficulties that other projects are running into in both New York and New Jersey? And how comfortable do you feel about East Coast offshore wind at this stage? So that's my first question. The second one concerns the Ofgem debt indexation informal consultation that's expected at the end of this year — what do you expect them to say? And how has your engagement with Ofgem gone so far? And do you see them as fairly open to doing nothing or to examining this data? So those are my 2 questions.
John Pettigrew
executiveYes. Thank you, Deepa. I'll take your first question in reverse order, actually. Let me just speak a bit about the issues you mentioned in the Northeast offshore market. I mean, clearly, we've all witnessed what has been happening up there in the Northeast, with several projects either pulling out or seeking to renegotiate. And obviously, you would need to speak with those companies regarding the details of that. What I'd say is that because of when we responded to the Smitation in New York, we could incorporate into our bids what was really happening in the supply chain, including items such as indexation, which we had the chance to offer in our bid. So we're glad that, provisionally, we have reached an agreement for the 1.3 gigawatts as part of our joint venture with RWE. We are now moving into the negotiation stage with NYSERDA. So in the end, that's a process we must work through over the coming few months. But in the end, our stance remains the same in that we -- this is a discretionary investment within our Nasal Ventures business. It has to fit within the group's overall capital program, and it has to deliver returns that, as we've said historically, must exceed those we'd see in our regulated businesses, given their nature.
John Pettigrew
executiveWhether that ends up being the case, though, is going to be settled by the negotiation. I'd also remind you — and I'm sure you know this — that under the joint venture structure, we hold the option to pull out at any point up until FID, should we conclude that the investment proposition doesn't work for National Grid. That option stays available to us as we move forward. Still, our hope is that negotiations get underway fairly soon and, my guess is, they'll probably stretch into the first quarter of next year. On the inflation consultation Ofgem is running regarding debt indexation, I have to say — in fairness to them — I think they've handled it in a very balanced way. They clearly understand how important inflation is as a foundation stone of regulation in the U.K., and they equally understand how important it is to build a regulatory framework that encourages investment going forward. As you're aware, the consultation, I believe, laid out 5 options, ranging from doing nothing through to voluntary contribution, with everything in between. NYSERDA has been working alongside the ENA and has laid out our response, which is that if you take a long-term view of this, we don't believe there's an issue. But obviously, given where inflation has sat over the last couple of years, Ofgem needs to examine it.
John Pettigrew
executiveI can't say where they'll end up. It might make sense to handle it within RIO-T3, potentially that's the right approach. But from the conversations I've had with them, I do think they're taking a very balanced approach to it. Okay. So let's take James from Deutsche Bank next, and then Martin Young from Investec.
James Brand
analystI have two questions. Both relate to the balance sheet to some extent. First, in the 5-year financial plan, your statement said you expect gearing levels and other credit metrics to remain within your current rating bands. Still, there's a perception among at least some investors that those metrics tighten somewhat over the plan period. So my first question: is that perception fair? Or do you believe a very comfortable buffer still persists on your rating metrics throughout the period? And second, longer term, obviously, CapEx looks like it's going to be pretty huge. I'm sure you won't lay out in detail just now how you'll fund that. But I was wondering whether there's any preferred approach you're willing to share for funding that future CapEx. In the past, you've obviously sold assets when needed in order to fund the big CapEx program — would that be the preference going forward, or are all options on the table...
John Pettigrew
executiveAll right, thanks, James. Andy, would you like to...
Andrew Agg
executiveSure. First, on the current 5-year frame — and just to restate what we said again this morning, which lines up very closely with our prior comments — even with the increase to GBP 42 billion that ASTI drives, as John laid out, we clearly expect that to keep delivering regulatory gearing in the low 70s, which is very much in line with what we've said before. And that's very much consistent with keeping a sensible and appropriate buffer against the credit metrics. As you know, the 2 key ones we monitor are Moody's RCF to debt and S&P's FFO to debt. So absolutely no change there. I can't speak to how others are modeling that, but from our side it's very clear, and it's unchanged from where we stood at year-end as well. On the longer term, as John has already said, I think there's still a lot of work to do around the cadence of the spend, the timing, and the regulatory frameworks that we're only just beginning to engage with Ofgem on as we look out to T3 and the ASTI framework. And of course, we'll want to work through all of that.
Andrew Agg
executiveAnd then for sure, we'd consider what funding approach makes sense, but it's reasonable to say that looking at how we operate now, we still enjoy access to a broad set of instruments. Obviously, we keep using senior debt at present. The script gets used by us continuously. We have both current and possible future entry to the hybrid market, where substantial headroom exists that we haven't drawn on before. We've shown we're able to make use of asset moves too. That's been visible over the past few years. And naturally, our toolkit is complete, extending as far as using items such as partnerships, which we've done across interconnectors and similar, plus of course broader entry to capital markets, debt and equity. So every one of those is open to us. But, as we've mentioned a couple of times, we'll return to the right instruments once the cadence and timing of the CapEx are clear to us.
John Pettigrew
executiveAll right, we’ll go to Martin now, and after that, Harry Wyburd.
Martin Brough
analystThis is somewhat in the same vein as what James asked and the remarks John made earlier regarding U.S. offshore wind. It seems to me there's a substantial opportunity for you to accomplish plenty of things well into the next decade. Not every one of those will be mandatory. You brought up partnerships as one possible avenue. But perhaps you could give us a high-level view of how you'll decide whether you want to take on something that potentially arrives at your door, since ultimately that ties back to James' question about how it can all be financed.
John Pettigrew
executiveYes. Thanks, Martin. I mean, I think what Andy and I just said kind of captures that. What I've consistently maintained about National Grid venture investments is that being in adjacent markets makes sense, since we can apply the capabilities we've built across grid and spot chances to potentially earn incremental returns beyond those from our regulated businesses. But we'll only proceed in a highly disciplined manner when returns exceed our hurdle rates on a risk-adjusted basis and when it suits the overall group capital investment plan. That approach is unchanged, whether we're examining onshore wind, offshore wind, or even the investments made in National Grid ventures, including items such as interconnectors. So that's the disciplined approach we'll keep applying. As I mentioned in my earlier answer regarding offshore wind, we're in the negotiation phase now. We'll see how it looks financially, but we also retain the option, if we choose, to exit that with no loss of income to National Grid going forward as well. Okay. So I was going to take Harry, Harry Wyburd next.
John Pettigrew
executiveSo, let's just work our way down the list, and then we'll go to Sam Arie.
Harry Wyburd
analystHarry Wyburd here, from Exane. I’ve got two questions, please. The first concerns politics, and in particular Great British Energy, which came up a few times again at the Labour conference. I was just wondering whether you have any further thoughts on how you expect Great British Energy could interact with what you’re doing. And specifically — thanks, Andy, for the list, I suppose, of tools on the balance sheet — but is there a chance that Great British Energy might be an additional tool available to you on the balance sheet? For example, might the government be willing to co-invest with you in certain projects? Or could this be a route to accessing very cheap government-backed capital for your projects? Then the second question is about debt cost. I think since you last had your full year results, gilt yields in your secondary market traded bond yields have risen by roughly 50 to 100 basis points. So I’m just wondering whether that was factored into what you mentioned this morning on your EPS CAGR. Have you nudged up slightly your new issue costs on debt? And how do you feel about how that interacts with the, obviously, indexation on your cost of debt allowances, which behaves a bit more slightly than the changes in rates that we’ve been seeing over the last few months?
John Pettigrew
executiveAll right. Thank you, Harry. I'll handle the first question and have Andy take the second one. On GB, and more generally on policy with the Labour Party — as you would expect, considering the position NaturalGlo holds in the U.K., we are always in dialogue with both the government and the Labour opposition. And I have to say, they understand, just as the government does, how crucial networks are to the energy transition. Many of the items we set out in our spring policy document — on policy reform, community benefits, and a special energy plan — line up very closely with their thinking. On Great British Energy, we've had some genuinely productive discussions with them. And we do see potential upside in certain things they mention that GB Energy might be able to do. For instance, drawing on the convening powers of government to potentially coordinate the supply chain at U.K. level, so that we can secure some of the capacity that will be needed globally — that is certainly an area where there could be potential benefit. In the same way, they've discussed putting money into technologies that perhaps aren't yet ready for private capital, and that strikes me as a very sensible idea.
John Pettigrew
executiveAt the conference, they did bring it up—possibly putting money into competing transmission where needed. And in the end, I believe our own view is that, provided we secure the proper regulatory framework and stable policies, there is actually ample access to capital in the private market, and that is probably not the best place for public funds to be spent. But they are also at quite early stages of thinking on this, and we keep engaging with them. Andy?
Andrew Agg
executiveYes. Thank you, Harry, for that. Regarding debt yields, I think first of all you'll have noticed in the results we published this morning that overall interest costs and treasury costs came in flat — slightly lower, in fact. Within that, though, yes, we are definitely seeing increased interest rates, both when it comes to refinancing debt that already exists and, naturally, when financing growth too, and in this first half that has been offset by other factors. On future guidance, yes, to be clear, I don't question the forward curves — we rely heavily on the curves we observe in the various markets. And on your point about spreads, we are fully aware of that today. Again, we tend to adopt reasonable assumptions regarding forward spreads, and once more, I don't build anything heroic into our forward guidance. So I'm at ease that the updated guidance we've issued through to 26 accounts very much for the macro factors we are seeing. As for how this links through to the debt mechanisms in regulation, as you know, in the U.S. we obviously still hold a right of pass-through treatment provided we keep issuing efficiently, which, naturally, we always aim to do. And in the U.K., given how the index operates and the true-up mechanism, I think we absolutely still believe — particularly with the adjustment Ofgem made to the ED2 mechanism later on — that this gives us the opportunity to keep performing well against that.
Andrew Agg
executiveHere's what I think I'd say, though: when we look ahead, especially toward T3, I really do believe the cost of debt mechanism is something we'd engage with Ofgem on. A growing CapEx book in an environment of rising interest rates is something I think will require us to revisit how the existing cost of debt mechanism works. And I think that's something that's often acknowledged today as well.
John Pettigrew
executiveSam, let’s take your question first, and then we’ll go to Rob from Morgan Stanley after you.
Sam Arie
analystI want to return to the subject I think everybody's been kind of digging at, which is the CapEx... the CAPEX outlook, the sustainability financing formula. I know you're kind of not wanting to delay or your card there right now, but maybe I could just add you in so I'm sharing a bit more thinking on how this is all going to add up, and perhaps correct me if I'm getting anything wrong here. But I think my first observation is that your -- what you might call business as usual CapEx is probably going up in the next period. We hear a lot about how important it is to debottleneck the network side of the energy transition, and clearly there's demand and so on. So you're probably going to need to spend the lease as much as you currently are doing plicat. Then you have the SC projects on top of that, then you maybe have some other things in the U.S. It seems like quite a big bump to the CapEx outlook. On the ASTI project, second point, I think we were previously hoping that Ofgem might have some kind of special help for you on the FT projects.
Sam Arie
analystYet it appears that in October, they seemed to have rejected that, and it will simply be handled as part of the broader price control. So I'm curious whether that was a letdown from where you sit. I heard your earlier remark that you keep working with Ofgem. I wonder whether that is what you meant. More broadly, though, there still seems to be a fairly large question here. And you noted, of course, that you can tap debt and equity markets and that you could do more asset rotation. I suppose those moves would be dilutive. So if I put all this as a question, it could be — am I correct to think the longer-term earnings growth rate must come down either because you cannot keep the CapEx equation balanced the same way you have in the current plan, or because you have to take some rather dilutive steps — to make the financial equation work, and that then dilutes EPS growth. I mean, I'm just trying to get a sense of — it seems to me that if I can pick one question to answer here, then it may be a bit stressful, but I may be estimating.
Sam Arie
analystAnd I would really like to get a sense of how tough you believe solving this problem is.
John Pettigrew
executiveThanks, Sam. Let's take that piece by piece. So I'll handle the first 2 questions, and then I'll turn to Andy — if you could take the third one. I mean, on the CapEx outlook, I'm kind of going to restate things, but I'll try to build out what I said before, which is that from where we sit, we believe it's really important to give the market transparency and clarity when we have some degree of certainty. Absolute certainty isn't required, but some degree of certainty is. And we're still not in a position yet where we know precisely what we're being asked to deliver on CapEx — and you cited some of the items that are uncertain, whether that's the KEDLI and KEDNY rate case in the U.S., the Massachusetts Electric brakes, which we're filing this month, we've got the electricity sector modernization plan in the U.S. And then in the U.K., we've got the ESO due to do its next transitional network plan in the new year. So we're working through that right now to get clarity on what we're being asked to do and what will be put out to competition and all those sorts of things.
John Pettigrew
executiveWhat matters most, I'd say, is the shape of that CapEx. Take the U.K. — absent any planning reform, building a transmission line takes 7 to 12 years, as you're aware. Should streamlining come through — one of the things Nick Winser advocated in his report — the profile would look very different than if those reforms don't materialize. In the same vein, local communities are fairly engaged, especially in East Anglia, regarding how they view these investments. So getting community benefits right will also shape what our profile looks like. That's what we're working through right now. And ultimately, we need a solid grasp of the regulatory framework, which ties into Andy's answer on funding — the speed of cash, slow money versus fast money, depreciation rates, returns, and the incentives to deliver faster or not. All of that has to be worked through. Once we have it, we'll be able to state very clearly what the CapEx profile looks like beyond 2026.
John Pettigrew
executiveWhen it comes to frameworks, including the ASTI framework and splitting that out, I'll take a broader view in my answer. The decision document Ofgem released not long ago, I'd say, is broadly in line with what we expected, and a lot in it pleased us greatly. So Ofgem acknowledging that the regulatory framework needs to change, I thought that was genuinely significant. They referenced evolving the RIIO framework. The acknowledgement that large projects will get a separate framework, I believe, appears in that document, and I consider that important. Yet they likewise mentioned wanting to streamline and simplify how the regulatory framework works, while also making a framework that is genuinely appealing to investors. So every bit of that pleased me greatly. That document included a statement about handling the financial side of ASD within RIIO T23. That's an issue we'll keep discussing with Ofgem. I genuinely believe there are benefits to separating that out. We can live with it if it's handled in T3, but my preference is to try to deal with it sooner, and we'll carry on that dialogue with Ofgem over the months ahead.
Andrew Agg
executiveYes. Thank you, Sam. Regarding what this might or might not imply for trends going forward, and to some extent this is getting quite hypothetical, given the earlier responses about all the uncertainties and the items we still have to work through. But what I'd say is that, as previous price controls have shown us, in fact, it isn't only the CapEx levels — other levers also carry significant weight for earnings profiles, especially across the U.K. businesses. And in fact, if you return to the FSN document, it contained positive commentary about the need to establish an investable framework, acknowledging that we may need to examine returns and so on. But as T2 showed us, there is also recognition that a broader set of cash levers needs consideration, which might include items such as asset lives, and might include items such as the farslow-money mix too. So every one of those elements will certainly factor into the future profile. So I think it is far too soon to begin speculating about what EPS CAGRs might or might not do over the long term.
Andrew Agg
executiveThere's still a great deal that has to happen before we reach that point.
John Pettigrew
executiveAll right, I’ll take the next question from Rob at Morgan Stanley, and after that, Jenny at Citi.
Robert Pulleyn
analystThis is just one point, and it takes a different angle on the earlier subject that I think is very much at the heart of investor debate right now — namely, the effect of inflation. Perhaps I could ask about what this mid- to high teens figure means, so let's take GBP 15 billion to GBP 19 billion of ASTI CapEx that you've confirmed today. What did that look like, say, 12 months ago when you were looking ahead? And while inflation is clearly passed through under your regulatory regime, it still has to be financed in advance — and on that basis, apart from, shall we say, the amount of work or the cost of finance, which was the earlier question, might the inflation we're witnessing across these infrastructure projects result in difficult choices on capital allocation between, frankly, the opportunities you have in IT, ED, U.S. and NGV. And if I can push things a little further, which of those lines would take priority for capital allocation.
John Pettigrew
executiveOkay, I'll take a shot at answering question one. I'll touch a bit on question 2 as well, and then pass it over to Andy. That's fine. So, regarding the mid- to high teens for the 17 ASTI projects — over the past 6 months we've done an enormous amount of work on the early ASTI project. I think Andy mentioned them. That's the Eastern Link projects 1 and 2, Branford Twin stead and Yorkshire Green. By doing that, we now have a far clearer picture of the scope. We also have a much clearer picture of the engineering solutions, and we've gone out to the supply chain and signed contracts. So all of that is what has driven the 40 to 42 million. We haven't really discussed ASTI for quite a long time, actually, in terms of its overall cost, as we've been working through with Ofgem on what our license obligation will be and on whether we're going to do all '17, which we only actually received information about at the start of this year. Actually, the last time it was mentioned, I think a figure around 12 for the 17 projects was often put in the consultation.
John Pettigrew
executiveThat takes us back to 2021 and 2022. Given inflation indexation and the most recent sense of conditions in the supply chain, you reach the mid- to high teens fairly fast, and that's what drove the rationale. As I mentioned earlier today, we'll keep updating the market as we move through the remaining projects in ASTI. But honestly, the figure in the consultation document roughly 18 months back was 12, and once you index that for inflation and factor in what we told you today, you land around mid- to high teens. On your inflation question, the one thing I'd add — and this ties to the big U.K. projects — is that the regulatory process actually works like this: as we engineer these projects forward, before we settle allowances with Ofgem, we genuinely get a chance to go out to the market and establish what those projects will cost. So where supply chain inflation is showing up, we can hold that discussion with Ofgem before the allowances are set for each individual project.
John Pettigrew
executiveAnd for these initial projects I just mentioned, we’re still working through that process. So where we’re encountering inflationary pressure, we can capture it and discuss it with Ofgem before things move forward — Andy?
Andrew Agg
executiveAnd I believe the second part of what you asked had to do with how this informs possible thinking regarding capital allocation. I think there are a couple of general points there. First, naturally, as you are surely aware, when it comes to the regulated businesses we run, we will 100% fulfill our regulatory duties. So as the owners of those businesses, those CapEx plans get agreed with our regulators, they satisfy customer needs, and we are required to deliver them, and we will always make that a priority and make sure we do so on both sides of the Atlantic. I think you have heard us say previously that following the pivot, the mix we have shifted to in terms of electric and gas, moving toward 75-25, is one we feel very comfortable with. The overall U.K. and U.S. split for the group, again relatively near 50-50, is again something we feel very comfortable with. So -- and as John mentioned a couple of times this morning, I think in his opening remarks, when we consider the discretionary opportunities at National Grid Ventures very carefully, we will, of course, be disciplined, and it would hinge on the return opportunities available and, of course, how and whether they fit within the group's overall capital frame.
Andrew Agg
executiveThat's pretty much how we'd approach capital allocation from here on out.
John Pettigrew
executiveNext, we’ll take Jenny from Citi, and after that Bartek from Societe Generale. Jenny, go ahead.
Jenny Ping
analystOkay, so this one's directed at Andy. Back when we went through the full year results and discussed that 6 to 7p, you suggested at the time that it was a temporary shift, and that's why it showed up in your earnings. But I recall you mentioning that should it turn into something enduring — if it's going to persist — then you'd definitely be looking at taking that impact out. And with the autumn statement coming up, there's more talk around full expensing and what that would mean. So I was just wondering: if we did get that confirmation, would you in effect put the 6 to 7p back into your earnings?
Andrew Agg
executiveYes. Thank you, Jenny. No, I’d simply restate exactly what I said back in May: at the moment, this is a temporary phenomenon of 3 years that has previously been announced. We didn’t believe it was the right thing to do to change our fundamental way of presenting our results. I’d repeat what I said there, though. And I’ve seen exactly the same commentary and speculation in the media around what the chance may or may not say. If it does become enduring, then absolutely, we would look again. And as I said then, if it’s material and it’s distortive to how we present our economic performance, we would absolutely look at the right way to do that, and that may lead us to add it back. But we’ll wait and see what the chances as first year.
John Pettigrew
executiveBartek?
Bartlomiej Kubicki
analystThere's still room for more, so please keep them brief. First off, there have been quite a few discussions around ASTI, upcoming investments, possible funding, and changes to regulation. I suppose you really can accelerate cash generation down the road by, say, having a bigger proportion of fast money or a shorter depreciation period. But purely as a hypothetical, would you think about switching the nominal—you favor moving the U.K. regulatory framework to a nominal regime in which returns would actually be higher, obviously, and cash flow generation would then come faster to fund future growth? Second, in your presentation you brought up the first transmission-connected solar farm. I'm just curious whether that's something that might occur more frequently in the U.K., and as a result, does it present an upside risk to your investments going forward? And third, regarding your FY '24 technical guidance, just 2 points: when I compare this guidance with the one given at the FY '23 stage, you've lowered your contribution expectations from JVs, stating that contributions from interconnections would be smaller. So I was just wondering whether you're already observing a normalization of earnings from interconnectors, or are we still at levels above the historical ones?
Bartlomiej Kubicki
analystTurning to the technical guidance, you also bring up an extra 4 bps of one-off ROE creation in New England. I believe that stems from the property tax return. Could you maybe explain what that is and whether it will genuinely affect your earnings and cash flows?
John Pettigrew
executiveThanks, Bartek. I'll handle the first 2 questions, and then I'll have Andy speak to guidance. I mean, when it comes to the regulatory framework — I do think getting the right regulatory framework in place for these major projects matters. And you already heard me mention this morning that, as we work through this, one thing that matters to us is having clarity on that — whether we're talking about returns, whether it's fast money or slow money, whether it's depreciation periods — all of that is open for debate, and we need to work through it. On regulation, actually, one thing I think is very beneficial for investors in National Grid is having that mix of nominal and real regulation across the U.K. and U.S. That gives you a slightly different mix between yield and growth, as you know, which is beneficial. And I'd add as well that a shift to nominal regulation would have quite a significant impact on customer bills, which is something we need to be mindful of as part of the NG transition. So for those reasons, I'm not really an advocate of phenomenal regulation in the U.K. But we do need to get the right regulatory framework.
John Pettigrew
executiveI’d certainly agree with you there. As for the transmission farms, actually, this is the first instance of solar pumps being connected directly to the transmission system. If you look at the connection queue that exists in the U.K. right now, there are over 400 gigawatts of parties seeking to connect to the transmission system, and of that 400 gigawatts, about 80 gigawatts is, I believe, solar. So there are a great many out there who are looking to connect to the transmission system. So I don’t view it as much of a risk, since they are customers that would seek to connect to the transmission system, or we will need to reinforce it. Ultimately, as you know, a lot of work is underway around connection queues and which are the real projects and which ones need to be removed. But nonetheless, we will need to serve those customers just as we serve other technologies. Andy?
Andrew Agg
executiveRegarding our guidance, I believe you brought up the 2 points. First, about our guidance as it relates to joint ventures. And as you mentioned, when it comes to interconnectors, it's probably too early to determine whether this is simply a reversion to long-term rates. I think what we've observed, obviously, as you're aware, over the last year or 2 is greater levels of arbitrage payments flowing through on the capacity auctions. We are definitely seeing that ease somewhat this year. But again, if you look at the curves, you do see them declining, though I think we'll need to wait and see whether that truly represents a long-term normalization. It's still healthy returns, just to be clear. It's just somewhat lower than what we've seen over the last year or 2. So we remain very pleased with how those interconnector assets are performing overall. And then regarding the one-off item in Massachusetts, what it is, it relates to regulatory agreements we reached with the DPU earlier this half concerning property tax costs that we incurred in prior years, which they've now agreed we should be entitled to recover, which is why we recognize it through the ROE this year.
Andrew Agg
executiveAt this point, we have received that clarity from the Massachusetts regulator.
John Pettigrew
executiveThat covers every question we received over the phone, but I believe there's still time — Nick, perhaps one question is coming in online.
Nick Ashworth
executiveAlright, let me squeeze in one final question, then. This is Ahmed Farman from Jefferies. There are a couple of things I'd like to ask. The first one concerns ASTI CapEx — I believe, hopefully, that's been covered by some of the earlier questions that came up. So the other one is this: the first half results show operating profits in the U.S. regulated business declining year-on-year. Could you share your thoughts on how you expect this business to perform in the second half? And what ROE do you anticipate achieving in New York and New England this year?
Andrew Agg
executiveOkay, absolutely. Thank you, Ahmed. First off, I'd like to point you toward a few remarks we included in the presentation — namely that, as has always been the case, we anticipate a very uneven first-half versus second-half split for the U.S. So because of that, we remain quite optimistic regarding how the U.S. business will perform overall across the entire year. You'll have noticed in the detailed guidance we provided for New York and New England that we do anticipate meaningful growth in New York. You'll observe that pro year end comes in a bit lower, reflecting the update we shared regarding the environmental charge in our preclose. Yet even taking that into account, we anticipate meaningful operating profit growth year on year in New York. When it comes to ROEs, our guidance remains the same apart from the single items I just mentioned in Massachusetts. So — and once again, that is unchanged from the guidance we issued back in May.
John Pettigrew
executiveAlright. Well then, I want to thank everyone for being with us today and for a truly excellent round of questions. I suppose, just to wrap up our main points, really with strong — truly solid financial results for the first 6 months and today reaffirming our full year guidance, as you just heard from Andy, very happy with how the business has performed operationally across the group and the regulatory headway we are making and also the sway we are having on the policy agenda as well. But very much entering an exciting phase of delivery of the en transition, as you have seen from the CapEx figures we reported today, but we feel very well placed both to navigate the challenges and to seize the opportunities that lie ahead of us as part of this energy transition. So thank you all for being with us, and I look forward to seeing you all in the next couple of weeks.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete National Grid plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to National Grid plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in National Grid plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.