New Fortress Energy Inc. (NFE) Earnings Call Transcript & Summary
November 8, 2023
Earnings Call Speaker Segments
Chance Pipitone
executiveAll right. Thanks, Melinda, and hello, everybody. I appreciate your presence on this conference call, during which we'll go over the results for our third quarter of 2023, what's happened lately, the operational side of things, and what lies ahead for us at NFE. Per Melinda's earlier note, a recording of this call is being made, and a replay can be accessed in the investors portion of our site, beneath the Events and Presentations subheading. At that same spot, there's a press release covering our third quarter 2023 results, along with the matching presentation we intend to go through during this call. While we move through our discussion, we'll be referencing that presentation; within it, you'll also come across a set of significant disclosures concerning forward-looking statements and non-GAAP financial measures. We urge those participating to look over these significant disclosures, along with the description of risk factors included in our SEC filings. So now, let's get into the call. Once more, I'm Chance Pipitone, and here with me today at New Fortress Energy are our Chairman and Chief Executive Officer, Wes Edens, our CFO, Chris Guinta, our Managing Director of New Business, Andrew Dete, plus other managers from our senior leadership team. Wes, the floor is yours.
Wes Edens
executiveAlright, thank you, Chance. Hello, everyone. Like Chance said, we've posted a presentation about Terminal B over on our site. There is an enormous amount of excellent material in there, and I won't revisit all of it or drag it out, but plenty of solid reference documents exist; so the earnings deck this quarter is a slim one given everything that's already available. So let's get started. Honestly, this was hands down the strongest operating quarter in this company's entire history. There are lots and lots of items worth covering regarding our operating achievements, though a few deserve mention. First and most importantly, from our perspective and that of numerous others, our inaugural FLNG unit now stands solidly in position; mechanical completion has been achieved. It sits at the site. The pipeline connection has been made. Commissioning is now in its closing phases. What the whole team pulled off is genuinely extraordinary: 5.4 million man-hours, two and a half years. That makes it, by every conceivable standard, the fastest liquefier ever delivered anywhere, and we take real pride in it, and clearly it's a true anchor of the supply side of our operations. Second, down in Puerto Rico, we finished both of our power plants there, with the latter reaching completion and COD during the final part of September. Brannen will cover that, though once again, it was constructed in record time, and it has had a tremendous effect on Puerto Rico's energy system, which makes us genuinely proud, and it's also a genuine anchor investment for us on the island and a foundation we can truly build upon for what we do there going forward. Finally, I'll hand things to Andrew Dete to discuss Brazil. We traveled down to Brazil together last week, and, well, two enormous achievements. Both terminals we operate there have reached mechanical completion. Each one has an FSRU that should be situated within roughly the next 30 to 45 days. Brazil represents an enormous, enormous opportunity for us, a gigantic market. Considerable commercial activity will emerge from all of this, but finishing everything and having it truly represent the payoff of many years of dedicated effort on our part across the FLNG, Puerto Rican, and Brazilian markets. In many ways, we now possess perhaps the two finest markets anywhere in the world for our business, both completely operational and producing cash flow. The quarter's second highlight is that we completely funded our balance sheet through the Terminal B that closed a few weeks back. That lets us now concentrate on the task in front of us, which is running our business. We anticipate having a very direct path now toward deleveraging the balance sheet, using operating cash flows along with asset sales as we progress toward an investment-grade rating, which we intend to reach over the coming 12 to 24 months. And finally, obviously, the reason we're here is to discuss earnings. Our core operating earnings hit a record. Chris is going to get into the specifics, but essentially, the way our business has been transformed — with cash flows now coming almost completely from our customers — that's a big deal for us. In Q1, core operating earnings were $15 million. Q2 brought $49 million in operating earnings. Q3 delivered $195 million in operating earnings. For Q4, we're expecting double or more what we saw in Q3, and Q1 should come in better than Q4. So we've covered a lot of ground toward generating stronger, high-quality cash flows, 100% downstream, and that sets us up really well as we head into the back half of the year. Take a quick look at page 4 — the quarterly financial results. Quality, duration, and growth are the three pillars of our earnings. Like I mentioned earlier, 100% of our earnings come from downstream customers — $208 million of adjusted EBITDA for the quarter. We're in the final stretch of the year now. Our outlook hasn't changed: $1.6 billion in Adjusted EBITDA for this year, $2.4 billion for next year. Within that $1.6 billion, roughly $200 million is expected from gains on asset sales in Q4. So timing could create some volatility around those, but they're fairly straightforward. Importantly, out of the $2.4 billion we're projecting for next year, almost all of it is already under contract. Of our $2.4 billion estimate for next year, everything except about $250 million is already contracted. So cash flow quality is 100% from downstream customers. Our portfolio's duration exceeds 12 years. And on growth — right now we're only utilizing about 25% of our terminals' capacity, so there's enormous room for organic growth ahead. Page 5: despite how we've performed operationally, our company is significantly undervalued. By every metric we examine, we're the lowest valued in the business. We believe this will get resolved simply by delivering results and running the company. But on an earnings per share basis, our estimate for this year is $2.50-$3.00. For next year, $6.50-$7.00. So if you apply an earnings per share multiple to that, there's no cheaper company than us in the infrastructure space anywhere on Earth. Looking at enterprise value to EBITDA, which is a solid gauge of business leverage, not only are we the lowest value on multiple, we're by far the least leveraged among these different sectors. And finally, regarding the company's growth, our compounded growth rate for earnings per share from 2022 through 2024 was 55% annual growth rate. An extraordinary growth rate. Beyond the fact that the growth rate has been remarkable, we believe the potential for upcoming expansion is definitely present, given the capacity available at our terminals and the fairly low utilization. So given that, let's move quickly to the construction update. As you know, I touched on this briefly at the start. What I'm going to do is hand it over to several team members to discuss it, but we have a number of extremely significant updates. The key takeaway is that the great majority of our construction work is now finished, so, but let's just walk through it. I'll ask Chris to begin with the FLNG project down in Mexico.
Christopher Guinta
executiveYes. Thank you, Wes. Morning, everyone. What has been achieved on FLNG 1 is truly extraordinary. Our FLNG work got underway from nothing on March 9, 2021, and 31 months later, we are pleased to report that gas has entered the system, and we anticipate wrapping up commissioning before this year ends. A normal LNG development generally requires 5 to 7 years on average, yet because of our amazing staff, contractors, equipment suppliers, and regulators, we are close to finishing one of the most sophisticated offshore LNG plants anywhere in the world. Let me briefly go over what has taken place and lay out what comes next. During the past 60 days, the 2 remaining rigs were relocated from where they were built in Corpus Christi to their lasting location in Altamira. Each of the three rigs has been raised into place, joined together, and linked to the subsea pipeline; on Monday, we turned the subsea pipeline's valve and sent the initial gas molecules into our system. The nat gas subsequently travels from the hot tap assembly, up through the riser, onto our rig, and into our high-pressure letdown valve. Between now and COD, the plan will be to send gas to the turbines and finish commissioning the power generation system, after which natural gas will go to our pretreatment module. Gas passes through the mixed refrigerant compressor and then the cold box, where LNG will be generated. After LNG is generated, it will travel to our floating storage unit, the NFE Penguin, which should reach the site in roughly 10 days. Our team has performed brilliantly at finishing the many construction work streams, commissioning key equipment in a careful and safe manner, and we anticipate the first drops of LNG within the coming weeks. Andrew?
Andrew Dete
executiveAppreciate that, Chris. Now shifting over to Brazil and what we're doing downstream there — Brazil's been a topic of discussion for us for some time, and we're really looking forward to the fact that on our upcoming call, we'll be able to report that both of the terminals in Brazil are up and running. Starting on page nine with Barcarena: that facility has been mechanically complete now for several months, and we also have our FSRU, the Energos Celsius, which has been going through conversion work at the Seatrium yard located in Singapore. Under contract, mechanical completion on that vessel wraps up at the end of November, after which it heads to Brazil, meaning the terminal enters operations right at the very end of 2023. Keep in mind that at Barcarena we already hold some long-term contracts; with Norsk Hydro, for instance, we have a 30 TBtu, 15-year contract that kicks in once the vessel shows up and begins sending gas in early January 2024. Beyond that, we hold a 25-year PPA tied to our 630-megawatt power plant. Yesterday we were pleased to announce that financing has closed with the Brazilian Development Bank to fully fund CapEx on that power plant — so 100% financed. And then that power plant is set to begin operations in Q3 2025. Right now it sits at roughly 37% complete under a fixed-price, fixed-date EPC contract with Mitsubishi and Toyo Setal. We also hold permits for over 1,000 megawatts of additional new power plants next to the terminal, and we're eager to get this terminal online to transform a region at the mouth of the Amazon, which currently has no gas and depends entirely on oil-based fuels, as well as to keep announcing new commercial activity at the terminal. Moving to page 10, we turn to Santa Catarina, which is located all the way down in southern Brazil. We've managed to make excellent progress there, and on Monday we announced the charter of the Energos Winter, which lets us bring the terminal online in January of 2024. We'll subcharter that vessel from Petrobras for 2024, and then at the end of the year we'll begin our long-term charter directly with Energos for that same vessel. That vessel will remain in Santa Catarina over the long term. On the right side, we're able to show our physical progress here. Going clockwise from the offshore terminal, we have the connection to the pipeline, then our 32-kilometer pipeline route, and then our city gate and gas conditioning station, where our pipeline ties into the region's pipeline system. This terminal is extremely exciting for us, since it marks the first time we're genuinely connected into a full transport pipeline system, which hands us a really diverse set of opportunities. In this region, we have baseload supply for existing gas customers, both industrial and local distribution companies; we can deliver firm gas supply to power plants that lack firm gas supply today. Roughly 2,000 megawatts of power generation already exists in the region without a secured gas supply. We're able to collaborate with greenfield power developers, and in that area there are approximately 1,000 megawatts of permitted plants. ... Owning power plants is another option for us. Brazil has a capacity market that is extremely well-regulated and well-run, and it can grant long-term contracts both for power capacity and for energy. Beyond that, we can offer balancing and additional services to the pipeline system. So the set of opportunities before us is enormously varied. We have a terminal — and in both instances, for Barcarena and Santa Catarina, that's genuinely a 5- or 6-year undertaking, you know, starting with permitting, moving through construction, all the way to where we stand today. So we're thrilled to hold ownership of two of Brazil's LNG terminals and to bring them online at the end of the year, and we look forward to sharing more about our commercial activity on our next call. Brannen, over to you.
Brannen McElmurray
executiveYes. Thanks, Andrew. For NFE, Brazil is genuinely an extraordinary market. Turning to slide 11, here's an update on what we're doing in Puerto Rico. To give a little background, roughly 3.2 million people live in Puerto Rico, and don't forget that around 5 million individuals of Puerto Rican heritage reside on the U.S. mainland. It's an amazing culture, deeply connected to American history, and it receives tremendous attention from us, from the federal government, and from many others. Sadly, Puerto Rico holds the questionable distinction of having the priciest electricity across the U.S., along with the least dependable power supply. A typical customer on the island faces a likelihood of losing power that is 500 times greater than that of a customer on the mainland. Following 2 catastrophic hurricanes, an earthquake, and additional challenges they've faced across the last 5 years, the federal government chose to commit a $22 billion investment toward rebuilding Puerto Rico's energy infrastructure system. After Hurricane Fiona hit in October 2022, a power system task force was created in Puerto Rico to stabilize the grid, involving agencies like DOE, FEMA, EPA, and several others. Earlier this year, NFE answered a request from FEMA and the Army Corps to bring 150 megawatts of power to Palo Seco and 200 megawatts to San Juan. We're extremely proud to share that both projects are finished, both running as base load, each operating more than 97% of the time, 2 times more dependable than PREPA's current system, and 25% more dependable than the private operators active in that market. The Army Corps has never completed a large-scale power project this quickly, which really means something considering their track record. Our power, 350 megawatts in operation but roughly 425 megawatts installed, accounts for over 10% of the installed power in Puerto Rico as of today; and after reviewing the stats this morning, we're delivering about 15% of the power flowing onto the grid at this very moment. So what does that mean for an ordinary Puerto Rican citizen? The power we're discussing, that 350 megawatts, is the least expensive power available on the island. It's the most dependable. It serves roughly 550 households, and most importantly, it has prevented approximately $600 million in economic losses from load shed events, which happen often in this market. We anticipate this power becoming a permanent piece of Puerto Rico's infrastructure. We view it as megawatts today, and later it will enable renewable energy integration. Thanks to how we performed, we were recently chosen as part of two groups that will take part in a $5 billion program started by the U.S. Army Corps of Engineers to address future events on the island. Like Wes mentioned when the call got started, this stands as a fantastic illustration of what NFE is trying to accomplish — supplying money, know-how, and forward-looking strategy to those areas so people there can count on steady electricity, enjoy better lives, and see stronger financial results. That purpose dovetails with what Genera is after; Genera being the platform we rolled out not long ago that functions as a private company running the PREPA generating fleet. Over on Genera's side, we've got 500 megawatts worth of battery initiatives underway right now, plus more than 1 gigawatt in dispatchable generation upgrades, all done for PREPA, carrying forward the work of modernizing the grid. Having said that, I'll hand things to Chris for an update on La Paz.
Christopher Guinta
executiveOkay, thanks a lot, Brannen. Let me give you a brief update on the La Paz power plant. It sits at our terminal in Baja California Sur, also known as BCS, and it uses our patented ISO Flex logistics approach to transport LNG in cylinders from the big offshore storage vessel over to the terminal, where the fuel is offloaded and then delivered to CFE-owned power plants, which is what we've been doing for 12 months now. Lately, we began carrying out regas operations and generating power at the plant we own, which we built starting in 2021. During Q3, we ran the 240-hour reliability tests on all 3 turbines and successfully finished the grid compatibility assurance steps that were needed to bring the asset into service in Q3. The photo on the right-hand side of this page displays our power plant, made up of 3 LM-6000 turbines, able to deliver as much as a maximum of 135 megawatts to the Baja power market. As we've noted previously, there's an agreement in place to sell the plant to the CFE in 2024, though NFE, NFE will keep owning the terminal and keep supplying gas to the plant until that sale is finalized. Until then, NFE keeps the cash flows tied to producing power and selling it into the local market. As a side note, NFE keeps the cash flows tied to producing power and selling it into the local market. Turn to slide 13, which covers the Nicaragua power plant. What's great about the Nicaragua development is that NFE has handled every single part of this project in one way or another. The power plant is built, it's on-site, it's waiting for gas. Right now we're working through permitting and early construction activities for an offshore FSRU terminal. This is going to resemble the terminal design we employed in Santa Catarina. After that, we'll bring the gas from offshore to onshore via a directional drill, and then we already hold existing rights of way to run the pipe from the shore out to the power plant. The FSRU is in the shipyard at present and will reach the site in Q2 of 2024, and the pipeline will be finished across the next 4 months. This contract is our This terminal is backed by a 25-year PPA with a local utility and is expected to come online in late Q2 2024. Please turn to slide number 15. What slide 15 shows you is the numerical version of what Wes has been talking about for months. That is, the company is close to wrapping up our roughly $7 billion of capital spend across the last 8 years. We've put money into critical infrastructure in key markets that are set for greater power development and fuel switching in the near term. On top of that, we took a proactive approach with money spent on essential equipment and building liquefaction plants, which will let us grow terminal volumes even with today's market—there's simply no near-term supply available for long-term offtake. This page lays out what's left to spend on FLNG 1 and 2: roughly $400 million between now and the close of 2024. On top of that, there's an additional $150 million of CapEx tied to finishing the terminals and converting ships. Once you net that against the money from the just-completed Terminal B deal plus the contractual reimbursements from Energos for vessel conversions, what remains is a capital plan that's fully funded, along with surplus cash. And if you factor in the more than $2.5 billion of free cash flow generated by operations and asset divestitures across the coming four—pardon me, five—quarters, the deleveraging turning point we predicted becomes clear. Thanks to these resources, we can pay off our revolver entirely and redeem the 2025 bonds, which brings our leverage ratio to under 2x. At this point, kindly go to slide 17, and I'll walk you through how we performed financially in Q3 of 2023. I have to say, I've rarely been this eager to share our results, since, as we've repeatedly told you, this quarter represented genuine, unadulterated cash flow generated by our core operations. There were no cargo sales, nothing cancelled, and no distortions from selling assets or writing things down. Segment revenue totaled $514 million, while operating margin came to $250 million overall. Downstream operating margin—that is, the volumes sold via our terminals to customers—reached $195 million. As Wes hinted, that's an incredible 4 times the Q2 figure and 13 times the Q1 figure; and indeed, we anticipate it will almost double again in this year's Q4. The ship segment delivered another $50 million of operating margin in each of the last 2 quarters, and that's roughly what should be expected from now through the close of 2024. Net income for the quarter came in at $62 million, equal to $0.30 per share on a diluted basis, and per Wes, our full-year projection falls between $250 million and $350 million. Kindly move to slide 18. Our discussions with the rating agencies remain productive—they've been extremely supportive as we work toward additional upgrades and, ultimately, an Investment Grade rating. As Wes noted earlier, reaching that target brings plenty of advantages, among them: one, entry to LNG offtake and trading markets that today are open only to Investment Grade participants. Two, lower borrowing expenses. And three, more financial flexibility through covenants and market access. At present our corporate ratings stand at BB-, BB-, B1 from S&P, Fitch, and Moody's, in that order. In a report published recently, Moody's gave a positive outlook to the corporate family rating; for our recent Terminal B issuance, we were notched up above the corporate level to BB at S&P and Ba3 at Moody's. In those reports, the rating agencies mention possibilities for upgrades in the near term as we keep carrying out our business strategy; they highlight four essential themes: a stabilized CapEx profile, consistency and visibility in earnings, how well operations perform, and the shift into generating free cash flow, which results in ongoing deleveraging. If you look at the 5 boxes shown on this page, you'll see that our main highlights are net debt below $3 billion and target leverage under 2 by the close of 2024. Greater diversity of assets, together with the duration of our downstream contracts, and steady earnings growth. In the fourth box, our business delivers a high conversion of free cash flow, which is anticipated to exceed 60% in the coming year, something we'll discuss on the following page. In the final box, the commissioning of essential infrastructure such as FLNG, the power assets located in Puerto Rico, and the terminals in Brazil. Lastly, please turn to slide 19, where we have a walk of Adjusted EBITDA down to net income covering 2022 through 2024. Let's remain on the Adjusted EBITDA line for a moment. Looking at 2024, it's worth noting that more than 85% of these cash flows are projected to originate from volumes sold to our downstream customers via our terminals. In 2024, nearly 90% of the vol — of these volumes are already under contract, which means we have more than $2.1 billion of EBITDA, basically in backlog; now, go further down the page, and net income for 2022 came to $185 million; for 2023, it's anticipated to be roughly $600 million and roughly $1.4 billion for 2024. After that we added back non-cash depreciation and amortization to arrive at the figures you see highlighted in the black row, which we call free cash flow before CapEx. $328 million in 2022, an estimated $775 million for this year, and an estimated $1.65 billion for next year. What stands out most on this slide is how sharply CapEx drops from 2023 to 2024. In the coming year, with just $400 million of growth CapEx and about $40 million of maintenance CapEx, we're projecting more than $1.2 billion of cash flow available for delevering. The conversion of income into free cash flow is remarkably high as we look at 2024 and beyond, and that will let us pay down debt, reinvest into new projects, or return capital to shareholders; with that, I'll hand the call back to Chance for Q&A. Sorry.
Wes Edens
executiveSo what I want to do is just pause for a second and let Ken Nicholson walk us through where things stand with our hydrogen business. The hydrogen team is right here in this room alongside us. Quite a bit is happening on that front; we've included a few slides in the appendix, but Ken, if you wouldn't mind giving us a quick update, that would be terrific.
Ken Nicholson
executiveOkay, thanks, Wes. This is Ken speaking, everyone. If you look at slides 21 and 22 in the supplement, there's a bit of an update on where things stand with Zero Parks. In Q3, I'd say we kept building a lot of momentum in this business. We're making good progress toward creating and standing up a company that we anticipate will be the largest in North America in what we do, and, far and away, the most profitable. This business will generate Green Hydrogen and hydrogen logistics terminals for customers across the energy, industrial, and transportation sectors, assisting them in decarbonizing all of their operations. The terminals we're building are primarily focused on serving regional needs in North America. But they all sit on waterfront property too, so there's potential to grow into export markets, and international demand is massive. We've basically mapped out the business plan to construct these with significant expansion in mind. Moving to slide 21, a quick update on Zero Park 1, our first location in Beaumont, Texas. This site was initially planned and engineered for 100 megawatts of capacity, which works out to as much as 50 tons per day of hydrogen output. We're now expanding the project's scope to 200 megawatts, equal to 110 tons per day of hydrogen. And this quarter, we secured a 100% off-take agreement with OCI. We really respect OCI and everything they're accomplishing. Right now, they operate a sizable facility for petrochemicals, ammonia, and methanol in Beaumont, and our role will be to provide them green hydrogen as they start making blue and green methanol and ammonia products. That agreement is set for the long haul, and at present it accounts for every bit of capacity we have available. We can still grow our operations in Beaumont, so we're eager to keep moving forward on that front. On the technology side, we're fully ready — we've been collaborating with the team at Electric Hydrogen, so the PEM technology is completely in place, and building work has begun. We expect to have that facility up and running by the end of next year, and it should be at full capacity when 2025 begins. Turning to slide 22, the larger strategy here involves expanding on our Beaumont operations. Aside from that location, we currently run two additional sites, and quite recently we began adding a fourth, which isn't shown on this slide. One of them sits in the Pacific Northwest, and progress there is moving quickly. The site is essentially locked in, and it's an excellent one. In a similar way, we've nailed down a site in the Northeast. There's also a fourth facility, located on the Gulf Coast as well, that strikes us as quite promising, and talks to finalize that location are at an advanced stage. To reiterate what I mentioned, ZeroPark 1 has reached FID in full, and building work is now proceeding. Regarding the remaining two or three projects, our expectation is that within roughly half a year, everything will be finalized and construction will begin. Let's say the sole achievement we ever make is erecting three parks — located in the Pacific Northwest, the Northeast, and Beaumont. In that scenario, this company would still generate $150 million of EBITDA annually. Debt is the primary means by which these facilities get financed. When it comes to Zero Parks, the current debt facility features an exceptionally low cost along with a very lengthy term. Our borrowing rate, as a matter of fact, sits below 5%. That just makes a project that already turns a profit even more profitable, and it adds more accretion on a cash flow basis. So as we go about growing this company, we're eager to keep giving investors updates. My sense is that we're going to witness considerable growth ahead.
Chance Pipitone
executiveThanks, Ken. If possible, I'll hand things back over to the operator. I want to open the lines so anyone can ask questions.
Chris Robertson
analystMorning, everyone, and thanks for letting me ask. I'd like to focus on what we should expect for EBITDA in Q4 as this inflection point arrives. Could you shed some light or assist us in bridging that gap? Should we anticipate any impact from non-contracted downstream assets within that figure — open or spot cargoes, or anything that isn't, as you put it, quote, unquote, "clean," Chris?
Ken Nicholson
executiveSure — the brief response is that there's a single cargo we anticipate selling during Q4. Beyond that, all remaining earnings flow via contracts to downstream customers, through our infrastructure.
Chris Robertson
analystAll right, understood. Yeah, that helps. Now, regarding the most recent asset-level financing for the Barcarena Power project, could you elaborate a little on the terms and structure of that financing? Can that be tapped progressively as the project moves forward? Or is it more of a single lump sum you would take down in the near term? And, I suppose on that same point, will any part of it be used to pay off the Barcarena term loan that comes due in February, or is that handled separately?
Ken Nicholson
executiveYeah. So hey, this is Andrew. So, the short response is yes. When we do, with our initial draw, we will completely repay the term loan that exists, and after that we can draw gradually as we proceed, as we finish construction financing. So, you know, comparable perhaps to a term loan A you might encounter in the U.S. or a mini-perm financing. But, this is clearly with the Brazilian Development Bank, and it also carries a very long tenor; so, the financing has a 20-year tenor, and at a very favorable rate. So I think overall, we are under 8% on that portion of debt.
Chris Robertson
analystAll right, understood. Yeah. My final question concerns the capital expenditures spent in Q3, plus roughly what the guidance looks like for the rest of 2024. So it seems like a portion of that CapEx might have been accelerated into this period. I'm just hoping to get some clarity — you know, it was fairly significant in Q3. Is that largely tied to money spent on building FLNG 2 and finishing FLNG 1, or what exactly caused that unevenness?
Christopher Guinta
executiveYeah, it's primarily the work taking place on FLNG 1. Some procurement efforts tied to FLNG 2 happened in Q3. There was also CapEx connected to the upcoming installation of the turbines for the San Juan Power Plant; so yeah, Q3 came in a bit uneven. More specifics will come out when we release the Q later today or first thing tomorrow morning. And I'm glad to walk through them with you, Chris.
Chris Robertson
analystOkay. That sounds excellent. I'll hand things over. Appreciate it.
Ben Nolan
analystYes, thank you. I was wondering whether you could provide a bit of detail regarding where things stand with the FLNG unit as it relates to the DOE. Is production of LNG now fully permitted for you? And beyond that, what are your thoughts on where the second FLNG unit would be deployed, or anything else you could share on that front would be useful, thanks.
Christopher Guinta
executiveYes. The brief response is that the matter the DOE brought up last week has been settled and published on our website; in our view it was simply a terminology matter, and they concurred with our position. So for us, Ben, it's no longer an issue. Regarding FLNG 2, our plan is to place units onshore at Altamira, and the interactions and feedback from the Mexicans have been favorable. Keep in mind, this is. Many of these units are being constructed by us. You have the option of multiple units offshore, and multiple units onshore as well. So the DOE's reaction was triggered by naming one at a particular site; and all we're saying is that our units are capable of going in either spot. Whichever one we choose, we can decide to place them there.
Ben Nolan
analystAll right. Thank you. That context is helpful. My follow-up was going to be about the $1 billion in asset divestitures. Clearly, the Baja power plant is one of them, but perhaps you can offer whatever specifics you're able. And also, I suppose, since the company is now producing considerably more free cash flow with much lower CapEx, maybe walk us through what's motivating these asset sales rather than simply keeping them and the cash flows tied to them.
Wes Edens
executiveAbsolutely, Ben, I'll give it a shot. Good to hear from you. We hold roughly $1.5 billion altogether in assets we classify as non-core that sit on the balance sheet; these are items that mattered more to us at various moments; a quick illustration would be the liquefier we constructed in Miami around seven or eight years back. It played a central role in building out the business and served as genuine validation, a milestone for us. These days that facility puts out roughly 100,000 gallons per day, so it isn't truly a significant piece of the company's total supply. That one would fall into this bucket. Yet by and large, the assets we're discussing divesting contribute minimal free cash flow and minimal EBITDA. So really they're just solid core assets; they fit better in someone else's portfolio, and I believe it genuinely tidies up our balance sheet and delivers plenty of additional cash flow to us. Honestly, my roster of non-core divestitures numbers four or five altogether. Each one is essentially its own separate, standalone transaction, and I believe and anticipate those will in fact reach completion within roughly the next six months, by and large. So, as Chris laid out, and when you examine the company's cash flow profile, now that our CapEx spending has dropped considerably and our earnings production has climbed considerably, that combined with the cash flow these divestitures generate will go a long way toward reducing the company's leverage and thereby move us along the road toward our objective of reaching Investment Grade. So it's something we'll give updates on each quarter as things progress, but I'd anticipate a handful of transactions across the coming six months or so. Nothing we're divesting is something where we feel we're giving up either EBITDA or cash flow. So all of these are excellent assets, but at this stage in the company's life, they aren't material to what lies ahead for us. So hopefully that's clear.
Ben Nolan
analystSure. I appreciate it. Thanks, Wes.
Wes Edens
executiveYou bet.
Sam Margolin
analystHello there, and good morning to all of you. I appreciate you taking my question. To start off, I'd like to ask about how growth looks downstream, and I want to point to a particular slide from the term loan deck, since that presentation included an illustrative build-up of margin calculated per MMBtu.
Wes Edens
executiveYes.
Sam Margolin
analystYou brought up markets where diesel is being replaced, and there's a fuel-switching element, so your margins there are much better than that. I wanted to ask if you could discuss a bit the chance that exists in those fuel-switching markets, where embedded margins are higher compared with the example shown in that deck. Thank you.
Wes Edens
executiveYeah. One of the business's core fundamentals is precisely what you just described — entering markets where diesel is the dominant fuel and converting them to natural gas is a certainty. Take Jamaica, for instance: when we look at the effect of moving from diesel to natural gas at the plant we converted first in 2016, the cumulative savings for Jamaica to date exceed $2 billion. So for them it's an enormously favorable savings, and it still produces sufficient margins for us. At today's oil price level, and therefore the diesel price level that results from it, in a lot of these markets the price is roughly mid-20s; meanwhile natural gas prices — Henry Hub is currently about $3.5. So clearly there's an enormous gap from the low end to the high end between those two, and that is what truly shapes how these markets behave. When I said before that I believed Puerto Rico and Brazil could literally be the two best markets for us anywhere on Earth, given what we do in terms of both converting fuel from diesel to natural gas and constructing new, more efficient power, there's no doubt these are the two most compelling markets for us precisely because of this phenomenon. In the Puerto Rico portfolio we currently manage, there's roughly 1,000 megawatts of power today that burns diesel rather than natural gas. Clearly that represents an enormous savings opportunity for Puerto Rican ratepayers if they switch to natural gas. And for us, it's a very, very steady source of new incremental volumes as we like to transfer going forward. So that's essentially the company's path. As I said, moving from $15 million in operating earnings in the first quarter to $195 million, and then doubling or more as we go forward, is simply an enormous, enormous change in the business, and it's entirely driven by these longer duration, customer downstream volumes. So it's a huge, huge moment in time for us, and now you can really begin to see it through the financials; then the Q4 financials, the Q1 financials, you'll see the full impact in a number of these markets, both in particular in Puerto Rico and Brazil, and we expect the growth to continue indefinitely. So it's a great point in time for us.
Sam Margolin
analystAll right, I appreciate that. Thank you. For the follow-up, maybe this is just a clarification for Chris, or anyone else who wants to take it. You said FLNG-2 is kind of a naming convention, and since these are modular assets, capacity varies depending on which reference materials you look at. Could you clarify what the total capacity would be at FLNG-2 as described in the deck? And could you also share what total invested capital in the FLNG group would be at the point FLNG-2 is completed? Thank you.
Christopher Guinta
executiveYeah. First, each train is 1.4 tons. We've talked about multiple trains that we're building. At this point, our focus is only on the first one, which is being deployed in Altamira offshore, and we're assessing where additional units will go. As we've said before, we're permitting sites in Mexico offshore, which is the one permitted now. That's for two trains; we're seeking permits for up to two trains at the onshore location, and we're also permitting two trains at the Louisiana location. So our invested capital isn't something I can point to just one of those locations. I'd say across module construction, and then specifically for the rigs, which are FLNG 1's deployment solution, total invested capital is about $2.5 billion, and we've disclosed that. So we believe that gives you everything you need to think about total paid-in capital for each of these units; we haven't broken it out by two, three, four, and five in progress payments. It's enough to say critical equipment has been procured, and we can maintain schedule to put multiple units in place, both offshore and onshore.
Sam Margolin
analystAll right, that makes sense. I really appreciate it.
Craig Shere
analystMorning. Thanks for fielding these questions. So to start, Wes, a few times during this call you mentioned how thrilling Puerto Rico and Brazil are. At this point you've got 5 markets that are completely finalized, which includes those along with Mexico, Jamaica, and Nicaragua. Since the entire system, once it's operating, sits at roughly 20% capacity utilization, what I want to know is: do you think there's any requirement to originate additional downstream projects in other parts of the world, or can these markets support significant yearly expansion for many years ahead?
Wes Edens
executiveTo answer that briefly, Craig, it's great to hear you on the call. In these sorts of core markets, the capacity we possess is far larger than what we're currently producing, so we've got years of organic expansion ahead in every one of them. Take Brazil — Andrew likely knows this better than me — but it's a nation about the same size as the US, with roughly equivalent population. Yet they consume only about 5% as much natural gas, correct? So being able to reach these markets today through these terminals is truly remarkable. As I recall, Brazil has six natural gas terminals. Two aren't linked to a pipeline. Of the other four, Petrobras owns a pair, and we own the remaining pair. That gives us a dominant position there. Same situation in Puerto Rico, where it's even more pronounced. Clearly, the world still has an enormous need for power that's cleaner and cheaper; and I believe the whole energy transition topic is certainly significant, but with 600 million Africans lacking power, and average energy usage in East Africa sitting at 3% of America's, there's a huge gap between what people require and what they can currently get. Naturally, certain markets will eventually become worthwhile for us. Looking ahead from 2024 into 2025, I expect no substantial additional terminals beyond those we've already pinpointed. That means completing the Nicaragua terminal. There's been plenty of publicity around the filings concerning the terminal we've proposed for Ireland. Ireland stands alone in the EU as the only nation without supply security. Honestly, I consider it insanity given what's at stake for that economy, that there wouldn't be an additional supply source; so they issued a ruling we didn't agree with, and we just submitted an appeal — I believe that was a couple of days ago, Cam — and we anticipate it'll be heard in due course. That market would make great sense for us on numerous levels, and even more crucially, it would make great sense for the Irish people. So we're strongly in favor of it. But the brief answer is that with the terminals and markets we can currently reach, we see an enormous amount of additional growth stretching many years ahead, just by delivering on it. And that's truly where the company's attention lies.
Craig Shere
analystAppreciate it. So, on to my next item: the chance to roll out FLNG and Fast LNG into stranded gas fields has always struck me as really compelling. Could you walk through what held things up during the Pemex talks over Lakach, and what possibilities remain open for stranded gas prospects globally in the years ahead?
Wes Edens
executiveSo, just to give a bit of background. We had a 50% stake in the Healy vessel, which the Golar team built, and it's operating off Africa's coast. That shows how a stranded gas field can be put into production — in this case, making LNG right now. Their next project, I believe, kicked off in 2017, possibly reached FID in 2019, and should be brought online during the second half of 2024. When you compare that with what we've done, the difference is pretty dramatic. We reached FID in March 2021, and our unit is already out there with gas running through it. It's wrapping up and being commissioned ahead of the close of 2023. So Fast LNG really is an accurate name. It stands as the quickest delivery of a facility of this kind anywhere, and given global energy demand, we believe these offshore stranded gas fields will require plenty of work along the lines of what we just brought into service. As things stand for us today, adding more capacity step by step isn't what we intend to do. Between the facility we now have in the Gulf of Mexico and the onshore project we've proposed — a distinct development, as we've often noted — we consider that sufficient for our requirements. Still, I'm certain there's substantial demand and a real role for the technology and skills our company possesses, and perhaps we'll wind up providing that for others and so forth. Yet when it comes to putting capital to work and CapEx spending, our attention is squarely on FLNG 1 and FLNG 2 right now, with nothing else planned. That said, I believe the wider point behind your question is whether this can be applied to those stranded gas fields offshore. The response is an emphatic yes, without a doubt. I expect you'll witness considerable growth in this area, and I suspect the methods we employed in building our own liquefier will be copied by others, maybe, and we'll see them appear in various regions around the globe; so...
Craig Shere
analystThanks.
Ryan Levine
analystMorning. I'd like to pick up where we left off regarding the FLNG permitting matter. Could you explain the purpose of the onshore DOE application, given that it isn't intended for FLNG one or two?
Wes Edens
executiveSure, this is genuinely quite straightforward. Allow me to clear it up, since I believe this amounts to nothing more than a source of misunderstanding. We sought DOE permits for our offshore facility and were granted them. As it happens, that facility sits 12 miles off the coast of Altamira, correct? That's all there is to it; and we got the FTA permits. Our non-FTA applications are in progress. We've also applied under the Jones Act. In fact, we've been in discussions with, you know, the different government agencies regarding all of these matters, and that is very much proceeding on schedule. On a separate note, we are looking into the possibility of placing the units onshore at a location that is likewise named Altamira, and that, I believe, is where things get murky. My take on it is that the name and the terminology were simply close enough that I think the department came back with, "Hey, look, if you intend to force your onshore development into your offshore permits, that isn't really how it works; it needs to be permitted on its own." Our response was: Naturally, that isn't what we're trying to do, and if we move forward with the onshore facility, we will submit a distinct application for it, as is mandated and as is fitting, once that becomes required. So, we made that filing publicly. They issued a public reply stating, "Great, thank you for that," and that concludes the matter. There were, you know, a few misleading reports, frankly, that got circulated, you know, within, in the investor community, claiming, "Oh, my gosh, this now calls into doubt whether we hold the permits or such." Nothing could be less accurate, and it was genuinely misleading. I was displeased about that, to be honest. But as far as we're concerned, it was merely a misconstrued, you know, inquiry from the DOE that we answered, they answered, and that concludes the matter; so from that perspective it's really quite simple.
Ryan Levine
analystGreat, thanks for that clarification. Now, switching to another subject — could you assist in connecting the third quarter EBITDA and CapEx with your full-year guidance, specifically regarding what the implied ramp looks like for the fourth quarter?
Wes Edens
executiveYeah. So, as you know, for the year, EBITDA is projected to reach $1.6 billion. As Wes mentioned, that figure does encompass a little under $200 million in gains from asset sales that we anticipate closing before the year ends. But what remains is roughly $1.4 billion, rounded, and our view is that the fourth quarter accounts for the rest.
Ryan Levine
analyst... Are there any significant factors in that, or anything notable breaking out, any amount we should expect FLNG to add, given what you've laid out?
Wes Edens
executiveZero, Ryan. The sole factor at play is a complete quarter's worth of operation from the new San Juan power plant.
Ryan Levine
analystAlright, that's great. I appreciate you letting me ask.
Wes Edens
executiveThanks, man.
Chris Robertson
analystHi there, apologies, everyone. There was one final item I wanted to ask about, building on what came before. Wes, you brought up the fact that we were picked for the multiple award task order contract, along with that $5 billion pool in Puerto Rico. Chris, I believe you may have said we were chosen as part of two groups in that process. Could you unpack that somewhat, or make clearer what exactly falls under it when it comes to the kinds of projects that pool targets?
Wes Edens
executiveOf course. Brannen, would you like to take that?
Brannen McElmurray
executiveSure, absolutely. Yeah, I appreciate the question; Brannen here. So to be specific, the Army Corps, as you correctly mention, rolled out a fresh program, and that's $5 billion in anticipated investment for Puerto Rico's infrastructure across the next, let's call it, 3 to 4 years; we, which is NFE, went up against two groups for that. NFE was chosen alongside two groups, so the way things will, you know, unfold going forward is after the Army Corps settles on sort of a portfolio of projects, which clearly they plan to fund, and that might be power generation or other, you know, comparable infrastructure builds, at that point, you know, our involvement would happen; it's quite like the two projects we secured in Palo Seco and San Juan, so we'd anticipate, you know, something comparable down the road; so I suppose the brief answer is, you know, the Army Corps program comes to $5 billion; they've made it public. You know, they'll define that over the next several months, and after that we will take part and compete. And, you know, up to now, we're 2 to 0, so I'm feeling pretty good about that.
Chris Robertson
analystAll right, so just to be clear, might that take in more power generation assets further downstream, rather than merely selling gas into the market?
Brannen McElmurray
executiveThat's right. I'd say, you know, one way you could look at it is that it's much like the 2 projects we've already finished — those being 350 MW — except they could simply sit in other places.
Chris Robertson
analystAll right, that's really useful. Thanks a lot.
Brannen McElmurray
executiveHappy to help.
Wes Edens
executiveOkay, I suppose this is just the closing part, since I believe we've finished taking questions. Over the 9 years that have passed since this company was founded, we've invested $7.5 billion to build out infrastructure, we now have 7 terminals standing, and 6 of those are running, with leading positions in Brazil as well as Puerto Rico. The business today operates at a genuinely enormous scale. Revenue for this year is projected at approximately $2.5 billion. For the following year, we anticipate that figure will roughly double, meaning $2.5 billion climbing to somewhere near $5 billion. Somewhere in the range of 40%-45% of that probably converts into free cash flow, and we are valued at the smallest multiple of any infrastructure company I know of anywhere on the planet. So I guess it's nice to be number one at something; still, when it comes to that sort of valuation, clearly it disappoints me, though I anticipate it will shift considerably once we truly deliver these results in Q4 and Q1 and beyond. So I believe we'll attract the investors we merit, and we'll receive the valuation we merit. And those among you who hold investments in it right now, I believe you'll be rewarded very handsomely. But truly, it has been an outstanding year for us so far. I think it positions us exceptionally well for both the year's end and for the coming year, given all the major transformations, not just in Puerto Rico, but also in Brazil and other markets around the world. Something we don't discuss much is what we've accomplished in the hydrogen business; we believe that operation is the leading green-side hydrogen business in the United States. As far as I know, it could very well be the sole profitable, substantially profitable hydrogen business to emerge from the IRA as things stand. The business plan that Ken and the others devised is one I strongly back, and essentially it means transforming the hydrogen business into production that takes place at the location where it gets consumed; so you begin by solving a chemistry issue, and the transportation issue resolves itself since you're actually using it right at the spot where you're producing it. So this is a tremendously exciting period for the company, and we feel wonderful about the quarter that just ended and the prospects ahead. I also want to thank everybody for spending the time to listen, and we look forward to bringing you our full year results in Q4 at some point early next year. Thank you.
Wes Edens
executiveAbsolutely. Melinda, thanks, and thanks to all of you for being here today. Once again, we're around, just like we always are, if you have anything you'd like to ask. Feel free to reach out to the investor relations team, and thanks once more. Have a great rest of your day.
Operator
operatorThat brings an end to the call for today, and we appreciate everyone taking part. Feel free to hang up whenever you like.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete New Fortress Energy Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to New Fortress Energy Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in New Fortress Energy Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.