Nordic Mining ASA (NOMO.OL) Q3 FY2025 Earnings Call Transcript & Summary

October 31, 2025

OB NO Materials Metals and Mining Earnings Calls 28 min

Earnings Call Speaker Segments

Finn Marum

Executives
#1

Good morning, and welcome to Nordic Mining's Third Quarter '25 Interim Presentation. We have a challenging quarter behind us with operational technical issues as well as a court case, but this is not without some bright spots. On the positive side, during the quarter, we crushed and milled more material during a 6-week period than we did in the preceding 6 months. The produced volumes of garnet and rutile were in spec, but the volumes were low. The issue that we faced was one of operational time, continuous operational time. And we've taken steps to address this by bringing on-site expertise from our customers and partners. The Barton Group that has 150 years' experience running their own mining operation have their operations manager on site working alongside our people. The Iwatani Group has a mineral separation plant in Australia that does titanium dioxide. They're also on-site assisting us, as well as technical support from Orion Resource Partners, our financing partner on the royalty side. Together, we've charted a new path forward with the stated aim of having a rutile cargo available for shipment at the end of the first quarter next year and also operating at design capacity towards the end of the second quarter next year. In order to provide transparency on our progress towards those targets, we're going to start publishing quarterly production statistics immediately following the quarter end so that you can follow and track how we go forward. In order to create a runway, we raised additional capital through a tap issue of our high-yield bond during the quarter. And given that additional capital and our plans going forward, this should carry us through to positive cash flow as it stands. During the quarter, we also had filed a lawsuit against us for a temporary injunction that is a stop of our mining operations. So we spent 5 days in the District Court at Sogn og Fjordane. We met well prepared, and we had the government's attorneys at our site. And we brought in that case, which was actually new compared to the other cases that have emerged is that an argument that the environmental impact indeed is quite low and significantly lower than has been stated and also raising the question if indeed the EU Water Directive is applicable in our case. The verdict in that case is expected on or about the 10th of November, and we will, of course, inform the market immediately. Another positive new item during the quarter or rather 2 days ago was during the Fennoscandian conference in Finland, we were actually awarded the Fennoscandian Mining Award for 2025. And in the picture here, you can see our Manager of Resource and Development, Trond Langeng, receiving the award on our behalf. This is a proud achievement for us and a testament to all our employees that work 24/7 to make this a success. So indeed, a very happy news item there. This time, I'm going to introduce a new face. Since our last quarterly report, we've been joined by our new Chief Commercial Officer, also responsible for Strategy and Business Development, Andreas Davidsen, and he will go through the market development. Andreas?

Andreas Davidsen

Executives
#2

Thank you, Finn Ivar. As you know, our rutile goes as a feedstock for titanium dioxide production and titanium metals production. We have 5-year contracts with the price fluctuating with the natural rutile price. In the titanium dioxide market, we saw the prices weakening in Q3 across most regions compared to the first half of the year. The main reason for the weakening of the prices is continued exports from China. However, we see a continued demand for titanium sponge and the market there remains strong. There is quite limited trade of natural rutile in the market, and we see the prices being flat from 2024. Below, you will see a graph of the natural rutile price, which we have produced together with our consultant, TZMI. You will see that the price is down from 2022, 2023, but flat from 2024. And we expect 2025 to be as 2024 and increasing somewhat thereafter. We see closures of mines of natural rutile, and we don't see much new supply. On the garnet market, we see the market as relatively tight in Europe and North America with strong demand for our products. And in garnet, Nordic Mining has fixed price for the first 5 years of the contract. So in conclusion, we see demand for all the volume we can produce for the next year. We see flat prices or slightly increasing for natural rutile, and we have a fixed price for garnet. Thank you. And then I will introduce Kenneth, who will speak about operations.

Kenneth Angedal

Executives
#3

So moving into Engebo Rutile and Garnet. Looking at the mining site, we can see a huge project moving forward into operation. We started the mining roughly 1 year ago, and we have been focusing on waste rock in the last months. If we look at the overall numbers, we have, in the quarter, mined roughly 550,000 tonnes of rock and year-to-date, 1.65 million tonnes. In general, the ore grade are in line with the feasibility study after we have done grade control of the mined ore. We have been prioritizing waste rock movement as the process plant has not been able or available to receive ore in certain periods. We are roughly 9 to 12 months ahead of ore mining as per now. In a totality of all of these items, we do not see any change to the mine plan except that we are ahead in waste rock. In terms of next year, we are preparing our new plan and updated plan on the basis of the waste rock mine already, and we plan to optimize the fleet and reduce the mining fleet for '26 because of this. The mine is well positioned for next year. Looking into the process plant and the production from a mineral separation point of view, we see that we have significantly increased the throughput on the mill and into the wet plant in the last quarter. We have increased the design on the crushing circuit, design load on the crushing circuit, but are still not 100% in that sense. We have not progressed significantly in the dry plant because of operational time and stability issues. Looking at the illustration on the left side, we have tried to show the totality of what we're doing throughout the ramp-up. We always need to have quality in place, and we are focusing on the throughput. Our operative challenge right now is to maintain a significant operational time throughout the plant. With having 100% design load on the mill means that we are inputting at design capacity when we run the mill, but are not achieving the expected output and recovery on the basis of the input. This is due to some limitations in our dry plant, which we are aware of and its failure related to material handling equipment moving dry material from A to B. We know what the cost is and are awaiting replacement. We have, for the last week, had roughly 70% operation time on the mill, which is a great achievement, and we work towards those numbers for the rest of the year. In terms of mineral production, we are still meeting the quality on the concentrate. But because of the instability, we have not been able to increase the production of rutile. When we are now increasing the throughput, we also constantly have to change and tune this mineral separation equipment all the way from the mineral separation in the wet plant throughout the dry plant. So it takes a lot of time to adjust, but we are moving very positively forward. Looking at 2025 and what we have done and achieved, we can go a little bit back to Q1 where our focus was ramping up the mining activities, increasing crushing throughput and we were running both crushing and mineral separation separately. In second quarter, our focus was debottlenecking the materials handling in the crushing circuit. We also started both crushing and mineral separation plant simultaneously. In Q3, as we have presented before, we've done modification to a large amount of pump circuits and slurry lines. After doing this, we have achieved design throughput on our mill. But we also have seen operational and technical challenges after this that has hampered our progress in the ramp-up. In Q4, we are seeing that our wet plant performance are deliberately by ourselves limited due to the capacity in the dry plant at current stage. We need to expect and replace some parts because of the limitations and design defects. I will come a little bit back to these defects in a few slides. Our focus going forward is to reduce wear and equipment failures to increase the operation time plant-wide. So some examples of what we are working with. On the left side, we have pump circuits that have been changed, a significant part of it, but we do also see other challenges as we are running right now. Start and stop of the plant introduces increased wear. We still see some design layout issues, mainly on how the pumps and the pipes are designed in and around each other that incurs cavitation in certain pumping systems and reduces then the internal life of the pumps. We are constantly doing changes on this, and we see a significant effect in reducing of the wear across the plant. We are also running an uprating program where high wear pumps are changed into a bigger size to reduce the required RPM on the system, which then limits the wear on the pump internals. Specifically on the dry plant, the identified bottleneck is a simplistic screw feeder in a complex system. We are limiting the throughput to reduce wear. We have seen increased wear, which we have done temporarily repair to and refurbishment with our own engineers, awaiting a new type of material handling system by the end of November. So you can say why didn't we see this before. Sometimes when you start a plant, excessive wearing points, equipment failures are not seen until you actually start up and run the plant. So in our throughput increase now, we have seen more items that we need to deal with and repair, modify and move on. This is what we do on a constant basis and are working with a plan. So our team is doing an excellent job with the limited time at our plant and new people coming in. So our people, both from a maintenance and operating perspective, are doing an excellent job in lifting up the production and keeping up 70% last week and plans for the coming weeks. Then leaving to Tord.

Tord Meling

Executives
#4

Thank you, Kenneth. The cash flow was affected by several factors. First of all, very limited revenue as only one small boat of garnet was shipped in the quarter, combined with a high activity in both the pit and the process plant and with extensive maintenance work. We have a NOK 94 million negative cash flow from operations. Other factors [Audio Gap] use of both external services and spare parts related to the maintenance stop in July. Okay. Yes, the maintenance stop in July and to handle challenges in the plant later in the quarter. CapEx from the construction project is limited in this quarter and remaining CapEx is holdback related to one EPC. We are exiting the quarter with $292 million in cash and have subsequently increased liquidity by USD 22.5 million through a tap issue of the existing bond. By this, we have secured a runway to support the updated ramp-up plan. The focus remains on production, which is very important for the financial performance going forward. To keep you somewhat more closely updated, we will start publishing quarterly production figures that will be published in the first couple of days after the end of the quarter. And therefore, you will receive an update on production for the fourth quarter in early January. Over to the P&L. There is an increase in the production expenses this quarter. First of all, the mining costs are higher than expected, which relates to the mining contract. Part of this relates to one-offs. But in general, the unit cost per tonne is higher than what we are targeting. The cost level will have a focus as we now move forward and together with the reduction in the activity level in the pit, as explained by Kenneth. In addition, operational challenges impact the operational cost as well. As mentioned in the previous slide, we have had a maintenance focus this quarter, which has resulted in increased use of spare parts and material as well as extra costs related to external services. There have also been a high use of overtime by our own employees. Finally, the OpEx is also somewhat impacted by legal bills relating to ongoing court cases, which are continuing into the fourth quarter. So with that, we move over to the Q&A.

Finn Marum

Executives
#5

Thank you.

Operator

Operator
#6

We have quite a few questions, and some of them are similar. So we'll try to group them. But we could start with Kenneth. Those are the questions looking a little backwards. Why did a plant designed and engineered by Hatch with extensive front-end engineering and process simulation still face such fundamental reliability issues in the dry plant and materials handling system?

Kenneth Angedal

Executives
#7

Yes, I think it's a good question. To start off, it is important to notice that our mineral separation equipment is not seeing any difficulties in achieving the grade and the quality of our products. So the mineral separation equipment is working as intended as per design. In terms of material handling, such as the pumps that we have all the changes and other items that we're working with, is a responsibility of the EPCs to deliver and move the material from A to B in between the mineral separation equipment. So this is, of course, items we have on our defect list towards our EPC contractors.

Operator

Operator
#8

Some of the delay stems from the dual mineral configuration itself, managing both rutile and garnet circuits comparing to what you would have been expected in a single mineral plant.

Kenneth Angedal

Executives
#9

I do not think there's a specific reason either or. But of course, garnet as an abrasive material does increase the wear. But I would say that it's about the number of machines and number of streams, which are the main impact. As part of the design, we are also recirculating a significant amount of streams to actually take out the most of the minerals at each given time, which means that this is extra processing capacity and recirculating loads that also wear out pipes and equipment. In many plants around the world, these items are not used in that amount of recirculating circuits and might be a simpler plant somewhere. But in total, it's not about rutile or garnet, it's about the size and the amount of streams, which we have started step by step, stream by stream.

Operator

Operator
#10

Kenneth, you're using electrical dryers instead of gas-fired systems. Has this contributed to the lower output and increased equipment wear in the dry plant?

Kenneth Angedal

Executives
#11

No, the electric dryer versus gas-driven dryers are not a significant impact in terms of wear.

Operator

Operator
#12

Who own the overall risk regarding register during the construction to operation transition and who signed off that all critical risks were closed before the project was declared complete?

Kenneth Angedal

Executives
#13

I can answer. Our commissioning plan is 5 or 6 steps depending how you look at it. So at each step, we have done checkouts. Some of these things that are merging now are not able to be seen in an earlier stage where you run material -- not run material, you run only water. Now we are increasing the throughput throughout the plant. So there are new things coming that have not been possible to see before. Of course, there might have been inherent items that we could, should and maybe should have seen before, but this has not been taken into account earlier, but we are dealing with now that we see the issues coming up.

Operator

Operator
#14

With the plant not operating as intended as of yet, will you receive compensation by the EPC contractors? And is this an ongoing process? If so, when and how much?

Kenneth Angedal

Executives
#15

No, I said, our focus is to get the plant to work, and we are writing down and notifying all of the effects that we are seeing towards both contractors and EPCs.

Operator

Operator
#16

Finn Ivar, why have you decided to release reports on production only quarterly? Why not monthly? As an investor, I'd like to be updated more often than quarterly.

Finn Marum

Executives
#17

I can certainly see that point, and we had a discussion about what makes sense and from an information point of view. And in our view, the quarterly production statistics will provide the best view on operations. The monthly will vary and the quarterly would provide a better view of actually how we're progressing.

Operator

Operator
#18

We have some legal questions here. During the trial where the NGOs are requesting a temporary injunction, it was mentioned that the state has the flexibility to grant Nordic Mining a temporary permit for a new production permit. Is that correct?

Finn Marum

Executives
#19

That is correct. That was a topic during the court case and certainly something that we took note of as a possibility going forward.

Operator

Operator
#20

Is the CEO positive regarding the court case?

Finn Marum

Executives
#21

Yes, very much so.

Operator

Operator
#22

When are you able to give us some news about dividends?

Finn Marum

Executives
#23

Right now, all our focus is on making the plant operating according to design specifications, and that's where our focus is for the next 6 months at least. And the dividend question, we will deal with in due course.

Operator

Operator
#24

Do you have any update on the Kvinnherad quartz project?

Finn Marum

Executives
#25

I think we mentioned this at our last quarterly report that we expect to see results from product being tested at customers late in the first half of next year. So no news as of now.

Operator

Operator
#26

Tord, last quarterly presentation, you stated that you were funded until cash flow positive. One month later, the bond was tapped again. Did you honestly not realize that the operational problems would cause a tap issue at that time of the last presentation? And what made you decide to raise debt instead of equity to cover the additional ramp-up costs?

Finn Marum

Executives
#27

Before you start answering that, Tord, if we look at the big picture here, we have a situation where we have a brand-new plant that we're working to operate. We have a new organization with most of the people having joined within the last 12 months. And we have a pretty unique ore as well that we need to learn how to deal with. So the situation is actually as I described in the quarterly report, one of continuous challenges that we have to deal with as we move forward. And with the experts that we have at hand on site now, we have increased visibility, and we have a good plan going forward. But of course, there's always the unknowns that could turn up. I'll let you answer the specific question, Tord.

Tord Meling

Executives
#28

Yes. So we came out of the maintenance stop in early August very positively. We had fixed many of the issues we were facing before the maintenance stop. So we thought that -- we believe that this was going according to plan. And then as we moved further down the production line, we saw issues coming, so we had to revise the production plan and thereby, we tapped the bond. Yes.

Operator

Operator
#29

How much financial buffer have you in case of if you face more delays in the ramp-up? And what if the first shipment of rutile is delayed from end of Q1 to Q2?

Tord Meling

Executives
#30

So we have an updated plan now, including a buffer, which takes into account a ramp-up period, longer ramp-up period than we previously had planned for. So all our efforts now are on getting the production up, production of rutile and garnet so that we can deliver on this plan. Then we will keep the buffer. We are also bringing in good help these days. And we, therefore, believe that this will result in income in the coming period. The customers are ready. They want to take delivery. So it all comes down to us producing minerals.

Operator

Operator
#31

Thank you. I think we have covered all the questions now.

Finn Marum

Executives
#32

Thank you.

For developers and AI pipelines

Programmatic access to Nordic Mining ASA earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.