NextDecade Corporation ($NEXT)

Earnings Call Transcript · May 1, 2026

NasdaqCM US Energy Oil, Gas and Consumable Fuels Earnings Calls 52 min

Highlights from the call

In the first quarter of 2026, NextDecade Corporation reported strong progress on its Rio Grande LNG facility, with construction tracking ahead of schedule and within budget. Revenue and earnings figures were not disclosed, but management reaffirmed early volume and cash flow guidance, indicating a positive outlook for the upcoming LNG production. The company is actively managing debt and exploring equity financing options for Train 6, signaling a commitment to maximizing shareholder value amidst favorable market conditions influenced by geopolitical events.

Main topics

  • Construction Progress at Rio Grande LNG: NextDecade reported that construction at the Rio Grande LNG facility is 'safely, on budget and ahead of schedule,' with Trains 1 and 2 at 67.8% completion. Management expressed confidence in meeting production targets, stating, 'we're currently tracking ahead of the schedule reflected in our early volumes and cash flow guidance.'
  • Market Dynamics and LNG Demand: Management highlighted that the ongoing Iran conflict has tightened global LNG supply, stating, 'a significant amount of LNG supply has been pulled out of the market between now and 2030.' This has led to increased demand for U.S. LNG, with management noting, 'we expect buyers to increasingly value long-term contracts out of the U.S.'
  • Early Cargo Sales Strategy: NextDecade began marketing early LNG cargoes, achieving margins of over $3 per MMBtu on fixed liquefaction fees. They reported selling over 175 TBtu on a free on board basis, which 'reduced the Phase I early LNG production exposed to LNG market price fluctuations by 33%.'
  • Financial Management and Debt Strategy: The company is focused on managing debt at the project level, with over $9 billion in credit facility commitments. They plan to refinance portions of their project-level credit facilities, stating, 'we expect to refinance the full term loan balances before the commercial operation dates for Trains 3, 4 and 5.'
  • Guidance Reaffirmation: NextDecade reaffirmed its early volume and cash flow guidance, projecting total LNG production of approximately 3,800 TBtu from early cargoes starting in 2027. Management indicated that cash flow generated from early sales could reach approximately $2 billion under favorable market conditions.

Key metrics mentioned

  • Construction Completion (Train 1 and 2): 67.8% (vs prior updates indicating steady progress)
  • Early LNG Production Guidance: 3,800 TBtu (projected from early cargoes beginning in 2027)
  • Early Cargo Sales: 175 TBtu (sold on a free on board basis, reducing market exposure by 33%)
  • Projected Cash Flow from Early Sales: $2 billion (under a $5 per MMBtu margin scenario)
  • Credit Facility Commitments: $9 billion (for Phase 1 construction)
  • Completion Percentage (Train 3): 44.2% (indicating ongoing progress)

NextDecade's strong operational progress and favorable market dynamics position it well for future growth. The company's proactive management of debt and focus on maximizing shareholder value through strategic financing options are key positives. Investors should monitor the commissioning timeline for Train 1 and the development of Trains 6 through 8 as potential catalysts for future stock performance.

Earnings Call Speaker Segments

Operator

Operator
#1

Good morning, and welcome to the NextDecade Corporation First Quarter 2026 Investor Call and Webcast. [Operator Instructions] As a reminder, this conference is being recorded. And now I would like to turn the call over to Megan Light, NextDecade's Vice President of Investor Relations.

Megan Light

Executives
#2

Thank you, and good morning, everyone. Welcome to NextDecade's First Quarter 2026 Investor Update Call and Webcast. The slide presentation and access to the webcast for today's call are available on our website at www.next-decade.com. Today, I am joined by Matt Schatzman, NextDecade's Chairman and Chief Executive Officer; and Mike Mott, NextDecade's Interim Chief Financial Officer. Before we begin, I would like to remind listeners that discussion on this call, including answers to your questions, contain forward-looking statements within the meaning of U.S. federal securities laws. These statements have been based on assumptions and analysis made by next decade in light of current expectations, perceptions of historical trends, current conditions and projections about future events and trends. Although NextDecade believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that the expectations will [indiscernible] be correct. NextDecade's actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in NextDecade's periodic reports that are filed with and available from the Securities and Exchange Commission. In addition, discussion on this call includes references to certain non-GAAP financial measures such as adjusted EBITDA and distributable cash flow. A definition of an additional information regarding these measures can be found in the appendix to our presentation. And now I will turn the call over to Matt Schatzman, executes Chairman and Chief Executive Officer.

Matthew Schatzman

Executives
#3

Thank you, Megan, and good morning, everyone. Thank you for joining us today. First quarter was productive across the NextDecade organization. We're making solid progress on the key 2026 priorities that we introduced on our fourth quarter call. First, one of our highest priorities continues to be progressing construction at the Rio Grande LNG facility, safely, on budget and ahead of schedule. Safety is engraved in our culture and our work. And in the first quarter, we achieved a low total recordable incident rate or TRIR of less than 0.1. I'm proud of both our team and the Bechtel team for continuing to progress construction at a rapid pace while maintaining high safety standards. We also continue to be within budget across all 5 trains under construction. Train 1 early electric commissioning is underway. Phase 1 continues to track ahead of the guaranteed substantial completion dates for the EPC contracts, and we're making excellent early progress on trains 4 and 5 at the site. Based on our current progress, Phase 1 is tracking ahead of the schedule reflected in our early volume guidance, providing a buffer to achieve the numbers we have provided. Our second key priority for 2026 is continuing to prepare our organization for commissioning, first LNG and the transition to operations. We've been advancing hiring, system implementations and process development ahead of first LNG. We've been rapidly hiring and expanding our team, and we currently have over 400 employees with the majority based in Brownsville. As part of our enterprise readiness efforts, we've made significant progress building the digital and operational foundation required for first LNG. Core enterprise platforms are starting to go live, and we've created a robust in-house integration capability that allows systems to exchange data and supports end-to-end business processes. This work positions us to scale efficiently, reduce operational risk and enter operations with strong governance, visibility and control across the enterprise. We're laser-focused on ensuring that the organization is prepared for introducing first gas into the facility in the second half of this year and producing the first LNG from Train one in the first half of next year. Our third key priority is to manage near-term exposure to LNG market margins through the sale of projected early LNG cargoes. As we mentioned on the fourth quarter call, early this year, we began marketing early cargoes that we expect to produce in Phase I prior to the commencement of our long-term SPAs for Train 3. In February, we sold over 175 TBtu on a free on board or FOB basis with fixed liquefaction fees that are expected to achieve margins calculated as the FOB sales price less our expected cost of natural gas feedstock and fuel of over $3 per MBtu. These sales reduced the Phase I early LNG production exposed to LNG market price fluctuations by 33%. Market margins have increased since the Aderant conflict began. And as we increase our visibility into expected early LNG production gain additional assurance on the timing from Bechtel later this year and early next year, we expect to sell additional early volumes to further reduce our market exposure during our ramp-up period. Our final key priority for this year is advancing the development and permitting of Train 6 through 8. Bechtel is in the process of performing a front-end engineering and design or FEED study for the Train 6 and third birth, and we expect to follow the formal FERC application for Train 6 before the end of this quarter. Additionally, we've begun early commercialization efforts for Train 6, and we're seeing strong demand for potential customers for long-term volumes. I'd like to remind everyone that additional LNG supplies were needed in the early 2030s before the IRAM conflict began and demand for long-term SPAs is even stronger today. Construction at the Rio Grain LNG facility continues to progress safely, on budget and ahead of schedule. As of March 2026, a Trains 1 and 2 are 67.8% complete. Train 3 is 44.2% complete and trains 4 and 5 are 10.6% and 6.8% complete, respectively. During the overall -- within these overall completion numbers, Trains 1 and 2 are functionally complete on the engineering and procurement front with the engineering of trains 1 and 2, just over 98% complete and the procurement just over 94% complete. Train 3 is not far behind Trains 1 and 2 with engineering over 90% complete to procurement over 80% complete. Since our last update, Bechtel has continued to make strong progress in construction of Phase 1 with work on Train 1 focused on piping, equipment installation, cable pooling, testing and system completions. The main cryogen, a key exchanger for Train 1 has also been successfully installed. Trains 2 and 3 made Noble progress on civil works, piping, structural steel and equipment installation and placement of the Train 2 compressor packages is underway. For tanks 1 and 2 welding of the inter tanks is progressing and concrete roof placement has been completed for both tanks. Early civil works are progressing for Train 4 site preparation activities are underway for Train 5 and production piling has commenced for Tank 3. Across the site, construction of permanent buildings is advancing, construction activities of the gas inland area are ongoing, dredging activities for the birth and the turning basin are substantially complete and channel deepening is nearing completion. The Bay Runner pipeline has been under construction since last fall and is expected to reach in service in the third quarter of this year. Bay runner is being constructed by Whistler LLC, a joint venture between WhiteWater Midstream, Enbridge and MPLX and will be our primary pipeline capacity into the terminal for trains 1 through 3. Early electrical commissioning of train line continues, and we continue to expect first gas into the facility in the second half of this year and first LNG production from Train 1 in the first half of 2027. In early April, FERC approved our request to ship to a 24/7 construction schedule at the site, a transition that has been contemplated in the EPC contract and will not increase our EPC or total project cost. 24/7 formats to facilitate Bechtel making continued progress ahead of schedule. We're currently tracking ahead of the schedule reflected in our early volumes and cash flow guidance, giving us some buffer for the unexpected events during commissioning and start-up of the trains while still achieving the production guidance we have provided. We're supporting our goal of increasing our capacity at the Rio Grande LNG facility up to 60 million tonnes per annum by advancing the development and permitting of Train 6 through 8. As we mentioned on our highlights slide, -- the FEED study for Train 6 is underway with Bechtel. Train 6 will have the same design as Trains 1 through 5, and the FEED study will support our regulatory filings with FERC and give us a general idea of where we expect to land on cost for Train 6. We currently expect Train 6 to look a lot like Train 5 from a project cost perspective, adjusted for inflation. We are also prepared to file a formal application with FERC for Train 6 and a third birth before the end of the second quarter of this year. The current administration's emphasis on U.S. energy dominance is a national security issue, including last week's determination that expanding LNG capacity is necessary under the Defense Production Act is expected to be helpful for the development of U.S. LNG, and we expect permitting new capacity to be smoother and faster under the current administration in the prior ones. Additionally, the DC Circuit Court's reversal in our case in March 2025 and the Supreme Court 7 County case later last year have set precedents that will go a long way in limiting the ability of certain groups tie-up permits in court over matters that have been appropriately analyzed by FERC in its environmental reviews. The permitting and regulatory framework for LNG infrastructure during the current administration appears to be taking less time, which is very encouraging. It gives us confidence that our future trains will receive approval faster than our first 5 trains. We believe it is possible that we could receive our FERC permit for Train 6 as early as mid-2027, which could set us up for an FID in the second half of 2017, if we can also sufficiently commercialize and finance Train 6 during that time frame. We expect that FID in the second half of 2027 would result in Train 6 coming online as early as 2032. As I mentioned earlier, we began commercializing efforts for Train 6 and and we're seeing very strong demand from potential SPA counterparties. We believe that one of the main outcomes of the Iran conflict will be increased attractiveness of long-term U.S. LNG volumes, and we'll discuss that more in a few minutes. The potential demand we are currently seeing for Train 6 provides us with a sales pipeline that is larger than the capacity of Train 6 and places us in a strong position for the subsequent commercialization of Train 7 and 8. We're advancing development of Train 7 and 8 with a focus on determining the supporting infrastructure they will require and finalizing their location on the site. Train 7 and 8 will need a flood control mechanisms such as the lever wall as they'll be outside the main levy around the site, and we're also evaluating potential tank [indiscernible] requirements. We continue to have the goals of permitting these trains during the current administration and commercializing them while they are in the permitting process. We currently have full ownership of Train 6 through 8, and we believe these trends could contribute significantly to future expect distributable cash flow across a wide range of financing scenarios. This year, as we advance permitting and commercialization of Train 6, we're working on potential financing options with the goal of maximizing distributable cash flow on a per share basis. Since our last call, global LNG market dynamics have shifted significantly as a result of the Iran conflict. Closure of the Strait of Hormuz during March and April tolled approximately 40 million tons of LNG supply out of the market with capacity at Rospan and Doss Island shut in. Each month of continued shut-in will result in a loss of an additional approximately 7 million tons, and we expect the production ramp-up that Rosatom will take weeks, if not months. Based on public announcements, the 2 damaged trains at Ross Lafon totaling almost 13 million tons per annum of capacity are estimated to require between 3 and 5 years to repair. Also, it's estimated that expansion capacity in cutter could be delayed by up to a year due to recent events. In total, a significant amount of LNG supply has been pulled out of the market between now and 2030, which we expect will tighten global balances. There's a lot we don't know today, including the full extent of the damage of [indiscernible], exact timing for production to return to the market and the ultimate impact of short-term demand destruction in price-sensitive markets, particularly in Southeast Asia. For the conflict again, we expect that the appending supply wave of LNG to spur extra normal gas demand growth and additional gas infrastructure investments in developing markets over the next few years. Clearly, with less supply in the market currently, this will slow down. Longer term, we do not see a slowdown in demand for natural gas and in particular, LNG. One very effective way for buyers around the world to acquire LNG at attractive prices is through long-term supply is through long-term supply and U.S. LNG SPAs indexed to Henry Hub are particularly attractive due to the diversified prolific natural gas resource base in the U.S. which effectively shelters buyers from the spikes in the price of LNG and natural gas in other parts of the world. In [indiscernible] pricing has decreased since the Iran conflict began and customers with long-term contracts out of the U.S. that are indexed to Henry Hub are currently able to deliver into Europe and Asia levels below $8 per MMBtu. Long-term LNG supplies out of the U.S. had been a buffer against market price shocks, not only during the current conflict but also during the prior market spikes associated with the Russia, Ukraine War and weather-related seasonal demand spikes. Long-term U.S. LNG supplies have also been attractively priced relative to short-term supplies in time market conditions like like we have seen in the past 2 to 3 years. Since 2021, an example, U.S. long-term SPA calculated at 115% of Henry Hub plus a fixed fee of $2.50 and shipping costs of approximately $2 would have delivered into Asia at an average of $8.83 per [indiscernible]. The JKM spot price over the same period was over $17.50, around double the long-term price. Excluding the market spikes related to RusheUkraine in 2022, and 2023 to present, the example U.S. long-term SPA price averaged approximately $5 per MMBtu lower than the short-term LNG price. Long-term Henry Hub-linked SPAs have also compared favorably to long-term LNG contracts linked to oil. Since 2021, long-term LNG contracts linked to Brent would have be it slows below 11%, inclusive of any fixed adder to beat the pricing of the most recent wave of long-term in rehab linked LNG contracts out of the U.S. Historically, these print linked LNG contracts have had slips between 11% and 15% plus a fixed [indiscernible]. Before the combo began, we received strong indications of demand for long-term supplies out of Train 6. And demand for long-term contracts is even higher today. With a prolific and diversified natural gas resource in the U.S., the favorable geopolitical environment, buyers can have confidence in U.S. supplies from reliability, energy security and economic standpoint. We expect buyers to increasingly value long-term contracts out of the U.S., which will spur additional capacity growth in the market. And with Train 6 through 8 under development, we're in a very good position to provide a meaningful amount of additional capacity to meet that demand. Now I'd like to turn it over to Mike to talk about our financial priorities. Mike?

Michael Mott

Executives
#4

Thanks, Matt, and thanks to everyone for joining us today. Matasjust walk you through key construction, operational and strategic priorities for 2026. And -- now I will spend a few minutes on our financial priorities for the year. First, we are focused on actively managing debt at the project level. Specifically, we plan to continue opportunistically refinancing portions of our project level credit facilities in the debt capital markets. Today, we have over $9 billion of credit facility commitments for Phase 1 about $3.8 billion for Train 4 and roughly $3.6 billion for Train 5. Over time, we expect to refinance each of these bank facilities into a mix of bullet and amortizing debt securities. We expect to refinance the full term loan balances before the commercial operation dates for Trains 3, 4 and 5, respectively. Since Phase 1 FID, we have refinanced more than $1.85 billion Phase 1 bank debt, and we expect to continue taking advantage of market opportunities this year. Importantly, this approach allows us to better manage project-level maturities by spreading them out over time and thoughtfully balancing bullet and amortizing structures. Our second financial priority is evaluating equity financing options for Train 6. As Matt mentioned, we are targeting an FID in the second half of 2017 and subject to achieving permitting, commercialization and financing prerequisites. This timing comes before we expect to be generating meaningful operating cash flows that could fund our equity requirements for Train 6, requiring us to look to other financing alternatives for this capital. We expect to contract a high percentage of Train 6 capacity, which could support project-level bank facilities covering up to approximately 75% of total project costs. Maximizing project level debt lowers the overall cost of capital and meaningfully reduces our equity requirements. Based on current SPA pricing, early estimates of Train 6 costs and the current interest rate environment, we expect the project to be highly accretive to next decade's distributable cash flow. As a result, all else equal, we will seek to both preserve our high economic interest to Train 6 and select the equity funding options that are most accretive to our distributable cash flow on a per share basis to maximize value for our shareholders. The FinCo bank facility that we will be used to fund a portion of our equity commitments for trains 4 and 5 remains a very attractive source of capital. It is priced at only about 150 basis points over our project level bank facilities and provides significant flexibility through delayed draws and penalty-free prepayments. We believe additional FinCo capacity will be available to help fund a portion of Train 6 equity needs. Beyond that, we are actively evaluating a range of alternatives to fund the remaining Train 6 equity requirements. We will continue working through these alternatives over the course of the year with a focus on finding the most accretive outcomes. -- and we expect to share more detail with you later this year as these options take shape. Today, we are reaffirming our early volume and cash flow guidance along with our steady-state outlook. This slide provides a high-level summary highlighting the key points. You can find more detailed assumptions and supporting slides in the investor presentation we posted earlier today. Let me start with a discussion of early volumes. We continue to project total LNG production of approximately 3,800 TBtu from early cargoes beginning with startup of Train 1 in 2027 and and extending through first commercial delivery to our long-term SPA customers under Train 5. Importantly, that total includes about 1,275 TBtu of LNG production in excess of what's currently contracted under long-term SPAs. As we discussed on our fourth quarter call, earlier this year, we sold forward more than 175 TBtu of those early volumes on an FOB basis. These sales carry fixed liquefaction fees and are expected to achieve cargo margins of more than $3 per MMBtu calculated as the FOB LNG sales price less our expected feed gas and fuel costs. As a result, we have reduced our exposure to LNG market pricing on early Phase 1 volume by roughly 1/3. As Matt mentioned earlier, we expect Bechtel to deliver our trains ahead of the guaranteed substantial completion dates. As a result, the majority of the uncontracted volumes reflected in our early production guidance are expected to be produced after substantial completion and prior to DFCD under the SPAs for each trade. As construction continues to progress, our confidence in these projections remains very strong. In fact, Bechtel is currently tracking modestly ahead of the scheduled assumed in our guidance which provides additional buffer and creates potential upside for early volumes that are not currently reflected in our projections. We expect the cash flow generated from sales of these early volumes to be used primarily to pay down a portion of the FinCo and Super FinCo loans that support our equity commitments for trains 4 and 5. Our early cash flow outlook guidance remains unchanged. Under an assumed margin of $5 per MMBtu on volumes in excess of our contracted SPAs, we project early production could generate approximately $2 billion and next decade share of distributable cash flow at the Rio Grande LNG project level. At a $3 per MMBtu margin, we project approximately $1.2 billion of distributable cash flow. There is potential upside to both scenarios driven by continued schedule strength, the pace of ramp-up to full production, the potential for production above nameplate capacity and possible additional market price upside. Turning to leverage and capital structure. On our last call, we introduced a steady state leverage target of 3 to 3.5x next decade level debt to adjusted EBITDA. We believe this target is appropriate given the long-dated highly visible cash flows created by our highly contracted portfolio with high-quality creditworthy customers. In the $5 per MMBtu early volume margin scenario, we expect next decade level debt to fall within that target range as we move into steady-state operations. In the $3 per MMBtu scenario, we would expect to pursue additional balance sheet optimization. In that case, we would consider contracting approximately an additional 2 million tons per annum under long-term SPAs across trains 4, 5. That would increase our 5 train portfolio to roughly 90% contracted, allow us to maximize project level debt, reduce overall equity requirements for both next decade and our partners. -- and ultimately reduce the amount we expect to draw under the FinCo loan, bringing next decade level debt back into our target range for steady-state operations. Because we contributed the net proceeds from the Super FinCo term loan into trains 4 and 5 at FID, we do not expect any additional next decade equity funding obligations through Das on the FIMCO loan for those trains for at least the next 2 to 3 years. This gives us a long runway to determine the optimal level of long-term contracting. And as Matt mentioned, we are seeing very strong demand in the long-term contracting market today. Moving our discussion to steady-state operations. We are also reaffirming our steady-state guidance today. In our base case scenario, assuming $5 per MMBtu market margins, both for early volumes and during steady state, we project annual next decade distributable cash flow of approximately $500 million following DST for the Train 5 SPAs and prior to our economic interest lift for trains 4 and 5 in the mid-2030s. After the flip, beginning in the mid-2030s we project annual distributable cash flow of approximately $800 million. In our additional pricing scenario, assuming $3 per MMBtu margins on early volumes per MBG margins on steady state volumes and an incremental 2 MTPA of long-term SPAs across trains 4 and 5. We project annual distributable cash flow of approximately $400 million prior to the economic interest split for Trains 4 and 5, which we would expect to occur a couple of years later than in our base case. In this scenario, we project post-distributable cash flow of approximately $500 million annually. As with our early volume outlook, there are potential upsides to our steady-state guidance including continued schedule improvement, ramp-up timing, production above nameplate capacity and ongoing operational efficiencies. Thank you again for joining us today. With that, we'll open the call up for questions.

Operator

Operator
#5

[Operator Instructions] The first question is from Sunil Sibal from Seaport Global Securities.

Sunil Sibal

Analysts
#6

So I wanted to start off on your request for additional workovers at the site. I was curious, is that kind of based or baked into your base construction schedule? Or does that kind of accelerate that from the base schedule?

Unknown Executive

Executives
#7

Yes. Thanks for the question. The 24/7 contemplated in the original EPC, it was an option and something that Vectecould call on if they wanted to use it. And I think that's what they're doing. They want to maintain the current schedule, and they want the flexibility to utilize 24/7, and that's what we've requested at FERC, how they end up utilizing and how many people they actually use is up to them. But I wanted to make sure it was clear to the market that this is not an incremental cost to us. This is something that was already baked into the EPC. And I think it's a positive sign that shows we have -- although we are already ahead of schedule, we haven't even utilized all the potential capabilities of a 24/7 schedule to further accelerate. I'm very optimistic that dental is going to remain ahead of schedule at this point. And I think by adding the 24/7 optionality, that gives us even more confidence.

Sunil Sibal

Analysts
#8

Okay. And I think you mentioned DPA in your prepared comments. So I was curious what seems like that's primarily related to accelerated permitting? Or there are other kind of potential levers that keeps you or other LNG developers in your view?

Matthew Schatzman

Executives
#9

Sorry, I missed the first part of that, referencing what?

Sunil Sibal

Analysts
#10

The Defense Production Act invocation.

Matthew Schatzman

Executives
#11

Yes, thanks. Yes, I think we'll have to see exactly how this impacts the timing. But clearly, what we've seen recently are some changes in the way FERC has handled some of the current requirements, such as the prefiling waiver for BV, which I view is very positive. That may only apply in certain circumstances. It's something that we're currently in discussions with FERC on and we're waiting to hear additional guidance. But clearly, the Trump's memorandum regarding the importance of LNG along with other energy infrastructure in the U.S. to energy security during this period of time, especially with LNG for our allies. I think it's a very positive sign and suggests that we're going to see these things move very rapidly relative to even what we've seen in the past couple of years under the first couple of years of the Trump administration.

Sunil Sibal

Analysts
#12

Got it. And then just a clarification on some of your comments. So I think you mentioned that as far as Train 6 is concerned, construction cost is kind of in line with train 5 plus inflation. And then you also commented that based on where the supply demand for long-term contracts is that, that market has strengthened. So I'm kind of curious, when you think about your project, say, 3 and 6 between these 2 factors kind of interplaying do you see improving returns on investment on the project versus where things were for Train 5 last year. And then how are you seeing -- in terms of the demand for additional cargoes -- is that primarily Europe, Asia, any color on that in terms of your discussion so far.

Matthew Schatzman

Executives
#13

Yes. On the second part, you're talking about the long-term demand are you talking about for the excess card you said additional cargoes you mean for long-term SPAs are you talking about for the short-term cargo sales?

Sunil Sibal

Analysts
#14

Actually both.

Matthew Schatzman

Executives
#15

Okay. All right. So first off, the economics of Train 5 were extremely good, and we expect the economics to track closely to the economic outcome for Train 5, again, adjusted for inflation, and we still have to price up the EPC contracts. And we likely won't do that until we're confident that FID is within months of that. And it's all dependent on how long we can get price validity, but it's tended to be about 90 days or so at most. But -- but inflation, we have to monitor it, it's inflation, it's interest rates are the 2 main factors that are going to impact the project cost. Inflation on the EPC. Obviously, interest rates on the financing costs and interest rearing construction. Both of those appear to be okay right now, but we'll have to see. We've had some early discussions with equipment providers for the main equipment. I've been very pleased, very optimistic that we're not currently seeing the same sort of constraints that we saw back last year as far as timing. But we're not planning to FID until second half of next year. So a lot of things can happen between now and then. But at least in the interim, what we're seeing right now, saying things are tracking, I think, very positively. As far as the demand for the LNG, I think it's the same group that we saw for 4 and 5. It's Asia, Middle East, not seeing as much out of Europe as far as long-term contracting, but still a lot of interest from major intermediaries that sell into Europe and have markets into Europe. But Asia and I think Middle East, especially look like they're going to be players in the next phase of RG LNG's expansion. In the shorter term, I'd say it's a combination of Europe and Asia.

Operator

Operator
#16

Next question is from Wade Suki from Capital One.

Wade Suki

Analysts
#17

Just maybe just detail a little bit on Sibal's question, maybe expand a little bit on kind of cost inflation we're not going to maybe get work until next year. But labor running a little hot. Maybe you could speak a little bit to the various equipment components, electrical kind of just thinking about other Gulf Coast projects progressing. Now we have rebuilding, reconstruction going well, hopefully going abroad with all the damage facility. Just wondering if you can kind of speak to those items as you see them today.

Matthew Schatzman

Executives
#18

Yes. inflation. It appears you've seen the most recent numbers that came out. Inflation appears to be heating up a little bit, but over time has been relatively modest. Again, we would expect the EPC cost to go up by at least inflation. A large part of our EPC since we're stick-built in the U.S. is going to be labor. Labor does tend to be a little bit higher than inflation, although this past year, it wasn't much above inflation. We all monitor this closely, not only for the EPC, but for every year, we have to look at our own employees' costs, and we want to be fair. So I think at least right now, it's not a worry, a major worry, but we'll see how things progress over the year. As far as equipment, again, as I said, I've been pleasantly surprised at this point with the feedback we've received from our major suppliers as far as the expected availability for equipment for Train 6, 7 and 8 and the timing of when we'll be able to receive that equipment. As far as the cost, that will be determined once we price everything up for the EPC contract. I do expect electrical equipment to continue to be in high demand, not just for LNG, but obviously for data center build-out and power generation. So -- we'll see how that comes in. But I would expect that any sort of cost inflation that we're going to see will likely be offset by contracting -- price contracting. And again, we're not seeing any sort of -- we're not seeing the same sort of price increases that we saw after the pandemic prior to Phase 1, which was fairly substantial. And then as you recall, between Phase 1 and Train 4 and 5, we had about a 10% increase, and there was a 2-year spread there. So it was running closer to 5% per annum as opposed to the current inflation. But that tracks pretty closely with what we were seeing in inflation. And obviously, some of the equipment stuff got really, really hot, especially around turbine orders, et cetera, that became the the constraints as far as schedule and delivery of the project.

Wade Suki

Analysts
#19

Great. Appreciate the color there. You kind of walked right into my next question, Matt. just to what extent these might kind of influence, if at all, long-term SBA pricing. And I always appreciate your broader thoughts or insight you could do whatever it could give us on what you're seeing out there with regard to kind of leading edge rates. That would be great. Any color would be awesome.

Matthew Schatzman

Executives
#20

Yes. Look, I think the market for LNG is between $2.50 and $3 on a fixed fee basis, 10%, and and Reata range. And I think it depends on the returns you're going to receive are going to be dependent on whether or not you're running a brownfield project or a greenfield project. [indiscernible] projects, I think, need higher contracting prices in order to get off the ground. If they go lower than and compete with the brownfields like us, I think they're going to have to get their upside through expansion. If they don't have a lot of expansion capability, I think it's a challenging market from an equity return perspective. Currently, as you guys have seen for our Train 4 and 5, we are -- we tend to not be on the lower end of the market. We tend to be I think, in the mid-range of the market, kind of the true market price if you look at it from a bid offer perspective. And that's where I expect we will be or close to that for Trains 6, 7 and 8.

Operator

Operator
#21

The next question is from Craig Shere from Tuohy Brothers.

Craig Shere

Analysts
#22

Is your nat gas sourcing team fully in place now? And you've talked about hedging out some of the initial commissioning cargoes and that you expect $3-plus netbacks net of your feedstock costs -- could you, by the end of the year, make any more formal announcements, not just on the sales side but on the purchase side and what you're doing there?

Matthew Schatzman

Executives
#23

Yes, something we'll take into consideration. We've been active on the supply side for a long term. And been working on that. And I expect that we should be able to give an update as to what we've done on a long-term basis. In addition, some of our customers have to give us notice before the end of the year as to their willingness to sell us gas under long-term contract prices. So either later this year into the year, maybe in the first quarter, right, we can provide some guidance as to what we term basis. a year or greater. I think that will be a good update. So thanks for this year. As far as the team you got it nicely. So we already had a gas supply team in place, but we're building out the short term, the -- what I'll call the trading and optimization team. They will be managing our gas supply for us, and we expect to have them definitely in-house completed before we have to start introducing gas into the facility, which will be later this year.

Craig Shere

Analysts
#24

Great. And you mentioned about this 24/7 construction that Bechtel officially kind of was the one who asked for it, and it's their discretion how to use it. Maybe you could just speak to their incentives by individual train or by individual FID. They may, depending on how well things are going overall may not necessarily make more money or incentives to accelerate further versus where they're already tracking. But when you think about well, now already 5 train project moving on to 6 and more that perhaps even if they slightly increase their costs, that you don't have to pay for that their NPV building out 6 to 8 trains over time could be higher and that they're still incentivized to maximize this under most conditions. Could you opine on that?

Matthew Schatzman

Executives
#25

I think what I'd say simply, Craig, is that without getting into the details of the commercial arrangement, which I don't believe we have disclosed what I would say is that Bechtel is highly incented to deliver substantial completion of each train prior to the guaranteed substantial completion date. And that there is value there that I think can more than compensate them for an increased labor cost if they choose to use it. There's also, as you know, guarantees. I mean, we're nowhere -- at this point, and we've already said and guided that we're nowhere near that guaranteed substantial completion date as far as the delivery of the trains, but they want to make sure that they achieve prior to guaranteed substantial completion because if they went past it, which, again, we're nowhere in this realm. -- there are key hole mechanisms and damages associated with that. So there's a bunch of different incentives for them to ensure that they deliver the trains on schedule, and there are more incentives for them to deliver them ahead of schedule.

Operator

Operator
#26

The last question is from Alexander Bidwell from Webber Research.

Unknown Analyst

Analysts
#27

Just wanted to, I guess, piggyback off some of the prior questions around Phase 1 construction. With the projects tracking ahead of schedule. Could you walk us through the path to maintaining that momentum as well as any avenues that could further accelerate the project schedule?

Matthew Schatzman

Executives
#28

Yes. I think it's -- importantly, it's execution. We don't currently have any concerns about equipment and supply chain, that appears to be going very well. So we haven't seen any major impact associated with the conflict in Iran, impacting that, which is good to see. I think the key here is we'll continue to provide you updates each quarter. You'll see the progress from the standpoint of the construction you note that we're engineering is effectively complete. [indiscernible] effectively complete for Phase 1 or close to it. So it really boils down to execution at the site and building it. 4 and 5, again, further out in the future, but you should expect to start seeing steel foundations being finished up this year and hopefully steel erecting at the trains. We've already talked about the filings for Tank 3. I hope to see that progress for Train 4 as well this year. But I think it really boils down to execution. There's really there's not one thing that we're specifically looking for. As far as the construction, it's just ongoing, continuing to do and execute what Bechtel has been able to do so far. The next phase, though, I think, is of equal importance, and that is the commissioning phase. You'll see gas being introduced in the facility this year. You should expect to see that -- we'll be working on the warm side of the facility there. We're looking at working on the flares, and we'll be working on the gas processing side of it. The cold side, you aren't going to -- you shouldn't expect to see that until next year when we start to -- we're seeing compressors and start testing and then start hopefully producing LNG. As we said in the first half of 2027. We haven't provided any specificity on which month that's going to be hope to be able to provide some additional guidance on that later this year as we continue to progress with Bechtel and we get a better indication of when that's going to occur. And then, of course, once we get through the commissioning process, which I think I've told the market that we're doing with [indiscernible], our operations team is seconded into Bechtel for the commissioning so that we have a seamless handover and substantial completion. Our team will have already worked on operating the facility during the commissioning with Bechtel, which we think is best practice. That should happen -- that will happen in substantial completion, which, again, is tracking ahead of guaranteed substantial completion, which currently, I think we've guided in the fourth quarter of next year. So those are the key components -- we've been very -- we believe and continue to try to be conservative in our guidance to the market because this is our first train. We are -- we've been around the block on this and other projects. We -- we know how these things work. So far, everything has gone extremely well. We would anticipate based on how well [indiscernible] has done building the facility that we expect the commissioning and hand over to go extremely well also. But we're not planning for the best, hoping for the best. We're going to plan for expected disruptions as you typically see when you're starting up a facility, especially a new one, we'll learn lessons from that. And then we would expect trains 2 and 3 to go even smoother because we'll learn from Train 1 commissioning and start-up. So I think these are the key components. And again, we will continue to update the market as we can with more details on when that facility is going to [indiscernible] going to start up, when we expect to produce first LNG, and when we expect to load our first cargo. And then the spread of timing between Train 1 and Train 2, Train 2 and Train 3.

Unknown Analyst

Analysts
#29

All right. Appreciate the color. And then just I guess real quick on the shipping side. Was wondering if you could provide any additional color on your plans around shipping capacity. I understand you guys have some vessels set to be chartered in. But is there any plans to expand or add additional vessels to handle the merchant book?

Matthew Schatzman

Executives
#30

Yes. We have 5 vessels under Charter, 3 long-term charters that are utilized for our Guandong DES deal, we've charted those from Dynagas. There are 3 new vessels. In fact, the first one just sailed yesterday from the Hyundai shipyard, I was there. on Tuesday and took a tour of the vessel. It's a phenomenal piece of kit that Hyundai has built for Donna Gas and Donna Gas as designed. We have 2 more of those coming this year. And then we have 2 more vessels that we've subchartered. All these will be used from our commissioning process for Train 1, and then we'll start utilizing those larger ships that we have -- that we are being built for us to deliver to our long-term market in China. We will likely run a DES type business for our excess cargoes. We believe that being able to do a delivered a ship business for our excess volumes, provides additional flexibility and optionality and should increase the value. So we do anticipate chartering more shifts on a short-term basis for Phase 1 volumes above the firm volumes that we've already sold. And then for Train 4 and 5, we are looking at additional capacity potentially on a longer-term basis. due to the fact that we currently, as you know, haven't sold all of our firm capacity out of those trains. However, as Mike mentioned in his comments, should we decide to sell more of that capacity a year or two from now, depending on how the short-term market goes, that may reduce how much capacity we would need under a longer-term basis. So we're going to be very mindful of that and make sure that we don't overcontract capacity before we need it. But we will be chartering more ships simply put.

Operator

Operator
#31

That concludes our call today. Thank you for joining and for your interest in NextDecade.

For developers and AI pipelines

Programmatic access to NextDecade Corporation earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.